1 NATIONAL CYCLONE RISK MITIGATION PROJECT PROCUREMENT PLAN (REVISION 0) I. General 1. Project information: Project Name: NATIONAL CYCLONE RISK MITIGATION PROJECT Country: INDIA Project Code: 2. Bank’s approval Date of the procurement Plan : February 26, 2010 3. Date of General Procurement Notice: December 9, 2009 4. Period covered by this procurement plan: 18 months (From January 01, 2010 to June 30, 2011) II. Goods and Works and non-consulting services. 1 a) Procurement Methods and Thresholds Category Method of Procurement Threshold (US$ Equivalent) Works ICB Works estimated to cost more than US$ 5,000,000 NCB Works estimated to cost more than US$ 30,000 and up to US$ 5,000,000 Shopping Goods estimated to cost up to US$ 30,000 Goods (also applicable for non- intellectual services and the services contracted on the basis of performance of measurable physical outputs) ICB Goods estimated to cost more than US$ 500,000 LIB Goods estimated to cost more than US$ 500,000 NCB Goods estimated to cost more than US$ 30,000 and up to US$ 500,000 Shopping Goods estimated to cost up to US$ 30,000 Direct Contracting Proprietary items of lesser value Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 26-Jan-2021

7 views

Category:

Documents


0 download

TRANSCRIPT

  • 1

    NATIONAL CYCLONE RISK MITIGATION PROJECT

    PROCUREMENT PLAN (REVISION 0)

    I. General

    1. Project information:

    • Project Name: NATIONAL CYCLONE RISK MITIGATION PROJECT • Country: INDIA • Project Code:

    2. Bank’s approval Date of the procurement Plan : February 26, 2010

    3. Date of General Procurement Notice: December 9, 2009 4. Period covered by this procurement plan: 18 months (From January 01, 2010 to June 30, 2011)

    II. Goods and Works and non-consulting services. 1 a) Procurement Methods and Thresholds

    Category Method of Procurement Threshold (US$ Equivalent)

    Works ICB Works estimated to cost more than US$ 5,000,000

    NCB Works estimated to cost more than US$ 30,000 and up to US$ 5,000,000

    Shopping Goods estimated to cost up to US$ 30,000

    Goods

    (also applicable for non-intellectual services and the services contracted on the basis of performance of measurable physical outputs)

    ICB Goods estimated to cost more than US$ 500,000

    LIB Goods estimated to cost more than US$ 500,000

    NCB Goods estimated to cost more than US$ 30,000 and up to US$ 500,000

    Shopping Goods estimated to cost up to US$ 30,000

    Direct Contracting Proprietary items

    of lesser value

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    wb350881Typewritten Text54908

  • 2

    1 b) Prior Review Threshold

    Works : USD 5,000,000 Force account- Prior review only Goods: ICB/LIB- USD 500,000 NCB- USD 200,000 Direct Contracting- Prior Review only Services: USD 100,000 (other than consultancy)

    The Procurement under NCB may be done only after satisfying the following NCB conditions : Invitations to bid shall be advertised in at least one widely circulated national daily newspaper, at

    least 30 days prior to the deadline for the submission of bids; No special preference will be accorded to any bidder either for price or for other terms and

    conditions when competing with foreign bidders, state-owned enterprises, small-scale enterprises or enterprises from any given State;

    Except in exceptional circumstances, there will be no negotiations of price with bidders, even with the lowest evaluated bidder.

    Extension of bid validity: (a) for the first request for extension if it is longer than four weeks; and (b) for all subsequent requests for extension irrespective of the period (such concurrence will be considered only in cases of Force Majeure and circumstances beyond the control of the purchaser or employer) will require prior approval by bank.

    Re-bidding: the system of rejecting bids outside a pre-determined margin or ‘bracket ‘of prices shall not be used.

    The two-or-three envelope system will not be used. Rate contracts entered into with DGS & D are not acceptable as substitute for NCB procedures.

    This may be used in lieu of shopping.

    2. Pre-qualification.

    3. Reference to (if any) Project Operational/Procurement Manual: Refer section 5.1 of the Procurement manual of the Project

    4. Any Other Special Procurement Arrangements: None

    5. Procurement Packages with Methods and Time Schedule – Refer attached consolidated Procurement plan

    III. Selection of Consultants 1 a) Selection Methods and Thresholds

    Method of Procurement Threshold (US$ Equivalent)

    Quality and Cost Based selection (‘QCBS’)

    USD 200,000

    Least Cost Selection- (‘LCS’) Based on the specifications of the assignment.

  • 3

    Method of Procurement Threshold (US$ Equivalent)

    (Procurement meeting requirements of Clause 3.6 of the Bank’s guidelines) Contract value less than US $ 200,000.

    Fixed Budget System – (‘FBS’)

    Based on the specifications of Assignment. (Procurement meeting requirements of Clause 3.5 of the Bank’s guidelines) Contract value less than US $ 200,000

    Selection based on Consultants Qualification (‘CQS’)

    Based on the specifications of Assignment. (Procurement meeting requirements of Clause 3.7 and 3.8 of the Bank’s guidelines) Contract value less than US $ 200,000

    Single Source Selection(‘SSS’)

    Based on the specifications of Assignment (if meets requisite criteria) (Selection meeting requirements of Clause 3.9- 3.13 of the Bank’s guidelines)

    Individual Consultants Based on the specifications of Assignment (if meets requisite criteria)

    1 b) Prior Review Threshold

    Consultancy Services: > US$ 100,000 for firms; and > US$ 50,000 equivalent for individuals

    All Single Source Selections (SSS) should be prior cleared with Bank.

    2. Short list comprising entirely of national consultants: Short list of consultants for services, estimated to cost less than $ 500,000 equivalent per contract, may comprise entirely of national consultants in accordance with the provisions of paragraph 2.7 of the Consultant Guidelines.

    3. Any Other Special Selection Arrangements: .None 4. Reference to (if any) Project Operational/Procurement Manual – Refer section 5.2 of the

    Procurement manual of the Project

    5. Consultancy Assignments with Selection Methods and Time Schedule – Refer attached consolidated Procurement plan

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    1 of 15

    Procurement Plan for Component B Country: IndiaReceipentProject: (Values in Millions)

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    Orissa

    622.80 12.84

    1 7.98 0.16 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    2 17.03 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    2 17.87 0.37 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    2 17.18 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 27-May-11 23-Nov-11 21-Feb-12RevisedActual

    2 14.11 0.29 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    2 16.52 0.34 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    2 17.07 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    2 16.00 0.33 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    2 17.40 0.36 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    2 15.85 0.33 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    1 8.68 0.18 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    2 15.42 0.32 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    1 5.88 0.12 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    2 15.75 0.32 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 28-Jan-12 27-Apr-12RevisedActual

    1 8.07 0.17 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    1 7.80 0.16 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    2 17.15 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    2 16.35 0.34 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    1 8.47 0.17 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12

    Government of India, Ministry of Home Affairs

    Dist: Balasore

    1 NCRMP/OR/BLS/CS/01

    2 NCRMP/OR/BLS/CS/02

    Kuruda and Kochiakoili of Bahanaga Block, Balasore District

    7

    Rural Development Department,Govt of

    OrissaBajana and Gandhiana of Bahanaga Block, Balasore District

    NCB

    Bishnupur of Bahanaga Block, Balasore District

    NCB

    Rural Development Department,Govt of

    Orissa

    5 NCRMP/OR/BLS/CS/05Ikadapal and Bishnupur of Baliapal Block, Balasore District

    NCB

    4 NCRMP/OR/BLS/CS/04

    Odasala and Nuapu of Bahanaga Block, Balasore District

    NCB

    3 NCRMP/OR/BLS/CS/03

    Rural Development Department,Govt of

    Orissa

    12 NCRMP/OR/BLS/CS/12

    Maharajpur and Mahamadabad of Remuna Block, Balasore District

    NCB

    11 NCRMP/OR/BLS/CS/11Jalapahi (Bhogarai) of Bhogarai Block, Balasore District

    NCB

    Badakia and Jayadevkasba of Balasore Sadar District, Balasore District

    NCB

    Gopinathpur and Parakhi of Balasore Sadar Block, Balasore District

    NCB

    Rural Development Department,Govt of

    Orissa

    Binjha of Balasore Sadar Block, Balasore District

    NCB

    Rural Development Department,Govt of

    OrissaRural Development Department,Govt of

    Orissa

    Panchupada and Alumeda of Balasore Sadar Block, Balasore District

    NCB

    Sarthabindha of Balasore Sadar Block, Balasore District

    NCB

    Rural Development Department,Govt of

    Orissa

    18 NCRMP/OR/BLS/CS/18

    NCRMP/OR/BL

    National Cyclone Risk Mitigation

    Orissa- Cyclone shelters-Orissa- Cyclone Shelters- Total

    Rural Development Department,Govt of

    Orissa

    Aunladiha and Dagara of Baliapal Block, Balasore District

    NCB

    Rural Development Department,Govt of

    Orissa

    Bisikadeipur and Govindapur of Baliapal Block, Balasore District

    NCB

    NCB

    NCRMP/OR/BLS/CS/099

    NCRMP/OR/BLS/CS/07

    8

    Rural Development Department,Govt of

    Orissa

    6 NCRMP/OR/BLS/CS/06Pakmundi and Surahida of Baliapal Block, Balasore District

    NCB

    Rural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    Deula and Kunduli of Baliapal Block, Balasore District

    NCB

    10 NCRMP/OR/BLS/CS/10

    Rural Development Department,Govt of

    Orissa

    Gotadiha and Kainagiri of Basta Block, Balasore District

    NCB

    NCRMP/OR/BLS/CS/08

    Rural Development Department,Govt of

    Orissa

    13 NCRMP/OR/BLS/CS/13Mandagaon of Remuna Block, Balasore District

    NCBRural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    15 NCRMP/OR/BLS/CS/15

    14 NCRMP/OR/BLS/CS/14

    17 NCRMP/OR/BLS/CS/17

    Rural Development Department,Govt of

    Orissa

    16 NCRMP/OR/BLS/CS/16

    Rural Development

    Hidigaon of Balasore Sadar

    NCB

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    2 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    RevisedActual

    2 16.97 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    1 8.27 0.17 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    2 14.50 0.30 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 31-Dec-11 30-Mar-12RevisedActual

    1 7.60 0.16 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    2 14.41 0.30 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    1 7.22 0.15 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    2 16.87 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    2 15.44 0.32 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 31-Dec-11 30-Mar-12RevisedActual

    1 7.45 0.15 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 31-Dec-11 30-Mar-12RevisedActual

    1 7.00 0.14 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    1 8.33 0.17 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    2 14.56 0.30 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    1 8.23 0.17 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    2 15.46 0.32 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 31-Dec-11 30-Mar-12RevisedActual

    1 9.29 0.19 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    1 8.56 0.18 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    2 16.44 0.34 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    2 12.60 0.26 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 2-Mar-10 3-Mar-10 3-Apr-10 3-May-10 31-May-10 1-Jun-10 28-Mar-11 25-Aug-11 23-Nov-11RevisedActual

    1 8.47 0.17 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    2 16.13 0.33 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 28-Jan-12 27-Apr-12RevisedActual

    3 24.74 0.51 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 28-Jan-12 27-Apr-12RevisedActual

    3 22.71 0.47 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 30-Mar-12 28-Jun-12

    19 NCRMP/OR/BLS/CS/19

    Artung of Basudevpur Block, Bhadrak District

    NCB

    Rural Development Department,Govt of

    Orissa

    NCB27 NCRMP/OR/BHK/CS/07

    24

    Sunaripokhari of Chandbali Block, Bhadrak District

    NCB

    Ankapada and Biriadia of Chandbali Block, Bhadrak District

    NCB26

    NCB

    NCBNCRMP/OR/GJM/CS/01

    Lunguri of Ganjam Block, Ganjam District

    NCRMP/OR/BHK/CS/06

    Nachhipur and Utarasahi of Chandbali Block, Bhadrak District

    Rural Development Department,Govt of

    Orissa

    NCB

    Rural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    Dist: Kendrapara

    30 NCRMP/OR/GJM/CS/02

    Dist: Jagatsinghpur

    31 NCRMP/OR/JSP/CS/01

    32 NCRMP/OR/JSP/CS/02

    Pokharia of Rajnagar Block, Kendrapara District

    NCB

    Gaudasahi (Bhuan), Badatara and Bangara of Gop Block, Puri District

    NCB

    Madhupur and Sahana of Astaranga Block, Puri District

    NCB

    NCBKendrapati and Bantilo of Astaranga Block, Puri District

    NCB

    35 NCRMP/OR/KPD/CS/03

    38 NCRMP/OR/PUR/CS/03

    Dist: Puri

    36 NCRMP/OR/PUR/CS/01

    37

    NCRMP/OR/BHK/CS/04

    25 NCRMP/OR/BHK/CS/05

    NCB

    NCRMP/OR/BHK/CS/01

    Dist: Bhadrak

    23 NCRMP/OR/BHK/CS/03Kaduanasi of Chandbali Block, Bhadrak District

    21

    Department,Govt of

    Orissa

    20 NCRMP/OR/BLS/CS/20Pakhar and Tentei of Soro Block, Balasore District

    NCBRural Development Department,Govt of

    Orissa

    Hidigaon of Balasore Sadar Block, Balasore District

    NCB

    22 NCRMP/OR/BHK/CS/02Balarampur and Khedualpur of Basudevpur, Bhadrak District

    NCB

    Rural Development Department,Govt of

    OrissaRural Development Department,Govt of

    Orissa

    Barakolha and Jantuali of Chandbali Block, Bhadrak District.

    Rural Development Department,Govt of

    Orissa

    NCB

    Rural Development Department,Govt of

    Orissa

    Kankan of Erasama Block, Jagatsinghpur District

    NCB

    28

    Rural Development Department,Govt of

    Orissa

    Samantarapur and Kusupur of Balikuda Block, Jagatsinghpur District

    NCB

    Dist: Ganjam

    29

    Rajapur of Ganjam Block, Ganjam District

    Baliarpur of Chandbali Bloc, Bhadrak District

    NCRMP/OR/BHK/CS/08

    Kajalabandha and Bilikana of Patamundai Block, Kendrapara District

    NCB

    34 NCRMP/OR/KPD/CS/02Satakuria of Patamundai Block, Kendrapara District

    NCB

    33 NCRMP/OR/KPD/CS/01

    Rural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    OrissaRural Development Department,Govt of

    OrissaRural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    NCRMP/OR/PUR/CS/02

    Rural Development Department,Govt of

    Orissa

    39 NCRMP/OR/PUR/CS/04Palanka and Chapamanik of Brahmagiri Block, Puri District

    NCBRural Development Department,Govt of

    Orissa

    Kahalapada of Brahmagiri Block, Puri District

    Rural Development Department,Govt of

    Orissa

    NCRMP/OR/PU Kanthijhadi, Kundish and

    NCBRural Development

    40 NCRMP/OR/PUR/CS/05

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    3 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    RevisedActual

    3 20.83 0.43 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 30-Mar-12 28-Jun-12RevisedActual

    2 17.09 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-Jul-10 8-Jul-10 9-Aug-10 8-Sep-10 6-Oct-10 7-Oct-10 4-Jun-11 31-Dec-11 30-Mar-12RevisedActual

    2 16.60 0.34 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    1 8.84 0.18 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    2 17.61 0.36 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 2-Jun-11 30-Oct-11 28-Jan-12RevisedActual

    78 622.80 12.84

    Total cost 545.42 11.25

    3 14.85 0.31 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    1 25.42 0.52 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual

    2 27.24 0.56 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    2 46.80 0.96 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual

    5 40.60 0.84 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    1 23.62 0.49 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual

    4 45.57 0.94 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    3 15.86 0.33 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual

    3 6.45 0.13 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    6 10.91 0.22 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    1 24.64 0.51 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    1 38.22 0.79 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual

    2 28.50 0.59 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual

    2 24.79 0.51 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual

    6 5.3980 0.11 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    1 25.24 0.52 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12Revised

    42 NCRMP/OR/PUR/CS/07

    Dhanitri, Runkei and Sukapokhari-Jaleswarpada of Kakatpur Block, Puri District

    NCBRural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa43 NCRMP/OR/PUR/CS/08

    Orissa- CS- Total

    Orissa- Approach Roads- TotalDist: Balasore

    45 NCRMP/OR/PUR/CS/10

    44 NCRMP/OR/PUR/CS/09

    1 NCRMP/OR/BLS/AR/01

    Bishnupur, Gandhiana and Odasala of Bahanaga Block, Balasore District

    NCB

    2 NCRMP/OR/BLS/AR/02Pakhar of Soro Block, Balasore District

    NCB

    Rural Development Department,Govt of

    Orissa11 Kaduanasi of Chandbali Block, Bhadrak District

    NCBNCRMP/OR/BHK/AR/02

    Rural Development Department,Govt of

    Orissa

    15 NCRMP/OR/BHK/AR/06

    Dosinga & Kaithakola of Chandbali Block and Nuagaon, Bachhada, Padhuan &

    NCBRural Development Department,Govt of

    Orissa

    NCRMP/OR/BHK/AR/05

    Khedualpur and Balarampur of Basudevpur Block, Bhadrak District

    Rural Development Department,Govt of

    Rajapur of Ganjam Block, Ganjam District

    NCB

    41 NCRMP/OR/PUR/CS/06

    Sarada of Gop Block, Puri District

    NCB

    Department,Govt of Orissa

    Gomundia and Jenapur of Krushnaprasad Block, Puri District

    NCBRural Development Department,Govt of

    Orissa

    Bajrakote and Budhibara of Krushnaprasad Block, Puri District

    NCB

    Rural Development Department,Govt of

    Orissa

    46 NCRMP/OR/PUR/CS/11

    Rural Development Department,Govt of

    Orissa

    Jamarsuan of Puri Sadar Block, Puri District

    NCB

    Kantasil and Rendua of Puri Sadar Block, Puri District

    NCB

    NCRMP/OR/BLS/AR/055

    4 NCRMP/OR/BLS/AR/04Binjha and Alumeda of Balasore Sadar Block, Balasore District

    Panchapada, Parakhi & Gopinathpurof Balasore Sadar Block and Gotadiha & Kainagiri

    NCB

    3 NCRMP/OR/BLS/AR/03Ikadapal and Bishnupur of Baliapal block, Balasore District

    NCBRural Development Department,Govt of

    OrissaRural Development Department,Govt of

    OrissaRural Development Department,Govt of

    Orissa

    NCB

    NCBRural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    NCRMP/OR/BLS/AR/07

    6 NCRMP/OR/BLS/AR/06Sarthabindha of Balasore Sadar Block, Balasore District

    NCB

    8 NCRMP/OR/BLS/AR/08NCB

    Dist: Bhadrak

    10 NCRMP/OR/BHK/AR/01

    Ankapada, Biriadia, Sunaripokhari, Barakhola & Jantuali of Chandbali Block and

    NCB

    7

    Chaumukh of Baliapal Block and Krushnanagar & Bichitrapur of Bhogarai Block, Balasore

    NCB9 NCRMP/OR/BLS/AR/09

    Jayadevkasba of Balasore Sadar Block and Mahamadabad, Maharajpur &

    Rural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    Talapada of Remuna Block and Maharudrapur & Barajdeuli of Bahanaga Block, Balasore

    Rural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    13 NCRMP/OR/BHK/AR/04

    Nachhipur and Utarasahi of Chandbali Block, Bhadrak District

    NCBRural Development Department,Govt of

    Orissa

    12 NCRMP/OR/BHK/AR/03

    NCB

    Dist: Ganjam

    14

    Baliarpur of Chandbali Block, Bhadrak District

    NCB

    16 NCRMP/OR/GJM/AR/01

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    4 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    Actual

    3 40.73 0.84 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    4 2.48 0.05 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual

    2 38.79 0.80 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    3 3.71 0.08 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    2 17.00 0.35 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual

    2 13.59 0.28 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 7-May-10 8-May-10 8-Jun-10 8-Jul-10 5-Aug-10 6-Aug-10 3-Apr-11 28-Jan-12 27-Apr-12RevisedActual

    1 12.09 0.25 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    2 6.83 0.14 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    3 6.11 0.13 Appraisal 20-Aug-09 24-Nov-09 2-Dec-09 22-Dec-09 8-Mar-10 9-Mar-10 9-Apr-10 10-May-10 7-Jun-10 8-Jun-10 4-Apr-11 30-Nov-11 28-Feb-12RevisedActual

    65 545.42 11.25Orissa Total 1168.22 24.09

    Andhra PradeshAndhra Pradesh- Cyclone shelters

    455.70 9.40

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    8 63.10 1.30

    Appraisal 1-Oct-09 11-Oct-09 30-Nov-09 15-Dec-09 5-Mar-10 6-Mar-10 6-Apr-10 6-May-10 3-Jun-10 4-Jun-10 15-Apr-11 24-Feb-12 24-May-12 Revised

    Actual

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    5 40.65 0.84

    Appraisal 1-Oct-09 11-Oct-09 30-Nov-09 15-Dec-09 5-Mar-10 6-Mar-10 6-Apr-10 6-May-10 3-Jun-10 4-Jun-10 1-Dec-10 30-May-11 28-Aug-11 Revised

    Actual

    Construction of D type cyclone shelter in Idduvanipelam, Srikakulam district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 9.59 0.20

    Appraisal 2-Oct-09 12-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of C type cyclone shelter in Gollavooru, Srikakulam district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 10.08 0.21

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of four cyclone shelters in Vajrapukothuru mandal, Srikakulam district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    4 33.82 0.70

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Madhupur of Astaranga, Puri District

    NCB

    25 NCRMP/OR/PUR/AR/05

    Gopinathpur, Malud and Nuapada of Krushnaprasad Block, Puri District

    3

    4

    5

    1Construction of eight cyclone shelters in Kavali mandal, Nellore District

    NCRMP/B-W/AP/MPCS/PRED/09/Kavali/

    003

    NCRMP/B-W/AP/MPCS/PRED/01/Kaviti/0

    01

    NCRMP/B-W/AP/MPCS/PRED/01/V.Koth

    uru/004

    NCRMP/B-W/AP/MPCS/PRED/01/Sompet

    a/002

    2

    NCRMP/B-W/AP/MPCS/PRED/01/V.Koth

    uru/003

    Construction of five cyclone shelters in Vajrapukothuru mandal, Srikakulam District

    Andhra Pradesh- Cyclone

    Orissa

    Ganjam District

    Rural Development Department,Govt of

    Orissa

    NCB

    Kankana of Erasama Block and Samantarapur & Kusupur of Balikuda Block, Jagatsinghpur

    NCB

    Dist: Jagatsinghpur

    M/AR/01

    Rural Development Department,Govt of

    Orissa

    17 NCRMP/OR/JSP/AR/01

    18 NCRMP/OR/JSP/AR/02

    Nuagarh, Fatepur & Nimidihi of Kujanga Block and Naradia of Erasama Block, Jagatsinghpur

    NCB

    Dist: Kendrapara

    19 NCRMP/OR/KPD/AR/01

    Satakudia of Patamundai Block and Pokharia of Rajnagar Block, Kendrapara District

    Rural Development Department,Govt of

    Orissa

    20 NCRMP/OR/KPD/AR/02

    Sana Rahama of Mahakalapada Block and Nuagaon & Badanaukana of Rajnagar

    NCBRural Development Department,Govt of

    Orissa

    NCB

    Dist: Puri

    21 NCRMP/OR/PUR/AR/01

    Gomundia and Jenapur of Krushnaprasad Block, Puri District

    Orissa- Roads- Total

    NCRMP/OR/PUR/AR/02

    Kahalapada and Chapamanik of Brahmagiri Block, Puri District

    Rural Development Department,Govt of

    Orissa

    24 NCRMP/OR/PUR/AR/04Kanthijhadi and Badatara of Gop Block, Puri District

    NCB

    Rural Development Department,Govt of

    Orissa

    Rural Development Department,Govt of

    Orissa

    23 NCRMP/OR/PUR/AR/03

    Rural Development Department,Govt of

    Orissa

    NCBRural Development Department,Govt of

    Orissa

    22 NCB

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    5 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    Construction of two cyclone shelters in Santhabommali mandal, Srikakulam district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    2 20.96 0.43

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of three cyclone shelters in Gara mandal, Srikakulam district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    3 26.64 0.55

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of A type cyclone shelter in Ragupalem, Srikakulam district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 7.24 0.15

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of A type cyclone shelter in Kommaravanipeta, Srikakulam district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 7.02 0.14

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of three cyclone shelters in Ranasthalam mandal, Srikakulam district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    3 23.81 0.49

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of A type cyclone shelter in Moosavanipeta, Srikakulam district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 7.43 0.15

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of two cyclone shelters in Pusapatirega, Vizianagaram district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    2 14.70 0.30

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of A type cyclone shelters in Thotapalli, Vizianagaram district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 7.02 0.14

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of C type cyclone shelter in Tikkavanipalem, Vishakhapatnam district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 10.02 0.21

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of three cyclone shelters in Nakkapalli mandal, Vishakhapatnam district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    3 27.07 0.56

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of two cyclone shelters in Payakaraopeta mandal, Vishakhapatnam district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    2 14.83 0.31

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of B type cyclone shelter in Venkayyapalem, Vishakhapatnam district

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 7.70 0.16

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11Revised

    11

    12

    13

    14

    15

    16

    6

    7

    8

    9

    10

    17

    NCRMP/B-W/AP/MPCS/PRED/01/Etcherl

    a/010

    NNCRMP/B-W/AP/MPCS/PRED/01/Ranast

    halam/008

    NCRMP/B-W/AP/MPCS/PRED/01/Gara/0

    06

    NCRMP/B-W/AP/MPCS/PRED/01/Ranast

    halam/009

    NCRMP/B-W/AP/MPCS/PRED/01/Santha

    bommali/005

    NCRMP/B-W/AP/MPCS/PRED/01/Laveru/

    007

    NCRMP/B-W/AP/MPCS/PRED/02/Bhogap

    uram/002

    NCRMP/B-W/AP/MPCS/PRED/03/Parava

    da/001

    NCRMP/B-W/AP/MPCS/PRED/02/Pusapa

    tirega/001

    NCRMP/B-W/AP/MPCS/PRED/03/Nakkap

    alli/002

    NCRMP/B-W/AP/MPCS/PRED/03/Rambill

    i/004

    NCRMP/B-W/AP/MPCS/PRED/03/Payaka

    raopeta/003

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    6 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    Actual

    Construction of two cyclone shelters in Thondangi mandal, East Godavari District

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    2 14.59 0.30

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of C type cyclone shelter in Pedaraghavulupeta, East Godavari District

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 10.09 0.21

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of two cyclone shelters in Nizampatnam mandal, Guntur District

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    2 17.48 0.36

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of B type cyclone shelter in Mollagunta, Guntur District

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 7.41 0.15

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of D type cyclone shelter in Chakicherla, Prakasam District

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 9.97 0.21

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of B type cyclone shelter in Pakala Main, Prakasam District

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 7.19 0.15

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    NCB AppraisalRevisedActual

    Construction of B type cyclone shelter in Thopupalem Kanuparthy, Prakasam District

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 7.19 0.15

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of B type cyclone shelters in Epuru Pattapupalem, Nellore District

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 7.84 0.16

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of three cyclone shelters in Bogole mandal, Nellore District

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    3 28.25 0.58

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of two cyclone shelters in Vidavalur mandal, Nellore District

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    2 14.03 0.29

    Appraisal 3-Oct-09 13-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Andhra Pradesh- Cyclone shelters- Total 55 455.70 9.40

    Andhra Pradesh- Roads1036.52 21.37

    21

    22

    23

    24

    NCRMP/B-W/AP/MPCS/PRED/09/Vidaval

    ur/004

    19

    20

    18

    27

    NCRMP/B-W/AP/MPCS/PRED/04/Uppala

    guptha/002

    NCRMP/B-W/AP/MPCS/PRED/09/Bogole/

    002

    NCRMP/B-W/AP/MPCS/PRED/09/Muthuk

    ur/001

    NCRMP/B-W/AP/MPCS/PRED/08/Ulavap

    adu/001

    NCRMP/B-W/AP/MPCS/PRED/04/Thonda

    ngi/001

    NCRMP/B-W/AP/MPCS/PRED/07/Nizamp

    atnam/001

    Andhra Pradesh- Roads-

    NCRMP/B-W/AP/MPCS/PRED/07/Repalle

    /002

    NCRMP/B-W/AP/MPCS/P

    RED/08/S. Konda/002

    NCRMP/B-W/AP/MPCS/PRED/08/N.G.

    Padu/003

    25

    26

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    7 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    Construction of road to habitation from Gumpam to Puligeddapalem (via) Palanki, Vizianagaram District

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 25.89 0.53

    Appraisal

    3-Oct-09 13-Oct-09 30-Nov-09 15-Dec-09 5-Mar-10 6-Mar-10 6-Apr-10 6-May-10 3-Jun-10 4-Jun-10 1-Dec-10 28-Aug-11 26-Nov-11RevisedActual

    Construction of roads to habitations in Talasamudram mandal, Srikakulam District

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    3 22.86 0.47

    Appraisal

    3-Oct-09 13-Oct-09 30-Nov-09 15-Dec-09 5-Mar-10 6-Mar-10 6-Apr-10 6-May-10 3-Jun-10 4-Jun-10 1-Dec-10 28-Aug-11 26-Nov-11RevisedActual

    Construction of roads to cyclone shelters in Srikakulam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    4 13.46 0.28

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Srikakulam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    4 16.60 0.34

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Srikakulam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    5 12.80 0.26

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Srikakulam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 5.66 0.12

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Srikakulam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    5 16.94 0.35

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Vizianagaram

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    6 11.43 0.24

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Vishakhapatnam

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    2 5.38 0.11

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Vishakhapatnam

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    4 20.65 0.43

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Vishakhapatnam

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    2 9.69 0.20

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in East Godavari

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 6.52 0.13

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11Revised

    3

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/00

    6

    NCRMP/B-W/AP/RHB/PRED/02/Pusapati

    rega/001

    NCRMP/B-W/AP/RCS/PRED/01/V.Kottur

    u/002

    NCRMP/B-W/AP/RCS/PRED/01/Santhab

    ommali/003

    NCRMP/B-W/AP/RCS/PRED/01/V.Kottur

    u/001

    1

    5

    4

    2

    NCRMP/B-W/AP/RCS/PRED/03/Nakkapal

    li/003

    NCRMP/B-W/AP/RCS/PRED/01/Polaki/00

    4

    NCRMP/B-W/AP/RCS/PRED/01/Etcherla/

    005

    NCRMP/B-W/AP/RCS/PRED/02/Bhogapu

    ram/001

    NCRMP/B-W/AP/RCS/PRED/03/Anandap

    uram/001

    NCRMP/B-W/AP/RCS/PRED/03/Rambilli/

    002

    NCRMP/B-W/AP/RCS/PRED/04/Karapa/0

    01

    6

    7

    8

    9

    10

    11

    12

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    8 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    Actual

    Construction of roads to cyclone shelters in East Godavari

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    2 5.53 0.11

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in East Godavari

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    1 1.36 0.03

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in East Godavari

    NCBPanchayati Raj

    Engineering Department (NABARD), Govt of AP

    6 14.59 0.30

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Krishna NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    4 15.49 0.32

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Srikakulam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    6 19.79 0.41

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Srikakulam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    4 17.04 0.35

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Srikakulam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    3 16.37 0.34

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Srikakulam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 9.94 0.20

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Srikakulam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 7.29 0.15

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Vizianagaram NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 10.27 0.21

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Vizianagaram NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 8.64 0.18

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Vishakhapatnam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 16.25 0.33

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11

    23

    24

    NCRMP/B-W/AP/RHB/PRED/01/Santhab

    ommali/001

    NCRMP/B-W/AP/RCS/PR

    ED/04/U. Kothapalli/002

    NCRMP/B-W/AP/RCS/PRED/04/Uppalag

    uptham/003

    NCRMP/B-W/AP/RHB/PRED/02/Bhogapu

    ram/003

    NCRMP/B-W/AP/RHB/PRED/01/Santhab

    ommali/002

    NCRMP/B-W/AP/RHB/PRED/01/Santhab

    ommali/003

    NCRMP/B-W/AP/RHB/PRED/02/Pusapati

    rega/002

    NCRMP/B-W/AP/RHB/PRED/01/Kavity/00

    4

    NCRMP/B-W/AP/RCS/PRED/04/Thondan

    gi/004

    NCRMP/B-W/AP/RCS/PRED/06/Machilipa

    tnam/001

    NCRMP/B-W/AP/RHB/PRED/01/Polaki/00

    5

    NCRMP/B-W/AP/RHB/PRED/03/Nakkapal

    li/001

    14

    15

    16

    13

    22

    17

    18

    19

    20

    21

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    9 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    RevisedActual

    Construction of roads to habitations in Vishakhapatnam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 7.81 0.16

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Vishakhapatnam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 5.30 0.11

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Vishakhapatnam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 9.05 0.19

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Vishakhapatnam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    3 13.18 0.27

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Vishakhapatnam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 11.18 0.23

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Vishakhapatnam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 7.55 0.16

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in East Godavari NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 6.23 0.13

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in East Godavari NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 4.46 0.09

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in East Godavari NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 10.68 0.22

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in East Godavari NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    4 19.58 0.40

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in West Godavari NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    5 21.48 0.44

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    32

    33

    27

    28

    29

    NCRMP/B-W/AP/RHB/PRED/03/Rambilli/

    006

    li/001

    NCRMP/B-W/AP/RHB/PRED/03/Nakkapal

    li/002

    NCRMP/B-W/AP/RHB/PRED/03/Anandap

    uram/003

    NCRMP/B-W/AP/RHB/PRED/03/Paravada

    /004

    NCRMP/B-W/AP/RHB/PRED/03/Payakara

    opeta/005

    NCRMP/B-W/AP/RHB/PRED/04/Tallarevu

    /002

    NCRMP/B-W/AP/RHB/PRED/04/Katreni

    kona/003

    NCRMP/B-W/AP/RHB/PRED/03/Atchutap

    uram/007

    NCRMP/B-W/AP/RHB/PRED/04/Karapa/0

    01

    NCRMP/B-W/AP/RHB/PR

    ED/04/U. Kothapalli/004

    NCRMP/B-W/AP/RHB/PRED/05/Mogaltur/

    001

    25

    26

    30

    34

    35

    31

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    10 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    Construction of roads to habitations in West Godavari NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    3 15.71 0.32

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in West Godavari NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 11.46 0.24

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Krishna NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 15.46 0.32

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Krishna NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    3 9.07 0.19

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Krishna NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 5.79 0.12

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Guntur NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    3 13.48 0.28

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Guntur NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    5 16.73 0.34

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Guntur NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    3 8.41 0.17

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Guntur NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    3 5.82 0.12

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Prakasam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    5 14.79 0.30

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Prakasam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 5.88 0.12

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Prakasam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 8.55 0.18

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11Revised

    NCRMP/B-W/AP/RCS/PR

    ED/07/PV Palem/001

    NCRMP/B-W/AP/RHB/PRED/05/Narsapur

    /002

    NCRMP/B-W/AP/RHB/PRED/05/Kalla/003

    NCRMP/B-W/AP/RHB/PRED/06/Kruthive

    nnu/003

    NCRMP/B-W/AP/RHB/PRED/06/Machipat

    nam/002

    NCRMP/B-W/AP/RHB/PRED/06/Machipat

    nam/001

    NCRMP/B-W/AP/RCS/PRED/07/Karlapale

    m/002

    NCRMP/B-W/AP/RCS/PRED/07/Nizampat

    nam/003

    NCRMP/B-W/AP/RCS/PRED/08/Tangutur

    /003

    NCRMP/B-W/AP/RCS/PRED/07/Bapatla/0

    04

    NCRMP/B-W/AP/RCS/PRED/08/Vetapale

    m/001

    NCRMP/B-W/AP/RCS/PRED/08/Chirala/0

    02

    39

    40

    36

    37

    38

    41

    42

    43

    44

    45

    46

    47

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    11 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    Actual

    Construction of roads to cyclone shelters in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 5.94 0.12

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 11.86 0.24

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 13.22 0.27

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 20.07 0.41

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 6.69 0.14

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 14.44 0.30

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 15.16 0.31

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 12.44 0.26

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to cyclone shelters in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 11.37 0.23

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Guntur NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 11.79 0.24

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Guntur NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 10.41 0.21

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Prakasam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    3 13.83 0.29

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11

    NCRMP/B-W/AP/RCS/PRED/09/Muthuku

    r/002

    NCRMP/B-W/AP/RCS/PRED/09/T.P.Gud

    ur/005

    NCRMP/B-W/AP/RCS/PRED/09/Bogole/0

    03

    NCRMP/B-W/AP/RCS/PRED/09/Kota/001

    NCRMP/B-W/AP/RCS/PRED/09/Kavali/00

    6

    NCRMP/B-W/AP/RCS/PRED/09/Chillakur/

    004

    NCRMP/B-W/AP/RHB/PRED/07/Karlapale

    m/001

    NCRMP/B-W/AP/RCS/PRED/09/DV.Satra

    m/008

    NCRMP/B-W/AP/RCS/PRED/09/Tada/009

    NCRMP/B-W/AP/RCS/PRED/09/Kavali/00

    7

    NCRMP/B-W/AP/RHB/PRED/07/Nagaram

    /002

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/

    001

    51

    52

    48

    49

    50

    53

    54

    55

    56

    57

    58

    59

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    12 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    RevisedActual

    Construction of roads to habitations in Prakasam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    4 14.40 0.30

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Prakasam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 10.45 0.22

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Prakasam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 18.53 0.38

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Prakasam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    3 12.43 0.26

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Prakasam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 14.21 0.29

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Prakasam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 13.68 0.28

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Prakasam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 15.89 0.33

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Prakasam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 18.24 0.38

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Prakasam NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 12.26 0.25

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 19.00 0.39

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 20.60 0.42

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    NCRMP/B-W/AP/RHB/PRED/08/S.Konda/

    002

    001

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur

    /10

    NCRMP/B-W/AP/RHB/PRED/08/Kothapat

    nam/003

    NCRMP/B-W/AP/RHB/PRED/08/Kothapat

    nam/004

    NCRMP/B-W/AP/RHB/PRED/08/Ongole/0

    06

    NCRMP/B-W/AP/RHB/PRED/09/Bogole/0

    02

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapad

    u/07

    NCRMP/B-W/AP/RHB/PRED/08/Tangutur

    /09

    NCRMP/B-W/AP/RHB/PRED/08/Chinaga

    njam/005

    NCRMP/B-W/AP/RHB/PRED/09/Bogole/0

    01

    NCRMP/B-W/AP/RHB/PRED/08/Ulavapad

    u/08

    63

    64

    69

    70

    60

    61

    62

    65

    66

    67

    68

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    13 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    Construction of roads to habitations in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 19.04 0.39

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    3 17.52 0.36

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 20.38 0.42

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 14.09 0.29

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 11.52 0.24

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 15.75 0.32

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 20.32 0.42

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 22.52 0.46

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    1 11.35 0.23

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Construction of roads to habitations in Nellore NCB

    Panchayati Raj Engineering Department (NABARD), Govt of AP

    2 9.01 0.19

    Appraisal

    2-Nov-09 12-Nov-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 8-Dec-10 4-Sep-11 3-Dec-11RevisedActual

    Improvements to Nowpada - Venkatapuram road from Km 0/0 to 15/0 in Srikakulam District

    NCBRoads and Bridges

    Department, Government of AP

    1 41.05 0.85

    Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 15-Dec-09 6-Mar-10 8-Mar-10 8-Apr-10 8-May-10 5-Jun-10 7-Jun-10 3-Jan-11 2-Jun-11 31-Aug-11RevisedActual

    Improvements to NH5 to Patnavanipeta road (via) Tamada connecting Sundarampalem from Km 9/6 to 12/6 in Srikakulam District

    NCBRoads and Bridges

    Department, Government of AP

    1 19.22 0.40

    Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 6-Mar-10 8-Mar-10 8-Apr-10 8-May-10 5-Jun-10 7-Jun-10 3-Apr-11 31-Aug-11 29-Nov-11

    81

    NCRMP/B-W/AP/RD/R&B/

    01/ Nowpada/006

    82

    78

    79

    77

    NCRMP/B-W/AP/RD/R&B/

    01/ Patnavanipeta/0

    NCRMP/B-W/AP/RHB/PRED/09/T.P.Gud

    ur/012

    NCRMP/B-W/AP/RHB/PRED/09/V.Chala

    m/007

    NCRMP/B-W/AP/RHB/PRED/09/Allur/008

    NCRMP/B-W/AP/RHB/PRED/09/Allur/009

    NCRMP/B-W/AP/RHB/PRED/09/Indukuru

    pet/011

    NCRMP/B-W/AP/RHB/PRED/09/Muthuku

    r/006

    NCRMP/B-W/AP/RHB/PRED/09/Chittamu

    r/003

    NCRMP/B-W/AP/RHB/PRED/09/Allur/010

    NCRMP/B-W/AP/RHB/PRED/09/Vidavalur

    /005

    NCRMP/B-W/AP/RHB/PRED/09/Kavali/00

    4

    75

    76

    71

    72

    73

    74

    80

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    14 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER

    Signing of the contract

    Issue of contract award notice

    50% work complete

    100% work complete

    Completion of contractual obligations

    RevisedActual

    Improvements to Konada-Ramatheertham road to Konathalapalem road (via) Pasupam, Yerukonda, Kollayavalasa from km.12/0 to 16/5 (km.0/0 to 4/0 i.e. upto NH5 crossing) in Vizianagaram District

    NCBRoads and Bridges

    Department, Government of AP

    1 15.86 0.33

    Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 11-Jun-11 8-Dec-11 7-Mar-12RevisedActual

    Andhra Pradesh- Roads- Total 186 1112.65 22.94

    Andhra Pradesh- Bridges208.95

    NCBRoads and Bridges

    Department, Government of AP

    1 46.20 0.95Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 20-Mar-10 22-Mar-10 22-Apr-10 22-May-10 19-Jun-10 21-Jun-10 21-Jun-11 18-Dec-11 17-Mar-12

    RevisedActual

    NCBRoads and Bridges

    Department, Government of AP

    1 33.37 0.69Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 15-Dec-09 20-Mar-10 22-Mar-10 22-Apr-10 22-May-10 19-Jun-10 21-Jun-10 21-Jun-11 18-Dec-11 17-Mar-12RevisedActual

    Construction of Minor Bridge at Km 7/2 near Puligadda of Konada – Ramatheertham R&B road to Konatalapalem via Yerukonda, Pasupam

    NCBRoads and Bridges

    Department, Government of AP

    1 34.39 0.71

    Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 7-Jan-11 6-Jun-11 5-Sep-11RevisedActual

    NCRMP/B-W/AP/Br/R&B/07/ Bapatla/010

    Reconstruction of HLB at km 5/2 of Bapatla-Suryalanka road in Guntur District.

    NCBRoads and Bridges

    Department, Government of AP

    1 35.83 0.74Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 20-Mar-10 22-Mar-10 22-Apr-10 22-May-10 19-Jun-10 21-Jun-10 17-Jan-11 16-Jun-11 14-Sep-11RevisedActual

    Construction of Bridge at Km 11/6-8 of NH5 to Patnavanipeta connecting Sundarapalem in Srikakulam District

    NCBRoads and Bridges

    Department, Government of AP

    1 25.85 0.53

    Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 6-Mar-10 8-Mar-10 8-Apr-10 8-May-10 5-Jun-10 7-Jun-10 3-Apr-11 31-Aug-11 29-Nov-11RevisedActual

    Construction of Minor Bridge across Uppugada at Km 7/6 of Srikakulam limits to Pukkalapeta via Killipalem in Srikakulam District

    NCBRoads and Bridges

    Department, Government of AP

    1 9.50 0.20

    Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 11-Jun-11 8-Dec-11 7-Mar-12RevisedActual

    Construction of Minor bridge at Km 12/2-4 of NH5 to Surampeta road via Naruva, Menthada in Srikakulam District

    NCBRoads and Bridges

    Department, Government of AP

    1 3.33 0.07

    Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 11-Jun-11 8-Dec-11 7-Mar-12RevisedActual

    Construction of Minor Bridge at Km 15/2 near Chakaligadda of Konada Ramatheertham R&B road to Konatalapalem via Yrukonda Pasupem, Kollayavalasa (ZP Road) in Vizianagaram District

    NCBRoads and Bridges

    Department, Government of AP

    1 6.34 0.13

    Appraisal 10-Aug-09 11-Oct-09 30-Nov-09 21-Dec-09 12-Mar-10 13-Mar-10 13-Apr-10 13-May-10 10-Jun-10 11-Jun-10 11-Jun-11 8-Dec-11 7-Mar-12RevisedActual

    5

    1

    6

    7

    83

    8

    4

    3

    NCRMP/B-W/AP/Br/R&B/0

    7/ Perali/011

    NCRMP/B-W/AP/Br/R&B/

    02/ Puligadda/007

    NCRMP/B-W/AP/Br/R&B/0

    1/ Bendigadda/004

    Construction of High level Bridge (HLB) across Bendigadda at Km 4/10 of Pundi - Parlakimindi road in Srikakulam District

    05

    NCRMP/B-W/AP/RD/R&B/ 02/ Konada/009

    Andhra Pradesh- Bridges-

    2

    Reconstruction of High Level Bridge (HLB) at km 2/4 of Bapatla-Pandurangapuram across Perali Drain in Guntur District

    NCRMP/B-W/AP/Br/R&B/0

    2/ Chakaligadda/0

    08

    NCRMP/B-W/AP/Br/R&B/0

    1/ Surampeta/003

    NCRMP/B-W/AP/Br/R&B/0

    1/ Patnavanipeta/0

    01

    NCRMP/B-W/AP/Br/R&B/0

    1/ Uppugada/ 002

  • Procument: GOODS AND SERVICESNATIONAL CYCLONE RISK MANAGEMENT PROJECT

    15 of 15

    Sno Package No. Description Method of Procurement

    Schedule/ Slice

    Procurement Authority Quantity (Number)

    Total Estimated Cost (Million local currency)

    Estimated Cost (Million USD)

    Stage Initiate preparation of Specification and Bid Document

    Preparation of IFB and submission to the Bank

    Preparation of the Bid Document

    Approval of IFB and Bid documents by the World Bank

    Publication of IFB in Newspapers and UNDB

    Beginning of Sale of Bid document

    Opening of Bids

    Submission of BER to Bank for approval/ Preparation of BER

    Approval of BER