multi-year price determination 4 revenue application · gdp growth as compared to the base case...
TRANSCRIPT
Multi-Year Price Determination 4
Revenue application
NERSA Public Hearings
Midrand Day 1
4 February 2019
• Eskom is satisfied with the robustness of its sales forecasting process.
• However, due to the lag between the completion of the forecast and the timing of the submission it is important that the forecast is revised closer to the decision date.
• NERSA MYPD methodology, applicable from 2019 year allows for review of sales forecast closer to decision date – this contributes to addressing the challenge.
• Eskom provided the revised sales forecast during the Rustenburg public hearings and it will be confirmed during the Gauteng public hearings.
• NERSA is afforded to undertake its own verification process before their final decision.
• The decision then forms the reference point of the RCA process.
• In addition, consideration by NERSA to review the ERTSA methodology that will allow NERSA to make sales volume adjustments on an annual basis based on latest available projections – will avoid increasing divergence.
Eskom maintains its sales forecasting process is sufficiently robust
2
NERSA methodologies should allow for adjustments on a regular basis
Actual Standard tariff sales trend compared to average tariff adjustment from 2007
• In 2008, 3,9% decrease YOY sales volumes was linked
to load shedding, ECS, crash in global economy etc.
• Recovery in 2009 attributed to growth in construction
industries with building of stadiums for World cup,etc
• Marikana, in 2012 impacting the Platinum sector
compounded by closure of ArcelorMittal in van der Bijl,
reduction at Samancor and closure of Silicon
Technologies in Newcastle.
• Subsequent periods reflect a general decline in
construction industry, especially steel &cement industry.
Key PointsAverage Tariff adjustments
Difficult to conclude on any correlation indicating other influencing factors
GWh sales
3
Specific reasons for drop in sales in Industrial sector provided by Eskom customers
• Low economic growth due to Global factors , e.g. Recession, Exchange rates, , Trade
barriers, etc.
• Decline in Commodities / Metal demand
• Implementing energy efficient technologies
• Mechanisation
• Labour/Industrial relations
• Changes in the structure of SA economy,
from Energy intensive Sectors ( Mining & Manufacturing) to the Services sector
• Government policy/legislation uncertainty
• Electricity supply reliability & availability
• Transport/logistics challenges
• Recycling of scrap
• Crime & Illegal Mining
The price of electricity alone is unlikely to reverse the deterioration
in the economy; it would require a holistic approach
4
National Treasury indicates impact of 15% increases
GDP is expected to deviate by an average
of 0.1 percentage point from the baseline
growth forecast.
Energy intensive sectors like mining are
anticipated to experience the most adverse
effects.
The gold and uranium sub-sector is
projected to be particularly sensitive given
the structural vulnerabilities that already
exist in the sector.
The electricity sector will be directly
affected by weaker demand of electricity.
Weaker demand for electricity is projected
across all household income groups.
The price elasticity of electricity demand is
estimated to be less than -0.5
NB: These results are based on a 15%
annual tariff increase over the MYPD 4
period.
Key Points
National Treasury study estimates price elasticity of demand to be less than
-0.5 with 15% increases
6
Extract from 2009 price elasticity study by external
consulting economists: matrix of possibilities, showing
estimated responses to potential changes……
7
• This matrix table explores the possible changes in
electricity consumption given different changes in
output and price, and is based upon the elasticity
estimates for the period 2003m1 – 2009m4.
• The changes in output and price are real (after
normal inflation/PPI has been removed). The darker
sections show where there is an increase in
consumption, the lighter sections show decreases.
This analysis assumes a linear demand curve
without threshold levels
• The table must be interpreted as the medium-
term change in price and output (6-7 years)
• I.e. for manufacturing a 75% real increase in price
coupled with a 20% increase in output is estimated
to result in a 3.7% decrease in electricity
consumption. However for only a 30% real increase
in price and a 20% increase in output results in
increase in consumption of nearly 10%
• For metals the contraction is to be less responsive
to price – but a similar scenario could see a
reduction around 8%.
• CAVEAT: The real increase in price is after inflation
– one must remember that electricity price hikes
have an impact on inflation
• The impact of a price increase must always be read
in conjunction with the impact of an increase in
gross value added.
Key PointsManufacturing Matrix
Metals Matrix
Metals Matrix Price Elasticity: -0.31
Income Elasticity: 0.78
-15% -10% -5% 0% 2% 5% 10% 15% 20% 25% 30%
0% -11.7 -7.8 -3.9 0.0 1.6 3.9 7.8 11.7 15.6 19.5 23.4
5% -13.3 -9.4 -5.5 -1.6 0.0 2.4 6.3 10.2 14.1 18.0 21.9
10% -14.8 -10.9 -7.0 -3.1 -1.5 0.8 4.7 8.6 12.5 16.4 20.3
15% -16.4 -12.5 -8.6 -4.7 -3.1 -0.8 3.2 7.1 11.0 14.9 18.8
20% -17.9 -14.0 -10.1 -6.2 -4.6 -2.3 1.6 5.5 9.4 13.3 17.2
25% -19.5 -15.6 -11.7 -7.8 -6.2 -3.9 0.1 4.0 7.9 11.8 15.7
30% -21.0 -17.1 -13.2 -9.3 -7.7 -5.4 -1.5 2.4 6.3 10.2 14.1
50% -27.2 -23.3 -19.4 -15.5 -13.9 -11.6 -7.7 -3.8 0.1 4.0 7.9
75% -35.0 -31.1 -27.2 -23.3 -21.7 -19.4 -15.5 -11.6 -7.7 -3.8 0.1
100% -42.7 -38.8 -34.9 -31.0 -29.4 -27.1 -23.2 -19.3 -15.4 -11.5 -7.6Ch
an
ge i
n R
eal
Pri
ce l
evels
Change in Real Output levels
Manufacturing Matrix Price Elasticity: -0.30
Income Elasticity: 0.94
-15% -10% -5% 0% 2% 5% 10% 15% 20% 25% 30%
0% -14.1 -9.4 -4.7 0.0 1.9 4.7 9.4 14.1 18.8 23.5 28.2
5% -15.6 -10.9 -6.2 -1.5 0.4 3.2 7.9 12.6 17.3 22.0 26.7
10% -17.1 -12.4 -7.7 -3.0 -1.1 1.7 6.4 11.1 15.8 20.5 25.2
15% -18.6 -13.9 -9.2 -4.5 -2.6 0.2 4.9 9.6 14.3 19.0 23.7
20% -20.1 -15.4 -10.7 -6.0 -4.1 -1.3 3.4 8.1 12.8 17.5 22.2
25% -21.6 -16.9 -12.2 -7.5 -5.6 -2.8 1.9 6.6 11.3 16.0 20.7
30% -23.1 -18.4 -13.7 -9.0 -7.1 -4.3 0.4 5.1 9.8 14.5 19.2
50% -29.1 -24.4 -19.7 -15.0 -13.1 -10.3 -5.6 -0.9 3.8 8.5 13.2
75% -36.6 -31.9 -27.2 -22.5 -20.6 -17.8 -13.1 -8.4 -3.7 1.0 5.7
100% -44.1 -39.4 -34.7 -30.0 -28.1 -25.3 -20.6 -15.9 -11.2 -6.5 -1.8
Change in Real Output levels
Ch
an
ge i
n R
eal
Pri
ce l
evels
NERSA analysis in 2018 indicated growth of 1.8% increase in electricity sales with a 5.23% nominal increase in price
Projected increase in electricity sales as per NERSA decision did not
materialise as anticipated.
8
9
Cost of Alternative Energy
Solar PV cost are projected to
decrease by approximately 8% per
annum up to 2020 – thereafter could
slowdown – cost plateau.
Future tariffs will change the value
proposition of PV systems.
The structure of the tariff (to reflect
capacity costs) plays a significant role
in the attractiveness of solar PVs:
Cost reflective tariff structure will
reduce the commercial viability of
solar PVs.
Limitations to solar PVs as a large
scale alternative:
Low load factor.
Not available on demand.
Battery backup ~ not yet
commercially and technically viable –
for large scale deployment.
Key Points
Research indication of Small Scale Embedded Generation (SSEG) Photovoltaic penetration in SA for energy component of electricity
• Electricity is a multitude of value products per kWh – these are Peak capacity, dispatched ramping, Energy,
Sync Power, System strength, frequency, voltage
• End 2017 PV penetration ~285MW + 100MW growth ~385MW Solar PV penetration for 2018
• <1% of system installed generation capacity;
• Most likely future scenario 100MW p.a. additional SSEG solar PV
• Most likely expected Solar PV penetration by 2021: 700MW-800MW
SSEG PV projected to grow conservatively
10
Key Points on relatively inelastic price elasticity of demand
Various studies of price elasticity of electricity demand have estimated electricity demand to be relatively inelastic – However:
– Demand response has increased following significant real price increases in the last decade (in excess of 250% in nominal terms),
– Above inflation price increases during the MYPD 4 period will put pressure on electricity intensive sectors which could result in a reduction in electricity consumption in the long term,
– The proliferation of Distributed Generation (DG) (e.g. end-user solar panels) could result in an erosion of sales volumes,
A 13% (19%) annual tariff increase could result in a 0.1 (0.3) percentage point deviation in GDP growth as compared to the base case scenario.
Higher tariffs are bound to dampen demand. However a reluctance to raise prices towards cost reflectiveness will deny the utility the ability to fund investments and maintenance required to sustain an adequate security of supply.
An inadequate security of supply has more negative repercussions to economic growth and social welfare than a tariff increase.
A long term tariff path is required to facilitate long term investment decisions. This will assist both investors and consumers to adapt as the sector goes through a structural change.
11
Eskom supports protection of vulnerable sectors
Eskom has heard various stakeholders at the public hearings indicate that 15% price
increases will impact their businesses and households
− Eskom understands potential impacts of increases in certain vulnerable sectors
− Many industrial and other consumers require reliable electricity supply
− Low consumption residential users require protection
Average price increase Eskom has motivated should not be confused with protecting
vulnerable sectors.
Eskom has actively encouraged exploring policy options with government to protect
identified vulnerable sectors.
It is recognised that further interventions are urgently needed
This requires the co-ordination of various parties – led by Government
− NERSA has already approved two short-term incentives that addressed distressed industries successfully.
− This should be tight up with the country’s industrial policy and economic development strategy.
However, average price of electricity cannot continue to be below prudent
and efficient cost
12
Production Plan requires many assumptions as inputs and determines how much energy is expected to be produced by each station
Changes in assumptions for updated Production
Plan include:
• Energy Forecast
• Generation plant availability
• Eskom New Build commissioning dates
• Eskom and IPP OCGTs optimization as per
system requirements
• Shut-down units at Grootvlei, Hendrina and
Komati are excluded
• Operating units from Grootvlei, Hendrina and
Komati are excluded from dead stop dates
New Build Medupi
Capacity (MW)Application CO
Dates
Revised CO
Dates
1st unit 720 Commercial Commercial
2nd unit 717 Commercial Commercial
3rd unit 720 Commercial Commercial
4th unit 722 31-Oct-18 30-Apr-19
5th unit 722 31-May-19 30-Apr-19
6th unit 722 31-May-19 30-Nov-19
New Build Kusile
Capacity (MW)Application CO
Dates
Revised CO
Dates
1st unit 720 Commercial Commercial
2nd unit 711 31-Oct-19 31-May-19
3rd unit 711 31-Aug-19 31-Dec-19
4th unit 711 31-Dec-20 31-Dec-20
5th unit 711 31-Aug-21 31-Aug-21
6th unit 711 30-Jun-22 30-Jun-22
Energy Availability
Factor2019/20 2020/21 2021/22
MYPD 4 application 78% 78% 78%
Impact of changes 71.5% 72.5% 73.5%
14
Production Plan for MYPD4 application showed that 3 stations were not required to generate electricity
• Based on assumptions used at the
time, the Production Plan showed
that Grootvlei, Hendrina and
Komati would not be required to
meet demand for duration of
MYPD4 period.
• Due to uncertainties in
assumptions, they were required as
backup or an “insurance policy”.
• No Capex and reduced Opex for
these stations in application.
• 12 units shut down – Duvha u3 and
11 units from Grootvlei, Hendrina
and Komati
• Additional 12 units from these 3
stations will shut down (dead stop
dates) in MYPD4 period.
• Under current assumptions, these
units will not be able to return within
12 months so are taken out of RAB
and from Production Plan
• No Capex for these units and
reduced Opex – no change
Application Production Plan Updated Production Plan
However, these plans are based on various assumptions so should Eskom
require these units in future, they could be returned to service and changes
to costs may be reflected in future MYPDs.15
Impact of changes on production plan, EAF and tech plan outage capex
Production Plan
GWh
MYPD 4 application Changes Impact of changes
2019/20 2020/21 2021/22 2019/20 2020/21 2021/22 2019/20 2020/21 2021/22
Coal 203 757 202 387 201 508 -6 995 -6 861 -5 825 196 762 195 527 195 684
Nuclear 14 902 14 155 13 655 -1 189 -636 -2 234 13 712 13 518 11 422
OCGT 211 211 211 1 963 823 291 2 174 1 034 502
Hydro 693 689 690 0 0 0 693 689 690
Pumped storage 5 069 5 164 5 091 -99 237 71 4 971 5 402 5 162
Sere 344 344 344 -30 -32 -32 314 312 312
Total Eskom Production 224 977 222 951 221 500 -6 350 -6 469 -7 729 218 626 216 482 213 771
IPPs 12 099 15 035 18 665 297 189 53 12 395 15 224 18 719
International trader 9 491 9 463 9 462 1 083 1 083 1 084 10 573 10 545 10 545
Gross Production 246 566 247 449 249 627 -4 971 -5 198 -6 592 241 595 242 251 243 035
Less-pumping -6 838 -6 965 -6 872 343 -106 114 -6 495 -7 071 -6 757
Nett Production 239 728 240 484 242 755 -4 628 -5 303 -6 478 235 100 235 180 236 278
Tech plan, Outage CAPEX
R’ millions
MYPD 4 application Changes Application with changes
2019/20 2020/21 2021/22 2019/20 2020/21 2021/22 2019/20 2020/21 2021/22
Total 12 187 12 809 12 384 3 194 5 291 4 244 15 381 18 100 16 628
16
The avoided cost of not running Grootvlei, Hendrina and Komati is more than double the estimated cost of OCGT fuel
Based on the current outlook, utilising OCGTs is
more cost effective
17
Reviving STPPP and MTPPP requires business case and time for various approvals
• A business case would need to be undertaken to determine viability
• If determined to be viable, then process can be initiated
• Procurement processes would be in accordance with National
Treasury and Eskom processes
• Eskom governance, PFMA and NERSA approvals are needed
• NERSA may require to undertake a public consultation process in
accordance with its processes
• Commitment from NERSA of cost recovery is essential
• Estimated timeframe is between 6 to 10 months
18
Eskom did not consider this option when Production Planning changes were
made due mainly to the extended timeframe required. It could be considered
for 2021 onwards
Of 231 outages in base plan (1 April 2016 –31 March 2019), 138 are either completed or in execution and 121 have been added
Outages were deferred or cancelled either due to units being shut down, or due to a change in
Eskom’s maintenance philosophy, from a time-based to a condition or risk-based maintenance
regime.
Of the original 50 outages deemed to be in backlog, 45 outages have been completed, two are in
execution, while three have been cancelled as the units have been shut down.
231
46
121
124
47
63
76
82
ExecutingBase Plan Completed
14
FY20Deferred Cancelled Additional FY21 FY22
19
Post Outage unplanned losses is small contributor to total unplanned losses
•
Post-outage UCLF performance was 0.60% of total UCLF (16.59%)
20
Eskom coal stations below benchmark costs for non-fuel O&M
• Applicable to non-fuel O&M costs,
• Including capitalised maintenance costs
• “Real @ Applicable R/$” uses ave. exchange rate
applicable to each year
FY
FY
Benchmarks considered:
− EPRI: $60.60/kW per year
− IEA: $66.34/kW per year
− Sub-Saharan Electricity Sector
report: $63.94/kW per year
The median value was used as the
comparison to Eskom Generation
− Note benchmark reflects costs that
are ‘levelised’ over life cycle i.e.
which smooth benchmark,
whereas comparison is to Eskom
power station annual costs, bulk
of which are in mid-life cycle which
implies higher costs for mid-life
refurbishment etc.
21
Generation staffing: aligned to average for USA coal-fired electricity generation industry
• Preliminary research indicates that average ratio for all US coal stations is 3.38MW per employee vs Eskom’s coal stations of 3.46MW per employee
• For Eskom Generation the 2016 World Bank report implied a ratio of 9.53MW per employee. This is significantly higher than their average for Africa of 2.3MW (of various technologies) per employee and 2.44MW per employee for coal (e.g. in the case of Botswana).
• At a ratio for Eskom coal plant of 3.46MW per employee (similar to the US actual data and 42% better than the WB’s ratio for Botswana coal stations), plus peaking and nuclear plant staffing, it translates to 13575 employees for Eskom Generation (as opposed to 4 648 per World Bank report).
• The assumptions used in the 2016 World Bank report seem flawed. If 9.53MW per employee was plausible to the USA it would imply that the US coal fired electricity industry’s current staffing is 2.8 times what it should be
22
Eskom’s Board is committed to rooting our fraud
and corruption
14 implicated senior executives exited. Finalisation of outstanding disciplinary hearings
relating to senior executives being accelerated
12 criminal cases opened, five of which involve nine senior executives
Total of 1 049 outstanding cases since April 2018, of which 934 have been finalised,
resulting in 115 under consideration
As at 31 December 2018, a total 295 whistle blow cases are under investigation, 140 cases
have been completed.
Lifestyle audits of senior management in progress. There is effective declaration of
interest
Investigated all irregular supplier contracts (so far, five are no longer doing business with Eskom). Recovered R902 million from McKinsey with an additional R99 million recovered relating to interest
Cooperating with eight regulatory bodies conducting major investigations
These are: National Treasury procurement investigations, Zondo Commission, Hawks, SIU, Parliamentary
Inquiry, National Director of Public Prosecutions, Standing Committee on Public Accounts and SAPS
Eskom will provide NERSA with details as soon as developments occur
24
Eskom will provide further details to NERSA as developments occur
NERSA’s estimate of Future Price Path (FPP)Reasons for Decision June 2009
Indication of the Future Price Path
Figure 1: 5 Year Expected Price Cone
Source: NERSA Modelling of Price Path 26
MYPD 2, 3, 4 revenue applications vs. NERSA’s FPP (constant 2009 Rands)
All three MYPD revenue applications plateaued (once they reached prices reflective of prudent and
efficient costs) around midway between FPP’s upper / lower cost-reflectivity boundaries:
MYPD2,3,4 revenue applications’ final years within FPP cost-reflective boundaries27
‘Benchmarking’ of NERSA’s FPP(constant 2018/19 Rands)
‘Lower boundary’ of US$ 8.5c/kWh is very low by any international benchmark. EIUG / BUSA’s
proposals to NERSA for MYPD3’s 5th year 2017/18 reached same level (although not yet cost-
reflective). IRP, World Bank report aligned to mid / upper boundary:
135c/kWh or
US$10c/kWh*
114c/kWh or
US$8.5c/kWh*
* @ R13.50:$1
EIUG proposed
104 -118c for MYPD3
BUSA 108c
IRP2018
Current ave. price
is 89.4c/kWh
(US$ 6.6c/kWh**)
World Bank
report
FPP’s upper / lower boundaries confirmed by numerous recent benchmarks28
Draft IRP and REIPPPP BW4 confirm NERSA’s FPP
FPP vs. MYPDs, BW4, IRP, BUSA / EIUG’s proposals and World Bank: all provide outcomes within
NERSA FPP upper/lower boundary regarding price required for financial sustainability:
Note : all three graphs have been
calibrated to the same tariff scale
Although there would be some
vulnerable industries, if it was true that
no industry can tolerate prices higher
than Eskom’s current ave.price of
89.4c/kWh (US$ 6.4c/kWh) it makes the
IRP totally academic
IRP ‘least cost’ scenario ~fits within FPP boundaries, other scenarios higher29
• The World Bank undertook an analysis of electricity utilities in 39 countries in Sub-Saharan Africa, which included an assessment of their opex and capex.
• The analysis concluded
that Eskom’s unit costsare very low relative to other SSA utilities (3rd
lowest).
• Similarly, Eskom’s average price is very low relative to other SSA utilities – but they are all pricing their electricity at unsustainably low levels thus are in (or heading to) significant financial difficulties.
“median tariff in SSA was
US$ 0.15 / kWh, median cost US$
0.21 / kWh” (World Bank)
World Bank’s 2016 report says Eskom’s price should
be US$ 10c/kWh ‘at benchmark performance’
World Bank’s analysis shows that
Eskom’s price should be US$ 10c/kWh
‘at benchmark performance’
``
US$ c/kWh
700 10 20 30 40 50 60
WB says Eskom’s current low price of 6.5c/kWh is >80% due to underpricing30
Balance sheet impact due to price gap
Balance Sheet impact: actual prices vs. NERSA FPP lower boundary:
Revenue gap for 2018/19
= R39bn after tax
31
Balance sheet impact due to price gap
Balance Sheet impact: actual prices vs. NERSA FPP lower boundary to midway:
Total revenue shortfall = R339bn (incl. interest at 9% p.a. and deduction of Company Tax)
R339bn
= 68% of Eskom’s liabilities at
31 Mar 2018. Debt ratio could have
been 25% (or ~35% if dividends of
R10bn p.a. had been paid). SAIG** ct.
rating requires <55%. This is the main
cause of the high debt ….
…. in effect an electricity
price subsidy which has
been funded through
Eskom’s balance sheet
** SAIG = Stand
Alone Investment
Grade
32
Balance sheet impact due to price gap
Balance Sheet impact : MYPD4 application vs. NERSA FPP mid-boundary:
Total revenue shortfall = R107bn (incl. interest at 9% p.a. and deduction of Company Tax)
R107bn
Hence Eskom’s
debt will continue
to increase over
period to 2024,
before stabilizing
33
By end of MYPD4 the cumulative effect of pricing below FPP is ~R450bn
Cost-efficiency remains crucial but be viewed in overall context
Illustrated below is price effect of (beyond plausible) R15bn p.a. reduction in O&M and PE :
Reduces required
price from mid-point
between upper/lower
boundary, to closer
(but still above) lower
boundary …
Would reduce required price by ~8c/kWh (Rands of 2018), from ~124c to 116c/kWh
… thus potential
future efficiency
gains cannot be an
argument against
increasing price to
lower boundary
At benchmark performance the price required to cover efficient costs >114c/kWh34
Main cause of the required price increase is the phasing-out of the current price subsidy
Main cause of price increase
is not increasing cost but
because the current price
subsidy is being phased out
…. which does not preclude subsidization of specific targeted customer categories, through direct,
targeted and transparent subsidies, in a way that leaves Eskom revenue-neutral
… which does not
preclude
subsidization of
specific customer
categories in future
Eskom cannot any longer fund the price subsidy / underpricing with debt35
NERSA’s FPP vs. MYPD4 – conclusions (1 of 2)
1. Electricity is a highly capital/asset intensive, high fixed and sunk cost business (=75%
of cost) i.e. main cost driver is assets being operated
2. Eskom of 2018 is essentially the same as Eskom of 2009, just larger – same power
stations plus 6GW more, with construction programme underway for further 6GW;
same network plus 36000km more lines; same customer base plus 1.9 million more.
No reason that the FPP estimated in 2009 would be any lower in 2018
3. For lower boundary of FPP NERSA stipulated a number of conditions to be fulfilled – of
which virtually none has happened. In addition NERSA did not price-in the cost
increases due to REIPPPP BW1-3
4. However Eskom’s required price by 2024 is still around mid-way between upper
and lower boundaries of NERSA’s FPP (and very competitive with the lowest-cost
IRP scenario)
5. Further efficiency gains in future might at most reduce the level to which the price is
required to migrate by ~6%
36
NERSA’s FPP vs. MYPD4 – conclusions (2 of 2)
6. Whilst Eskom has not been perfect regarding fuel cost, operational cost, capital
expenditure or technical performance, objective analysis indicates that debt situation is
mainly (>80%) a function of having had to take responsibility for the build programme,
without the electricity price responding as was required. Even with a price path at the
lower boundary of NERSA’s FPP Eskom’s debt ratio would have been ~35% today
7. Phasing-out of overall price subsidy does not preclude subsidization of specific targeted
customer categories, through direct, targeted and transparent subsidies – i.e. fair revenue
for Eskom does not dictate the price to poor people in South Africa, or to certain
vulnerable industries.
These two propositions can thus be true at the same time:
(a) Eskom needs to receive enough revenues to be sustainable, thus able to meet all
debt commitments and cover all prudent and efficient costs;
(b) poor people and vulnerable industries could be protected (this could include
government-funded production or consumption subsidies – which is of course a
matter of government policy)
8. However the model of Eskom accumulating the underpricing effect on its balance
sheet as debt is unsustainable and has reached its limit. It is crucial for the sake of
Eskom, the ESI and South Africa that this be rectified urgently – it cannot be
delayed beyond MYPD4
37
Compounded annual growth rate (CAGR) for Primary energy from MYPD3 to MYPD4 – MYPD 4 Application
FY14
Act
FY15
Act
122,131
FY16
Act
FY17
Act
FY19
Proj
FY18
Act
FY21
App
FY22
App
83,426
69,811
85,069 84,723 87,185
102,541
114,781
132,667
FY20
App
37.20%
8.47%
6.26%
8.36%
Coal IPPs Other PE
CAGR
Co
al
IPP
sO
ther P
E
39
CAGR for Primary Energy from MYPD 3 to MYPD 4 – with changes made to production plan to reflect recent reality
56%
12%
5% 18%
10%
5%
9%
5%6%
15%
102,539
0%
FY2013/14
Actual
FY2017/18
Actual
3%10%
58%
24%
0%
11%
2%3%
4% 1%11%
59%
0%0%4%
FY2014/15
Actual
54%
10%
1%
83,426
0%
FY2015/16
Actual
3%
57%
26%
69,812
3%
2%
3%
FY2018/19
Projection
1%1%1%0%0%
55%
26%
7%
0%
2%
3%
FY2016/17
Actual
6% 0%
3%
57%
28%2%
3%
1% 1%
0% 3%
3% 0%
FY2020/21
Application
56%
31%
6%
87,184
59%
2%
3%
26%1%
8% 1%1%
FY2021/22
Application
10%
85,068 84,723
117,885123,982
133,148
FY2019/20
Application
8.41%
International purchasesCoal
IPPs Other PE
Environmental levy
Nuclear
OCGT
DMP
40
Primary energy CAGR increase is from 8.36 to 8.41
CAGR for employee benefits, maintenance and other expenses (excl other income & arrear debt)
24.9%
48.2%
25.0%
27.6%
FY18
Act
48.1%
FY14
Act
48.2%
26.1%
50,759
FY16
Act
27.6%
46.6%
29.9%
23.5%
FY17
Act
47,189
24.3%
49.0%
29.7%
FY19
Proj
47.8%
29.1%
FY20
App
23.1%
27.0%
47.0%
28.8%
24.2%
FY21
App
61,449
47.1%
22.7%
25.7%
30.2%
55,99455,354
47.4%
21.2%
FY22
App
51,276
FY15
Act
46,114
59,925 58,919
3.26%
2.14%
4.53%
+3.36%
Employee Benefits Maintenance Other (incl GTD, Cx, R&D, CSI & IDM)
Em
plo
yee
be
ne
fitsM
ain
ten
an
ce
Oth
er
41
CAGR for each component of Generation operating expenditure is below inflation
29.8%
FY20
App
FY15
Act
27.2%
29.7%
43.1%
FY16
Act
27.3%
25.8%
46.9%
33.6%
FY17
Act
31,305
32.9%
FY21
App
33.6%
FY18
Act
34.1%
FY19
Proj
30,737
34.8%
31.0%
26.0%
32.5%
36.5%
30.1%
31.5%
38.4%
30.3%
FY22
App
43.1%
27.3%
35.8%
30.9%
31.1%
FY14
Act
43.0%
25,737
35,688
33.9%
25,682
29,54328,585
33,34534,582
5.78%
5.01%
1.41%
Other (incl GTD, Cx, R&D, CSI & IDM)Employee Benefits Maintenance
CAGR
Em
plo
yee
be
ne
fitsM
ain
tenance
Oher
42
Average REIPPP prices per technology compared to Eskom Generation price
43
Eskom Generation Price is lower than all renewable technologies – even
with decreasing renewable prices
Impact of Eskom’s Revenue
Requirement
for MYPD 4
Application is based on recovering operating
costs and to achieve cash flow neutral position
by the 3rd year
With changes, Eskom is not requesting additional revenue
Allowable Revenue
(R'millions)ƒx
MYPD 4 application Changes Impact of changes
2019/20 2020/21 2021/22 2019/20 2020/21 2021/22 2019/20 2020/21 2021/22
Regulated Asset Base 1 268 310 1 336 120 1 401 506 - 15 310 - 12 984 - 10 764 1 253 000 1 323 136 1 390 742
WACC % x -1.32% -0.21% 1.45% -0.05% 0.11% 0.21% -1.36% -0.10% 1.66%
Returns + -16 687 -2 765 20 314 -394 1471 2741 -17 081 -1 294 23 055
Expenditure + 56 619 59 820 62 663 56 619 59 820 62 663
Primary energy + 73 386 75 876 79 561 1 758 1 175 267 75 144 77 051 79 828
IPPs (local) + 29 590 34 324 41 002 1 245 578 132 30 836 34 902 41 134
International purchases + 3 533 3 734 3 957 336 351 372 3 869 4 084 4 329
Depreciation + 64 651 72 919 75 649 - 2 710 - 3 322 - 3 222 61 942 69 597 72 427
IDM + 189 193 202 189 193 202
Research &
Development+ 176 187 198 176 187 198
Levies & Taxes + 8 272 8 198 8 147 - 236 - 253 - 290 8 036 7 945 7 857
RCA +
Subtotal 219 730 252 485 291 692 0 0 0 219 730 252 485 291 692
Corporate Social
Investment (CSI)- - 192 - 193 - 151 0 0 0 - 192 - 193 - 151
Total Allowable
Revenue219 537 252 292 291 542 0 0 0 219 537 252 292 291 542
Average standard tariff
price increase15.0% 15.0% 15.0% 2.1% 0.4% 0.5% 17.1% 15.4% 15.5%
45
Change in % increase due mainly to recovery of efficient costs over realistic
sales volume
0
10
20
30
40
50
60
70
80
90
100
0
50 000
100 000
150 000
200 000
250 000
300 000
350 000
400 000
450 000
500 0002
00
7/0
8
20
08
/09
20
09
/10
20
10
/11
20
11
/12
20
12
/13
20
13
/14
20
14
/15
20
15
/16
20
16
/17
20
17
/18
20
18
/19
Pri
ce
c/k
Wh
Ra
nd
mil
lio
ns
Price levels and Debt increasing
Total debt (LHS) c/kWh (RHS)
Debt continues to increase even though price levels are increased – indicating too low prices
The average price has
increased 5 fold whereas
debt has grown by nearly
10 fold over the same
window
46
Significant losses continue even with MYPD 4 application
Eskom Holding - MYPD4 Application (R’milliions)Projections Application Application Application
FY2019 FY2020 FY2021 FY2022
Revenue 190 862 220 359 253 095 292 401
Primary Energy -75 991 -87 050 -89 080 -92 014
IPP costs -26 549 -30 836 -34 902 -41 134
Other income 1 127 1 206 1 244 1 301
Employee benefit expense -27 140 -26 762 -27 684 -28 935
Arrear Debt -4 436 -4 442 -3 647 -3 903
Other expenses -28 213 -29 231 -31 234 -32 514
Profit before depreciation 29 658 43 244 67 791 95 203
Depreciation -22 095 -27 926 -26 906 -29 950
Profit after depreciation 7 563 15 318 40 886 65 252
Net FV gains/(loss) on embedded derivatives and
financial instruments-222 -1 649 -1 926 -3 086
Net Finance costs -27 467 -33 392 -42 594 -48 112
Net (loss)/profit (20 125) (19 723) (3 635) 14 054
47
Capitalised interest not disclosed in Income Statement. Historic depreciation
included per accounting standards.
Eskom’s status as a going concern – in jeopardy
• As disclosed in Eskom’s recent Annual Financial statements, the going concern
status is highlighted as a emphasis of matter.
• This indicates that level of financial distress that Eskom is experiencing through its
inability to meet its financial commitments
• Eskom cannot solve financial and operational sustainability challenges that it faces
alone - the shortfall in tariff cannot be solved through cost reductions alone, and
further indebtedness adds to the problem
• If Eskom’s Audited Financial Statements are qualified by the auditors on a basis that Eskom is not a going concern this will trigger the following events:
• Lenders will recall their loans as Eskom will be in breach of the loan covenants
• Government will be liable to pay for the loan agreements that are guaranteed causing a run on a third of Government debt
• Eskom will also have to prepare the Audited Financial Statements on a liquidation basis
48
Co
nseq
uen
ces
Cu
rren
t sta
tus
In conclusion, Eskom’s financial situation is unsustainable
• Restoring financial sustainability will require:
• Eskom to continue maintaining cost escalations within inflation range
• Price increases of about 2% p.a. are required to cover IPPs costs growth
• Year 1 reaches 6,4% (4.4% from RCA liquidation decision + IPPs 2%)
• Balance sheet support from the shareholder
• Government support will be required to address the arrear debt recovery from
Municipalities
• Customers require reliable supply of electricity
• Efficiency and prudency evaluation must be cognisant of the operational context and
circumstances
• Restoring operational performance comes at a cost which must be funded and
recovered through revenue requirements
• Debt providers, rating agencies, auditors and other stakeholders will await this crucial
decision
• Ultimately a part of the solution will impact either the electricity consumer or the
taxpayer
49