CONFIDENTIAL INFORMATION
2
Agenda
Project deliverables
Project schedule
Project team
Outstanding risks and any planned actions
Budget and financial information.
L&T contract completion
Project handoff to operational support.
Defect reports, change requests and technical and customer support.
Lessons learned
Next steps –
Tasks moved to post-deployment
Printing solution and more needed hardware
CONFIDENTIAL INFORMATION
3
Planned vs Actual Deliverables
Planned Actual
1. Finance a.General Ledger b.Accounts Receivables c.Accounts Payable d.Job Cost Processes
2. Distribution processes
3. Procurement Processes
4. Production Planning Processes a.Material Requirement Planning (MRP) b.Shop Floor Control (SFC) & Mfg Accounting
5. Inventory Control Processes
6. Sales Order Management
7. Fixed Assets# -
8. Maintenance# - #BW team decided to implement Fixed Assets & Maintenance module as a part of Phase II plan.
CONFIDENTIAL INFORMATION
4
Project Schedule Planned vs Actual
S Project Phases Planned Actual
1 Core team identification 25-Feb-10 25-Feb-10
2 Hardware requirements 25-Feb-10 25-Feb-10
3 JDE AS-IS Process discussion 12-Mar-10 12-Mar-10
4 JDE AS-IS process sign-off 17-Mar-10 17-Mar-10
5 JDE Overview Training 19-Mar-10 19-Mar-10
6 Pain areas discussion 14-Apr-10 22-Apr-10
7 JDE TO-BE Process discussion 14-Apr-10 22-Apr-10
8 JDE Decision points concluded and Gaps identified 14-Apr-10 14-Apr-10
9 JDE TO-BE process sign-off 15-Apr-10 17-Apr-10
10 CAMS AS-IS/To-BE process 14-Apr-10 4-Jun-10
11 JDE/CAMS Configuration Phase 6-May-10 20-May-10
12 Perform JDE Conference Room Piloting 6-May-10 14-May-10
13 JDE Master Data Preparation & Sign-off 31-May-10 10-Jul-10
14 JDE Training 18-May-10 29-Jun-10
15 JDE ICRP preparation 4-Jun-10 15-Jun-10
16 JDE ICRP 18-Jun-10 9-Jul-10
17 CAMS Training/iCRP sign-off 18-May-10 19-Jul-10
18 JDE Master data loading in production environment 30-Jun-10 25-Jul-10
19 Go live 1-Jul-10 26-Jul-10
20 Users Sign-off 15-Jul-10 Pending
Target 1-Jul-10
Revised Target
26-Jul-10
CONFIDENTIAL INFORMATION
Project Steering Committee - BorgWarner
Steve Snyder – VP of Business Development
Steve Carlson – VP of Finance
Yvonne Everhart – VP Information Technology
Bill Liacone – Controller GSC and GO Morse TEC
V.D. Umashanker – Managing Director MTI
CONFIDENTIAL INFORMATION
Project Team with Disband Plan - BorgWarner
Name Project Role Disband Plan Timeframe
Paul Corter Project Manager 16-Aug-10 5 Months
Gerry Munchel Ithaca IT Ongoing offshore Support Need based
Cathy Kaib Ithaca IT Ongoing offshore Support Need based
Stan Bish Ithaca IT Ongoing offshore Support Need based
Chris Bodary Ithaca IT Ongoing offshore Support Need based
Andrew Willard Ithaca IT 16-Aug-10 5 Months
Swetha Swamy Project Coordinator MTI 16-Aug-10 5 Months
R. Murali Plant Manager MTI 16-Aug-10 5 Months
Suresh Babu MTI IT Ongoing onshore Support Need based
Narayanaraju MTI IT Ongoing onshore Support Need based
Kumaran MTI IT 16-Aug-10 5 Months
G. Murali Procurement/Purchasing 16-Aug-10 5 Months
P Saravanan Purchase 16-Aug-10 5 Months
S J Gnanakumar Purchase 16-Aug-10 5 Months
R Mohan Rao Customer Support & Materials 16-Aug-10 5 Months
Tholkappian Customer Support 16-Aug-10 5 Months
Balakrishnan Materials 16-Aug-10 5 Months
V Ganesh Materials 16-Aug-10 5 Months
Saranya Customer Support 16-Aug-10 5 Months
K Saravanan Production 16-Aug-10 5 Months
V Saravanan Manufacturing 16-Aug-10 5 Months
Anbazhagan Manufacturing 16-Aug-10 5 Months
Rajeshwar Singh Manufacturing 16-Aug-10 5 Months
Sudhakar Manufacturing 16-Aug-10 5 Months
Preethi Jacqulin Finance 16-Aug-10 5 Months
Prabhakaran Finance 16-Aug-10 5 Months
Bhuvaneshwari Finance 16-Aug-10 5 Months
Dinesh Finance 16-Aug-10 5 Months
Meenakshi Finance 16-Aug-10 5 Months
Ranjith Finance 16-Aug-10 5 Months
Poomani Finance 16-Aug-10 5 Months
Saritha Finance 16-Aug-10 5 Months
Temp 1 Finance for Valgen entries 30-Sep-10 6 Months
Temp 2 Finance for Valgen entries 30-Sep-10 6 Months
Temp 3 Finance for Valgen entries 30-Sep-10 6 Months
Temp 4 Purchase for Valgen entries 30-Sep-10 6 Months
Temp 5 Materials for Valgen entries 30-Sep-10 6 Months
Temp 6 Materials for Valgen entries 30-Sep-10 6 Months
CONFIDENTIAL INFORMATION
Sathish Kumar - Project Management/Manufacturing
Srinivasan Kannan - Distribution
Madhanagopal Dineshkumar - Distribution
Pankaj Chaugule - Finance
Anup Kuttava - Finance
Vasu Jain - Manufacturing
Team Composition L&T Infotech
CONFIDENTIAL INFORMATION
Outstanding Risks and Planned Actions
• User to follow transactions based on SOP
• Troubleshooting functional issues may be a concern in Mfg area
• Deployment of customizations completed by Narayanaraju
• Enhancing ACOM functionalities
• Integration of SST
• Cheque Printing
• Implementing Fixed assets & Maintenance modules
CONFIDENTIAL INFORMATION
All Values in $
Project Budget & Spending Status
Project Budget
•Project Cost: $ 130 K (Approved)+$ 40.3 K (Amendment)
•Payment Terms ($ 130 K) with Implementation partner
10 % -Advance along with the order acceptance
15 % -After completion of To-Be Process
20 % -After completion of Configuration Phase
20 % -After completion of Training
25 % -On Go-Live ( UAT )
10 % -After completion of Post Go-Live Support
100% Advance for the Cams software. NOTE: $ 20.8 K of $40.3 k will be paid as a part of last installment
Budget Status BUDGET Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec TOTAL
Actual Actual Actual Actual Actual Actual Actual Forecast Forecast Forecast Forecast Forecast
JDE - L&TI
Contract 0 0 24,066 12,007 16,010 16,010 20,012 36,649 0 0 0 1,24,754
JDE - Hardware
expenses 0 0 4,521 1,559 0 0 0 957 10,073 0 0 17,110
JDE - Contract
Team # 0 0 0 0 2,144 721 1532 766 669 0 5,832
JDE - Ithaca
Team Travel
expenses #
0 0 0 12,766 -1,481 0 0 0 11,391 0 0 22,676
JDE Subtotal 0 0 28587 26332 16673 16731 20012 39138 22230 669 0 0 1,70,372
CONFIDENTIAL INFORMATION
LTI Contract Completion
• Implementation contract is live till 13-Aug-10.
• LTI committed to support 4 working days in Sep-10 with one Finance resource
for Aug month end closure.
• No post go live support contract is signed with LTI.
CONFIDENTIAL INFORMATION
Operational Support
• MTI-IT team will assist the user group for operational issues.
• MTI team will collaborate with Ithaca team on need basis
CONFIDENTIAL INFORMATION
Post Go live issues status
• All the issues are getting recorded thru mail. Accordingly
Corrective action is taken
• Finance is in the process of validating the transactions based
on actual entries
CONFIDENTIAL INFORMATION
Lessons Learned…
1. Project phase completion should not coincide with month end closure. 29th to 5th
of every month to be exempted while preparing project timeline.
2. Master data loading to be done before training phase to test all possible
scenarios.
3. All hardware prerequisites need to be a part of contract with implementation
partner. CAMS MY-SQL license requirement was known to the team only during
configuration phase.
4. Data loading method need to be signed-off immediately after TO-BE process.
5. Master data preparation template to be circulated to user group immediately
after TO-BE process sign-off in line with point 4
6. Multiple master template format for the same master to be avoided. This
creates confusion among users during data preparation.
7. Security mapping to be completed immediately after training phase.
8. Department Heads to review their team progress status as a part of their
morning meeting agenda to bring more focus on involvement.
9. Department Heads to give surprise assignments to the team after training
phase to validate the learning effectiveness
CONFIDENTIAL INFORMATION
…Lessons Learned…
10.User to have a check list of all possible scenarios related to their function
including exceptions while discussing AS-IS and TO-BE process.
11.Transactions should not be delegated unless the respective officer is well
trained to do so.
12.User to focus more on process validation rather than focusing reports during
CRP phase.
13.Participation of Finance stakeholder is mandatory in all the process discussions
during AS-IS and TO-BE process phase.
14.User to validate the standard operating procedure (SOP) manual during iCRP
phase.
15.User to follow user manual work flow for a week or fortnight after go live to
ensure proper transaction execution.
16.Month end closure to be included as a part of post go live support with IT
implementation partner.
17.Business process re-engineering to be completed before initiating TO-BE
process.
18.Consultants transportation to be included as a part of contract assumption
CONFIDENTIAL INFORMATION
…Lessons Learned
19.Minimum no. of customizations to be included as a part of project contract
20.Project timeline should not overlap with yearly financial audit (Especially during
AS-IS & TO-BE process discussions)
CONFIDENTIAL INFORMATION
Challenges Accomplished
1. Full blown ERP is implements in 5 months span with 15+ core team members
2. Successful multi location coordination between LTI, MTI, BW Ithaca & CAMS
3. Core team engaged in process discussions despite other commitments
4. Many new processes and modules are implemented
5. Execution of multi level BOM as a part of Product costing/Mfg Accounting
6. …
CONFIDENTIAL INFORMATION
Next Steps…
1. Complete project closure report
2. Multi functional printer purchase
3. Minor customizations based on user group need
4. Establish trouble shooting register to record all the issues