mwmh fact sheet 5

Upload: shailesh-atkari

Post on 06-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 MWMH Fact Sheet 5

    1/5

    1051 9 9 7 M I N E S I T E W A T E R M A N A G E M E N T H A N D B O O K

    The intent o this act sheet is to allow the mine

    operator to build small earth dams (arm dams)

    or minor or temporary water supply or to orm

    part o a diversion drainage scheme. I the dam is

    an important water supply or food mitigation tool

    then input rom civil engineers and hydrologists

    is vital. The calculation o expected catchment

    yields and food fows are covered elsewhere in

    this handbook; hence this act sheet will cover

    the selection o a dam site, dam design and

    dam construction. The inormation in this act

    sheet is collated rom the text Nelson (1991).

    Selecting a Dam Site

    The easiest and most ecient dams involve

    constructing an earth embankment across a small

    valley. These are commonly known as gully dams and

    will be the ocus here. Other types o small dams,

    including hillside dams, turkeys nest ponds andexcavated tanks, are easible alternatives i a suitable

    gully is not available, and involve many o the same

    principles to be discussed. The important points to

    consider when selecting a dam site are as ollows:

    minesitelicenceconditionsshouldbechecked

    or local water resources authorities contacted to

    ensure a dam is allowable under environmental,

    water use and dam saety restrictions;

    thestoragevolumeshouldbeselected

    to suit the expected catchment runo

    volumes. This will prevent excessive

    earthworks or an eroded spillway;

    unlessthedamisforsedimentcapturepurposes,

    the upstream (u/s) catchment should not be

    excessively disturbed. I this is unavoidable,

    an u/s silt trap will have to be installed and

    constantly maintained (ie. emptied);

    anideal site is on a fat gradient watercourse

    in a wide fat-bottomed valley immediately

    upstream o a narrow gorge. Sides o the

    valley must remain stable when saturated

    to avoid land slips into the dam;

    theoundations or the dam must be

    suciently strong to support the embankment

    without excessive settlement and must

    be impervious to seepage. Sti inorganic

    clay is ideal while sedimentary rock can be

    acceptable. Fractured igneous rock or deep

    layers o sand and gravel should be avoided;

    theavailability o suitable material nearby

    is vital. Available quantities will determine thetype o embankment used as illustrated in the

    attached table (Figure FS 5.1). Impervious

    material or embankment construction should

    contain 20%-30% clay with sand, silt and some

    gravel. No rocks greater than 75 mm size should

    be present. As a saety actor, two to three times

    the expected quantities should be available; and

    a subsurace geotechnical investigation should

    be carried out on avoured sites to assess the

    above actors as well as groundwater levels,

    cuto trench depths and borrow pit boundaries.

    The investigation should include excavated pits

    along the dam centreline, spillway and in borrow

    areas ollowed by geotechnical testing o samples.

    Dam Design

    Good design o the dam and spillway is vital to ensure

    a stable embankment and to prevent ailure due to

    erosion or excessive seepage leading to piping ailure.

    Piping ailure results rom seepage water transporting

    materialoutoftheembankmentcausingapipe

    which rapidly expands leading to massive ailure. The

    basic geometric design principles or a stable dam

    are illustrated in Figure FS 5.1. The ollowing points

    should also be accounted or in the dam design. Cuto excavations are used to prevent

    seepage under the embankment by providing a

    impervious barrier linking the embankment to

    Construction of Small Earth Embankment Dams

    F A C T SH EET NO. 5

  • 8/3/2019 MWMH Fact Sheet 5

    2/5

    106 1 9 9 7 M I N E S I T E W A T E R M A N A G E M E N T H A N D B O O K

    impervious oundation material. It must be connected

    directly to the impervious embankment material

    and must be keyed into suitable oundation material

    as shown in the table below. I a cuto trench is

    impractical due to excessive depths, an eective

    alternative where oundations are moderately

    pervious is to use a clay blanket 0.6 m thick (approx.)

    extended 35 m (approx.) u/s rom the embankment.

    Spillway fows must be diverted away rom the

    downstream (d/s) toe o the embankment to

    avoid erosion. A small return wall at the spillway

    may be required, as shown in the gure. I

    continuous small fows are expected over thespillway it is advisable to install a trickle pipe

    or a small fow channel just below the main

    spillway level. This will prevent scour erosion.

    Outlet pipes are sometimes necessary to create

    a gravity supply, supply a pump, drain water

    or dam maintenance, satisy legal requirements

    or to allow the dam to be used as a food fow

    detention storage. I these requirements are

    not applicable it is best to avoid outlet pipes.

    Freeboard is required on dams to allow

    or uncertainties in food fow estimation,

    inaccuracies in construction and wave action.

    The heights shown on the gure assume

    a maximum 500 mm fow depth over the

    spillway. I an alternative spillway arrangement

    is used, the reeboard must be altered to suit.

    Dam Construction

    Good control o construction methods and

    material condition is vital to achieve a water

    tight dam. The ollowing construction phases

    and guidelines should be adopted:

    priortocommencingconstructionofthe

    dam a surveyor should identiy the extent o

    inundation, the embankment centre line and

    batter toe lines, the spillway and borrow pits;

    ensuretheproperequipment is available.

    This should include scrapers and dozers or

    small embankments while larger projects will

    also require graders, rollers and water carts;

    ifthedamislocatedinagullyorstream

    which fows regularly it will be necessary

    to dewater the site. This is best achieved

    using an upstream weir and a gravity drain

    which bypasses the dam. Groundwater in

    trenches will need to be pumped out;

    areliablewater supply is important i

    the material used in the embankmentneeds conditioning (ie. addition o

    water to allow proper compaction);

    theareatobeinundatedbythedamwater

    must generally be cleared and grubbed. This

    includes removing all trees, shrubs, rocks and

    any debris. This can be modied i aquatic

    habitat is to be an ancillary unction o the

    storage. This should be burnt or pushed

    downstream o the embankment. At the same

    time the area under the embankment should

    be cleared and have all topsoil stripped

    (100 mm minimum) and stockpiled;

    Construction of Small Earth Embankment Dams

    F A C T SH EET NO. 5

    Suitable oundation

    material (SFM)

    Required penetration

    depth into SFM

    Width o cuto

    trench at base

    Batter slopes or

    excavated trenchClay 0.6 m 2.5 m minimum 1 :1

    Rock 0.3 m 0.3 m vertical

  • 8/3/2019 MWMH Fact Sheet 5

    3/5

    1071 9 9 7 M I N E S I T E W A T E R M A N A G E M E N T H A N D B O O K

    thecuto excavation should then be carried

    out and impervious material placed and

    compacted to bring the level back up to that o

    the stripped oundation. The whole oundation

    area is then lightly scarifed (50 mm deep) in

    preparation or construction o the embankment;

    borrow pits should ideally be within the area

    covered by the stored water. They should

    have side slopes o 3H:1V and should be

    positioned a minimum o 6 m away rom the

    upstream toe o the dam embankment;

    embankment construction requires control o:

    the moisture content o the embankment

    material when placed must generally be within

    the range 3% dry to 2% wet o optimum

    moisture content. This is the moisture content

    which allows the maximum density to be

    achieved by the compaction equipment used;

    the loose thickness o layers placed

    should not exceed 100 mm i dozers

    and scrapers are used or compaction

    or 200 mm or sheepsoot rollers;

    the degree o compaction achieved should be

    95% Standard Compaction or 90% Modied

    Compaction. This will usually require between

    our and eight passes with a sheepsoot roller;

    batter slopes should be controlled using

    a template (timber triangle with therequired horizontal and vertical length

    ratios ie. 3H:1V) and spirit level;

    thespillway must be constructed absolutely

    level to ensure there are no preerential

    fow paths which will erode. When

    cutting is complete the surace should be

    topsoiled, grassed and compacted;

    outlet pipes, i required:

    must only be placed in a trench cut into

    natural ground or compacted embankment.

    The trench should be at least 100 mm

    deeper than the pipe diameter;

    between three and six cuto collars (1.2m x

    1.2m) shall be evenly spaced along the pipe

    to prevent seepage o water along the pipe;

    do not place pipes at the very base o the

    dam i sediment is likely to be a problem;

    it is advisable to include a trash

    rack at the inlet to the pipe;

    valves should be placed at the

    discharge end or in a pit on the d/s

    slope o the embankment; and

    topsoil to a depth o 100 to 150 mm

    minimum and good holding grass such

    as kikuyu or couch should be placed over

    the entire embankment (u/s and d/s) andspillway. This should be ertilised and

    irrigated i necessary to ensure rapid growth

    and hence immediate erosion prevention.

    Construction of Small Earth Embankment Dams

    F A C T SH EET NO. 5

  • 8/3/2019 MWMH Fact Sheet 5

    4/5

    Dam Element

    GEOMETRIC DESIGN CRITERIA

    Homogenous Zoned Dam Diaphragm Dam

    HEIGHT OF DAM (m) 0-3 3-6 6-9 0-3 3-6 6-9 0-3 3-6 6-9CREST WIDTH (m) 2.8 3.5 4 2.8 3.5 4 2.8 3.5 4

    UPSTREAM BATTER SLOPE (H : V) 3:1 3:1 3.5:1 2:1 2.5:1 3:1 3:1 3:1 3.5:1

    DOWNSTREAM BATTER SLOPE (H : V) 2.5:1 3:1 3:1 2:1 2.5:1 3:1 2.5:1 3:1 3:1

    DIAPHRAGMTHICKNESSD(m)

    (Perpendicular to dam ace)

    0.6 0.85 1.1

    FREEBOARD (m) : FETCH < 1000 m 1.0 m - Assuming 0.5 m maximum spillover depth

    FETCH > 1000 m 1.5 m - Assuming 0.5 m maximum spillover depth

    SETTLEMENT ALLOWANCE (mm)

    (Construction level above required

    crest level)

    150 300 500 150 300 500 150 300 500

    108 1 9 9 7 M I N E S I T E W A T E R M A N A G E M E N T H A N D B O O K

    Construction of Small Earth Embankment Dams

    F A C T SH EET NO. 5

    F I G U R E F S 5 . 1

  • 8/3/2019 MWMH Fact Sheet 5

    5/5

    1091 9 9 7 M I N E S I T E W A T E R M A N A G E M E N T H A N D B O O K

    Construction of Small Earth Embankment Dams

    F A C T SH EET NO. 5

    SPILLWAY DESIGN

    FLOOD FLOW MINIMUM

    INLET WIDTH

    MINIMUM OUTLET WIDTH (m)

    (Various Return Slopes.)

    (m3 /s) (m)