myanmar power sector overview
DESCRIPTION
Energy Industry in MyanmarTRANSCRIPT
Power Sector Overview: Demand, Supply Options and
the Role of Renewable Energies
Nay Pyi Taw 1-11-2012
Kachin
Sagaing
Shan
Mandalay
Magway
Chin
Rakhaing
Bago Kayar
Yangon Ayeyarwaddy Kayin
Mon
Tanintharyi
Area of Country 261, 319 sq-mile
Population around 59.78 million The country consists of
States
(1) Kachin
(2) Kayah
(3) Kayin
(4) Chin
(5) Mon
(6) Rakhaing
(7) Shan
Regions
(1) Saggaing
(2) Tanintharyi
(3) Bago
(4) Magway
(5) Mandalay
(6) Yangon
(7) Ayeyarwaddy
Brief Introduction to The Republic of Union of Myanmar
2
After change in constitutional structure, Myanmar has been
awakening as a country with reforms not only in strategic
and tactic approaches, also the environmental and
technological issues included.
The power sector is playing critical role in the development
of the country.
Then, insufficient supply of electricity in the last summer
highlighted the needs of proper and concrete Power
Development Plan and also leads a change in Energy Policy.
Introduction
3
1. To employ the available energy resources in power generation for the
sufficient supply of electricity.
2. To promote the effective and efficient use of electricity for future
energy sufficiency, reserves and sustainability in our nation.
3. To conduct the reliable power quality to be supplied safely.
4. To enhance the electricity distribution system to be developed in
accordance with the advance technologies.
5. To adopt the environment-friendly ways in electricity generation,
transmission and distribution.
6. To encourage the expansion of power transmission and distribution
throughout the country and the Public-Private-Participation in each
sector.
4
Policies
1. In order to transmit the generated power, increased in the period of
fifth five-year plan, through Myanmar Power System to Regions
and States, the Transmission Lines and Primary Substations are to
be implemented and also the Distribution Plans for electricity supply
to the Industries and Public are to be worked out.
2. To provide the technical know-how and policy support to the local
people with their cooperation and participation in using alternative
energy such as bio-mass in rural areas, far from the National Grid.
3. To meet the electricity demand for the areas, where electricity
through the National Grid is not accessible, are to be supplied by
Mini Hydro and Diesel Generators.
5
Objectives
4. In order to be reliable the quality of Myanmar Power System which
is conducted for generation, transmission, distribution and
consumption of electric power and to supply the electricity with the
least of power interruption and loss at the Standard Voltage Level,
our skillful staffs shall carry out by getting technical know-how from
abroad.
5. To fulfill the power demand of Myanmar, not only Hydro Power
Generation and also Gas Turbine Power Plants are to be in
operation, and Wind Power and Solar Power Plants are
economically and widely constructed to reinforce the power supply.
6
Objectives(cond.)
Distribution
Generation
YESB (MOEP )
Transmission
End User
HPGE (MOEP )
MEPE (MOEP )
MEPE (MOEP ) ESE (MOEP )
JV/IPP
7
Hydro
Coal
Gas
Diesel
500 kV (future)
230 kV
132 kV
66 kV
33 kV
11 kV
0.4 kV
Electricity Supply to Consumer
Grid System Isolated Total(MW) (MW) (MW) (%)
Installed Capacity 3,494.90 100.08 3,594.98 100.00%Hydroelectric 2,660.00 33.34 2,693.34 74.92%Gas 714.90 - 714.90 19.89%Coal 120.00 - 120.00 3.34%Diesel - 63.02 63.02 1.75%Bio Mass - 3.72 3.72 0.10%
74.92%
19.89%
3.34% 1.75% 0.10%
Hydroelectric Gas Coal Diesel Bio Mass
8
Installed Capacity in 2012
Grid System Isolated Total(MWH) (MWH) (MWH) (%)
Generation Capacity 8,548.37 76.40 8,624.77 100.00%Hydroelectric 6,144.88 43.65 6,188.53 71.75%Gas/Steam 2,012.02 - 2,012.02 23.33%Coal 391.47 - 391.47 4.54%Diesel - 32.75 32.75 0.38%
9
71.75%
23.33%
4.54% 0.38%
Hydroelectric Gas/Steam Coal Diesel
Generation Capacity in 2010-2011
Year
Generated Unit (GWh)
1988-89 2226.45
1992-93 3006-60
1996-97 4130.31
2000-01 5117.64
2004-05 5608.24
2008-09 6621.76
2011-12 10338.08
2226
1988
-89
1992
-93
1996
-97
2000
-01
2004
-05
2008
-09
2011
-12
2000
4000
6000
8000
10000
12000
GW
h
Yr
10338
10
Yearly Power Generation from (1988-89) to (2011-12)
Monthly Peak Generation growth (2006 ~ 2012) Peak Generation in May declines because of the low water level of reservoirs.
600
900
1200
1500
1800Ap
rilJu
lyO
ctob
erJa
nuar
yAp
rilJu
lyO
ctob
erJa
nuar
yAp
rilJu
lyO
ctob
erJa
nuar
yAp
rilJu
lyO
ctob
erJa
nuar
yAp
rilJu
lyO
ctob
erJa
nuar
yAp
rilJu
lyO
ctob
erJa
nuar
yAp
rilJu
ly
Monthly Peak Generation (MW)
Monthly Peak Generation (MW)
11
Monthly Peak Generation (MW)
Yearly Peak Generation Growth (2006 ~ 2012)
As New Large Power Plants have commissioned in 2011 then the peak generation
become 50 % higher than 2009
996 1004 10611129
1379
1588 1640
750
1000
1250
1500
1750
2006 2007 2008 2009 2010 2011 2012
Yearly Peak Generation (MW)
Yearly Peak Generation (MW)
12
Tigyit 120MW
Hydro Power Plant
Sr No.
Type of Power Plant
Number
Installed Capacity
(MW)
1. 2.
Hydro Power Gas & Steam
19 11
2660.0 834.9
Total 30 3494.9
Mone 75MW
Sedawgyi 25MW
Zawgyi-2 12MW
Zawgyi-1 18MW
Bluchaung-1 28MW
Paunglaung 280MW
Shwetaung 55.35MW
Yenwe 25MW
Zaungtu
20MW
Myanaung
34.7MW
Hlawga 154.2MW
Thaton 50.95MW
Mawlamyaing
12MW
Ahloneံ 154.2MW
Ywama 70.3MW
Yeywa 790MW
Khapaung
30MW
Shweli-1 600MW
KengTawng 54MW
Shwekyin
75MW
Kun 60MW
KyeeOhnKyeeWa 74MW
Tapein 240MWံ
Steam Power Plant
Gas Power Plant
13
Thaphanseik 30 MW
Kyunchaung 54.3 MW
Man 36.9 MW
Thaketa
92 MW
Kinda 56 MW
Bluchaung-2 168MW
Location of Existing Power Plants
Voltage (kV)
Nos. of Line
Length
miles km
230 46 1,922.68 3,095.52
132 42 1,412.33 2,273.85
66 138 2,247.75 3,618.87
Total 226 5,582.76 8,988.24
Existing Transmission Lines
Voltage (kV)
Nos. of Substation
Capacity (MVA)
230 30 3,760
132 25 1,322.5
66 130 1,975.5
Total 185 7,058.0
Existing Substations
14
National Grid System In our National Grid System, there are 30 Nos. of Generating Power
Stations, ie (19) Hydropower Station, (1) Coal Fire Power Plant, (10) Gas
Turbine (including 4 Combined Cycle in Yangon).
The major electric power stations feed electricity into the National Grid
System with 230 kV, 132 kV and 66 kV transmission lines and substations.
Voltage (kV)
Length Capacity
miles km (MVA)
33 4,446.91 7,115.06 3,865.64
11 7,990.39 12,784.62 3,805.68
6.6 869.28 1,390.85 1,465.44
Total 13,306.58 21,290.53 9,136.76
Existing Distribution Lines & Substations
15
Distribution System and Electrification Ratio
The National Grid System connect with the Distribution System via 33 kV,
11 kV and 6.6 kV distribution lines and substations.
Population 59.78 million
Numbers of Household 8.91 million
Electrified Household 2.39 million
Percentage 27 %
Electrification Ratio
GDP & Population Growth Rate of States and Divisions (Ref: Statistical Year Book – 2010)
National GDP Growth Rate: 11%
National Population Growth Rate: 1.2%
States GDP Population
Kachin 6.9 1.26
Kayah 6.2 1.44
Kayin 8.1 1.19
Chin 7.3 1.63
Mon 10.3 0.99
Rakhaing 12.6 1.07
Shan 8.8 1.16
Divisions GDP Population
Sagaing 7.3 0.95
Tanintharyi 7.7 1.34
Bago 11.1 1.07
Magway 6.2 1.05
Mandalay 10.3 1.08
Ayeyarwaddy 6.7 1.12
Yangon 16.2 1.15
16
• In 10 years period, from (2001-02) to (2011-12), the economy
of country reflected with the average GDP of 11%.
• The rate of change of Electricity Demand related to GDP is 1.4
times (Elasticity Factor).
• Electricity Demand was increased 2 times than that occurred
in past 10 years period.
GDP & Population Growth Rate of States and Divisions (Ref: Statistical Year Book – 2010)
17
The maximum demand growth rate is around 15% from 2010 to 2012. The
maximum demand forecasting of summer time for the year 2013 to 2016 are as
follows:
Sr
No Year Demand (MW) Increased
Percentage
1. 2010 1371 -
2. 2011 1588 15.8%
3. 2012 1850 16.49%
4. 2013 2128 15%
5. 2014 2447 15%
6. 2015 2814 15%
7. 2016 3236 15% 18
Short Term Demand Forecasting for (2010-2016)
Sr No.
Name of Power Plant Executing Agency
Total Installed Capacity
Commissioning step by step
2012-2013
2013-2014
2014-2015
2015-2016
1. Shweli-1 (purchasing No-4 machine)
JV 100 100 -
2. Shibwenge CPI 99 99 -
3. Phyuu MOEP 40 40 -
4. Thautyaekhaut-2 Golden Energy 120 120 -
5. Nancho MOEP 40 40 -
6. Bluchaung Future Energy 52 52 -
7. Upper Bluchaung New Energy Oasis
29 29 -
8. Upper Paunglaung MOEP 140 140 -
Total 620 199 252 169 - 19
MW
Under Construction Hydro Power Plants during Short Term Plan
Sr No.
Location Company Name
Installed
Capacity
(MW)
Project Commissioning
2013 2014 2015 2016
1. Hlawga
Hydro Lancang(China) 530 - 126 252 152
Zeya & Associates 50 50 - - -
2. Ywama
Myanshwepyi 50 50 - - -
EGATi (Thailand) 240 120 120 - -
3. Ahlone Toyo Thai (Thailand) 120 100 20 - -
4. Thaketa
Busan Korea Biotechnology Co., (Korea)
500 - 168 168 164
Consultant Int’l Co. 50 50 - - -
20
Under Construction Gas and Combined Cycle Power Plants from (2012-13) to (2015-2016)
Short Term Plan for Transmission Lines and Substations
Voltage (kV)
Number of Lines
Lines Length (mile)
500 2 263
230 29 2363
132 3 105
66 30 1343
33 - 1146
11 - 2951
0.4 - 1952
Total 64 10,123
Transmission Lines
Voltage (kV)
Number of
Substations
Installed Capacity
(MVA)
500 3 1500
230 26 2700
132 10 720
66 70 1162
33 148 979
11 2752 629
- - -
Total 3,009 7,690
Substations
21
Long Term Demand Forecasting
Project Term
Condition after Project Term
Expected
Population
(million)
Power Demand Expected Consumptio
n per one person (kWh)
Expected Consumptio
n per one household
(%)
(MW) (GWh)
Yr 2011-12 Existing Condition
60.44 1,806 10,444 173 27%
From Yr (2012-13) To Yr (2015-16)
63.14 3,078 17,797 282 34%
From Yr (2016-17) To Yr (2020-21)
66.69 5,686 32,874 493 45%
From Yr (2021-22)
70.45 10,400 60,132 854 60%
22
Electricity Demand Curve in MW (2012 ~ 2031) Growth rate of Population 1.1%, of GDP 10.5%, of Electricity 13%
2155
2426
2732
3078
3477
3929 44
42 5025 56
86 6416 72
44 8167 92
14 1040
0
1174
7
1327
4 1500
9 1697
8
1921
6
20003000400050006000700080009000
1000011000120001300014000150001600017000180001900020000
2012
…
2013
…
2014
…
2015
…
2016
…
2017
…
2018
…
2019
…
2020
…
2021
…
2022
…
2023
…
2024
…
2025
…
2026
…
2027
…
2028
…
2029
…
2030
…
Electricity Demand (MW)
23
0
5000
10000
15000
20000
2500020
16-1
7
2017
-18
2018
-19
2019
-20
2020
-21
2021
-22
2022
-23
2023
-24
2024
-25
2025
-26
2026
-27
2027
-28
2028
-29
2029
-30
2030
-31
2216 2216 2216 2216 2216 2216 2216 2216 2216 2216 2216 2216 2216 2216 2216
4520 5108 5775 6532
7392 8341
9417 10617
11978 13521
15271
17257
19511
22072
24981
3477 3929 4442 5025 5686
6416 7244
8167 9214
10400 11747
13274
15009
16978
19216
Long Term Demand Forecasting and New Constructed Installed Capacity
Existing Installed Capacity
Reserve Capacity
Capacity to Expend
Required Capacity
MW
24
Long Term Plan to be Constructed Hydropower Plants
Sr No.
Power Plants Name
Constructed Company
Name
Total Installed Capacity
Projects Commissioning Step
2016-17
2018-19
2019-20
2020-21
1. Ann MOEP 10 10
2. Thahtay MOEP 111 111
3. Upper Kengteng MOEP 51 51
4. Upper Yeywa MOEP 280 280
5. Shweli-3 MOEP 1050 1050
Total 1502 10 162 280 1050
25
Future Plan of Transmission Lines Future Plan of Substations
Voltage (kV)
Nos. of Line
Length
mile km
500 6 1,693.0 2724.04
230 80 5,894.0 9483.45
132 12 410.5 660.49
66 33 1,222.1 1966.36
Total 131 9,219.6 14,834.34
Voltage (kV)
Nos. of Substation
Capacity (MVA)
500 10 5,000
230 25 2,360
132 10 675
66 31 340
Total 76 8,375
26
Transmission Lines and Substation (Future Plan)
In order to reinforce the present National Grid System and to facilitate
power transmission from new generating stations to National Grid System,
Ministry of Electric Power has a long term plan of 131 Transmission Lines
and 76 Substations for future.
Renewable Energy Resources
Renewable Energy Resources
Biofuels
Geothermal
Hydro Solar
Wind
Tidal
Myanmar is situated in the south eastern part of the Asian continent. It enjoys abundant sun shine all year round, especially in the Central Myanmar Dry Zone Area. Similarly as in wind energy, to utilize solar as a substitute in place of conventional energy sources, more research and development work need to be carried out. The cooler, dry season lasts from November to April and the hotter, wet season from May to October. Sunshine is plentiful during the dry season average 7 to 10 hours a day. During the rainy season, the weather is cloudier and daily sunshine amounts is average only 3 to 4 hours a day.
Solar Energy
Wind Energy New Energy and Industrial Technology Development Organization(NEDO) of Japan performed in 1997 a study on renewable energy potential in GMS region and assessed that Myanmar has potentially available in Wind Energy. Promising areas to harness wind energy are in three regions, namely Hilly Regions of China and Shan states. Coastal regions in the south and western part of the country and central part of Myanmar. Use of wind energy is at the very initial stage. Due to the expensive initial cost, the utilization of wind energy needs to be implemented in cooperation with foreign participants under technology transfer and financial assistance program.
Hydro Energy Feasible Hydropower Project in Myanmar by Region Wise Sr. No. Region/State No. of Project Installed Capacity(MW)
1 Kachin 14 15959.50 2 Kayar 5 954.00 3 Kayin 9 6904.00 4 Chin 1 380.00 5 Sagaing 5 2432.00 6 Taninthari 6 711.00 7 Bago 8 558.00 8 Magwe 5 359.00 9 Mandalay 9 1475.00
10 Mon 2 290.00 11 Rakhine 6 871.00 12 Shan 16 12564.8
Total 86 43,458.30
Hydro Energy Feasible Hydropower Project in Myanmar by River Basin Wise Sr. No. Region/State No. of Project Installed Capacity(MW)
1 Ayeyarwaddy 29 18775.50 2 Chindwin 8 2997.00 3 Sittaung 11 1148.00 4 Thanlwin 21 17788.00 5 Mekong 3 867.80 6 Others 14 1882.00
Total 86 43,458.30
Estimated Hydropower Potential : more than 108,000 MW
Feasible Project : 43,458.30 MW
Geothermal Myanmar is one of the countries with abundant geothermal resources. A total of 93 geothermal locations have been identified throughout the country. Out of the 93 geothermal sites, 43 of them were investigations had been made.
Conclusion for Renewable Energy In the renewable energy sector, Myanmar has abundant renewable energy sources. However, they are at the initial stages due to an under- developed energy infrastructure such as institutional and legal frame- work, financial and human resource capacity constraint. In addition, they require substantial studies, research and experimental works need to be performed. The identified key issues in renewable energy develop- ment are as follows: • To have adequate information on each and every type of renewable energy sources of the country • To encourage more inter-ministries and inter-departmental interaction and cooperation • To promote private participation in the development program • To define and specify energy policy incorporating renewable energy
34