mwea 89th annual conferencesiphons $2,100 $2,000 $4,100 culverts (stream crossings) $9,700 $86,000...

26
MWEA 89 th Annual Conference Boyne Mountain Resort, Boyne Falls, MI June 24, 2014 Dan Christian, PE, D.WRE Tetra Tech 1

Upload: others

Post on 21-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

MWEA 89th Annual Conference Boyne Mountain Resort, Boyne Falls, MI

June 24, 2014 Dan Christian, PE, D.WRE Tetra Tech

1

Page 2: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Goal ◦ Paradigm shift on stormwater management ◦ Proactive planning ◦ Improved technical way of doing business

Solid Foundation ◦ Establishing priorities ◦ Defining critical system components

Project Elements ◦ Input from stakeholders and the public ◦ Asset evaluation ◦ Capital improvements ◦ Master plan update ◦ Technical reference manual update

2

Page 3: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

What are the assets? (Inventory)

What are the assets worth? (Valuation)

Where are the assets located? (Geographic Information System)

How is the system operated? (Level of Service)

What is the condition? (Probability and Consequence of Failure)

What is needed to be done? (Construct, Maintain or Replace)

How much will it cost? (Financial Plan)

3

Page 4: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Inventory and evaluation of assets

Improved knowledge of timing and magnitude of future investments

Understanding of service level options and costs

Improved coordination with other utilities

4

Maintain a desired level of service at the lowest life cycle cost

Page 5: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Pipes (e.g. sewers and CB laterals)

Structures ◦ Inlets (e.g. catch basins)

◦ Outlets

◦ Junction chambers (e.g. manholes)

Culverts and bridges

Open channels and roadside ditches

Storage basins

Pump stations

Green infrastructure practices

5

Page 6: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Inventory and component location

Evaluation and rating

Determination of unit price replacement and repair costs

Complete valuation of the system

Defining range of levels of service and strategies for asset renewal

Summary of efforts necessary to meet the desired level of service

6

Page 7: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Probability of Failure Consequence of Failure

Probability of Failure – the likelihood that it will fail

Major Elements ◦ Percent consumed (actual age

divided by the estimated effective life)

◦ Maintenance condition

◦ Structural condition

Consequence of Failure – the financial or health and human safety cost resulting from asset failure

Major Elements ◦ Size, depth and special devices

(e.g. backflow prevention devices)

◦ Proximity to floodplains, environmental hazards, buildings, and roadways

7

Business Risk Exposure (BRE) = Probability of Failure (PoF) x Consequence of Failure (CoF) x Redundance Factor (R)

Page 8: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Inventory basin information ◦ Asset type, physical characteristics (size, material, depth,

installed date, proximity information) – GIS

◦ Incomplete information spot checked and typically assumed from adjacent resources

Condition assessment ◦ Sample assessment information by asset type

◦ Continuous improvement process established

8

Page 9: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Louis Street NW

72-inch sewer

Box

Brick

Built in 1922

9

Page 10: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

10

COF Factor Rating Description Value Weight Weighted Value

Depth of Pipe

1 = depth <= 8 feet 3 = 8 < depth <= 15 feet

10 = depth > 15 feet 3.0 1.0 * 3.0 = 3.00

Pipe Size

2 = size <=12 inches 10 = 12 < size <= 24 inches 25 = 24 < size <= 42 inches 35 = 42 < size <= 72 inches

50 = size > 72 inches

3.0 0.7 * 3.0 = 2.10

Proximity to

Floodplain

0 = Not in a floodplain 1 = Within 100 year floodplain

2 = Within 500 year floodplain

0.5 0 * 0.5 = 0.00

Proximity to Environment

al Hazard

0 = Not within close proximity 1 = Within 100 feet

2 = Contained onsite

0.5 0.5 * 0.5 = 0.25

Proximity to

Buildings

0 = More than 20 feet away 1 = Within 20 feet

2 = Under a building

2.0 0 * 2.0 = 0.00

Proximity to

Roadway

0 = Not influencing roadway 3 = Within 15 feet of centerline, minor 8 = Within 25 feet of centerline, major

10 = Within 50 feet of railroad

1.0 0.8 * 1.0 = 0.80

Total

10.0 6.15 (or 61.5 on

a scale of 1-100)

POF Factors Rating Description Value Weight Weighted Value

Percent

Consumed

Actual age divided by the

estimated effective life 7.0 0.91 * 7.0 = 6.37

Maintenance

Condition

1 = Excellent 2 = Good 3 = Fair 4 = Poor

5 = Failure Imminent

1.0 0.8 * 1.0 = 0.8

Structural

Condition

1 = Excellent 2 = Good 3 = Fair 4 = Poor

5 = Failure Imminent

2.0 0.8 * 2.0 = 1.6

Total

10.0 8.77 (or 87.7 on a

scale of 1-100)

Exam

ple

Analy

sis

Probability of Failure

Consequence of Failure

Page 11: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Asset Age (years) 0-25 years 26-50 years 51-75 years 76-100

years

Greater than

100 years

Gravity Mains 4,631 2,637 2,225 2,114 268

Catch Basin Laterals 7,309 2,963 3,299 3,960 1,248

11

Asset Quantity Baseline System Value

(Current Cost)

Baseline Future System Value

(Replacement Cost at Failure)

Gravity Mains 2,030,660 feet $365,757,000 $933,842,000

Laterals 514,583 feet $43,065,000 $113,942,000

Inventory of gravity mains and laterals by age

Value of gravity mains and laterals

Annual cost to replace gravity mains at end of estimated effective life

Page 12: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Sewers,

Manholes and

Catch Basins

95%

Pump Stations

and Forcemains

2%

Storage

Facilities

0% Green

Infrastructure

1%

Ditches,

Culverts and

Outfalls

2% $529M system value 40 miles of open channels not included

12

Page 13: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

System Component Quantity (unit) Baseline System Value (Current Cost)

Baseline Future System Cost (Replacement

Cost at Failure) Gravity Mains 385 miles $365,757,000 $933,842,000

Manholes 10,748 each $39,051,000 $105,349,000

Laterals 97 miles $43,065,000 $113,942,000

Catch Basins 17,054 each $55,910,000 $136,594,000

Pressurized Mains 664 feet $131,000 $505,000

Siphons 339 feet $250,000 $618,000

Culverts 3,600 feet $1,649,000 $3,530,000

Outfalls 356 each $1,669,000 $3,530,000

Open Channels 40 miles NA $2,570,000

Ditches 72 miles $5,703,000 $1,223,000

Detention Basins 5 each $1,725,000 $4,614,000

Pump Stations 11 each $12,051,000 $26,236,000

Green Infrastructure 13 each $1,842,000 $8,451,000

Integrated System Total $528,803,000 $1,341,004,000

13

Page 14: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Probability of Failure

Consequence of Failure

Business Risk

14

Page 15: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

A B (assumed for planning)

C Current Level, D

Inspection/ Assessment

10-year cycle on all assets

10-year cycle on assets over 50-years old

10-year cycle on assets over 75-years

Known problems and planned construction

Corrective Maintenance

On 50% of assets past effective life

On 30% of assets past effective life

On 15% of assets past effective life

Respond to failure and complaints

Preventative Maintenance

On 10% of inspected assets

On 10% of inspected assets (over 50-years old)

On 10% of inspected assets (over 75-years old)

NA

Renewal Strategy (sewers and manholes)

System replacement every 100-years

System replacement every 125-years

System replacement every 150-years

Replace at failure

Green Infrastructure

30% of capital investment with green practices

20% of capital investment with green practices

10% of capital investment with green practices

Evaluate on select project sites

Annual Investment Required

$22.9M $14.7M $10.4M $4.1M

* A excerpt from the level of service strategy table 15

Page 16: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Operation and Maintenance

25%

System Renewal 60%

Street Sweeping 8%

Planning 4%

Regulatory Compliance

2% Development Regulation

1%

Annual Required Investments

$5.9M Operational

$8.8M Capital Investment

$14.7M Total

16

Page 17: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Assets Inspection Prevention

Maint. Corrective

Maint. System

Renewal Total

Investment

Gravity Mains $212,000 $1,207,000 $598,000 $2,927,000 $4,944,000

Manholes $6,100 $55,000 $23,000 $313,000 $397,100

Laterals $20,100 $104,000 $25,000 $575,000 $724,100

Catch basins $894,000 $26,000 $48,000 $746,000 $1,714,000

Pressurized Mains $300 $1,400 $1,700

Siphons $2,100 $2,000 $4,100

Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700

Open Channels $11,000 $11,000 $291,000 $313,000

Roadside Ditches $3,200 $72,000 $75,200

Discharge Points $47,000 $6,000 $142,000 $14,000 $209,000

Creek gates $13,200 $0 $13,200

Detention Basins $6,500 $15,000 $21,500 Infiltration Basins (underground) $500 $8,000 $8,500

Lift Stations $64,400 $2,531,000 $2,595,400

Hydro Separators $4,000 $900 $4,900

Green Infrastructure $25,000 $1,314,000 $1,339,000

Subtotal of asset classes $1,319,100 $1,495,000 $836,000 $8,825,000 $12,474,400

O&M (inspection, corrective and preventative maintenance) $3,651,000

Capital Renewal (system renewal) $8,825,000

Street Sweeping $1,140,000

Planning $600,000

Regulatory Compliance $350,000

Development Regulation $160,000

Total Investment $14,726,000 17

Page 18: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Project Name Description Budget (1994 $)

Est. Cost (2013 $)

Indian Mill Creek Dredging Dredging $100,000 $436,000

Burton-Breton Branch - Channelization and Cleaning Channelization and Cleaning $180,000 $253,300 Burton-Breton Branch - Enlargement of Culverts Replace culverts $1,000,000 $198,300

Indian Mill Creek Flap Gate at Jennette Ave Backflow Prevention $10,000 $18,000

Oakleigh Ave in Hogadone District - channelization/cleaning Storm Sewer $150,000 $261,000

Maplegrove Detention Pond Detention $300,000 $522,000

Colton Dr Culvert Replacement Replace culvert and driveway approach, re-grade ditch

$15,100

Eastcastle Drain Improvements Replace outfall and repair erosion damage $15,600

Capilano Stormwater Improvements Replace 18" pipe back to MH and clean and channelize

$41,400

Outfall replacement Indian Mill Creek at Richmond Replace outfall and repair erosion, complete bank stabilization

$6,600

Moreland and Longmeadow Stormwater Improvements Extend new storm sewer $138,200

Coldbrook Drain Rehabilitation - Michigan Ave and Fuller 100' of 114" x 75" pipe across Michigan St $147,500

Plaster Creek Bank Erosion Full design channel protection and naturalized bank stabilization

$506,500

Eastridge Stormwater Improvements Add catch basins and new pipes to outfall $94,000

Shawmut Hills Baseball Diamond Stormwater Improvements

Re-grade ditches, and add underground infiltration basin

$74,300

Leffingwell Culvert and Erosion Repair Channelization, bank stabilization and add spillways $15,100

Brookshire Outfall Replacement and Erosion Repair Replace outfall and stabilize bank $70,700

18

Page 19: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

2015 2016 2017 2018 2019 2020 2021 2022 2023

Capital Projects

Capital Projects for Other Utilities $74 $339 $925 $1,359 $1,500 $1,500 $1,500 $1,500 $1,500

Previously Unfunded Projects $436 $470 $261 $0 $522 $0 $0 $0 $0

Assessment Program Repairs $3,969 $3,732 $3,198 $2,717 $2,726 $3,419 $3,505 $3,592 $3,681

Miscellaneous Projects $31 $48 $286 $675 $86 $0 $0 $0 $0

Lift Station Fund $2,531 $2,575 $2,620 $2,666 $2,713 $2,760 $2,809 $2,858 $2,908

Green Infrastructure $1,314 $1,337 $1,360 $1,384 $1,408 $1,433 $1,458 $1,484 $1,510

Drainage Improvements & Misc. Repairs $175 $178 $181 $184 $188 $191 $194 $198 $201

County Drain Comm. Assessment $45 $46 $47 $47 $48 $49 $50 $51 $52

Emergency Repairs $250 $254 $259 $263 $268 $273 $277 $282 $287

Subtotal Capital Projects $8,825 $8,979 $9,137 $9,296 $9,459 $9,625 $9,793 $9,965 $10,139

Operation and Maintenance

Collection System $3,222 $3,278 $3,335 $3,394 $3,453 $3,513 $3,575 $3,637 $3,701

Open Channels, Culverts, Outfalls $329 $335 $341 $347 $353 $359 $365 $372 $378

Detention Basins $7 $7 $7 $7 $8 $8 $8 $8 $8

Pump Stations $64 $66 $67 $68 $69 $70 $71 $73 $74

Green Infrastructure $29 $30 $30 $31 $31 $32 $32 $33 $33

Subtotal Operation and Maintenance $3,651 $3,715 $3,780 $3,846 $3,913 $3,982 $4,052 $4,122 $4,195

Street Sweeping $1,140 $1,160 $1,180 $1,201 $1,222 $1,243 $1,265 $1,287 $1,310

Planning Projects $600 $611 $621 $632 $643 $654 $666 $678 $689

Regulatory Compliance $350 $356 $362 $369 $375 $382 $388 $395 $402

Development Regulation $160 $163 $166 $169 $171 $174 $178 $181 $184

Total Investment $14,726 $14,984 $15,246 $15,513 $15,784 $16,060 $16,342 $16,628 $16,919

Funding based on Level of Service B All dollar amounts are reported as $1,000s

19

Page 20: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

A B C D

Operational

Inspection $2,102,500 $1,319,100 $905,800 $40,000

Prevention Maintenance $3,920,000 $1,495,000 $796,200 $0

Corrective Maintenance $1,296,000 $836,000 $414,000 $730,598

Street Sweeping $1,200,000 $1,140,000 $1,020,000 $980,000

Planning $1,000,000 $600,000 $200,000 $0

Regulatory Compliance $400,000 $350,000 $300,000 $289,197

Development Regulation $160,000 $160,000 $160,000 $160,000

Total Operational $10,078,500 $5,900,100 $3,796,000 $2,199,795

Capital Renewal $12,788,500 $8,824,300 $6,580,800 $1,920,000

Total Investment $22,867,000 $14,724,400 $10,376,800 $4,119,795

20

Page 21: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Largest portion of 20-year capital improvement plan is for renewal of existing assets through projects yet to be defined.

Level of Service B – sewers greater than 50-years old would be investigated over a 10-year period

21

Year FY Number of

Reaches

Pipe Assessment

Length (LF)

Est. Cost for Selected

Renewal

1 2014 532 117,159 $14,233,000

2 2015 452 98,633 $15,383,000

3 2016 381 87,094 $17,635,000

4 2017 467 103,480 $14,557,000

5 2018 494 103,331 $14,682,000

6 2019 565 115,766 $8,371,000

7 2020 541 113,964 $3,329,000

8 2021 554 118,038 $3,562,000

9 2022 422 87,020 $4,673,000

10 2023 545 107,023 $4,355,000

Totals: 4,953 1,051,508 $100,780,000

Page 22: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Quick Budgeting Analysis

Example ◦ $268,000 Baseline Current Replacement Value

◦ $42,000 Renewal Strategy Cost

◦ $5,000 Inspection Cost

22

Page 23: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Continuously update and improve the dataset

Transition from an age based to a condition based system

Use the system as a planning and cost estimating tool for operation, maintenance, rehabilitation and renewal projects

Periodically review and update: ◦ weights and values assigned to the probability and consequence

of failure variables

◦ unit price cost information

◦ planned project areas

◦ renewal strategy variables

23

Page 24: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Creation of a Stormwater Oversight Commission ◦ January 28, 2014 ◦ Responsibilities shall be to report on stormwater performance,

review expenditures and capital investment strategies, monitor achievement of stormwater outcomes, and make recommendations to the City Manager and City Commission regarding policies and a plan for achieving Stormwater Management Level C

Vital Street and Sidewalk Investment Guidelines ◦ February 11, 2014 ◦ Low impact design will be the default design approach for street,

sidewalk and right-of-way repair, improvement and reconstruction and shall be used unless clear engineering difficulties prevent its use in order to enable the City to achieve a minimum of Stormwater Management Level C investment by FY2022

24

Page 25: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Environmental Services Department

Engineering Department

Dept. of Energy and Sustainability

Chamber of Commerce

West Michigan Environmental Action Council

EMA, Inc. (City GIS Contractor)

Woolpert LLC (Infrastructure Optimization toolset)

25

Page 26: MWEA 89th Annual ConferenceSiphons $2,100 $2,000 $4,100 Culverts (stream crossings) $9,700 $86,000 $14,000 $109,700 Open Channels $11,000 $11,000 $291,000 $313,000 Roadside Ditches

Dan Christian, PE, D.WRE

Tetra Tech

26