mtl p pgimaster planning process - edl · future housing developments through “metro...
TRANSCRIPT
M t Pl i g PMaster Planning Process
Weld County School District RE-5J
Master Planning Process
•Enrollment , Capacity, and Growth
Facility Framework
ENROLLMENTCAPACITY &
GROWTH
Facility Framework
Long Range Growth Forecast
Weld County School District RE-5J
Master Planning Process
•Enrollment , Capacity, and Growth
Facility Framework
FACILITIESASSESSMENT
ENROLLMENTCAPACITY &
GROWTH
Facility Framework
Long Range Growth Forecast
•Facilities Assessment
Visual Studies of every School and Site
Documentation of Existing Facility Conditions
Order of Magnitude Cost Analysis (repair or replace)
Prioritization of Repairs/Replacement
Weld County School District RE-5J
Master Planning Process
•Enrollment , Capacity, and Growth
Facility Framework
FACILITIESASSESSMENT
ENROLLMENTCAPACITY &
GROWTH
Facility Framework
Long Range Growth Forecast
•Facilities Assessment EDUCATIONAL PROGRAM
Visual Studies of every School and Site
Documentation of Existing Facility Conditions
PROGRAM
Order of Magnitude Cost Analysis (repair or replace)
Prioritization of Repairs/Replacement
•Educational Program Educational Program
Functional Assessment of Facilities to meet Educational needs
Community Use of Facilities
Weld County School District RE-5J
1. Enrollment, Capacity & GrowthENROLLMENT
CAPACITY& GROWTH
Weld County School District RE-5J
Weld Re-5J Actual Value
Change From Prior Year Bonding
Actual Value Actual ValueCapacity (6%)
(thousands) (thousands) PercentYear (thousands)
2006 $ 1,302.8 NA $ 78.2
2007 1,427.8 $ 124.9 9.6% 85.7
2008 1,479.7 52.0 3.6% 88.8
2009 1,452.2 (27.6) -1.9% 87.1
2010 1,389.3 (62.9) -4.3% 83.42010 1,389.3 (62.9) 4.3% 83.4
2011 1,447.3 58.0 4.2% 86.8
2012 1,516.4 69.0 4.8% 91.0
2013 1 553 8 37 5 2 5% 93 22013 1,553.8 37.5 2.5% 93.2
2014 1,637.1 83.2 5.4% 98.2
2015 1,987.4 350.3 21.4% 119.2
Weld County School District RE-5J
2016 2,038.5 51.1 2.6% 122.3
Housing Construction Based Upon Development Expectations: p
Annual 2017 to 2022 and Project Completion by Elementary Area
Anticipated AbsorptionAnticipated Absorption Total Units
Add'l bRemain.
2022Area 17 18 19 20 21 22
Add'l. by 2022
2022-buildout
Letford - - - - - - - 200
Milliken 128 127 205 210 209 176 1,056 908
Pioneer Ridge 37 71 134 134 99 100 576 7,733
Based upon interviews with town and county officials and area developers and builders, November and
Total: 165 198 339 345 309 276 1,632 8,841
Weld County School District RE-5J
p v w w w y v p b , N v bDecember 2016. Major developments only; excludes recorded exemptions and other small projects.
Weld Re-5J Annual Enrollment Change f P i Yfrom Prior Year
6.0%
4.0%
5.0%
ange
2.0%
3.0%
Per
cen
t C
h
0.0%
1.0%
P
2006
-07
2007
-08
2008
-09
2009
-10
2010
-11
2011
-12
2012
-13
2013
-14
2014
-15
2015
-16
Weld County School District RE-5J
Year
Potential Enrollment Based Upon Development Expectations: Annual 2017 to 2022 and Project Completionj p
Additional Students Forecast by Year
By School Level 17 18 19 20 21 22 2022-Proj.
Comp. Proj.
Comp. Elementary (K-5): Letford - - - - - - 60 60 Milliken 34 34 50 52 52 44 264 530 Pioneer Ridge 11 21 40 40 30 30 2,330 2,503
T l 45 55 91 93 82 74 2 654 3 094Total 45 55 91 93 82 74 2,654 3,094
Middle (6-8): Milliken 22 27 45 46 40 36 1,308 1,524
Total 22 27 45 46 40 36 1 308 1 524Total 22 27 45 46 40 36 1,308 1,524
Sr. High (9-12): Roosevelt High 26 32 53 54 47 42 1,501 1,754
Total 26 32 53 54 47 42 1,501 1,754
Based upon interviews with town and county officials and area developers and builders, November and
ota 6 3 53 54 47 4 ,50 ,754
K-12 Total: 93 114 188 192 169 153 5,463 6,372
Weld County School District RE-5J
p v w w w y v p b , N v bDecember 2016. Major developments only; excludes recorded exemptions and other small projects.
Enrollment Forecast Summary by School: 2017 to 2022 Aby School: 2017 to 2022 Avg.
Actual Ann. %Schools 2016 2017 2018 2019 2020 2021 2022 ChangeElementary Schools:
Knowledge Quest 276 276 281 279 277 277 276 0.0%Knowledge Quest 276 276 281 279 277 277 276 0.0%Letford 551 560 562 545 544 566 567 0.5%Milliken 572 545 562 570 575 611 622 1.4%Pioneer Ridge 613 635 670 651 680 702 718 2.7%
Total PK-5 2,012 2,015 2,075 2,045 2,076 2,155 2,183 1.4%
Middle Schools: Knowledge Quest 126 131 125 126 128 128 128 0.3%Milliken Middle 715 737 743 807 819 815 803 2.0%
Total 6 8 841 868 868 933 947 943 931 1 7%Total 6-8 841 868 868 933 947 943 931 1.7%
High School: Roosevelt High 927 951 1,002 1,019 1,033 1,043 1,113 3.1%Other Programs 52 50 50 50 50 50 50 -0.7%
B d p fi l O t b r 1 r llm t t d t *E l d r llm t i th r pr r m i l di O li Tr iti
979 1,001 1,052 1,069 1,083 1,093 1,163
Total PK-12 3,832 3,884 3,995 4,047 4,106 4,192 4,277 1.8%
Weld County School District RE-5J
Based upon final October 1 enrollment count data. *Excludes enrollment in other programs including Online, Transition, CBOCES and Off Site.
Enrollment Forecasts vis-à-vis Permanent Facility CapacityPermanent Facility Capacity
Perman.Facility Actual
Schools Capacity 2016 2017 2018 2019 2020 2021 2022 2016 2019 2022El S h l
Permanent FacilityCapacity Less Enrollment
Enrollment
Letford 624 551 560 562 545 544 566 567 73 79 57 Milliken 676 572 545 562 570 575 611 622 104 106 54 Pioneer Ridge 728 613 635 670 651 680 702 718 115 77 10
Total Elementary 2,028 1,736 1,739 1,794 1,766 1,799 1,879 1,907 292 262 121
Elementary Schools:
Middl S h lMilliken Middle 928 715 737 743 807 819 815 803 213 121 125
Total Middle 928 715 737 743 807 819 815 803 213 121 125
Roosevelt HS 976 927 951 1,002 1,019 1,033 1,043 1,113 49 (43) (137)
Middle Schools:
High Schools:
Other Programs NA 52 50 50 50 50 50 50 NA NA NATotal Sr. High 976 979 1,001 1,052 1,069 1,083 1,093 1,163
Total TraditionalSchool PK-12 3,430 3,477 3,589 3,642 3,701 3,787 3,873
Charter SchoolsKnowledge Quest ES 276 276 276 281 279 277 277 276 - (3) - Knowledge Quest MS 134 126 131 125 126 128 128 128 8 8 6
Charter Total 410 402 407 406 405 404 405 404 8 5 6
Grand Total 3,832 3,884 3,995 4,047 4,106 4,192 4,277 Note: School capacities are for permanent facilities only excluding portables
Weld County School District RE-5J
*Excludes enrollment in other programs including Online, Transition, CBOCES and Off Site.Note: School capacities are for permanent facilities only, excluding portables.
Facility Utilization and EfficiencyPerman. Facility Student Enrollment Utilization RateFacility Student Enrollment Utilization Rate
Schools Capacity 2016 2019 2022 2016 2019 2022
Based Upon Total Enrollment Elementary Schools:
Knowledge Quest 276 276 279 276 100.0% 101.1% 100.0%
Letford 624 551 545 567 88.3% 87.4% 90.8%
Milliken 676 572 570 622 84.6% 84.3% 92.1%
Pioneer Ridge 728 613 651 718 84.2% 89.4% 98.6%Total Elementary 2,304 2,012 2,045 2,183 87.3% 88.8% 94.8%
Middle Schools: Knowledge Quest 134 126 126 128 94.0% 94.1% 95.7%
Milliken Middle 928 715 807 803 77.0% 87.0% 86.5%Total Middle 1,062 841 933 931 79.2% 87.9% 87.7%
High Schools:
Roosevelt HS 976 927 1,019 1,113 95.0% 104.4% 114.0%
Sr. High Total 976 927 1,019 1,113 95.0% 104.4% 114.0%
Weld County School District RE-5J
Note: School capacities are for permanent facilities only, excluding portables.
Capacity Planning Recommendations
Near-term concerns (next three to four years) can be accommodated by interim measures, e.g. mobiles
I t i l i (f t 10 ) h ld i l d Interim planning (four to 10 years) should include preparation for a new elementary school and a new high school
A new elementary school should open the fall that enrollment will exceed the existing capacity by 25 percent or moreor more
A new high school should open the fall that enrollment will exceed the existing capacity by 20 percent or more
Future housing developments through “metro districts”.
Weld County School District RE-5J
2. Facilities Assessment
FACILITIESASSESSMENT
• Visual Studies of each School and Site, by the Architect and Engineering Team:
(Structural, Electrical, Mechanical/Plumbing, IT, Civil)
D t ti f E i ti g F ilit C diti i th • Documentation of Existing Facility Conditions, in the Facility Assessment Document
• Order of Magnitude Cost Analysis (repair or replace), by a General Contractor (Adolfson & Peterson). Costs have been escalated approximately 2+ years.
• Initial Prioritization of Assessment Items
Weld County School District RE-5J
Roosevelt High SchoolRoosevelt High SchoolSelect High Priority Items:• New Roof• Improve Roof drainage• New Fire Sprinkler System
(@Main Building & Ag Shop)(@ Main Building & Ag Shop)• New HVAC Equipment• New HVAC Controls• Ventilation Upgrades• New Emergency Generator• Fire Alarm System Upgradesy pg• Security System Upgrades
Weld County School District RE-5J
High Priority Costs: +/‐ $12,800,000
Letford Elementary SchoolLetford Elementary SchoolSelect of High Priority Items:• New roof• Improve roof drainage• Repair Water Infiltration Issues• New Fire Sprinkler System• Fire Alarm System Upgrades• Egress Lighting Upgrades• ADA Upgrades
S it S t U d• Security System Upgrades
Weld County School District RE-5J
High Priority Costs: +/‐ $7,800,000
Pioneer Ridge Elementary SchoolPioneer Ridge Elementary SchoolSelect of High Priority Items:• Repair Water Infiltration issuesp• Mitigate exterior drainage issues
Weld County School District RE-5J
High Priority Costs: +/‐ $63,000
District Transportation BuildingDistrict Transportation BuildingSelect of High Priority Items:• Building Replacementg p
Weld County School District RE-5J
High Priority Costs (New Building): +/‐ $3,300,000
Milliken Elementary SchoolMilliken Elementary SchoolSelect of High Priority Items:• Improve Roof Drainagep g• New Roof• Playground Equipment Upgrades• Playground Play Surface Upgrade• Playground Play Surface Upgrade• New Fire Sprinkler System• ADA Upgrades• Repair Water Infiltration Issues• HVAC Upgrades• Fire Alarm System Upgradesy pg• Egress Lighting Upgrades• Security System Upgrades
Weld County School District RE-5J
High Priority Costs: +/‐ $7,500,000
Early Learning CenterEarly Learning CenterSelect of High Priority Items:• Playground Surface Upgradesyg pg• New Fire Sprinkler System• Improve Roof Drainage
Weld County School District RE-5J
High Priority Costs: +/‐ $475,000
Milliken Middle SchoolMilliken Middle SchoolSelect of High Priority Items:• New Roof• Improve Roof Drainage• New Fire Sprinklers• HVAC System Upgrades• HVAC System Upgrades• Egress Lighting Upgrades• Fire Alarm System Upgrades
Weld County School District RE-5J
High Priority Costs: +/‐ $9,500,000
Facilities Assessments - High Priority Items:
Hard Construction Costs
ROOSEVELT HIGH SCHOOL
LETFORD ELEMENTARY SCHOOL
PIONEER RIDGE ELEMENTARY SCHOOL
TRANSPORTATION CENTER
MILLIKEN ELEMENTARY SCHOOL
EARLY LEARNING CENTER
TRANSPORTATION CENTER
EARLY LEARNING CENTER
MILLIKEN MIDDLE SCHOOL
Weld County School District RE-5J
HIGH PRIORITY TOTAL
Facilities Assessments – All Priorities – by School
Weld County School District RE-5J
3. Educational Program
EDUCATIONAL PROGRAM
Weld County School District RE-5J
Mill Levy Override (MLO) Educational Program Enhancements
DISTRICT PRIORITIES PROGRAMS NEW FACILITIES
• Safety and Security • Full Day Kindergarten • Operations and • Safety and SecurityEnhancements
• Class Size Relief
• Full-Day Kindergarten
• Enhanced InterventionPrograms
• Operations and Maintenance
• Teachers and Support Districtwide
• Technology and Curricular Resource that
• Increased Secondary Elective Options
Staff
Enhance Learning
• Enhanced college and career counseling
• Increased Concurrent Enrollment & Advanced Placement Options
career counseling services • Enhanced Districtwide
Gifted Programming
Weld County School District RE-5J
Community Input
• 2016-2017 Studies: Demographics, Master Planning, DAC
• Spring 2017 Survey, Focus Groups, and Interviews
• Launched [email protected] g
• May 2017 Community Meeting
201 2018 S• 2017-2018 School Year
• Form Advisory Committees
• Community Meeting Schedule
Weld County School District RE-5J
New High School – Comparison Costs
Weld County School District RE-5J
New High School – Initial Project Program:Building Components:
• 1,200 Student Capacity
• +/- 217 000 SF
Site Components:
• +/- 60 Acres
• Stadium with Track and Football Field +/ 217,000 SF
• Small Learning Communities
• STEM & Career Exploration Center
Stadium with Track and Football Field (Seating for 3,000)
• Soccer Field
• Library / Media Center
• 600 Seat Auditorium / Drama Classroom
• Multi-Purpose Field
• Baseball / Softball Fields
• Parking for 675 vehiclesClassroom
• Vocal / Instrumental Classrooms
• Visual Arts Suite
Parking for 675 vehicles
+/- $103,500,000• Main Gym (1,600 Seats) /
Auxiliary Gym (250 seats)
• Dining / Student Commons
Weld County School District RE-5J
g /
Mill Levy / Bond Election Tax Impacts:
Weld County School District RE-5J
Mill Levy / Bond Election Tax Impacts:
Weld County School District RE-5J
New High School – Conceptual Project Schedule:
• Pre-Bond Work: May 2017 through October 2018
2018 B d El i N b 6 2018• 2018 Bond Election: November 6, 2018
• Site Procurement / Due Diligence: November/December 2018
• Contract Negotiations: November 2018
• Project Design: December 2018 through May 2019
• Permitting: June/July 2019
• Construction: August 2019 – July 2021Construction: August 2019 July 2021
• Owner Move-In: August 2021
• Owner Occupancy / Start of School: Fall 2021
Weld County School District RE-5J
• Owner Occupancy / Start of School: Fall 2021