multilateral well completions and interventions

93
Multilateral Well Completions and Interventions Why and How 8/25/2015 1 George E. King Engineering GEKEngineering.com

Upload: kevin-steinbach

Post on 14-Dec-2015

91 views

Category:

Documents


12 download

DESCRIPTION

N/A

TRANSCRIPT

Page 1: Multilateral Well Completions and Interventions

Multilateral Well Completions and Interventions

Why and How

8/25/2015 1 George E. King Engineering

GEKEngineering.com

Page 2: Multilateral Well Completions and Interventions

Application Objective

1. Multiple targets Increase reserves by combining targets that

separate reservoirs are separately uneconomic

isolated fault blocks

good quality sand bodies

2. Limited Size Targets Achieve high productivity in a confined

oil lenses space which would limit horizontal

bocks limited by conductive faults well length

3. Drainage Patterns Improve areal sweep

more linear flow

flexibility to control inflow location

modify over time by sidetracking

4. Completion by layer Improve vertical sweep

different prod. via layers

5. Improve Existing Wells Increase productivity and reserves

multilateral sidetracking

6. Handle Reservoir Geology Increase productivity

penetrate natural fractures

penetrate shale barriers

7. Limit water/gas production Reduce gas and water handling costs

reduce drawdown, less coning and loss of hydrocarbon production caused

distancing from faults by water or gas

8. Injection Increase injectivity.

new wells Improve areal and vertical sweep.

sidetracks of existing wells Reference: SPE 35711, Salas, et. al.

Some Potential Applications For Multi-lateral Wells

8/25/2015 2 George E. King Engineering

GEKEngineering.com

Page 3: Multilateral Well Completions and Interventions

Best Candidates

• Compartments

– vertical boundaries

– lenses

– fault blocks

• Launching points for fracs

• Launching points for more laterals??

8/25/2015 3 George E. King Engineering

GEKEngineering.com

Page 4: Multilateral Well Completions and Interventions

Multi-Laterals at Primrose

Stacked laterals with uncemented slotted liner in upper layer

~ 2000 ft

50 ft

8/25/2015 4 George E. King Engineering

GEKEngineering.com

Page 5: Multilateral Well Completions and Interventions

Multilaterals in Sharjah

Open hole laterals in the same layer

~ 4000 ft

~ 3000 ft

8/25/2015 5 George E. King Engineering

GEKEngineering.com

Page 6: Multilateral Well Completions and Interventions

Swell Packers

Across Shales

Quad-Lateral

(TAML-Level 4)

Producer/Injector

9200’ TVD

Thru-Tubing Retrievable Electric

Submersible

Pump (ESP)

Power Transfer Collar

ESP Feed through

Hydraulic Set Packer

Flow Meter

ESP Feed through

Hydraulic Set Packer

Flow Meter

Flow Meter

Flow Meter

ESP Feed through

Hydraulic Set Packer

ESP Feed through

Hydraulic Set Packer

SC-SSSV

ESP Feed through

Hydraulic Set Packer

5 ½” Tubing

to Surface

5 ½” Tubing

9 5/8” x TBD

IsoRite (LRS)

5 ½” Tubing

5 ½” Tubing

ESP Wire

9 5/8” x TBD

IsoRite (LRS)

9 5/8” x TBD

IsoRite (LRS)

ESP Wire

5 ½” Tubing

Mechanical Advantages • Thru-tubing retrievable pump and motor

• Access to all laterals

• Motherbore flow control

• Downhole/real time injection splits

• Potential lateral flow control*

• Access to log laterals and remedial work

Technology Developments • Power Transfer Method to ESP

(Inductance – Coil, Sealed “Wet Connect”)

• 7-Line Feed through Packer

(9 5/8” x 5 1/2” x 4.892”)

• Orienting and Locking Method for IsoRite LRS

(Lateral Re-Entry System)

Reservoir Benefits • Hot water for flooding cold, viscous

reservoir (200+ degrees F)

• Local source of water

• Potential improved horizontal sweep

TPI Isolation

Sleeve

TEW

Neckless

Swell Packers

Across Shales

Cemented Junction

Freeze Protect

(Crude or Methanol Water)

Cemented Junction

Cemented Junction

Shale

Shale

Injection Zone Injection Zone

High Perm

Shut Off Injection

(Straddle)

Injection Zone

Injection Zone

Injection Zone

Shale

Shale

Injection Zone

Injection Zone

Injection Zone

Shale

Shale

Top of Sad

Water Source

Swell

Packer

*Potential Lateral Flow Control

Straddle to Seal Off

or Reduce Injection

No Water Injection (Straddle)

Shale

Shale

Injection

Zone

Injection

Zone

Prepared By:

Jerry Brady…………. BPX Alaska

Joe Hess……………. Halliburton

Donn Schmohr…….. BPX Alaska

Mik Triolo…………… BPX Alaska

Scott Mattison……… BPX Alaska

Laura Larson………. BPX Alaska

9-5/8” Casing

12-1/4” Hole

10-3/4” Flush Joint

Casing

12-1/4” Hole

10-3/4” X 9-5/8”Casing Alignment

Sub 7” X 5-1/2” B X 5-1/2”P Keyed

Tubing Alignment Sub

8/25/2015 6 George E. King Engineering

GEKEngineering.com

Page 7: Multilateral Well Completions and Interventions

Amoco Norway Downhole Splitter

8/25/2015 7 George E. King Engineering

GEKEngineering.com

Page 8: Multilateral Well Completions and Interventions

Lateral Technology Levels • Level 1 - Open/Unsupported Junction

• Level 2 - Mother Bore Cased & Cemented, Lateral Open

• Level 3 - Mother Bore Cased & Cemented, Lateral Cased but not Cemented

• Level 4 - Mother Bore & Lateral Cased & Cemented

• Level 5 - Pressure Integrity at Junction (not cement)

• Level 6 - Pressure Integrity at Junction achieved with casing

• Level 6S - Downhole Splitter

8/25/2015 8 George E. King Engineering

GEKEngineering.com

Page 9: Multilateral Well Completions and Interventions

L e v e l 1 , 2 L e v e l 1 , 2 L e v e l 1 , 2 L e v e l 3 L e v e l 3 L e v e l 3

M u lti-la te ra l o p e n h o le o p e n h o le o p e n h o le l in e r l in e r l in e r

O p tio n s o p p o se d sta c k e d fo rk e d o p p o se d sta c k e d fo rk e d

H y d ra u l ic se a l a t ju n c tio n ? n o n e n o n e n o n e n o n e n o n e n o n e

Iso la tio n a lo n g w e l lb o re ? l im i te d l im i te d d i ffic u l t n o n o n o

P e rfo ra tin g p o ssib le ? d i ffic u l t v . d i ffic u l t y e s l im i te d v . d i ffic u l t l im i te d

L in e r/sc re e n in se rtio n p o ssib le ? y e s v . d i ffic u l t y e s y e s y e s y e s

L a rg e d ia m e te r la te ra l re c o m p .? y e s y e s y e s n o n o n o

P o ssib le u se in o ld w e l l? y e s d i ffic u l t y e s y e s y e s y e s

U se fu l in h ig h p re ssu re w e l l? n o n o n o n o n o n o

P o te n tia l in u n sta b le fo rm .? l im i te d n o l im i te d l im i te d l im i te d l im i te d

L a te r w a te r c o n tro l p o ssib le ? d i ffic u l t v . d i ffic u l t l im i te d n o n o n o

G e n e ra l stim u la tio n p o ssib le ? y e s y e s y e s y e s y e s y e s

M u l tip le stim u la tio n p o ssib le ? d i ffic u l t n o l im i te d n o n o n o

P ro d u c tio n c o n tro l p o te n tia l? d i ffic u l t n o l im i te d n o n o n o

En try w i th w ire l in e ? d i ffic u l t n o l im i te d l im i te d n o y e s

En try w i th C T ? y e s d i ffic u l t y e s y e s d i ffic u l t y e s

U p /d o w n d ip p o te n tia l? y e s l im i te d y e s y e s l im i te d y e s

R isk , n o t a c h ie v in g c o m p le tio n ? lo w m o d e ra te lo w m o d e ra te h ig h m o d e ra te

R isk , o f lo o sin g e n ti re w e l l? m o d m o d e ra te lo w lo w m o d e ra te lo w

C o st o f c o m p le tio n ? lo w m o d e ra te lo w m o d e ra te h ig h m o d e ra te

N u m b e rs D o n e m a n y m a n y m a n y m a n y m a n y m a n y

8/25/2015 9 George E. King Engineering

GEKEngineering.com

Page 10: Multilateral Well Completions and Interventions

Level 1

• Consolidated formation required

• Lateral access limited, but not impossible

• Production control limited (better options than with a slotted or perfed liner)

8/25/2015 10 George E. King Engineering

GEKEngineering.com

Page 11: Multilateral Well Completions and Interventions

10

101896

© 1996 Baker Hughes Incorporated

All rights reserved.

Level 1 - Open Hole Trunk

Open Hole Laterals

l Consolidated formations

l Lateral access limited

l Production control limited

8/25/2015 11 George E. King Engineering

GEKEngineering.com

Page 12: Multilateral Well Completions and Interventions

Level 2

• consolidated formations best use

• can straddle for production control

• full opening main bore

8/25/2015 12 George E. King Engineering

GEKEngineering.com

Page 13: Multilateral Well Completions and Interventions

11

101896

© 1996 Baker Hughes Incorporated

All rights reserved.

Level 2 - Cased Hole Trunk

Open Hole Junction

l Consolidated formations

l Full opening main bore access

l Lateral re-entry potential

8/25/2015 13 George E. King Engineering

GEKEngineering.com

Page 14: Multilateral Well Completions and Interventions

8/25/2015 14 George E. King Engineering

GEKEngineering.com

Page 15: Multilateral Well Completions and Interventions

Level 3

• consolidated formation preferred, but completions made in unconsolidated formations

• junction is the weak point of completion

(no integrity or control)

• full bore access to main and lateral

8/25/2015 15 George E. King Engineering

GEKEngineering.com

Page 16: Multilateral Well Completions and Interventions

12

101896

© 1996 Baker Hughes Incorporated

All rights reserved.

Level 3 - Cased Hole Trunk

Mechanically Supported Junction

l Consolidated formations

l Noncemented junction

l No hydraulic integrity at the

junction

l Mainbore and lateral re-entry

access

8/25/2015 16 George E. King Engineering

GEKEngineering.com

Page 17: Multilateral Well Completions and Interventions

Level 4

• Consolidated formation

• mechanical supported junction

• no pressure isolation at junction - (junction is normally cemented)

• fullbore access to main, reduced lateral size (but still has full bore access).

8/25/2015 17 George E. King Engineering

GEKEngineering.com

Page 18: Multilateral Well Completions and Interventions

13

101896

© 1996 Baker Hughes Incorporated

All rights reserved.

Level 4 - Cased Hole Trunk

Cased and Cemented Lateral

l Consolidated formations

l Mechanically supported

junction

l No hydraulic integrity at

the junction

l Full bore access to main

bore AND lateral

8/25/2015 18 George E. King Engineering

GEKEngineering.com

Page 19: Multilateral Well Completions and Interventions

Level 5

• Consolidated or unconsolidated formation

• mechanical supported junction

• pressure isolation at junction is provided by mechanical seal (not cement)

• access preserved to main and lateral for re-entry, but may not be full-bore

8/25/2015 19 George E. King Engineering

GEKEngineering.com

Page 20: Multilateral Well Completions and Interventions

14

101896

© 1996 Baker Hughes Incorporated

All rights reserved.

Level 5 - Cased Hole Trunk

Hydraulically Isolated Junction

l Consolidated or unconsolidated formations

l Cement does not qualify as hydraulic isolation

l Mainbore and lateral re-entry access8/25/2015 20

George E. King Engineering GEKEngineering.com

Page 21: Multilateral Well Completions and Interventions

Level 6

• Consolidated or unconsolidated formation

• mechanical supported junction

• pressure isolation at junction is provided by mechanical separation/isolation

• fullbore access to main and lateral (may be two equal laterals in special case of level 6s.

8/25/2015 21 George E. King Engineering

GEKEngineering.com

Page 22: Multilateral Well Completions and Interventions

8/25/2015 22 George E. King Engineering

GEKEngineering.com

Page 23: Multilateral Well Completions and Interventions

8/25/2015 23 George E. King Engineering

GEKEngineering.com

Page 24: Multilateral Well Completions and Interventions

Need?

• Recognize compartmentalization

• Boundaries

– pinchouts

– faults

– folds

– inclusions

– selective chemical modification

8/25/2015 24 George E. King Engineering

GEKEngineering.com

Page 25: Multilateral Well Completions and Interventions

8/25/2015 25 George E. King Engineering

GEKEngineering.com

Page 26: Multilateral Well Completions and Interventions

8/25/2015 26 George E. King Engineering

GEKEngineering.com

Page 27: Multilateral Well Completions and Interventions

Oil Fingerprinting

• Every source of hydrocarbon has slightly different characteristics

• Marker materials - suggestions – carbon number plot shape

– carbon number anomalies (wax ends)

– asphaltene content, resins, etc.

• Can separate producing intervals be identified? Already been done!

8/25/2015 27 George E. King Engineering

GEKEngineering.com

Page 28: Multilateral Well Completions and Interventions

When is a compartment important?

• if it has a significant effect on recovery, then it is important.

Modeling is suggested to get to recovery numbers and decisions. You will have to make some assumptions about the connection - geologic info helps!

8/25/2015 28 George E. King Engineering

GEKEngineering.com

Page 29: Multilateral Well Completions and Interventions

1991 OB Pilot

1992 UB Pilot

Phase 1-5

Phase 6-7 Phase 10 Quads

Phase 8 Phase 10 Duals Phase 9

1991 OB Pilot Single Laterals

1992 UB Pilot Single Laterals

Phases 1-5 Single Laterals

Phases 6-7 Dual Laterals

Phase 8 Re-Entries

Phase 9 Quad Laterals

Phase 10 Dual Laterals & Quad

Laterals

$3,500

$3,000

$2,500

$2,000

$1,500

$1,000

$500

$0

0 500 1000 1500 2000 2500 3000 3500 4000

Co

st

per

Hz. M

ete

r

Fig. 7 - Drilling, Completion, Artificial Lift & Tie-in Costs 71314001.ppt

Average Horizontal Length (meters)

8/25/2015 29 George E. King Engineering

GEKEngineering.com

Page 30: Multilateral Well Completions and Interventions

FLUID

OIL

Quad Laterals

(7 wells)

Dual Laterals

(25 wells)

Single Laterals

(66 wells)

0 500 1000 1500 2000 2500 3000 3500 4000

Average Horizontal Length (meters)

Fig. 8 - Horizontal Well Fluid and Oil Rate Multiples

18

16

14

12

10

8

6

4

2

0

Hz. R

ate

/Ve

rt. O

ffs

et

Ra

te

71314002.ppt 8/25/2015 30 George E. King Engineering

GEKEngineering.com

Page 31: Multilateral Well Completions and Interventions

0 10 20 30 40 50 60 70 80 90 100

1000

100

10

1

0

Oil

Ra

te (

CD

) (m

3/d

)

Cum Oil Prod (E3m3)

Fig. 9 - Production Comparison: Single Lateral and Vertical Offset

1992 SINGLE LATERAL

191/12-18-006-13W2

1991 VERTICAL INFILL

141/14-18-006-13W2

71314003.ppt 8/25/2015 31 George E. King Engineering

GEKEngineering.com

Page 32: Multilateral Well Completions and Interventions

100

50

10

5

0.5

0.1

1

Oil

Ra

te (

CD

) (m

3/d

)

0 10 20 30 40 50 60 70 80 90 100

Cum Oil Prod (E3m3)

Fig. 12 - Production Comparison: Dual Lateral and Vertical Offsets 71314004.ppt

1995 DUAL LATERAL

191/08-28-005-13W2

1987 VERTICAL INFILL

121/14-27-005-13W2

1986 VERTICAL INFILL

141/08-28-005-13W2

8/25/2015 32 George E. King Engineering

GEKEngineering.com

Page 33: Multilateral Well Completions and Interventions

1996 QUAD LATERAL 191/14/005/13W2

1995 DUAL LATERAL 191/01-35-005-13W2

1993 SINGLE LATERAL 191/08-28-005-13W2

1986 VERTICAL INFILL 121/08-35-005-13W2

86 87 88 89 90 91 92 93 94 95 96

1000

50

10

1

0.1

Oil

Rate

(C

D)

(m3/d

)

Cum Oil Prod (E3m3)

Fig. 13a - Production Comparison: Quad, Dual, Single Laterals and Vertical Offset

71314005.ppt

5

0.5

8/25/2015 33 George E. King Engineering

GEKEngineering.com

Page 34: Multilateral Well Completions and Interventions

1996 QUAD LATERAL 191/14/005/13W2

1995 DUAL LATERAL 191/01-35-005-13W2

1993 SINGLE LATERAL 191/08-28-005-13W2

1986 VERTICAL INFILL 121/08-35-005-13W2

1000

100

10

0.1

1

Oil

Ra

te (

CD

) (m

3/d

)

1 10 20 30 40

Cum Oil Prod (E3m3)

Fig. 13b - Production Comparison: Quad, Dual, Single Laterals and Vertical Offset

71314006.ppt 8/25/2015 34 George E. King Engineering

GEKEngineering.com

Page 35: Multilateral Well Completions and Interventions

Alternatives to Multi-laterals

• fracturing

• multiple completions

• multiple wells

8/25/2015 35 George E. King Engineering

GEKEngineering.com

Page 36: Multilateral Well Completions and Interventions

Response to adding a lateral

• Depends on well placement, barriers, reservoirs, fluids and homogeneity within the compartment.

• Always question the model results. – What is the grid of the model

– what are the assumptions

– Examples………..

8/25/2015 36 George E. King Engineering

GEKEngineering.com

Page 37: Multilateral Well Completions and Interventions

An idealized reservoir

study…

Compare it with field

results.

8/25/2015 37 George E. King Engineering

GEKEngineering.com

Page 38: Multilateral Well Completions and Interventions

case 1

case 2

case 3

case 4

case 5

case 6

case 7

case 8

case 9

100 ft

200 ft

250 ft

333 ft

500 ft

500 ft

500 ft

1000 ft

Cases 2 - 9 add an extra 1000 ft to the original 1000 ft wellbore length

SPE 3711: Salas, Clifford, Jenkins 8/25/2015 38

George E. King Engineering GEKEngineering.com

Page 39: Multilateral Well Completions and Interventions

8/25/2015 39 George E. King Engineering

GEKEngineering.com

Page 40: Multilateral Well Completions and Interventions

8/25/2015 40 George E. King Engineering

GEKEngineering.com

Page 41: Multilateral Well Completions and Interventions

8/25/2015 41 George E. King Engineering

GEKEngineering.com

Page 42: Multilateral Well Completions and Interventions

8/25/2015 42 George E. King Engineering

GEKEngineering.com

Page 43: Multilateral Well Completions and Interventions

Multi-laterals

• 2 to 5 legs or laterals

• legs – opposed

– stacked

– forked

– multi-planar (can be one leg)

• A “lateral” does not have to be horizontal - many, probably most aren’t.

8/25/2015 43 George E. King Engineering

GEKEngineering.com

Page 44: Multilateral Well Completions and Interventions

Considerations

• how many laterals

• need for re-entry – diagnostics

– mechanical access

– chemical access

• need for pressure seal

• wellbore stability

• lengths

8/25/2015 44 George E. King Engineering

GEKEngineering.com

Page 45: Multilateral Well Completions and Interventions

US Multi-lateral Use (1995)

• Oil 72%

• Gas 25%

• Water Flood 2%

• Gas Storage 1%

• Old numbers! - floods and thermal application increasingly use multi-laterals

8/25/2015 45 George E. King Engineering

GEKEngineering.com

Page 46: Multilateral Well Completions and Interventions

US Multi-lateral (1995)

• 2 legs - 45%

• 3 legs - 43%

• 4 legs - 9%

• 5 legs - 5%

• At this point in the development, most multi-laterals had been drilled in the Austin chalk and Baaken shale.

8/25/2015 46 George E. King Engineering

GEKEngineering.com

Page 47: Multilateral Well Completions and Interventions

Junction Design

• 1. Formation Character

• 2. Differential Pressure at Junction

• 3. Production Control Requirements

• 4. Well Path Planning

8/25/2015 47 George E. King Engineering

GEKEngineering.com

Page 48: Multilateral Well Completions and Interventions

Formation Character

• Strength - sand or shale, reactive, phase sensitive.

• Stability - both now and later

• If the rock in the junction has a sonic travel time of less than 120 u, expect junction failure on drawdown - this is an estimate from underbalanced perforating work.

8/25/2015 48 George E. King Engineering

GEKEngineering.com

Page 49: Multilateral Well Completions and Interventions

Differential Pressure

• Amount of differential - this is a minor point if the load is applied slowly, until water influx gets there.

• Shock / surge loads - this is very significant

– control?

• isolate the junction

• eliminate the surge (controlled startups at every shut down).

8/25/2015 49 George E. King Engineering

GEKEngineering.com

Page 50: Multilateral Well Completions and Interventions

Production Control

• Surge volumes, frequency, and rate of application of surge.

• downhole or surface equip. slug sensitive? Emulsions, upsets, etc. ?

• gas / water influx control needed?

• re-entry likelihood?

• abandonment concerns?

8/25/2015 50 George E. King Engineering

GEKEngineering.com

Page 51: Multilateral Well Completions and Interventions

Well Path Planning

• angle to zone

• depth

• potential for smooth turnout

• influence of other junctions

8/25/2015 51 George E. King Engineering

GEKEngineering.com

Page 52: Multilateral Well Completions and Interventions

SPE 35712 - M-L Catagories

• Draining a single layer in which areal permeability anisotrophy is critical (affects production with conventional methods).

• Draining of several stacked layers which may or may not communicate.

• Draining of several compartments which may or may not communicate.

8/25/2015 52 George E. King Engineering

GEKEngineering.com

Page 53: Multilateral Well Completions and Interventions

SPE 3712 - ML choices

• Catagories – 1. Draining a single layer in which areal permeability anisotrophy is critical

(affects production with conventional methods).

– 2. Draining of several stacked layers which may or may not communicate.

– 3. Draining of several compartments which may or may not communicate.

• Choices – option 1 favors horizontal mother bore

– option 2 favors vertical motherbore

– option 3 favor horizontal mother bore, depending on compartment location.

8/25/2015 53 George E. King Engineering

GEKEngineering.com

Page 54: Multilateral Well Completions and Interventions

SPE 35712 - ML - flow management

• Will production be commingled?

• Need of re-entry to branches.

• Downhole control needs

8/25/2015 54 George E. King Engineering

GEKEngineering.com

Page 55: Multilateral Well Completions and Interventions

ML - Advantages

• higher PI

• control for gas/water coning

• increased reservoir contact

• better chance of intersecting fractures

• better sweep potential (check alignment)

• specific EOR applications

8/25/2015 55 George E. King Engineering

GEKEngineering.com

Page 56: Multilateral Well Completions and Interventions

ML- Disadvantages

• higher initial costs

• higher risks

• candidate selection difficulties

• sensitivity to heterogenities (can be advantage)

• poor vertical perm in horizontals

• infant completion/workover/production technology

• cross flow

8/25/2015 56 George E. King Engineering

GEKEngineering.com

Page 57: Multilateral Well Completions and Interventions

Making The Opening

• Section Mill

• Whipstock / Window Mills

• Premilled Window

• Cavity Shots

• See the section on window cutting

8/25/2015 57 George E. King Engineering

GEKEngineering.com

Page 58: Multilateral Well Completions and Interventions

ML Productivity - the right choice?

• Options

8/25/2015 58 George E. King Engineering

GEKEngineering.com

Page 59: Multilateral Well Completions and Interventions

Stacked Multi-lateral

61934001 8/25/2015 59

George E. King Engineering GEKEngineering.com

Page 60: Multilateral Well Completions and Interventions

Opposed

61934002 8/25/2015 60

George E. King Engineering GEKEngineering.com

Page 61: Multilateral Well Completions and Interventions

Stacked and Opposed

61934003 8/25/2015 61

George E. King Engineering GEKEngineering.com

Page 62: Multilateral Well Completions and Interventions

Forked

61934004 8/25/2015 62

George E. King Engineering GEKEngineering.com

Page 63: Multilateral Well Completions and Interventions

Multi-planer

61934005 8/25/2015 63

George E. King Engineering GEKEngineering.com

Page 64: Multilateral Well Completions and Interventions

Branched

61934006 8/25/2015 64

George E. King Engineering GEKEngineering.com

Page 65: Multilateral Well Completions and Interventions

Dual Well Using "Relief Well" Intersection Technology from

Recompletion or New Well

50423012 8/25/2015 65

George E. King Engineering GEKEngineering.com

Page 66: Multilateral Well Completions and Interventions

Opposing Laterals

• Reasons:

– Cut friction pressure losses, in wells producing at high rates.

– Position well bores to flank areas

8/25/2015 66 George E. King Engineering

GEKEngineering.com

Page 67: Multilateral Well Completions and Interventions

Opposing Laterals

50423014 8/25/2015 67

George E. King Engineering GEKEngineering.com

Page 68: Multilateral Well Completions and Interventions

Potential Updip Completion

• Uses:

– chasing attic oil

– moving a contact away from rising water

8/25/2015 68 George E. King Engineering

GEKEngineering.com

Page 69: Multilateral Well Completions and Interventions

50423015 8/25/2015 69

George E. King Engineering GEKEngineering.com

Page 70: Multilateral Well Completions and Interventions

Isolation Potential

• Levels

– Open Hole

– Selective Isolation

– Selective Re-entry

– Full Time Isolation

8/25/2015 70 George E. King Engineering

GEKEngineering.com

Page 71: Multilateral Well Completions and Interventions

Downhole Test of Multilateral Reentry Completion: Schlumberger-Anadrill’s RapidAccess System

Conducted at Amoco’s

Drilling Technology Test Facility

Catoosa, Oklahoma

November 1997

8/25/2015 71 George E. King Engineering

GEKEngineering.com

Page 72: Multilateral Well Completions and Interventions

Test steps successfully completed

• cased a vertical well with orienting sub as part of the casing sting

• milled a window; one trip

• used gel to control debris

• drilled a lateral

• cemented a drop-off liner in the lateral

• cleaned out and retrieved whipstock from main wellbore

8/25/2015 72 George E. King Engineering

GEKEngineering.com

Page 73: Multilateral Well Completions and Interventions

RapidAccess System Schlumberger-Anadrill

Lateral completed open hole or with liner

Orienting sub (keyway)

Up to 3 laterals can be drilled, each with different keyways, which allows selective reentry for stimulations or other workovers

8/25/2015 73 George E. King Engineering

GEKEngineering.com

Page 74: Multilateral Well Completions and Interventions

Control within the lateral

• Profiles and sleeves

• ECPs at strategic positions

• Hydraulic flow control

• Screens and liners

• Most operations depend on ability to enter the lateral.

8/25/2015 74 George E. King Engineering

GEKEngineering.com

Page 75: Multilateral Well Completions and Interventions

8/25/2015 75 George E. King Engineering

GEKEngineering.com

Page 76: Multilateral Well Completions and Interventions

Lateral placement?

• location of contacts

• thickness of zones

• relationship to kickoff point

– departure angle

– dogleg angle

– re-entry needs

8/25/2015 76 George E. King Engineering

GEKEngineering.com

Page 77: Multilateral Well Completions and Interventions

8/25/2015 77 George E. King Engineering

GEKEngineering.com

Page 78: Multilateral Well Completions and Interventions

8/25/2015 78 George E. King Engineering

GEKEngineering.com

Page 79: Multilateral Well Completions and Interventions

Well path based on geologic

information.

8/25/2015 79 George E. King Engineering

GEKEngineering.com

Page 80: Multilateral Well Completions and Interventions

Completion ability an issue too

• Must be able to get the completion into place

• Can it be kept on line and producing steadily?

• re-entry?

• isolation?

• Plug and Abandonment?

8/25/2015 80 George E. King Engineering

GEKEngineering.com

Page 81: Multilateral Well Completions and Interventions

8/25/2015 81 George E. King Engineering

GEKEngineering.com

Page 82: Multilateral Well Completions and Interventions

One of many proposed lateral entry control systems – all are expensive and few are well proven.

8/25/2015 82 George E. King Engineering

GEKEngineering.com

Page 83: Multilateral Well Completions and Interventions

There are many sketches of lateral exit windows; and most have window debris that make exit and return very difficult.

The typical window is from 10’ to 20 ft in length (casing length opening).

8/25/2015 83 George E. King Engineering

GEKEngineering.com

Page 84: Multilateral Well Completions and Interventions

Lateral Re-Entry Needs

• 1. Logging the lateral

• 2. Lateral shutoff

• 3. Stimulation

• 4. Cleanout

8/25/2015 84 George E. King Engineering

GEKEngineering.com

Page 85: Multilateral Well Completions and Interventions

Alaska Multi-lateral Well Interventions

Taylor West

PE

GPB Orion / Polaris

Well Management Masterclass, Oct 30-Nov 3, 2006 8/25/2015 85

George E. King Engineering GEKEngineering.com

Page 86: Multilateral Well Completions and Interventions

VO Producer Design • Production Interval:

– 6-¾” production holes with 4-½” slotted liners or 4”x 4.8” Screens

• Completion Design: – 4-½” tubing with GL artificial lift

and Jet Pump back-up via sliding sleeve

• Functionalities: – Monobore design

– Mechanical integrity at window

– Thru-tubing access to all laterals

– Selective lateral isolation

– Selective lateral access using diverter or MLT tool

Lateral Entry Module (LEM)

LEM

Diverter and Isolation Sleeve

Lateral DiverterLateral

Isolation Sleeve

Well Management Masterclass, Oct 30-Nov 3, 2006 8/25/2015 86

George E. King Engineering GEKEngineering.com

Page 87: Multilateral Well Completions and Interventions

ML Interventions Challenges & Checklist

• GPB uniquely positioned to lead effort due to access

• Current design ~ 3 yrs old

• Limited experience – mixed success

• Risk to high value wells discourages “testing”

• Need to test Baker component functionalities

• Need to test access / logging technologies

• Need to develop new techniques & tools

• Need to build confidence with town & wells group

Well Management Masterclass, Oct 30-Nov 3, 2006

Preparations

– Intensive focus from Wells Group CTU PEs

–iCoil installed in 1-3/4” service coil w/ straightener

–Bench tested all BHAs through model junction

–Incorporated learnings from Milne & West Sak interventions

Activity

Kit Functionality:

Diverter Set

Diverter Pull

Isolation Sleeve Set

Isolation Sleeve confirm full shut-off

Coil transit / work through sleeve

Sleeve Pull

Motherbore memory logging

Motherbore FCO /Stim

Use Mainbore centralizer (coil / PL tools)

Open Mainbore Shear Disk

Able to reach TD in Laterals

Mainbore IBP located on junction

Work through Diverter:

1-3/4" Coil entry through Diverter

Confirm CoilCade modeling for Depth reached

I-Coil DSP (real-time CCL/Temp/Press)

I-Coil DTS - flowing & pump-in

Downhole fluid sampling

memory tools - surveillance & diagnostics

FCO w/ carrying fluids

Simple Stimulation (Diesel/Xylene)

E-line Tractor Production logging, WFL

Diagnose / Identify water entry along a lateral

Shut-off water entry along a lateral

Discovery Tool Lateral Access w/o diverter:

Shop Testing through junction

Jet Blaster for slot cleaning & FCO

FCO w/ carrying fluids

8/25/2015 87 George E. King Engineering

GEKEngineering.com

Page 88: Multilateral Well Completions and Interventions

CTU ML Interventions Key learnings

Significant FEL - early Wells Group engagement gave ownership

Drift / wash runs ensure success in running full-diameter components

Not easy to stay in the mother bore

Not a smooth design – lips, ledges (mostly at windows)

No significant fill evident in laterals

New surprises on previous givens – PPROFs – slick is best!

Pipe straightener – limited additional depth reached (+300’)

Metal-to-metal lubricants extended coil reach 3000’+

ML checklist items

Proved worth of iCoil – knowing where you are (ccl), pressure, temp

Diverter set / transit w/ tools / retrieved

Sleeve set / transit / confirmed sealing / pull

Lateral entry / Sample / FCO / Stim

MLT “Discovery Tool” lateral entry – 1st successful run in this completion design

Mainbore and lateral logging – ID water and gas entries

Well Management Masterclass, Oct 30-Nov 3, 2006 8/25/2015 88

George E. King Engineering GEKEngineering.com

Page 89: Multilateral Well Completions and Interventions

Well Management Masterclass, Oct 30-Nov 3, 2006

Technologies

8/25/2015 89 George E. King Engineering

GEKEngineering.com

Page 90: Multilateral Well Completions and Interventions

Well Management Masterclass, Oct 30-Nov 3, 2006

Learnings

8/25/2015 90 George E. King Engineering

GEKEngineering.com

Page 91: Multilateral Well Completions and Interventions

Problems in Re-Entry

1. EOT location relative to junction 2. Making the corner 3. Stiffness of tube 4. Departure angle 5. Junction shape

8/25/2015 91 George E. King Engineering

GEKEngineering.com

Page 92: Multilateral Well Completions and Interventions

Solutions in Re-Entry

1. “poke and hope” 2. bent face 3. bent face and motor 4. “gate” products a. whipstocks b. selective ramps / lugs or profiles

8/25/2015 92 George E. King Engineering

GEKEngineering.com

Page 93: Multilateral Well Completions and Interventions

Can you be sure where you are?

1. Pipe depth measurement 2. MWD tools 3. Conformance to model prediction 4. End of the lateral measurement 5. Others?

?

8/25/2015 93 George E. King Engineering

GEKEngineering.com