    Assignment Project Schedule

    Schedule the following project subject to given resource limits. Assume start date as 05 Nov 2012.

    Identifier Activity Predecessor Days Resource

    Perform Planning and Scheduling

    A1 Revise overall projectplan

    None 10 N, P

    A2 Complete detailed plan

    for detail design

    A1 3 P

    A3 Revise skeleton andgeneric plan for rest

    A1 3 P

    A4 Brief new teammembers

    A2, A3 1 M, N, P

    A5 Complete phaseestimate

    A4 4 O, P

    A6 Review plan A5 1 M, N, O, P

    A7 Revise plan A6 11 O, P

    A8 Complete project

    schedule

    A5start + 3 4 N

    A9 Milestone A7, A8 0

    Prepare Database Design

    B1 Document data modelsto catalog

    None 13 B, P

    B2 Determine filestructures for flat files

    B1 10 B

    B3 Prepare copylibs for flatfile structures

    B1 7 B

    B4 Define each process B2, B3 3 B, P

    B5 Review process access

    with databaseadministration

    B4 1 D, M, N, P

    B6 Physical databasedesign

    B5 10 B, R

    B7 Review design B6 1 B, D, M, N, P

    B8 Revise design B7 10 B, R

    B9 Conduct call patternreviews

    B6 8 B

    B10 Milestone B8, B9 0

    Prepare Physical Design Documents

    C1 Prepare process toprogram specifications B4 10 P

    C2 Determine securityspecifications

    B9, C1 8 B, P

    C3 Prepare physical systemflow

    C2 10 B, P

    C4 Milestone C3 0

    D1 Design programs andwrite specifications

    A8, B9 10 B, P

    D2 Write data conversionand interface programs

    D1 6 R(3)

    D3 Revise documents D2 20 R (3)D4 Milestone D3 0

  • 7/27/2019 msproject-ex3

    2/2

    E1 Implementation C3, D3 6 B, P, R

    E2 Testing E1 10 B, P, R

    E3 Final acceptance E2 2 M, N, D

    E4 Milestone E3 0

    Work5 days Per WeekHolidays

    3rd and 4th Monday in Nov3rd Monday in Dec, 25 Dec

    1st and 3rd Wednesday in Jan 2013

    Details of Resources

    Resources Cost/Day Resources Cost/Day

    M Manager $300(1) R SystemsprogrammersR1,R2 and R3

    $200(3)

    N Assistant $150(1)

    O Cost estimator $200(1) D Database

    administrator

    $500(1)

    P System analysts P1, P2 $350(2) B Database designers $300(1)

    Answer the following:-Stage-1

    (a) What is the project finish date before leveling?

    (b) Which are the over scheduled resources?

    Carry out resource leveling and show your results

    (d) Save the project as a baseline.

    (e) Generate the following:-(i) Gantt chart showing start and finish dates of each activity and resources assigned.(ii) Network diagram(iii) Relationship diagram(iv) Resource sheet(v) Resource Usage(vi) Task Sheet(vii) Task Usage

    Stage-2Consider that 27 days have passed. Task completion status is as follows:-

    (a)A1,A2, A4,B1 and B2 is 100%(b)A3, B3 and B4 is 50%

    Carry out EV analysis find SPI,CPI and EAC

    Note : 1. Assume suitable values wherever required.2. You may use Microsoft Project or any other suitable software application-----------------------------------------------------------------------------------------------------------