national report presented by the mexican united …...article 16. emergency preparedness 16.0...

200
National Report presented by the Mexican United States to meet the requirements of the Nuclear Safety Convention 2007-2009 Period September 2010

Upload: others

Post on 22-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

National Report presented by

the Mexican United States to meet the requirements of the

Nuclear Safety Convention 2007-2009 Period

September 2010

Page 2: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

INDEX I INDEX II ABBREVIATIONS AND DEFINITIONS III INTRODUCTION / PREPARATION AND SCOPE OF THE NATIONAL

REPORT

National policy Nuclear Programme in Mexico Report Information to the public

IV SUMMARY ARTICLE 6. EXISTING NUCLEAR INSTALLATIONS 6.0 Obligations

- Existing nuclear installations in United Mexican States - Overview of important safety-related issues, including events at nuclear

facilities during the past three years, and measures taken - Description of projects and planned measures for continuous safety

improvement, on a case-by-case basis, for each type of nuclear facility - Identification of the facilities that were required to shutdown - A statement on the contracting party position regarding the continued

operation of nuclear facilities, including those that do not comply with the obligations stated in Articles 10 - 19 of the Convention; explaining how safety and other issues were taken into account to achieve this position

ARTICLE 7. LEGISLATIVE AND REGULATORY FRAMEWORK 7.0 Obligations 7.1 Establishing and maintaining a legislative and regulatory framework

- Overview of the primary legislative framework for nuclear safety, including interfacing national legislation

- Ratification of international conventions and legal instruments related to nuclear safety

7.2 (i) National safety requirements and regulations - Overview of the secondary legislation for nuclear safety - Overview of regulations and guides issued by the Regulatory Body

I-1 2007-2009 Period

Page 3: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

- Overview of the process of establishing and revising regulatory requirements, including the involvement of interested parties

7.2 (ii) System of licencing - Overview of the licencing system and processes including types of licenced

activity and, and the procedure for relicencing - Involvement of the public and interested parties - Legal provisions to prevent the operation of a nuclear installation without a

valid licence 7.2 (iii) System of regulatory inspection and assessment

- Regulatory strategies - Overview of the regulatory inspection and assessment process with regard to

the safety of nuclear installations - Basic features of inspection programmes

7.2 (iv) Enforcement of applicable regulations and terms of licences - Power for legal actions - Overview of enforcement measures available to the Regulatory Body - Experiences with legal actions and enforcement measures

ARTICLE 8. REGULATORY BODY 8.0 Obligations 8.1 Establishment of the Regulatory Body

- Legal foundations and statute of the Regulatory Body - Mandate, mission and tasks - Authorities and responsibilities - Organizational structure of the Regulatory Body - Development and maintenance of human resources over the past three years - Measures to develop and maintain competence - Developments with respect to financial resources over the past three years - Statement of adequacy of resources - Quality management system of the Regulatory Body - Openness and transparency of regulatory activities - External technical support - Advisory committees

8.2 Status of the Regulatory Body - Place of the Regulatory Body in the governmental structure - Reporting obligations

I-2 2007-2009 Period

Page 4: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

- Means by which effective separation of the Regulatory Body from the agencies responsible for promotion of nuclear energy is ensured

ARTICLE 9. RESPONSIBILITY OF THE LICENCE HOLDER 9.0 Obligations

- Formulation in the legislation (quotation) assigning the prime responsibility for safety to the licence holder

- Description of the main means by which the Licence holder discharges the prime responsibility for safety

- Description of the mechanism by which the Regulatory Body ensures that the licence holder discharges its prime responsibility for safety

ARTICLE 10. PRIORITY TO SAFETY 10.0 Obligations

- Overview of the contracting party’s arrangements and regulatory requirements regarding policies and programmes to be used by the licence holder to prioritize safety in activities for design, construction and operation of nuclear installations

Description of the agreements and regulatory requirements Licence holder safety policies Licence holder safety culture programmes and development Arrangements for safety management Arrangements for safety monitoring and self-assessment Independent safety assessments Quality management system

- Measures taken by licence holders to implement arrangements for the priority of safety, such as those above and any other voluntary activities and good practices

- Regulatory process for monitoring and oversight of arrangements used by the licence holders to prioritize to safety

- Means used by the Regulatory Body to prioritize safety in its own activities ARTICLE 11. FINANCIAL AND HUMAN RESOURCES 11.0 Obligations 11.1 Financial resources

- Mechanisms for the provision of financial resources to the licence holder or applicant in order to ensure safety of the nuclear installation throughout its lifetime

I-3 2007-2009 Period

Page 5: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

Principles for the financing of safety improvements to the nuclear installation over its operational lifetime

Principles for financial provisions during the period of commercial operation for decommissioning and management of spent fuel and radioactive waste from nuclear installations

- Statement with regard to the adequacy of financial provisions - Contracting party’s processes to assess the financial provisions

11.2 Human resources - Overview of the contracting party’s arrangements and regulatory

requirements concerning staffing, qualification, training and retraining of staff for nuclear installations

Human resources of CFE / Nuclear Power Plant’s Division Organization of CFE / Nuclear Power Plant’s Division

- Methods used for the analysis of competence requirements and training needs for all safety related activities in nuclear installations

- Arrangements for initial training and retraining of operations staff, including simulator training

- Capabilities of plant simulators used for training with regard to fidelity to the plant and scope of simulation

- Arrangements for training of maintenance and technical support staff - Improvements to training programmes as a result of new insights from safety

analyses, operational experience, development of training methods and practices

- Methods used to assess the sufficiency of staff at nuclear installations - Policy or principles governing the use of contracted personnel to support or

supplement the Licence holder’s staff - Methods used to assess the qualification and training of contractor’s

personnel - Description of the national supply of, and demand for, experts in nuclear

science and technology - Regulatory review and control activities

ARTÍCULO 12. HUMAN FACTORS 12.0 Obligations

- Overview of the contracting party’s arrangements and regulatory requirements to take human factors and organizational issues into account for the safety of nuclear installations

I-4 2007-2009 Period

Page 6: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

- Consideration of human factors in the design of nuclear installations and subsequent modifications (see also Article 18.3)

- Methods and programmes of the licence holder for analyzing, preventing, detecting and correcting human errors in the operation and maintenance of nuclear installations

- Self-assessment of managerial and organizational issues by the operator - Arrangements for the feedback of experience in relation to human factors and

organizational issues - Regulatory control and review activities

ARTICLE 13. QUALITY ASSURANCE 13.0 Obligations

- Overview of the contracting party’s arrangements and regulatory requirements for the quality assurance programmes, quality management systems, or management systems of the licence holders

Provisions and regulatory requirements for the quality assurance programmes

Quality management systems - Status with regard to the implementation of integrated management systems

at nuclear installations - Main elements of a typical quality assurance, quality management or

management system programme covering all aspects of safety throughout the lifetime of the nuclear installation, including delivery of safety related work by contractors

Quality assurance essential elements Quality Assurance (QA) categories Authorization to contractors Corrective actions Reporting Periodic assessment of the Quality Assurance Programme

- Audits programmes of the licence holders - Audits of vendors and suppliers by the licence holders - Regulatory review and control activities

ARTICLE 14. ASSESSMENT AND VERIFICATION OF SAFETY 14.0 Obligations 14.1 Assessment of safety

I-5 2007-2009 Period

Page 7: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

- Overview of the contracting party’s arrangements and regulatory requirements to perform comprehensive and systematic safety assessments

- Safety assessments within the licencing process and the safety analysis reports for different stages in the lifetime of nuclear installations (e.g. siting, design, construction, operation)

- Periodic safety assessments of nuclear installations using deterministic and probabilistic methods of analysis

- Overview of the safety assessments performed and the main results of those assessments for existing nuclear installations

- Regulatory review and control activities 14.2 Verification of safety

- Overview of the contracting party’s arrangements and regulatory requirements for the verification of safety

- Main elements of programmes for continued verification of safety (in-service inspection, surveillance, functional testing of systems, etc.)

- Elements of aging management programme(s) - Arrangements for internal review by the licence holder of safety cases to be

submitted to the Regulatory Body - Regulatory review and control activities

ARTICLE 15. RADIATION PROTECTION

15.0 Obligations

- Overview of contracting party’s arrangements and regulatory requirements concerning radiation protection at nuclear installations, including applicable laws not mentioned under Article 7

- Regulatory expectations for the licence holder’s processes to optimize radiation dose and to implement the “As low As Reasonably Achievable” (ALARA) principle

- Implementation of radiation protection programmes by the licence holders, including:

Observation of dose limits, main results for doses to exposed workers Conditions for the release of radioactive material into the environment,

operational control measures and main results Processes implemented and steps taken to ensure that radiation

exposure are kept as low as reasonably achievable for all operational and maintenance activities

Environmental surveillance and main results - Regulatory review and control activities

I-6 2007-2009 Period

Page 8: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes

- Overview of the Contracting Party’s arrangements and regulatory requirements for on-site and off-site emergency preparedness, including applicable laws not mentioned under Article 7

- Overview of the main elements of the national plan (and regional plan, if applicable) for emergency preparedness, including the role and responsibilities of the Regulatory Body and other main actors

- Implementation of related measures - Implementation of emergency preparedness measures by the license holders

Classification of Emergencies Main elements of the on-site and, where applicable, off-site emergency

plans for nuclear installations Facilities provided by the license holder for emergency preparedness (if

appropriate, give preference to descriptions under Article 18 and Article 19 (4), respectively)

- Training and exercises, evaluation activities and main results of performed exercises

- Regulatory review and control activities 16.2 Information of the public and neighbouring states

- Overview of Contracting Party’s arrangements for informing the public in the vicinity of the nuclear installations about emergency planning and emergency situations

- Arrangements to inform competent authorities of neighboring States, as necessary

16.3 Emergency preparedness for contracting parties without nuclear installations ARTICLE 17. SITING 17.0 Obligations 17.1 Evaluation of site related factors

- Overview of the Contracting Party’s arrangements and regulatory requirements relating to the siting and evaluation of sites of nuclear installations, including applicable national laws not mentioned under Article 7

Overview of assessments made and criteria applied for evaluating all site related factors affecting the safety of the nuclear installation

I-7 2007-2009 Period

Page 9: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

Overview of design provisions used against human made external events and natural occurring external events such as fire, explosion, aircraft crash, external flooding, severe weather conditions and earthquakes

- Regulatory review and control activities 17.2 Impact of the installation on individuals, society and environment

- Criteria for evaluating the likely safety related impact of the nuclear installation on the surrounding population and the environment

- Implementation of these criteria in the licensing process 17.3 Re-evaluation of site related factors

- Activities for re-evaluation of the site related factors as mentioned in Article 17(1) to ensure the continuing acceptability of the safety of the nuclear installation

- Results of recent re-evaluation activities - Regulatory review and control activities

17.4 Consultation with other contracting parties likely to be affected by the installation

- International arrangements - Bilateral agreements with neighbouring States, as applicable and as

necessary ARTICLE 18. DESIGN AND CONSTRUCTION 18.0 Obligations 18.1 Implementation of defense in depth

- Overview of the Contracting Party’s arrangements and regulatory requirements concerning the design and construction of nuclear installations

- Status with regard of the applications for all nuclear installations of the defense in depth concept, providing for multiple levels of protection of the fuel, the primary pressure boundary and the containment, with account taking of internal and external events

- Extent of use of design principles, such as passive safety or the fail safe function, automation, physical and functional separation, redundancy and diversity, for different types and generations of nuclear installations

- Implementation of design measures (plant modifications, backfitting) to prevent beyond design basis accidents or to mitigate the radiological consequences, if they were to occur

- Improvements implemented for design for nuclear power plants as a result of deterministic and probabilistic safety assessments made since the previous

I-8 2007-2009 Period

Page 10: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

National Report, and an overview of the main improvements implemented since the commissioning of the nuclear installations

- Regulatory review and control activities 18.2 Incorporation of proven technologies

- Contracting Party’s arrangements and regulatory requirements for the use of technologies proven or qualified testing or analysis

- Measures taken by the licence holder to implement proven technologies - Analysis, testing and experimental methods to qualify new technologies, such

as digital instrumentation and control equipment - Regulatory review and control activities

18.3 Design for reliable, stable and manageable operation - Overview of the Contracting Party’s arrangements and regulatory

requirements for reliable, stable and easily manageable operation, with specific consideration of human factors and human-machine interface (see also Article 12)

- Implementation measures taken by the licence holder - Regulatory review and control activities

ARTICLE 19. OPERATION 19.0 Obligations 19.1 Initial authorization

- Overview of the Contracting Party’s arrangements and regulatory requirements for the commissioning of a nuclear installation, as constructed, is consistent with design requirements and safety requirements

- Conduct of appropriate safety analyses - Start up programme - Programmes of verification that installations, as constructed, are consistent

with the design and in compliance with safety requirements - Regulatory review and control activities

19.2 Operational limits and conditions - Overview of the Contracting Party‘s arrangements and regulatory

requirements for the definition of safe boundaries of operation and the setting of operational limits and conditions

- Implementation of operational limits and conditions, their documentation, training in them, and their availability to plant personnel engaged in safety related works

- Review and revision of operational limits and conditions as necessary

I-9 2007-2009 Period

Page 11: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

- Regulatory review and control activities 19.3 Procedures for operation, maintenance, inspection and testing

- Overview of the Contracting Party’s arrangements and regulatory requirements on procedures for operation, maintenance, inspection and testing of a nuclear installation

- Establishment of operational procedures, their implementation, periodic review, modification, approval and documentation

- Availability of the procedures to the relevant nuclear installation staff - Involvement of relevant nuclear installation staff in the development of

procedures - Incorporation of operational procedures into the management system of the

nuclear installation - Regulatory review and control activities

19.4 Procedures for responding to operational occurrences and accidents - Overview of the Contracting Party’s arrangements and regulatory

requirements on procedures for responding to anticipated operational occurrences and accidents

- Establishing event based and / or symptom based emergency operating procedure

- Establishing procedures and guidance to prevent severe accidents or mitigate their consequences

- Regulatory review and control activities 19.5 Engineering and technical support

- General availability of necessary engineering and technical support in all safety related fields for all nuclear installations, under construction, in operation or under decommissioning

- General availability of necessary technical support on the site and also at the licence holder or utility headquarters, and procedures for making central resources available for nuclear installations

- General situation with regard to dependence on consultants and contractors for technical support to nuclear installations

- Regulatory review and control activities 19.6 Reporting of incidents significant to safety

- Overview of the Contracting Party’s arrangements and regulatory requirements to report incidents significant to safety to Regulatory Body

- Overview of the established reporting criteria and reporting procedures for incident to safety and other such as near misses and accidents

I-10 2007-2009 Period

Page 12: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

- Statistics of reported incidents significant to safety for the past three years - Documentation and publication of reported events and incidents by both the

licence holders and Regulatory Body - Policy for use of the INES scale - Regulatory review and control activities

19.7 Operational experience feedback - Overview of the Contracting Party’s arrangements and regulatory

requirements on the licence holders to collect and analyze and share operational experience

- Overview of programmes of licence holders for the feedback of information on operating experience from their own nuclear installation, from other domestic installations and from installations abroad

- Procedures to analyze domestic and international events - Procedures to draw conclusions and to implement any necessary to the

installation and to personnel training programmes and simulators - Mechanisms to share important experience with other operating organizations - Use of international information databases on operating experience - Regulatory review and control activities for Licence holder programmes and

procedures - Programmes of the Regulatory Body for feedback of operational experience

and the use of existing mechanisms to share important experiences with international organizations and with other regulatory bodies

19.8 Management of spent fuel and radioactive waste on the site - Overview of the Contracting Party’s and regulatory requirements for the on-

site handling of spent fuel and radioactive waste - On-site storage of spent fuel - Implementation of on-site treatment, conditioning and storage of radioactive

waste - Activities to keep the amount of waste generated to the minimum practicable

for the process concerned, in terms of both activity and volume - Established procedures for clearance of radioactive waste - Regulatory review and control activities

I-11 2007-2009 Period

Page 13: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ABBREVIATIONS AND DEFINITIONS

ACI American Concrete Institute ACQ Adverse Conditions to Quality AFI Areas for Improvement

ALARA As Low As Reasonable Achievable

ANSI American National Standards Institute

ASME American Society of Mechanical Engineers

ASSET Assessment of Safety Significant Events Team

ASTM American Society of Testing Materials

BOP Balance of Plant BRAC BWR Radiation Assessment and Control BWR Boiling Water Reactor BWROG Boiling Water Reactor Owners Group CAP Corrective Action Programme CFE Federal Electricity Commission CFR Code of Federal Regulations

CIRO Independent Operations Review Committee CNSNS National Commission of Nuclear Safety and Safeguards

CONAE National Commission for Energy Savings

CONASUPO Distributor and Commercial Promoter

CQAP Construction Quality Assurance Plan CR Condition Reports CRE Energy Regulatory Commission

CROS Site Operations Review Committee DBA Design Basis Accidents

II-1 2007-2009 Period

Page 14: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

DID Defense in Depth

DOO Direction Operation Office

ECCS Emergency Core Cooling Systems

EHC Electro-hydraulic Control EOP Emergency Operating Procedures

EPG Emergency Procedure Guidelines

EPRI Electric Power Research Institute

EPU Extended Power Up-rate

EREP External Radiological Emergency Plan EREPC External Radiological Emergency Plan Committee ERO Emergency Response Organization

FCRI Federal Commission for Regulatory Improvement

FEIR Final Environmental Impact Report FSAR Final Safety Analysis Report FW Feed Water

GE General Electric Gy Gray HIC High-integrity Containers HPCI High Pressure Coolant Injection

HVAC Heating Ventilating and Air Conditioning

IAEA International Atomic Energy Agency

ICRP International Commission on Radiological Protection

IDR Important Deficiency Report

IEEE Institute of Electrical and Electronic Engineers IEP Internal Emergency Plan

II-2 2007-2009 Period

Page 15: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

IIE Electric Research Institute

IMS Integral Management System

INES International Nuclear Event Scale

ININ National Institute for Nuclear Research

INPO Institute of Nuclear Power Operations

IPE Individual Plant Examination IRS Incident Reporting System ISEU Independent Safety Engineering ISI In-service Inspection

ISO International Organization for Standardization

IVVI In Vessel Visual Inspection

JTA Job Task Analysis

km kilometre LER Licensee Event Report

LVNPS Laguna Verde Nuclear Power Station MCR Main Control Room MELCORE Melting Core

Mexico United Mexican States

MOS Mexican Official Standard mR milli Roetgen MSR Moisture Separator Reheaters

mSv milli Sievert MWe Megawatt electric MWt Megawatt thermal NACN National Advisory Committee of Normalization

NEA Nuclear Energy Agency

II-3 2007-2009 Period

Page 16: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

NEI Nuclear Energy Institute NPP Nuclear Power Plant’s

NRC Nuclear Regulatory Commission

NRE Notification of Reportable Event NSSS Nuclear Steam Supply System

NUPIC Nuclear Utilities Procurement Issues Committee

OBE Operating Basis Earthquake ODCM Off-site Dose Calculation Manual OQAP Operation Quality Assurance Plan OSART Operational Safety Assessment Review Team

OTS Operating Technical Specifications P&L Profit and Loss

PASS Post-Accident Sampling System

PCP Process Control Program

PEIA Preliminary Environmental Impact Assessment PEMEX Mexican oil company PMH Probable Maximum Hurricane

PRIS Power Reactor Information System

PSA Probabilistic Safety Analysis

PSAR Preliminary Safety Analysis Report PSR Periodic Safety Review

QA Quality Assurance QAP Quality Assurance Plan

QMS Quality Management System

R Roetgen

II-4 2007-2009 Period

Page 17: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

RASCAL Radiological Assessment System for Consequences Analysis

RCIC Reactor Core Isolation Cooling

Rem Roetgen Equivalent Man RG Regulatory Guides RHR Residual Heat Removal

ROP Reactor Oversight Process

RPV Reactor Pressure Vessel

RTP Rated Thermal Power SAFSTOR Safe Storage

SAT Systematic Approach to Training

SCART Safety Culture Assessment Review Team

SCRAM Sudden Control Rod Action Movement

SDH Standard Design Hurricane

SDP Significance Determination Process

SPDS Safety Parameter Display System

SRCM Storage for radioactive contaminated materials

SRI Statement of Regulatory Impact

SRO Senior Reactor Operator SSC Structures, Systems and Components SSE Safe Shutdown Earthquake SSEFPS Safe Shutdown Earthquake Fire Protection System ST System Test

Sv Sievert TEDE Total Effective Dose Equivalent

II-5 2007-2009 Period

Page 18: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

the Commission National Commission of Nuclear Safety and Safeguards the Constitution Political Constitution of the United Mexican States

the Nuclear Law Regulatory Law of the Constitutional Article 27 on Nuclear Matters

TLD Thermo Luminescent Dosimeter

TMI Three Mile Island

TMVB Trans-Mexican Volcanic Belt

TS Temporary Storage TÜV TÜV Anlagentechnik Gmbh

U-1 Unit 1 U-2 Unit 2 US United States of America VS Balance of Plant systems

WANO World Association of Nuclear Operators

II-6 2007-2009 Period

Page 19: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

INTRODUCTION

PREPARATION AND SCOPE OF THE NATIONAL REPORT National Policy National policy regarding nuclear activities is embodied in the Regulatory Law of the Constitutional Article 27 on Nuclear Matters. The principle of this Law is that nuclear energy must be used only for pacific applications and of all activities, including planning, design, siting, construction, testing, operation, modification, as well as closure and decommissioning, safety always has the highest level of importance. The nuclear programme of the Mexican United States The Federal Electricity Commission (CFE) is not considering in its future projects the construction of a new nuclear power plant to generate electricity. Currently, CFE is carrying out the Extended Power Up-rate (EPU) project to increase the power of the Laguna Verde Nuclear Power Station (LVNPS) Units 1 & 2 up to 120% (2317 MWt) of the Rated Thermal Power (RTP) originally licensed power (1931 MWt). LVNPS is currently operating at 105% (2027 MWt) of the RTP and expects concluding the EPU project for both units in 2010. National Report In accordance with Article 5 of the Nuclear Safety Convention, this document summarizes the measures taken from January 1, 2007 to December 31, 2009, in relation to LVNPS Units 1 & 2; the only existing nuclear installation in Mexico as far as the Convention is concerned. A description of LVNPS main characteristics is presented in Table 6.1 in Article 6 of this National Report. This report is self contained and organized according to the structure of the 19 Articles of the Convention. The report was prepared upon request of the Ministry of Energy by both the National Comisión Nacional de Seguridad Nuclear y Salvaguardias (CNSNS), the Mexican regulatory body in nuclear matters, as coordinator, and the Nuclear Power Plant’s Division of CFE, responsible for the safe operation of LVNPS. The Government of the Mexican United States (hereinafter indistinctly denominated “Mexico”) fully recognizes, through this report and its annexes, the commitment to continue pursuing all the fundamental principles of nuclear and radiation safety and

III-1 2007-2010 Period

Page 20: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

physical security in the Mexican nuclear facilities, in order to maintain and increase their safety level. This report describes safety assessments performed by internal and external organizations at every phase of LVNPS. These assessments do not indicate the existence of any adverse condition for LVNPS safe operation. Therefore, in the opinion of the Mexican State, it is concluded that Mexico continues meeting the commitments of the Nuclear Safety Convention. Information to the Public This National Report, like previous reports corresponding to the 1st, 2nd, 3rd and 4th Review Meeting of the Nuclear Safety Convention, as well as the questions made by the Contracting Parties and the answers provided to them, are public documents in compliance with the Mexican "Federal Law of Transparency and Access to Government Public Information" which came into force on June 12, 2002, and the recommendations from the Convention contained in document INFCIRC/572/Rev.3 September 2009.

III-2 2007-2010 Period

Page 21: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

SUMMARY This document is the fifth National Report of the Mexican United States (hereinafter indistinctly denominated “Mexico”) on the Nuclear Safety Convention for the 2007-2009 period. This report addresses the Laguna Verde Nuclear Power Station (LVNPS) safety issues and the activities of the Mexican regulatory body – Comisión Nacional de Seguridad Nuclear y Salvaguardias (CNSNS) showing how the Mexican State achieves and maintains a high level of nuclear safety through the improving steps taken in the country, supporting international cooperation and complying with all the obligations set by the Nuclear Safety Convention. Article 6 presents the main characteristics of LVNPS, the only existing nuclear power plant in Mexico, including the most relevant events that occurred over the past three years. Article 7 describes the primary legislative framework and secondary legislation related to Nuclear Safety, and the changes that have occurred in the licencing, evaluation, inspection and enforcement measures during the period of this National Report. It is important to note that the implementation of the Reactor Oversight Process (ROP) similar to the United States of America (US) Nuclear Regulatory Commission (NRC), continued and that it has required no changes to the regulatory framework. Article 8 presents the legal foundation, the development and maintenance of financial resources, and the measures to develop and maintain the competence of human resources of CNSNS. The Quality Management System, the organizational structure, the place in the government’s organization, and the independence of the CNSNS are also addressed. It should be noted that this Article discusses the challenges that Mexico faces, which were identified during the fourth peer review meeting held in April 2008. They include the following: (1) the possibility that the Mexican regulatory body had independence in the practice but that required to possess “de jure” independence; and (2) the need to hire qualified personnel or qualify newly hired personnel through a systematic approach to training. In this regard, it is emphasized that the organizational structure of the CNSNS has remained unchanged and continued being an organism administratively dependent of the Ministry of Energy with limited financial and human resources. Article 9 describes the legal responsibilities of the Licence holder with respect to safety and the CNSNS’s mechanisms to ensure that the Licence holder complies with those responsibilities. Article 10 presents the agreements and regulatory requirements implemented by the Licence holder to give priority to safety, such as safety culture programmes, which include Safety Management, self-assessments and international agreements to conduct independent safety assessments. Among the most important activities

IV-1 2007-2009 Period

Page 22: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

implemented in this area, stand out the development of performance indicators in accordance with the Reactor Oversight Process requirements, the consolidation of a quality management system and the implementation of essential Safety Culture processes. Article 11 mentions the financial provisions of the Licence holder to ensure the safety of the nuclear installation during commercial operation, decommissioning, and spent fuel and radioactive waste management from the plant. The agreements and regulatory requirements established by CNSNS to rule the training and retraining of staff for nuclear installations and the contracted personnel to support or supplement the Licence holder’s staff are also described. It is important to note that this Article discusses the human resource management to replace LVNPS staff that is retiring, which was one of Mexico’s challenges identified during the fourth peer review meeting held in April 2008. The human factors issues in the design of nuclear installations and subsequent modifications are mentioned in Article 12. It is noteworthy that the "Black Board" condition is maintained in both control rooms of LVNPS, and the implementation and follow-up of the human performance programme for error prevention continued. Article 13 describes the Licence holder’s Quality Assurance Programme and Quality Management System. Additionally, it describes the regulatory review and control activities conducted by the CNSNS. Article 14 describes the arrangements and regulatory requirements for comprehensive and systematic safety assessments, including their results, and for conducting safety verifications. It is noteworthy that the CNSNS will continue implementing and adapting the USNRC Reactor Oversight Process, applying the Risk-based Inspections Guidelines, reviewing the General Regulation for Radiation Safety and applying the Quality Management System. Article 15 describes the Licence holder’s processes to optimize the radiation dose and apply the “As low As Reasonably Achievable” (ALARA) principle in all operation and maintenance activities, as well as for the release of radioactive material into the environment. Additionally, as part of the regulatory review and control activities conducted by the CNSNS, the strategies to reduce the LVNPS collective dose implemented during the period of this National Report were assessed. Article 16 presents an overview of the arrangements and regulatory requirements for on-site and off-site emergency preparedness, and the main elements of the emergency preparedness national plan, including the regulation and responsibilities of the regulatory body and other government agencies. Article 16 also includes the Emergency Conventions (ConvEx-3) exercise that was conducted, involving the International Atomic Energy Agency and other international bodies.

IV-2 2007-2009 Period

Page 23: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Article 17 describes the arrangements and regulatory requirements concerning the siting and assessment of the sites for nuclear installations; the impact of the installation on individuals, the community and the environment; as well as the regulatory assessments to verify compliance with these requirements. Article 18 describes the arrangements and regulatory requirements of the Contracting Party concerning the design and construction of nuclear installations, the implementation of design measures (plant modifications, remodelling), including the LVNPS planned extended power up-rate up to120%. Then, in Article 19 the arrangements and regulatory requirements of the Mexican United States for the definition of the safety limits and, the establishment of operation limits and conditions are described. The general availability of engineering and technical support in all safety-related areas for nuclear installations under construction, in operation or decommissioning is also addressed. The arrangements and regulatory requirements of the Contracting Party to assure that the Licence holder collects, analyzes and shares operational experience are presented. Finally, the arrangements and regulatory requirements of the Contracting Party for the Licence holder on-site management of spent fuel and radioactive waste are presented. The conclusion from the information presented in this National Report is that LVNPS continues maintaining a safety performance level similar to other nuclear plants operating in countries with more nuclear experience. Currently there are no identified conditions that might adversely affect a safe operation; therefore, there are no plans to prematurely shut down the installation before the end of its licensed lifetime. Finally, it is concluded that the Mexican United States have laws, regulations and means for appropriate inspection and supervision by its regulatory body - independent from the exploitation organisms - which ensures that LVNPS operation does not represent an undue risk to health and public safety nor the environment.

IV-3 2007-2009 Period

Page 24: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTICLE 6. EXISTING NUCLEAR INSTALLATIONS 6.0 Obligations "Each Contracting Party shall take appropriate measures to ensure as soon as possible, a safety assessment of existing nuclear facilities at the time the Convention enters into force for that Party. When necessary, in the context of this Convention, the Contracting Party shall ensure that all reasonably feasible improvements to enhance safety of the nuclear facility are urgently adopted. If the safety enhancement were impossible to achieve, plans should be put in place to close down the nuclear facility as soon as practically feasible. The closing timetable may take into account the global energy context and possible alternatives, as well as the social, environmental and economic consequences." - Existing nuclear installations in Mexican United States As far as the Convention on Nuclear Safety is concerned, there is a single nuclear installation in Mexican United States called Laguna Verde Nuclear Power Station (LVNPS) consisting of two units with Boiling Water Reactors (BWR) of 682 MWe net electrical capacity each. The facility is located in the State of Veracruz in the Gulf of Mexico, 75 kilometers north of Veracruz City. Table 6.1 provides the main features of both LVNPS units. In the 2007-2009 reporting period there were no new nuclear facilities.

Table 6.1 List of Existing Nuclear Facilities

Name Laguna Verde Unit 1 Laguna Verde Unit 2

Licence No. CNLV-1/1 CNLV-2/1

PRIS Code MX-1 MX-2

Type BWR BWR

Thermal Power MWt 2027 2027

Net Capacity MWe 682 682

Operator CFE CFE

NSSS Vendor General Electric General Electric

Cooling Open, Gulf of Mexico Open, Gulf of Mexico

2007-2009 Period 6-1

Page 25: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Name Laguna Verde Unit 1 Laguna Verde Unit 2

Construction Start Date 1-October-1976 1-June-1977

First Criticality 8-November-1988 6-September-1994

Grid Connection 13-April-1989 11-November-1994

Commercial Operation 24-July-1990 10-April-1995

Licence Expiration Date 24-July-2020 10-April-2025 - Overview of important safety-related issues, including events at nuclear

facilities during the past three years, and measures taken The most important safety issues are listed below:

1.- Regarding the Probabilistic Safety Analysis (PSA), new developments that help prevent human errors and improve human-machine interaction (see Article 12)

2.- Strategic plans for final disposal of medium and low level radioactive waste, construction of a decontamination building and development of financial mechanisms to ensure the facility decommissioning at the end of its useful lifetime (see Article 11)

3.- Adequacy of licensee’s procedures and controls to comply with the General Regulation for Radiation Safety and the ICRP-26 (see Article 14)

4.- Continuous verification of Environmental Qualification of the equipment and components at the nuclear facility (see Article 14)

5.- Preventive maintenance programme and its modifications, resulting from refueling outages (see Article 19)

6.- Strengthening of Safety Culture elements, with special emphasis on conservative decision making and strict procedure compliance (see Article 10)

7.- Keeping track of individual and collective radiation dose, contamination of personnel, dry solid waste generation, and unplanned exposure to radiation during refueling outages (see Article 14)

8.- Knowledge management, retirement of experienced executive personnel in the industry (power plant, research centers) and the Comisión Nacional de Seguridad Nuclear y Salvaguardias (CNSNS) (see Article 8)

9.- CNSNS granted authorization for the construction and operation of two LVNPS "Storage Places for Radioactively Contaminated Materials” (see Article 19)

10.- The CNSNS granted authorization for the reconditioning and operation of one LVNPS “Storage Place for Radioactively Contaminated Materials” called "4 Naves" (see Article 19)

2007-2009 Period 6-2

Page 26: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

The most important events at LVNPS during this period are described below.

1. On April 14, 2007, while LVNPS Unit 1 was normally operating, when a reduction in the Hydraulic Power Unit oil level occurred. The unit went to a scheduled shutdown and a leak was found in the flow control valve actuator of the reactor recirculation system.

2. On December 20, 2007, LVNPS Unit 2 was operating at 100% Rated Thermal Power when operator manually scrammed the reactor due to a loss of main condenser vacuum caused by the loss of steam flow to the ejector that was in service.

3. On April 13, 2008, while LVNPS Unit 1 at rated power, the minimum flow valve of feedwater turbine pump “B” opened caused by an air supply line rupture. The transient caused instability in the Heaters Drain System and the Condensate System.

4. On October 28, 2008, while LVNPS Unit 2 was normally operating a speed surge occurred in the feedwater turbine pump loop “B” due to the loss of speed reference signal. The operators proceeded to reduce load immediately down to 86% power. However high-high water reactor level set point was reached, automatically tripping the main turbine and both reactor feedwater turbine pumps, with subsequent reactor scram.

5. During the 13th refueling outage of the Unit 1 programme several planned inspections were considered, including a visual one to reactor internals. As a result of this inspection, technicians discovered that 9 / 10 jet pumps set had flaws indications on the supporting region. Consequently, inspection surface was increased, as recommended by the Electrical Power Research Institute (EPRI) document BWRVIP-41 "BWR Jet Pump Inspection and Flow Evaluation Guidelines”. As a result of this inspection, it was found that in Jet Pumps 9 / 10 the riser had an important flaw indication.

As part of the measures taken in response to these events, the following results were obtained: 1) improvements to pre-refueling outage programmes, 2) strengthening of the adherence to procedures, 3) improvements to procedures, 4) strengthening of human performance tools, 5) design changes, 6) replacement of damaged components, and 7) feedback from the internal operating experience and the retraining programmes. - Description of projects and planned measures for continuous safety

improvement, on a case-by-case basis, for each type of nuclear facility Since 1998, LVNPS has implemented a programme to solve the most important safety issues. This programme is for 1998 to 2010 and seeks five objectives, namely: Safety, Environment, Production, Human Resources and Costs.

2007-2009 Period 6-3

Page 27: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

LVNPS has defined as the most important of all five, the improvement of nuclear safety. Topics covered by this programme include, among others, the following:

1. Collective dose reduction (Ongoing, see Article 15) 2. Control of intergranular stress corrosion (Ongoing, see Article 19) 3. Replacing the suction filters of the Emergency Core Cooling Systems (ECCS)

to avoid clogging (Implemented) 4. Improving the reactor vessel instrumentation to avoid the degasification

problem during the reactor vessel depressurization (Implemented) 5. Installation of a core instability automatic detection and suppression system

(Implemented) 6. Second Level Low Voltage Protection (Implemented) 7. Replacement of the discharge valves of the reactor recirculation system, with

valves with improved design(Implemented) 8. Modernization of the LVNPS full scope simulator. The simulator consists of

104 advanced models, new computing platform and new communication interfaces (Implemented)

9. Conversion to Improved Technical Specifications (Ongoing) 10. Implementation of an equipment reliability programme (Implemented) 11. Implementation of a programme for obsolete equipment replacement

(Ongoing) 12. LVNPS modernization and Power Up Rate submittal to the CNSNS for review

and assessment (Implemented). - Identification of the facilities that were required to shutdown During the reporting period, CNSNS has not identified any situation leading to order the shutdown of any one of LVNPS units. - A statement on the Contracting Party position regarding the continued

operation of nuclear facilities, including those that do not comply with the obligations stated in Articles 10 - 19 of the Convention; explaining how safety and other issues were taken into account to achieve this position

Based on the information presented in this Article and the rest of the National Report prepared to meet the commitments under the Nuclear Safety Convention; it is concluded that the Mexican United States has laws, regulations and means for adecuate inspection and supervision by its Regulatory Body - independent from the

2007-2009 Period 6-4

Page 28: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

exploitation organisms - which ensures that LVNPS operation does not represent an undue risk to health and public safety nor the environment. Regarding the specific compliance with the obligations derived from the Nuclear Safety Convention, the progress and achievements during the 2007-2009 reporting period is presented in each of the following articles. The conclusion from the existing objective evidence, a summary of which is presented in this report, is that LVNPS continues maintaining a safety performance level similar to other nuclear plants operating in countries with more nuclear experience. Currently, there are no identified conditions that might adversely affect safe operation; therefore, there are no plans to prematurely shut down the facility before the end of its licenced lifetime.

2007-2009 Period 6-5

Page 29: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTICLE 7. LEGISLATIVE AND REGULATORY FRAMEWORK 7.0 Obligations “Each Contracting Party shall establish and maintain a legislative and regulatory framework to govern the safety of nuclear installations. The legal and regulatory framework shall provide for: i) The applicable safety related national requirements and provisions;

ii) A licencing system for nuclear facilities and a scheme to prevent the operation of

a non-licenced nuclear installation;

iii) A system of regulatory inspection and assessment of nuclear facilities to verify compliance with the applicable provisions and the licence terms;

iv) The measures to ensure compliance with applicable provisions and the licence

terms, including suspension, modification or revocation." Article 7 (1) Establishing and maintaining a legislative and regulatory

framework - Overview of the primary legislative framework for nuclear safety, including

interfacing national legislation Introduction This article presents a summary of the Laws, Standards and Regulations that provide legal support to: Mexican institutions related to nuclear and radiation safety, and nuclear power plants licencing process by the Comisión Nacional de Seguridad Nuclear y Salvaguardias (hereinafter CNSNS). It should be understood that the information cited in this article does not intend to reproduce in its full extent the referred Laws and Regulations. However, at the end of this article, additional information is provided in order to give a more complete view of the Mexican regulatory framework. National requirements and provisions

2007-2009 Period 7-1

Page 30: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

The legislative and regulatory framework is supported by the Political Constitution of the Mexican United States (hereinafter denominated “the Constitution”) from which a series of laws, regulations, and standards are derived. The Constitution, in its Article 27, establishes that nuclear energy must be used only for peaceful uses and that the exploitation of nuclear fuels for the generation of nuclear energy as well as the regulation of its application in all areas corresponds extensively to the State. In accordance with the Constitution, the generation of electric power by nuclear means is considered strategic, and the public sector is exclusively responsible for such activity. Consequently, the Mexican State has created the organizations for the management of such strategic areas under its responsibility. The Regulatory Law on Nuclear Matters of Article 27 of the Constitution (hereinafter denominated “the Nuclear Law”) entered into effect on February 5, 1985. It gives the Federal Electricity Commission (hereinafter “CFE”) exclusively, the right to generate electricity from nuclear fuels. The design and construction of nuclear power plants also corresponds to this institution considering the opinion of the National Nuclear Research Institute. The Nuclear Law also provides nuclear reactors shall only be for no power production purposes shall only be operated by public sector and universities, institutes and universities, and research centers authorized by Law. CFE, a decentralized government agency of the Public Administration, has legal personality and patrimony. It is understood that a decentralized organs is an entity of the Public Administration created by a Congress of the Union law or decree, or a Federal Executive Branch decree, regardless of the legal structure adopted, it is constituted with funds and assets from the Federal Administration. Its objective is to provide a public or social service, the exploitation of nationally owned assets or resources, scientific and technological research, and obtaining or applying resources for assistance or social security. Likewise, the Constitution in its Article 89, Fraction I empowers the President of the Republic to “promulgate and execute the laws issued by the Congress of the Union, providing the administrative support for allowing its exact observance”. Hence the Federal Executive Branch, through the Department of Energy, regulates and supervises compliance with the provisions on nuclear safety and radiation protection. This attribution is based on Article 33, Fraction X of the Organic Law of Federal Administration. By virtue of Article 17 of the Organic Law of the Federal Administration, Mexican State Ministries are authorized to delegate to “desconcentrated” administrative agencies to obtain a more effective attention and a more efficient dispatch of matters of their competency. These agencies shall have specific powers to resolve matters

2007-2009 Period 7-2

Page 31: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

within the competence determined in each case, in accordance with applicable legal provisions. From the administrative standpoint, this Article supports the creation Comisión Nacional de Seguridad Nuclear y Salvaguardias (CNSNS). Being a under the Department of Energy, the CNSNS serves as the Regulatory Body responsible for overlooking nuclear and radiation safety, physical security and safeguards. Therefore, the CNSNS has authority over radioactive material user activities in the industry and medical treatment, but not on X ray devices for diagnostic purposes, these are supervised by authorities in the health sector. The Organic Law of the Federal Public Administration empowers the Department of Energy, to exert the responsibilities of the State on nuclear matters, as well as on the utilization of assets and natural resources required to generate, transmit, transform, distribute, and supply electricity whose objective is to provide public service and “to direct the activity of the decentralized entities whose objective is related to… the generation of nuclear power, in conformity with environmental legislation" (Article 33, Fractions II and III). As stipulated in Article 17 of the Nuclear Law, as the nuclear fuel is property of the State, the Federal Executive may only authorize its use under the terms of this Law and always under surveillance of the CNSNS. The Nuclear Law establishes in its Article 19 that “safety is essential in all activities involving nuclear energy and it should be considered from the planning, design, construction and operation up to the closure and decommissioning of nuclear and radioactive facilities as well as in the disposal and final destination of all the waste.” In accordance with this Law, nuclear safety is defined as the “set of actions and measures to prevent the equipment, materials and nuclear facilities and their operation from producing undue risks to the population’s health and property, or damage to the quality of the environment" (Article 20). It also defines as objective of the radiation safety "to protect workers, the population and their property, and the environment in general, by preventing and limiting the effects that could result from exposure to ionizing radiation"(Article 21). This Law defines two types of facilities: nuclear and radioactive. The first one is defined as "one in which nuclear fuel or material is manufactured, processed, used, reprocessed or stored”, and the second as "one in which radioactive material or equipment containing it, is produced, manufactured, stored, used; or radioactive wastes are treated, conditioned or stored" (Article 3, Fractions II and III, respectively). According to the Nuclear Law, both nuclear and radioactive facilities must have nuclear safety systems that meet the requirements established in other legal and regulatory provisions of the Law (Article 22, second paragraph). Similarly, the Law foresees in Article 27, third paragraph that "the nuclear facilities shall be staffed with

2007-2009 Period 7-3

Page 32: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

nuclear and radiation safety personnel required, and the head of the corresponding public agency shall be responsible for strict compliance with the applicable regulations." Regarding to incident notification and management, Article 23 of the Nuclear Law provides that when aware of an incident involving nuclear materials or fuels, radioactive materials or equipment containing them, or conditions that might cause it, the CNSNS shall be notified. In these cases, CNSNS might order or carry out the removal of the equipment, tools or materials that imply some risk, for deposit in places that meet the appropriate safety conditions. The Nuclear Law establishes the bases for implementing a licencing system for both nuclear and radioactive facilities, and for the suspension of license in case of failure to comply with any established conditions. For the granting of any licence or permit it is essential for nuclear and radioactive facilities to meet the requirements for the siting (selection, survey and evaluation of the location), design, construction, operation, modification, cease of operations, definitive shutdown, and decommissioning established in the regulatory provisions of the Nuclear Law. These requirements shall reflect the risk associated with operations that involve radioactive material, and depending on the activity and radio-toxicity of the isotopes that are present (Article 25). Under the provisions of Article 26 of the Nuclear Law, the Department of Energy is empowered to grant authorizations for siting, design, construction, operation, modification, cease of operations, definitive shutdown, and decommissioning of nuclear and radioactive facilities. The authorizations for the construction and operation of nuclear facilities will only be granted, by presenting relevant information, on how the safety objectives will be met and which procedures and methods will be used during the phases of siting, design, construction, operation, modification, cease of operations, definitive shutdown, and decommissioning of the installation, as well as the corresponding radiological emergency plan. Necessary information must also be included on the impact caused by the installation to the environment (Article 28). An authorization is also required for handling, transport, storage and custody of nuclear materials and fuels, and radioactive materials and equipment containing them (Article 30). The Nuclear Law empowers the CNSNS as the responsible agency for reviewing, evaluating and authorizing the bases for the siting, design, construction, operation, modification, cease of operations, definitive shutdown, and decommissioning of nuclear and radioactive installations; as well as everything related to the manufacture, use, handling, storage, reprocessing and transport of nuclear fuels and materials, radioactive materials and equipment containing them; and the processing, conditioning, dumping, and storing of radioactive wastes; and any disposal of them (Article 50, Fraction III).

2007-2009 Period 7-4

Page 33: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

For the licencing of nuclear facilities, the Nuclear Law foresees that the CNSNS must issue its opinion prior to the Department of Energie’s authorization (Article 50, Fraction IV). - Ratification of international conventions and legal instruments related to

nuclear safety The Mexican United States (hereinafter indistinctly denominated “Mexico”) has committed to implement the safety and health protection measures, as stated in the Informative Circular No. 18/Rev.1, by subscribing an agreement with the International Atomic Energy Agency (IAEA) whereby the Agency would assist in the implementation of a project for a nuclear power plant (INFCIRC/203). Thus, the United Mexican States apply and are obligated to comply with the Agency´s Basic Safety Standards and recommended safety conditions in the corresponding parts of the Agency's practical guidelines on the " safe operation of nuclear power plants " and the " safe design and construction of reactors”; as well as the Agency's guidelines on the "organization of regulatory activities for power reactors”, and the “siting of reactors from the point of view of seismic characteristics of the ground”. Additionally, the International Treaties are included in the Mexican legislative framework. Once approved by the Mexican Senate, they assume the legal status of a Mexican law. Mexico is signatory of the international treaties listed in Annex 7.1. Concerning the nuclear area, Mexico has also signed the bilateral treaties shown in Annex 7.2. Article 7 (2) (i) National safety requirements and regulations - Overview of the secondary legislation for nuclear safety Since the conception of the Laguna Verde Nuclear Power Plant (LVNPP), government authorities decided that, in addition to applying the regulations of the IAEA, the regulations of the nuclear steam supply system supplier’s country of origin would be applied. This requirement is stated in Condition No. 3 of the Commercial Operation Licence for both LVNPP Units. For this reason, Title 10 “Energy” of the United States of America (US) Code of Federal Regulations (CFR), and all industry standards and guidelines issued from this title were established as a regulatory requirement. Similarly the Regulatory Guidelines issued by the US Nuclear Regulatory Commission (NRC) have been adopted. Radiation safety matters are regulated based on the General Regulation for Radiation Safety, which entered into force on November 23, 1988. This Regulation stipulates requirements on the Dose Limit System (Title Third), the Licence holder, the Responsible for Radiation Safety and Occupationally Exposed Personnel (Title

2007-2009 Period 7-5

Page 34: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Seventh); on Radiological Accidents and Preventive or Safety Measures (Title Ninth); on Approvals, Permits and Licences (Title Tenth); and Administrative Procedures (Title Eleventh), which includes inspections, audits and examinations, as well as sanctions and the motion for reconsideration. There are also the Regulations for Hazardous Materials and Waste Ground Transportation, which came into force on April 8, 1993. These regulatory provisions apply for transport of Class 7 materials "Radioactive Materials". The Department of Communications and Transport is the competent authority, however, this does not exclude the Department of Energy’s authority, through the CNSNS, to grant authorizations for transportation of nuclear and radioactive materials. Under the Mexican legislation is also the Law of Civil Liability for Nuclear Damages, which came into force on January 1, 1975. This Law establishes an indemnity financial system for people affected by a nuclear accident. As noted by this Law, the operator is responsible for all damage caused by any nuclear accident occurring in a nuclear installation under its charge. CFE is the sole entity authorized to generate electricity using nuclear fuels (Article 15). Besides the Nuclear Law, there is also the General Law of Ecological Equilibrium and Environmental Protection, which came into force on January 29, 1988 and whose decree by which amends, adds and repeals itself, came into force on December 14, 1996. Article 154, Chapter VII “Nuclear Energy”, of this Law states that "The Department of Energy and the National Commission for Nuclear Safety and Safeguards (CNSNS), with the participation, if needed, of the Department of Health, will supervise that the radioactive minerals exploration, exploitation and benefit, the use of nuclear fuels, nuclear energy applications and in general, activities related to it; are conducted in nuclear and radioactive facilities with adherence to the official Mexican standards on nuclear and radiation safety, and physical security to avoid human health risks and ensure the ecological equilibrium preservation and environmental protection, corresponding to the Department of Health to carry out an environmental impact assessment." The Law mentioned above gives the Department of Environment, Natural Resources and Fishing the authority to perform the environmental impact assessment. However, it is important to mention that the evaluation of the nuclear installations effect on the environment, from the radiation safety standpoint, corresponds to the CNSNS. - Overview of regulations and guides issued by the regulatory body Normalization is the process to regulate the activities performed by both private and public sectors in different areas, such as nuclear. These instruments can be Mexican Official Standards, Mexican Standards and Reference Standards, which are abided by the provisions of the Federal Law on Metrology and Normalization.

2007-2009 Period 7-6

Page 35: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

In regard to the Mexican standards on nuclear and radiation safety, during the 2007-2009 period, the Mexican government issued the following revisions: NOM-028-NUCL-2009 "Radioactive Waste Management in Radioactive Installations which Use Open Sources" and NOM-034-NUCL-2009 “Requirements for Selection, Qualification and Training of Nuclear Power Plant Personnel.". A complete list of rules on nuclear matters is located in the Annex 7.3. - Overview of the process of establishing and revising regulatory

requirements, including the involvement of interested parties It is one of the duties of the CNSNS, as an agency of the Federal Administration, to help out integrating the National Normalization Programme with proposals and preparation of Mexican Official Standards (MOS) on nuclear safety. Mexican Official Standards are mandatory technical regulations, issued by competent agencies, establishing applicable rules, specifications, attributes, guidelines, characteristics or directions for a product, process, installation, system, activity, service or, production or operation method, as well as those relating to terminology, symbology, packaging, or labeling and those that relate to their enforcement or implementation. The Federal Law on Metrology and Normalization establishes a uniform procedure for the preparation of MOSs by the agencies of the Federal Public Administration, which is summarized below.

1.- The topics to be prepared shall be included in the National Normalization Programme.

2.- The competent agency prepares the standard draft along with its Statement of Regulatory Impact (SRI), reviewing if there are other standards related to the subject. If applicable, the corresponding agencies will coordinate the preparation of a single MOS by subject or sector. Also the Mexican and international standards related to the subject of the standard draft should be taken into account.

3.- The standard draft is submitted to the corresponding National Advisory Committee of Normalization (NACN) – the stakeholders are included as part of this committee – to receive its comments in a period not exceeding 75 calendar days.

4.- The agency that developed the standard draft will provide well-substantiated answers to the comments made by the Committee, no later than 30 calendar days from the date on which they were submitted. If appropriate, it will make the corresponding changes. When the agency that presented the project, considers

2007-2009 Period 7-7

Page 36: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

that the comments submitted by the Committee are not relevant , it may request the committee chair the approval of the draft without changes.

5.- Once the NACN approves the standard draft, the corresponding agency sends it along with its SRI to the Federal Commission for Regulatory Improvement (FCRI), for its resolution.

6.- The agency responds to all the FCRI´s comments made about the standard draft and its SRI, incorporating to these documents the pertinent adaptations and modifications until the FCRI issues its final opinion about them.

7.- The standard draft ruled is submitted to the NACN for approval of its publication in the Official Gazette of the Federation as a MOS project. The stakeholders including the general public may make comments to the corresponding NACN in the following 60 calendar days.

8.- At the end of the 60 days, the corresponding NACN will review the comments received and, if appropriate, change the project within a period not to exceed 45 calendar days.

9.- The NACN will order the publication in the Official Gazette of the Federation of the answers to the comments received and the changes to the project, at least 15 calendar days before the publication of the MOS.

10.- Once approved by the corresponding NACN, the MOSs are issued by the competent agency and published in the Official Gazette of the Federation for its implementation.

The MOSs also shall be reviewed every five years and the Technical Secretariat of the National Commission for Normalization notified about the outcome of the review, otherwise they will lose their validity. Article 7 (2) (ii) System of licencing - Overview of the licencing system and processes including types of licenced

activity and, and the procedure for relicencing System description of the licencing system and its processes According to the provisions of the Nuclear Law, Chapter IV Articles 25 and 28, and Chapter VI Article 50 Fractions III, IV, V, VII and XIII, CNSNS has the authority for reviewing, evaluating and authorizing the bases for the siting, design, construction, operation, modification, cease of operations, definitive shutdown, and decommissioning of nuclear and radioactive installations; as well as everything related to the manufacture, use, handling, storage, reprocessing and transport of nuclear fuels and materials, radioactive materials and equipment containing them;

2007-2009 Period 7-8

Page 37: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

and the processing, conditioning, dumping, and storing of radioactive wastes; and any disposal of them. During the siting authorization, the CNSNS reviews the most important aspects related to the site where the installation will be built, including the parameters that may affect the design, including: the site seismology, severe weather (probable maximum hurricane, flash flood, tornado, etc) and other aspects of interest. Information concerning the current and future distribution of the population is also reviewed. Subsequently, in accordance with the provisions of the US 10 CFR for the licencing process, two stages have been established. The first one starts with the formal delivery of the Construction Permit Application accompanied by a characteristics description of the installation and essentially of the safety systems that the installation will have to ensure that it will not present an undue risk. Among the documents sent by CFE to the CNSNS to support the LVNPP application, are the following: (1) Preliminary Safety Analysis Report (PSAR) and (2) Preliminary Environmental Impact Assessment Report (PEIA). During this stage, the CNSNS reviewed the design criteria (structures, systems and components –SSC- characteristics, nuclear analysis, etc.) and particularly all the issues related to the impact of the site characteristics on the structures, systems and components design of the installation, and the impact of the installation on the environment. The review by the CNSNS includes questioning the applicant to resolve doubts from the reports, or the prescription of additional requirements if the current ones do not guarantee safety. After reviewing these reports, a technical report is sent to the Department of Energy to issue the Construction Permit. The report includes recommendations and conclusions about the installation’s safety. During the LVNPP construction, the CNSNS, through audits and inspections, supervised this phase to assure that the installation was built in accordance with the safety analysis report and the conditions set by the Construction Permit. Once the detailed design of the installation is finalized, the commercial operation licence can be requested. This requires that another detailed report on the plant’s safety be sent to the CNSNS. This report is called the Final Safety Analysis Report (FSAR). This document contains the same information as the preliminary report (PSAR); however, the information is no longer generic but specific to the installation. Also a Final Environmental Impact Report (FEIR) is prepared, which includes the environmental monitoring programme to be operative during the whole plant lifetime, to monitor the effect that the installation causes on the environment. All the measurements performed during at least five years prior to the plant´s operation are used as reference.

2007-2009 Period 7-9

Page 38: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

The FSAR review by the CNSNS includes assessing the actual operating conditions. The acceptance criteria for pre-operational testing, start-up testing (as well as its impact on the accident analysis) and during commercial operation (in the preliminary report they were generic) are reviewed too. The proposed technical specifications are also examined, which once approved by the CNSNS are part of the Operating Licence to govern the operation of the installation. The scope of activities for the inspection of the major safety components that will be performed during the plant’s lifetime (in-service inspection) is also evaluated. The training of the installation’s operational personnel is verified by examinations. When the construction progress is such that the safety related equipment and component testing can begin, the CNSNS’s personnel witnesses the tests and reviews the results, to verify that the equipment meets the design criteria. The FSAR original version reflects the plant’s detailed design. The FSAR is continuously updated right up to the start of commercial operation. After that, it is updated on a regular basis to reflect the installation’s “as built” condition. In order to support the granting of the operating licence, the CNSNS prepares a technical report with recommendations and conclusions. It is submitted to the Department of Energy, which following the recommendations may or may not grant the licence. Licence renewal procedure So far there has been no licence renewal, so there is no procedure for this activity in the CNSNS. However, considering that the licence holder plans to submit a licence renewal application for both LVNPP units, the development of the corresponding procedure has started based on the regulations of the country of origin of the reactor. - Involvement of the public and interested parties The Nuclear Law does not provide for citizen participation in public hearings. However, information related to the licensing system and its processes is available to the public and interested agencies in accordance with "Federal Law of Transparency and Access to Government Public Information" which came into force on June 12, 2002, and the recommendations from the Convention included in document INFCIRC/572/Rev. 2, September 2, 2002. - Legal provisions to prevent the operation of a nuclear installation without a

valid licence The legal provision to prevent operation of a nuclear installation without a valid license is provided for in Article 26 of the Regulatory Law of the Constitutional Article 27 on Nuclear Matters, stating that "The sitting, design, construction, operation,

2007-2009 Period 7-10

Page 39: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

modification, termination operations, decommissioning and dismantling of nuclear installations and radioactive, requires the authorization of the Department of Energy". Article 7 (2) (iii) System of regulatory inspection and assessment - Regulatory strategies

Recently, the CNSNS defined a new strategy to carry out an integral and systematic safety review of LVNPP through the Reactor Oversight Process (ROP). In this process, the resources and information obtained through the assessment and inspection procedures that the CNSNS has set up are taken advantage of. The Reactor Oversight Process is considered an additional method to the deterministic conventional forms of assessment, review and inspection activities that were taking place. The current orientation of these activities by the CNSNS is an integration of information obtained from both deterministic and probabilistic methods that contributes to a better safety assessment of the LVNPP. This the Reactor Oversight Process. - Overview of the regulatory inspection and assessment process with regard

to the safety of nuclear installations The purpose of the inspections conducted is to carry out an independent performance verification of the LVNPP and assess the condition of its facilities, and achieve a high degree of confidence that the safety objectives prescribed or approved by the CNSNS are met. The inspection process allows verifying the safety of the LVNPP. This review determines that the Licence holder:

1. Complies with all laws, regulations and applicable licence conditions as well as all the pertinent codes, guidelines, specifications and practices.

2. Is staffed with competent and effective management, has a good safety culture and self-assessment systems to ensure a satisfactory installation’s safety and the workers, the public and environment protection.

3. Achieves and maintains the required quality and behavior regarding both the safety related activities and the installation’s structures, systems and components (SSC) throughout its useful lifetime.

4. Has enough competent personnel to perform its work efficiently and safely both at all times and at all stages of the installation’s useful lifetime.

2007-2009 Period 7-11

Page 40: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

5. Determines, assesses and immediately corrects the deficiencies and the abnormal conditions and, if necessary, they are duly reported to the regulatory body.

6. Determines and properly assesses any other safety issue that is not specified in the authorization nor prescribed in the regulations.

Moreover, the Reactor Oversight Process allows carrying out a safety assessment of LVNPP, using the information of the findings documented by the CNSNS, and the reportable events, documented condition reports, and the analysis results of the Performance Indicators provided by the Licence holder. The Reactor Oversight Process is a risk-informed, tiered approach. There are key strategic areas called safety cornerstones that are logically aligned towards fulfilling the CNSNS’s mission. There are three key strategic areas: reactor safety, radiation safety, and physical security; and seven safety cornerstones, linked to the key strategic areas, covering the essential safety aspects of installation operation. Satisfactory licence holder performance in the seven cornerstones provides reasonable assurance that the CNSNS’s mission is being accomplished with no further action required. Otherwise, it is necessary to take the steps described later in the Action Matrix. The seven safety cornerstones are:

1.- Initiating events – Limit the events frequency. 2.- Core damage mitigating systems - Availability, reliability and capacity. 3.- Barrier Integrity: Fuel clad, pressure barrier and containment. 4.- Emergency Preparedness: Drills and actual emergencies appropriate

performance. 5.- Public radiation safety: Liquid and gaseous effluents, inadvertently release of

solid radioactive waste, environmental radiation monitoring and transport of radioactive materials within the power plant.

6.- Occupational radiation safety: Areas access control, radioactive materials control and application of ALARA criterion.

7.- Physical Security: Design basis threat and radiological sabotage. In addition to the seven cornerstones, there are three "cross-cutting" elements common to all of them. 1.- Human performance. 2.- Safety culture. 3.- Corrective action programme (CAP)

2007-2009 Period 7-12

Page 41: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

The oversight process begins by collecting information from two sources: Performance Indicators, which are informed quarterly to the CNSNS by LVNPP, and the inspections, which are motivated by different causes. The set of indicators and the inspections cover the safety cornerstones and the cross-cutting elements. The process continues with the assessment of this information. For the performance indicators, data is compared against prescribed thresholds, and for inspections, the inspection findings are first prioritized and then evaluated for safety significance using established procedures. The Performance Indicators information (data) and the inspections information (findings) are classified using a color codes. A given color combination results and the cornerstones affected are known. The resulting information allows assessing the Licence holder performance in the period of interest. This evaluation identifies five levels (Action Matrix) from best to worst in relation to safety significance. For each level, there is an associated information level and a regulatory response to the Licence holder to correct the situation. This response is gradual and relative to the significance that the Licence holder performance has on safety. The response includes meetings at different management levels between the CNSNS and the Licence holder, monitoring, supplemental inspections and other actions.

- Basic features of inspection programmes The basic features of the CNSNS’s inspection programme include a set of inspections both scheduled and responsive throughout the lifetime of the nuclear installation, and inspections to other relevant areas of both the LVNPP and its contractors to ensure compliance with regulatory requirements. Inspection methods include the review and assessment of the installation, procedures, records and documentation; supervision and staff interviews; and tests and measurements. Regulatory inspections are conducted by resident inspectors and non-resident special inspectors. The findings of these inspections are documented in inspection reports prepared by the CNSNS’s inspecting staff. The reports content include the objective, areas inspected, description of the activities conducted, findings and observations, inspection timeline, and conclusions. The reports are distributed. There is also a semi-annual supervision and a follow-up program of the inspection conclusions, in order to provide feedback to the baseline inspection programme. As indicated in Article 14.2 of this National Report, the inspection frequency depends on the type of activity and its significance for the installation’s safety. The baseline inspection programme indicates the minimum number of scheduled inspections to be performed during the period in which the installation performance has a "response from the installation" status. Additionally, the baseline inspection programme includes some inspections to verify: (1) the quality-related areas, (2) supervising groups and (3) the cross-cutting elements.

2007-2009 Period 7-13

Page 42: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

It should also be noted that sometimes, there might be a need to conduct supplemental inspections focused on: (1) Safety related emerging generic issues; (2) a specific objective when the Licence holder performs major maneuvers, such as functional testing after power upgrades or replacement of major components; (3) issues resulting from the performance assessment using the Performance Indicators and the findings of scheduled inspections; and (4) the response to operational events which should be evaluated on a case by case basis. Article 7 (2) (iv) Enforcement of applicable regulations and terms of licences - Power for legal actions In accordance with the provisions of the Regulatory Law of Constitutional Article 27, Chapter IV Articles 34, 35, 36, 37, 38, 39 and 40, and Chapter VI Article 50, Fraction XII, the CNSNS has the authority to execute enforcement actions and decree administrative sanctions. - Overview of enforcement measures available to the regulatory body To comply with the regulation, during the 2007-2009 reporting period, the CNSNS prepared the document "Guideline for Assessing the Impact on Safety of Non-compliances or Violations to the Regulatory Framework at National Nuclear Facilities", see Annex 7.3. In order to implement the criteria of the Guideline mentioned before, two procedures were developed to classify the significance of the non-compliances or violations, and then propose the corresponding enforcement actions or administrative sanctions. The first one assigns a Significance Level based on the evaluation of four factors (actual consequences, potential consequences, impact to the regulatory process and any willful aspects of the violation). The second procedure uses the Significance Determination Process (SDP) to determine the risk significance. The SDP assigns a color of green, white, yellow or red, depending on the risk significance. Green corresponds to the lowest risk and red to the highest risk. The Guideline as well as the procedures, stress regulatory requirements compliance and stimulates early detection and correction of non-compliances by the Licence holders. Thus, there are different types of enforcement actions that go from warning letters to sanctions and, eventually authorization revocation. In all cases, the LVNPP is required to correct the non-compliance, conduct a thorough investigation within an agreed period and take all necessary measures to prevent a recurrence. The CNSNS makes sure that the LVNPP has effectively implemented all the preventive and corrective measures, and the appropriate improvement actions.

2007-2009 Period 7-14

Page 43: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

- Experiences with legal actions and enforcement measures During the 2007-2009 reporting period, the CNSNS, using the Guideline and the procedures mentioned in the previous section, assessed the inspection findings documented by CNSNS and some Event Reports of the LVNPP. The results have shown that the reporting period LVNPP non-compliances have been of low safety significance that have not required a strong enforcement action or any administrative sanction.

2007-2009 Period 7-15

Page 44: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

ANNEX 7.1 INTERNATIONAL TREATIES SIGNED BY MEXICO ON NUCLEAR MATTERS APPLICABLE TO THE COMMISSION INTERNATIONAL ATOMIC ENERGY AGENCY

NAME DATE OF

SIGNATUREDATE OF

ENTRY INTO FORCE

NOTES

Treaty for the proscription of nuclear weapons in Latin America

February 14, 1967

September 20, 1967

As stated in Article 14, Mexico commits itself to submit semi-annual reports on the application of safeguards to nuclear materials in the country

Treaty on the non-proliferation of nuclear weapons

July 1, 1968 January 21, 1969

This Treaty obliges Mexico to keep an accounting and control system of nuclear materials subject to IAEA safeguards

Agreement for the application of safeguards related to the Treaty for the proscription of nuclear weapons in Latin America and the Treaty on the non-proliferation of nuclear weapons

September 27, 1972

September 14, 1973

Article 7 obliges Mexico to establish and maintain an accounting and control system of all nuclear materials subject to safeguards. Article 63 obliges Mexico to report changes in the inventory of nuclear materials and report the nuclear material balance

Subsidiary arrangements relating to the Agreement for the application of safeguards related to the Treaty for the proscription of nuclear weapons in Latin America and the Treaty on the non-proliferation of nuclear weapons

September 17, 1972

September 14, 1973

Under these Arrangements Mexico is obliged to provide the following: information on facilities and nuclear material outside them; reports on accounting and changes in the inventory; materials balance, together with the corresponding physical inventory report; and the transfer of nuclear material from or to our country

Vienna convention on civil liability for nuclear damages

April 25, 1989

July 25, 1989 The Convention obliges our country to cover the damage caused by an accident at a Mexican nuclear installation.

Convention on physical protection of nuclear materials

April 4, 1988 May 4, 1988 The Convention obliges Mexico to take appropriate measures, under its national legal framework and in accordance with international law, to ensure that the nuclear materials are protected during their transportation, use and storage.

Convention on prompt notification of nuclear accidents

September 26, 1986

June 10, 1988 This Convention obliges Mexico to be prepared to address radiological and nuclear emergencies, to facilitate the exchange of information with the IAEA and the signatory countries; in addition to provide information to the IAEA about any radiological or nuclear accidents. Mexico is also obliged to establish points of contact for the help and participate in IAEA exercises.

2007-2009 Period

7-16

Page 45: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

NAME DATE OF SIGNATURE

DATE OF ENTRY INTO

FORCE

NOTES

Convention on assistance in the event of nuclear accident or radiological emergency

September 26, 1986

June 10, 1998 The Convention’s objective is to provide and / or receive assistance in case of a nuclear or radiological accident. Mexico is obliged to establish points of contact for the help and participate in IAEA exercises.

Convention on nuclear safety

November 9, 1994

October 24, 1996

Mexico is obliged to prepare the annual report on the nuclear safety implemented in nuclear power reactors, participate in meetings of the Contracting Parties and to answer the questions posed by other country members

2007-2009 Period

7-17

Page 46: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

2007-2009 Period 7-18

ANNEX 7.2 BILATERAL AGREEMENTS SIGNED BY THE COMMISSION

NAME DATE OF SIGNATURE

DATE OF ENTRY INTO FORCE

NOTES

Australia: Agreement between the governments of Mexico and Australia for cooperation in the peaceful uses of nuclear energy and nuclear material transfer

February 28, 1992

Exchange of diplomatic notes

None

Administrative agreement on safeguards between the Department of Energy and the Australian safeguards office

May 26, 1994 May 26, 1994 The Commission is obliged to submit annual reports on nuclear materials imported from Australia

Canada: Memorandum of understanding for technical cooperation and exchange of information on nuclear regulatory issues

November 16, 1994

February 24, 1995 Exchange of diplomatic notes

The Commission is obliged to submit annual reports on nuclear materials imported from Canada.

Cuba: Agreement of cooperation between the Department of Energy and the Ministry of Science, Technology and Environment of the Republic of Cuba on nuclear and radiation safety

May 24, 1996 May 24, 1996 As part of this Agreement, several international cooperation actions took place.

Guatemala: Agreement of cooperation between the Commission and the General Directorate for Nuclear Energy of Guatemala on radiation safety

February 26, 1996

February 26, 1996 As part of this Agreement, several international cooperation actions took place.

Spain: Agreement of technical cooperation between the Commission and the Nuclear Safety Council of Spain

March 8, 1994 March 8, 1994 As part of this Agreement, several international cooperation actions took place.

United States of America: Agreement of cooperation between the Commission and the Nuclear Regulatory Commission on research of nuclear reactor safety

June 2, 1997. Extended on November 12, 2002

June 2, 1997. Extended on November 12, 2002

As part of this Agreement, several international cooperation actions took place.

Agreement between the Commission and the Nuclear Regulatory Commission on maintenance and implementation of thermo-hydraulics codes

June 2, 1997 June 2, 1997 As part of this Agreement, several international cooperation actions took place.

Page 47: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

Annex 7.3 Summary of Mexican Official Standards applicable to nuclear facilities

Standard Title Publication date

NOM-001-NUCL-1994 DOSE EQUIVALENT CALCULATION FACTORS Feb-6, 1996

NOM-002-NUCL-1994 (replaced by

NOM-002-NUCL-2004) LEAK AND TIGHTNESS TESTS FOR SEALED SOURCES Sep-2-2004

NOM-004-NUCL-1994 CLASSIFICATION OF RADIOACTIVE WASTE Mar-4, 1996

NOM-005-NUCL-1994 ANNUAL RADIONUCLIDE INCORPORATION LIMITS AND DERIVED

CONCENTRATIONS IN AIR FOR OCCUPATIONALLY EXPOSED PERSONNEL

Feb-16, 1996

NOM-006-NUCL-1994 CRITERIA FOR THE APPLICATION OF ANNUAL INCORPORATION LIMITS FOR CRITICAL PUBLIC GROUPS Feb-20, 1996

NOM-008-NUCL-2003 Version 1994.

Cancelled RADIOACTIVE CONTAMINATION CONTROL Dec-29, 2003

NOM-012-NUCL-2002 Version 1995.

Canceled

REQUIREMENTS AND CALIBRATION OF IONIZING RADIATION MONITORS Jun-19, 2002

NOM-018-NUCL-1995 METHODS TO DETERMINE ACTIVITY CONCENTRATION AND TOTAL ACTIVITY IN RADIOACTIVE WASTE PACKAGES Aug-12, 1996

NOM-019-NUCL-1995 REQUIREMENTS FOR LOW LEVEL RADIOACTIVE WASTE PACKAGES FOR THEIR DEFINITIVE STORAGE NEAR THE SURFACE Aug-14, 1996

NOM-021-NUCL-1996 LIXIVIATION TESTS FOR SOLIDIFIED RADIOACTIVE WASTE SPECIMENS Aug-4, 1997

NOM-024-NUCL-1995 REQUIREMENTS AND CALIBRATION OF DIRECT READING DOSIMETERS Aug-5, 1997

NOM-026-NUCL-1999 MEDICAL SURVEILLANCE FROM OCCUPATIONALLY EXPOSED PERSONAL TO IONIZING RADIATION Jul-5, 1999

NOM-028-NUCL-1996 RADIOACTIVE WASTE HANDLING IN RADIOACTIVE FACILITIES THAT USE OPEN SOURCES Dec-22, 1998

NOM-031-NUCL-1999 REQUIREMENTS FOR THE QUALIFICATION AND TRAINING OF THE OCCUPATIONALLY EXPOSED PERSONAL TO IONIZING RADIATIONS Dec-28, 1999

NOM-034-NUCL-2004 Version 2000.

Canceled

SELECTION, QUALIFICATION AND TRAINING REQUIREMENTS OF OCCUPATIONALLY EXPOSED PERSONNEL IN NUCLEAR POWER

PLANTS Aug-4, 2009

NOM-035-NUCL-2000 LIMITS FOR CONSIDERING A SOLID RESIDUE AS RADIOACTIVE WASTE May-19, 2000

NOM-036-NUCL-2001 REQUIREMENTS FOR FACILITIES FOR TREATMENT AND CONDITIONING OF RADIOACTIVE WASTE Sep-26, 2001

2007-2009 Period 7-19

Page 48: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

Summary of Mexican Official Standards applicable to nuclear facilities but outside the Commission’s competence

Standard Title

NOM-005-STPS-1998 HEALTH AND SAFETY CONDITIONS IN THE WORKPLACE FOR HANDLING, TRANSPORTATION AND STORING OF DANGEROUS

CHEMICAL SUBSTANCES

NOM-012-STPS-1999 HEALTH AND SAFETY CONDITIONS IN THE WORKPLACE RELATING TO THE MANUFACTURING, USE, HANDLING, STORING OR

TRANSPORTATION OF IONIZING RADIATION SOURCES

NOM-017-STPS-2008 SELECTION, USE AND HANDLING OF PERSONAL PROTECTIVE EQUIPMENT IN THE WORKPLACE

NOM-002-STPS-2000 SAFETY CONDITIONS - PREVENTION, PROTECTION AND FIRE FIGHTING IN THE WORKPLACE

NOM-010-STPS-1999 HEALTH AND SAFETY CONDITIONS IN THE WORKPLACE RELATED TO THE HANDLING, TRANSPORTATION, PROCESSING OR STORING OF

CHEMICAL SUBSTANCES ABLE TO CONTAMINATE THE WORK ENVIRONMENT

NOM-018-STPS-2000 SYSTEM FOR THE IDENTIFICATION AND COMMUNICATION OF RISKS AND HAZARDS FROM DANGEROUS CHEMICALS IN THE WORKPLACE

NOM-052-SEMARNAT-2005 THE CHARACTERISTICS, THE IDENTIFICATION PROCEDURE, CLASSIFICATION AND HAZARDOUS WASTE LISTINGS

NOM-053-SEMARNAT-1993 PROCEDURE TO PERFORM THE EXTRACTION TEST TO DETERMINE THE COMPONENTS THAT COULD MAKE A WASTE HAZARDOUS

BASED ON THEIR TOXICITY TO THE ENVIRONMENT

NOM-054-SEMARNAT-1993 PROCEDURES TO DETERMINE THE INCOMPATIBILITY BETWEEN TWO OR MORE WASTES CONSIDERED HAZARDOUS BY THE MEXICAN

OFFICIAL STANDARD NOM-052-ECOL-1993

NOM-133-SEMARNAT-2000 ENVIRONMENTAL PROTECTION. POLYCHLORINATED BIPHENYLS (PCBs). HANDLING SPECIFICATIONS

2007-2009 Period 7-20

Page 49: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTICLE 8. REGULATORY BODY 8.0 Obligations “Each Contracting Party shall establish or designate a Regulatory Body in charge of implementing the legislative and regulatory framework referred to in Article 7. It shall be invested with authority, competence, and appropriate financial and human resources to fulfill the responsibilities assigned.” “Each Contracting Party shall take appropriate measures to ensure effective independence between the Regulatory Body functions and any other organism or institution which is concerned with the promotion or utilization of nuclear energy.” Article 8 (1) Establishment of the Regulatory Body - Legal foundations and statute of the Regulatory Body Legal bases The Mexican United States Regulatory Body regarding nuclear safety, radiation safety and safeguards areas is the National Comisión Nacional de Seguridad Nuclear y Salvaguerdias (CNSNS), which was established by the Regulatory Law of Constitutional Article 27, on January 26, 1979. As mentioned in Article 7.1 of this National Report, the following articles of the Nuclear Law, amended in 1985, give support to the Commission’s functions: Articles 13, 17, 18, 19, 23, 28, 29, 32, 33, 34, 35, 36, 37 and 50. Statutes The CNSNS does not have statutes because it is a desconcentrated (see Article 7.1 of this report) agency under the Department of Energy, which has no legal personality nor patrimony of its own. - Mandate, mission and tasks Mandate The CNSNS was created by the Regulatory Law of Constitutional Article 27 on nuclear matters. Article 50, Fraction I of this Law states that it is a desconcentrated agency (see article 7.1, national requirements and provisions) under the Department of Energy. The CNSNS serves as the Regulatory Body responsible for overlooking nuclear and radiation safety, physical security and safeguards.

2007-2009 Period 8-1

Page 50: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Mission The CNSNS’s mission is: Assure that the activities which involve nuclear and radioactive materials and sources of ionizing radiation are carried out with maximum safety, taking into account the current technological developments. Tasks The main tasks carried out by the CNSNS are: development of regulations and guidelines; review and assess; licence, inspection and enforcement. It also performs other supplemental tasks, such as: emergency preparedness, examination and licensing of main control room operators; issuing licences and import permits; use, transport, and storage of radioactive materials; participation in technical assistance and international cooperation agreements; and independent execution of research and development projects or in association with other regulatory agencies or research centers, or academic institutions. - Authorities and responsibilities Authorities The primary attributions of the CNSNS are to propose and overlook the application of nuclear safety, radiation safety, physical security and safeguards standards and regulations for the operation of nuclear and radioactive installations, as well as the use, handling, transport and possession of nuclear and radioactive materials. Responsibilities The CNSNS’s responsibility is setting the bases and preparing the technical reports to grant the permits and licences for nuclear facilities by the Department of Energy. In the case of radioactive installations, the Commission has the authority to issue the corresponding licence. It is also responsible for conducting audits, technical visits, inspections and verifications to nuclear and radioactive facilities, including physical security and safeguards issues. The Commission has the authority, by law, to decree sanctions to the facilities that do not comply with the regulatory framework. Similarly, for the licensing of nuclear facilities operators, the Commission performs the evaluation of candidates through written examinations and simulator-based operational assessments, and when appropriate, it grants the operator’s licences. Additionally, according to the General Law of Ecological Equilibrium and Environmental Protection, the Commission is responsible for reviewing the environmental information contained in the licence applications of future plants, and the periodic reports submitted by operating plants during its operation, both to avoid undue risks to human health and ensure the preservation of ecological equilibrium and environmental protection. However, the Department of Environment, Natural Resources and Fisheries performs the environmental impact assessment. In addition, the Commission has an independent radiation

2007-2009 Period 8-2

Page 51: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

environmental monitoring system, through an isotopic analysis of environmental samples collected periodically in the plant’s vicinity and processed in the Commission own laboratory. The surveillance results allow verifying the consistency of the periodic reports presented by the Licence holder. - Organizational structure of the Regulatory Body Figure 8.1 shows the Commission´s organization, which has four Divisions. The four Divisions report to the General Director and have the following objectives: Nuclear Safety Division – Responsible for proposing the regulations on nuclear and radiation safety, as well as verifying their compliance at nuclear facilities. Radiation Safety Division – Responsible for proposing the regulations on radiation safety and verifying their application in radioactive installations. It is also responsible for the national systems of safeguards and the regulation of physical security at nuclear and radiation facilities, and operates the national system of environmental radiation surveillance. Technology, Regulation and Services Division – Responsible for updating and adapting the regulatory framework and providing technical support on nuclear safety, radiation safety, physical security and safeguards required by the Commission’s staff. It manages the information and communications technology system. Finance and Administration Division – Responsible for managing the human, financial and material resources, in accordance with applicable regulations and policies. It handles or provides the services that are generally required for the maintenance and conservation of the facilities and assets. The Commission also has the Legal and International Affairs Department, and the Emergency Committee, which both report to the General Director. - Development and maintenance of human resources over the past three

years The Commission currently has the following staff:

2007-2009 Period 8-3

Page 52: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Number of Positions

General Organization Structure 2003/ 2006

2007/ 2009

Difference

General Director Office 8 8 0

Nuclear Safety Division 33 30 -3

Radiation Safety Division 57 67 +10

Technology, Regulation and Services Division 26 33 +7

Finance and Administration Division 36 47 +11

Internal Controller Division 4 5 +1

TOTAL 164 195 + 26 - Measures to develop and maintain competence The Commission has systems to enroll the staff in training programmes to ensure their learning of appropriate skills, as well as the achievement and maintenance of adequate competence levels. In order to achieve this objective, the Commission relies on the following:

1.- General training about public service. 2.- Specialized technical training. 3.- Annual training programme.

However, despite the actions mentioned above, the qualification requirements for professional staff have not been formally established. As noted in the previous National Report, the Commission has started an analysis to define the requirements on knowledge, skills and attitudes that the staff involved in safety-related activities of nuclear facilities must have. However, in this reporting period there has not been substantial progress of this activity. Since safety culture is very important for the Commission’s activities; it was requested the approval for delivery of a basic training on "Fundamentals of nuclear and radiation safety." The training was approved and delivered to all Commission´s personnel as a strategic measure aimed to enhance the safety of nuclear facilities. Newly hired personnel coming directly from the universities may sometimes have limited knowledge on nuclear and radiological concepts. The procedure that has been adopted in these cases is to put the newly hired employees in a training programme, which includes the technical and scientific issues included in the responsibilities of the Commission. The safety culture is not only

2007-2009 Period 8-4

Page 53: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

promoted and taught in the classroom, a direct practical experience is also provided through on the job training. The Commission does not always have the means to recruit staff with sufficient knowledge and expertise in the areas of nuclear and radiation safety. In these cases, the newly hired employees are subject of a specific training programme, aimed to correct skills and knowledge gaps in those subjects. To develop and maintain the staff’s competence, personnel are enrolled in training programmes provided by other regulatory bodies. For instance, the US Nuclear Regulatory Commission has trained some of the Commission’s personnel about Boiling Water Reactors at the Technical Training Center facilities in Chattanooga, Tennessee. Likewise, training has been received from other international institutions of Spain, France, Germany, Argentina, Japan, Brazil, Philippines, etc. During the period of this national report, training has been received from several Mexican certified organizations, as well as by the International Atomic Energy Agency (IAEA) and other international regulatory bodies. Most of the training received during this reporting period was of technical nature, however some courses dealing with public administration have been applied in order to meet the goal of 40 hours of training per person per year. - Developments with respect to financial resources over the pasts three

years The total budget assigned to the Commission comes from the Mexican government. The allocation of financial resources in the last three years is shown below.

YEAR BUDGET

MEXICAN PESOS BUDGET

US DOLARS

2007 85,266,525.61 6,558,963.51

2008 80,237,598.95 6,172,122.99

2009 85,266,525.61 6,558,963.51 Because the Commission is a deconcentrated agency of the Department of Energy, there is no income from its operation; since the fees paid by users of radioactive material for its licensing, handling and transport are collected directly by the Federal Treasury.

2007-2009 Period 8-5

Page 54: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

- Statement of adequacy of resources The main challenges facing the Commission are related to the financial and human resources available for its operation. The saving policies established by the Federal Government have caused limited financial resources for its operation. In the last three years, there has not been a budget increment in spite of the fact that the activities in the nuclear and radiation areas have increased. Regarding human resources, the challenge facing the Commission is staff recruitment. The first generation was trained in nuclear engineering and accumulated nuclear and radiation experience. The second generation, that represents the largest number of current employees, has received training on their particular specialty and, additionally, has acquired the knowledge and experience of the first generation. However, due to the limited job offer in the industry and particularly in the nuclear field; the universities that offer a nuclear curriculum have been negatively impacted by a reduced enrollment. In fact they have faced situations of possible termination of operations; because the new generation is not interested in nuclear issues. It is foreseen that when the first and second generations retire, there will be a shortage of qualified professionals. - Quality management system of the Regulatory Body The Commission has an institution-wide Quality Assurance Plan since 1999. In particular, in the area of nuclear regulation, a Quality Management System (QMS) has been developed and implemented, which is regularly updated. The QMS includes all the processes carried out to meet the Commission’s regulatory responsibilities regarding nuclear facilities. This Quality Management System is based on the ISO 9000-2000 requirements and implemented through the procedures manual. In order to make the Quality Management System implementation more efficient, all processes were expected to be incorporated and training on the QMS to all personnel during the reporting period were implemented. Therefore, during the 2007-2009 period courses were delivered on the Quality Management System and, both the Quality Management Manual and the management procedures were updated. - Openness and transparency of regulatory activities The Federal Law of “Transparency and Access to Public Government Information” which came into force on June 12, 2002, establishes guidelines for classifying government information, so the only a vary small amount is confidential and not accessible to the public. In order to support the compliance with this Law, the federal government created the web-based application

2007-2009 Period 8-6

Page 55: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

INFOMEX, which the Commission uses to provide information to the public when requested. - External technical support Although the Commission has qualified personnel in various technical areas, in some instances, consultants from the National Institute for Nuclear Research and the national universities support some activities. The external consultants must provide a detailed written report. The report includes the bases and methods used for the assessment, the conclusions and any additional recommendation that may facilitate the Commission’s decision making process. Additionally, there is a contract clause that states that the consultants shall keep independence from the licence holder to avoid conflicts of interests. - Advisory committees Article 51 of the Regulatory Law of the Constitutional Article 27 on Nuclear Matters states: "The National Commission of Nuclear Safety and Safeguards will be headed by a Director General, and have an Advisory Council and the staff necessary to perform its attributions.” Likewise, Article 52 of the same Regulatory Law states: "The Advisory Council’s purpose is to advise the National Commission of Nuclear Safety and Safeguards. In order to achieve this goal the council will provide the technical support requested and perform the studies required to attend the consultations made by its President." The Advisory Council has not been created. Article 8 (2) Status of the Regulatory Body - Place of the Regulatory Body in the governmental structure The structure of the Department of Energy provides an office of the Undersecretary of Electricity. This office is responsible to support the whole operation of the Commission, according to the internal regulations of the Department of Energy. It is the responsibility of the Department of Energy to issue and update, through the Commission, the appendixes, technical standards, manuals and instructions, needed to develop, make explicit and identify options to comply with the provisions of the General Regulation for Radiation Safety. The Commission has the authority to interpret and apply this Regulation.

2007-2009 Period 8-7

Page 56: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Figure 8.2 shows the position of the Commission in the Federal Government organization. - Reporting obligations The Commission is required to file a monthly progress report to the Minstry of Treasury about the compliance with goals set up at the beginning of the fiscal year. It also has the obligation to provide the administration an annual accounting report to the Department of Energy. The report informs about the programmes executed and the results achieved by the Commission’s management. - Means by which effective separation of the Regulatory Body from the

agencies responsible for promotion of nuclear energy is ensured According to the provisions of the Regulating Law of Article 27 of the Constitution, on January 26, 1976, the National Commission of Nuclear Safety and Safeguards was created as a deconcentrated Agency of Department of Energy. This Law empowers the Commission as the responsible agency for all matters related to nuclear resources, control and surveillance of nuclear power production with maximum safety at nuclear facilities. The Commission is also responsible for assuring the adherence to the standards on nuclear and radiation safety, physical security and safeguards. It should be noted that the Regulating Law states that the Federal Executive Branch can also exercise these powers, through the Department of Energy. Moreover, Article 10, Fraction III of the Department of Energy Internal Regulations states that "The Under Secretaries and the Principal Officer have, within the scope of their jurisdiction, the attribution to coordinate the desconcentrated administrative agencies assigned to them by these Regulations or by the Secretary. They also assist the Secretary in coordinating those desconcentrated administrative agencies, assigned directly to him/her, within the scope of matters of their competence." Additionally, Article 33 of the same Internal Regulations states: "The desconcentreted administrative agencies shall be subject to the Department of Energy specific regulations and these Internal Regulations. In terms of the provisions of Article 17 of the Organic Law of Federal Public Administration the desconcentrated agencies are subordinated to the Department of Energy. The heads of the desconcentrated administrative agencies will meet with the Secretary to agree on matters within their competence and, for the most effective attention, and resolution of those matters, they may coordinately work with the corresponding Under Secretary." Finally, Article 19, Fraction XXIII of the same Internal Regulations states: "The General Director of Distribution and Supply of Electric Energy, and Nuclear Resources has the authority to enforce legal and administrative codes on nuclear matters and issue, if needed, the appropriate enforcing criteria."

2007-2009 Period 8-8

Page 57: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Fraction XXIV of the same article states: "The General Director of Distribution and Supply of Electric Energy, and Nuclear Resources has the authority to propose for approval of the Under Secretary for Electricity the draft of regulating provisions and, if necessary, regulation on the nuclear area." It can be concluded that the CNSNS is not administratively independent of the agencies responsible for promoting nuclear technology. Moreover Department of Energy Internal Regulations delegate to the Direction General of Distribution and Supply of Electricity , and Nuclear Resources, under the Undersecretary for Electricity the authority, assigned in the Nuclear Law to the Secretary of Energy for the same functions assigned to CNSNS. Furthermore, the signature of licenses for nuclear installations, previously the competence of the Secretary, has been delegated to the Director General of Distribution and Supply of Electricity, and Nuclear Resources. Although since its creation, the Regulatory Body has been conducting all its affairs with complete technical independence this disposition could challenge this independence.

2007-2009 Period 8-9

Page 58: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

DEPARTMENTOF ENERGY

GENERAL DIRECTOR

CNSNS

ADVISORYCOUNCIL

DIVISION OF TECNOLOGY,REGULATION AND SERVICES

DIVISION OF FINANCES AND ADMINISTRATIONDIVISION OF RADIATION SAFETYDIVISION OF NUCLEAR SAFETY

EMERGENCY COMMITTEE TECHNICAL ADMINISTRATIVE CONTROLLER

DEPARTMENT OF INTERNALAUDITAND CONTROL

AND EVALUATION

DEPARTMENT OFRESPONSIBILITIES AND

COMPLAINTS

DEPARTMENT OF LEGAL AND INTERNATIONAL MATTERS

DEPARTMENT OFREGULATION

AND SERVICES

DEPARTMENT OFTECHNOLOGY

DEPARTMENT OFEVALUATION

DEPARTMENT OFOPERATIONALVERIFICATION

DEPARTMENT OFRADIATION

INSTALLATIONS

DEPARTMENT OFENVIRONMENTAL

AND RADIATION SURVEY

DEPARTMENT OFPROCEDURES AND

REGULATIONS

DEPARTMENT OF PHYSICALSECURITY AND SAFEGUARDS

REGULATIONS ANDTRAINING

DOCUMENTCENTER

COMPUTER ANDINFORMATION

SYSTEMS

TRANSIENTS ANDACCIDENTS

RISK MANAGEMENT

LICENSE-BASEDMODIFICATIONS

ENGINEERING

OPERATIONALEXPERIENCE

CERTIFICATON AND OPERATIONS

PERFORMANCEVERIFICATON

INSPECTIONPROGRAM

RESIDENCY

OPERATIONALANALYSIS

MEDICAL ANDINVESTIGATION APPLICATIONS

INDUSTRIALAPPLICATIONS

RADIATION IMPACTAND

EMERGENCIES

RADIOCHEMISTRY

RELEVANTINSTALLATIONS

ELECTRONICS ANDDOSIMETRY

METHODS ANDANALYSIS

RADIATIONREGULATIONS

SAFEGUARDS

AREA OFPHYSICALSECURITY

REGULATORY ACTIONS DEPARTMENT

ENFORCEMENT

NEW REGULATION IMPLEMENTATION

UNITED MEXICAN STATESNATIONAL REPORT

NATIONAL COMMISSION ON NUCLEAR SAFETY AND SAFEGUARDS ORGANIZATION CHART

Figure 8.1

Period 2007-20098-10

Page 59: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

PRESIDENCY OF THE UNITED MEXICAN STATES

ELECTRIC RESEARCHINSTITUTE

(IIE)

NATIONALNUCLEAR RESEARCHINSTITUTE

(ININ)

FEDERALELECTRICITY COMMISSION

(CFE)[Decentralized body]

NATIONAL COMMISSION OFNUCLEAR SAFETY AND

SAFEGUARDS(CNSNS)

[Semi-autonomous body]

ENERGY REGULATORY COMMISSION (CRE)

[Semi-autonomous body]

NATIONAL COMMISSION FOR ENERGY SAVINGS

(CONAE)[Semi-autonomous body]

DEPARTMENT OF ENERGY

Period 2007-2009

Figure 8.2

8-11

Page 60: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTICLE 9. RESPONSIBILITY OF THE LICENCE HOLDER 9.0 Obligations "Each Contracting Party shall ensure that the foremost responsibility for the safety of a nuclear facility is assumed by the licence holder and take appropriate enforcement measures to assure that the licence holder meets its responsibilities." - Formulation in the legislation (quotation) assigning the prime responsibility

for safety to the licence holder The Regulatory Law of the Constitutional Article 27 on Nuclear Matters states in its Article 27 that "The nuclear facilities shall be staffed with the nuclear and radiation safety personnel required, and the head of the corresponding public agency shall be responsible for the strict compliance with applicable standards." Likewise, the Law of Public Liability for Nuclear Damages that entered into effect on December 29, 1974, provides in its Article 4 that “The operator’s public liability for nuclear damages is objective”; that is, the operator of the nuclear installation is responsible for potential damages that might be caused by the installation. - Description of the main means by which the Licence holder discharges the

prime responsibility for safety Nuclear safety of Laguna Verde Nuclear Power Station (LVNPS) Units 1 & 2 is CFE’s responsibility, through the Nuclear Power Plant Division, as accepted and observed in the Quality Assurance Plan. According to this plan, the CFE’s General Director keeps the obligation before the Commission for conducting a safe operation and design changes of the LVNPS Units 1 & 2, according to the guidelines established in the regulatory framework, Operation Licences, Operating Technical Specifications and Quality Assurance Plan. - Description of the mechanism by which the Regulatory Body ensures that

the licence holder discharges its prime responsibility for safety The main responsibilities defined by the Commission to be met by the Federal Electricity Commission, operator of the Laguna Verde Nuclear Power Station, are stipulated in the Operating Licence Terms of each of the units. The Commission has also established several mechanisms to guarantee that the Licence holder satisfies each one of the items related to the obligations acquired through the licence. These mechanisms include: 1) a baseline inspection program, 2)

2007-2009 Period 9-1

Page 61: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

periodic assessments of all important to safety activities, 3) evaluation of the design changes, operational events, and safety improvements resulting from the operational experience, and 4) classification of the findings identified during inspections and operational events to determine the significance on the plant’s safety. These activities lead to very frequent interaction between LVNPS and the Commission. The meetings and assessments agreements are documented and sometimes they generate mandatory requirements. As indicated Articles 8 and 14 of this National Report, the baseline inspections program is aimed to collect enough information about the performance of nuclear facilities and the Licence holder’s activities. This allows determining along with the performance indicators, when appropriate, if the Licence holder is meeting the safety objectives, and identify performance issues to enable the Regulatory Body to follow-up and take actions before safety is compromised. The inspections frequency depends on the type of activity and its significance for the installation’s safety. The baseline inspection program indicates the minimum number of scheduled inspections to be performed during the period in which the installation performance has a "response from the installation" status. Additionally, the baseline inspection program includes some inspections to verify: (1) the quality-related areas, (2) supervising groups and (3) the cross-cutting elements. The latter are programmed with a biennial frequency. Additional information about the functions and responsibilities of the Commission, as well as specific activities to verify that the LVNPS meets its responsibilities on safety are presented in Articles 8 and 14 of this National Report.

2007-2009 Period 9-2

Page 62: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTICLE 10. PRIORITY TO SAFETY 10.0 Obligations "Each Contracting Party shall take appropriate measures to ensure that all entities engaged in activities directly related to nuclear facilities shall establish policies that give due priority to nuclear safety." - Overview of the Contracting Party’s arrangements and regulatory

requirements regarding policies and programmes to be used by the licence holder to prioritize safety in activities for design, construction and operation of nuclear installations

Description of the agreements and regulatory requirements

Regarding the agreements and regulatory requirements to give priority to safety, Articles 19, 20, 21, 28, 32, 34, and 50 of the Regulatory Law of the Constitutional Article 27 on Nuclear Matters establish that of all facilities activities performed by the Licence holder, including planning, design, construction and operation as well as definitive shutdown and decommissioning, safety always has the highest level of importance.

Licence holder safety policies LVNPS safety policy is shown in Annex 10.1.

Licence holder safety culture programmes and development LVNPS does not have a specific safety culture programme; however, it has implemented a set of essential processes, which have been developed to create a sustainable framework for safety culture. This framework is shown in Annex 10.2 where the safety culture pyramid is described and is constructed with the regulatory framework and processes of continuous performance improvement. The development of the processes of continuous performance improvement consists of the following: 1. The safety culture is an integral part of the Policies, Vision and Mission. 2. Extensive on-site communication. 3. Observation programmes. 4. Continuous learning organization. 5. Monitoring the safety culture process.

2007-2009 Period 10-1

Page 63: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

6. Management process. 7. Process of effective and conservative decision-making. 8. Process for determining the operability of systems and components. 9. Systematic approach to training. 10. Housekeeping and materials conditions. 11. International agreements.

Arrangements for safety management LVNPS voluntarily established policies and the safety culture manual, which have been monitored through the implementation of continuous improvement processes and the evaluation of surveys that have been applied to installation staff.

Arrangements for safety monitoring and self-assessment LVNPS is collecting performance indicators data according to the requirements established in the Reactor Oversight Process (ROP), in order to compare LVNPS performance with similar plants and emulate the best international practices. As an example, in Annex 10.3 the results for the fourth quarter of 2009 are displayed. Performance indicators for radiation protection, industrial safety and environmental protection have also been developed. The self-assessment process is being used by LVNPS’s groups to identify opportunities for improvement. The process has improved significantly, both in quantity and quality of self-assessments. In 2008, more than 60 self-assessments were conducted both in LVNPS and the attention areas of industry. More than 120 condition reports, resulting from the self-assessments have also been documented, and more than 150 corrective actions have been implemented to correct the problems encountered. Additionally, in order to strengthen the safety culture and evaluate the improvements, an annual assessment is performed using the eight principles of the Institute of Nuclear Power Operations (INPO) / World Association of Nuclear Operators (WANO). The results from these evaluations are presented in Annex 10.4.

Independent safety assessments Currently, LVNPS is subject to two types of external assessments.

a) The first one, in compliance with the Licence and in accordance with the Operating Technical Specifications (OTS) requirement, an internal inspection and an audit to the fire protection programme and the quality assurance programme are performed at least every 12 months.

2007-2009 Period 10-2

Page 64: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

These inspections can be performed by CFE’s qualified personnel, external inspectors or by staff of a company specialized in fire protection or quality assurance. If CFE’s qualified personnel are chosen, then at least every three years the inspection and the audit must be performed by staff of a company specialized in the topics mentioned above.

b) The second type corresponds to external assessments that go beyond

regulatory requirements, such as International Atomic Energy Agency (IAEA) Assessment of Safety Significant Events Teams (ASSET), Operational Safety Assessment Review Team (OSART) and Safety Culture Assessment Review Team (SCART) missions and peer reviews carried out by WANO, because LVNPS is Level 3 member of this association since 1997.

Table 10.1 presents the external assessments conducted from 1997 to December 2006.

ASSESSMENTS DATE

WANO (Level 3 peer review)

November 1999

TÜV ANLAGENTECHNIK (Independent audit)

November 2000 to January 2001

WANO (Level 3 peer review)

December 2002

Table 10.1 LVNPS external assessments

Table 10.2 presents the external assessments carried out during the period 2007 and 2009 by IAEA (SCART) missions and WANO assessments (Mid cycle and peer review).

ASSESSMENTS DATE

WANO (Mid cycle review)

December 2007

WANO (Peer review)

February 2009

SCART November 2009

Table 10.2 LVNPS external assessments

2007-2009 Period 10-3

Page 65: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

The mid cycle review took place during December 2007 and focused on the implementation of the identified areas for improvement (AFI). The result was considered by WANO very satisfactory, since three out of four AFIs were positively rated (A: definitely resolved or B: in the process of resolution) and no AFI without improvement was found. In February 2009, a WANO Atlanta Center peer review was conducted at LVNPS. The areas of Operation, Maintenance, Engineering, Chemistry, Training, Industrial Safety, Protection Radiation, Planning, Organizational Effectiveness, etc. were reviewed. 15 areas for improvement and 5 strengths were identified as a result of the review, which allowed keeping a Level 2 rating according to the standard set by WANO. LVNPS is subject to these assessments approximately every two years. In October 2009, LVNPS received an IAEA SCART mission for the first time, with satisfactory results. The final report issued by the review group includes 35 strengths and 3 recommendations. The report highlights the robust safety culture found in the plant which was evident through interviews with workers, their performance as well as the processes of all the groups.

Quality management system LVNPS developed a Quality Management System (QMS), which consists of a set of documents such as: the quality policy, the organization manual, quality management manual, work procedures, quality records, and training programmes. The QMS has been audited by a certification company which granted a certified status for the following standards: (1) ISO 9001:2008 "Quality Management Systems", (2) ISO 14001:2004 "Environmental Protection Management System", and (3) NMX-SAST-001-2008 "Occupational Health and Safety." - Measures taken by licence holders to implement arrangements for the

priority of safety, such as those above and any other voluntary activities and good practices

The actions and good practices that the Nuclear Power Plant’s Division of CFE has implemented to improve the safety culture in its organization, are listed below.

1. Workshops on Safety Culture. The object of these workshops has been to reinforce the values to maintain an organizational Safety Culture through the following:

a) Stressing a high respect for nuclear technology. b) Increasing awareness, understanding and applying the Defense in Depth

(DID) concept.

2007-2009 Period 10-4

Page 66: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

c) Encouraging the development and implementation of the work and operation Good Practices.

2. Survey to measure the Safety Culture level.

Since 2006, various surveys have been applied to measure the Safety Culture level, considering the eight INPO / WANO principles from the document "Principles for a Strong Nuclear Safety Culture" as mentioned previously in Section “Self-assessment and agreements for safety monitoring” of this Article.

3. Safety Culture Performance Indicators.

The Nuclear Power Plant’s Division of CFE shares the performance indicators directly related to the Safety Culture via intranet with all CFE’s personnel. Currently, the CFE with IAEA assistance is complementing this set of indicators with others to show more directly aspects of Safety Culture. A division-wide procedure entitled "Safety Performance Indicators" is applied.

4. Assessment of LVNPS staff perceptions on Safety Culture. The surveys that the CFE has been implementing since 1998, changed in 2000 and 2006. In these instances, a brief questionnaire to measure the level of staff awareness regarding LVNPS Safety Culture was used. The results allowed reorienting the allocation of resources to the areas that need improvement and the surveys have also served as a way to verify the effectiveness of the actions taken.

5. Implementation and continuous improvement of the Safety Culture.

Several important actions have been implemented to provide continuous improvement on Safety Culture issues, as described previously in Section “Licence holder programmes on safety culture and development” of this Article.

- Regulatory process for monitoring and oversight of arrangements used by

the licence holders to prioritize to safety CNSNS evaluates the mechanisms used by LVNPS to give priority to safety. To this end, the recommendations established by the IAEA (TECDOC-369 "Management for Excellence in Nuclear Power Plant Performance") are followed to determine through the analysis of the inspection reports that:

1. There is an effective appointment of responsibility and authority. 2. There is the ability to anticipate, identify and correct problems. 3. A culture of quality is achieved and maintained.

2007-2009 Period 10-5

Page 67: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

4. The use of key resources is optimized. 5. There is a proper interface between organizations. 6. There is the ability to focus on long-term performance.

Every three months, the Commission holds a meeting with LVNPS to inform it about any weaknesses detected in the attributes listed above, with the objective that weakness be properly addressed.

- Means used by the regulatory body to prioritize safety in its own activities The CNSNS is advocating the expanded application of Probabilistic Safety Analysis (PSA) technology in all regulatory activities where it is technically feasible, considering the state of the art of PSA methods and data to complement the deterministic regulatory approach and support defense in depth philosophy. This position is aimed to increase the regulatory process efficiency and effectiveness by incorporating risk-based information to have a comprehensive decision-making, in order to reduce unnecessary burdens on the Licence holder. This approach also facilitates the allocation of the CNSNS and License holder’s resources and efforts on the most safety significant issues. In this regard, some of the mechanisms used by the Commission to give priority to safety in their own activities are: 1) the analysis and consideration of changes to regulations, regulatory guidelines, licensing requirements, inspection programmes and regulatory practices; 2) commitment on the allocation of resources that takes into account risk-based information, 3) take the appropriate actions to train the Commission´s staff so its personnel develop skills for the interpretation of risk-based information, while developing their activities; 4) perform the necessary actions to improve the PSA methods and analysis, and data collection of equipment and human reliability to support an extended use of PSA techniques in operative and regulatory activities; and 5) commitment to maintain and improve the licenced facilities safety level, as well as an open and easy communication with the License holder.

2007-2009 Period 10-6

Page 68: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

Annex 10.1

NUCLEAR POWER PLANT’S DIVISION

SAFETY CULTURE POLICY All of us, the employees that work in the Nuclear Power Plant’s Division, including the additional personnel (hourly employees and contractors) consider nuclear safety as the essential priority. The decisions and actions are based on this priority and they are followed-up to verify that the nuclear safety-related problems receive due attention. The work environment, our attitudes and behaviors, as well as the policies, training and procedures foster this culture. Safety culture.- is the organization’s behavior and values (leaders play a role model and employees make part of them) that place priority to nuclear safety above Production and Budget. All of us, the employees that work in the Nuclear Power Plant’s Division consider SAFETY top priority, taking conservative and efficient decisions, applying the human error prevention tools, using and adhering to procedures, and appraising continuous learning and fostering a SAFETY conscious work environment manifesting a questioning attitude without fear of retaliation.

We are committed to the following principles to achieve a strong NUCLEAR SAFETY CULTURE

Nuclear safety is responsibility of every one of us.

The leaders demonstrate compromise with safety.

Confidence spreads throughout the organization.

Decision making reflects that safety comes first.

Nuclear technology is recognized as special and unique.

The organization fosters a questioning attitude.

Organizational learning is adopted.

Nuclear safety is constantly evaluated.

RAFAEL FERNANDEZ DE LA GARZA, BS. MANAGER OF NUCLEAR POWER PLANT’S DIVISION

2007-2009 Period

10-8

Page 69: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

Annex 10.2

5. Safety Culture Survey6. Work Management Process7. Conservative and Effective Decision 

Making Process8. Operable/Operability Determination 

Process9. Systematic Approach to Training10. House Keeping and material 

condition11. International Agreement 

(INPO,WANO,NEI)

1.Mexican Regulatory Body  (CNSNS)2.Operation licensing and Technical Specification Compliance3.Safeguard International Agreement (IAEA).4.Convention on Nuclear Safety (IAEA)

1. Policy/Vision/Mission ( Safety Culture)2. Site Wide Communication3. Observation Programme4. Continuous Learning Organization

Corrective Action ProgrammeHuman Performance ProgrammeOperation Experience ProgrammeBenchmarking ProgrammeSelf Assessment Programme

5. Reactor Oversight Process6. Quality Assurance 

Programme7. 50:59 Evaluation Programme8. Quality Control Programme9. Independent Safety 

Engineering Unit

2007-2009 Period

10-9

Page 70: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

Annex 10.3

PERFORMANCE RATING DISPLAY BASED ON PERFORMANCE INDICATORS

U1

Q1/09 Q2/09Q3/09 Q1/09 Q2/09Q3/09 Q1/09 Q2/09 Q3/09 Q1/09 Q2/09 Q3/09 Q1/09 Q2/09 Q3/09 Q1/09 Q2/09 Q3/09 T1/07 T2/07 T3/07

Q1/09 Q2/09 Q3/09 Q1/09 Q2/09Q3/09 Q1/09 Q2/09 Q3/09 Q1/09 Q2/09 Q3/09 T1/07 T2/07 T3/07

Q1/09 Q2/09 Q3/09 Q1/09 Q2/09Q3/09 Q1/09 Q2/09 Q3/09

Q1/09 Q2/09Q3/09 Q1/09 Q2/09 Q3/09

Q1/09 Q2/09Q3/09

Q1/09 Q2/09Q3/09

Q1/09 Q2/09Q3/09

Emergency Preparedness

Occupational Radiation

Safety

Public Radiation

Safety Initiating Events

Scrams with Loss of Normal Heat

Removal (G)

Unplanned Scrams (G)

Radiological Effluent ODCM /

OTS Reactor Coolant

System Activity (G)

Unavailability of RHR System (G)

Unplanned Power Changes (V)

Unavailability of Emergency Diesel Gen. System (G)

Unavailability of HPCS System (G)

Unavailability of RCIC System (G)

Alert and Notification System

Reliability (G)

EREP Loudspeaker Testing (G)

Occupational Exposure Control Effectiveness (G)

Functional Failures of Safety Systems

(G)

Drill / Exercise Performance (G)

Maintenance Rule Application I & II (G)

(V)

Radiation Safety

Emergency Response Organization Drill Participation (G)

Reactor Coolant System Leakage

(G)

Maintenance Rule Application III & IV

(G)

Barrier Integrity

Mitigating Systems

Reactor Safety

Keys: Green (G) = Acceptable performance White (W) = Acceptable performance but out of the normal expected range Yellow (Y) = Acceptable performance with minimum reduction of safety margins Red (R) = Out of design basis Blue (B) = Incomplete data or not provided by responsible area

2007-2009 Period

10-10

Page 71: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

U2

Q1/09 Q2/09Q3/09 Q1/09 Q2/09Q3/09 Q1/09 Q2/09 Q3/09 Q1/09 Q2/09 Q3/09 Q1/09 Q2/09 Q3/09 Q1/09 Q2/09 Q3/09 T1/07 T2/07 T3/07

Q1/09 Q2/09Q3/09 Q1/09 Q2/09Q3/09 Q1/09 Q2/09 Q3/09 Q1/09 Q2/09 Q3/09 T1/07 T2/07 T3/07

Q1/09 Q2/09 Q3/09 Q1/09 Q2/09Q3/09 Q1/09 Q2/09 Q3/09

Q1/09 Q2/09Q3/09 Q1/09 Q2/09 Q3/09

Q1/09 Q2/09Q3/09

Q1/09 Q3/09

Q1/09 Q2/09Q3/09

Emergency Preparedness

Occupational Radiation

Safety

Public Radiation

Safety Initiating Events

Scrams with Loss of Normal Heat Removal (W)

Unplanned Scrams (G)

Radiological Effluent ODCM /

OTS Reactor Coolant

System Activity (G)

Unavailability of RHR System (G)

Unplanned Power Changes (V)

Unavailability of Emergency Diesel Gen. System (G)

Unavailability of HPCS System (G)

Unavailability of RCIC System (G)

Alert and Notification System

Reliability (G)

EREP Loudspeaker Testing (G)

Occupational Exposure Control Effectiveness (G)

Functional Failures of Safety Systems

(G)

Drill / Exercise Performance (G)

Maintenance Rule Application I & II (G)

(V)

Radiation Safety

Emergency Response Organization Drill Participation (G)

Keys: Green (G) = Acceptable performance

Q2/09

Reactor Coolant System Leakage

(G)

Maintenance Rule Application III & IV

(G)

Barrier Integrity

Mitigating Systems

Reactor Safety

White (W) = Acceptable performance but out of the normal expected range Yellow (Y) = Acceptable performance with minimum reduction of safety margins Red (R) = Out of design basis Blue (B) = Incomplete data or not provided by responsible area

2007-2009 Period

10-11

Page 72: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

Annex 10.4

ANNUAL SURVEY ON SAFETY CULTURE - 2009

2006 2007 2008 2009

No. SAFETY CULTURE PRINCIPLES % EVAL % EVAL % EVAL % EVAL 1. Nuclear safety is responsibility of every

one of us 88.7 VERY

GOOD 91.9 VERY GOOD 92.6 VERY

GOOD 91.8 VERY GOOD

2. The leaders demonstrate compromise with safety

78.4 GOOD 77.6 GOOD 80.9 GOOD 79.7 GOOD

3. Confidence spreads throughout the organization

75.2 GOOD 78.6 GOOD 81.0 GOOD 81.3 GOOD

4. Decision making reflects that safety comes first

82.1 GOOD 83.2 GOOD 86.8 VERY GOOD 85.8 VERY

GOOD

5. Nuclear technology is recognized as special and unique

89.2 VERY GOOD 88.7 VERY

GOOD 89.9 VERY GOOD 90.7 VERY

GOOD

6. The organization fosters a questioning attitude

82.5 GOOD 88.0 VERY GOOD 90.2 VERY

GOOD 89.7 VERY GOOD

7. Organizational learning is adopted 77.3 GOOD 80.9 GOOD 82.0 GOOD 82.7 GOOD

8. Nuclear safety is constantly evaluated 83.0 GOOD 84.4 GOOD 86.5 VERY GOOD 86.2 VERY

GOOD 9. Status and physical condition of the

plant 86.5 VERY

GOOD 83.0 GOOD 86.2 VERY GOOD 88.2 VERY

GOOD

TOTAL 82.5 GOOD 84.0 GOOD 86.2 VERY GOOD 86.2 VERY

GOOD

EVALUATION CRITERIA RANGES EVALUATION COLOUR

85 % ≤ X< 100 % VERY GOOD GREEN 75 % ≤ X < 85 % GOOD WHITE 65 % ≤ X < 75 % SATISFACTORY YELLOW 1 % ≤ X < 65 % NON SATISFACTORY RED

RESULT

• The table shown above presents the results after processing the LVNPS personnel answers

• The survey results indicate that Safety Culture in Nuclear Power Plant’s Division of CFE was rated as “Very Good” (range 85% - 100%) in 6 principles and “Good” (range 75% - 85%) in the other 3 principles.

• The survey results indicate an acceptable Culture Safety at LVNPS with a tendency to keep improving.

2007-2009 Period

10-12

Page 73: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTICLE 11. FINANCIAL AND HUMAN RESOURCES 11.0 Obligations "Each Contracting Party shall take appropriate measures to ensure the availability of enough financial resources to maintain the safety of each nuclear installation throughout its lifetime.” “Each Contracting Party shall take appropriate measures to ensure the availability of qualified and sufficient personnel with appropriate academic background, training and retraining, to cover all safety-related activities in or for each nuclear installation throughout its lifetime.” Article 11 (1) Financial resources - Mechanisms for the provision of financial resources to the licence holder

or applicant in order to ensure safety of the nuclear installation throughout its lifetime

Principles for the financing of safety improvements to the nuclear

installation over its operational lifetime Financial resources to assure a safe and reliable operation and maintenance of LVNPS come from the Federal Government- They are requested via the application for authorization of the budget as part of the strategic and operative programmes of the fiscal year. The Operation and Maintenance expenditures are privileged at LVNPS as compared to the rest of CFE’s facilities; since the requirements of the Mexican Regulatory Body must be met to maintain the Operating Licence of the generation units. The management process of the financial resources contributes to meeting the plant safety standards during normal operation and refueling outages and major maintenance programmes. The improvements, additions and replacements of structures, systems and main components of the production-related buildings are considered in a business plan, supported on the strategic objectives, and have the ultimate goal of ensuring the their reliability. The financial resources management for improvements is based on a cost benefit analysis whenever it is proved that the investment will bring added value and be profitable.

2007-2009 Period 11-1

Page 74: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Principles for financial provisions during the period of commercial operation for decommissioning and management of spent fuel and radioactive waste from nuclear installations

The provision for decommissioning costs, handling and disposal of radioactive waste from the plant at the end of its lifetime is booked and appear in the financial statements. The accrual is calculated based on the provision jointly issued by the LVNPS and CFE corporate offices. These indicate that starting January 1999, the LVNPS is integrating a fund equivalent to $ 0.00026 US dollars/kWh generated, as part of production costs for future storage of radioactive waste and decommissioning. Safe Storage (SAFSTOR) has been chosen as the decommissioning strategy for LVNPS, which is in accordance with the provisions of NUREG/CR-6174 and defines five stages of work: a) Planning, regulatory assessment, engineering and preparation for final reactor

shutdown. b) Ceasing plant operation and preparing for decommissioning. c) Safe removal of spent fuel from reactor vessel, and storing it in the fuel pool (5

to 6 years). d) Extended period for fuel safe storage (approximately 60 years). e) Decontamination and dismantling at the end of the Licence period for

decommissioning (60 years). - Statement with regard to the adequacy of financial provisions

The information about the allocation and expenditure of financial resources and the accounting accruals of LVNPS are presented in the Profit and Loss (P&L) Statement and the Statement of Financial Position. - Contracting Party’s processes to assess the financial provisions

According to Article 27 of the constitution, nuclear energy generation and regulation belongs exclusively to the state, so the state is responsible for securing the financial resources for the safe operation of the installation. Article 11 (2) Human resources - Overview of the Contracting Party’s arrangements and regulatory

requirements concerning staffing, qualification, training and retraining of staff for nuclear installations

2007-2009 Period 11-2

Page 75: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

For staffing, qualification, training and retraining of staff for nuclear installations, the Commission and the Licence holder agreed at the outset to implement the requirements of standard ANSI / ANS 3.1-1981 "Selection, Qualification and Training of Personnel for Nuclear Power Plants." However, in the case of nuclear power plants, on November, 2000 the requirements of the Mexican Official Standard NOM-034-NUCL-2000 "Requirements for Selection, Qualification and Training of Personnel for Nuclear Power Plants” entered into force. It should be noted that this standard was subjected to the five-year review process. The new version was published in the Official Gazette of the Federation, on Monday, August 3, 2009.

• Human resources of CFE / Nuclear Power Plant’s Division The workforce of the Nuclear Power Plant’s Division of CFE amounts to 1322 permanent employees as of December 2006.

• Organization of CFE / Nuclear Power Plant’s Division The organization of CFE currently has a General Director; four Under Directors of the following offices: Projects of financed investment, Finance, Administration, and Operation; and one Under Delegated Director of the office of Modernization and Structural Change. Figure 11.1 shows the current organization of CFE. - Methods used for the analysis of competence requirements and training

needs for all safety related activities in nuclear installations The Systematic Approach to Training (SAT) is applied at LVNPS since 2006, to define the training requirements of the personnel performing safety-related activities. The starting point to define the competencies required for each particular position is the Job Task Analysis (JTA) based on the job description. The result from the JTA is the set of competencies that need to be developed and maintained by personnel for a given position. The selection of the method to achieve the competencies required is based on the information available, which may be one of the following: - Task analysis. - Competency analysis by group of tasks. - Competency analysis based on learning objectives. - Competency analysis based on guidelines.

2007-2009 Period 11-3

Page 76: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

The objective of the training needs analysis is to determine if changes to processes and procedures, plant modifications, reworks, use of new technology, actual or potential performance weaknesses, internal or external operational experience, etc. require training or implementation of other actions to prevent or correct performance weaknesses. Once the issue or weakness is identified, the technical area generates a request for training needs analysis. This request may also be generated after evaluating the area performance or whenever the Department Head considers appropriate and calls for a meeting with the Training Committee for their attention. At that meeting, the corrective or preventive actions to be taken are defined. These actions provide feedback to the training programmes in order to make them more both efficient and effective. - Arrangements for initial training and retraining of operations staff,

including simulator training The initial training for Reactor Operators is a classroom course on nuclear technology, complemented with hands-on Classroom Simulator. After about a year, the trainees are sent to the plant to temporary fill in the position of Field Operator to become familiar with all plant activities, always under the supervision of the holder of such position. Subsequently they take a simulator course in the LVNPS full scope simulator, after which the candidate is assigned to the Main Control Room. Finally they are prepared for the Licence examination reviewing some topics, including both classroom and simulator-based training on the Emergency Procedures. Retraining is delivered every two years and combines at least 40 hours of plant simulator and 60 hours of classroom per year. The retraining covers plant systems, abnormal operation and emergencies, internal and external operational experience, administrative procedures, etc. Additionally, before every refueling outage, training is delivered whose content covers, among others, the changes to be implemented, fresh fuel, Operating Technical Specifications and plant start-up on the simulator. - Capabilities of plant simulators used for training with regard to fidelity to

the plant and scope of simulation The full scope simulator was modernized in 2005 with a new software platform. Likewise, the updates necessary to maintain physical fidelity, with respect to the LVNPS Unit 2 which is the referenced unit, were completed. - Arrangements for training of maintenance and technical support staff

2007-2009 Period 11-4

Page 77: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Training of maintenance and technical support personnel is delivered according to procedures which describe the training curriculum. The procedures describe different delivery forms for training (classroom, laboratory, on the job training, interim assignments, etc.). Classroom courses focus mainly on theory while laboratory-based courses include theory fundamentals supplemented with practical exercises on mock-ups. During the initial training, the trainees attend classroom courses or laboratory-based courses. Then they are assigned to the area in which they are being trained. The assignment duration is oriented to help the technicians “under training” acquire the skills necessary to complete the qualifications as technicians. During this period, the trainees keep attending training such as interim assignments or on the job training, as well as classroom and laboratory training, or other complementary training. Later, during retraining, personnel is trained in those topics that are identified as necessary for maintaining their qualifications. The topics include the actions resulting from the Requests for Training Needs Analysis, Operational Experience, refresher training or specific needs resulting from personnel performance. - Improvements to training programmes as a result of new insights from

safety analyses, operational experience, development of training methods and practices

The external operational experience has required improving the procedures, and post-drill critique techniques and the use of human performance tools. Improvements have also been implemented to classroom, full scope simulator, process simulator, workshops and mock-ups training. In this regard, since 2006 there is a classroom simulator of the plant. The simulator uses the same software and models that the full scope simulator and has touch screen technology that helps interaction with the main screen displays. Additionally, since 2008 a hydraulic loop or Process Simulator went into operation for practical training on technical subjects, reinforcing the adherence to plant standards, and application of error prevention techniques. - Methods used to assess the sufficiency of staff at nuclear installations

Personnel are evaluated on theoretical aspects through written examinations and the practical skills are assessed in the simulator. The evaluation is also complemented using on the job training guidelines and Performance Standards. The job performance is evaluated by observers, using an evaluation card. The results are used to determine a performance indicator to take corrective actions when deviations are identified.

2007-2009 Period 11-5

Page 78: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

- Policy or principles governing the use of contracted personnel to support

or supplement the Licence holder’s staff The principles governing the use of contractor personnel to support or supplement LVNPS staff are established considering two types of contractors:

1. Contractors who carry out their activities under the responsibilities of the Quality Assurance Programme of the Nuclear Power Plant’s Division and / or

2. Contractors those are evaluated and qualified by the Quality Assurance

department of the Nuclear Power Plant’s Division, to perform safety-related activities under their own Quality Assurance Programme.

Also the following procedures are established: - PAA-02 establishes the general administrative process for biddings and

preparing contracts. - PAS-13 establishes the participation of the Quality Assurance department in the

process of contracting safety significant services. - PAG-27 provides guidelines for the receipt of work performed by contractors to

ensure that all work and its associated documentation are properly completed and delivered to CFE.

- Methods used to assess the qualification and training of contractor’s

personnel Contractors performing safety-related functions are required to present evidence of qualifications of their staff. The documents are evaluated by the Quality Assurance department and the contracting area. The qualification and training requirements of such personnel are stipulated in the corresponding contract. - Description of the national supply of, and demand for, experts in nuclear

science and technology As stated in Article 8, Section “Measures to develop and maintain competence” of this National Report, there is very low demand of nuclear professionals because there is only one operating nuclear plant in the country; therefore, the supply of students and graduates from the few universities and institutes of technology that offer nuclear engineering programmes, is very low.

2007-2009 Period 11-6

Page 79: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

- Regulatory review and control activities The CNSNS evaluates the following: (1) on an annual basis - the revisions of the initial training and retraining programmes of the personnel required in 10CFR50.120 (Systematic Approach to Training) and the personnel performing safety-related activities; (2) on semi-annual basis - the performance of the technical staff of the areas of maintenance (electrical, mechanical and, instrumentation and control), chemistry, radiation protection, plant engineering, design engineering, reactor engineering and Field Assistant Operators, and (3) on a quarterly basis - the performance of reactor operators and supervisors, as well as the performance of the LVNPS full-scope simulator. As part of the control measures established by the Commission is the preparation of the following: (1) the semi-annual results report on the implementation of the Systematic Approach to Training for the personnel specified in 10CFR50.120 and reactor engineering; (2) the quarterly results report on the retraining cycles of reactor operators and supervisors; (3) the annual results report on the evaluation of reactor operators and supervisors; and (4) the biennial programme of retraining for the reactor operators and supervisors. The reports mentioned above are reviewed by the specialist staff of the Commission. The purpose of the review is to verify that the personnel qualification and training requirements are met at all times, since they are key for the safe operation of nuclear facilities. For the case of contractors’ personnel, the Commission has established that the staff of those companies or organizations engaged in any activity or function for more than a year must meet all regulatory requirements for such activity or function. When an interim activity or function is performed for less than one year, the Commission, as part of its baseline inspection programme, verifies that the staff of the contractors accredited to the nuclear installation, are duly qualified to perform the task assigned. The verification is performed as follows:

1) Contractor documents which were used to qualify its personnel to perform the assigned task; or

2) Previous verification of the contractor's personnel ability to perform the task assigned, by personnel of the nuclear installation; or

3) Successful completion by the contractor's personnel of those Licence holder´s training programme segments regarded as necessary to perform the task assigned.

2007-2009 Period 11-7

Page 80: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

11-8 Period 2007-2009

UNITED MEXICAN STATES

NATIONAL REPORT

Page 81: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

NPP DivisionIndependent Operation Review Committee (CIRO)

Independent Safety Engineering Group (GIIS)

External Project Coordinating Unit

Legal Department

Site Operations Review Committee

(CROS)General Manager of Operation

Production Maintenance Nuclear Safety Engineering Administration Services

Operation U-1

Operation U-2

Chemical Engineering

Radioactive Waste

Work Management

Radiation Protection

Reactor Engineering

Refueling

Internal Emergency Plan

Mechanical

Electrical

Instrumentation and Control

Construction Support

Special Programs

Technical Support

Quality Assurance

Quality Control

Licensing

Operational Experience and

Evaluation

Enviromental Engineering

Industrial Safety

Corrective Action

Medical Services

"Fix it now" Team

Radioactive Waste Final Disposal

Coordination of projects

Design Engineering

Site Engineering

Systems Engineering

Technical Management

Supplies

Technical and Administrative Management

Work and Administrative

Services

Accounting

Financial Management

Training

Telecommunications

Communications

Infrastructure

PIDIREGAS

Figure 11.2

FEDERAL COMMISSION OF ELECTRICITY (CFE) NUCLEAR POWER PLANT DIVISION ORGANIZATION CHART

UNITED MEXICAN STATES NATIONAL REPORT

11-9 Period 2007-2009

Page 82: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTÍCULO 12. HUMAN FACTORS

12.0 Obligations "Each Contracting Party shall take appropriate measures to ensure that the capabilities and limitations of human performance are taken into account over the lifetime of a nuclear installation." - Overview of the Contracting Party’s arrangements and regulatory

requirements to take human factors and organizational issues into account for the safety of nuclear installations

As mentioned in Article 7, since the inception of the Laguna Verde Nuclear Power Station (LVNPS) Project, government authorities decided that, in addition to applying the regulations of the International Atomic Energy Agency (IAEA), the regulations of the nuclear steam supply system supplier’s country of origin would be equally applied. This requirement is stated in Condition No. 3 of the Commercial Operation Licence for both LVNPS Units. For this reason, in the Mexican regulation the 10CFR50.34(f)(2)(iii) is applied, which requires a variety of controls and displays as aid to the operator, and a control room that reflects the state of art of the Human Factors Engineering principles. - Consideration of human factors in the design of nuclear installations and

subsequent modifications (see also Article 18.3) As a result of the accident at Three Mile Island Nuclear Power Plant in 1979, the United States Nuclear Regulatory Commission (USNRC) published the document NUREG-0660, and later on NUREG-0737 and its Supplement No. 1. These documents required a detailed revision be performed as of the design of control rooms (item I.D.1) at nuclear power plants in operation and under construction as well, to be equipped with a Safety Parameter Display System (SPDS) (item I.D.2) in order to improve the operator-process interface, and this way, reduce the probability of occurrence and the severity of the operator’s errors as well as to help them in their decision-making during abnormal and emergency conditions. To meet the requirements mentioned above, CFE issued the “General Plan for LVNPS Unit 1 Main Control Room Design Review.” Once the activities of the plan were concluded, CFE forwarded to the Commission the document "Report on LVNPS Unit 1 Main Control Room Design Review", in compliance with the requirement established in 10 CFR 50.34(f)(2)(iii). Regarding the compliance of Unit 2 with the requirements of NUREG-0700 and NUREG-0801, it was agreed with the Commission execution of a two-phase project plan, taking into account that LVNPS has twin units that are identical in design except for a few very specific differences.

2007-2009 Period 12-1

Page 83: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

During the first phase of the project plan, all changes made in Unit 1 were implemented in Unit 2. In the second phase, all the specific differences between the control rooms of both units were identified. Then, based on the documents generated, several inspections were performed. In the second phase, a Job Task Analysis (JTA) of the Emergency Procedures was also performed and the results were used to develop several accident scenarios, which were used for training the Unit 2 shifts personnel on the LVNPS full scope simulator. In order to be able to fulfill the activities in the second phase, CFE issued and put under the consideration of the Commission, the “LVNPS Unit-2 General Control Room Design Review Plan”. As part of the improvements introduced to the design since the LVNPS Units-1 & 2’s start-up, there is a Safety Parameter Display System in each unit’s control room that is an integral part of the Process Data Integral System, which is used to monitor and record all process parameters. This system allows the operator to have an actual vision as well as a retrospective vision of the behavior of the most important process parameters, allowing appropriate decision-making and reducing possible errors. Also LVNPS constantly has been making improvements to the control rooms, which are logged in the Corrective Action Programme. Additionally, CFE satisfactorily concluded the execution of the programme for reduction of alarms presenting problems in order to achieve the “Black Board” condition, in where a list of alarms was determined to operate inadequately from the original design of Units 1 & 2; design modifications required elimination of the alarms having problems in accordance with the programme established. This issue arose from the pre-startup testing of both LVNPS units, caused by configuration problems manifested themselves by having alarms that did not work properly. Also during the 2007-2009 period a follow up to the "Black Board" condition was made, which is maintained in both LVNPS control rooms. Additionally, in order to provide better attention regarding human performance and error prevention issues at LVNPS, the Coordination of Human Performance was founded. This group promotes awareness on the Fundamentals of Human Performance and its application in the plant activities. These actions are based on a proactive attitude to prevent errors, having the main objective of achieving a safe and reliable performance. Also, the results of the Level 1 & 2 Probabilistic Safety Analysis (PSA) and human reliability analysis keep being considered to identify accident sequences where the human factor plays a major contribution to the core melt frequency. The specific application of these results is through the dominant sequences simulation in the full scope LVNPS simulator to train and test operators on appropriate responses. Moreover, in what could be regarded as LVNPS human performance good practice, the following operative aids were implemented:

2007-2009 Period 12-2

Page 84: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

a) Symptom-based procedures with flow charts and operational support devices to handle operational transients and accidents, which would allow operators an adequate response in this type of events.

b) SPDS was installed in the simulator and training material was prepared for abnormal or emergency conditions.

c) Use of self-assessment and self checking verification card (golden card) d) Since 2000 there is a special group to perform the root cause analysis for all

the events that occurred at LVNPS. e) Since 1999 the Systematic Approach to Training (SAT) has been incorporated

for the training of LVNPS personnel. f) Since 1998 the Independent Safety Engineering Unit carries out an

assessment of the Nuclear Power Plant’s Division of CFE top management performance, to identify improvements needed in human performance.

g) The permanent personnel passed the courses on defense in depth principles, among others, as part of the Safety Culture Reinforcement Programme.

h) Nuclear Power Plant’s Division personnel in the Operation, Maintenance and Chemical Engineering, Reactor Engineering, Support Engineering and Radiation Protection areas have attended the course Human Performance Fundamentals for Error Prevention.

i) The control room staff of both LVNPS units has been trained on conservative decision making.

- Methods and programmes of the licence holder for analyzing, preventing,

detecting and correcting human errors in the operation and maintenance of nuclear installations

One important aspect that has enabled continuous improvement at LVNPS, among others, is the implementation and follow-up of the human performance programme for preventing errors. The programme can be defined as those activities in the plant to improve the staff behavior by knowing human performance fundamentals and by knowing, using and applying error reduction techniques to meet the task goals in accordance with LVNPS established standards. These techniques have allowed minimizing the events and their safety significance. For more information see Article 10, Section “Licence holder programmes on safety culture and development” of this National Report. During 2007 the precautionary tool called "PREVIA" was integrated to the work management process, which is oriented mainly to an advance review of the task to systematically identify error-prone situations, the potential consequences and defective and / or missing defenses before handling the equipment at the plant. This tool has improved the performance of the activities covered by the planning process and identified weaknesses in the procedures quality. The work management process has created an adequate working environment, supported by the use of error

2007-2009 Period 12-3

Page 85: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

prevention techniques, that strengthens the habit to hold a meeting before the work, a questioning attitude, use and adherence to procedures, a critical review after the work is concluded, etc. In the 2007-2009 period, the delivery of courses on human performance fundamentals continued; the workshop on human performance tools for error prevention was developed and delivered; and the 11 techniques adopted in the Nuclear Power Plant’s Division were taught including: advance review of the task using the precautionary tool "PREVIA", questioning attitude, self-assessment, use and adherence to procedures in conjunction with the use of the phonetic alphabet and marking of procedures, three-way communication, meeting before the work, verification practices (peer checking, independent and simultaneous), signaling, and a critical review after the work is concluded. Workshops on specific subjects such as the use and adherence to procedures, verification practices, advance review of the task using the precautionary tool "PREVIA", questioning attitude, three-way communication and self- assessment were also conducted. The workshop on advanced techniques of field observation was also delivered. Scenarios and mock-ups have been used for training on techniques to reduce errors. A dynamic simulator was acquired to change the behavior of frontline workers and supervisors regarding work practices and techniques to reduce errors. In 2009 a behavioral training programme both in classroom and the simulator (SIMPRO) began to strengthen work practices and high staff performance. - Self-assessment of managerial and organizational issues by the operator In 2007 the human performance self-assessment process started, involving the areas of maintenance, operation, industrial safety, radiation protection, human performance, etc. This process has generated information through field observations of the activities performance. The information has been concentrated in the Corrective Action Programme (CAP) through the condition reports. This work environment has created a reporting culture that has grown in the last three years and has allowed evaluating the progress in the use of human performance tools. We know that the behavior can be seen and heard, consequently it can be measured and if it can be measured, it can be changed. - Arrangements for the feedback of experience in relation to human factors

and organizational issues The events that have occurred over the 2007-2009 period have generated case studies that allow reinforcing the use of error prevention techniques and above all learn from the event to avoid repetition. In accordance with the CAP methodology, the root cause analyses have been generated. Additionally, the CNSNS promotes the Licence holder organization, training and initiative to identify by itself continuous improvement projects, as part of a systematic programme. These projects may be

2007-2009 Period 12-4

Page 86: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

about organizational efficiency, human behavior, self-assessment, knowledge management, works and tasks management, etc. These projects were mentioned in Article 10. - Regulatory control and review activities As a result of the Three Mile Island (TMI) accident, the Commission set as a requirement for LVNPS the implementation of 10CFR50.34 (f) (2) (iii). The objective of this requirement is that the staff playing a vital role in the efficient and safe power generation, such as operators and maintenance personnel, operates, verifies and resets the plant equipment and its components in such a way that the causing factors of human error are eliminated as much as possible. Consistent with this requirement, it was also established as a general guide that in order to comply with 10CFR50.34(f)(2)(iii), LVNPS should follow the directions of Standard Review Plan Chapter 18, NUREG-0800 (NRC, 2004), which in combination with the Human Factors Engineering Programme Review Model described in NUREG-0711, provide detailed criteria to be considered in a Human Factors Programme. As a result of the implementation of all tasks required in Standard Review Plan Chapter 18, the Commission reviewed the LVNPS compliance with the human factors engineering principles. Also, to ensure that the conditions to minimize the human factors were maintained, the Commission established in the current LVNPS Units 1 & 2 commercial operation Licences two requirements to maintain valid these licences. The two requirements are:

a) Requirement No. 2. This requirement establishes that the LVNPS simulator should meet the requirements of fidelity, response and reliability. Also the simulator should have the Safety Parameter Display System.

b) Requirement No. 6. This requirement establishes that LVNPS must continue and conclude, during 2000, the Alarm Reduction Programme in the main Control Room, implementing the necessary design changes.

The regulatory control and review activities regarding the Human Factors during the 2007-2009 period that the CNSNS has chosen to carry out are the following:

a) The practices suggested in the “Human Factors Engineering Programme Review Model” described in NUREG-0711 whose recommendations can and must be applied during the design, construction and operation of nuclear facilities.

According to this review model, it was verified in several Licence holder activities the inclusion of the Human Factors Engineering principles, by reviewing the following items:

2007-2009 Period 12-5

Page 87: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

1. Operational experience - The Commission inspections have systematically considered this item. The External and Internal Operational Experience evaluation and feedback process is reviewed during the Commission’s inspections.

2. Man-machine interface design – The Commission reviewed the due consideration given to ergonomics and functionality for operators in the control room instrumentation that is affected by the extended power Uprate.

3. Training Programme – The Commission has followed-up the development and implementation process of the Systematic Approach to Training. This approach considers the knowledge and skills that the staff must have to safely perform a task.

b) The development of a system for evaluating human performance started in

1999 and continued during the reporting period. Its main objective is to identify and correct the causes that lead to human error. This methodology evaluates aspects such as: environmental conditions; interface with the equipment design or condition; verbal and written communication; training methods and qualification of personnel; planning and work practices; supervision methods; and administrative methods. As a result of this methodology, improvements in the review process of LVNPS control room design were implemented and wider dissemination of the safety culture and self-assessment concepts were demanded.

c) The evaluation to determine how the organization and management impact the

human performance and safety of the installation.

2007-2009 Period 12-6

Page 88: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTICLE 13. QUALITY ASSURANCE 13.0 Obligations "Each Contracting Party shall take appropriate measures to ensure that quality assurance programmes are implemented and applied to have confidence that the requirements that are specified for all activities important to nuclear safety are met throughout the lifetime of a nuclear installation." - Overview of the Contracting Party’s arrangements and regulatory

requirements for the quality assurance programmes, quality management systems, or management systems of the licence holders

• Provisions and regulatory requirements for the quality assurance

programmes During the commercial operation phase of Laguna Verde Nuclear Power Station (LVNPS) Units 1 & 2, the execution of activities important to safety is regulated through the Quality Assurance Plan (QAP), which was designed to meet the requirements set in 10 CFR 50 Appendix B and NUREG-0800, Rev. 2, according to the regulatory framework established for the LVNPS licensing. This plan has a set of procedures to achieve its implementation, which include all activities covered by the QAP. The procedures are reviewed every two or five years, depending upon their safety significance, as indicated in Article 19. Also the QAP considers the compliance with Regulatory Guides established in the Safety Reports and the controls and requirements of ANSI/ANS-3.2-1982, with the exceptions to be agreed upon with the National Comisión Nacional de Seguridad Nuclear y Salvaguardias (the Commission). The QAP also describes the Quality Assurance requirements and controls that applied to LVNPS Units 1 & 2 during its useful lifetime, including decommissioning. Besides the QAP scope regarding the four Quality Assurance categories (plus fire protection and radioactive waste), the QAP has a broader scope; because it includes the Operating Technical Specifications (OTS), the software classified as important for safety and the Internal and External Radiation Emergency Plans, among others.

• Quality management systems If LVNPS adopts a quality system that is internationally accepted, such as the ISO standards, the Commission shall review how these international standards compare with 10CFR50 Appendix B. Based on this review, the Commission must conclude if

2007-2009 Period 13-1

Page 89: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

some requirements are required, in addition to those already established in the existing regulations. - Status with regard to the implementation of integrated management systems

at nuclear installations As part of the Federal Electricity Commission’s (CFE) Institutional Programme of Total Quality and in compliance with the guidelines of the General Directorate, the Nuclear Power Plant's Division permanently maintains a Policy of continuous improvement of its Division-wide Quality System. This has allowed certifying the Division´s Quality Management, Environmental, and Occupational Health and Safety Systems since September 1997, January 1999 and November 2002, respectively. So far the certifications remain valid. In 2005, as a result of the evolution of the management systems of the Nuclear Power Plant's Division, an integral certification of the Quality Management, Environmental, and Occupational Health and Safety Systems was achieved. Later, in 2007 the Nuclear Power Plant's Division, as part of the generation branch of the CFE’s Under Direction of Operation (DOO), participated in establishing, implementing and maintaining a multiple-site Integral Management System (IMS) applicable to all workplaces of the DOO. The IMS includes aspects relating to Quality, Environmental, and Occupational Health and Safety, based on the requirements of ISO-9001, ISO-14001, and NMX-SAST-001 valid standards. This helps the continuous improvement of the efficiency and effectiveness of the Nuclear Power Plant's Division Management System, and its competitiveness to meet the customer and stakeholders requirements. In October 2008, the IMS certification was achieved in adherence to the international standards listed below.

1995 Accreditation of the Environmental Engineering Laboratory awarded by the Mexican Accreditation Entity

1997 Institutional Total Quality Award granted by CFE General Directorate

1997 Certification on NMX-CC-003-1995, equivalent to the ISO-9001: 1994 (Quality Management System)

1999 Certification on NMX-SAA-001-IMNC-1998, equivalent to ISO-14001: 1996 (Environmental Management System)

2002 Certification on NMX-SAST-001-IMNC-2000, equivalent to BSI OHSAS-18001: 1999 (Occupational Health and Safety System)

2003 Certification on NMX-CC-9001-2000, equivalent to ISO-9001: 2000 (Quality Management System)

2005 Integral Certification of the Quality Management, Environmental, and Occupational Health and Safety Systems

2007-2009 Period 13-2

Page 90: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

2006 Accreditation of the Metrology Laboratory granted by the Mexican Accreditation Entity

2006 Migration to the NMX-SAA-14001-IMNC-2004 Standard, equivalent to ISO-14001: 2004 (Environmental Management System)

2006 Certification as a Clean Industry granted by the Mexican Federal Attorney for Environmental Protection

2007 Environmental Excellence Award granted by the Mexican Federal Attorney for Environmental Protection

2008 2007 National Quality Award

2008 Multi-site Management Integral Certification granted by the International Entity “Quality Certifications”, as part of DOO

2009 Golden Ibero-American Award granted by the Ibero-American Foundation of Quality

- Main elements of a typical quality assurance, quality management or

management system programme covering all aspects of safety throughout the lifetime of the nuclear installation, including delivery of safety related work by contractors

• Quality assurance essential elements

The essential elements of the QAP Nuclear Power Plant's Division to cover safety aspects during the construction, testing, licensing, operation and decommissioning phases are defined based on the following: 1. All design construction, testing and operation of Structures, Systems and

Components (SSC) important to safety must be conducted under strict management and administrative controls to ensure that the operation of LVNPS Units 1 & 2 does not cause an undue hazard to the public health and safety.

These controls consist of planned and systematic actions that guarantee the adequate accomplishment of activities related to design, purchasing, fabrication, handling, shipping, storage, cleaning, assembling, installation, inspection, testing, operation, maintenance, reparation, refueling and changes, are realized in such manner that the SSCs important to safety perform satisfactorily in service.

2. The activities above mentioned shall be performed using approved procedures by

duly qualified trained personnel. Similarly, the control actions must be performed by independent personnel to the one performing the work under control.

2007-2009 Period 13-3

Page 91: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

CFE, represented by its General Director, holds the total responsibility for the implementation of the Quality Assurance Plan through the Nuclear Power Plant’s Division, who as well delegates the responsibility for the development, control and verification of its effective execution to the Quality Assurance Department. In order for the Quality Assurance Head to be able to carry out his/her responsibilities in an efficient and timely manner, he/she has sufficient organizational authority, freedom and support from the Nuclear Power Plant’s Division management as well as from the General Direction observed through an alternate line of authority via the Nuclear Safety Under Division Office. Four categories were settled as part of the QAP. These four categories define the required Quality Assurance effort for structures, systems and components, as well as towards suppliers, service contractors, in terms of the safety significance of such components or services.

• Quality Assurance (QA) categories QA-1 Category: Assigned to components, subsystems, systems, structures, processes and services requiring the highest level of reliability in their functioning. It applies to components of the reactor coolant pressure boundary and core support structures wherein a failure may cause loss of the reactor coolant at a greater rate than the normal capacity of the makeup water system. QA-2 Category: Classification assigned to structures, systems, subsystems, components, processes and services required to:

1. Insert negative reactivity for shutting down the reactor. 2. Prevent rapid insertion of positive reactivity. 3. Maintain appropriate core geometry under any plant process condition. 4. Provide emergency core cooling. 5. Provide and maintain containment. 6. Remove reactor and core residual heat.

QA-3 Category: Classification assigned to components, subsystems, systems, Class 1E equipment, structures, processes and services that:

1. Provide or support any safety system function. 2. Process or contain radioactive waste whose release in the event of a

component failure may cause a person within the limits of the site, a whole body dose or its equivalent in any part of the body, greater than 5 mSv.

QA-4 Category: Classification assigned to components, subsystems, systems, structures, processes and services which do not have a safety function assigned, but

2007-2009 Period 13-4

Page 92: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

are Seismic I Category. It also applies to supports that do not have a Seismic I Category, but are designed in such a manner to not harm seismic or safety-related components upon failure. In order to maintain a very high level of quality two additional categories were defined, and partial fulfillment of 18 Quality Criteria in 10CFR Appendix B were set in other systems necessary to comply with the objectives of minimizing fire risks and radioactive waste control. These categories are: QA-SPCI Category: Classification assigned to fire protection components that do not belong to the Safe Shutdown Earthquake Fire Protection System (SSEFPS), but are used to protect areas containing QA category equipment. QA-RW Category: Classification assigned to process equipment, pipes and valves that are not Class 1, 2 or 3, but form the radioactive waste pressure barrier. The six quality categories include the application of quality principles to equipment and components in which the function is: to maintain the structural integrity of the coolant pressure boundary, control essential functions (reactivity, core cooling, containment integrity) and handling of radioactive waste (in which a failure would produce doses greater than 5 mSv). The requirements and controls described in the QAP apply to: 1. Activities affecting the SSCs with Quality Assurance category 1, 2 and 3. 2. Activities affecting the original design conditions and installation of SSCs with

Quality Assurance category 4. 3. The development, control, use and modification of the software used in safety-

related applications such as calculations, operation and equipment and systems response, calibration of measuring equipment, etc. It also applies to the software used to comply or support compliance with regulatory requirements such as record management, compliance with the Operating Technical Specifications, dose control of personnel, etc.

4. Radiation protection activities and ALARA policies of the plant, as well as environmental radiation surveillance activities required by the OTS.

5. Activities affecting systems and components with Quality Assurance category SPCI. The criteria described in the QAP Chapters 3, 4, 5, 7, 10, 11, 14, 15, 16, 17 and 18 will apply, in compliance with Branch Technical Position APCSB-9.5-1 Appendix A. The detailed description of how the Fire Protection Programme complies with the rest of the BTP-APCSB-9.5-1 requirements is provided in Table 9.5-4 of the Safety Reports.

6. Activities of designing, purchasing, assembling, installation, testing, and systems and components operation that form the radioactive waste pressure barrier

2007-2009 Period 13-5

Page 93: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

(Quality Assurance category RW). The criteria described in QAP Chapters 3, 4, 5, 6, 7, 10, 11, 12, 13, 14, 15, 16, 17 and 18 will apply.

7. Activities related to the Process Control Programme and the Off-Site Dose Calculation Manual.

8. Calibration and maintenance activities of the instrumentation necessary to collect the data required by the OTS.

9. Activities related to the Internal Emergency Plan and External Radiological Emergency Plan that are the responsibility of the Nuclear Power Plant's Division.

10. The compliance with the requirements of the Safety Reports, Operating Licence and Permits granted by the Commission and the regulations, codes and standards applicable to LVNPS.

11. Training, indoctrination and personnel qualification activities established in QAP Section 2.5.

12. Reporting activities (according to the position established by the Commission), for manufacturing defects found in safety-related components.

• Authorization to contractors

There are approved procedures to authorize contractors, which ensure that the works at the LVNPS will be made based on a Quality Assurance Programme according to 10CFR50 Appendix B, either by the contractor’s own QAP or by the Nuclear Power Plant's Division Quality Assurance Programme. The authorization process for safety-related works to be carried out by contractors is performed considering two types of contractors: 1. Contractors who carry out their activities under the responsibilities of the Quality

Assurance Programme of the Nuclear Power Plant’s Division and / or 2. Contractors that are evaluated and qualified by the Quality Assurance department

of the Nuclear Power Plant’s Division, to perform safety-related activities under their own Quality Assurance Programme.

• Corrective actions

The QAP establishes measures to ensure that the identified Adverse Conditions to Quality (ACQ) be immediately controlled, analyzed, corrected and, according to their significance, informed to appropriate management levels. Currently, LVNPS is implementing an integral corrective action system, called Corrective Action Programme (CAP), which is similar to the one used at several United States of America plants. This programme is part of the continuous improvement efforts and has the objective to promote reporting the ACQ related to Nuclear, Radiation, Industrial, and Physical Safety, and to Internal and External

2007-2009 Period 13-6

Page 94: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Operational Experience. One of the CAP’s main mechanisms is that the different organizations of the Nuclear Power Plant's Division respond to the Findings documented during the Commission’s inspections and the Deficiencies generated during Quality, Industrial Safety and Occupational Health Audits with the purpose for determining, communicating and planing the appropriate corrective actions. The ACQ are classified according to their safety significance as: Level 1 (L1), 2 (L2) and 3 (L3). These levels are based on the criteria established and evaluated through the Root Cause Analysis, Apparent Cause, or Direct Cause to determine the corrective actions and their implementation period, according to their safety significance. During the reporting period, an average of 4,000 Condition Reports (CR) per year has been issued. It is important to note that all LVNPS staff has access to the CAP through 1,300 computer stations.

• Reporting

There is a Licence holder-Regulatory Body interface through a reporting system based on the regulations listed below:

Reporting Applicable regulation Component defects 10CFR 21 Important deficiencies 10CFR 50.55 (e)

Reports for component defects correspond to non-conformities in the components design and manufacture, and equipment that affect their performance. Usually these reports are extrinsic to the Licence holder and are generated by manufacturers and suppliers of equipment and services important to safety, with the exception of equipment and components that have been procured by the Licence holder as commercial-grade and dedicated for use in the nuclear installation. The Important Deficiency Report (IDR) is a significant breach of the Quality Assurance programme and even though the original regulation only applies to the construction phase, the Licence holder and the Commission have agreed to keep it valid during the LVNPS operational phase. It is important to note that the reporting system is managed by the Quality Assurance organization.

• Periodic assessment of the Quality Assurance Programme

2007-2009 Period 13-7

Page 95: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

The Nuclear Power Plant's Division in compliance with Condition No. 12 of the LVNPS Units 1 & 2 Operating Licence assess at least every two years, with independent and qualified staff, the following: 1. Effectiveness of the Quality Assurance Programme, and

2. The Nuclear Power Plant’s Division top management performance, reporting its

results to the Division head. Since 1998, these assessments are conducted by the Independent Safety Engineering Unit (ISEU). This unit reports directly to the Head of the Nuclear Power Plant’s Division and is totally independent of all functional areas of the Division. The objective is to verify that the QAP implementation is effective to ensure a safe and reliable operation of LVNPS, and to determine what improvements are needed to promote a successful operation. The effectiveness of the QAP implementation is determined based on the following aspects. a) Review and assessment of:

1. The performance indicators provided by the Corrective Action Programme Management and Control System, which are based on the data gathered about the staff and organization performance, as well as the SSCs related to each one of the QAP 18 criteria.

2. Changes made to the organization of the Nuclear Power Plant's Division. 3. Quality Assurance reviews and audits results.

b) Performance assessment of the top management in accordance with the guidelines of the International Atomic Energy Agency (IAEA) TECDOC-369 "Management for Excellence in Nuclear Power Plant Performance":

1. Failure to effectively assign responsibility and authority. 2. Inability to anticipate, identify and correct problems by one self. 3. Failure to achieve and maintain the quality culture. 4. Failure to optimize the use of key resources. 5. Inadequate interface between organizations. 6. Inability to focus on long-term performance.

- Audits programmes of the licence holders

2007-2009 Period 13-8

Page 96: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

The Quality Assurance Plan incorporates measures to establish and execute a system of planned audits and surveillances to verify the correct implementation of the QAP requirements in all the organizations responsible for providing a required service. The audits include an objective assessment of the practices, procedures, instructions, activities, performance of the areas, etc., as well as review of documents and records to ensure that the QAP is properly and effectively implemented. The surveillances are carried out by the Nuclear Power Plant's Division Quality Assurance organization. The Nuclear Power Plant's Division has established the policy that the maximum interval between audits to the same functional area is two years. However, for areas that need more attention due to recurring problems or their situation, audits could be performed more frequently than two years. Also the OTS prescribes performing semi-annual and annual Audits for some specific areas. In Annexes 13.1 and 13.2 are presented, as an example, the Operation and Engineering Quality Assurance Programmes for the 2009-2010 period. - Audits of vendors and suppliers by the licence holders The CFE’s Quality Assurance organization assess and qualifies all suppliers of equipment, components and services important to LVNPS safety. The assessment is performed by a CFE direct audit to the supplier Quality Programme implementation or audits carried out under the Nuclear Utilities Procurement Issues Committee (NUPIC) cooperation programme, since CFE is a NUPIC member. The qualifications are generally based on the ANSI / ASME N 45.2.12 "Quality Assurance Programme Requirements for Nuclear Facilities” and ANSI / ASME N 45.2.13 "Quality Assurance Requirements for the Procurement Control of Items and Services for Nuclear Facilities." In Annex 13.3 is presented, as an example, the audits programme of the Suppliers Control Group for 2009. - Regulatory review and control activities During the construction and evaluation phases, the Commission assesses the Quality Assurance Plan and its revisions, to verify compliance with the requirements set in 10 CFR 50 Appendix B and NUREG-0800, Rev. 2, as it is established in the mandatory regulatory framework for LVNPS licensing. In fact, during this reporting period two QAP revisions were evaluated. These revisions were prepared to reflect changes in the LVNPS organization and the dedication activities of commercial-grade items. Also, as stated in Article 14 of this National Report, the Commission through its inspections baseline programme reviews the programmes and activities of quality

2007-2009 Period 13-9

Page 97: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

related areas, such as Quality Assurance and Quality Control, the supervision groups such as the CIRO (Independent Operations Review Committee) and the Independent Safety Engineering Unit, suppliers and contractors, and dedication programmes of commercial-grade items and corrective actions. For the Corrective Action Programme, both the resident inspectors (monthly, semi-annually and annually) and the head quarters inspectors (every two years) verify: (1) the CAP effectiveness to identify and resolve problems according to their safety significance; (2) specific problems with generic implications; (3) the impact that the combination of otherwise riskless individual problems have on safety; and (4) if the Licence holder is properly logging the information. Additionally, in order to reduce the response and implementation time a continuous communication channel has been established between the Quality Assurance Department and the Commission. This communication allows following up the corrective actions resulting from the documented Findings from the inspections carried out by the Commission at LVNPS. Finally, the Commission, through indicators and inspections to the maintenance rule, verifies if the Licence holder is following up issues that may affect the operability and availability of equipment under 10CFR50.65.

2007-2009 Period 13-10

Page 98: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

Annex 13.1

PAGE 1 OF 2 AREA OR ACTIVITY2009 Audit No.

1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2

02/09

01/09

03/09

04/09

05/09

06/09

07/09

08/09

09/09

10/09

11/09

12/09

13/09

14/09

15/09

16/09

SPECIAL

? Audit scheduled Rev. 4 Prepared by: Approved by:

Audit re-scheduled Publication date: Alfonso Olivares C., BS Roberto Parissi Crivelli, BS? Audit executed Responsible for area Quality Assurance Head? Audit cancelled

?

?

CORRECTIVE ACTIONS ?

NOV DEC

?

?

AUG SEP OCTAPR MAY JUN JULFEB MAR

Keys:

18-Dec-09

?

?

IN-SERVICE INSPECTIONS

ISEU

TRAINING

COMBINED AUDIT ISO/SASI

JAN

OTS

PROCESS CONTROL PROGRAM

INSTRUMENTATION & CONTROL

INDEP AUDIT TO FPS AND LOSS PREVENTION

REACTOR ENGINEERING

REFUELING PLANNING

MAINTENANCE

EMERGENCY PLAN

ORGANIZATION

ENVIRONMENTAL RADIATION SURVEILLANCE

CORRECTIVE ACTIONS

?

?

?

?

?

?

?

?

?

?

SYSTEMS ENGINEERING

Federal Commission of Electricity AUDITS TWO-YEAR PROGRAM Quality Assurance

2009 - 2010

10th

U2

REFUELIN G

2007-2009 Period

13-11

Page 99: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

Annex 13.2

2010 AREA OR ACTIVITY Audit No. U-1 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3

245/10/AC ?

246/10/SOT

? 14th 11th

R247/10/MAN?

248/10/IAI E?

249/10/CD F?

U250/10/WII?

251/10/IIE ? E

L252/10/CNT?

I253/10/ULT?

254/10/AC ?

255/10/ENTTO?

256/10/ININU-1 ? U-2

257/10/CERT?

258/10/IBE?

259/10/DCSM?

? Audit scheduled Rev. 3 Prepared by: Approved by: Audit re-scheduled Publication date: Guillermo Valdivieso Zucolotto, BS Roberto Parissi Crivelli, BS

? Audit executed Responsible of area Quality Assurance Head

? Audit cancelled

JAN

Corrective actions results

Organization, Training

ASME XI certification

National Institute for Nuclear Research activities

“DCSM” activities Keys:

15-Jan-10

Corrective actions results

Environmental qualification maintenance

Electrical Research Institute activities

Document control

“Ultra Ingenieria” activities

“Iberdrola” activities

“Washington” activities

JUL SEP OCTFEB DEC

IAI activities

Contracts

SOT under CFE’s QAP

MAR APR MAY JUN NOVAUG

Federal Commission of Electricity AUDITS TWO-YEAR PROGRAM Quality Assurance Engineering

2009 - 2010

G

N

L

I

EE

E

F

U

R

G

N

PAGE 1 OF 1

NOTE: AUDIT LVI-248/10/IAI IS CANCELLED DUE TO LACK OF SAFETY SIGNIFICANT ACTIVTIES OF THE CURRENT CONTRACT

2007-2009 Period

13-12

Page 100: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

UNITED MEXICAN STATES NATIONAL REPORT

Annex 13.3

Supplier / Contractor NUPIC No. 2009 AUDIT Auditoria 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2 3 4 5 6 7 8 9 0 1 2

NLVE-197 ?NLVE-198 ?NLVE-199 ?

20394 NLVE-200 ?20386 NLVE-201 ?

20407 NLVE-202 ?

20361 NLVE-205 ?

NLVE-206 ?

20316 NLVE-207 ?

20324 NLVE-208 ? ?

NLVE-209 ?

NLVE-210 ?

NLVE-211 ?

NLVE-212 ?

? Audit scheduled Rev. 4 Prepared by: Approved by:

Audit re-scheduled Publication date: Agustin Grajales Lima, BS Roberto Parissi Crivelli, BS? Audit executed Responsible of Area Quality Assurance Head

? Audit cancelled

08-Jun-09

K

eys:

HILTI INC.

INTERVALVE

JAMES JONES Co.

NATIONAL TECHNICAL SYSTEMS (NTS)

GLOBAL NUCLEAR FUEL AMERICAS

VANATOME

ERGYTECH

SIDAT S.A.

DEC AUG NOVAPRMAR JUN JUL OCTMAY

UNITED CONTROLS INTERNATIONAL, INC

FEB

IHI SOUTHWEST TECHNOLOGIES INC

SEP

TRENTEC

DUAL RINGO VALVETECNATOM

JAN

Federal Commission of Electricity AUDITS TWO-YEAR PROGRAM Suppliers control

2009 - 2010 PAGE 1 OF 1

2007-2009 Period

13-13

Page 101: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTICLE 14. ASSESSMENT AND VERIFICATION OF SAFETY 14.0 Obligations "Each Contracting Party shall take appropriate measures to ensure: i) Comprehensive and systematic safety assessments are carried out before the construction and commissioning of a nuclear facility and throughout its lifetime. Such assessments shall be well documented, subsequently updated in the light of operating experience and significant new safety information, and reviewed under the authority of the regulatory body; ii) Verification by analysis, surveillance, testing and inspection is carried out to ensure that the physical state and the operation of a nuclear facility continue to be in accordance with its design, applicable national safety requirements, and operational limits and conditions.” Article 14 (1) Assessment of safety - Overview of the contracting party’s arrangements and regulatory

requirements to perform comprehensive and systematic safety assessments According to the provisions of the Regulating Law of Article 27 of the Constitution, Chapter IV Articles 25 and 28, and Chapter VI Article 50 Fractions III, IV, V, VII and XIII, the Comisión Nacional de Seguridad Nuclear y Salvaguardias (the Commission) has the authority for reviewing, evaluating and authorizing the bases for the siting, design, construction, operation, modification, cease of operations, definitive shutdown, and decommissioning of nuclear and radioactive installations; as well as everything related to the manufacture, use, handling, storage, reprocessing and transportation of nuclear fuels and materials, radioactive materials and equipment containing them; and the processing, conditioning, dumping, and storing of radioactive wastes; and any disposal of them. - Safety assessments within the licencing process and the safety analysis

reports for different stages in the lifetime of nuclear installations (e.g. siting, design, construction, operation)

Safety assessments - construction phase In 1973 prior to construction, the Federal Electricity Commission (CFE) presented to the Department of Reactors of the National Institute for Nuclear Energy (identified at that time as the "Regulatory Authority"), the safety analyses corresponding to: the

2007-2009 Period 14-1

Page 102: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Preliminary Safety Analysis Report (PSAR), Preliminary Environmental Impact Assessment Report (PEIA) and Quality Assurance Construction Programme. During that period, the Laguna Verde Nuclear Power Station (LVNPS) installations were subjected to different evaluations, inspections and audits, which were performed by the Commission and plant organizations as well as external auditors. 1.- LVNPS internal audits / inspections The audits and surveillances were carried out by the Quality Control and Quality Assurance Departments. The activities of both organizations were continuously performed under a specific programme. 2.- Regulatory activities performed by the Commission For the Construction Permit to be awarded, the Commission evaluated the PSAR. Eight hundred questions were generated from this, resulting in the issuance of 44 amendments to the PSAR. The assessment process allowed granting several Provisional Construction Permits. The Definite Construction Permit for LVNPS was awarded in 1979. Later, in September 1992, an extension to such Definite Permit was issued, specifically for completing the construction of LVNPS Unit 2. During the construction of LVNPS Units 1 & 2, the Commission performed inspections and surveillances to activities of design, engineering, installation, special processes and non-destructive testing. Similarly, following a continuous and systematic programme, the Commission performed audits and inspections to the main suppliers of services and equipment important to nuclear safety. In addition to the aforementioned activities, resident inspectors were assigned to the construction site. In order to carry out some of these assessment activities the International Atomic Energy Agency (IAEA) provided technical assistance to the Commission through experienced personnel. 3.- External assessments The external assessments had the support of three IAEA missions through the Operational Safety Evaluation Groups and were conducted in January 1986, January 1987 and September 1987. In addition, there was a mission carried out by the Radiation Protection Advising Team in December 1986. There were no substantial defects reported in the LVNPS safety systems, including the administrative and quality assurance systems. 4.- Pre-operational testing programme

2007-2009 Period 14-2

Page 103: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

The pre-operational testing programme started with the transfer of systems and components from the construction organization to LVNPS operation personnel. Since the outset of the assessment of this programme, the Commission developed a work plan which among other activities, included: evaluation of safety-related test procedures, witness tests and evaluation of test results. Safety assessments - Operation phase 1.- Commercial operating licence On June 29, 1979, CFE submitted to the Commission a Final Safety Analysis Report (FSAR) to support the application for the operating licence of LVNPS Unit 1. The FSAR was assessed by the Commission; therefore, on June 24, 1990 an operation licence for LVNPS Unit 1 with a thermal power of 1,931 MWt was granted. Given the differences between Units 1 & 2 of LVNPS, in 1994 it was presented for evaluation of the Commission a second FSAR specific for Unit 2. On April 15, 1995 an operating license for Unit 2 at the same power was issued. 2.- First amendment to the commercial operating licence (105% Nominal Thermal

Power) In the second semester of 1995, CFE began approaching the Commission regarding its intention to make a 5% thermal power Uprate for both LVNPS units. Then in early 1999, CFE presented a formal application. After reviewing the amended sections of the FSAR and the support documentation, the Commission approved the testing programme in order to verify a stable performance of LVNPS under this new condition. During the evaluation process, the Commission asked 55 questions to and held 39 technical meetings with CFE. The Commission also evaluated the Operating Technical Specifications (OTS) that were modified for this new condition. Generally speaking, as a result of these assessments, the Commission confirmed that it was no necessary to implement any physical changes to the structures, systems and components of LVNPS Units 1 & 2. The Commission also witnessed all phases of testing during the rise of power in steps of 1%, concluding that the test results were within the acceptance criteria that were specified. The Commission’s evaluation and inspections results were documented in a Safety Assessment Report which was the basis for recommending the Ministry of Energy that a modification to the original operating licences, from 1,931 MWt to 2,027 MWt, could be granted. Based on the successful results and the favorable opinion of the Commission, on December 8, 1999, the CFE received from the Ministry of Energy two new operating licences for both units of LVNPS, authorizing a 5% power Uprate up to 2027 MWt.

2007-2009 Period 14-3

Page 104: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

3.- Second amendment to the commercial operating licence (120% Nominal Thermal Power)

Finally, in November 2005, CFE announced its intention to make a 20% power Uprate with respect to the power originally licenced. On July 10, 2008, the CFE presented the formal application to the Commission for the power Uprate. Until December 2009, as part of the ongoing assessment process, the Commission has asked 632 questions and held seven technical meetings with the CFE. 4.- Assessments and verifications during start-up testing Just like for the pre-operational stage, prior to initial nuclear fuel loading, CFE presented a start-up generic testing programme in order to demonstrate that LVNPS Units 1 & 2 can handle foreseen transients with sufficient safety margins during its operation lifetime. In this respect, the Commission developed a work plan including among other activities: evaluation of test procedures for safety-related systems, witness of tests and evaluation of test results. The specific details of these activities are presented in Article 19.3 of this National Report. 5.- Assessments during commercial operation During the commercial operation, the major activities carried out by the Commission are described below.

a) Assessment of the following:

1. Proposals of changes to Operating Technical Specifications or amendments to the Operating Licence.

2. Changes to the Pump and Valve Operability Programmes under ASME Code, Section XI, and proposals of exemption to comply with the same code.

3. Results of In-service Inspection Programmes under ASME, Section XI for active and passive components, and proposals of exemption to comply with the same code (Repairs, Code cases, etc.)

4. New reactor cores for each refueling cycle. 5. Event Reports that are delivered to the Commission. 6. Activities of aging control and mitigation (maintenance of environmental

qualification, corrosion, radiation damage, water chemistry, etc.), and structural integrity.

b) Review of the following:

1. Applicability of the internal and external operational experience to LVNPS.

2007-2009 Period 14-4

Page 105: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

2. Design changes (modifications) to systems, structures and components important to safety.

3. Tests and experiments to be performed at LVNPS. 4. Development and implementation of new regulations.

The assessments of the Change Requests of the LVNPS Units 1 & 2 Commercial Operating Licences were among the relevant activities for the reporting period. The change requests were to modify the licenced range of the core total flow from 87-107% to 81-107%.. CNSNS review covered, among others, areas such as: transient analysis, protection against over pressure of the reactor vessel, thermal-hydraulic stability, performance of emergency systems, Operating Technical Specifications, etc. - Periodic safety assessments of nuclear installations using deterministic and

probabilistic methods of analysis Condition No. 5 of the Operating Licences of LVNPS Units 1&2 establishes as a requirement a Periodic Safety Review (PSR) which must be met every ten years. This review is not intended to renew the licence every ten years or object the operation of the plant for the period licenced. It is useful rather to complement the analyses and studies that are continuously carried out to support applications for authorization of design changes or changes to the OTS. The Periodic Safety Review objectives are the following:

a) Make an analysis of the installation behavior for different aspects of nuclear safety in a time period long enough to identify trends.

b) Verify the effectiveness of the methodology used in the analyses of different aspects of the installation nuclear safety, documented in regular reports.

The scope of the Periodic Safety Review, using deterministic and probabilistic methods, includes the different aspects of the installation nuclear safety described below:

1.- Analysis of operational experience. 2.- Analysis of equipment performance. 3.- Design changes. 4.- Configuration control. 5.- Situation analysis of the new international regulation and the new regulation

of the nuclear steam supply system supplier’s country of origin.

2007-2009 Period 14-5

Page 106: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Analysis of the operational experience The analysis of the operational experience includes the experience about: a) the operation, b) the operational radiation protection, c) the control of liquid and gaseous effluents, d) environmental radiation surveillance, and e) the solid radioactive waste management for the period considered. Analysis of equipment performance The analysis of equipment performance shall include compliance verification with: seismic and environmental qualification requirements, the maintenance rule, the In-service Inspection Manual, the surveillance requirements set in the Operating Technical Specifications and the Management Plan for the plant lifetime. Design changes All the design changes to each structure, system or component are assessed, considering them jointly and taking into account their final status. The assessment identifies: the changes made, the change objective, the resulting actions, the changes implementation, the improvements achieved and the deficiencies detected during their implementation, as well as future plans to increase the plant safety. Configuration control The review is intended to verify: (1) whether the corrective actions resulting from the programme performed for the plant design bases revision have been adequate and fully implemented and (2) the existence of a process to ensure maintenance of the plant design bases, and If a design bases change may be needed, the change should be properly controlled, analyzed, documented and, handled in accordance with the applicable requirements. Situation analysis of the new international regulation and the new regulation of the nuclear steam supply system supplier’s country of origin Based on the plant licensing requirements, the analysis of the new regulation shall include standards issued by international organizations, specifically, the IAEA safety codes and guidelines, and regulations issued by the nuclear steam supply system supplier’s country of origin. The review is intended to verify whether the corrective actions resulting from the new regulation analysis have been adequate and fully implemented.

2007-2009 Period 14-6

Page 107: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Management system The Licence holder shall evaluate the implementation progress, effectiveness and improvement actions of the management system. In addition, the Licence holder shall conduct a review of the organization, policies and, strategic and operational planning. - Overview of the safety assessments performed and the main results of

those assessments for existing nuclear installations Regarding the safety assessments performed by the Licence holder, in 1997 the Commission requested to CFE that the LVNPS Unit 1 Periodic Safety Review report had to include all the FSAR table of contents. Later in 2006, the Commission established that to meet the LVNPS Unit 2 PSR requirement, CFE should follow the IAEA Safety Guide NSG-2-10, including the radioactive waste situation. Therefore, these reports were submitted in 1999 for LVNPS Unit 1 and in 2008 for LVNPS Unit 2. These reports allowed identifying areas for improvement, changes, plant aging issues, operational experience and technical processes in order to ensure the highest level of safety and an analysis with respect to the latest standards and practices. As a result of the assessment of the documentation provided by the Licence holder, there were no safety significant issues. However, among the results of this assessment were the improvements to the safety management integral system which are presented in Article 10 and surveillance aspects related to the site which are described in Article 17, of this National Report. - Regulatory review and control activities During 2009, the Commission assessed compliance of LVNPS with the IAEA Safety Guide NSG-2-10, concluding that the PSR report was acceptable. The Commission also found that the Safety Improvement Programmes have been adequate to LVNPS needs, verifying the installation status versus the technological developments that may have arisen during the period covered by the PSR. Also the Commission assessed the overall evolution of the processes and procedures included within the PSR scope, identifying the changes made, changes objective, the resulting actions, their implementation, the improvements achieved and the deficiencies identified. During this assessment, the Commission paid special attention to the regulatory analysis in order to verify compliance with the regulatory framework established which includes the national regulation, the regulation of the nuclear steam supply system

2007-2009 Period 14-7

Page 108: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

supplier’s country of origin, and the IAEA guides. The Commission will also monitor the safety management integral system through the inspections base-line programme and the indicators described in Article 10 of this National Report. Article 14 (2) Verification of safety - Overview of the contracting party’s arrangements and regulatory

requirements for the verification of safety In accordance with the provisions of the Regulatory Law of Constitutional Article 27, Chapter IV Article 32 and Chapter VI Article 50 Fraction XII, the Regulatory Body has the authority to conduct audits, inspections, verifications and surveys to confirm compliance and adherence to the legal provisions regarding nuclear, radiation and physical safety, and safeguards; and to execute enforcement actions and decree administrative sanctions as foreseen by this Law and its regulations. - Main elements of programmes for continued verification of safety (in-service

inspection, surveillance, functional testing of systems, etc.) During the 2007-2009 period, the Commission has been following the Reactor Oversight Process (ROP) guidelines, to comply with the IAEA Safety Guide GS-R-1 "Legal and Governmental Infrastructure for Nuclear, Radiation, Radioactive Waste and Transport Safety". The inspections base-line programme is used for the continuous verification of safety, as part of the ROP. Annex 14.1 shows the "Control Matrix of Scheduled Inspections" which identifies the inspections base-line programme to be executed every two years. The inspections base-line programme is aimed to collect enough information about the performance of nuclear facilities and the Licence holder’s activities. This allows determining along with the performance indicators, when appropriate, if the Licence holder is meeting the safety objectives, and identify performance issues to enable the Commission to follow-up and take actions before safety is compromised. The inspections frequency depends on the type of activity and its significance for the installation’s safety. The inspections base-line programme indicates the minimum number of scheduled inspections to be performed during the period in which the installation performance has a "response from the installation" status. Additionally, the inspections base-line programme includes some inspections to verify: (a) the quality-related areas, (2) supervising groups and (3) the cross-cutting elements. It should also be noted that sometimes, there might be the need to conduct supplemental inspections focused on: (1) Safety related emerging generic issues; (2) a specific objective when the Licence holder performs major maneuvers, such as functional testing after power Uprate or replacement of major components; (3) issues

2007-2009 Period 14-8

Page 109: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

resulting from the performance assessment using the Performance Indicators and the Findings of scheduled inspections; and (4) the response to operational events which should be evaluated on a case by case basis. Both, the main office inspectors and the resident inspectors (one resident inspector for each unit) take part in the programme implementation. The resident inspectors also verify daily LVNPS operation, as well as compliance with the Operating Technical Specifications and other regulatory requirements established by the Commission. The resident inspectors also follow-up the events that occur in the installation, and the corrective and preventive actions that are taken to prevent their recurrence. Additionally, as part of the continuous verification, the findings documented during inspections and the operational events are categorized according to their safety significance. This exercise has the purpose of determining performance indicators similar to the United States of America Nuclear Regulatory Commission ROP performance indicators to compare LVNPS performance with similar plants and emulate the best international practices. The radiation protection performance indicators have also been developed, which allow monitoring the LVNPS collective doses behavior, as mentioned in Article 15 of this National Report. For the Corrective Action Programme, both the resident inspectors (monthly, semi-annually and annually) and the main office inspectors (every two years) verify: (1) the CAP effectiveness to identify and resolve problems according to their safety significance; (2) specific problems with generic implications, (3) the impact that the combination of otherwise riskless individual problems have on safety; and (4) if the Licence holder is properly logging the information. - Elements of aging management programme(s) LVNPS has had, almost from the beginning of its commercial operation, some programmes for aging management. These programmes have been based on both, internal (Service Water System using seawater, high temperatures in the primary containment, etc.) and external (visual inspection of welding, of the vessel and its internals) operational experience. The programmes have been classified into four groups: (1) preventive - to prevent the aging effects, for example, painting tanks to prevent external corrosion; (2) attenuation - to lessen the aging effects, for example, the water chemistry programme, which mitigates the effects of internal corrosion on piping; (3) condition surveillance – to monitor and examine the presence and extent of the aging effects, for example, structures visual inspection to identify cracking in the structures, and ultrasonic techniques to measure the pipe wall thickness to detect erosion or corrosion induced wall thinning; and (4) behavior monitoring – to test the structures or components ability to perform their functions for which they were designed, for example, maintenance rule.

2007-2009 Period 14-9

Page 110: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

These programmes have allowed defining two types of components: structures and components subject to aging management under the 10CFR54.21 (a) (1) (i) and (ii) provisions, and those that are considered consumable by the same standard. - Arrangements for internal review by the licence holder of safety cases to be

submitted to the regulatory body As mentioned in Article 7.2(i) Section “Description of the Secondary legislative framework related to nuclear safety” of this National Report, the government authorities decided that, in addition to applying the regulations of the IAEA, the regulation of the nuclear steam supply system supplier’s country of origin would be equally applied. For this reason, 10CFR50.59 is used to preserve the original licensing bases contained in the information provided to the Commission, as part of the application for the Operating Licence and subsequent amendment. Procedure PAS-03 is used to prepare, review or approve 10CFR50.59 Safety Evaluations, based on the following criteria:

1. Any LVNPS change which could make incorrect or incomplete the information contained in the FSAR, or which may violate a commitment established in that report.

2. Conduction of tests or experiments not described in the FSAR or carried out under different conditions to those described in that report.

3. Any newly known condition at LVNPS that has the possibility of deviation from the arguments presented in the licensing bases.

4. Structures, Systems and Components (SSC) that were authorized to perform a work on them or isolated but they were not returned to its original condition after completion of the activity, regardless of being inoperable.

5. Changes to the procedures included in Annex PAS-03-1. If the safety evaluation concludes that is not an “unreviewed safety question”, LVNPS can implement the SSC changes or modifications without asking approval of the Commission. However, if the safety evaluation concludes that it is an “unreviewed safety question”, LVNPS must request permission from the Commission, before implementing the SSC changes or modifications. The procedure PAS-03 also establishes that a 10CFR50.59 Safety Evaluations is not required in the following cases:

1. Routine maintenance activities described in the LVNPS approved

procedures.

2007-2009 Period 14-10

Page 111: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

2. Works on SSCs that are inoperable, authorized to perform work on them (or isolated), or failed; provided that they do not stay in one of these conditions once they return to normal condition.

3. Data collection in SSCs that are operating in their normal condition (alignment, electrical or pneumatic power, supporting, etc.), following normal procedures and within normal operating ranges.

- Regulatory review and control activities Introduction The Commission follows-up the Licence holder programmes to manage the aging effects on the SSCs, through the inspections base-line programme which includes the following:

ASME Code Section XI “In-service inspection” ASME Code Section XI “Internals Vessel Visual Inspection” Erosion corrosion (flow-accelerated corrosion) Snubbers Vessel integrity Leak testing of primary containment Water chemistry Quality assurance Corrective action programme Maintenance rule Environmental qualification Fire protection

Some of these surveillances are described in greater detail in the following sections. ASME Code Section XI “In-service inspection” The Commission verifies the In-service Inspection (ISI) activities, through volumetric, surface and visual periodic examinations to components and their supports to look for degrading indications. The LVNPS examinations have been mainly used to verify the structural integrity of Class 1, 2 and 3 mechanical components, such as piping, welding, elbows, etc., according to the ASME Code Section XI, Subsections IWB, IWB and IWD guidelines. The examinations also have been used to maintain the components ASME classification and certification when they are repaired according

2007-2009 Period 14-11

Page 112: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

2007-2009 Period 14-12

to ASME Section III. The volumetric studies such as ultrasonic, radiographic, liquid penetrant and magnetic particle are verified, during the Commission´s inspections. ASME Code Section XI “Vessel Internals Visual Inspection” The Commission verifies the In Vessel Visual Inspection (IVVI) activities performed by the Licence holder to test the structural integrity of the vessel internal components through surface examination. For the 2007-2009 period, the Licence holder has submitted periodic reports (after each refueling outage) which describe the components condition and the progress of the corrective and preventive activities for the previous fuel cycle. The reports are reviewed by the Commission’s staff. Erosion - corrosion (flow-accelerated corrosion) programme During the first fuel cycles of LVNPS commercial operation, the Commission required the establishment of a programme to monitor the problem of flow-accelerated corrosion; because the working fluid of the Service Water System is seawater. This situation caused that the coils of the Ventilation System cooling units and the coils of the Nuclear Closed Cooling Water System heat exchangers started developing pores. After each refueling outage, the Licence holder prepares reports which describe the components condition and the progress of the corrective and preventive activities for the previous fuel cycle. The reports are reviewed by the Commission’s staff.

Page 113: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

A N N E X 14.1

“CONTROL MATRIX OF SCHEDULED INSPECTIONS”

Inspection Area Initiating Events

Mitigation Systems

Barriers Integrity

Emergency

Preparedness

Occupational

Radiation Safety

Public Radiation

Safety

Baseline Programm

e

Frequency Responsible Area

OPERATIÓN UNIT 1 X X X X YES A ACO OPERATIÓN UNIT 2 X X X X YES A ACO

MECHANICAL MAINTENANCE UNIT 1

X X X YES A AVD

MECHANICAL MAINTENANCE UNIT 2

X X X YES A AVD

ELECTRICAL MAINTENANCE UNIT 1

X X X YES A AVD

ELECTRICAL MAINTENANCE UNIT 2

X X X YES A AVD

I&C MAINTENANCE UNIT 1 X X X YES A AVD I&C MAINTENANCE UNIT 2 X X X YES A AVD RADIATION PROTECCIÓN

UNIT 1 X X X YES A API

RADIATION PROTECCIÓN UNIT 2

X X X YES A API

SYSTEMS ENGINEERING UNIT 1

X X X YES A ACO

SYSTEMS ENGINEERING UNIT 2

X X X YES A ACO

REACTOR ENGINEERING UNIT 1

X X YES A ACO

REACTOR ENGINEERING UNIT 2

X X YES A ACO

EFFLUENTS MONITORING UNIT 1

X YES A API

EFFLUENTS MONITORING UNIT 2

X YES A API

2007-2009 Period 14-13

Page 114: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Inspection Area Initiating Events

Mitigation Systems

Barriers Integrity

Emergency

Preparedness

Occupational

Radiation Safety

Public Radiation

Safety

Baseline Programm

e

Frequency Responsible Area

FIRE PROTECTION UNIT 1

X X YES A AVD

FIRE PROTECTION UNIT 2

X X YES A AVD

CHEMISTRY UNIT 1 X X YES A API CHEMISTRY UNIT 2 X X YES A API

INTERNAL EMERGENCY PLAN UNIT 1

X YES A ACO

INTERNAL EMERGENCY PLAN UNIT 2

X YES A ACO

TRAINING X X X YES A ACO MAINTENANCE RULE X X X YES A ADV

REFUELING UNIT 1

X X X YES R AR

REFUELING UNIT 2

X X X YES R AR

ISI, IVVI AND SNUBBERS UNIT 1

X YES R AVD

ISI, IVVI AND SNUBBERS UNIT 2

X YES R AVD

RADIATION PROTECCIÓN REFUELING UNIT 1

X YES R API

RADIATION PROTECCIÓN REFUELING UNIT 2

X YES R API

SUPPLIERS UNIT 1 NO R API SUPPLIERS UNIT 2 NO R API

PERFORMANCE INDICATORS X X X X X X YES A AVD EXTERNAL OPERATIONAL

EXPERIENCE NO B ACO

QUALITY ASSURANCE OPERATION

NO B API

QUALITY ASSURANCE NO B API

2007-2009 Period 14-14

Page 115: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Inspection Area Initiating Events

Mitigation Systems

Barriers Integrity

Emergency

Preparedness

Occupational

Radiation Safety

Public Radiation

Safety

Baseline Programm

e

Frequency Responsible Area

ENGINEERING CROS NO B ACO CIRO NO B API ISEU NO B API

DEDICATIÓN PROCESS NO B API QUALITY CONTROL NO B API

WASTE MANAGEMENT X YES A API ASME XI CERTIFICATION

UNIT 1 NO B AVD

ASME XI CERTIFICATION UNIT 2

NO B AVD

ORGANIZATIÓN AND HUMAN FACTORS

X X X X X X YES B AVD

CORRECTIVE ACTION PROGRAMME

X X X X X X YES B API

SAFETY CULTURE X X X X X X YES B ACO KEYS: A = Annually ACO = Certification and Operation Area. B = Two years API = Inspection Programme Area. R = Refueling outage AVD = Performance Verification Area.

SR = Under direction

2007-2009 Period 14-15

Page 116: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTICLE 15. RADIATION PROTECTION

15.0 Obligations “Each Contracting Party shall take the appropriate measures to ensure that in all operational states the radiation exposure to the workers and the public caused by a nuclear facility shall be kept as low as reasonably achievable and that no individual shall be exposed to radiation doses which exceed prescribed national dose limits.” - Overview of Contracting Party’s arrangements and regulatory requirements

concerning radiation protection at nuclear installations, including applicable laws not mentioned under Article 7

Since there were no national regulations for nuclear power plants at the time the Laguna Verde Nuclear Power Station (LVNPS) was built, government authorities decided that the regulations of the nuclear steam supply system supplier’s country of origin would be applied. Therefore for the radiation protection area, the compliance with 10CFR20, in force at that time in United States of America (US), was explicitly set as a requirement, which was not consistent with the International Atomic Energy Agency (IAEA) ICRP-26. Subsequently, in 1988 the General Regulation for Radiation Safety entered into force which still is valid and is consistent with the ICRP-26 and with the current 10 CFR 20. - Regulatory expectations for the licence holder’s processes to optimize

radiation dose and to implement the “As low As Reasonably Achievable” (ALARA) principle

The Article 7 of the General Regulation on Radiation Safety indicates that the dose received as a consequence of an exposition of ionizing radiation sources and from practices that involve irradiation with ionizing radiation or incorporation of radioactive material, will be subject to a dose limiting system whose fundamental principles are the following: a) Practices that may produce doses to workers shall not be approved unless a

positive net benefit is obtained. b) The design, planning, use and subsequent application of the sources and

practices should be carried out in a manner that ensures that the expositions are maintained as low as possible considering social and economic factors;

c) The establishment of limits for dose equivalents. - Implementation of radiation protection programmes by the licence holders,

including:

2007-2009 Period

I5-1

Page 117: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Observation of dose limits, main results for doses to exposed workers

In order to limit operation personnel doses, LVNPS buildings were divided into zones (reactor, turbine, radioactive waste, liquid purification, main control rooms of both units, hot workshops, and open areas of low potential contamination). These zones include five categories that consider radiation levels according to the following extreme cases: a) Zone 1 - unlimited permanence is allowed with an exposure rate of less than 25

E-7 Sv/h, when integrated per year does not exceed the 0.005 Sv/year dose limit.

b) Zone 5 - the highest radiation level zone. Access is restricted and controlled. Also LVNPS has a specific group called "Radiation Analysis Group”, to orient and drive the implementation of the ALARA criterion in all activities developed by its personnel. The group leader is the Head of the Radiation Protection Organization, supported by analysts of the same organization. The analysts have functions of analysis, evaluation, control and optimization of the personnel radiation exposure in their respective activities. Table 5.1 presents a summary of the historic workers collective and individual radiation doses for LVNPS Units 1 & 2; and Figures 15.1 a & b present the historic data for the workers annual collective radiation dose for LVNPS Units 1 & 2, respectively. Regarding the individual radiation dose, while the Commission set a Limit for the Total Effective Dose Equivalent (TEDE) of 50 mSv / year, according to the references previously mentioned in this Article; LVNPS adopted an administrative average level of 20 mSv / year which has been achieved since 2003 over the last five years. Table 15.1 shows the compliance with this administrative level.

TABLE 15.1

Summary of Workers Collective and Individual Radiation Doses

Annual Collective Dose(Sv-person)

Annual Dose per MW(Sv-person /MW)

Individual Dose (mSv) Year

Unit 1 Unit 2 Unit 1 Unit 2 Average High (max)*1990 1.34435 N/A 0.0055 N/A 1.1610 10.07 1991 5.14748 N/A 0.0106 N/A 2.0520 N/A 1992 5.44015 N/A 0.0122 N/A 2.4510 20.30 1993 1.96603 N/A 0.0035 N/A 1.7460 20.59 1994 6.02126 N/A 0.0125 N/A 2.4020 19.92 1995 4.93073 0.9974 0.0100 0.0025 2.7510 24.75 1996 12.51806 3.6390 0.0288 0.0078 5.4270 37.97 1997 1.94839 2.5529 0.0031 0.0045 2.1140 18.76 1998 5.95528 3.5833 0.0113 0.0067 3.3650 31.72

2007-2009 Period

I5-2

Page 118: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Annual Collective Dose Annual Dose per MW Individual Dose

(Sv-person) (Sv-person /MW) (mSv) Year Average Unit 1 Unit 2 Unit 1 Unit 2 High (max)*

1999 6.20219 1.1332 0.0117 0.0019 2.1700 21.54 2000 1.33760 4.3173 0.0025 0.0110 2.5800 23.02 2001 3.97322 2.6083 0.0080 0.0052 2.9251 26.75 2002 2.89238 0.5401 0.0058 0.0009 2.1062 17.95 2003 0.66160 3.1542 0.0010 0.0057 1.9926 18.52 2004 3.59474 3.4792 0.0073 0.00626 1.8064 21.72 2005 2.78328 0.5748 0.0048 0.00089 1.0420 14.59 2006 0.65405 2.3086 0.0010 0.00389 0.8612 12.43 2007 3.05512 2.4202 0.0052 0.00405 1.2998 18.72 2008 8.72841 0.6497 0.0192 0.00098 1.9377 22.84 2009 1.30837 3.3115 0.0020 0.00599 0.8803 14.10

TOTAL 80.46269 35.2697 * NOTE: The values presented in this column correspond to the maximum values for that year and they are not necessarily for the same individuals. However, for any individual, the average value of 20 mSv has not been exceeded over the last five years.

Conditions for the release of radioactive material into the environment, operational control measures and main results

There is environmental radiation surveillance information available from the pre-operational phase (9-12 years before the start of LVNPS commercial operation) up to this date. The information has been collected through the surveillance and sampling systems of the LVNPS Environmental Engineering Laboratory. Figures 15.4 and 15.5 present the historical results of the direct environmental surveillance. Such figures make evident that the radiation levels remain on the same order as the levels existing during the pre-operational phase. It is worth noting that during all these years, events non-related to LVNPS have been detected, which contributed to raising the environmental background. The radiological impact to the general public is calculated from the LVNPS emissions, using the models established in the Operating Technical Specifications. In all cases, the impact has represented a small fraction of the corresponding limits, as shown in the figures listed below. Figure 15.6.- Annual historical data of liquid releases (Units 1 & 2) Figure 15.7.- Annual historical data of gaseous releases (Unit 1) - noble gases Figure 15.8.- Annual historical data of gaseous releases (Unit 2) - noble gases Figure 15.9.- Annual historical data of gaseous releases (Unit 1) – iodine, particles

and tritium Figure 15.10.- Annual historical data of gaseous releases (Unit 2) – iodine, particles

and tritium

2007-2009 Period

I5-3

Page 119: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

The annual dose due to liquid releases has shown a drastic reduction since 1996, due to an improved water re-utilization management; which substantially reduced the liquid releases. This tendency can be observed in Figure 15.6. Since 1996, there is a notorious reduction tendency in the public dose due to gaseous releases, which can be observed in Figures 15.7 to 15.10.

Processes implemented and steps taken to ensure that radiation exposure are kept as low as reasonably achievable for all operational and maintenance activities

Introduction Figure 15.2 shows that the LVNPS collective dose had a steady reduction tendency up to 2006. However, when the actions and recommendations to protect the vessel internals were implemented, this trend was reversed. The application of Hydrogen and Noble Metals produced a substantial change in the reactor water chemistry. The chemical recombination processes produced an increase of the cobalt 60 (Co-60) concentration, with respect to the values observed in previous years. This change was reflected, in both, the collective dose and the BRAC index of both units. The radiation control started when the technology to reduce the effects of the intergranular corrosion to the vessel internals was proposed, taking advantage of the best global experience. As part of this project, the zinc injection was adopted to control the iron and, consequently, the Co-60, concentrations. The Dose Reduction Committee is taking dose control measures aimed at the following three fundamental aspects.

a. Source term control (Figures 15.3 a/b) b. Work practice improvement c. Equipment reliability

Regarding the source term control, the actions include: a reduction of the Co-60 sources (Stellite-free turbines as part of the power Uprate changes); and use of cobalt-selective resins which are being applied in the Reactor Water Cleanup System, iron control, hydrogen injection control, on-line application of noble metals, and the application of the Electric Power Research Institute (EPRI) water chemistry guide during shutdowns and refueling outages. The work practices have been improved using mockups to reduce activity execution time and, consequently, the dose. The use of the human performance tools for error reduction is another action that impacts the dose reduction by reducing the rework required. As for the reliability equipment, preventive maintenance and the actions in advance of the component failures are considered as strategies for greater impact on the results of normal operation.

2007-2009 Period

I5-4

Page 120: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Implemented strategies The strategies implemented during the National Report period to reduce the LVNPS collective dose can be summarized as follows: 1. The Dose Reduction Committee was formally founded. 2. Use of the lessons learned from internal operational experiences. For example,

the problems identified during the 13th refueling outage of LVNPS Unit 1 were corrected and the improvement actions were implemented in the 10th refueling outage of LVNPS Unit 2.

3. Follow-up to the Dose Reduction Plan commitments. 4. EPRI´s staff advisory on the source term control. Future strategies The foreseen collective dose reduction strategies for the period 2009-2011 will be established based on the source term control recommendations from EPRI’s staff.

Environmental surveillance and main results LVNPS has an Environmental Radiation Surveillance Programme which ensures continuous monitoring of the environmental impact during normal operation. The highlights of the LVNPS environmental surveillance are presented below. Atmospheric releases

a) External radiation, air 30 sampling stations b) Inhale, air 16 sampling stations c) Radiation deposited on soil

Rain water 1 station Agricultural products 5 stations Grass 4 stations Milk 4 stations Beef 1 station

Liquid effluents

a) Release to ocean 1 station b) Fish 13 stations c) Aquatic biotic 1 station d) Bio-tracers 3 stations e) Sea sediment 4 stations f) Beach sand 4 sampling stations g) Underground fresh water 3 sampling stations

Conclusions

2007-2009 Period

I5-5

Page 121: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

a) The concentration limits set in the LVNPS Operating Technical Specifications have never been exceeded, by any single sample nor considering the average.

b) Since the concentration limits were not exceeded and the exposures measured with Thermo Luminescent Dosimeters (TLD) remained below the pre-operational values; it can be established that no member of the general public exceeded the limits due to the LVNPS emissions.

c) The total beta activity detected during the reporting period shows the same behavior as in previous years. The variations observed from 1978 to date are of the same order.

d) The results from the Environmental Surveillance Programme have shown that the radiation dose for the LVNPS’s vicinity population has not increased, due to the LVNPS operation; or at least, if there is any increase, it cannot be discriminated from the very low values measured during the reporting period.

e) Sr-90 and Cs-137 are the only artificial radionuclides that have been detected in the samples, at a relatively high regularity. However, they were detected during the pre-operational surveillances, even before the LVNPS construction. It is presumed that nuclear weapons testing produced them and reached the LVNPS site through radioactive fallout. Therefore, the presence of these radionuclides is not attributable to the LVNPS operation and they show a very slow reduction trend due to its half-life

f) During the 2007-2009 period, some radionuclides due to the LVNPS operation were detected, these include: Cr-51, Mn-54, Co-58, and Co-60 all with very low activity.

- Regulatory review and control activities Annex 14.1 presents the "Control Matrix of Scheduled Inspections" which includes the inspections to the areas of radiation protection, effluents and radioactive waste management. In addition to the inspections, the performance of the Radiation Protection strategic area is monitored through the Nuclear Power Reactors Surveillance System. As part of the assessment, both the general public radiation safety and the LVNPS workers occupational safety fundamentals are considered. Statistical data of the workers collective dose also is kept to properly react in case of an increase above the doses observed. Also during the Extended Power Uprate (EPU) project, the Commission has monitored the activities to assure they comply with the applicable national regulation for Radiation Protection and LVNPS commitments. The activities include removal, cutting, transport and storage of large contaminated components and minor modifications on components or equipment. Regarding the exposure to the public caused by LVNPS normal operation, the Commission has several mutually independent ways to verify compliance with the current regulation on environmental impact, including the ones listed below.

2007-2009 Period

I5-6

Page 122: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

a) Analysis of the section “Radioactive emissions” of the production daily report,

which contains real time data from the instrumentation of the radiation effluents process.

b) Assessment of the LVNPS accounting semi-annual reports for effluents. The report consolidates data from sampling procedures and isotopic analyses of liquid and gaseous emissions during the reporting period. The second half year reports are actually an annual summary, which also contain dose calculations and relevant weather information. Part of the Commission´s assessment is an independent reproduction of those dose calculations to verify its consistency. The assessment is performed in accordance with the US Nuclear Regulatory Commission Regulatory Guide 1.109.

c) Assessment of the Environmental Radiation Surveillance Annual Programme Report prepared by an external laboratory, which contains sampling and isotopic analysis information from different environmental strata.

d) An independent assessment of the LVNPS Units 1&2 radiation environmental impact through an isotopic analysis of environmental samples periodically collected in the plant’s vicinity and processed in the Commission’s laboratory. This programme has functioned as an additional verification, whereby the Commission has confirmed the consistency of the information submitted by the Licensee.

Both the LVNPS and the Commission laboratories participate in inter-comparison international programmes to ensure their measurement reliability.

2007-2009 Period

I5-7

Page 123: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

ESTADOS UNIDOS MEXICANOS INFORME NACIONAL

15-9 Periodo 2007-2009

FIGURE 15.1.a

HISTORICAL DATA OF ANNUAL COLLECTIVE DOSE (LVNPS UNIT-1)JANUARY 1989 - DECEMBER 2009

0

100

200

300

400

500

600

Ene-

89

Ene-

90

Ene-

91

Ene-

92

Ene-

93

Ene-

94

Ene-

95

Ene-

96

Ene-

97

Ene-

98

Ene-

99

Ene-

00

Ene-

01

Ene-

02

Ene-

03

Ene-

04

Ene-

05

Ene-

06

Ene-

07

Ene-

08

Ene-

09

Ene-

10

Col

lect

ive

Dos

e (r

em -

pers

on/m

onth

)

RO-01

RO-02

RO-03

RO-04

RO-05

RO-06

RO-07

RO-09RO-08RO-10

RO-11

RO-12

RO-13

Page 124: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

ESTADOS UNIDOS MEXICANOS INFORME NACIONAL

15-10 Periodo 2007-2009

FIGURE 15.1.b

HISTORICAL DATA OF ANNUAL COLLECTIVE DOSE (LVNPS UNIT-2)JANUARY 2005 - DECEMBER 2009

0

50

100

150

200

250E

ne-9

5

Ene

-96

Ene

-97

Ene

-98

Ene

-99

Ene

-00

Ene

-01

Ene

-02

Ene

-03

Ene

-04

Ene

-05

Ene

-06

Ene

-07

Ene

-08

Ene

-09

Ene

-10

Col

lect

ive

Dos

e (r

em -

pers

on/m

onth

)

RO-01

RO-02

RO-03

RO-04

RO-05

RO-06RO-07

RO-08

RO-09

RO-10

Page 125: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

ESTADOS UNIDOS MEXICANOS INFORME NACIONAL

15-11 Periodo 2007-2009

0

1

2

3

4

5

6

7

8

9

Ave

rage

Col

lect

ive

Dos

e pe

r Uni

t(S

v-pe

rson

)

1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009

Figure 15.2LVNPS: Collective Dose Evolution

*

* **

*

* Year with 2 refueling outages

Page 126: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

ESTADOS UNIDOS MEXICANOS INFORME NACIONAL

15-12 Periodo 2007-2009

0

50

100

150

200

250

300

350

400

29-May-90

17-Sep-91

30-Sep-92

06-Mar-94

16-May-95

25-Nov-96

24-Abr-98

20-Ago-99

30-Ago-00

24-Jun-01

03-Nov-02

12-May-04

09-Ago-05

23-Mar-07

02-Oct-08

BWR'sMedian

Figure 15.3aLVNPS U-1: Historic BRAC Index (mR/h)

Source Term ReductionProgram starts

*

* After chemical decontamination

7-fold increment of Co-60 in

Reactor Water

Page 127: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

ESTADOS UNIDOS MEXICANOS INFORME NACIONAL

0

50

100

150

200

250

300

350

400

450

500

10-Mar-95 09-Ago-96 24-Sep-97 08-Jun-00 09-Nov-01 05-May-03 12-Nov-04 15-May-06 14-Jun-07 22-Nov-07 16-Abr-09 BWR'sMedian

Figure 15.3bLVNPS U-2: Historic BRAC Index (mR/h)

Source Term ReductionProgram starts

*

3-fold increment of Co-60 in Reactor Water

* After chemical decontamination

MSR plates

15-13 Periodo 2007-2009

Page 128: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

ESTADOS UNIDOS MEXICANOS INFORME NACIONAL

15-14 Periodo 2007-2009

Figura 15.4

Total β activity - Integrated monthly averagesAugust 1978 to December 2009

0.00

1.00

2.00

3.00

4.00

5.00

6.00

7.00

8.00

9.00

10.00

1978

1979

1980

1981

1982

1983

1984

1985

1986

1987

1988

1989

1990

1991

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

Time

mB

q/m

3

Fallout due to nuclear weapons testing

Technical Specification Limit

Confidence interval: 95%Chernobyl

Chichonal

Pre-operation stage Operation stage

Operation U-1

July 1990 Operation U-2April 1995

Page 129: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

ESTADOS UNIDOS MEXICANOS INFORME NACIONAL

15-15 Periodo 2007-2009

Figura 15.5

ENVIRONMENTAL RADIATION LEVELSVECINITY OF LVNPS

30 Monthly Average MONITORING STATIONS

0

200

400

600

800

1000

1200

1400

1982

1983

1984

1985

1986

1987

1988

1989

1990

1991

1992

1993

1994

1995

1996

1997

1998

1999

2000

2001

2002

2003

2004

2005

2006

2007

2008

2009

YEAR

μGy/

year

Operation U-1July 1990

Operation U-2April 1995

+2s

-2s

Pre-operation stage Operation stage

+2s

Page 130: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

ESTADOS UNIDOS MEXICANOS INFORME NACIONAL

15-16 Periodo 2007-2009

Figure 15.6HISTORIC DATA OF ANNUAL LIQUID RELEASES

(LVNPS UNITS 1 & 2)

0.0

0.5

1.0

1.5

2.0

2.5

3.0

3.5

1990 1991 1992 1993 1994 1995* 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009

Dos

e [m

rem

]

Operating Technical Specification Limit: 3 mrem

Year

Page 131: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

ESTADOS UNIDOS MEXICANOS INFORME NACIONAL

15-17 Periodo 2007-2009

Figura 15.7HISTORIC DATA OF ANNUAL GASEOUS RELEASES, UNIT 1

NOBLE GASES

0

1

2

3

4

5

6

7

8

9

10

11

12

1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009

Year

Dos

e [m

rad]

Operating Technical Specification Limit: 10 mrad

Page 132: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

ESTADOS UNIDOS MEXICANOS INFORME NACIONAL

15-18 Periodo 2007-2009

Figure 15.8HISTORIC DATA OF ANNUAL GASEOUS RELEASES, UNIT 2

NOBLE GASES

0

1

2

3

4

5

6

7

8

9

10

11

12

1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009

Year

Dos

e [m

rad]

Operating Technical Specification Limit: 10 mrad

Page 133: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

ESTADOS UNIDOS MEXICANOS INFORME NACIONAL

15-19 Periodo 2007-2009

Figure 15.9HISTORIC DATA OF ANNUAL GASEOUS RELEASES, UNIT 1

IODINE, PARTICLES & TRITIUM

0

3

6

9

12

15

18

1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009

Year

Dos

e [m

rem

]Operating Technical Specification Limit: 15 mrem

Page 134: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

ESTADOS UNIDOS MEXICANOS INFORME NACIONAL

15-20 Periodo 2007-2009

Figure 15.10HISTORIC DATA OF ANNUAL GASEOUS RELEASES, UNIT 2

IODINE, PARTICLES & TRITIUM

0

3

6

9

12

15

18

1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009

Dos

e [m

rem

]

Operating Technical Specification Limit: 15 mrem

Year

Page 135: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations

1. Each Contracting Party shall take the appropriate measures to ensure that there are on-site and off-site emergency plans that are routinely tested for nuclear facilities and cover the activities to be carried out in the event of an emergency.

For any new nuclear facility, such plans shall be prepared and tested before it commences operation above a low power level agreed by the regulatory body.

2. Each Contracting Party shall take the appropriate measures to ensure that, insofar as they are likely to be affected by a radiological emergency, its own population and the competent authorities of the States in the vicinity of the nuclear facility are provided with appropriate information for emergency planning and response.

3. Contracting Parties which do not have a nuclear facility on their territory,

insofar as they are likely to be affected in the event of a radiological emergency at a nuclear facility in the vicinity, shall take the appropriate measures for the preparation and testing of emergency plans for their territory that cover the activities to be carried out in the event of such an emergency.

Article 16 (1) Emergency plans and programmes - Overview of the Contracting Party’s arrangements and regulatory

requirements for on-site and off-site emergency preparedness, including applicable laws not mentioned under Article 7

Article 28 of the Nuclear Law states: "Authorizations for construction and operation of a nuclear facility shall be issued only when it can be demonstrated, by presenting the pertinent information, how safety objectives are to be attained and which procedures and methods will be used during the siting, design, construction, operation, modification, cease of operations, definitive shutdown, and decommissioning. In addition, the corresponding radiological emergency plan shall be presented. Such information should follows the terms and forms stipulated in the regulatory provisions of this Law”. In the same way, Article 50, Fraction VII, defines the National Commission of Nuclear Safety and Safeguards’ (the Commission) attributions and responsibilities: "Prior to the start-up of operations, review, assess and authorize the plans that should be in place for dealing with anomalous or emergency conditions in nuclear and radioactive installations".

2007-2009 Period 16-1

Page 136: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

The General Regulation on Radiation Safety establishes in a particular manner, in Article 124, that: “Prior to initiating operations, all radioactive (and nuclear) facilities must have an Emergency Plan congruent with the National System for Civil Protection guidelines and based on a survey of the radiological consequences of accidents that could occur at the facility”. Condition No. 13 of the Operating Licenses of Laguna Verde Nuclear Power Station (LVNPS) Units 1 & 2 emphasizes the necessity to maintain updated the radiological emergency plans. - Overview of the main elements of the national plan (and regional plan, if

applicable) for emergency preparedness, including the role and responsibilities of the Regulatory Body and other main actors

Introduction The Emergency Preparedness for the LVNPS is formed by two complementary plans known as the Internal Emergency Plan (IEP) and External Radiological Emergency Plan (EREP). Internal Emergency Plan The Internal Emergency Plan forms part of the LVNPS Integrated Emergency Preparedness, developed by the Federal Commission for Electricity (CFE). The Internal Emergency Plan describes the organization, resources and directives that will be applied under emergency situations at LVNPS. This organization fulfills the requirement of the United States of America (US) Nuclear Regulatory Commission (NRC) NUREG- 0654. There is an essential group called “Technical Support Group” composed of the Coordinator of Emergencies at the Site and four directors (Radiation Control, Evaluation of Accidents, Repairs of Emergency and Operations) supported by two Notifiers of Emergency and an Advisory Group, with task groups for each of the response areas such as: Fire Protection Brigade, Operational Support, Evaluation of Accidents, Radiochemistry, Dose Projection, Monitoring and Decontamination, Environmental Monitoring, Damage Control, Logistics Support and Physical Security. Additionally, LVNPS has a Technical Support Centre located in an area adjacent to the main Control Room of each unit, where there are work stations with signals from the Integral Information Process System, which provides safety parameters display and key variables of the operating plant status, and the radiation and environmental status.

2007-2009 Period 16-2

Page 137: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

External Radiological Emergency Plan The radiological emergency response organization (ERO) is composed of the Federal and State entities listed below. These entities form the External Radiological Emergency Plan Committee (EREPC):

- Ministry of the Interior - Federal Commission of Electricity - Ministry of Communications and Transportation - Federal Preventive Police - Ministry of Defense - Ministry of Navy - Government of Veracruz State - Ministry of Health for Veracruz State - National Institute for Nuclear Research - National Commission of Water - Federal Attorney for Environmental Protection - CONASUPO Distributor and Commercial Promoter

Representatives of these institutions, with responsibilities in the EREP, participate in the updating of the plan and its procedures regarding personnel training, public information, verification of human and material resources as well as the planning and performing drills and exercises. - Implementation of related measures In order to maintain the effectiveness of the EREP a series of both material and human resources, and also agreements (with state and local authorities) have been established which include the following:

a) Monitoring equipment for response personnel. b) Equipment to determine the magnitude and continuous assessment of a

radioactive material release to the environment. c) Equipment to notify the emergency, on-site and off-site. d) Equipment to evacuate personnel on-site and public from affected area

sectors. e) Site facilities and supplies to decontaminate individuals on-site. f) Off-site facilities and supplies to decontaminate response personnel and the

public. g) Off-site medical facilities and supplies to provide first aid treatment during an

emergency.

2007-2009 Period 16-3

Page 138: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

h) Off-site medical facilities and supplies to provide first aid treatment and specialized medical attention to response personnel and the public.

i) Arrangements to provide medical services and handle on-site radiological emergencies with qualified medical staff.

j) Arrangements to provide medical services with qualified medical staff to attend patients as a result of radiological emergencies.

k) Arrangements for transporting injured and contaminated people from the site and public affected.

l) Technical Support facilities and facilities for operation near the site, from where a good management and effective control can be achieved during an emergency.

m) At least one on-site and another off-site communication system, each one having its own back-up power system.

n) Arrangements to provide sheltering to public evacuated. o) Arrangements for surveillance of the emergency zone as well as for the rescue

of people possibly affected. p) Arrangements to control water and food required within the zone.

- Implementation of emergency preparedness measures by the license

holders

Classification of Emergencies The EREP describes means for determining the magnitude of a radioactive material release, as well as its continuous assessment. The plant and instrumentation conditions, in addition to on-site and off-site radiation surveillance, are used to define emergency action levels. The need for notification and participation of local and state authorities are determined using those emergency action levels. When and what kind of personnel and public protective measures are to be used on-site and off-site boundaries are determined based also on the emergency action levels. There are four classes of emergencies defined as follows. Unusual Event – This class refers to uncommon events in progress or which have occurred, indicating a potential degradation of the plant safety level. In an event of radioactive releases, the value of these exceeds 2 times the Operating Technical Specifications (OTS) limits for a period greater than 60 minutes, not requiring a response or off-site monitoring, unless degradation of safety systems persists. Alert – This class includes those events in progress or which have occurred involving a real or potential substantial degradation in plant safety level. In the event of radioactive releases, it is expected for such releases to exceed 200 times the OTS limit for a period greater than 15 minutes.

2007-2009 Period 16-4

Page 139: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

On-Site Emergency – This class refers to events in progress or which have occurred involving real or probable major failures of operations necessary for public protection. In the event of radioactive releases, it is expected for these to exceed the integrated whole body dose of 1 mSv (100 mR) or infant thyroid dose of 5 mSv (500 mR) during release duration up to site boundary. General Emergency – It includes those events in progress or which have occurred involving a substantial degradation of the core, real or imminent, or melting of the core having a potential to lose contention integrity. Discharges are expected to exceed the integral whole body dose of 10 mSv (1000 mR) or infant thyroid of 50 mSv (5000 mR) beyond site boundary. Two zones are defined for those areas or zones surrounding LVNPS that require of population protective measures: Plume Zone (a radius of 15 km from LVNPS) and Ingestion Zone (a radius of 70 km from LVNPS). To support emergency preparedness activities the following tools are available:

a) Integral Process Information System, that includes the Safety Parameter Display System (SPDS).

b) The computer code known as Radiological Assessment System for Consequences Analysis (RASCAL) developed by Oak Ridge National Laboratory.

c) Methods of Core damage estimation based on computer code known as “Melting Core” (MELCOR) developed by Sandia National Laboratory.

In addition to these computational tools, the following analytical tools are available, for confirmatory purposes only:

a) Isotopic analysis using Gamma spectrometers. b) Ionic chromatography. c) Atomic adsorption.

All systems and equipment mentioned above are available at LVNPS and qualified and trained personnel to operate them are available.

Main elements of the on-site and, where applicable, off-site emergency plans for nuclear installations

Internal Emergency Plan The implementation of the Internal Emergency Plan is a CFE’s responsibility, for the preparedness, response and recovery phases.

2007-2009 Period 16-5

Page 140: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

The Internal Emergency Plan is made up of the following facilities:

a) Technical support centre. b) Main control room. c) Operational support centre. d) Dose projection centre. e) Accident evaluation centre. f) Damage control centre. g) Radiation control centre. h) Medical assistance centre. i) Environmental surveillance centre. j) Alarms central station. k) Decontamination and first aid station. l) Post-accident sampling station.

The IEP also provides for the existence of the following materials and equipment:

a) Personal protective equipment. b) Breathing protective equipment. c) Radiation monitors. d) Contamination monitors. e) High volume air monitors. f) Electronic dosimeters and Thermo Luminescent Dosimeters (TLD) g) Primary and alternate communication systems. h) Plant alarm systems (fire, emergency, evacuation) i) Intensive-care medical unit. j) Fire rescue unit. k) Environmental surveillance unit. l) Buses for personnel transportation. m) Potassium iodine for radiation prophylaxis.

External Radiological Emergency Plan The External Radiological Emergency Plan is a responsibility shared by several Federal and State of Veracruz entities which form the External Radiological Emergency Plan Committee (EREPC). The entities that participate are: Federal Commission of Electricity, Ministry of the Interior, Ministry of Defense, Ministry of Navy, Ministry of Communications and Transportation, Preventive Federal Police, Civil Protection Office of the State of Veracruz, Health Office of the State of Veracruz, Federal Attorney for Environmental Protection, National Commission of Water, and Distributor and Commercial Promoter (CONASUPO).

2007-2009 Period 16-6

Page 141: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Facilities provided by the license holder for emergency preparedness (if appropriate, give preference to descriptions under Article 18 and Article 19 (4), respectively)

The responsibilities of each agency are defined in the EREP Manual and its procedures for each phase of the plan: preparedness, response and recovery. Facilities that make up the EREP are the following: Operated and maintained by CFE:

a) Main emergency control centre. b) Alternate emergency control centre. c) Vehicles and equipment decontamination centre – North. d) Vehicles and equipment decontamination centre – South. e) Monitoring centre for evacuee – North. f) Monitoring centre for evacuee – South. g) Exposure control post – North. h) Exposure control post – South. i) Evacuation routes within Plume Zone (over 130 km of paved roads) j) Environmental engineering laboratory (TLD reading and sampling analysis) k) Back-bone communications network including central and repeater stations.

Operated and maintained by other institutions:

a) Temporal shelters. b) Hospital of specialized medical assistance. c) State (of Veracruz) health laboratory. d) Aircraft decontamination centre. e) Hospitals of general medical assistance.

The EREP also provides for the existence of the following materials and equipment:

a) Personal protective equipment. b) Breathing protective equipment. c) Radiation monitors. d) Contamination monitors. e) High volume air monitors. f) Electronic dosimeters and TLDs. g) Primary and alternate communication systems. h) Fire rescue unit.

2007-2009 Period 16-7

Page 142: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

i) Ambulances. j) Vehicles to notify the population. k) Tow trucks to clear evacuation routes. l) Buses for personnel transportation m) Potassium iodine for radiation prophylaxis

- Training and exercises, evaluation activities and main results of performed

exercises The training related to emergency plans and programmes receiving LVNPS, has an annual validity and is divided into Internal Emergency Plan and the External Radiological Emergency Plan. Training for personnel involved in the Internal Emergency Plan The nearly 700 LVNPS employees who have assigned duties in the Internal Emergency Plan receive continuing training every year. The following table shows the number of courses attended, depending upon the tasks the staff is involved.

YEAR Training (courses)

2007 2008 2009 Physical security 6 6 5

Chemical 6 8 6

Damage control 19 21 18 Operation support group – Non-licensable 6 8 6

Accident evaluation 4 4 4 Unit monitoring and decontamination 6 7 6

Dose projection 3 3 3 On-site environmental monitoring

3 3 3

Medical 3 4 4

Notifiers 5 5 5

Technical support 2 1 1 Operation support group – Licensable

16 16 16

Logistics support (warehouse) n/a 3 4

2007-2009 Period 16-8

Page 143: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Training for personnel involved in the External Radiological Emergency Plan The nearly 300 LVNPS employees who have assigned duties in the External Radiological Emergency Plan receive continuing training every year. The following table shows the number of courses attended, depending upon the tasks the staff is involved.

YEAR Training (courses)

2007 2008 2009 Train the trainers on EREP 1 1 1 Evacuee monitoring centre 4 4 4 Vehicle decontamination centre 4 4 4 Exposure control 2 2 2 Notification 2 2 2 Services 0 1 1 Dose calculation 2 2 1 Technical analysis 2 2 2 Monitoring and decontamination techniques

0 0 4

Decontamination mobile unit 0 0 1 CFE’s task force coordination 1 1 1 Logistics support 1 1 1 Environmental surveillance 2 2 2 Course “Emergency plans for EREP´s coordinator” (NEI)

0 0 1

Site recount 2 2 2 Transportation 1 1 1 Laboratory 1 1 1

Additionally, CFE supports the training of staff from the different state and federal agencies, participating in the EREP. Either the people take the training delivered by LVNPS at CFE facilities (for example, the Federal Attorney for Environmental Protection personnel attended the CFE’s course “Monitoring and decontamination techniques”), or CFE’s teachers deliver the courses in other agencies facilities (for example, Train the trainer on EREP, Use of communications equipment, Emergency Plan, LVNPS Nuclear technology, Radiation monitors). Internal Emergency Plan exercises and drills During the 2007-2009 period, several Internal Emergency Plan drills were conducted to verify the facilities and equipment readiness, and the staff training. The number of drills for each area per year is summarized in the following table.

2007-2009 Period 16-9

Page 144: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

YEAR AREA 2007 2008 2009

Emergency notification 4 4 4 Fire protection 52 47 57 First aid 1 1 1 Monitoring and decontamination 5 4 4 Environmental surveillance 1 1 1 Dose projection 2 2 2 Post-accident sampling 6 6 4 Accident evaluation (plant condition and situation) 2 2 2

PEI-FT-82 1 2 1 Damage control 2 2 2 Accounting and evacuation 2 2 2 Severe storm 2 2 2

External Radiological Emergency Plan exercises and drills During the 2007-2009 period, several External Radiological Emergency Plan drills were conducted to verify the facilities and equipment readiness, and the staff training. The number of drills for each area per year is summarized in the following table.

YEAR AREA 2007 2008 2009 Notification to control Head 3 3 1 Evacuee monitoring, classification and decontamination 4 6 4

Vehicle and equipment monitoring and decontamination 4 6 4

Off-site environmental surveillance 1 2 1

Exposure control and Laboratory 1 3 1 Dose calculation 1 3 1 Accident evaluation, Protection actions and Technical analysis 2 3 1

Communications 1 3 1 Logistics support 1 3 1 IEP / EREP desk exercises 1 4 1 Site recounting, transportation and evacuation of convening centres

1 4 1

Total 20 40 17

2007-2009 Period 16-10

Page 145: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Also in 2008, an integrated exercise to test the full operation of the information exchange mechanism worldwide was conducted. The exercise is referred as the International Atomic Energy Agency (IAEA) Convention Exercise “ConvEx-3” and it had the participation of the IAEA and other international bodies and agencies of several countries. The exercise allowed testing the effectiveness of early notification treaties and international cooperation in case of emergencies at nuclear power plants. Evaluation activities Training on emergency planning has two delivery methods as mentioned above. Theoretical training (classroom training) and practical training (field drills). The training evaluation is done as follows.

a) Theoretical training At the end of the training session, the trainees take a written examination to demonstrate that the necessary knowledge to carry out the activity that they have assigned in the Emergency Response Organization (ERO) was acquired and / or reinforced.

b) Practical training

During the training sessions, the trainees are required to perform their assigned activity, according to the emergency plan for a preset accident scenario (unknown to the trainees). They need to use all the material resources to undertake such activity. The accident response is evaluated according to each trainee performance, which must be in adherence to the procedure and operational manual, taking into account the critical steps to satisfactorily perform the activity.

Both the theoretical and practical training are evaluated following the procedure PERE-214 guidelines. Main results During the 2007-2009 period, the following emergency plans improvements were made.

a) External Radiological Emergency Plan i. Creation of an advisory group for the EREP Control Headquarters,

consisting of multidisciplinary staff with experience in plant operation and, dose calculation and accident evaluation issues.

ii. The emergency facilities, including the main and alternate emergency control centres were restored.

2007-2009 Period 16-11

Page 146: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

iii. The roads of all the evacuation routes were paved, including some secondary roads.

iv. The back-bone communication network was restored and a Mobile Decontamination Unit for people, equipment and vehicles was acquired.

b) Internal Emergency Plan

i. The Nuclear Energy Institute (NEI) 99-01 “Methodology for

Development of Emergency Action Levels”, Revision 4, was used and the NRC Bulletin 2005-02, "Emergency Preparedness and Response Actions for Security-Based Events" was implemented.

ii. The regulatory requirement set forth in Section N.1.b of NRC NUREG-0654 states that every person of the Emergency Response Organization shall participate in at least one drill every five years. This requirement was met, by nearly 700 employees that form the ERO.

iii. Version 3.0.5 of the RASCAL computer code for dose projection and calculation was installed.

iv. The Internal Emergency Plan deficiencies identified by the Commission were solved.

- Regulatory review and control activities Internal Emergency Plan According to the base-line inspection programme, the Commission annually carries out an inspection to the Internal Emergency Plan to verify the following:

a) The changes made to the Emergency Response Organization. b) The independent reviews and audits, and the internal reviews and audits

conducted to the Internal Emergency Plan. c) The alert and notification system. d) The method for increasing the ERO. e) The changes to the emergency action levels and the Internal Emergency Plan. f) The effectiveness in identifying and correcting weaknesses and deficiencies. g) The drill programme and the assessment of the drills performed. h) The facilities and equipment. i) ERO member training.

Moreover, the Commission’s inspectors ask LVNPS staff to perform exercises, to witness compliance with the Internal Emergency Plan applicable regulation.

2007-2009 Period 16-12

Page 147: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

As a result of these inspections, the Commission found the following:

a) Weaknesses in the training delivered to personnel involved with the ERO. b) Organizational changes that can decrease the effectiveness of the Internal

Emergency Plan. For example, incorporating the unit that makes the independent verification of the IEP into the ERO, without previous notice to the Commission.

c) Deficient external communications. External Radiological Emergency Plan The Commission’s control and assessment of the External Radiological Emergency Plan have been implemented through a documental review, a field inspection of the EREP’s Task Forces and the execution of exercises for the EREP activities. During the 2007-2009 period, the Commission organized, at IAEA’s request, the IAEA Emergency Conventions (ConvEx-3) exercise, which took place from July 9 to 10, 2008. As a result of this exercise the Commission issued a report with several recommendations, mainly related to the following:

a) The documents generated during the exercise were not properly filled out according to the instructions and the information delivery was, in some cases, untimely.

b) The understanding of the accident scenario scope used for the exercise was not optimal, because some required data was not documented, including some last minute changes in the plant events during the simulator runs.

c) The ability to perform environmental surveillance (water and food) outside the 16 km radio.

In this regard, the Commission verified that the deficiencies mentioned above were included in the Corrective Action Programme (CAP), to determine the corrective and preventive actions. The Commission will follow up through the inspections base-line programme. Also, the inspection to the CAP will verify the license assessments to prevent recurrence of those weaknesses. Article 16 (2) Information of the public and neighboring states - Overview of Contracting Party’s arrangements for informing the public in the

vicinity of the nuclear installations about emergency planning and emergency situations

One of the key factors for a successful implementation of the measures to protect the population living in a radius of up to 16 km from LVNPS is the information regarding

2007-2009 Period 16-13

Page 148: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

their participation in the event of a radiological emergency. The main information media are the following:

a) The EREP calendar, which is distributed in all homes and businesses located in a radius of up to 16 km from LVNPS. The calendar has information on actions to be completed by the population in case of an emergency. This information is delivered to about 3,800 households.

b) The bus-classroom known as “Vasconcelos”, acquired by CFE and operated by the state of Veracruz government, has an influence radius of 16 km from LVNPS. Such bus-classroom reaches about 3,500 people per year and delivers information regarding the LVNPS, nuclear technology, the External Radiological Emergency Plan and the civil protection plan.

c) Visits of communities to the LVNPS Information Centre started in 2009. The information centre makes the invitation and provides transportation for the community groups. The communities have the opportunity to go to the centre and receive information about the External Radiological Emergency Plan. This programme received about 1,000 people in the year.

d) From 2004 to 2008, a reach out programme called “EREP fairs” for all communities was carried out, to share information about the protection measures through different activities. The programme was replaced by the visitor’s programme to the Information Centre mentioned previously.

- Arrangements to inform competent authorities of neighboring States, as

necessary Since 1988, Mexico is part of the “Convention on Early Notification of a Nuclear Accident” and the “Convention on Assistance in the Case of a Nuclear Accident or Radiological Emergency”; therefore, there is a procedure to notify a radiological emergency at a Mexican nuclear installation if such an emergency has the likelihood to affect the territory of neighboring States. The procedure objective is to notify under the terms of the convention mentioned previously and its application is the responsibility of the Commission. Regardless of this, Mexico has bilateral agreements for exchange of technical information (including the occurrence of significant events) with their closest neighbors. Mexico is also part of the IAEA Early Communications International System, which would be used to immediately provide information to the IAEA in the event of a radiological emergency at LVNPS. The same information is available to neighboring States. Mexico is also a signatory of the “Vienna Convention on Civil Liability for Nuclear Damage”. It is important to mention that the nearest country to LVNPS site is over 500 km away. Mexico has a National System for Civil Protection. In the event of a radiological emergency at a nuclear installation in Unites States of America, near the border with

2007-2009 Period 16-14

Page 149: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Mexico, with likelihood to affect the national territory, the DN3 Plan would be activated. The Ministry of National Defense is responsible to apply the DN3 Plan under the direction of the Ministry of the Interior, assisted by the Ministry of Health and CONASUPO. The DN3 Plan includes the infrastructure required to establish adequate communications, evacuation capacity and establishment of control points for taking the appropriate actions during the emergency. However, it should be noted that the US nuclear power plants are sited more than 100 km from the Mexico’s border and other Central American countries such, as Guatemala, do not have this kind of power stations. Article 16 (3) Emergency preparedness for Contracting Parties without

nuclear installations Not applicable.

2007-2009 Period 16-15

Page 150: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTICLE 17. SITING 17.0 Obligations “Each Contracting Party shall take the appropriate measures to ensure that appropriate procedures are established and implemented: i) for evaluating all relevant site-related factors likely to affect the safety of a nuclear facility for its projected lifetime; ii) for assessing the likely safety impact of a proposed nuclear facility on individuals, society and the environment; iii) for re-assessing as necessary all relevant factors referred to in sub-paragraphs (i) and (ii) so as to ensure the continued safety acceptability of the nuclear facility; iv) for consulting Contracting Parties in the vicinity of a proposed nuclear facility, insofar as they are likely to be affected by that facility and, upon request providing the necessary information to such Contracting Parties, in order to enable them to evaluate and make their own assessment of the likely safety impact on their own territory of the nuclear facility. Article 17 (1) Evaluation of site related factors - Overview of the Contracting Party’s arrangements and regulatory

requirements relating to the siting and evaluation of sites of nuclear installations, including applicable national laws not mentioned under Article 7

Prior to granting the Construction Permit, the owner of Laguna Verde Nuclear Power Station (LVNPS) provided information for authorization of the location of the site where the construction was to initiate; even though the Nuclear Law is posterior to the initiation of the construction work, the regulatory standards to approve this stage of the installation were 10CFR100 and 10CFR50 Appendix A. The following Regulatory Guides (RG) were added as soon as edited:

a) RG 1.29, defining seismic design classification. b) RG 1.59, related to design basis for flooding. c) RG 1.60 defining seismic design response spectrum. d) RG 1.61 establishing seismic design damping values. e) RG 1.70 on safety report standard forms and contents. f) RG 1.76 on design basis tornado.

2007-2009 Period 17-1

Page 151: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

g) RG 1.91 considering human activities nearby nuclear installations, defining explosion characteristics occurring within the vicinity of the plant.

h) RG 1.102 on protection against floods. i) RG 1.111 on radioactive effluent dispersion. j) RG 1.132 on foundation investigations. k) RG 4.2 on environmental impact reports.

Also, the Regulatory Guide 1.165, "Identification and Characterization of Seismic Sources and Determination of Safe Shutdown Earthquake" was used in 1999 to assess the changes to the Operating Technical Specifications (OTS).

Overview of assessments made and criteria applied for evaluating all site related factors affecting the safety of the nuclear installation

The main objective of assessing the location of nuclear facilities from the nuclear safety standpoint is to protect the public and the environment from the radiological consequences of radioactive releases due to accidents. The assessment must also take into account the emissions caused by normal operation of the installation. The suitability assessment of a site to build a nuclear installation must take into consideration the following aspects:

1. The effects of external events that take place in the region where the site is located (these events can be natural or man-made);

2. The site and the characteristics of its surrounding that could influence the exposure of humans and the environment to emissions of radioactive materials;

3. The population density and distribution, and other off-premise characteristics insofar as they are likely to prevent applying emergency measures and assessing the risks to individuals and the population.

Overview of design provisions used against human made external events and natural occurring external events such as fire, explosion, aircraft crash, external flooding, severe weather conditions and earthquakes

LVNPS Units 1 & 2 siting design basis After performing an analysis, with technical assistance of experts from the International Atomic Energy Agency (IAEA) in 1968, on the different sites proposed, it was decided that the site with suitable seismic, accessibility, cooling water supply, demographic and location characteristics was the place located on geographic co-ordinates UTM Latitude 19° 43’ 30” North and Longitude 96° 23’ 15” West, in the State of Veracruz.

2007-2009 Period 17-2

Page 152: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Once the preliminary selection was made, detailed studies were initiated, considering Geography, Demography, Meteorology, Hydrology, Geology, Geotectonic, and Seismicity as well as the impact these would have on the facilities, occurrence of diverse weathering and man-made activities. This information was provided as part of the Preliminary Safety Analysis Report (PSAR), later updated in the Final Safety Analysis Report (FSAR) and submitted to the National Comisión Nacional de Seguridad Nuclear y Salvaguardias (the Commission) as a support of the license application to operate LVNPS Units 1 & 2. In addition, the Commission requested the delivery of a Final Environmental Impact Report (FEIR) in addition to the information presented in the Final Safety Analysis Report. Main site characteristics (Geography and Demography, Impact of Industrial Installations and Geology, Seismology and Geotectonic Engineering) used in defining design basis related to LVNPS Units 1 & 2 siting are briefly identified below. Geography and demography The demography analysis performed took into account population growth perspectives, zones of its influence and changes in the land uses up to the year 2020. Areas of property over which the Federal Electricity Commission (CFE) has authority were defined exactly as required by the applicable standards, for instance the Restricted Area, Controlled Area and Exclusion Area.

There are no high-density population areas within a vicinity of 10 km from LVNPS. Similarly, there is only one settlement of 5 inhabitants within a radio of 2 km from the plant. The low population area, as defined in 10CFR100, consists of an area of a radio of 15 km from the site. Population projected within this zone for the year 2020 is approximately 34,530 inhabitants, being considered a low density population. Population centers currently of over more than 20,000 inhabitants covering a radio of 70 km from LVNPS are:

CITY

POPULATION

DISTANCE FROM SITE (km)

DIRECTION

Coatepec 127,531 65.6 WSW

Jalapa 635,364 57.5 WSW

Veracruz and surrounding suburbs

~ 1,000,000 70.0 SSE

2007-2009 Period 17-3

Page 153: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Impact of industrial transportation and military facilities nearby the site

There are no military, chemical or manufacturing industries, airport or chemical storage facilities within a radio of 8 km from the site which could potentially affect the operation of LVNPS Units 1 & 2. The most important route of transportation within a radio of 10 km is Federal Road No. 180 running north to south and 2 km east from the site. This road serves as the means of access to LVNPS having a vehicle flow of less than 3,000 vehicles per day. The nearest commercial railway is located at 40 km from the site and there is a private industrial railway extension 15 km from the site, which is rarely used. The nearest airport is located 70 km south from Laguna Verde, in Veracruz. The main runway is 2,500 m long and 45 m wide. A maritime route between Veracruz and Tampico passes in front of the site at an approximate distance of 83 km. In addition, small fishing boats operate over 5 km away from Laguna Verde’s coast. The design of the intake structure of LVNPS Units 1 & 2 considers breakwaters to protect it from any impact produced by this kind of boats. A 7.5 cm diameter oil pipe and another 121 cm diameter pipe for natural gas, property of the Mexican oil company (PEMEX) passes by LVNPS’ installations (Reactor Building) at approximately 1,200 m.

As part of the assessment of the impact of facilities within the vicinity on LVNPS Units 1 & 2, the following events were analyzed:

Explosions

a) Due to the distance between the road and maritime routes, and LVNPS, no event postulated on such routes represents a risk for structures important to safety, since the effects caused are involved in considerations of the seismic design basis, tornado design basis and hurricane design basis.

b) Hypothesis of gas pipe line incidents were analyzed in regards to:

Explosion and thermal load through ignition of leaked gas

Results of the analysis show both that the pressure peak caused as well as the thermal load produced by explosion are inferior to the hurricane design basis and thermal structural design.

Toxic chemicals

2007-2009 Period 17-4

Page 154: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

No important amounts of toxic chemicals are used or stored within the vicinity (8 km) of LVNPS. Fires There are not any external installations within the vicinity of LVNPS, which could lead to producing fire conditions. Therefore, considering the above-cited information, it is observed that there are not any installations within the vicinity which may be considered as a basis for the design of LVNPS. The design of Structures, Systems and Components (SSC) for LVNPS Units 1 & 2 was based upon normal and extreme meteorological and hydrological conditions, which could hypothetically appear at site. This includes the consideration of maximum sustained winds, tornado winds, effects from a maximum possible hurricane, maximum probable flooding and siege, surge and tsunami wave effects. Furthermore, and in a conservative manner, structures important to safety have been analyzed against stresses resulting from an elevated 3 m high flood above the installation’s ground level. Geology, seismology and geotectonic engineering LVNPS siting is located at the intersection of parallel 20 and the Trans-Mexican Volcanic Belt (TMVB). This belt is an east-west trending belt of volcanic vents and volcanic units that extends from the Pacific coast north of Puerto Vallarta to the area of the LVNPS site on the Gulf of Mexico. The TMVB is the indirect result of the subduction of the oceanic Cocos Plate sliding beneath continental Mexico from the Middle America Trench along the Pacific Coast of southern Mexico. The subducted slab of the Cocos Plate melts at depths of about 100 km, producing magma that rises to form the volcanoes and related magma bodies of the TMVB. Heat flow measurements suggest that the TMVB typically have a thin brittle crust with the remaining crust below being typically plastic rather than brittle. This thin brittle crust cannot store great strain energy, which explains why the TMVB is located in an area of relatively low seismicity, and that the damaging earthquakes that have occurred within the TMVB have not approached in magnitude to the great earthquakes typical of the Benioff Zone. LVNPS’s siting is located in the Trans-Mexican volcanic belt, close to the eastern border of the province. The installation is founded on a mass of Pliocene-Pleistocene basaltic rocks running along the Gulf of Mexico over an approximate 1.4 km extension of a variable 30 to 50 meter thickness. Stratigraphic studies show the existence of a subjacent layer of alluvium consolidated deposits of a 40 to 65 meter thickness deposited over andesitic material, extending itself 150 meters in depth. The basaltic

2007-2009 Period 17-5

Page 155: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

layer presents a columnar fracture of thermal nature of lengths going from 6 to 8 meters.

In order to satisfy the regulatory requirements, CFE performed the following studies: Physiography, Geological History, Differential Settlements and Upheavals, Stratigraphy, Faulting, Chemical Weathering, Cavernous and Carstic Terrain, Subsoil Faults Under Dynamic Load, Pre-consolidation Evidence through Volcanic Erosional Processes, Liquefaction, Slope Stability, Permeability and Paretic Levels, Seismic Stability of Alluvium Materials subjacent to Superficial Basalt and Flow of Ashes and Lava from a Potential Volcano Eruption. Because of the proximity of the site to different volcanoes of the eastern TMVB, the near field effects (ash fall and lava) at El Abra and the far field effects eruption at Pico de Orizaba, were analyzed. Due to the geologic characteristics, morphology of the cone and crater, other kinds of possible effects were not considered possible. There is not any evidence to associate the cinder cones at El Abra with historic macro-seismicity. In this specialty, the atmospheric shock waves induced by explosions were also considered. The following regional environmental studies were performed covering a radio of 320 km: Volcanic activity, Superficial faulting, Tsunami and Tectonic of sea bed, Attenuation of vibratory movements of Trans-Mexican volcanic belt terrain, Tectonic provinces and maximum historically-related earthquakes, Acellerograms, Determination of Design Basis and Operation Basis Earthquakes, Geological-Seismic conditions on continental platform and Sea bed boundary, Correlation of regional seismicity with that of the site, Structural relations between "Graben", "Palma Sola", "Cofre de Perote" and "El Farallon", Related tectonics; Analysis of two faults parallel to volcanic cones of "El Abra", Related tectonics; Distribution of mine fracture systems and the zone of "La Viga-Tuxtla" as well as distinction fracture system of "El Abra, Tectonics related. The seismic design basis for LVNPS was defined using the Peak Ground Accelerations that were computed for the maximum earthquakes identified for each seismotectonic province and similarly for each of the potential seismogenic structures that were identified within the Trans Mexican Volcanic Belt. Peak ground accelerations were computed using six different formulas that appear in common literature (Campbell, Joyner and Boore, Idriss, Bufaliza, Esteva and Villaverde and Esteva conservative). The response spectrum for the design Safe Shutdown Earthquake (SSE) was obtained using the criteria of the United States of America (US) Nuclear Regulatory Commission (NRC) Regulatory Guide 1.60 and, the value of 0.26 g for the safe shutdown peak acceleration was determined. The return period for the design SSE is

2007-2009 Period 17-6

Page 156: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

2,000 years. From this value it was obtained as 0.14 g for the Operating Basis Earthquake (OBE) that corresponds to nearly a half of the SSE.

These seismic design parameters for LVNPS were originally developed from a conservative assessment of the potential for earthquakes in eastern continental Mexico and the adjacent area of the Gulf of Mexico and are based on pre 1979 site specific studies regarding site ground motion characteristics. Subsequently the CFE has undertaken a series of geological, geophysical, seismological, and engineering investigations to better evaluate the potential for earthquake induced ground motion at the site. The results of these studies confirm the conservatism of the original design parameters and do not suggest the necessity for changes in the original design criteria. These last studies were issued in 1987 and performed taking into account a large amount of data coming from different sources: PEMEX, The US Geological Survey, The Texas University, and The Texas A & M University. These studies not only confirmed the original design ground acceleration and potential for an earthquake, but they strongly indicate that a lower ground acceleration motion could be proposed to the Commission. The original and current ground motion is 0.26 g and the last studies suggest an acceleration of 0.18 g. As part of the Periodic Safety Review (PSR) process, performed back in 1999, the above was confirmed and currently CFE is carrying out a Probabilistic Safety Analysis (PSA) of External Events which considers seismic events. Particularly, in relation to the volcanic risk and as an example of the detail and deepness of the studies performed, both active and non-active volcanoes within a radio of 150 km from the site, including those corresponding to the sea bed, were analyzed. In order to provide conservative results of the effect of a volcano eruption, the following was considered as an analysis basis event:

1. The birth of a new volcano 13.5 km away from the site in direction of the

ash volcanoes "El Abra", producing quantities of ash and lava equivalent to data on the Paricutin Volcano, and

2. The eruption of the "Peak of Orizaba", considering the amount of ash expulsed equivalent to that of Mount St. Helen in US on May 18, 1980.

Results determined that the effect of a nearby ("El Abra”) or so far ("Peak of Orizaba”) volcano eruption would not affect the safe condition of LVNPS Units 1 & 2. - Regulatory review and control activities The Commission assessed the FSAR provided by the license applicant to assure that the report includes on-site and off-site characteristics and an analysis of relevant accidents. Compliance with the site-related regulations presented in Section 17.2 of

2007-2009 Period 17-7

Page 157: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

this Article was also assessed. The physical characteristics and the man-made risks assessed are presented below. Earthquakes The seismic and geological conditions of the region, and the geological and geotechnical engineering aspects of the site area were assessed. Additionally, information on historical earthquakes and the earthquakes recorded by the instrumentation of the region was collected and documented, in order to determine the earthquakes associated risks through regional seismotectonic assessments. Superficial faults An assessment was made to determine if there were superficial faults in the site´s vicinity and the probability that earthquakes could have been caused by them. Volcanoes The existence of volcanoes in the site vicinity and the effects they would have on the installation safety were assessed. Hurricanes and tornadoes The possibility of having hurricanes and tornadoes in the region of the site was assessed and historical data of these phenomena were collected. For hurricanes, the associated risks were determined with the available data, considering factors such as wind speed, pressure and extreme rainfall. For tornadoes, the risks considered were based on the maximum rotation of wind, pressure differentials and the pressure rate of change. In both cases, the missiles supposedly generated by these phenomena were taken into account. Floods The possibility of occurrence of floods due to rains, tsunamis and sieges was assessed. For floods caused by rain, the meteorological and hydrological model was reviewed, taking into account the uncertainty and the amount of available data for the region. For floods caused by tsunamis, the likelihood of occurrence based on the seismic records and the known seismotectonic characteristics was addressed. Geotectonics The site and its surroundings were assessed to determine the potential for slope instability and ground liquefaction. The geologic maps to determine the existence of natural formations, such as caves, were also reviewed and the geotectonic characteristics of subsurface materials and the site soil profile were investigated.

2007-2009 Period 17-8

Page 158: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Explosions The region activities involving the handling, processing, transport and storage of chemicals, or flammable materials that could cause explosions or clouds capable of producing gas deflagration or detonation were assessed. The risks associated with the explosions in terms of overpressure and toxicity was also assessed, taking into account the distance to the installation. Airplane crashes The potential airplane crashes in the vicinity of the site were assessed, based on the characteristics of air traffic. Article 17 (2) Impact of the installation on individuals, society and

environment - Criteria for evaluating the likely safety related impact of the nuclear

installation on the surrounding population and the environment In compliance with the General Law of Ecological Equilibrium and Environmental Protection, as well as the requirements for granting the LVNPS Operating License, CFE submitted to the Commission a Final Environmental Impact Report (FEIR) following the guidelines of the USNRC Regulatory Guide 4.2. The main purpose of this report is to demonstrate that the impact of the LVNPS operation will not cause relevant disturbances in the site immediate environment. - Implementation of these criteria in the licensing process The Licensee has established an environmental surveillance program to determine the impact of the LVNPS normal operation. The surveillance program is governed by Section 12 of the LVNPS Units 1 & 2 Operating Technical Specifications. This program was run since 1978, depending on the type of sample, in the pre-operational phase up to 1988 to determine the base of reference. The reference enables comparing the data generated during the LVNPS normal operation, allowing detecting quickly and safely any alteration to the environment. It is important to mention that LVNPS carries out an environmental surveillance program 300% larger than that established in the OTS, ensuring a more effective and efficient surveillance of the environment and the population. Prior to the granting of the LVNPS Units 1 & 2 Operating Licenses, the Commission assessed the FEIR both, for normal operation conditions, in terms of the radioactive liquid and gaseous, chemicals, biocides and sanitary effluents; as well as for abnormal conditions or accident scenarios. The accident scenarios assumed for the assessment had the objective to verify the installation’s capacity to control and

2007-2009 Period 17-9

Page 159: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

mitigate the severe abnormal conditions, although the scenarios had a very low occurrence probability. The assessment results concluded that the real impact of the LVNPS operation produce effects on the environment which fully meet the design bases of the installation. Despite the environment surveillance program developed and implemented by CFE is appropriate and reliable, and its results are subjected to an international inter-comparison analysis; since 1979 the Commission started a program of measurements of environmental samples to determine the base of reference and monitor LVNPS operation completely independent of CFE’s program. So far the results obtained by CFE have been consistent with those obtained by the Commission. The pre-operational environmental radioactivity values and the current data show no statistically significant variations among them. Article 17 (3) Re-evaluation of site related factors - Activities for re-evaluation of the site related factors as mentioned in Article

17(1) to ensure the continuing acceptability of the safety of the nuclear installation

The site-related factors that have required re-assessment to ensure a continuous safety level at LVNPS are:

1. Seismic events. LVNPS staff has recorded a number of seismic events. Two of these events have been of particular interest; one occurred on June 1997 and another on August 2000. Both earthquakes exceeded the OBE spectra in the high frequency range.

2. Identification of the design basis for the maximum wave height, the magnitude and direction of winds and tides applicable to the design of the LVNPS intake structure. LVNPS staff, driven by the external operational experience, reviewed the available historical data of the wave height, and the magnitude and direction of winds and tides to determine if they are covered by the original design and implement changes according to the results.

3. Intake structure fouling due to the entry of kelp. LVNPS staff, driven by the external operational experience, reviewed if there were intake structure fouling events caused by organic and inorganic material.

- Results of recent re-evaluation activities The results from site-related activities that have required re-assessments were:

2007-2009 Period 17-10

Page 160: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

1. Seismic events.

It was concluded that the seismic events re-assessed have not had adverse effects on the LVNPS safety. However, conservatively the following measures were taken: (a) the guidelines of the USNRC Regulatory Guide 1.166 “Pre-Earthquake Planning and Immediate Nuclear Power Plant Operator Post-earthquake Actions”, which consider the effects of high frequency ground motions, were adopted. Therefore, the OBE Exceedance Criterion was incorporated into LVNPS; (b) the nuclear damage scale proposed in Electrical Power Research Institute NP-6695 “Guidelines for Nuclear Plant Response to an Earthquake” was incorporated, which is similar to the Mercalli intensity scale; and (c) LVNPS seismic monitoring system was updated.

2. Identification of the design basis for the maximum wave height, the magnitude

and direction of winds and tides applicable to the design of the LVNPS intake structure.

It was determined that:

a) For the period 1980 to 2009, a maximum wind speed of 163 km/h at the

site occurred in 1986, which is below the Probable Maximum Hurricane (PMH) of 304 km/h and the Standard Design Hurricane (SDH) of 234 km/h parameters for LVNPS. For the period 1871-2009 the maximum wind speed recorded in the vicinity of the site is 280 km/h due to the tropical cyclone “Janet” which occurred in 1955. Therefore, the wind magnitude and direction used as design basis remain valid.

b) The average wave heights that have been recorded at LVNPS site are in the range of 0.1 to 0.5 m. Therefore, the actual maximum wave height has not exceeded the LVNPS design parameter of 5.5 m.

The sea levels recorded at the LVNPS intake structure associated to the natural high and low tides are within the design range of -1.6 m and 4.136 m. However, the seawater level in the intake structure has been affected by the silt in the waterway, producing low level values very close to the minimum. The studies performed by the Department of Mathematical Modeling of the Civil Engineering Studies, determined that the silt can cause a drop of 0.5 m of the seawater level. For this reason, as a corrective action, waterway was dredged up to a depth of 5 m.

3. Intake structure fouling due to the entry of kelp.

As a result of the assessment, it was found that the fixed and traveling mesh capacity, based on the design parameters, is greater than the water intake requirements. However, considering the maximum expected rate of arrival and the physical characteristics of kelp, and the rake configuration, both the fixed

2007-2009 Period 17-11

Page 161: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

and traveling mesh would be blocked by the kelp trapped into them. To address this issue, a nylon mesh at the dock entrance preventing the massive transfer of kelp into the intake was installed. The amount of kelp that can go through the nylon mesh is within the removal capacity of the fixed and traveling mesh cleaning systems.

- Regulatory review and control activities The regulatory control and assessment activities performed include the following:

1. Seismic events. The Commission has assessed the analysis performed by the Licensee to evaluate the effects of seismic events. The Commission has determined that no damage has occurred to the LVNPS systems, structures or components. The actions taken by the LVNPS were also considered conservative and acceptable.

2. Identification of the design bases for the maximum wave height, the magnitude and direction of winds and tides applicable to structures in the LVNPS intake structure. As a result of the assessment performed by the Commission, it was found that the tides (sea levels), the magnitude and direction of winds, and wave height at the intake structure are within the original design parameters. Likewise, it was considered that despite the intake seawater level was affected by the silt in the waterway, the corrective action of dredging at depths of 5 m, has ensured that the silt does not have negative effects on sea level in the intake lift. For this reason, it is considered that the corrective actions solved this problem, so no further actions were required.

3. Intake structure fouling due to the entry of kelp.

As a result of the assessment performed by the Commission, which included the possible loosening of the nylon mesh, it was found that it is not possible to have an accident different from those previously analyzed in the FSAR nor it is an “unreviewed safety questions”. Although the fixed and traveling mesh system is not safety related, the arrival of kelp does not compromise LVNPS safety because of the adequate monitoring and filtering and cleaning devices installed, as well as their current situation.

Article 17 (4) Consultation with other Contracting Parties likely to be affected

by the installation - International arrangements

2007-2009 Period 17-12

Page 162: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

An international agreement subscribed by Mexico is understood as any "written international agreement agreed between States and governed by international law, whether embodied in a single instrument or in two or more related instruments, and whatever its particular designation" as stated in Article 2, paragraph a) of the Vienna Convention on the Law of Treaties of 1969 and those celebrated between Mexico and international organizations. The international treaties signed by Mexico on nuclear safety are presented in Annex 7.1 of this National Report. - Bilateral agreements with neighboring States, as applicable and as

necessary The bilateral agreements signed by Mexico on nuclear safety are presented in Annex 7.2 of this National Report.

2007-2009 Period 17-13

Page 163: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTICLE 18. DESIGN AND CONSTRUCTION 18.0 Obligations “Each Contracting Party shall take the appropriate measures to ensure that: i) The design and construction of a nuclear installation provides for several reliable levels and methods of protection (defense in depth) against the release of radioactive materials, with a view to preventing the occurrence of accidents and to mitigating their radiological consequences if they occur; ii) The technologies incorporated in the design and construction of a nuclear installation are proven by experience or qualified by testing or analysis; iii) The design of a nuclear installation allows for reliable, stable and easily manageable operation, with specific consideration of human factors and the man-machine interface.” Article 18 (1) Implementation of defense in depth - Overview of the Contracting Party’s arrangements and regulatory

requirements concerning the design and construction of nuclear installations

The Regulatory Law of the Constitutional Article 27 on Nuclear Matters in Articles 15, 19, 20, 21, 25, 26, 28, 32, 34 and 50, in general terms, establishes the requirements to be satisfied by nuclear installations from the design phase, during construction and the operation phase. Since the first edition of the Nuclear Law that dates from 1979, when the design of Laguna Verde Nuclear Power Station (LVNPS) was found to be quite advanced and the construction already had initiated four years back, the criteria that ruled the general conception of the original design was based on the philosophy that “any nuclear installation built in Mexico shall satisfy the applicable requirements as it should be licensed in the country of origin of the nuclear steam supply system”. Due to this, the first agreement of the referenced standard for licensing was based on Title 10 “Energy” of the Code of Federal Regulations (CFR) of the United States of America (US) or 10CFR. In particular, 10CFR50 and Appendix A, establish fundamental criteria for design, fabrication, construction, testing and performance requirements for Structures, Systems and Components (SSC) important to safety. This ensures in a reasonable manner that the installation may be operated without undue risk to health and safety of operational personnel and that of the public and their property.

2007-2009 Period 18-1

Page 164: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Based on this regulatory framework, basic design criteria satisfied the following six groups: General Requirements, Protection by Means of Multiple Barriers against Fission Products, Protection and Reactivity Control Systems, Fluid Systems, Reactor Containment, and Fuel and Radioactivity Control. On the other hand, the construction process was performed in compliance with industrial standards, codes, industrial and quality standards corresponding to the quality required by the nuclear industry in US. For example, concrete structures were raised under the standards of the American Concrete Institute (ACI), mechanic systems and components under the standards of the ASME Code Section III, Division I and US Nuclear Regulatory Commission (NRC) Regulatory Guides 1.20, 1.46, 1.60, 1.61, 1.92 y 1.122, among others. Electrical and electronic components were constructed, fabricated and qualified taking into account the standards requirements of the Institute of Electrical and Electronic Engineers” (IEEE); the selection of special materials, welds, paint, etc. were performed in accordance with standards of the “American Society of Testing Material” (ASTM). Other aspects such as the Pre-service and In-service Inspections of the coolant pressure boundary components were carried out based on ASME Code, Section XI and the assessment of the Quality Assurance Programmes based on standards from the “American National Standards Institute” (ANSI), Series ANSI N45.2. - Status with regard of the applications for all nuclear installations of the

defense in depth concept, providing for multiple levels of protection of the fuel, the primary pressure boundary and the containment, with account taking of internal and external events

The barrier integrity maintenance to prevent the leak of radioactive material was adopted from the siting selection, conceptual and specific design stage including the construction stage of LVNPS. The focus covered three levels: Level One

LVNPS has been demanding a high degree of reliability to prevent the occurrence of abnormal situations by incorporating in the design the redundancy and diversity necessary to guarantee that critical functions (reactivity control, core cooling and control of radioactive material) are permanently guaranteed, relying for this purpose on methodologies such as quality assurance and the capability of important systems to be tested and inspected.

2007-2009 Period 18-2

Page 165: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Level Two LVNPS postulated that despite the care adopted in Level One, occasional abnormal situations could arise; therefore, all necessary devices should be incorporated in the design to avoid such situations from becoming an accident. Level One and Two were evaluated in Chapter XV of the Final Safety Analysis Report (FSAR) and in the Probabilistic Safety Analysis (PSA) Level 1 & 2 (Individual Plant Examination). Level Three The presence of a very low probability event exceeding design basis is assumed, resulting in core damage and release of radioactive material to the environment. Developing and implementing the External Radiological Emergency Plan (EREP) based on the analysis performed is a practicable application of this level. - Extent of use of design principles, such as passive safety or the fail safe

function, automation, physical and functional separation, redundancy and diversity, for different types and generations of nuclear installations

The list presented below provides a better understanding to what extent the design principles are used at LVNPS.

1.- The essential safety actions are carried out by equipment with sufficient redundancy and independence, in such a way that no single failure, of active or passive components, prevents the function required, even in some cases in the long term.

2.- The passive components of safety systems and engineering safeguards are operated from the control room.

3.- The design of nuclear safety systems and engineering safeguards assure their functionality.

4.- The design of nuclear safety systems and engineering safeguards includes factors that take into consideration natural phenomena such as: earthquakes, floods and storms that might occur at LVNPS site.

5.- The electrical power supplies on reserve have sufficient capacity to energize all the nuclear safety systems and engineering safeguards.

6.- The design incorporates electrical power supplies on reserve to enable a quick shutdown and reactor decay heat removal, when the normal auxiliary power is not available.

7.- LVNPS has redundant capacity and operational independence for shutting down the reactor, independently of the normal reactivity control. This support system

2007-2009 Period 18-3

Page 166: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

has the capacity to shut down the reactor from any normal condition and to keep it in that condition.

8.- The systems that have a redundant or backup safety function are physically separated and arranged so that any credible event that could cause damage to a region of the nuclear isle does not compromise the functional capacity of the counterpart system.

9.- None of the equipment or systems required for a safe shutdown of the reactor is shared between Units 1 & 2.

- Implementation of design measures (plant modifications, backfitting) to

prevent beyond design basis accidents or to mitigate the radiological consequences, if they were to occur

LVNPS has implemented design measures to prevent the occurrence of Design Basis Accidents (DBA) or mitigate their radiological consequences. The Three Mile Island accident was assessed and the design and operational lessons learned were considered, in compliance with the NUREG 0737 requirements. The actions taken are described in Appendix A of the FSAR. - Improvements Implemented for design for nuclear power plants as a result

of deterministic and probabilistic safety assessments made since the previous National Report, and an overview of the main improvements implemented since the commissioning of the nuclear installations

Some modifications were implemented during the 13th refueling outage of Unit 1 (August 31 to December 9, 2008) and the 10th refueling outage of Unit 2 (April 5 to May 31, 2009), in preparation for the Extended Power Uprate (EPU) project up to 120% of the Nominal Thermal Power (NTP). This is internally known as the 1st phase of the EPU project. The 1st phase of the EPU project included the restoring and modernization of the Balance of Plant (BOP) systems of both LVNPS Units 1 & 2. These modifications were considered necessary to ensure a correct and efficient operation for the thermal power Uprate of both units up to 120% of the original NTP, once the licensing process is complete. A summary of the LVNPS major improvements during 2008 and 2009 is presented below. Replacement of the Moisture Separator Reheaters with new equipment designed for the EPU conditions After the power Uprate from 100 to 105%, the chevron Moisture Separator Reheaters (MSR) were assessed, concluding they were not sufficient for drying and reheating the exit steam of the high pressure turbine for thermal powers above 105%.

2007-2009 Period 18-4

Page 167: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Subsequently, the MSRs were operationally assessed for the power Uprate conditions of up to 120%, concluding that it was necessary to replace, at least, the moisture separator and the piping of the two-stage reheating. However, considering the damage that they already had due to the erosion-corrosion effect experimented during the first years of operation, all the MSRs were replaced with others of new design. Installation of the new instrumentation of the MSR In preparation for the Extended Power Uprate up to 120%, it was required to change, among other equipment, the MSRs A/B with new advanced design reheaters with greater resistance to erosion–corrosion. At the same time, the following equipment was installed to replace existing equipment or as an additional. a) 10 level transmitters with advanced analog technology. b) Additional monitoring instrumentation for temperature and flow. c) Impulse lines and digital flow transmitters in the MSRs A/B area for normal system operation. d) 2 instrument racks were installed in an area that meets the ALARA criterion, which will have local panel displays of the temperatures measured in the body of each MSR and, flow indicators for measuring the flow of the high and low pressure side, and the drains of each MSR. Replacement of the low and high pressure feedwater heaters In preparation for the new EPU conditions, the existing low and high pressure feedwater heaters were replaced by heaters of greater capacity, which also have various thermal and mechanical improvements to enhance their performance. Replacement of the main condenser piping The main condenser must be operable throughout the operation of the unit; because the main turbine and, consequently, the cycle efficiency depend upon it. Main condenser failures, causing load reductions and/or unit shutdowns, represent a significant loss on the unit power generation. Therefore, every one of the main condenser components must ensure a reliable and efficient operation. Due to the LVNPS planned power Uprate up to 120% and the system operability, the main condenser was redesigned to: 1) Improve the thermal cycle performance for the new power Uprate conditions. 2) Accommodate the air removal system due to the non-condensable flow

increase, for the new power Uprate conditions.

2007-2009 Period 18-5

Page 168: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

3) Eliminate the copper carryover to the Feedwater System and the reactor vessel by replacing the Cu-Ni piping with Titanium piping.

4) Provide 40 years of service while minimizing the potential for flow-induced vibration, maintenance and inspection intervals, and also exclude operational problems.

Installation of an on-line cleaning system for the main condenser A cleaning system for the condenser piping was installed in each one of 108” lines of the water circulation system, including backwash filters to have an efficient operation of the main condenser for the new 120% power Uprate conditions. Within the scope of the EPU project, the modifications to the main condenser to ensure its integrity and correct operability included: changing to Titanium the material of the condenser piping and; installing an on-line continuous automatic cleaning system for the condenser piping, with spherical elements and including impurity filters for an improved availability of the main condenser. Replacement of the primary containment H2/O2 analyzers Previously, the Hydrogen concentration monitoring in the LVNPS Unit 1 reactor primary containment was made using the Hydrogen analyzer of the Post-Accident Sampling System (PASS). This equipment was not redundant, so in case of failure there was no other way to monitor this parameter. The Oxygen concentration monitoring was made with the Oxygen analyzer of T6l System, which was redundant. Since the hydrogen and oxygen concentrations are important parameters for safe operation; it is necessary to have redundancy, which was not the case with the previous Hydrogen Analyzer of the LVNPS Unit 1. According to the LVNPS Unit 1 operational experience and maintenance records, the required time to calibrate the Oxygen analyzers had been excessive. Moreover, in some cases, it had been necessary to ask the equipment supplier to check and calibrate the system. Additionally, there was an increasing difficulty to obtain spare parts due to its obsolescence. In contrast, the LVNPS Unit 2 calibration time is only four hours and without major complications. - Regulatory review and control activities The review of the generic letters issued by the USNRC is included as part of the regular follow-up of the changes to the regulations of the nuclear steam supply system supplier’s country of origin. In this reporting period, the generic letter GL 2003-01, "Control Room Habitability," is of particular interest. The Licence holder carried out the actions requested in this letter to confirm that its installation's main control room meets the habitability requirements. This included a testing programme

2007-2009 Period 18-6

Page 169: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

which ended in 2008, in order to determine the existing infiltrations toward the main control room as established in the generic letter. Article 18 (2) Incorporation of proven technologies - Contracting Party’s arrangements and regulatory requirements for the use

of technologies proven or qualified testing or analysis As a policy, major changes and equipment upgrades taking place in LVNPS, follows the criterion of non-use technologies that are not tested or have not been used primarily in other nuclear power plants. - Measures taken by the licence holder to implement proven technologies All the modifications that use new proven technologies are evaluated according to the 10CFR50.59 and informed to the Commission. - Analysis, testing and experimental methods to qualify new technologies,

such as digital instrumentation and control equipment All the digital instrumentation that uses software and control panels of equipment are tested and validated before their installation. The qualification activities are governed by a Quality Assurance Plan based on the requirements of 10CFR50, Appendix B. The software’s QAP is monitored by the Commission and LVNPS controls the QAP by its own procedures. - Regulatory review and control activities The Commission verifies that the new technologies are tested in accordance with the provisions of 10CFR52.47 (b) either through the analysis of information provided by the supplier, a suitable testing programme, operational experience, or a combination of all of the above. Article 18 (3) Design for reliable, stable and manageable operation - Overview of the Contracting Party’s arrangements and regulatory

requirements for reliable, stable and easily manageable operation, with specific consideration of human factors and human-machine interface (see also Article 12)

2007-2009 Period 18-7

Page 170: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

LVNPS considers the human factors and human-machine interface in the design of nuclear installations. Specifically, the FSAR presents a review of the human factors engineering and the design of the Main Control Room (MCR) and control centers that are located outside the MCR. Article 12 of this National Report also discusses the human factors issue in more detail. LVNPS conducts activities related to human factors engineering and human-machine interface according to Chapter 18 of NUREG-0800 "Standard Review Plan" Rev.1, and NUREG-0700 "Human-System Interface Design Review Guideline" Rev. 2 issued in May 2002. In addition, LVNPS also uses NUREG-0711 “Human Factors Engineering Programme Review Model,” Rev. 2 to evaluate the design of the control rooms. - Implementation measures taken by the licence holder The measures taken by the Licence holder to consider human factors resulting from the Three Mile Island accident are described in Article 12 of this National Report. - Regulatory review and control activities Recently, LVNPS has begun to replace analog instrumentation with digital instrumentation. The digital technology is able to improve the operational performance and the adoption of these technologies in the nuclear industry represents a challenge for regulatory bodies. In particular, these challenges include (1) digital technology is more complex than analog technology; (2) digital technology is rapidly changing and requires the Commission’s staff updating their knowledge about the design, testing and applications; (3) new failure modes associated with digital instrumentation; and (4) the need to update the acceptance criteria and review the procedures used to evaluate the digital systems safety in response to the technological changes to cope with the state of the art. As part of the control activities for safe, stable and easily manageable operation with special consideration on human factors and human-machine interface; the Commission has been following-up these issues through its base-line inspections programme in the Operation, Training, Maintenance, Instrumentation & Control, and Engineering areas, as well as during the LVNPS Operators and Reactor Supervisor licensing process. The Commission raised in 2009 the need to start a project for directing the control and assessment activities regarding both safety culture, and human and organizational factors. The project is currently in the initial phase, defining the procedures to be followed by the Commission to carry out the inspections of its base-line programme to verify the

2007-2009 Period 18-8

Page 171: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

safety assessment and improvement programmes regarding Organization and Human Factors, as part of the Reactor Oversight Process (ROP).

2007-2009 Period 18-9

Page 172: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

ARTICLE 19. OPERATION 19.0 Obligations “Each Contracting Party shall take the appropriate measures to ensure that: i) the initial authorization to operate a nuclear facility is based upon an appropriate safety analysis and a commissioning programme demonstrating that the facility, as constructed, is consistent with design and safety requirements; ii) operational limits and conditions derived from the safety analysis, tests and operational experience are defined and revised as necessary for identifying safe boundaries for operation; iii) operation, maintenance, inspection and testing of a nuclear facility are conducted in accordance with approved procedures; iv) procedures are established for responding to anticipated operational occurrences and to accidents; v) necessary engineering and technical support in all safety-related fields is available throughout the lifetime of a nuclear facility; vi) incidents significant to safety are reported in a timely manner by the Licensee to the Regulatory Body; vii) programmes to collect and analyze operating experience are established, the results obtained and the conclusions drawn are acted upon and that existing mechanisms are used to share important experience with international bodies and with other operating organizations and regulatory bodies; viii) the generation of radioactive waste resulting from the operation of a nuclear facility is kept to the minimum practicable for the process concerned, both in activity and in volume, and any necessary treatment and storage of spent fuel and waste directly related to the operation and on the same site as that of the nuclear facility take into consideration conditioning and disposal.” Article 19 (1) Initial authorization - Overview of the Contracting Party’s arrangements and regulatory

requirements for the commissioning of a nuclear installation, as constructed, is consistent with design requirements and safety requirements

2007-2009 Period 19-1

Page 173: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

As mentioned in Article 7 of this National Report, the National Commission of Nuclear Safety and Safeguards (the Commission) is a decentralized organism under the Ministry of Energy responsible for verifying the compliance of the national and international regulation for the siting, design, construction, commissioning and operation of nuclear installations. The Commission, to fulfill its functions, has established a two-stage "Licensing Process": the first one starts with the formal delivery of the Construction Permit Application accompanied by an installation characteristics description and essentially of the safety systems that the installation will have to ensure that it will not present an undue risk to public health and safety. Among the documents sent by the Federal Electricity Commission (CFE) to the Commission to support the Laguna Verde Nuclear Power Station (LVNPS) application are the following:

a) Preliminary Safety Analysis Report (PSAR) b) Preliminary Environmental Impact Assessment (PEIA) Report.

During this stage, the Commission reviewed the design criteria (Structures, Systems and Components -SSC- characteristics, nuclear analysis, etc.) and particularly all the issues related to the impact of the site characteristics on the SSC design of the installation, and the impact of the installation on the environment. After reviewing these reports, a technical report was sent to the Ministry of Energy to support and issue the Construction Permit. During the LVNPS construction, the Commission, through audits and inspections, supervised this phase to assure that the installation was built in accordance with the safety analysis report and the conditions set by the Construction Permit. Once the detailed design of the installation was finalized, the commercial operation license was requested, as part of the Commission’s Licensing Process second stage. The following information supported the application:

a) The Final Safety Analysis Report (FSAR). b) Final Environmental Impact Report (FEIR)

The Commission assessed these reports, including the acceptance criteria for pre-operational testing, start-up testing and the proposed Operating Technical Specifications (OTS). These assessments and the results from the Commission’s inspections and audits allowed preparing a technical report for the Ministry of Energy to issue the LVNPS Operating Licensee. - Conduct of appropriate safety analyses In the initial licensing, the preliminary and the final safety analysis reports were

2007-2009 Period 19-2

Page 174: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

defined within the regulatory framework and in accordance with the format set in United States of America (US) Nuclear Regulatory Commission (NRC) Regulatory Guide 1.70. For granting the LVNPS original operating license, the Commission reviewed the FSAR, taking advantage of the experience gained in reviewing the PSAR, supported by experts from the International Atomic Energy Agency (IAEA) in some particular topics, through the Technical Cooperation Programmes. Later, in the LVNPS commercial operation phase, the Commission reviewed and assessed the safety analysis report for the power Uprate up to 5% which covered almost every topic of the FSAR. The Commission’s assessments were documented in a Safety Assessment Report. The Commission witnessed each of the five output levels, from 1% to 105%, so it was found stable behavior of the plant. The safety analysis, for total steam and the new thermal power conditions, was performed as part of the primary containment systems safety analysis in the event of a loss of coolant accident, both inside and outside the containment. • Start up programme As part of the compliance obligation with USNRC Regulatory Guide 1.68, a start-up programme was implemented in LVNPS. This programme began with the initial fuel loading for which the Operating Technical Specifications were applied. The start-up programme was divided into four main phases: Phase I. Tests with reactor vessel open (initial fuel loading) Phase II. Initial heating Phase III. Power tests Phase IV. Warranty tests Testing conditions Within the previous mentioned testing phases, the start-up programme was divided into 8 test conditions, in which specific Structure, System and Component tests were performed.

2007-2009 Period 19-3

Page 175: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

TEST

CONDITION CONDITIONS / REGION OF FLOW-POWER MAP

VA From fuel loading up to the time of installation of the drywell cover. CA After installing the drywell cover and up until the reactor was settled

at pressure and temperature rated conditions. C1 Before and after synchronization of main generator of 5% to 20% of

the Rated Thermal Power (RTP), with reactor recirculation pumps at low speed and the control valve between the maximum and minimum position.

C2 After main generator synchronization, with a control rod pattern of 50% to 75% at or below the recirculation flow master control lower analytical limit, up to a 50% RTP.

C3 From 50% to 75% of the control rod pattern, above 80% of the core flow and within the maximum allowable valve control opening up to a 75% RTP.

C4 At the natural circulating line and its intersection with the lines between 95% and 100% of rod patterns up to a 75% RTP.

C5 From the lines of 95% to 100% of the control rod patterns and between those of a minimum flow at the recirculation pumps (control valve in minimum position) rated speed and 5% above the inferior analytical limit of the recirculation flow automatic control up to a 75% RTP.

C6 Within 95% to 100% of RTP and between 95% and the maximum allowable flow through the core.

General acceptance criteria Three general acceptance criteria were established to validate the start-up testing:

a) Level 1 Acceptance criteria

Failure to meet the criteria of this level obliges the unit to be lead to a standby condition considered satisfactory and safe based on test results previously performed.

b) Level 2 Acceptance criteria

Failure to meet the criteria of this level does not require altering the test programme or operation of the unit. It is recommendable to investigate adjustments required as well as analytical and surveillance methods.

2007-2009 Period 19-4

Page 176: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

c) Level 3 Acceptance criteria

Failure to meet the criteria of this level does not require altering the test programme or unit operation. Limits established under this category are related to individual component expectations or transient behavior of control loops. This level is not associated with vessel or fuel protection systems.

Start-up testing performed The number of start-up tests performed for each one of the tests conditions to verify Balance of Plant systems (VS) and System Test (ST) for the systems of the Nuclear Steam Supply System (NSSS) is shown below.

TEST CONDITION

(ST) TEST PERFORMED

(VS) TEST PERFORMED

Open vessel (VA) 15 3

Heating (CA) 28 11

Condition 1 (C1) 15 18

Condition 2 (C2) 21 36

Condition 3 (C3) 35 22

Condition 4 (C4) 6 -

Condition 5 (C5) 7 -

Condition 6 (C6) 47 40

Warranty 2 -

T O T A L: 176 130 Testing for the 5% power Uprate Due to the fact that under the power Uprate condition neither the pressure at the Reactor Pressure Vessel (RPV) nor the reactor recirculation flow were affected, many of the start-up tests were validated by analysis of the test results during the initial start-up testing for both units. However the change in the main steam flow required the following tests to prove the stable operation under this new condition:

a) Stable behavior for normal operation. b) Stable operation of the Reactor Core Isolation Cooling (RCIC) System c) Thermal limits evaluation and calibration of feedwater flow transmitters for each

power step from 100% up to 105%. d) Pressure Regulator EHC (including regulator failure to verify the transference to

the backup regulator)

2007-2009 Period 19-5

Page 177: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

e) Feedwater control and feedwater system, stable RPV level control and operation.

f) Chemistry. g) Isotopic analysis. h) Environmental radiological monitoring at the release and discharge points, inside

the restricted area. - Programmes of verification that installations, as constructed, are consistent

with the design and in compliance with safety requirements Introduction Nuclear safety classifications are established by the design of the installation such that the applicable standards and codes, and quality requirements are satisfied throughout the construction, testing and, start up phases. Similarly, after initial startup, applicable regulatory and quality requirements are established based on SSC importance to safety such that no undue risk to public health and safety occurs over the life of the installation. Construction stage At this stage, the main means for achieving the safety levels required was strict compliance with LVNPS’ Construction Quality Assurance Plan (CQAP). Compliance with CQAP requirements was applied both to the behavior of individuals and organizations. The application of the CQAP is a means for guaranteeing, in a highly reliable manner, that SSC important to safety shall be built, installed, inspected and tested in conformance with applicable design specifications, codes and regulations. Operation stage The following means have been implemented for the operation stage to maintain the installation at the highest safety levels required by the Commission. Operating Technical Specifications The document that regulates the operation of nuclear installations within the limits deriving from the safety analysis is denominated Operating Technical Specifications. They are ruled by the 10CFR50.36. LVNPS was designed under criteria directed to avoid radioactive material releases to the environment. In order to demonstrate the adequacy of its implementation, accidents hypothetically postulated were analyzed and results were presented as part

2007-2009 Period 19-6

Page 178: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

of the information in the Final Safety Analysis Report. This served to establish safety parameters or limits and conditions that restrict the operation of the installation beyond the same. The OTS were developed based on USNRC NUREG-0123, parameters identified in the FSAR and recommendations in standard ANSI/ANS 5.8.4 in which it is specified that:

a) Each nuclear plant license application must include in the request “Technical Specifications” proposed, their bases and the administrative controls.

b) Each license shall include Technical Specifications deriving from safety analysis and their evaluation by the Commission.

The OTS are incorporated in the Operating License and they contain guidelines and conditions under which the plant must operate. Compliance with the OTS ensures that the operation is maintained within the limits determined by the safety analysis. Any deviation requires corrective actions to be taken and immediate notification to the Commission. A modification to the OTS requires previous authorization from the Commission, since they are part of the Operating License. The OTS are integrated by the following sections: (1) Definitions; (2) Operating limiting conditions; (3) Surveillance requirements; (4) Core characteristics; and (5) Administrative controls. Maintaining the safety reports In order to assure that LVNPS Units 1 & 2 shall operate during their lifetime in conformance with the bases that served for awarding the Operating License, any change or modification to the installation, the procedures or the execution of tests or experiments ought to be submitted for a Safety Evaluation. The purpose for such evaluation is: a) To review that all change proposed be covered by license bases; that is, by

analyses, models, methods and assumptions made in Safety Reports. This way, it is ensured that these bases are not modified and therefore do not require previous approval of the Commission.

b) For those cases in which it is identified that the change proposed is not covered by the license bases, to ensure that approval of the Commission is required prior to the implementation of the change.

c) To identify whether the change proposed modifies or affects an Operating Technical Specifications, in which case previous authorization shall be requested to the Commission, which eventually would authorize the modification to the OTS.

d) To request a periodic summary report briefing each and every change performed, that due to their nature were not submitted for approval of the Commission prior

2007-2009 Period 19-7

Page 179: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

to their implementation, so that the Commission is informed of the nature of all changes.

This process allows maintaining the Safety Reports effective, implying that the operation of LVNPS Units 1 & 2 is always covered by the license bases as well as by the OTS approved. Periodic safety review The Periodic Safety Review (PSR) provides a global view of plant safety, with the objective of determining the modifications that should be carried out in order to maintain a high level of safety. The objectives of the PSR are the following:

a) Analyze the installation behavior for different aspects of nuclear safety in a time period long enough to identify trends.

b) Verify the adequacy of the methodology used in conducting the analysis of various aspects of the nuclear safety of the installation documented in the periodic reports.

- Regulatory review and control activities Revision to Section 14 “Testing Programmes” of the FSAR was performed to determine the capability of the initial test programme for LVNPS Units 1 & 2 as well as the evaluation of the execution of such tests and verification of the acceptance of the final results from a safety point of view. All this, as a prerequisite for the initial authorization of operation of both LVNPS units. In order to establish a very strict control over the performance of tests and over the power Uprate programme and so to have no doubt about the reliability of the steps and the decisions made on the route to 100% of power, the Commission established a requirement through which different power stages would be subject to an evaluation of LVNPS behavior as regards to the testing performed at the preceding stage. From here, it was established that LVNPS had to achieve authorization from the Commission to carry on. This process, during the testing to be performed, ensured that LVNPS would maintain itself within the standards established by the acceptance criteria. If for some reason, these tests did not satisfy the acceptance criteria, the corresponding analyses were demanded immediately. During the start-up phase, the Commission carried out 39 inspections to Unit 1 and 17 inspections to Unit 2. These inspections were intended to verify groups and activities related to the start-up testing, such as Instrumentation & Control, Reactor Engineering, Maintenance, Start-up Superintendence, Quality Assurance and Quality Control. Based on the above, the original Operating Licenses were awarded on August 24, 1990 for LVNPS Unit 1 and April 10, 1995 for LVNPS Unit 2.

2007-2009 Period 19-8

Page 180: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

For the 5% Power Uprate condition, the Commission evaluated and authorized the testing programme for both units of LVNPS. The safety related tests were witnessed by the Commission’s staff in order to verify that the expected values for safety and operational parameters were obtained as described in the Safety Analysis. As a consequence of the evaluation and analysis of the results, the Commission determined LVNPS had a stable behavior and that it could operate in the 5% Power Uprate condition. Finally the Ministry of Energy granted the new Operating Licenses in December 8, 1999 for both units of LVNPS with the same expiration date as the original ones, that is, July 24, 2020 (Unit 1) and April 10, 2025 (Unit 2). Article 19 (2) Operational limits and conditions - Overview of the Contracting Party‘s arrangements and regulatory

requirements for the definition of safe boundaries of operation and the setting of operational limits and conditions

The LVNPS Units 1 & 2 operating license contains the Operating Technical Specifications which are the set of limits and conditions derived from the safety analysis, testing and operational experience. The 10CFR50.36 defines the requirements for the OTS of a plant. The Operating Technical Specifications should describe, at least, the specific characteristics of the installation and the operating condition required to protect the public health and safety. The applicant must identify the items that apply directly to maintain the integrity of physical barriers that are designed to contain radioactive material. Specifically, 10CFR50.36 requires that the OTS should be derived from the analysis and assessments that are in the Final Safety Analysis Report. The Licensee cannot, for any reason, change the OTS without prior permission of the Commission. - Implementation of operational limits and conditions, their documentation,

training in them, and their availability to plant personnel engaged in safety related works

The control of the limits and operation conditions is defined in the Operating Technical Specifications, which determine the documentation required for the proper control of the situations that reduce the safety margin, either to planned or unexpected situations. The staff in charge of this control is generally the Licensed Reactor Supervisors, who have been extensively trained on the installation operation, with emphasis on the control of the OTS. The staff in charge of monitoring safety-related equipment is trained following the Systematic Approach to Training (SAT) methodology. This training is provided to the personnel of the operation maintenance (mechanical, electrical or instrumentation & control), chemistry, and radiation protection areas, and in general, to all personnel that perform activities on that equipment.

2007-2009 Period 19-9

Page 181: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

The controlled copy of the OTS is under the custody of the LVNPS staff designated by the Commission; in particular, at least two copies are located in the main control room of each unit. Additionally, an updated version of the OTS is available in the LVNPS intranet, which can be accessed from any computer station located within the installation premises. There are also updated copies at CFE’s offices located in Dos Bocas (in State of Veracruz) and the Commission’s main office located in Mexico City. - Review and revision of operational limits and conditions as necessary The assessment and changes to the Operating Technical Specifications are usually performed when the equipment or the installation operating conditions are changed. For the specific reporting period of this National Report, the changes have been due to equipment updating and the Extended Power Uprate (EPU) Project. Both the review and changes must be supported with a safety analysis, which should include the potential impact they may have on the integrity of the fission products barriers, and presented to the Commission as a change request for its approval. - Regulatory review and control activities Assessment activities Any request for change to the OTS enters the assessment process of the Commission. This process is composed of a preliminary review of the documentation to verify that is complete; a review of the generic aspects; and finally a detailed assessment of the specific aspects applicable to the Licensee. Throughout the process, the compliance with the licensing bases of the plant is verified. The end result of the assessment process is an assessment report and the corresponding opinion. Control activities Any non-compliance to the OTS is notified immediately by the Licensee to the Commission according to requirements in section 19.6. In addition, the resident inspector verifies the operation log daily to assure the non-compliances were reported in accordance with the provisions of the existing regulation. Article 19 (3) Procedures for operation, maintenance, inspection and testing - Overview of the Contracting Party’s arrangements and regulatory

requirements on procedures for operation, maintenance, inspection and

2007-2009 Period 19-10

Page 182: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

testing of a nuclear installation As described in Article 13 of this National Report, all activities important to safety relating to the LVNPS Units 1 & 2 operation are performed with strict adherence to the Operation Quality Assurance Plan (OQAP). This obliges the use of approved procedures by qualified personnel. - Establishment of operational procedures, their implementation, periodic

review, modification, approval and documentation Establishment of operating procedures For control of all activities ruled by the OQAP, LVNPS has divided its procedures into the following groups.

a) Administrative procedures. b) Operating procedures subdivided into several categories such as General

Operation, System Operations, Abnormal Operation, Alarm Response, Emergency Operation, and Operational Verification.

c) Maintenance procedures classified into Preventive, Corrective, Refueling, Special Processes and Generic Maintenance.

d) Reactor engineering: Reactor Verification, Reactor Analysis and Fuel Handling. e) Radiological Protection: Radiological Protection (Generic) and Reduction in

Personnel Exposure (ALARA). f) Internal emergency plans (plan and procedures). g) Instrumentation: Instrumentation Maintenance and Instrumentation Verification. h) Chemistry and radiochemistry. i) Material control. j) Physical security. k) Training. l) Quality control: Quality Control Generic Activities, Non-destructive Examination

and Functional Testing. m) Control of documents. n) Fire protection. o) Programming and results planning.

Application LVNPS has a policy for applying the procedures, which establishes that all the installation personnel must use and adhere to the procedures relating to their work activity.

2007-2009 Period 19-11

Page 183: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Periodic assessment LVNPS procedure PAG-02 establishes the requirements for the preparation, issuance, review, approval, cancellation, and reactivation of the LVNPS operation procedures. The periodic assessments may be annual, every two years, every five years, or depending on the needs (for example, operational changes). The procedure modifications can be due to operational changes or from the periodic review results. The operational changes are those changes to the procedures that do not change their purpose but are necessary to continue their application on the field; otherwise the plant safety or reliability would be affected. The scope of operational changes includes the modifications generated by the Corrective Action Programme (CAP) or modification packages. - Availability of the procedures to the relevant nuclear installation staff There are booths for the control and availability of procedures of all areas, such as maintenance, operation, etc. The location of the procedures that all staff can use is clearly indicated in these booths. Additionally, an updated version of all the procedures is available in the LVNPS intranet, which can be accessed from any computer located within the installation premises. There are also updated copies at CFE’s offices located in Dos Bocas (in State of Veracruz) and the Commission’s main office located in Mexico City. - Involvement of relevant nuclear installation staff in the development of

procedures LVNPS has a policy for developing the procedures, which establishes that all the qualified personnel must be involved in the preparation and revision of the procedures. - Incorporation of operational procedures into the management system of the

nuclear installation The management system of procedures is indicated in the LVNPS Procedure PAG-02 procedures for the management of the technical-operational and PAG-32 procedure for the management of administrative procedures. - Regulatory review and control activities

2007-2009 Period 19-12

Page 184: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

During preparation and conduction of the inspections contained in the Commission’s base-line inspection programme, the inspection staff follows the guidelines established in Procedure IP-42453 "Operating Procedures Inspection" of the USNRC. The regulatory control and assessment activities include the following:

a) Verify that the plant procedures are reviewed and approved in accordance with the Operating Technical Specifications and Operating License conditions.

b) Verify that the technical adaptation of the procedures is consistent with the desired actions and operation modes.

c) Verify that interim changes to procedures are performed in accordance with the requirements of the Operating Technical Specifications and administrative procedures.

Article 19 (4) Procedures for responding to operational occurrences and

accidents - Overview of the Contracting Party’s arrangements and regulatory

requirements on procedures for responding to anticipated operational occurrences and accidents

As a result of the accident at Three Mile Island Nuclear Power Plant in the US, the CNSNS requested CFE to review existing procedures for addressing transients and accidents. This motivated the application of the Emergency Procedure Guidelines (EPG) to LVNPS Units 1 & 2, which were developed in a generic manner for Boiling Water Reactors (BWR) by the BWR Owner’s Group (BWROG) of which CFE forms part. The incorporation of such Emergency Operating Procedures (EOP) does not require amending the design basis of the unit and they are not based on design considerations, but rather guidelines to respond to conditions beyond the license basis. CFE developed EOP for LVNPS using guidelines in NEDO 31331 “BWR Owner’s Group Emergency Procedures Guidelines” to comply with the intention of Item I.C.1 of NUREG-0737 “Guidelines for the assessment and development of transient and accident procedures”; therefore, the EPG are based on the following:

a) The entry conditions and operator actions are linked to certain parameters and symptoms of the plant. The actions are appropriately specified to restore and maintain these key plant parameters within the limits that define a safe plant condition.

b) It is not required to identify an initiating event to determine which procedure

2007-2009 Period 19-13

Page 185: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

developed with the EPG should be used. Similarly, the operator actions prescribed are appropriate regardless of the initiating event or the sequence in which subsequent events may occur.

c) The operator actions prescribed are consistent with the manner in which control room operators actually operate, including the performance of concurrent or parallel actions.

d) The operator actions prescribed are based on the existing configuration of the SSC of the plant, with the exception of instrument ranges, regardless of changes that may be proposed or adopted in the future.

e) All possible plant conditions that can have general operation guidelines are covered, regardless of their occurrence probability. This is why the Emergency Procedure Guidelines cover a wide range of conditions that include both the most and least severe conditions in comparison to those which were considered to develop the design basis of the plant. These conditions include multiple equipment failures and human errors.

f) Although there are guidelines to respond to plant conditions that may extend beyond the original design basis of the plant, there is no intention or purpose to extend any design basis above what is currently established.

g) The plant systems that can be used to respond effectively to plant emergency conditions are identified, regardless of their safety class or the qualification of the system equipment and components.

h) The operator actions, the limits and action levels are based on engineering calculations using best estimate methods, contrasting with the traditional analytical methods and assumptions of licensing and design basis.

i) The best possible operation guidelines are specified, regardless of the licensing assumptions or requirements, and the design basis. For example, the operator actions are not necessarily conditioned on a waiting time (say, 10 minutes) assumed as input to a licensing analysis.

- Establishing event based and / or symptom based emergency operating

procedure Introduction The procedures that are used at LVNPS to respond to anticipated operating incidents and accidents are divided into Abnormal Operating Procedures, which are based on events and the Emergency Operating Procedures which are based on the Emergency Procedure Guidelines indicated in the preceding paragraph. Abnormal Operating Procedures An evaluation was performed on the design of LVNPS Units 1 & 2 to verify its

2007-2009 Period 19-14

Page 186: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

response to unforeseen operation incidents and accidents considered as design basis. These are classified in five categories as follows:

CATEGORY

TYPE OF EVENT

OCCURRENCE EVENT/YEAR

I Normal Operation Normal

II Expected Transients 1 – 1/20

III Infrequent Transients < 1/20 –1/100

IV Design Basis 1/100 – 1/10,000

V Special N/A The response to the transients shown in the previous categories is carried out using the Abnormal Operating Procedures. Emergency Operating Procedures An overview of the Emergency Operating Procedures structure and interrelationships is shown in Figure 19.1 One can see that there are twelve critical parameters controlled by the EOP: three for reactor control, five for primary containment control, three for secondary containment control and one for radioactive release control. Only three of them require transferring its control among different portions of the EOP, these are:

a) Reactor water level. b) Reactor pressure. c) Suppression pool water level.

- Establishing procedures and guidance to prevent severe accidents or

mitigate their consequences At this time, LVNPS has not developed procedures for severe accidents; because there is no regulatory requirement set for their development. - Regulatory review and control activities The Commission used in 1992 the guidelines established in NUREG/CR-2005, Rev.1, "Checklist for Evaluation of Emergency Operating Procedures Used in Nuclear Power Plants” in order to verify the proper implementation of the EOP in the LVNPS simulator.

2007-2009 Period 19-15

Page 187: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

During the 2007-2009 period, the Commission performed inspections to the Operation and Training Departments, and conducted operation examinations in the simulator, both to grant new Operator licenses and to renew the licenses of Operators and Reactor supervisors of LVNPS. During these activities, which are scheduled annually, in relation to the Emergency Operating Procedures, it was verified that:

a) If there were significant changes to the EOP, CFE had met the regulatory commitments and requirements.

b) If there were significant changes to the EOP technical guideline of the BWR owners group, CFE’s procedures were technically suitable for incorporating these changes, and that any deviation from them was completely justified.

c) The entry and exit conditions from the EOP were easy to follow, and that the transition among the normal, abnormal and EOP was properly defined and that could be easy to follow.

d) The use of the notes and warnings of the EOP was consistent and correct. e) The Main Control Room Operators received the training required before the

changes to the EOP were implemented. Article 19 (5) Engineering and technical support - General availability of necessary engineering and technical support in all

safety related fields for all nuclear installations, under construction, in operation or under decommissioning

LVNPS has an engineering group that provided technical support during the construction and commissioning phases of the two units and now it is continuously providing technical support to maintain safe and reliable operation of systems, equipment and components of LVNPS Units 1 & 2. - General availability of necessary technical support on the site and also at

the licence holder or utility headquarters, and procedures for making central resources available for nuclear installations

The continuous technical support includes two on-site groups of engineers for the areas of systems, and programmes and components. There is another off-site group of engineers for the design and maintenance of documentary configuration. - General situation with regard to dependence on consultants and contractors

for technical support to nuclear installations General Electric has been responsible for the design, manufacture and delivery of the

2007-2009 Period 19-16

Page 188: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Nuclear Steam Supply System (NSSS) for both LVNPS units and provided consulting during the construction and commissioning of equipment. As of to date, GE provides technical support for the NSSS. The turbine generator set was designed, manufactured and delivered by Mitsubishi Heavy Industries, which supports its modifications and major maintenance. In addition, the company URS, Washington Division (formerly Ebasco Co.), was the architect-engineer for the design, construction and testing of both LVNPS units. URS continues providing technical support in the assessment and design changes. - Regulatory review and control activities As mentioned in Article 14 of this National Report, the Commission verifies annually the Engineering and Technical Support areas through its base-line inspection programme. During the refueling outages, the Commission also verifies that the service suppliers meet the following: their Quality Assurance Programmes or they are included in LVNPS‘s QAP; comply with the training and qualifications required for the activities that will develop; and the Radiation Protection and Industrial Safety controls established by LVNPS. Article 19 (6) Reporting of incidents significant to safety - Overview of the Contracting Party’s arrangements and regulatory

requirements to report incidents significant to safety to Regulatory Body According to the regulatory framework, LVNPS must report to the Commission the occurrence of all incidents covered by categories defined in 10CFR50.72 and 10CFR50.73 using the format identified as “Notification of Reportable Event” (NRE). Such format includes a summary of the event; immediate corrective actions; core emergency cooling system and engineering safeguards system conditions; as well as information on radiological conditions. This notification is sent to the on-site Resident Inspector as well as to the Commission’s headquarters. According to the incident significance, the notification shall be sent immediately, within one hour or within four hours. In compliance with 10CFR50.73, LVNPS must send a “Licensee Event Report” (LER) within 30 days after the occurrence of the event to completely describe the event, the result of the root cause analysis and corrective and preventive actions proposed. - Overview of the established reporting criteria and reporting procedures for

incident to safety and other such as near misses and accidents The notification and reporting of the LVNPS safety significant events are carried out

2007-2009 Period 19-17

Page 189: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

2007-2009 Period 19-18

according to the reporting and notification criteria set in Procedure PAS-07 "LVNPS Event Notification and Reporting to the Commission", which is based on 10CFR50.72, and 10CFR50.73 and NUREG-1022 "Event Reporting Guidelines: 10CFR50.72 and 50.73." - Statistics of reported incidents significant to safety for the past three years Figure 19.2 shows a plot for the events that have occurred at LVNPS, which has a downward trend for the last few years; due to the implementation of the Corrective Action Programme to analyze these events and prevent their repetition.

Number of Reported Events per year in LVNPS U1 & U2

19

0

84

0

73

0

55

0

66

0

37

0

36

19

4448

2628 2830

0

10

20

30

40

50

60

70

80

90

48

30

59

52

3535

68

49

54

42

35

25

35

22

2830

2327 28

3234

15

2020

U-1 19 84 73 55 66 37 36 44 26 28 59 35 68 54 35 35 28 23 28 34 2048

U-2 0 0 0 0 0 0 19 48 28 30 52 35 49 42 25 22 30 27 32 15 20

1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 8 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009

30

199

Figure 19.2 - Documentation and publication of reported events and incidents by both the

licence holders and Regulatory Body Licence The notification and reporting of LVNPS safety significant events is done through the Licensee Event Reports which are sent to the Commission in accordance with the regulatory provisions.

Page 190: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Also, LVNPS shares its operational experience with the international nuclear community through the World Association of Nuclear Operators (WANO), which publishes the most significant operational events. Regulatory Body The Commission participates in the IAEA/Nuclear Energy Agency (NEA) Incident Reporting System (IRS) meetings to share operational experience of the Mexican nuclear installation with member countries of the international community, and to collect and implement the international experience in Mexico. The Commission also participates in the IAEA International Nuclear Event Scale (INES) meetings. - Policy for use of the INES scale An operational event that causes a special inspection and has an INES Level 2 or higher shall be informed to the IAEA INES system. - Regulatory review and control activities The Commission assesses the LERs presented by LVNPS to verify that they were prepared in compliance with the regulation. When a safety significant event or safety special interest event occurs at LVNPS, the Commission performs an in-depth assessment and investigation of the causes that originated the event and the existence of recurrent events; and, when required, questions or imposes the corrective actions scope and/or the completion due date. For the analysis of the reportable events, the Commission prepares statistics to identify trends on the type of event, root causes, recurrences, etc, in order to determine the need to implement any regulatory action, as a result of the statistical analysis. As mentioned in Article 14 of this National report, in 2009 the Commission started categorizing the operational events according to their safety significance. This exercise has the purpose of determining performance indicators similar to US NRC Reactor Oversight Process (ROP) performance indicators to compare LVNPS performance with similar plants and emulate the best international practices. Additionally, several administrative procedures were developed including the Class I, II and III reactive inspections, depending on the level of response required by the safety significance of the event. These procedures assure a systematic, comprehensive and predictable response from the Commission. Article 19 (7) Operational experience feedback - Overview of the Contracting Party’s arrangements and regulatory

requirements on the licence holders to collect and analyze and share

2007-2009 Period 19-19

Page 191: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

operational experience The Operating License states that LVNPS shall continue with the feedback from the national and international operational experience and implement changes to relevant legislation that the Commission considered applicable and within the deadlines established, according to the changes, to increase safety and, public and environment protection. - Overview of programmes of licence holders for the feedback of information

on operating experience from their own nuclear installation, from other domestic installations and from installations abroad

Introduction The programmes on both the internal and external operational experience feedback are carried out according to the guidelines set in Procedures PAS-18 “Programme for reviewing external operational experience of the Nuclear Power Plant’s Division” and PAS-26 “Activities of the Operational Experience Programme". External operational experience Procedure PAS-26 provides the methodology, guidelines, and scope of the external operational experience review process; also describes each stage of the process and the people responsible; and the interfaces between different organizations involved in the review process. The review process begins with an information search of events that have occurred in the nuclear industry and non-nuclear industry. This search is carried out mainly on the websites of the Institute of Nuclear Power Operations (INPO), the World Association of Nuclear Operators and the US Nuclear Regulatory Commission. The procedure differentiates two types of documents: those that are just for information (e.g., guides, best practices, etc.); and those that document events that require an evaluation to determine if similar events could happen at LVNPS. The first type of documents are translated into Spanish and disseminated to LVNPS staff through the intranet, newsletters, e-mail and posters, as well as in supervisor and working group meetings. For the documents that require an evaluation, a preliminary screening is carried out to identify events potentially applicable to LVNPS. These events are assigned to specialists for a detailed review and accurately determine if similar events could happen at LVNPS. If that is the case, actions to prevent their occurrence are implemented. The reports of the most significant events are reassessed every 2 years to determine whether the actions initially implemented continue to be valid or additional actions are necessary. Internal operational experience

2007-2009 Period 19-20

Page 192: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Regarding the internal operational experience, the events at LVNPS are documented in the Corrective Action Programme and reviewed by specialists, and the corresponding corrective actions are defined and implemented. - Procedures to analyze domestic and international events The analysis of domestic events is performed according to the Procedure PAG-46 "Analysis of Events." This procedure provides guidelines and instructions to determine the root cause, the apparent cause or the direct cause of the events, depending on the significance level assigned to them by applying Procedure PAG-71 "Corrective Action Programme". The root cause is determined for events classified as levels 1 and 2 (regulatory); the apparent cause is determined for level 2 events; and the direct cause is determined for level 3 events. The methodologies used for the research and analyses of the events are: Job Task Analysis, Cause-Effect Analysis; Event Trees and Causal Factors Analysis; Fault Tree Analysis, Change Analysis, Barrier Analysis, and Human Performance Assessment. The methodology used, one or more than one, depends on the complexity and nature of the event. The events in foreign power stations are evaluated following the guidelines and instructions of Procedure PAS-18 "Review Programme of External Operational Experience of the Nuclear Power Plant’s Division". Because the events were already analyzed and the actions to prevent their recurrence were defined by the personnel of the plants in which they occurred using their procedures, or if they were significant generic events that occurred at several plants and the analysis was already performed by INPO/WANO; the LVNPS evaluation is performed from the prevention perspective to determine if similar events could happen at LVNPS, if there are preventing barriers or, if the barriers are missing, to implement them. - Procedures to draw conclusions and to implement any necessary to the

installation and to personnel training programmes and simulators The external operational experience is analyzed to determine the extent to which this experience could happen at the installation and, consequently, issue the preventive actions to prevent it from happening. This analysis is carried out by the areas that would be involved if a similar event occurred at LVNPS. The group determines the appropriate actions, according to the administrative procedure PAG-74 regarding the modifications to the installation. The preventive actions are logged and controlled through the Corrective Action Programme procedure PAG-71. Often the corrective actions imply changes to processes and/or training programmes, including the training using full scope, classroom and process simulators, according to the procedures EP-9152 and EP-9159 that govern the training to licensed (control room operators) and non-licensed personnel (field operators), respectively, and the procedure EP-9178 to control the simulator changes.

2007-2009 Period 19-21

Page 193: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

- Mechanisms to share important experience with other operating organizations

The mechanisms for sharing important experiences with other organizations are established in Procedure PAS-18 “Programme for reviewing external operational experience of the Nuclear Power Plant’s Division". This procedure sets the criteria to select or define what LVNPS operational events should be shared with other organizations. These criteria are the same ones set in WANO’s “Operating Experience Programme Reference Manual”, which are applicable to all nuclear power plants. The WANO’s reference manual is followed regarding the event reports content and format, and the event index system used for category, consequences, systems, components, condition, activity, group, direct cause, root cause and causal factors. - Use of international information databases on operating experience The main databases of information on operational experience of events that have occurred in plants of other countries used in LVNPS include those of the Institute of Nuclear Power Operations, the World Association of Nuclear Operators, the US Nuclear Regulatory Commission and NEA Incident Reporting System. - Regulatory review and control activities for Licence holder programmes and

procedures As mentioned in Article 14 of this National Report, the Commission verifies every two years the external operational experience through its base-line inspection programme. Also, during the inspections carried out to different safety-related areas a systematic follow-up of the internal operational experience and the feedback to all staff is performed. Additionally, the inspection to the Corrective Action Programme includes a follow-up to the trend analysis and self-assessments performed by LVNPS staff, relating to internal and external operating experience. The Commission’s staff reviews the operational experience documented in the generic letters and bulletins issued by the USNRC, and forwards to LVNPS any applicable one that requires a response from the installation. - Programmes of the Regulatory Body for feedback of operational experience

and the use of existing mechanisms to share important experiences with international organizations and with other regulatory bodies

As mentioned in above, the Commission participates in the NEA/IRS and the IAEA/INES meetings to share operational experience of the Mexican nuclear installation with member countries of the international community, as well as to learn about the experience of other countries, and implement any changes if necessary.

2007-2009 Period 19-22

Page 194: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Article 19 (8) Management of spent fuel and radioactive waste on the site - Overview of the Contracting Party’s and regulatory requirements for the on-

site handling of spent fuel and radioactive waste Regarding to the spent fuel, LVNPS has adopted the strategy to store all the spent fuel generated during the licensed lifetime of both units in the Spent Fuel Pool, one pool per unit. The applicable requirements for the pools and support system design are the requirements established in 10CFR50. Additionally, the applicable requirements relating to radiation safety associated with the spent fuel management are those stated in the General Regulation for Radiation Safety. With regard to the radioactive waste, the current regulation based on the General Regulation for Radiation Safety, applicable to the radioactive waste management at nuclear installations is the following: NOM-004-NUCL-1994 Classification of radioactive wastes. NOM-008-NUCL-2003 Contamination control. NOM-018-NUCL-2000 Methods for determining the activity concentration and total

activity in radioactive waste packages. NOM-035-NUCL-2000 Limits to classify a solid waste as a radioactive waste. NOM-036-NUCL-2000 Requirements for radioactive waste treatment and

conditioning installations. In addition to the Mexican Official Standards just mentioned, the radioactive waste management shall comply with the applicable requirements relating to radiation safety stated in the General Regulation for Radiation Safety and the applicable regulation. - On-site storage of spent fuel The storage pool (one per LVNPS unit) was originally designed in 1972 for a capacity of just 580 fuel assemblies, equivalent to an 18-month fuel cycle. Towards the end of 1989, analyses were performed for the final arrangement of fuel racks in the storage pool, based on the use of steel racks having special receptacles to retain Boron. LVNPS submitted an analysis to the Commission, which after evaluating the heat removal capacity from the pool cooling systems as well as the sub-criticality factor, gave authorization to increase the capacity of each storage pool to up to 7.16 cores (3,177 fuel assemblies), from which 6.16 cores (2,733 assemblies) are designated for routine storage and a complete core for emergency situations. The above cited represents a storage capacity for the total estimated operation lifetime of LVNPS. - Implementation of on-site treatment, conditioning and storage of radioactive

2007-2009 Period 19-23

Page 195: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

waste Liquid waste treatment The liquid wastes collected come from different sources, so they are divided as follows: equipment drains, floor drains, regeneration and chemical drains, detergents and laundry drains, and miscellaneous drains. The treatment process is carried out in batches, maintaining a surveillance and control of the chemical quality through analysis and sampling. The specific actions depend upon the two following activities:

a) For recycling, LVNPS procedures set the chemical parameters that need to be complied with.

b) For release to the environment, the radioactive material is analyzed to ensure that any discharge is As Low As Reasonably Achievable (ALARA) and in conformance with the requirements specified in 10CFR20 and 10CFR50, including the dose design objective specified in 10CFR50 Appendix I.

Currently, LVNPS is implementing a new treatment system using reverse osmosis technology to improve the radioactive waste processes as part of the ongoing continuous improvement effort. Gaseous waste treatment The gaseous treatment systems are designed according to the origin and radiation levels expected in the LVNPS extraction and ventilating systems such as: radioactive gaseous (off-gas) waste treatment system, the turbine gland seal system and ventilation systems of different process buildings of the installation. It has been verified that the off-gas treatment system is designed to collect and delay exhaust of noble gases produced by fission, which are removed from the condenser by means of steam jet ejectors. The noble gas process continues through a hydrogen recombiner, 10-minute retention tanks, and pre-filter systems, activated carbon beds and high-efficiency air filters and then, finally, through a ventilating air current, which is monitored before being sent to the atmosphere. This hydrogen recombiner system is designed to support the postulation of hydrogen explosions (generated by radiolysis). It has high concentration alarm detection, which alert the main control room operator if the recombiner has problems, thus it is isolated and the redundant train is put into service. Environmental dosimetry studies performed considering LVNPS in operation have demonstrated that design basis suppositions of gas treatment systems are adequate. Based on the above, it is considered that gas treatments satisfy their function of limiting the release of radioactive material in a gaseous form.

2007-2009 Period 19-24

Page 196: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Solid waste treatment This subsystem is designed to collect and process humid and dry wastes generated at LVNPS in order to be able to confine them in a safe and reliable manner inside containers appropriate for its eventual isolation. These can be stored in steel containers or high-integrity high density polyethylene containers. The solid waste processing is controlled by the guidelines of the LVNPS Process Control Programme (PCP), which complies with the Operating Technical Specifications, 10CFR61 and NOM-019-NUCL-1995 (see Table 7.1 of this National Report). The wet waste can be treated by the following process:

a. Cyclical draining from a high integration container where the free water content is reduced to less than 1% by volume.

The dry waste can be treated by one of the following processes:

a. For the compactable waste, hydraulic compressing with 4:1 reduction factors b. For non-compactable waste, direct packaging.

The sources of wet solid waste are: spent ion exchange resins, sludge of the phase separators, concentrated chemical laboratory waste, regeneration and decontamination solutions. The sources of dry solid wastes include: cartridge filters, clothing, paper, plastics, thermal insulation, sand, grit and contaminated replacement components. The drums and High-integrity Containers (HIC) with high-level radioactive waste already processed coming from both units are initially stored in the decay area, within the Radioactive Waste Building. Later the drums and containers are transferred to the On-site Temporary Storage (TS). The polyethylene HIC and the steel drums are manufactured with radiation resistance, structural strength and corrosion resistance, and consistent with the requirements of seismic design and Quality Assurance for final storage. LVNPS has three areas for Temporary Storage of radioactive solid waste: 1. Plant Temporary Storage inside the Radioactive Waste Building, with storage

capacity for HICs and steel drums of 55 gallons, for wet and dry radioactive waste for two years of operation.

2. On-site Temporary Storage outside the double fence area but on-site, to store HIC and steel drums of 55 gallons for wet waste. The storage is reaching its capacity limit; therefore, LVNPS is building a new storage.

2007-2009 Period 19-25

Page 197: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

3. “Dry solid radioactive waste repository” outside the double fence but on-site, to store steel drums of 55 gallons for dry radioactive waste.

During LVNPS Unit 1 start-up, it was decided to design and build an On-site Temporary Storage installation for wet low and medium radioactive waste; since there was no final repository site. This On-site TS was licensed as an extension of the storage area of the Radioactive Waste Treatment Building. This installation was constructed in 1991, with an initial storage capacity for 5 years of operation of both units, considering the original design output of waste. Based on the LVNPS policy for waste reduction, the waste treatment process was improved; and the storage area was restructured and its capacity was optimized, resulting in an increased storage capacity to accommodate waste up to 2007. The On-site TS is getting close to its maximum capacity; therefore, in 2006 LVNPS applied for the licensing of a storage expansion project, which is expected to be completed in mid-2010. The new storage will provide additional storage capacity. Also, a “Dry solid radioactive waste repository” was enabled and licensed in 1993 to have sufficient storage capacity for dry radioactive waste, which provides optimized capacity until 2007, assuming a production similar to the current volumes. In 2006, studies for the implementation of additional volume reduction methods were started to increase the storage capacity; since the storage is about to be full. In 2007, a super-compaction process was carried out, which reduced the volume by a factor of approximately 3:1 of 6,000 compactable solid waste drums. A decontamination process is planned to reduce the volume of metallic waste, which is expected to reduce the volume by about 20% of the current volume, which approximately represents 300 cubic meters. As part of the continuous improvement effort, CFE is in the process of incorporating a new wet solids treatment system, which consists of a dryer and granulator that will equally serve both LVPNS units and replaces the evaporators-extruders that have operated for 15 years. In addition, the new technology system will reduce the final waste compacting ratio to 4:1. With these actions, CFE intends to maintain a reliable waste solidification and reduce the wet solids volume. The unusable reactor tools and components, such as depleted control rod blades, pitted fuel rods, etc., are stored in the spent fuel pool. - Activities to keep the amount of waste generated to the minimum practicable

for the process concerned, in terms of both activity and volume In relation to LVNPS radioactive waste generation minimizing processes, several strategies are being put in place, some of them are:

1. Separation of radioactive material and more efficient, cleaner and expeditious decontamination of tools and objects contaminated, in new separation and

2007-2009 Period 19-26

Page 198: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

decontamination workshops. 2. Incineration of mixed wastes (grease, oils, sludge, etc.) trough international

contractors. 3. For compactable solid radioactive waste, super-compacting and fragmenting; for

not compactable waste, selective decontamination mainly of metallic waste. 4. Optimizing the use of materials to maintain equipment, tools and items free of

contamination. - Established procedures for clearance of radioactive waste CFE has a Technical Manual for the Process Control Programme which is mandatory as prescribed by the OTS 3/4.11.3. The manual objective is to ensure that the treatment and conditioning processes are carried out for all the different types of low-level solid radioactive waste generated at LVNPS, such as: spent resins, temporary resins, precoat sludge, sludge from cleaning, sludge concentrates, activated carbon, active dry and other waste. - Regulatory review and control activities With regard to radioactive waste cleanup, the Technical Manual for the Process Control Programme is intended to comply with the OTS 3/4.11-3, NOM-019-NUCL-1995, 10 CFR 61 and the Branch Technical Position ETSB-11-3; therefore, the Commission assessed this Manual. As mentioned in Article 14 of this National Report, the Commission verifies annually the Radioactive Waste Management through its base-line inspection programme. In particular, the inspection verifies the radioactive waste confinement, stability and control at LVNPS installations dedicated to these activities. Additionally, during the 2007-2009 period, relating to the radioactive waste management, the activities presented below were carried out. LVNPS storages for radioactive contaminated materials Due to the execution of the Extended Power Uprate project in both LVNPS units and since there is no installation with sufficient space and special structures for temporary storage of dry solids radioactively contaminated materials, CFE formally requested to the Commission authorization to construct and operate a set of five “Storage for radioactive contaminated materials” (SRCM). Initially, the SRCMs would receive contaminated materials from the EPU project only; however, the CFE reconsidered its position. LVNPS plans to use the installations for storage of radioactive contaminated materials, free from transferable contamination, generated anywhere at LVNPS,

2007-2009 Period 19-27

Page 199: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

during normal operation, refueling outages, and special projects such as the Extended Power Uprate project itself. As part of the regulatory control activities, the applications for the construction and operation of the SRCMs were assessed by the Commission. As part of the review process, additional information requests were generated, technical meetings were held between the staffs of the Commission and CFE, and technical recognitions visits were made. The design characteristics of the SRCMs, the ventilation systems (HVAC), fire protection, electrical system, aspects of radiation protection and the decommissioning of the storages, among other issues, were assessed. LVNPS storage for radioactive contaminated materials called “4 Naves” CFE informed the Commission that no additional SRCMs would be constructed in addition to the SRCM # 1 and SRCM # 2 already licensed. Considering, on the other hand, the need for sufficient space for temporary and safe storing of metal containers type B12, B25, ISO and other special forms for temporary storage of dry solids radioactively contaminated materials, free from transferable contamination, generated during normal operation, refueling outages and special projects such as the EPU project itself; CFE requested authorization for the reconditioning and operation of one LVNPS “Storage for Radioactive Contaminated Materials” called "4 Naves". As part of the regulatory control activities, the applications for the reconditioning and operation of one LVNPS “Storage for Radioactive Contaminated Materials” called "4 Naves" were assessed by the Commission. As part of the review process, additional information requests were generated, technical meetings were held between the staffs of the Commission and CFE, and technical recognitions visits were made. The structural aspects of the installation and the improvement actions were assessed to ensure radiation safety while the radioactive contaminated materials remain stored in containers type B12, B25, ISO and other special forms. The electrical and fire protection systems were evaluated, as well as the procedures for the control of physical security, and radiation and industrial safety.

2007-2009 Period 19-28

Page 200: National Report presented by the Mexican United …...ARTICLE 16. EMERGENCY PREPAREDNESS 16.0 Obligations 16.1 Emergency plans and programmes-Overview of the Contracting Party’s

MEXICAN UNITED STATES NATIONAL REPORT

Figure 19.1 Structure of Emergency Operating Procedures

RPV CONTROL

RC/L RPV Water Level

RC/P RPV Pressure

RC/Q Reactor Power

C3 Steam Cooling

C1 Alternate Level Control

C2 Emergency RPV Depressurization

C4 RPV Flooding

C5 Level/Power Control

PRIMARY CONTAINMENT CONTROL SP/T

Suppression Pool

Temperature

DW/T Drywell

Temperature

CN/T Containment Temperature

PC/P Primary

Containment Pressure

SP/L Suppression

Pool Water Level

PC/G Combustible

Gas Concentration

SECONDARY CONTAINMENT CONTROL SC/T

Secondary Containment Temperature

SC/R Secondary Containment Radiation

SC/L Secondary Containment Water Level

RADIOACTIVITY RELEASE CONTROL

2007-2009 Period 19-29