nasa advisory council presentation...2013/12/09  · nasa advisory council presentation status of...

21
NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration Systems Development December 9, 2013

Upload: others

Post on 21-Feb-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration Systems Development December 9, 2013

Page 2: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

Progress Video

Page 3: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2

EFT-1 flt h/w EM-1 flt h/wProgress to date

Milestones are "complete"milestones unless noted

ESD Summary ScheduleESD Summary ScheduleElement

HEO / ESD

SLS

Booster

Core Stage

ICPS

Orion

Flight Article

GSDO

Veh. Integ. / LaunchOffline Proc. /CCC & Range

12/5C-SRR C-SDR APMC EFT-1

Design-to Sync Build-to Sync

EM-1Uncrewed

3/11MCR

7/19

ASM

3/30

SRR/SDR

5/17Brd reconvene

PDR CDR DCR

9/14

DM-3 BRR PDR CDR QM-1 QM-2 DCR Production

EM-1 H/W(Aft Skirt, RSRMV Seg/Aft Exit Cone)

EM-1 H/WFwd Assy

10/17

ATP SRR/SDR PDR

STA Mfg/Assy/Instrument

Core Stage 1 Mfg/Assy/Integration @ MAF

CDR

STA Struct. Tests

Struct TestStart STA Mfg Cmplt

ProductionDCR

B-2 Test Stand CmpltGreen Run Tests @ SSC

EM-1 H/W

Trade StudiesStart

IssueJFOC

Start Design@ Prime

Production

StartProd EM-1 HW

6/18

PTR 2

11/17

PTR 3 MPCV Synch

DAC-1 POD B/L ERB 1/25

KDP-B APMC

1/30DAC-1K/O ERB

EFT-1 Flt. Art.Ready

Delta PDR (UR) CDR (UR) SAR (UR)

LAS Comp Qual

Design CM AI&T Vehicle on dock at KSC

SM AI&T

11/30

MCR SRR/SDR PDR CDROPI W/C3R

ORDML-VAB

ORDML-PAD

w/C3R ORD

10/3

Pad InfrastructConst start

BasicC&C

MPPF Fac.Construct

ML Struct Mod Start

RPSF Booster Ops

ready

VAB PlatformConst start

Flame Deflect.Const. st.

ML Arm UmbInstall st.

ML/VABV&V cmplt

OPI w/C3RSAR/ORR

ML-VABSAR/ORR

ML-PADw/C3R SAR/ORR

Orion CSM

LV Fwd, LV Aft

LV Core

Integ Ops (EM-1)Transferto Pad

EFT-1 flt h/w EM-1 flt h/wProgress to date

Milestones are "complete"milestones unless noted

Version: 2013-10-31

For comments [email protected]

Page 4: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

Orion EFT-1 Accomplishments Crew Module Propulsion and ECLSS System Assembly

4

Page 5: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

Orion Fully Powered at KSC

5

Page 6: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

Orion EFT-1 Accomplishments Heat Shield Developmental Flight Instrumentation Installation

6

Page 7: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

ORION EFT-1 ACCOMPLISHMENTS Thermal Protection System Tile and Backshell Status

Complete

Complete Complete

11/2/13  

11/2/13  12/21/13  

11/19/13  

1/10/14  

11/19/13  

E

F

A

B

G I

D

H C

A   100%  E   100%  

F   64%  

B 100%   D   100%  

G 100%   I   100%  

H 100%  

C 100%  

96%  

Total  Backshell  

Page 8: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

Paint Applied 8

Paint in Process

Pore Sealer Sanding Primer/Pore Sealer Application

Loading into the Super Guppy

Page 9: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

Arrival at Kennedy Space Center

•  Image placeholder

Page 10: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

EFT-1 Service Module

Page 11: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

Nozzle Ablative Insulation Fit Checks on Flight Nozzles at Stennis Space Center

Core Stage Flight Computers Installed and Almost Ready for Testing

SLS Program Highlights

Completed Painting of the Crew Vehicle Stage Adapter

VAC Foundation – Overall View !Self Propelled Modular Transporter to Support Manufacturing and Assembly of the Core Stage

Page 12: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

SLS Core Stage Manufacturing Commitments Enabled

12 Drawings for 70% of the mass of Core Stage has been released Updated: 10/17/2013

Page 13: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

Weld Tools Operational

Enhanced Robotic Weld Tool (Domes)

Segmented Ring Tool (Rings) Vertical Weld Center (Barrels)

Page 14: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

First Dome Welded at MAF

Page 15: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

GSDO Accomplishments Vehicle Integration & Launch (VIL)

15

CT-­‐1  rolled  out  of  HB  3  and  in  CT  yard  for  tesFng   Removal  of  items  in  AB  compartments  of  ML  Base  

Roller  Assembly  InstallaFon  Work         Flame  Trench/Flame  Deflector  DemoliFon  

Page 16: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration
Page 17: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

2014

17

Page 18: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

Exploration Mission One (EM–1)

Page 19: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

Asteroid Redirect Crewed Mission Overview

Page 20: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

Partners  and  Suppliers  in  America    

Page 21: NASA Advisory Council Presentation...2013/12/09  · NASA Advisory Council Presentation Status of Exploration Systems Development Dan Dumbacher Deputy Associate Administrator for Exploration

•  NASA continues to make great progress with SLS, Orion and GSDO –  SLS preparing for final KDP-C approval Jan 2014 –  GSDO preparing for PDR early 2014 –  Orion on track for EFT-1 in September, 2014

•  SLS, Orion, and GSDO programs remain on track for the first

integrated test flight, Exploration Mission-1.

21

Summary