Assignment Project Schedule
Schedule the following project subject to given resource limits. Assume start date as 05 Nov 2012.
Identifier Activity Predecessor Days Resource
Perform Planning and Scheduling
A1 Revise overall projectplan
None 10 N, P
A2 Complete detailed plan
for detail design
A1 3 P
A3 Revise skeleton andgeneric plan for rest
A1 3 P
A4 Brief new teammembers
A2, A3 1 M, N, P
A5 Complete phaseestimate
A4 4 O, P
A6 Review plan A5 1 M, N, O, P
A7 Revise plan A6 11 O, P
A8 Complete project
schedule
A5start + 3 4 N
A9 Milestone A7, A8 0
Prepare Database Design
B1 Document data modelsto catalog
None 13 B, P
B2 Determine filestructures for flat files
B1 10 B
B3 Prepare copylibs for flatfile structures
B1 7 B
B4 Define each process B2, B3 3 B, P
B5 Review process access
with databaseadministration
B4 1 D, M, N, P
B6 Physical databasedesign
B5 10 B, R
B7 Review design B6 1 B, D, M, N, P
B8 Revise design B7 10 B, R
B9 Conduct call patternreviews
B6 8 B
B10 Milestone B8, B9 0
Prepare Physical Design Documents
C1 Prepare process toprogram specifications B4 10 P
C2 Determine securityspecifications
B9, C1 8 B, P
C3 Prepare physical systemflow
C2 10 B, P
C4 Milestone C3 0
D1 Design programs andwrite specifications
A8, B9 10 B, P
D2 Write data conversionand interface programs
D1 6 R(3)
D3 Revise documents D2 20 R (3)D4 Milestone D3 0
-
7/27/2019 msproject-ex3
2/2
E1 Implementation C3, D3 6 B, P, R
E2 Testing E1 10 B, P, R
E3 Final acceptance E2 2 M, N, D
E4 Milestone E3 0
Work5 days Per WeekHolidays
3rd and 4th Monday in Nov3rd Monday in Dec, 25 Dec
1st and 3rd Wednesday in Jan 2013
Details of Resources
Resources Cost/Day Resources Cost/Day
M Manager $300(1) R SystemsprogrammersR1,R2 and R3
$200(3)
N Assistant $150(1)
O Cost estimator $200(1) D Database
administrator
$500(1)
P System analysts P1, P2 $350(2) B Database designers $300(1)
Answer the following:-Stage-1
(a) What is the project finish date before leveling?
(b) Which are the over scheduled resources?
Carry out resource leveling and show your results
(d) Save the project as a baseline.
(e) Generate the following:-(i) Gantt chart showing start and finish dates of each activity and resources assigned.(ii) Network diagram(iii) Relationship diagram(iv) Resource sheet(v) Resource Usage(vi) Task Sheet(vii) Task Usage
Stage-2Consider that 27 days have passed. Task completion status is as follows:-
(a)A1,A2, A4,B1 and B2 is 100%(b)A3, B3 and B4 is 50%
Carry out EV analysis find SPI,CPI and EAC
Note : 1. Assume suitable values wherever required.2. You may use Microsoft Project or any other suitable software application-----------------------------------------------------------------------------------------------------------