NAME OF WORK CONSTRUCTION OF 4 NOS BRIDGE AT KHUTRI CANAL OPPOSITE BASTI Amount of Work. Rs: 9,539,000/- CHANARAN, CHAK NO.113/DNB, BRIDGE AT SHAHI WALA CANAL OPPOSITE Earnest Money.Rs: 191,000/- MUDRASSA QARI SHAHBAZ BAJWA, BRIDGE AT SALARI CANAL, CHAK NO.84/DB Time Limit: 06 Months. OPPSITE DERA MALIK AZEEM BOHAR AND BRIDGE AT CHUMMAN WALI CANAL OPPOSITE GRAVEYARD CHAK NO.134/DRB TEHSIL YAZMAN & DISTRICT BAHAWALPUR. Pay item No. or reference to special specification Description of item Quantity in Units Unit of Measurement In figures In Words 1 2 3 4 5 6 7 8 1 -- Bridge at Khutri Canal 756 P.Sft (Per Square feet) 2 -- Bridge at Shahi Wala Canal 644 P.Sft (Per Square feet) 3 -- Bridge at Salari Canal 182 P.Sft (Per Square feet) 4 -- Bridge at Chumman Wali Canal 168 P.Sft (Per Square feet) 1 411-1 to 411-13 . 301-1 & 202-3 Earth work in ordinary soil for embankment all lead and lift i/c ploughing and mixing with blade grade or disc harrow or other suitable equipment and compaction by mechanical means at OMC and dressing to designed section complete in all respect, 95% to 100% maximum modified AASHO dry density. 79.200 %oCft (Thousand Cubic feet) Executive Engineer Highway Division, Bahawalpr BID SCHEDULE Sr. No. Unit Rate ( To be filled in by the contractor) Amount (to be filled in by the contractor)

Upload: others

Post on 17-Apr-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

NAME OF WORK CONSTRUCTION OF 4 NOS BRIDGE AT KHUTRI CANAL OPPOSITE BASTI Amount of Work. Rs: 9,539,000/-

CHANARAN, CHAK NO.113/DNB, BRIDGE AT SHAHI WALA CANAL OPPOSITE Earnest Money.Rs: 191,000/-

MUDRASSA QARI SHAHBAZ BAJWA, BRIDGE AT SALARI CANAL, CHAK NO.84/DB Time Limit: 06 Months.

OPPSITE DERA MALIK AZEEM BOHAR AND BRIDGE AT CHUMMAN WALI CANAL

OPPOSITE GRAVEYARD CHAK NO.134/DRB TEHSIL YAZMAN & DISTRICT BAHAWALPUR.Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

1 -- Bridge at Khutri Canal756

P.Sft (Per

Square feet)

2 -- Bridge at Shahi Wala Canal644

P.Sft (Per

Square feet)

3 -- Bridge at Salari Canal182

P.Sft (Per

Square feet)

4 -- Bridge at Chumman Wali Canal168

P.Sft (Per

Square feet)

1 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

79.200

%oCft

(Thousand

Cubic feet)

Executive Engineer

Highway Division, Bahawalpr

BID SCHEDULE

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

Executive Engineer,Executive Engineer,

NAME OF WORK 1. REHABILITATION OF METALLED ROAD HEAD RAJKAN NEAR AL-NOOR Amount of Work. Rs: 10,372,000/-

HOSPITAL (LENGTH 0.60 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR. Earnest Money.Rs: 207,500/-

Time Limit: 06 Months.

2. CONSTRUCTION OF METALLED ROAD FROM KHUTRIE BANGLOW TO DERA

RA-SHABAN (LENGTH 0.88 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

1. REHABILITATION OF METALLED ROAD HEAD RAJKAN NEAR AL-NOOR

HOSPITAL (LENGTH 0.60 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

1 18.1/401-5.1 Dismantling of exisitng dry brick soling / road edging.

7.38

%Cft

(Hundred

Cubic feet)

2 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

19.680

%oCft

(Thousand

Cubic feet)

3 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 3936

P.Rft

(Per Running

foot)

4 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of

work except gravel and aggregate.

65.60

%Cft

(Hundred

Cubic feet)

5 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including

its operation,fuel and hire charges,etc) cmplete including carriage of

all materials to site of work except bajri/crushed stone aggrgate,using

67 lbs bitumen & 7.50 Cft Bajri 100 Sft area.

196.80

%Sft

(Hundred

Square feet)

ROAD FURNITURE

6 Manufacturing of Rectangular Sign Board Size 4'x6' With Double Post

of G.I Pipe 3" Dia 12' Height Complete Base & Lettering / Symboling

With Diamond Grade Reflective Sheet / Tape (Single Side)

Informatory Board.

1 Each

BID SCHEDULE

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

2. CONSTRUCTION OF METALLED ROAD FROM KHUTRIE BANGLOW TO DERA

RA-SHABAN (LENGTH 0.88 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

1 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

194.052

%oCft

(Thousand

Cubic feet)

2 501-1 to 501-6/501-

6.2

P/L of Sub base course of crushed stone agg: of approved quality and

grade and supply and spreading I/c placing and mixing and

compaction of Sub Base Course material to required depth camber

and grade to achieve 100% maximum modified dry density I/c carriage

of all material to site of work complete in all respect.

147.21

%Cft

(Hundred

Cubic feet)

3 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 5773

P.Rft

(Per Running

foot)

4 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of

work except gravel and aggregate.

147.21

%Cft

(Hundred

Cubic feet)

5 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including

its operation,fuel and hire charges,etc) cmplete including carriage of

all materials to site of work except bajri/crushed stone aggrgate,using

67 lbs bitumen & 7.50 Cft Bajri 100 Sft area.

294.41

%Sft

(Hundred

Square feet)

ROAD STRUCTURE

Construction of 2' Span RCC Slab Culvert 24' Formation 02 Nos.

6 17.1 to 17.5.

402-14.1

Excavation in foundation of building, bridges and other structures,

including dag-belling, dressing, refilling around structure with

excavated earth, watering ramming lead up to one chain and lifts up to

5 ft in ordinary soil.

0.664

%oCft

(Thousand

Cubic feet)

7 20.1/701-18-15 Cement concrete brick or stone ballast 1.5” to 2” gauge, in foundation

and plinth ratio 1:4:8 complete in all respect I/c supply of all material. 5.28

%Cft

(Hundred

Cubic feet)

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

8 21.1 to 21.4/801-

35.1

Pacca brick work ratio 1:4 cement sand mortar complete in all respect

including supply of all material. 7.20

%Cft

(Hundred

Cubic feet)

9 851-5/821-14.2 Fabrication mild steel reinforcement for cement concrete, including

cutting bending laying in position, making joints and fastening,

including cost of binding wire and labour charges for binding of steel

reinforcement (also includes the removal of crust from bars) complete

in all respect.b) Deform bars.

3.96

% Kg

(Hundred Kilo

Gram)

10 20.4/701-18.3 Providing and laying reinforced cement concrete (including pre-

stressed concrete) using coarse sand and screened graded and

washed aggregate in required shape and design including forms,

moulds, shuttering lifting, compacting, curing, rendering, and finishing

exposed surface complete including supply of material ( but excluding

the cost of steel reinforcement its fabrication and placing in position

etc.b) Reinforced cement concrete in roof slabs, beams columns,

lintels, girders and other structural member laid in situ or pre-cast laid

in position or pre-stressed members cast in situ, complete in all

respect. Type “C”( Nominal mix 1:2:4)

162.66

P.Cft

(Per Cubic

foot)

ROAD FURNITURE

11 Manufacturing of Rectangular Sign Board Size 4'x6' With Double Post

of G.I Pipe 3" Dia 12' Height Complete Base & Lettering / Symboling

With Diamond Grade Reflective Sheet / Tape (Single Side)

Informatory Board.

1 Each

The amount of Rs.7,694/- of material received after dismentling of

existing road structure shall be recovered from the contractor

of existing culverts in recpect of the quantity of material.

Executive Engineer

Highway Division, Bahawalpr

Executive Engineer,Executive Engineer,

NAME OF WORK CONSTRUCTION OF METALLED ROAD FROM SUKHAIL ROAD BASTI NIAZI KHAN Amount of Work. Rs: 9,414,000/-

TO BASTI ZAFAR KHAN MOUZA SUKHAIL & CONSTRUCTION OF BRIDGE ON Earnest Money.Rs: 188,500/-

BAHAWAL WAH AT RD 126490 (LENGTH:0.97 KM) Time Limit: 06 Months.

TEHSIL AHMEDPUR EAST & DISTRICT BAHAWALPUR.Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

1 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

197.499

%oCft

(Thousand

Cubic feet)

2 501-1 to 501-6/501-

6.2

P/L of Sub base course of crushed stone agg: of approved quality and

grade and supply and spreading I/c placing and mixing and

compaction of Sub Base Course material to required depth camber

and grade to achieve 100% maximum modified dry density I/c carriage

of all material to site of work complete in all respect.

159.08

%Cft

(Hundred

Cubic feet)

3 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 6363

P.Rft

(Per Running

foot)

4 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of

work except gravel and aggregate.

106.05

%Cft

(Hundred

Cubic feet)

5 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including

its operation,fuel and hire charges,etc) cmplete including carriage of

all materials to site of work except bajri/crushed stone aggrgate,using

67 lbs bitumen & 7.50 Cft Bajri 100 Sft area.

318.16

%Sft

(Hundred

Square feet)

ROAD STRUCTURE

Construction of 2' Span RCC Slab Culvert 24' Formation 08 Nos.

6 17.1 to 17.5.

402-14.1

Excavation in foundation of building, bridges and other structures,

including dag-belling, dressing, refilling around structure with

excavated earth, watering ramming lead up to one chain and lifts up to

5 ft in ordinary soil.

2.656

%oCft

(Thousand

Cubic feet)

BID SCHEDULE

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

7 20.1/701-18-15 Cement concrete brick or stone ballast 1.5” to 2” gauge, in foundation

and plinth ratio 1:4:8 complete in all respect I/c supply of all material. 21.12

%Cft

(Hundred

Cubic feet)

8 21.1 to 21.4/801-

35.1

Pacca brick work ratio 1:4 cement sand mortar complete in all respect

including supply of all material. 28.80

%Cft

(Hundred

Cubic feet)

9 851-5/821-14.2 Fabrication mild steel reinforcement for cement concrete, including

cutting bending laying in position, making joints and fastening,

including cost of binding wire and labour charges for binding of steel

reinforcement (also includes the removal of crust from bars) complete

in all respect.b) Deform bars.

15.84

% Kg

(Hundred Kilo

Gram)

10 20.4/701-18.3 Providing and laying reinforced cement concrete (including pre-

stressed concrete) using coarse sand and screened graded and

washed aggregate in required shape and design including forms,

moulds, shuttering lifting, compacting, curing, rendering, and finishing

exposed surface complete including supply of material ( but excluding

the cost of steel reinforcement its fabrication and placing in position

etc.b) Reinforced cement concrete in roof slabs, beams columns,

lintels, girders and other structural member laid in situ or pre-cast laid

in position or pre-stressed members cast in situ, complete in all

respect. Type “C”( Nominal mix 1:2:4)

650.64

P.Cft

(Per Cubic

foot)

11 Construction of Bridge on Bahawal wah Canal 1.00 Each

ROAD FURNITURE

12 Manufacturing of Rectangular Sign Board Size 4'x6' With Double Post

of G.I Pipe 3" Dia 12' Height Complete Base & Lettering / Symboling

With Diamond Grade Reflective Sheet / Tape (Single Side)

Informatory Board.

1 Each

Executive Engineer

Highway Division, Bahawalpr

NAME OF WORK REHABILITATION OF METALLED ROAD FROM HAJI MUKHTAR BHUTTA MULLAN Amount of Work. Rs: 9,413,000/-

WALI MOUZA LALLU NAICH (LENGTH 1.17 KM) TEHSIL AHMEDPUR EAST Earnest Money.Rs: 188,500/-

& DISTRICT BAHAWALPUR. Time Limit: 06 Months.

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

1 18.1/401-5.1 Dismantling of exisitng dry brick soling / road edging.

142.64

%Cft

(Hundred

Cubic feet)

2 18.1/401-5.1 Dismantling and removing road pavement, etc., including screening

and stacking of byproducts upto one chain lead (30 metre). 116.47

%Cft

(Hundred

Cubic feet)

3 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

240.513

%oCft

(Thousand

Cubic feet)

4 501-1 to 501-6/501-

6.3

Re-Lying sub base course of dismentalled material of Stone

aggregate (received after dismentalling of existing road as sub base

course of specied thickness complete in all respect including breaking

charges to specified size (Stone aggregate) compacted to all respect.

116.47

%Cft

(Hundred

Cubic feet)

5 501-1 to 501-6/501-

6.3

Re-Lying sub base course of dismentalled material of Brick aggregate

(received after dismentalling of existing road as sub base course of

specied thickness complete in all respect including breaking charges

to specified size (Stone aggregate) compacted to all respect.

142.64

%Cft

(Hundred

Cubic feet)

6 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 7852

P.Rft

(Per Running

foot)

7 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of

work except gravel and aggregate.

209.17

%Cft

(Hundred

Cubic feet)

BID SCHEDULE

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

8 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including

its operation,fuel and hire charges,etc) cmplete including carriage of

all materials to site of work except bajri/crushed stone aggrgate,using

67 lbs bitumen & 7.50 Cft Bajri 100 Sft area.

435.61

%Sft

(Hundred

Square feet)

ROAD STRUCTURE

Re-Construction of 2' Span RCC Slab Culvert 24' Formation 01 No.

9 18.1 Dismantling cement concrete plain 1:4:8 complete in all respect.

2.98

%Cft

(Hundred

Cubic feet)

10 18.1 Dismantling cement concrete 1:2:4 complete in all respect. 4.78 %Cft

(Hundred

Cubic feet)

11 17.1 to 17.5.

402-14.1

Excavation in foundation of building, bridges and other structures,

including dag-belling, dressing, refilling around structure with

excavated earth, watering ramming lead up to one chain and lifts up to

5 ft in ordinary soil.

0.332

%oCft

(Thousand

Cubic feet)

12 20.1/701-18-15 Cement concrete brick or stone ballast 1.5” to 2” gauge, in foundation

and plinth ratio 1:4:8 complete in all respect I/c supply of all material. 2.64

%Cft

(Hundred

Cubic feet)

13 21.1 to 21.4/801-

35.1

Pacca brick work ratio 1:4 cement sand mortar complete in all respect

including supply of all material. 3.60

%Cft

(Hundred

Cubic feet)

14 851-5/821-14.2 Fabrication mild steel reinforcement for cement concrete, including

cutting bending laying in position, making joints and fastening,

including cost of binding wire and labour charges for binding of steel

reinforcement (also includes the removal of crust from bars) complete

in all respect.b) Deform bars.

1.98

% Kg

(Hundred Kilo

Gram)

15 20.4/701-18.3 Providing and laying reinforced cement concrete (including pre-

stressed concrete) using coarse sand and screened graded and

washed aggregate in required shape and design including forms,

moulds, shuttering lifting, compacting, curing, rendering, and finishing

exposed surface complete including supply of material ( but excluding

the cost of steel reinforcement its fabrication and placing in position

etc.b) Reinforced cement concrete in roof slabs, beams columns,

lintels, girders and other structural member laid in situ or pre-cast laid

in position or pre-stressed members cast in situ, complete in all

respect. Type “C”( Nominal mix 1:2:4)

81.33

P.Cft

(Per Cubic

foot)

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

ROAD FURNITURE

16 Manufacturing of Rectangular Sign Board Size 4'x6' With Double Post

of G.I Pipe 3" Dia 12' Height Complete Base & Lettering / Symboling

With Diamond Grade Reflective Sheet / Tape (Single Side)

Informatory Board.

1 Each

The amount of Rs.14,521/- of material received after dismentling of

existing road structure shall be recovered from the contractor

of existing culverts in recpect of the quantity of material.

Executive Engineer

Highway Division, Bahawalpr

Executive Engineer,Executive Engineer,

NAME OF WORK 1. CONSTRUCTION OF METALLED ROAD FROM DERA JAM SHABBIR CHAK NO.73/DB Amount of Work. Rs: 16,908,000/-

TO CHAK NO.85/DB COLONY (LENGTH 0.38 KM) TEHSIL YAZMAN Earnest Money.Rs: 338,500/-

& DISTRICT BAHAWALPUR. Time Limit: 06 Months.

2. REPAIR OF METALLED ROAD FROM ADDA 42000 TO CHAK NO.110/DNB

(LENGTH 2.00 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

3. CONSTRUCTION OF METALLED ROAD FROM CHAK NO.117/DB DERA ABDUL GHAFOOR

TO GOVT. PRIMARY SCHOOL CHAK NO.117/DB (LENGTH 1.00 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

1. CONSTRUCTION OF METALLED ROAD FROM DERA JAM SHABBIR CHAK NO.73/DB

TO CHAK NO.85/DB COLONY (LENGTH 0.38 KM) TEHSIL YAZMAN

& DISTRICT BAHAWALPUR.

1 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

86.044

%oCft

(Thousand

Cubic feet)

2 501-1 to 501-6/501-

6.2

P/L of Sub base course of crushed stone agg: of approved quality and

grade and supply and spreading I/c placing and mixing and

compaction of Sub Base Course material to required depth camber

and grade to achieve 100% maximum modified dry density I/c carriage

of all material to site of work complete in all respect.

63.57

%Cft

(Hundred

Cubic feet)

3 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 2493

P.Rft

(Per Running

foot)

4 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of

work except gravel and aggregate.

63.57

%Cft

(Hundred

Cubic feet)

5 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including

its operation,fuel and hire charges,etc) cmplete including carriage of

all materials to site of work except bajri/crushed stone aggrgate,using

67 lbs bitumen & 7.50 Cft Bajri 100 Sft area.

127.13

%Sft

(Hundred

Square feet)

BID SCHEDULE

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

ROAD STRUCTURE

Construction of 2' Span RCC Slab Culvert 24' Formation 02 Nos.

6 17.1 to 17.5.

402-14.1

Excavation in foundation of building, bridges and other structures,

including dag-belling, dressing, refilling around structure with

excavated earth, watering ramming lead up to one chain and lifts up to

5 ft in ordinary soil.

0.664

%oCft

(Thousand

Cubic feet)

7 20.1/701-18-15 Cement concrete brick or stone ballast 1.5” to 2” gauge, in foundation

and plinth ratio 1:4:8 complete in all respect I/c supply of all material. 5.28

%Cft

(Hundred

Cubic feet)

8 21.1 to 21.4/801-

35.1

Pacca brick work ratio 1:4 cement sand mortar complete in all respect

including supply of all material. 7.20

%Cft

(Hundred

Cubic feet)

9 851-5/821-14.2 Fabrication mild steel reinforcement for cement concrete, including

cutting bending laying in position, making joints and fastening,

including cost of binding wire and labour charges for binding of steel

reinforcement (also includes the removal of crust from bars) complete

in all respect.b) Deform bars.

3.96

% Kg

(Hundred Kilo

Gram)

10 20.4/701-18.3 Providing and laying reinforced cement concrete (including pre-

stressed concrete) using coarse sand and screened graded and

washed aggregate in required shape and design including forms,

moulds, shuttering lifting, compacting, curing, rendering, and finishing

exposed surface complete including supply of material ( but excluding

the cost of steel reinforcement its fabrication and placing in position

etc.b) Reinforced cement concrete in roof slabs, beams columns,

lintels, girders and other structural member laid in situ or pre-cast laid

in position or pre-stressed members cast in situ, complete in all

respect. Type “C”( Nominal mix 1:2:4)

162.66

P.Cft

(Per Cubic

foot)

ROAD FURNITURE

11 Manufacturing of Rectangular Sign Board Size 4'x6' With Double Post

of G.I Pipe 3" Dia 12' Height Complete Base & Lettering / Symboling

With Diamond Grade Reflective Sheet / Tape (Single Side)

Informatory Board.

1 Each

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

2. REPAIR OF METALLED ROAD FROM ADDA 42000 TO CHAK NO.110/DNB

(LENGTH 2.00 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

1 18.1/401-5.1 Dismantling of exisitng dry brick soling / road edging.

5.66

%Cft

(Hundred

Cubic feet)

2 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

39.360

%oCft

(Thousand

Cubic feet)

3 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 3018

P.Rft

(Per Running

foot)

4 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of

work except gravel and aggregate.

75.55

%Cft

(Hundred

Cubic feet)

5 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. Of approved quality,including cleaning or

road surface neating and sparaying bajri and rollin wih road roller

(including its operation,fuel and hire charges,etc) cmplete including

carriage of all materials to site of work except bajri/crushed stone

aggrgate,using 67 lbs bitumen & 7.50 Cft Bajri 100 Sft area.

150.88

%Sft

(Hundred

Square feet)

6 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. Of approved quality,including cleaning or

road surface neating and sparaying bajri and rollin wih road roller

(including its operation,fuel and hire charges,etc) cmplete including

carriage of all materials to site of work except bajri/crushed stone

aggrgate,using 35 lbs bitumen & 4.00 Cft Bajri 100 Sft area.

151.54

%Sft

(Hundred

Square feet)

7 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. Of approved quality,including cleaning or

road surface neating and sparaying bajri and rollin wih road roller

(including its operation,fuel and hire charges,etc) cmplete including

carriage of all materials to site of work except bajri/crushed stone

aggrgate,using 32 lbs bitumen & 3.5 Cft Bajri 100 Sft area.

505.12

%Sft

(Hundred

Square feet)

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

ROAD FURNITURE

8 Manufacturing of Rectangular Sign Board Size 4'x6' With Double Post

of G.I Pipe 3" Dia 12' Height Complete Base & Lettering / Symboling

With Diamond Grade Reflective Sheet / Tape (Single Side)

Informatory Board.

1 Each

3. CONSTRUCTION OF METALLED ROAD FROM CHAK NO.117/DB DERA ABDUL GHAFOOR

TO GOVT. PRIMARY SCHOOL CHAK NO.117/DB (LENGTH 1.00 KM) TEHSIL YAZMAN

& DISTRICT BAHAWALPUR.

1 18.1/401-5.1 Dismantling of exisitng dry brick soling / road edging.

43.30

%Cft

(Hundred

Cubic feet)

1 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

229.086

%oCft

(Thousand

Cubic feet)

2 501-1 to 501-6/501-

6.2

P/L of Sub base course of crushed stone agg: of approved quality and

grade and supply and spreading I/c placing and mixing and

compaction of Sub Base Course material to required depth camber

and grade to achieve 100% maximum modified dry density I/c carriage

of all material to site of work complete in all respect.

167.28

%Cft

(Hundred

Cubic feet)

3 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 6691

P.Rft

(Per Running

foot)

4 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of

work except gravel and aggregate.

167.28

%Cft

(Hundred

Cubic feet)

5 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including

its operation,fuel and hire charges,etc) cmplete including carriage of

all materials to site of work except bajri/crushed stone aggrgate,using

67 lbs bitumen & 7.50 Cft Bajri 100 Sft area.

334.56

%Sft

(Hundred

Square feet)

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

ROAD STRUCTURE

Construction of 2' Span RCC Slab Culvert 24' Formation 03 Nos.

6 17.1 to 17.5.

402-14.1

Excavation in foundation of building, bridges and other structures,

including dag-belling, dressing, refilling around structure with

excavated earth, watering ramming lead up to one chain and lifts up to

5 ft in ordinary soil.

0.996

%oCft

(Thousand

Cubic feet)

7 20.1/701-18-15 Cement concrete brick or stone ballast 1.5” to 2” gauge, in foundation

and plinth ratio 1:4:8 complete in all respect I/c supply of all material. 7.92

%Cft

(Hundred

Cubic feet)

8 21.1 to 21.4/801-

35.1

Pacca brick work ratio 1:4 cement sand mortar complete in all respect

including supply of all material. 10.80

%Cft

(Hundred

Cubic feet)

9 851-5/821-14.2 Fabrication mild steel reinforcement for cement concrete, including

cutting bending laying in position, making joints and fastening,

including cost of binding wire and labour charges for binding of steel

reinforcement (also includes the removal of crust from bars) complete

in all respect.b) Deform bars.

5.94

% Kg

(Hundred Kilo

Gram)

10 20.4/701-18.3 Providing and laying reinforced cement concrete (including pre-

stressed concrete) using coarse sand and screened graded and

washed aggregate in required shape and design including forms,

moulds, shuttering lifting, compacting, curing, rendering, and finishing

exposed surface complete including supply of material ( but excluding

the cost of steel reinforcement its fabrication and placing in position

etc.b) Reinforced cement concrete in roof slabs, beams columns,

lintels, girders and other structural member laid in situ or pre-cast laid

in position or pre-stressed members cast in situ, complete in all

respect. Type “C”( Nominal mix 1:2:4)

243.99

P.Cft

(Per Cubic

foot)

ROAD FURNITURE

11 Manufacturing of Rectangular Sign Board Size 4'x6' With Double Post

of G.I Pipe 3" Dia 12' Height Complete Base & Lettering / Symboling

With Diamond Grade Reflective Sheet / Tape (Single Side)

Informatory Board.

1 Each

The amount of Rs.51,055/- of material received after dismentling of

existing road structure shall be recovered from the contractor

of existing culverts in recpect of the quantity of material.

Executive Engineer

Highway Division, Bahawalpr

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

Executive Engineer,Executive Engineer,

NAME OF WORK 1. REHABILITATION OF METALLED ROAD FROM ADDA QAZI WALA PULL TO DERA Amount of Work. Rs: 9,843,000/-

QAZI BASHIR (LENGTH 0.81 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR. Earnest Money.Rs: 197,000/-

Time Limit: 06 Months.

2. REPAIR OF METALLED ROAD FROM CHAK NO.119/DNB TO CHAK NO.120/DNB VIA

GOVT. MIDDLE SCHOOL CHAK NO.120/DNB (LENGTH 1.56 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

1. REHABILITATION OF METALLED ROAD FROM ADDA QAZI WALA PULL TO DERA

QAZI BASHIR (LENGTH 0.81 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

1 18.1/401-5.1 Dismantling of exisitng dry brick soling / road edging.

9.96

%Cft

(Hundred

Cubic feet)

2 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

15.941

%oCft

(Thousand

Cubic feet)

3 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 5314

P.Rft

(Per Running

foot)

4 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of work

except gravel and aggregate.

140.49

%Cft

(Hundred

Cubic feet)

5 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. Of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including

its operation,fuel and hire charges,etc) cmplete including carriage of all

materials to site of work except bajri/crushed stone aggrgate,using 79

lbs bitumen & 9.75 Cft Bajri 100 Sft area.

236.16

%Sft

(Hundred

Square feet)

6 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. Of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including

its operation,fuel and hire charges,etc) cmplete including carriage of all

materials to site of work except bajri/crushed stone aggrgate,using 67

lbs bitumen & 7.50 Cft Bajri 100 Sft area.

67.24

%Sft

(Hundred

Square feet)

ROAD FURNITURE

7 Manufacturing of Rectangular Sign Board Size 4'x6' With Double Post

of G.I Pipe 3" Dia 12' Height Complete Base & Lettering / Symboling

With Diamond Grade Reflective Sheet / Tape (Single Side) Informatory

Board.

1 Each

BID SCHEDULE

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

2. REPAIR OF METALLED ROAD FROM CHAK NO.119/DNB TO CHAK NO.120/DNB VIA

GOVT. MIDDLE SCHOOL CHAK NO.120/DNB (LENGTH 1.56 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

1 18.1/401-5.1 Dismantling of exisitng dry brick soling / road edging.

19.19

%Cft

(Hundred

Cubic feet)

2 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

30.701

%oCft

(Thousand

Cubic feet)

3 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 10234

P.Rft

(Per Running

foot)

4 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of work

except gravel and aggregate.

170.56

%Cft

(Hundred

Cubic feet)

6 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. Of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including

its operation,fuel and hire charges,etc) cmplete including carriage of all

materials to site of work except bajri/crushed stone aggrgate,using 67

lbs bitumen & 7.50 Cft Bajri 100 Sft area.

511.68

%Sft

(Hundred

Square feet)

ROAD FURNITURE

7 Manufacturing of Rectangular Sign Board Size 4'x6' With Double Post

of G.I Pipe 3" Dia 12' Height Complete Base & Lettering / Symboling

With Diamond Grade Reflective Sheet / Tape (Single Side) Informatory

Board.

1 Each

The amount of Rs.30,403/- of material received after dismentling of

existing road structure shall be recovered from the contractor

of existing culverts in recpect of the quantity of material.

Executive Engineer

Highway Division, Bahawalpr

NAME OF WORK CONSTRUCTION OF METALLED ROAD FROM BHINDA ROAD TO BASTI CHAKIR Amount of Work. Rs: 9,414,000/-

KHAN (LENGTH 1.24 KM) TEHSIL AHMEDPUR EAST & DISTRICT BAHAWALPUR. Earnest Money.Rs: 188,500/-

Time Limit: 06 Months.

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

1 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

214.753

%oCft

(Thousand

Cubic feet)

2 501-1 to 501-6/501-

6.2

P/L of Sub base course of crushed stone agg: of approved quality and

grade and supply and spreading I/c placing and mixing and

compaction of Sub Base Course material to required depth camber

and grade to achieve 100% maximum modified dry density I/c carriage

of all material to site of work complete in all respect.

207.98

%Cft

(Hundred

Cubic feet)

3 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 8156

P.Rft

(Per Running

foot)

4 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of

work except gravel and aggregate.

138.65

%Cft

(Hundred

Cubic feet)

5 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including

its operation,fuel and hire charges,etc) cmplete including carriage of

all materials to site of work except bajri/crushed stone aggrgate,using

67 lbs bitumen & 7.50 Cft Bajri 100 Sft area.

415.96

%Sft

(Hundred

Square feet)

ROAD STRUCTURE

Construction of 2' Span RCC Slab Culvert 24' Formation 03 Nos.

6 17.1 to 17.5.

402-14.1

Excavation in foundation of building, bridges and other structures,

including dag-belling, dressing, refilling around structure with

excavated earth, watering ramming lead up to one chain and lifts up to

5 ft in ordinary soil.

0.996

%oCft

(Thousand

Cubic feet)

7 20.1/701-18-15 Cement concrete brick or stone ballast 1.5” to 2” gauge, in foundation

and plinth ratio 1:4:8 complete in all respect I/c supply of all material. 7.92

%Cft

(Hundred

Cubic feet)

BID SCHEDULE

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

8 21.1 to 21.4/801-

35.1

Pacca brick work ratio 1:4 cement sand mortar complete in all respect

including supply of all material. 10.80

%Cft

(Hundred

Cubic feet)

9 851-5/821-14.2 Fabrication mild steel reinforcement for cement concrete, including

cutting bending laying in position, making joints and fastening,

including cost of binding wire and labour charges for binding of steel

reinforcement (also includes the removal of crust from bars) complete

in all respect.b) Deform bars.

5.94

% Kg

(Hundred Kilo

Gram)

10 20.4/701-18.3 Providing and laying reinforced cement concrete (including pre-

stressed concrete) using coarse sand and screened graded and

washed aggregate in required shape and design including forms,

moulds, shuttering lifting, compacting, curing, rendering, and finishing

exposed surface complete including supply of material ( but excluding

the cost of steel reinforcement its fabrication and placing in position

etc.b) Reinforced cement concrete in roof slabs, beams columns,

lintels, girders and other structural member laid in situ or pre-cast laid

in position or pre-stressed members cast in situ, complete in all

respect. Type “C”( Nominal mix 1:2:4)

243.99

P.Cft

(Per Cubic

foot)

ROAD FURNITURE

11 Manufacturing of Rectangular Sign Board Size 4'x6' With Double Post

of G.I Pipe 3" Dia 12' Height Complete Base & Lettering / Symboling

With Diamond Grade Reflective Sheet / Tape (Single Side)

Informatory Board.

1 Each

Executive Engineer

Highway Division, Bahawalpr

Executive Engineer,Executive Engineer,

NAME OF WORK CONSTRUCTION OF METALLED ROAD FROM GHOARI CHOWK TO MAIN GAZAIN Amount of Work. Rs: 16,446,000/-

ABBASI CHWOK VIA BASTI NAZIK GHORI MOUZA SULTAN PUR (LENGTH 1.96 KM) Earnest Money.Rs: 329,000/-

TEHSIL AHMEDPUR EAST & DISTRICT BAHAWALPUR. Time Limit: 06 Months.

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

1 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

402.580

%oCft

(Thousand

Cubic feet)

2 501-1 to 501-6/501-

6.2

P/L of Sub base course of crushed stone agg: of approved quality and

grade and supply and spreading I/c placing and mixing and

compaction of Sub Base Course material to required depth camber

and grade to achieve 100% maximum modified dry density I/c carriage

of all material to site of work complete in all respect.

327.87

%Cft

(Hundred

Cubic feet)

3 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 12858

P.Rft

(Per Running

foot)

4 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of

work except gravel and aggregate.

218.58

%Cft

(Hundred

Cubic feet)

5 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including

its operation,fuel and hire charges,etc) cmplete including carriage of

all materials to site of work except bajri/crushed stone aggrgate,using

67 lbs bitumen & 7.50 Cft Bajri 100 Sft area.

655.74

%Sft

(Hundred

Square feet)

ROAD STRUCTURE

Construction of 2' Span RCC Slab Culvert 24' Formation 09 Nos.

6 17.1 to 17.5.

402-14.1

Excavation in foundation of building, bridges and other structures,

including dag-belling, dressing, refilling around structure with

excavated earth, watering ramming lead up to one chain and lifts up to

5 ft in ordinary soil.

2.988

%oCft

(Thousand

Cubic feet)

7 20.1/701-18-15 Cement concrete brick or stone ballast 1.5” to 2” gauge, in foundation

and plinth ratio 1:4:8 complete in all respect I/c supply of all material. 23.76

%Cft

(Hundred

Cubic feet)

BID SCHEDULE

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

8 21.1 to 21.4/801-

35.1

Pacca brick work ratio 1:4 cement sand mortar complete in all respect

including supply of all material. 32.40

%Cft

(Hundred

Cubic feet)

9 851-5/821-14.2 Fabrication mild steel reinforcement for cement concrete, including

cutting bending laying in position, making joints and fastening,

including cost of binding wire and labour charges for binding of steel

reinforcement (also includes the removal of crust from bars) complete

in all respect.b) Deform bars.

17.82

% Kg

(Hundred Kilo

Gram)

10 20.4/701-18.3 Providing and laying reinforced cement concrete (including pre-

stressed concrete) using coarse sand and screened graded and

washed aggregate in required shape and design including forms,

moulds, shuttering lifting, compacting, curing, rendering, and finishing

exposed surface complete including supply of material ( but excluding

the cost of steel reinforcement its fabrication and placing in position

etc.b) Reinforced cement concrete in roof slabs, beams columns,

lintels, girders and other structural member laid in situ or pre-cast laid

in position or pre-stressed members cast in situ, complete in all

respect. Type “C”( Nominal mix 1:2:4)

731.97

P.Cft

(Per Cubic

foot)

ROAD FURNITURE

11 Manufacturing of Rectangular Sign Board Size 4'x6' With Double Post

of G.I Pipe 3" Dia 12' Height Complete Base & Lettering / Symboling

With Diamond Grade Reflective Sheet / Tape (Single Side)

Informatory Board.

1 Each

Executive Engineer

Highway Division, Bahawalpr

Executive Engineer,Executive Engineer,

NAME OF WORK 1. REPAIR OF METALLED ROAD FROM CHAK NO.141/DRB TO CHAK NO.142/DRB Amount of Work. Rs: 16,305,000/-

(LENGTH 0.50 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR. Earnest Money.Rs: 326,500/-

Time Limit: 06 Months.

2. REPAIR OF METALLED ROAD FROM CHAK NO.22/DRB TO CHAK NO.19/DRB

DERA JAMAL DIN NAICH(LENGTH 3.50 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

3. REPAIR OF METALLED ROAD FROM CHAK NO.39/DNB BIG TO CHAK NO.39/DNB

SMALL (LENGTH 2.00 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

1. REPAIR OF METALLED ROAD FROM CHAK NO.141/DRB TO CHAK NO.142/DRB

(LENGTH 0.50 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

1 18.1/401-5.1 Dismantling of exisitng dry brick soling / road edging.

6.15%Cft (Hundred

Cubic feet)

2 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

9.840

%oCft

(Thousand

Cubic feet)

3 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 3280P.Rft (Per

Running foot)

4 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of

work except gravel and aggregate.

54.67%Cft (Hundred

Cubic feet)

5 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. Of approved quality,including cleaning or

road surface neating and sparaying bajri and rollin wih road roller

(including its operation,fuel and hire charges,etc) cmplete including

carriage of all materials to site of work except bajri/crushed stone

aggrgate,using 67 lbs bitumen & 7.50 Cft Bajri 100 Sft area.

164.00%Sft (Hundred

Square feet)

BID SCHEDULE

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

2. REPAIR OF METALLED ROAD FROM CHAK NO.22/DRB TO CHAK NO.19/DRB

DERA JAMAL DIN NAICH(LENGTH 3.50 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

1 18.1/401-5.1 Dismantling of exisitng dry brick soling / road edging.

6.15%Cft (Hundred

Cubic feet)

2 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

68.880

%oCft

(Thousand

Cubic feet)

3 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 6560P.Rft (Per

Running foot)

4 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of

work except gravel and aggregate.

150.33%Cft (Hundred

Cubic feet)

5 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. Of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including its

operation,fuel and hire charges,etc) cmplete including carriage of all materials

to site of work except bajri/crushed stone aggrgate,using 67 lbs bitumen &

7.50 Cft Bajri 100 Sft area.

328.00%Sft (Hundred

Square feet)

6 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. Of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including its

operation,fuel and hire charges,etc) cmplete including carriage of all materials

to site of work except bajri/crushed stone aggrgate,using 35 lbs bitumen &

4.00 Cft Bajri 100 Sft area.

246.00%Sft (Hundred

Square feet)

7 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. of approved quality,including cleaning or road

surface neating and sparaying bajri and rollin wih road roller (including its

operation,fuel and hire charges,etc) cmplete including carriage of all materials

to site of work except bajri/crushed stone aggrgate,using 32 lbs bitumen & 3.5

Cft Bajri 100 Sft area.

820.00%Sft (Hundred

Square feet)

ROAD FURNITURE

8 Manufacturing of Rectangular Sign Board Size 4'x6' With Double Post

of G.I Pipe 3" Dia 12' Height Complete Base & Lettering / Symboling

With Diamond Grade Reflective Sheet / Tape (Single Side)

Informatory Board.

1 Each

Pay item No. or

reference to special

specification

Description of item Quantity in

Units

Unit of

Measurement

In figures In Words

1 2 3 4 5 6 7 8

Sr.

No.

Unit Rate ( To be filled in by

the contractor)

Amount (to be

filled in by the

contractor)

3. REPAIR OF METALLED ROAD FROM CHAK NO.39/DNB BIG TO CHAK NO.39/DNB

SMALL (LENGTH 2.00 KM) TEHSIL YAZMAN & DISTRICT BAHAWALPUR.

1 18.1/401-5.1 Dismantling of exisitng dry brick soling / road edging.

24.60%Cft (Hundred

Cubic feet)

2 411-1 to 411-13.

301-1 & 202-3

Earth work in ordinary soil for embankment all lead and lift i/c

ploughing and mixing with blade grade or disc harrow or other suitable

equipment and compaction by mechanical means at OMC and

dressing to designed section complete in all respect, 95% to 100%

maximum modified AASHO dry density.

39.360

%oCft

(Thousand

Cubic feet)

3 552-1 to 552-5 Providing and laying road edging of 3" (three inches) wide & 9" (nine

inches) deep brick on end complete in all respect. 13120P.Rft (Per

Running foot)

4 501-1 to 501-6/551-

6.1

P/L of water bound macadum base course of crushed stone agg: of

approved quality and grade and supply and spreading of Stone

screening I/c placing and mixing and compaction of Base Course

material to required depth camber and grade to achieve 100%

maximum modified dry density I/c carriage of all material to site of

work except gravel and aggregate.

218.67%Cft (Hundred

Cubic feet)

5 612-1 to 612-6/612-

7.1

Providing surface treatment to road,including supply of bitumen and

bajri/crushed stone agg. Of approved quality,including cleaning or

road surface neating and sparaying bajri and rollin wih road roller

(including its operation,fuel and hire charges,etc) cmplete including

carriage of all materials to site of work except bajri/crushed stone

aggrgate,using 67 lbs bitumen & 7.50 Cft Bajri 100 Sft area.

656.00%Sft (Hundred

Square feet)

ROAD FURNITURE

6 Manufacturing of Rectangular Sign Board Size 4'x6' With Double Post

of G.I Pipe 3" Dia 12' Height Complete Base & Lettering / Symboling

With Diamond Grade Reflective Sheet / Tape (Single Side)

Informatory Board.

1 Each

The amount of Rs.38,487/- of material received after dismentling of

existing road structure shall be recovered from the contractor

of existing culverts in recpect of the quantity of material.

Executive Engineer

Highway Division, Bahawalpr

Executive Engineer,Executive Engineer,