  • 8/3/2019 Naga Aleki

    1/55

    1

    TSMEGYPT

    Compliance Records

    for water treatment plants

  • 8/3/2019 Naga Aleki

    2/55

    2

    Company Name: QUENA Company for water

    and waste water .

    Plant Name: Naga Eliqy -QUENA

  • 8/3/2019 Naga Aleki

    3/55

    3

    Inspectors Compliance Summary

    Decision and Findings

    THE INSPECTION RESULT

    We confirm that the management ofNaga Eliqy Water treatment plant

    under the lead of Eng. Mohamed Mahmoud Ahmed, within the

    inspection of 11/12/2011 and 12/12/2011 has fulfilled the requirements

    of TSM (Egypt).

    TSM (Egypt) Inspection Team:

    Eng. Michael Buckler, Lead Inspector....

    Dipl.-Ing.(FH), Holger Gruetzmacher,

    Inspector,....Eng. Mohamed Maged,

    Inspector

  • 8/3/2019 Naga Aleki

    4/55

    4

    Inspectors Findings During The Inspection:

    H2 - The HR responsibility is not clearly shown in the structure. The

    responsibility for HR should preferably be with the plant manager.

    H3 - The job descriptions do not state clearly what qualification is needed to fill

    the post.

    The stated qualification of the OHS manager in the job description does not

    comply to the labour law.

    H5 - The Assessment is not yet done! The TSM (Egypt) Inspection team

    recommends to do the assessment after 9 month plant operation, in December2011 and after that yearly (according to regulations).

    H6 - Readings of the raw water flow meter do not comply with the records kept.

    (Quaterly report)

    H7 - The library should be developed further. O&M documents should be

    preferably in arabic (Gas sensor and alarm system).

    H10 - Instructions from the daily dosage sheet are not all signed.

    OHS4 - The layout is very colorful but does not differentiate between important

    information and less important information (landscape)

    OHS5 - The emergency plan for power failure is not published. The plant could

    not establish if there is an automatic interlock for the grid/generator connection.

    OHS10 - The plant could not prove that the gas sensors have been tested and

    are in working condition.

    The plant failed in the practical exercise of the chlorine leak . (Staff not wearing

    the mask properly, staff is unsure of the use of the repair kit, the exercise took

    a long time), Training of staff is urgently needed.

    OHS11 - To switch the submersible pump on/off, the operator needs to open an

    electrical board.

  • 8/3/2019 Naga Aleki

    5/55

    5

    O3 - The process of informing consumers of interruption of water supply is not

    clear. The documents shown did not prove the process explained.

    O10 - In close range of the intake are animals and a storage place for construction

    debris, what is not acceptable. Signs should be posted to inform the public aboutregulations referring to the intake protection.

    M1 - The TSM(Egypt) Inspection Team recognizes the problem of drawings not

    been handed to the plants of this type and recognizes as well the effort of the

    plant to overcome the problem. Nevertheless the drawing should be completed

    in number and improved by using standard signs. (This is a recommendation only)

    M4 - The existing asset register in the CMMS should be completed .

    M5 - The plant has started applying the maintenance reporting system. The plant

    is still under warranty what prevents the staff to apply the system in all details.

    The AC should make sure that the implementation of it is done and accompanied

    by training.

    M7 - The SMPs are only published in one office and need to be distributed to

    every workstation. Some stations ( Al2SO4) show signs of lack of Maintenance.

  • 8/3/2019 Naga Aleki

    6/55

    6

    Contents

    HR management

    OHS

    PART 2

    Operations

    Maintenance

    QA/QC

  • 8/3/2019 Naga Aleki

    7/55

    7

    TSM Compliance Forms

    PART 1 1-1 HR management (W/WWTP)

    1-2 OHS (W/WWTP)

    PART 2

    2-1 Operations (WTP)

    2-2 Maintenance (WTP)

    2-3 QA/QC (WTP)

  • 8/3/2019 Naga Aleki

    8/55

    8

    1-1TSM Compliance Forms: HR Management for wtp

    H 1

    Is there a technical affair responsible of TSM program?

    TSM

    References:

    TSM template H1TSMH1

    Guidelines:

    A decree for a TSM Technical Affairs Responsible must be issued; he could be

    the plant manager or any technical engineer in the plant or outside the plant

    as a Technical support manager or O&M sector head he could be responsible

    for follow up the program in one plant or more, or planning/construction

    supervision

    He has the know how to act adequately.

    Review decree number and date of approval

    Inspectors may discuss the program concept with the TSM responsible.

    (TSM(

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    9/55

    9

    H 2

    Is there an organization chart for the plant?

    References:

    Egyptian code of O&M of wtp/ chapter 8-3 and WWTP chapter7

    8-3

    .

    TSM template Nr. H2

    TSMH2

    Guidelines:

    Organization chart must be developed and approved for the plant according to the

    following criteria:

    Plant capacity

    Plant type(water-wastewater)

    Technology

    The chart includes name, position and picture of key Positions, (plant manager-

    operation managermaintenance managerlaboratory managerHRD manager and

    OHS specialist, etc.)

    Review the organization chart and its approval date Ensure the matching between key positions and real staff

    :

    (-)-

    -

    (

    .

    Inspectors

    Assessment:

    The HR responsibility is not clearly shown in the structure. The responsibility for HR

    should preferably be with the plant manager.

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    10/55

    10

    H 3

    Are there job descriptions comply with the qualification requirements for the

    key staffs of the plant?

    References:

    Egyptian code of O&M of wtp/ chapter 8-3 andwwtp chapter7

    8-3

    .

    TSM template Nr. H3

    TSMH3

    Guidelines:

    Submit job descriptions of key staff which includes plant manager, OHS

    specialist, operation manager maintenance manager ,HRD manager and lab

    manager, etc. also CVs and the decrees issued to occupy the positions.

    Review the job descriptions of the key staff and the decrees issued to occupy

    the positions. .

    Select on CV and compare to the job requirements as in job description.

    Inspector may select one of the job descriptions and discuss the job tasks withthe occupier.

    .

    .

    .

    .

    Inspectors

    Assessment:

    The job descriptions do not state clearly what qualification is needed to fill the post.

    The stated qualification of the OHS manager in the job description does not comply

    to the labour law.

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    11/55

    11

    H 4

    Are there instructions showing the levels of authority delegation for key

    positions during absence of original occupiers to works staff?

    References:

    Best practice

    Guidelines:

    Issue instructions to show the level of authority delegation of the key position

    Hold a delegation list including dates, names of actual key staff or the delegates (you

    can use a white board and the suitable pens for that purpose).

    Review the delegation instructions and delegation approval date.

    Inspector may check that delegation instructions match the names appearing in the

    delegation board (if applied).

    )

    )

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    12/55

    12

    H 5

    Is the performance of the plant staff assessed on an annual basis?

    References:

    Egyptian code of O&M of wtp 8-1 and wwtp chapter7

    template Nr H5

    8-1

    .

    Guidelines:

    Submit forms of staff assessment (annual or other).

    Review the assessment forms and approval date.

    (

    )

    .

    Inspectors

    Assessment:

    The Assessment is not yet done! The TSM (Egypt) Inspection team recommends to

    do the assessment after 9 month plant operation, in December 2011 and after that

    yearly (according to regulations).

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    13/55

    13

    H 6

    Do you develop quarterly plant performance indicators of the plant?

    References:

    Egyptian O&M WTP Code chapter 10-3 and Requirements of HCWW and EgyptianO&M WWTP Code chapter7

    10-3

    TSM template Nr. H6

    TSMH6

    Guidelines:

    Submit quarterly performance indicators (HCWW forms), present indicators

    graphically for 1 year at least (if possible).

    Review the indicators, the inspector may ask interpretation of the indicators

    and actions taken.

    (

    )

    ( ).

    .

    Inspectors

    Assessment:

    Readings of the raw water flow meter do not comply with the records kept.

    (Quaterly report)

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    14/55

    14

    H 7

    Is there a place where training materials and plant documents are kept?

    References:

    O&M code of wtp chapter 6-1-10 and Egyptian O&M WWTP Code

    chapter4-1-10.

    6-1-10

    4-1-10.

    Guidelines:

    The plant have to establish a place to keep all training material, catalogues and

    documents as well as codes, standards ,environmental lawsetc. Issue decree

    of responsible, borrowing system.

    Check the location and responsible decree and the borrow log book.

    /

    .

    .

    Inspectors

    Assessment:

    The library should be developed further. O&M documents should be preferably in

    arabic (Gas sensor and alarm system).

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    15/55

    15

    H 8

    Do you develop annual training plan for the plant staff and you follow up

    implementation centrally?

    References:

    Egyptian code of O&M of wtp/ chapter 8-1 and Egyptian O&M WWTP Code chapter7-

    1-4

    8-1

    7-1-4

    Guidelines:

    Submit annual training plan clarifying training needs assessment, training

    certificates.

    Review training plan.

    Review training certificate (internally and externally).

    .

    .

    (

    .)

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    16/55

    16

    H 9

    Do you have administration procedures for approving and recording annual

    leave, sick leave, and other absences?

    References:

    Egyptian code of O&M of wtp/wwtp chapter 8-1 and Egyptian O&M WWTP Codechapter7-2

    8-1

    7-2TSMH9

    Guidelines:

    Submit a copy of all administrative forms related to work orders and different

    vacations and internal orders in addition to vacation request procedures and

    other absences with all details in a clear place for all staff.

    Check installation of these procedure during site visit.

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    17/55

    17

    H 10

    Is there a system in place secured, that staff members have only access to

    valid instructions?

    References: O&M code of wtp chapter 8-3 and Egyptian O&M WWTP Code chapter4-2 3

    2

    Guidelines:

    Variation of operational instructions due to lab analysis results must be update and

    announce for the operators (for wwtp: RAS and WAS rate, DO concentration and

    chlorine dose) and for wtp :alum dose, chlorine dose ,frequency of back wash and

    sludge drawing off.

    Variations also includes the following factors:

    Equipments lock-out/tag-out for maintenance and sudden facility upset

    Exchanging facility operations

    Sudden changes in maintenance plans and facing emergency risks Changes of units operation plan.

    In all previous cases, all staff should be notified in written.

    Check presented instructions (system).

    :

    (

    )

    Inspectors

    Assessment:

    Instructions from the daily dosage sheet are not all signed.

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    18/55

    18

    1-2TSM Compliance Form: OHS

    OHS 1Is the position of OHS specialist / technician in the plant occupied?

    /

    References:

    labour law 12/2003 (ministerial decree of manpower and emigration no 134- article 2):

    (If the plant staff exceeds than 50 labour, they have to nominate fulltime specialist

    (engineer/chemist) while if it is less than that, they have to nominate fulltime

    technician)

    12/2003(

    )

    (

    /)

    .

    Guidelines:

    You have to issue internal decree according to the labour number of the plant.

    Check the decree and its approval date.

    Inspector may discuss the job tasks with the responsible.

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    19/55

    19

    OHS 2Is there an OHS committee in the plant?

    References: ministerial decree of manpower and emigration no 134- article 3.

    3.

    Guidelines:

    you have to develop a f ile contains the following documents:

    Internal decree of OHS committee Establishment.

    Monthly meeting logbook, stamped and signed by manpower.

    Review the committee organizational decree and date of approval.

    Check the monthly record approved from the ministry of manpower and training.

    Inspector may discuss the committee decisions and how to follow up and activate its

    recommendations.

    :

    .

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    20/55

    20

    OHS 3

    Do you inform the ministry of manpower about accidents, permanent

    disease, occupational diseases and work injures, using their reporting forms?

    References:

    Ministerial decree of manpower and emigration no 126/2003 article 2. /.

    TSM template Nr. OHS 3

    TSMOHS 3

    Guidelines:

    If the staff does not exceed 50 members, the plant has to fill the statistics and

    accidents forms and sends it to the man power office of your area every 6 months.

    For the bigger plants > 50 members, the 5 forms should be filled in.

    Review the forms and ensure its submission to the Man Power office according to the

    staff number.

    50

    .

    5

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    21/55

    21

    OHS 4

    Do all hazardous areas (confined space, electric switch boards, chlorine

    buildingetc have warning signs?

    References: Ministerial decree of manpower and emigration no 211/2003

    /

    TSM template Nr. OHS 4

    TSM OHS 4

    Guidelines:

    Show list of hazardous areas in the plant like:

    Sedimentation tanks Aeration tanks Drying beds and thickener - electric switch

    boards Chlorine building labs - valves chambers warehouses pump houseetc.

    Mark this area with warning signs.

    Review the hazardous areas list

    Visit to ensure the suitability of warning signs to the hazardous area.

    :

    - -

    -

    --

    ....

    Inspectors

    Assessment:

    The layout is very colorful but does not differentiate between important information

    and less important information (landscape)

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    22/55

    22

    OHS 5

    Do you have an action plan for all emergency cases (Fire, chlorine leak,

    confined space entry for evacuation of injured persons and power cut,

    emergency exits

    -

    )

    References:

    Ministerial decree of manpower and emigration no 211/2003

    /

    TSM template no OHS 5..

    TSMOHS 5

    Guidelines:

    You have to develop a plant scenario for emergency cases.

    Fire, chlorine leak, confined space entry for evacuation of injured persons, power cut and

    emergency exits.

    Check the emergency plans to face risks mentioned above.

    Make sure that all plans are attached and fixed in the proper areas.

    Check emergency exists and routes are located to the plant layout and matching reality. The inspector may discuss one of the staff about his understanding of the plan.

    :

    1-2-

    3- 4-

    -5

    .

    .

    .

    .

    Inspectors

    Assessment:

    The emergency plan for power failure is not published. The plant could not establish

    if there is an automatic interlock for the grid/generator connection.

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    23/55

    23

    OHS 6

    Do you have a plan to secure the plant from potential risks approved from the

    Civil Protection authorities

    References:

    Ministerial decree of manpower and emigration no 211 /2003

    211/2003

    TSMOHS 6

    Guidelines:

    Submit a plan to face potential risks approved from the Civil Protection authorities

    that includes for example:

    List number of extinguishers, types, capacity, their locations on

    general layout expiry date hazardous areas routine check plan training plan for

    25% of the plant staff on civil defense and rescue tasks.

    Review the plant security plan approved by civil defense.

    Inspector may check the expiry date of the extinguishers and the training plan for 25%of the staff on civil defense tasks

    :

    -

    -

    25% -

    ...

    .

    25%

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    24/55

    24

    OHS 7

    Is there an annually routine medical check up for all of the staff?

    References: According to ministerial decree of manpower and emigration no 180 /2003

    /

    Guidelines:

    You have to contact health office of your area for annual medical check up and keep a

    file for all staff; you have to record this medical check up in the monthly OHS

    committee meeting.

    Review the medical check up lists and its frequency.

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    25/55

    25

    OHS 8

    Are there sanitary utilities for personal in the plant?

    References: Ministerial decree of manpower and emigration no 211 /2003

    /

    Guidelines:

    You have to establish WC-Shower room for washing and changing labours clothes.

    Show warning signs to prevent food and beverage in places where there is a direct

    contact with waste water

    Prepare a food court with a WC to wash hands before eating.

    Review the availability of WC, showers, space for changing labours clothes and food

    court.

    .

    .

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    26/55

    26

    OHS 9

    Do all plant operating staff have appropriate personal protection equipment

    (PPE)?

    References:

    Ministerial decree of manpower and training no 211 /2003

    211/2003

    Guidelines:

    Gloves, overalls, safety shoes, goggles, safety helmet must be submitted to every

    labor based on their personal responsibility to deal with: mechanical, electrical,

    chemical, biological, confined space Hazards

    Prepare a cabinet for each staff member to keep their PPE after work shifts.

    Review the personal protection equipment list and their storage areas

    (

    )

    ) (

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    27/55

    27

    OHS 10

    Is there safety equipment ( gas detectors, breathing apparatus, safety ropes, floats

    . to deal with risk situations )chlorine leak, confined space entry,.) is it regularly

    inspected and the labours get a training on using it?

    .

    References:

    Ministerial decree of manpower and training no 211 /2003

    211/2003

    Guidelines:

    Attach and fix the safety equipments in relevant places.

    Submit routine check documents

    Submit staff training certificates on the equipment use.

    Make sure that safety equipments are fixed in relevant places.

    Inspector may check staff skills to use any equipment practically.

    Review routine check documents

    .

    .

    .

    .

    .

    .

    Inspectors

    Assessment:

    The plant could not prove that the gas sensors have been tested and are in working

    condition.

    The plant failed in the practical exercise of the chlorine leak . (Staff not wearing the

    mask properly, staff is unsure of the use of the repair kit, the exercise took a longtime), Training of staff is urgently needed.

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    28/55

    28

    OHS 11

    Is mechanical and electrical equipment properly contained and guarded to

    prevent injury to personnel?

    References:

    Labour law no 12/2003 chapter 5- clause 224

    /

    Guidelines:

    Secure the mechanical and electrical equipment with wire screens,

    handrails, coupling guards, etc. to protect the staff against accidents or

    injuries.

    This includes screens, intake, pumps, water works and ladders.

    Check that the labors are secured in doing their works during site visit.

    .

    :--

    -

    -.

    .

    Inspectors

    Assessment:

    To switch the submersible pump on/off, the operator needs to open an electrical

    board.

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    29/55

    29

    2-1 TSM Compliance Form: Operation of water treatment plants (WTP)

    :

    O 1

    Is there a routine program for the visual inspection of the plant units for

    checking that is it functioning properly?

    References:

    O&M Egyptian code of WWTP- chapter 5

    TSM template Nr. O 1

    TSMO1

    Guidelines:

    One of the items of routine operation plan is checklists that the equipment and treatment

    process are functioning correctly. It is checked by the operators so ,You have to submit check

    lists( includes the following min requirement):

    Visual inspection of M&EL equipment.

    Visual inspection of treatment process of all treatment units

    Fix the Visual inspection instructions in certain areas in the plant

    Submit the form of reporting an upset or an operation as an outcome of the

    inspections program.

    Review the visual inspection list

    Inspector may make sure that staff understands the program during the visit.

    .

    :

    .

    Inspectors

    Assessment:

    ComplianceDecision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    30/55

    30

    O 2Are chemical dose rates in the water recorded and the records kept for 1year?

    References: Best practices

    Guidelines:

    All consumable / chemicals (chlorine, polymers) have to be recorded and kept for at

    least 1 year (manual /electronic).

    Submit a summarized graph to illustrate the amount of treated wastewater against

    consumable chlorine for the last 12 months.

    Review the records and the data for at least one year

    .

    12.

    12

    (

    )

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    31/55

    31

    O 3

    Are the consumers informed before planned interruption of water supply?

    References: HCWW instructions.

    Guidelines:

    You have to coordinate with the Costumers service center of your company (hot line

    form) and inform them with the planned time for any interruption either because of

    emergency maintenance activities or because of the consequences of main power cut

    off.

    Show forms used in the last interruptions

    Inspect presented documents

    (

    )

    .

    Inspectors

    Assessment:

    The process of informing consumers of interruption of water supply is not clear. The

    documents shown did not prove the process explained.

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    32/55

    32

    O 4Are there records of the operational data of each of the operation processes?

    References: O&M Egyptian code of wtp chapter 10

    .

    Guidelines:

    You have to develop log sheets, records for each operational process.

    Operational data include frequency backwash, sludge quantity, operating

    hours of pumps, etc.

    Check the operation log sheets to make sure of accurate records and manager

    signature.

    ....

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    33/55

    33

    O 5

    Do the activities in each operational process follow the Standard Operational

    Procedure?

    References:

    O&M Egyptian code of wtp chapter 10

    TSM template Nr. O 5

    5

    Guidelines:

    You have to develop SOP of all plant operation procedures, displayed in appropriate

    place to be guidance for the operators.

    Present also work order and fault report as an output of this program.

    Review the standard operational process during the visit

    Inspector may ask some staff members to measure their understanding.

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    34/55

    34

    O 6

    Are the wastes and sludge disposed according to laws and regulations?

    References: Egyptian environmental law no 48/1982and law 4/1994 article 2 48/1982

    4/19942

    Guidelines:

    You have to dispose all wastes (sludge-backwash screening solids- etc) out of water

    table or to the drying beds or sludge thickener.

    Check how wastes (back wash water and sludge) are disposed.

    .

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    35/55

    35

    O 7

    Is a report including calculation of the O&M cost of treatment developed

    monthly?

    References:

    O&M Egyptian code of wtp chapter 6-2-7-6

    6-2-7-6

    TSMO7

    Guidelines:

    Develop monthly report including cost of treatment of 1 m3.

    Use the plant performance indicators in developing the needed.

    Review the monthly report.

    .

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    36/55

    36

    O 8Are there operation plan for the plant?

    References: O&M Egyptian code of water treatment plants chapter 2-2

    2-2

    Guidelines:

    Operational plan includes the following parameters:

    Operation schedule of equipment (in service and standby units).

    Record of flow for inlet and outlet and measure losses.

    Identify daily alum and chlorine dose

    Timing of Filters wash according to pressure difference in each filter.

    Review the submitted operational plan

    Inspector may discuss with any of staff members to make sure they understand the

    plan

    :

    .

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    37/55

    37

    O 9Are the lab results communicated to the operation department?

    References: O&M Egyptian code of WTPchapter 2

    Guidelines:

    You have to coordinate with the lab to control the operational process(alum dose -

    chlorine dose-frequency of backwash- --etc).

    Develop daily sheet (or other system) for at least chemical doses. It must be signed

    mutually by shift engineer and shift chemist.

    Review the key operational factors list

    Inspector might discuss with the operation and labs manager to know the labs role incontrolling operation condition.

    .

    ( )(

    )

    .

    ( )

    .

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    38/55

    38

    O 10

    Are all needed precautions realized to protect the raw water at the intake

    from contamination?

    References: Ministry of Health decree 458/2007 ,301/1995 and 27/1978

    458/2007301199527

    Guidelines:

    Install barrier to protect water intake against any illegal discharge or hazard (oil and grease

    spill-raw material or chemical spill).

    Develop a routine program for analysis and monitoring of quality of water intake.

    Coordinate also with (MOI) to plan dredging of the water body course closer to the intake

    to avoid influence of the raw water.

    Protect the intake with (e.g.) mesh, fence, and floats.

    Monitor application of decree of (MOH) No 301/1995 and 27/1978 and prevent any

    building at a deep of 50 m of the intake restricted area and upstream of the water intakewith 500 MT and downstream of the water intake with 200 MT.

    Supply the materials and the needed substances (sponge sheets burlap roll) to deal with

    emergency pollutants

    Check precautions on site visit of the water intake.

    ( )

    .

    . 301/1995

    50

    500

    200 .

    (

    -

    ...

    )

    .

    Inspectors

    Assessment:

    In close range of the intake are animals and a storage place for construction debris,

    what is not acceptable. Signs should be posted to inform the public about

    regulations referring to the intake protection.

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    39/55

    39

    2-2 TSM Compliance Form: Maintenance of WTP

    M 1Are the basic drawings and documents of the plant available?

    References:

    O&M Egyptian code of wtp chapter 6-1-10 --

    Guidelines:

    Min requirement are :

    Plant Lay out

    single line diagrams

    process flow

    chemicals delivery system High Voltage/Low Voltage distribution Systems

    O&M documents

    Check the mentioned documents.

    :

    .

    Inspectors

    Assessment:

    The TSM(Egypt) Inspection Team recognizes the problem of drawings not

    been handed to the plants of this type and recognizes as well the effort of

    the plant to overcome the problem. Nevertheless the drawing should be

    completed in number and improved by using standard signs. (This is a

    recommendation only)

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    40/55

    40

    M2

    Is the key process monitoring instruments maintained and/or calibrated on a

    regular basis?

    References: O&M Egyptian code of WTP chapter 2-2-2, 2-3-1-6 -----

    Guidelines:

    This question refers to mechanical, electrical equipment or electronic devices showing

    water quality, water level, pressure, flow, voltage, current, frequency or chemical

    dosing rates .it also include all actions for quality measurements (incl. calibration)

    Submit a list of monitoring instruments you have, the actions for calibration,

    certificates of approved calibration and calibration methods. Calibration should be

    performed in specialized companies

    Check the instruments list

    Check the process of calibration and the certificates

    Check the proper functioning of some instruments

    ) . .)

    .

    .

    .

    InspectorsAssessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    41/55

    41

    M3

    Is there a system for inventory of material and spare parts available, which

    shows their quantity, types, and identification cards for each

    equipment/spare part considering the correct storage concepts?

    /

    References:

    O&M Egyptian code of wwtp chapter 4 .

    Guidelines:

    Present documents (register) showing which parts and materials available and in what

    quantity?

    Computerized or manual.

    Attach an identification card to the store components considering the correct storing

    criteria; use the recommended code by the Holding company.

    Review the inventory system during the visit.

    (

    )

    .

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    42/55

    42

    M 4

    Do the electro-mechanical maintenance works comply with the maintenance

    management process?

    References: O&M Egyptian code of wtp chapter 6

    TSM template M4

    TSMM4

    Guidelines:

    That includes planned, corrective and overall maintenance, work history and reports

    Present (manual or automatic) maintenance system of routine maintenance activities,

    and work orders and fault report as an output of system implementation.

    Check maintenance schedule (auto/manual) and select one of the work order or fault

    report to insure program implementation.

    .

    ( )

    .

    ()

    .

    Inspectors

    Assessment:

    The existing asset register in the CMMS should be completed .

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    43/55

    43

    M 5

    Does the maintenance report include the reasons for failure, proposed

    corrective works and the needed budget?

    References: O&M Egyptian code of wtp chapter 6

    Guidelines:

    Present fault report, work order include fault analysis of faults, cost of repair and

    repair actions.

    Select one of the work orders randomly and make sure that failure reasons are

    documented, budget and the needed actions for repair.

    Visit one of the buildings and ask for operating one of the stand by equipment.

    .

    .

    .

    Inspectors

    Assessment:

    The plant has started applying the maintenance reporting system. The plant is

    still under warranty what prevents the staff to apply the system in all details.

    The AC should make sure that the implementation of it is done and

    accompanied by training.

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    44/55

    44

    M 6

    Are there rehabilitation /maintenance plan of civil works of all structures

    )process structures, civil works, etc. reported regularly to the companys

    management?

    /

    ..

    )

    References:

    O&M Egyptian code of wtp chapter 7

    Guidelines:

    Rehabilitation needs /maintenance plan of civil works of the above units Includes

    tanks, reservoirs, chambers, administration ancillary buildings, landscaped areas,

    irrigation, networks, roads, sidewalk and fences etc

    Check the rehabilitation/maintenance plan and notification of the company with the

    needs.

    During site visit, check landscape, fences, leaks from the treatment units and .etc.

    /

    .

    .

    ...

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    45/55

    45

    M 7

    Do the activities in each maintenance process follow the Standard

    Maintenance Procedure?

    References:

    O&M Egyptian code of wtp chapter 6

    TSM template Nr. M7

    TSMM7

    Guidelines:

    Submit the SMP to all the components of the treatment plant.

    Instructions to available and visible to relevant staff.

    Review the standard maintenance procedures(SMP) are displayed inside every

    compartment or treatment unit during the site visit

    Inspector might ask one of the staff members to check his understanding.

    .

    .

    Inspectors

    Assessment:

    The SMPs are only published in one office and need to be distributed to every

    workstation. Some stations ( Al2SO4) show signs of lack of Maintenance.

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    46/55

    46

    2-3 Compliance Form: QA/QC (Water Treatment Plant)

    Q 1

    Do treatment chemicals (alum) comply with the requirements of the relevant

    Egyptian standard specifications?

    References:

    (Egyptian standards of alum specification)

    (

    )

    TSM template Nr. Q1

    TSMQ1

    Guidelines:

    Submit the standard specifications for the alum and the results of the samples analysisprovided to the plant

    Review the presented documents. Compare results of sample analyses with standard

    specifications.

    .

    .

    .

    InspectorsAssessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    47/55

    47

    Q 2

    Is the water analyzed regularly at the inlet, outlet and after relevant process

    steps complying the Egyptian code?

    References: O&M Egyptian code for WTP chapter 5-1-1&5-3 ---Q2 TSM

    Guidelines:

    Develop sampling program includes the following criteria as a min requirement:

    Sampling locations (inside and outside of the plant) and type.

    Sampling frequency

    Sampling reservation methods.

    Number of samples.

    Analytical standard.

    Locate the sampling points on the plant layout.

    Develop a list of the total monthly samples (conforming non-conforming and the reasons)

    Attach and fix the plant layout with the above data

    Check the plant layout signed with above mentioned data

    Check the samples sheet (comply/non comply)

    Inspector may discuss the results and sampling system to make sure understanding the program

    .

    :

    (

    )

    (

    -)

    .

    (

    )

    .

    .

    (

    )

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    48/55

    48

    Q 3

    Are the lab instruments and glassware are calibrated and maintained

    periodically?

    References: O&M Egyptian code for WTP chapter 5-2 -

    Guidelines:

    Prepare a list of instruments to be calibrated.

    Calibrate instruments internally by standard solution (or based on manufacturer

    instructions)

    Keep calibration certification with the instrument logbook

    Outside calibration done only for all types of thermometers and other devices in national

    institute of calibration or any other specialized companies.

    Keep a piece of calibrated glassware and use it to calibrate the whole glassware in annual

    base.

    Review calibration certificates

    Inspector may discuss the process of calibration during lab visit. Check the list of instruments that need routine calibration

    .

    (

    )

    .

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    49/55

    49

    Q 4Are there identification cart attached to all chemicals and instruments?

    (

    References: Good practices TSM template Nr. Q4

    TSMQ4

    Guidelines:

    Develop, attach and fix ID card for all chemicals and instruments.

    Check IDs.

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    50/55

    50

    Q 5Are raw and produced water analyses results recorded daily and archived?

    References:

    O&M code of wtp chapter 10

    Guidelines:

    Keep daily lab data records for at least 1 year.

    Check daily data and is kept for one year at least.

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    51/55

    51

    6Q

    Are the analyses results, done by other inspectors (Ministry of Health,

    Holding Company and Regulator) are kept and used on the plants level?

    References:

    Instructions of HCWW

    Guidelines:

    Keep last analyses data of any monitoring entities.

    Check analyses reports of other regulators. Compare with plant results.

    Inspectors may discuss in case of conflict with plant results to know remedial actions

    taken.

    .

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    52/55

    52

    Q 7Do you havea log book for each lab instrument?

    References:

    O&M Egyptian code of wtp chapter 5-2

    -

    TSM template Nr. Q7

    TSMQ 7

    Guidelines:

    Prepare a log book for each lab instrument including requested data.

    Check log books during lab visit. Check data recorded. Signing of lab manager.

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    53/55

    53

    8QIs there a registered book for all chemicals, standard solutions and glassware?

    References: GPL O&M Egyptian code of wtp chapter 5

    Guidelines:

    Develop an inventory of all chemicals, buffer solutions and glassware Identify at least

    size, quantities and expire date.

    Check the inventory list (book). Data Recorded. Discuss to prove reliability.

    ()

    .

    /

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    54/55

    54

    Q 9Is the filter media inspected regularly against mud ball

    )

    References:

    O&M Egyptian code of WTP chapter 2-4-5-2

    ---

    TSM template Nr. Q9

    TSMQ9

    Guidelines:

    Test sample of filter media for mud ball content.

    Present test results and action in case of detecting mud balls.

    Check results of analyses in case of mud balls discovered by lab analyses.

    (

    .)

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature

  • 8/3/2019 Naga Aleki

    55/55

    Q 10

    Is there a safety plan to protect chemists against lab common incidences?

    References: Ministerial decree of manpower and immigration no 234/2003

    /

    TSM template NO Q10

    TSMQ10

    Guidelines:

    Develop a plan to protect the staff against common incidences

    Submit a copy of your plan includes:

    Chemical spill

    Fires

    Chemicals burst.

    Protection of the staff from chemicals fumes.

    Safety guide lines and warning signs.

    Storage of chemicals in a safe way

    Fume hood cupboard , air ventilators , eye wash and fire extinguishers, etc Fix the plans in clear places

    Fix and hang fire extinguishers

    :

    - - -

    -

    - -

    ...

    -

    -

    .

    .

    Inspectors

    Assessment:

    Compliance

    Decision:

    Yes

    Signature

    No

    Signature