national status and activity report
DESCRIPTION
National Status and Activity Report. Republic of Serbia. Zoran Lukic / Plovput. DISC 13, Belgrade, 03/12/2013. Course. RIS in Serbia – current status overview NEWADA Duo ICT related activities Co-Wanda ICT related activities Other activities. RIS. - PowerPoint PPT PresentationTRANSCRIPT
National Status and Activity Report
Republic of Serbia
Zoran Lukic / Plovput
DISC 13, Belgrade, 03/12/2013
Course
RIS in Serbia – current status overview NEWADA Duo ICT related activities Co-Wanda ICT related activities Other activities
RIS
RIS implemented on the Danube and Sava During 2013 problems with budget for RIS
O&M resulting in RIS in Serbia being not operational
System was restored in October 2013 Uncertain O&M for Serbian RIS in 2014
•Tracking and Tracing
•Electronic Reporting System
•Hull Database
•Data Gateway
•Lock Management System
Systems
•Inland AIS Standard
•Inland ECDIS Standard
•Notices to Skippers Standard
Intl. Standards
•AIS Transponders
•ECDIS
•XML
Technologies
• Tracking and Tracing• Electronic Reporting System• Hull Database• Data Gateway• Lock Management
Applications
• Fairway Information Service• Traffic Management Services• Traffic Information Services• Etc…
Services
Vessel Tracking and Tracing
Vessel Tracking and Tracing
Vessel Tracking and Tracing
Vessel Tracking and Tracing
Vessel Tracking and Tracing
Onshore control terminals
50 user terminals in different governmental organizations– Border police– River police– Gendarmerie– Customs– Captaincies…
Electronic NtS System
Lock Management System
Lock Management System
Position correction systems
Position correction systems
Positionaccuracy
betterthan0,5m
Onboard navigation system
Onboard navigation system
49 governmental vessels 160 commercial vessels
NEWADA Duo ICT related Activities
Remote AtoNs monitoring pilot - pending Virtual AtoNs pilot - pending Improved FIS portal - pending Paper ENCs - pending WLAN installation (Iron Gate 2 lock) - pending
Co-Wanda ICT related activities
RIS pilot for waste disposal – pending Virtual Vignette pilot - pending
Kladovo, waste disposal facility
RS
RS
HUHU
BG
RO
Mohacs
Belgrade
vvignette
vvignette
vvignette
vvignette
vvignette
Other Activities
RIS Services usage obligations
19th of July, Governmental Decree adopted
To have and use transponder onboard, starting from 1st of January 2014
To use electronic notices to skippers, according to the NtS Standard, from 1st of January 2014
To have ECDIS system onboard (according to Inland ECDIS Standard), from 1st of January 2015
To use electronic reporting system, according to the ERI Standard, from 1st of January 2015
Related Activities - AtoNs
Project proposal for full roll-out of AtoNs on the Danube (Remote AtoNs and Virtual AtoNs) approved by Ministry
Approval from EU Delegation obtained Financial Agreement EU-Serbia to be signed
in December 2013
Other activities - AtoNs
Timeframe 2014-2017 Budget approx. 3MEur, IPA 2013 funds Three projects
– Supplies of equipment – System integration– Supervision
Other activities – DISC 13
Thank you very much for your attention !
Questions and Discussion