navigation conditions, columbia lock and dam
TRANSCRIPT
NAVIGATION CONDITIONS, COLUMBIALOCK AND DAM, CHATTAHOOCHEE
RIVER, GEORGIA AND ALABAMAHydraulic Model Investigation
TECHNICAL REPORT NO. 2-571
July 1961
ARMY-MRC VICKSBURG, MISS.
PREFACE
A hydraulic model investigation of the proposed Columbia Lock and
Dam, Chattahoochee River, was authorized by the U. S. Army Engineer Dis-
trict, Mobile, in a letter dated 3 September 1958 to the U. S. Army Engi-
neer Waterways Experiment Station. The study was conducted in the Hy-
draulics Division of the Waterways Experiment Station during the period
September 1958 to June 1959.
During the course of the study Messrs. R. L. Bloor and J. H. Douma
of the Office, Chief of Engineers; Messrs. C. P. Lindner and L. R. Leach
of the U. S. Army Engineer Division, South Atlantic; and Messrs. G. W.
Gaines, W. C. Knox, A. M. Cronenberg, F. F. Escoffier, A. F. Baer, A. W.
Kerr, and Claude Colquitt of the Mobile District visited the Waterways
Experiment Station at different times to observe certain model tests and
discuss test results. The Mobile District was kept informed of the
progress of the study by monthly progress reports and special repqrts at
the end of each test.
The investigation was conducted under the general supervision of
Mr. E. P. Fortson, Jr., Chief of the Hydraulics Division, and Mr. G. B.
Fenwick, Chief of the Rivers and Harbors Branch, and under the direct
supervision of' Mr. J. J. Franco, Chief of the Waterways Section. The
engineer in immediate charge of the model was Mr. J. E. Glover, assisted
by Messrs. Lloyd Woods, 0. H. Rhodes, and A. E. Hullum. This report was
prepared by Messrs. Glower and Franco.
Col. Edmund H. Lang, CE, was Director of the Waterways Experiment
Station at the time of this investigation; Mr. J. B. Tiffany was Technical
Director.
iii
CONTENTS
PREFACE
SUMMARY
PART I: INTRODUCTION..
The Apalachicola, Flint, anColumbia Lock and DamPlanned Method of OperationNeed for, Scope, and Purpos
PART II: THE MODEL.......
DescriptionScale RelationsAppurtenancesModel Adjustment . .
PART III: TESTS AND RESULTS
Types of TestsTest ProcedureOriginal Design......Plans A and AlPlans B, Bl, and B2Miscellaneous TestsPlan CPlan DPlans E and El
PART IV: DISCUSSION OF RESULTS,
Limitations of Model Results . .ConclusionsRecommendations
PHOTOGRAPHS 1-9
PLATES 1-19
V
Page
iii
vii
. . . . . . . . 1
Chattahoochee Waterway ..... 1
of Model Study..... ......... 2
4
4567
8
8810121415171718
19
191921
CONCLUSIONS AND RECOMMENDATIONS 0
0
0 0 " " " " " i i
" . . "
" " " "
" " " "
" . " " "
" " " "
" " "
" " " .
" " " "
" " " "
SUMMARY
Columbia Lock and Dam, proposed for construction on the Chattahoo-chee River, will provide a navigable pool extending upstream 28.7 miles tothe Walter F. George Lock and Dam. The model investigation was concernedwith the study of navigation conditions in the lock approaches to determinethe adequacy of the proposed design, and with the development of measuresto overcome or minimize the effects of any adverse conditions. An undis-torted model, scale 1:100, reproducing approximately 1.5 miles of theChattahoochee River including the lock and dam structure was used for theinvestigation.
Tests indicated that, because of the position of the lock and damwith respect to the channel alignment, currents moving from the left banktoward the dam will cross the upper approach to the lock. Downbound towsapproaching the lock would have to maintain sufficient steerageway toovercome the effects of these currents which would tend to rotate the towin a clockwise direction as the bow of the tow entered slack water or movethe tow riverward of the lock guard wall as the tow moved across the cur-rents. Navigation conditions in the upper approach can be improved by:extending the proposed excavation along the left bank landward so thattows can negotiate the turn into the approach farther upstream beforelosing steerageway due to reducing speed to enter the lock approach; ex-tending the guard wall upstream to provide greater protection from cross-currents for tows attempting to maneuver within the approach; installingports in the upper guard wall; and installing a training dike to deflectflow into the upper lock approach.
No navigation difficulties are expected in the lower lock approach.
vii
-N- GULF
it OF MEXICO
SCALE IN MILES
100 0 100 200
Fig. 1. Location map
NAVIGATION CONDITIONS, COLUMBIA LOCK AND DAM
CHATTAHOOCHEE RIVER, GEORGIA AND ALABAMA
Hydraulic Model Investigation
PART I: INTRODUCTION
The Apalachicola, Flint, and Chattahoochee Waterway*
1. The Columbia Lock and Dam, proposed for construction on the
Chattahoochee River 46.5 miles above its mouth and about a mile south of
Columbia, Alabama, is a unit in the Apalachicola, Flint, and Chattahoochee
Waterway (see fig. 1). In order to develop the full potential of the
waterway, a comprehensive plan providing for flood control, power, and
navigation was authorized in Section 2 of the River and Harbor Act of
March 2, 1945, Public Law No. 14, Seventy-ninth Congress, first session,
and in Section 1 of the River and Harbor Act of July 24, 1946, Public Law
No. 525, Seventy-ninth Congress, second session, and modified by the
resolution of the House of Representatives adopted May 19, 1953. This
project provides for a channel, 9 ft deep and 100 ft wide, from the mouth
of the Apalachicola River to Columbus, Georgia, on the Chattahoochee
River, and to Bainbridge, Georgia, on the Flint River by the construction
of navigation-power dams at the junction of the Flint and Chattahoochee
Rivers (Jim Woodruff Dam) and near Ft. Gaines, Georgia (Walter F. George
Dam); a low navigation dam between the Jim Woodruff and Walter F. George
Dams near Columbia, Alabama (Columbia Lock and Dam); a multipurpose dam at
Buford, Georgia (Buford Dam), on the upper Chattahoochee River; and sup-
plemental channel work in the Apalachicola River. Other flood-control and
power elements of the comprehensive plan have not yet been authorized for
construction. The elements of the plan authorized for construction, with
the exception of the Columbia Lock and Dam, are all in progress or
completed.
* Prototype information obtained principally from: Design Memorandum No.3, Columbia Lock and Dam, Chattahoochee River, Georgia and Alabama,U. S. Army Engineer District, Mobile, Alabama; House Document No. 342,76th Congress; and House Document No. 300, 80th Congress, 1st session.
Columbia Lock and Dam
2. The Columbia Lock and Dam will provide a normal upper pool
elevation of 102.0.* This will provide a 9-ft navigable depth extending
28.7 miles upstream to Walter F. George Lock and Dam; however, some chan-
nel improvement will be necessary at the upper end of the pool. The dam
will consist of (a) a gated section, containing four tainter-gate bays,
each with a clear width of 60 ft, and having a crest elevation of 82.0,
and (b) a 340-ft fixed-crest section with crest at elevation 102.0. The
lock will have clear dimensions of 82 by 450 ft and a maximum lift of
25 ft.
Planned Method of Operation
3. During the greater part of the year when the flow in the Chatta-
hoochee River is low, it is planned to operate the turbines at the Walter
F. George powerhouse only during hours of peak demand. This type operation
will cause flow in the Columbia pool to fluctuate from practically zero to
as much as 30,000 cfs daily. In order to narrow the range of discharge
over the Columbia spillway and build up the tailwater elevation gradually,
it is planned to regulate headwater levels and discharges at the gated
spillway. The pool at the Columbia Lock and Dam will be drawn down to an
elevation not less than 96.0 starting about an hour and a half before the
turbines at the Walter F. George powerhouse are put into operation. The
pool drawdown surge thus created will move progressively up the reservoir,
and about the time it would begin to affect the upper end of the pool,
power operation of the Walter F. George powerhouse will begin and the surge
generated by the turbine discharge will move downstream, counteracting and
quickly reversing the drawdown surge in the Columbia pool.
Need for, Scope, and Purpose of Model Study
4. The original design of the Columbia Lock and Dam was based on
* All elevations are in feet above mean sea level.
sound theoretical design practice and experience with similar structures.
However, navigation conditions vary with location and flow conditions up-
stream and downstream of a structure, and an analytical study to determine
the hydraulic effects that can reasonably be expected to result from a
particular design is both difficult and inconclusive. Thus a comprehen-
sive model study to investigate these effects was considered necessary.
5. The location of Columbia Lock and Dam just downstream of a bend
in the river, and the arrangement of the structures with the lock on the
left bank below the point of the bend were already fixed at the time of
the model study. Therefore, the specific purposes of the model tests were
to demonstrate flow conditions that would occur in the upper and lower
lock approaches at various river flows, and to assist in development of
any modifications--other than relocating or rearranging the structures--
that might eliminate or minimize undesirable conditions.
PART II: THE MODEL
Description
6. The model reproduced a short reach of the Chattahoochee River,
extending from 4000 ft above to 4200 ft below the proposed site for the
Columbia Lock and Dam (fig. 2). The model was of the fixed-bed type with
Fig. 2. Site map
the greater part of the channel and overbank area molded in sand-cement
mortar, and the remainder, consisting of areas along the left bank likely
to be modified during the study, molded in pea gravel to sheet-metal tem-
plates (fig. 3). The dam crest, lock, and guard walls were fabricated of
sheet metal. Piers on the gated section of the spillway were made of Plexi-
glas. The lock and dam gates were simulated schematically with sheet-metal
slide-type gates since their only function was to maintain the upper pool
at the desired elevation without regard to gate opening or stilling basin
act i on.
Fig. 3. The model
7. The model was molded in accordance with a 1953 hydrographic
and topographic survey except for areas proposed for dredging which were
molded to the after-dredged condition. Sufficient overbank area was in-
cluded in the model to contain the maximum navigable pool (a pool eleva-
tion of 114.0 at a discharge of 86,000 cfs).
Scale Relations
8. The model was built to an undistorted scale ratio of 1:100,
model to prototype, to obtain accurate reproduction of velocities, cross-
currents, and eddies that would affect navigation. Other scale ratios
resulting from the linear scale ratios were: area, 1:10,000; velocity and
time, 1:10; discharge, 1:100,000; and roughness (Manning's "n"), 1:2.15.
Appurtenances
9. Water was supplied to the model from a comprehensive circulating
system, and discharge was measured with a venturi meter. Water-surface
elevations were measured by means of 10 piezometers located in the model
channel and connected to a centrally located gage pit. Upper pool stages
were controlled by opening and closing the dam gates; tailwater elevations
were controlled by means of a tailgate located at the lower end of the
model.
10. Velocities and current directions were determined in the model
by means of wood cylinder floats weighted on one end to simulate the maxi-
mum permissible draft for loaded barges using the waterway (9-ft proto-
type). A model tow and towboat, shown in fig. 4, were used to determine
Fig. 4. Model towboat and tow
and demonstrate the effects of currents on tows navigating the lock ap-
proaches. The over-all length and width of the towboat with tow simulated
the largest tow for which the lock was designed (78 ft wide by 450 ft
long) with a draft of 9 ft; the dimensions of the towboat itself were not
to scale. The towboat was equipped with twin, screw-type propellers
powered by a small electric motor operating from batteries located in the
tow. The towboat was controlled electronically by remote control and
could be made to run in forward or reverse, at variable speed, and at
various sets of the' rudders.
Model Adjustment
11. Inclusion of the proposed plan in the initial model construc-
tion precluded adjustment of the model to existing prototype conditions.
This type of adjustment was not considered necessary since the proposed
improvements would involve a radical change from existing conditions. The
model surface was of brushed cement mortar, providing a roughness
(Manning's "n") of about 0.0135, which corresponds to a prototype rough-
ness of about 0.029. Based on experience with other models of this type,
brushed concrete gives a very close approximation of the roughness re-
quired to reproduce prototype conditions. Because of the short reach of
river included in the model, any errors in the simulation of prototype
roughness would produce too small an error in the water-surface elevation
to appreciably affect test results.
8
PART III: TESTS AND RESULTS
Types of Tests
12. Tests were concerned primarily with the study of currents and
velocities and the behavior of the model tow in the lock approaches with
various riverflows, dredging plans, and alterations of the lock guard
wall simulated. Also included in the testing program were studies to de-
termine the velocities of currents impinging on the riverbank opposite the
lock discharge outlet during lock emptying, currents around the landside
lock wall during lock filling, and the effect of flow through the gated
spillway on navigation conditions in the lower lock approach. The model
scale was not sufficiently large to permit a study of the discharge coef-
ficients of the spillways or the effectiveness of the stilling basin.
These features were studied on larger-scale section models, and results
of these tests will be presented in a separate report.
Test Procedure
13. Tests consisted of reproducing selected, representative river-
flows (both controlled and uncontrolled) and determining current veloc-
ities and directions and their effects on the model tow. Controlled river-
flows were reproduced by introducing the proper discharge, setting the
tailwater elevation for that discharge, and manipulating the dam gates
until the required upper pool elevation was obtained. Except in certain
instances, all controlled-riverflow tests were conducted with all dam
gates opened the same amount. Uncontrolled riverflows were obtained by
introducing the proper discharge with the dam gates open full, and
manipulating the tailgate until computed tailwater elevation for that
flow was obtained. Lock-emptying discharges were simulated by filling the
lock and adjusting the lock-emptying valve until the rate of emptying was
the same as the computed rate. All flows were permitted to stabilize be-
fore any data were recorded. Representative flows selected for testing
and/or demonstrations included the following:
a. Flow of 20,000 cfs with upper pool at elevation 96.0 (normal
All of the
stages.
hinged-pool operation). Peak flow from all units atWalter F. George powerhouse regulated by operation ofspiliway gates. This flow was also tested with anormal upper pool elevation of 102.0.
b. Flow of 32,000 cfs with upper pool at elevation 96.0(hinged-pool operation). This is the maximum capacityof the Columbia spillway with all gates fully open andpool at lowest elevation permissible.
c. Flow of 32,000 cfs with normal upper pool elevation of102.0. This is the normal condition with peak flow fromthe Walter F. George powerhouse and local inflow.
d. Flow of 45,000 cfs with normal upper pool elevation of102.0. This is the capacity of the Columbia spillway withall gates fully open. This condition is expected to occurabout two or three times a year for periods of about fourdays.
e. Flow of 86,o000 cfs with upper pool elevation 114.0. Thisis the maximum flow at which navigation through the lockis feasible. It is expected to occur about once in threeyears for a duration of about 10 days.
above-listed flows were reproduced in the model as constant
14. Velocities were determined by timing the travel of the floats
described in paragraph 10 over a measured distance; current directions
were ascertained by plotting the paths of the floats with respect to
ranges established for the purpose. In plots of currents in turbulent
areas or where crosscurrents existed, only the main trends are shown for
clarity. The model towboat and tow were observed to determine the effects
of currents on their behavior and the maneuvering required to overcome the
effects of adverse currents in approaching the lock. Some of the current
patterns were determined by taking vertical, time-exposure photographs of
the movement of the wood floats. To obtain current velocities, an
electronic flash was operated during the time exposure, thus superimposing
the location of the floats on the photographs at known time intervals.
The distance between the float locations as defined by two successive
flashes and the time interval were used to compute velocities. Velocities
obtained during lock emptying were, verified by setting a constant lock dis-
charge equal to the maximum instantaneous lock discharge and measuring ve-
locities along the riverbank opposite the lock discharge outlet with a ve-
locity meter.
9
10
Original Design
Description
15. The original design proposed for the Columbia Lock and Dam is
shown in fig. 5. The essential features of this plan were:
a. A lock near the left bank with clear chamber dimensions of450 by 82 ft and with tops of the lock walls at elevation115.0.
b. A 500-ft-long upper guard wall and a 370-ft-long lowerguard wall.
c. An approach channel from the lock to a point about 2400 ftupstream obtained by dredging the left bank to a bottomelevation of 83.0.
d. A lower approach channel obtained by dredging the left bankto a bottom elevation of 64.0 for a distance of about 2300ft from the lock to where the approach channel joined thenavigation channel which was dredged to a bottom elevationof 67.0.
e. A 620-ft-long dam, of which 280 ft was gated spillway witha crest elevation of 82.0, and 340 ft was fixed-crestspillway with a crest elevation of 102.0. The gated spill-way was equipped with four tainter gates, each 60 ft wideby 21 ft high.
f. An upstream approach to the gated spillway excavated toelevation 77.0, and an exit area below the spillway ex-cavated to elevation 72.0.
Results
16. Velocities and current directions obtained during the test of
this plan are shown in photographs 1-6 and reveal that high-velocity cur-
rents occurred just riverward of the bend in the left bankline immediately
above the lock. Velocities near the left bank of the bend were 1.3 to 2.0
fps with a 20,000-cfs flow (photograph 1), 3.2 to 4.4 fps with a 45,000-
cfs flow (photograph 2), and 4.0 to 6.5 fps with an 86,000-cfs flow (photo-
graph 3). During low flows, the high-velocity currents moved from along
the left bank to the spillway, passing close to the end of the upper guard
wall of the lock. Dulring~ the higher flows, the high-velocity currents
followed the same general alinment, except that they tended to swing
farther riverward of the end of the guard wall.
1-7. The currents moving from the left bank toward the end of the
guard wall would provide a strong crosscurrent in the path of" a tow
POLI EL 15.0PNORAL UPPER PO
EL 102.0
2 MIRYW R P T7.
FLOOR a 0 Q
TYPICAL SECTION THROUGH LOCK
20 0 20 40 60FT
yi
. ETYPICAL SECTION FIXED-CREST
SPILLWAY
10 0 10 2 0 2.F
LEGEND
8 GAGE NUMBER AND LOCATION- - CONTOURS BELOW POOL ELEVATION
---- CONTOURS ABOVE POOL ELEVATION
PARTIAL PLAN GATED SPILLWAY
30 0 30 60 90FT
," .. ."'EL VA R/ES".:." _:.: .. "'n...w..."..": v
TYPICAL SECTION GATED SPILLWAY
10 0 10 20 0 FT
SCALES IN FEET
ROTOTYPE 200 0 200 400 600 800
MODEL 2 0 2 4 6 a
Fig. 5. Plans and details of~ original design
12
attempting to enter or leave the upper lock approach. A downbound tow
attempting to turn into the lock approach would have its stern in high-
velocity currents with its bow in relatively slack water, and thus there
would be a strong tendency for the tow to be rotated counterclockwise.
Since the turn has to be made a short distance above the end of the guard
wall at a point where the speed of the tow should be reduced for entrance
into the lock approach, it would be difficult for the towboat to develop
sufficient steerage to overcome the effects of the crosscurrents, and the
tow would be in serious danger of hitting the end of the upper guard wall.
Since currents do not follow the left bank into the approach to the lock,
tows could not be made to enter the lock approach by flanking. Upbound
tows would tend to have their bows forced riverward by the high-velocity
currents from along the left bank. However, upbound tows could be under
full power and thus could develop sufficient steerageway to overcome the
effects of these currents.
18. In the lower lock approach, a fairly large eddy developed with
upstream currents of about 2.0 to 2.8 fps close along the left bankline.
River currents at the head of the eddy were generally less than 1 fps,
and occurred some distance downstream of the end of the guard wall (see
photographs 4-6). Tows could avoid the upstream currents close to the
left bank and approach the lower guard wall with practically no
difficulty.
19. Currents resulting from a lock-emptying operation with mini-
mum tailwater elevation (no flow over the spillway) impinged on the
right bank as shown in photograph 7. Maximum velocities measured along
the right bank opposite the lock-emptying outlet were in the order of
5 to 6 fps.
Plans A and Al
Description
20. Plan A, as shown in plate 1, was designed to improve navigation
conditions in the upper approach, and was the same as the original design
except for the following:
a. Additional dredging of the left bank was accomplished inorder to move the bend in the left bankline farther upstream.
13
This involved removing an additional 150 ft at the pointin the left bankline and extending the dredge cut about450 ft farther upstream.
b. Thirteen ports, 25 ft wide and with tops at elevation 93.0,were installed in the guard wall, and concrete sheet-pilecells were placed at the end of the guard wall to form a300-ft extension of the wall with 10-ft openings spaced asshown in plate 1. This modification was made in an effortto reduce the crosscurrents in the lock approach.
c. A training dike, consisting of ten 15-ft-diameter sheet-pile cells spaced on 30-ft centers, was placed opposite andjust downstream of the bend in the left bankline in an ef-fort to deflect flow into the lock approach.
d. A 50-ft wing wall was added at the upstream end of thelandside lock wall, angled 45 degrees therefrom to reducethe danger of tows hitting the end of this lock wall.
21. Plan Al was the same as plan A, except that the training dike
was eliminated. Only preliminary tests were conducted with plans A and Al
installed in the model.
Results
22. Velocities and current directions in the upper lock approach
with plans A and Al installed are shown in plates 2-4. With plan A, cur-
rents along the left bank moved into the lock approach. The eddy preva-
lent in the upper lock approach with the original design installed was
practically eliminated during the 45,000-cfs flow (plate 2) and was re-
duced appreciably during the 86,000-cfs flow (plate 3). The model tow
could not be made to drift into the approach with plan A. However, be-
cause of the location of the bend farther upstream and currents moving
into the lock approach, tows could maintain more speed and steerage and
thus overcome the effects of the crosscurrents, or could be flanked around
the bend and driven into the approach without serious difficulties.
23. Removal of the training dike in plan Al reduced the currents
moving toward the landside of the guard wall and increased the size and
length of the eddy along the left bank (plate 4). Because of the currents
moving toward the riverside of the guard wall, there was very little flow
through the ports in the guard wall. With this plan, tows could not be
flanked around the bend in the left bank. To enter the lock approach,
tows had to move with more power and steerage to overcome the effect of
the crosscurrents than with plan A.
14
Plans B, Bl, and B2
Description
24. Plan B was designed to improve navigation conditions in the
upper approach without the use of a training dike which might be ob-
jectionable to navigation and would increase cost of the project. The
features of this plan, shown in plate 5, included the following:
a. The excavation along the left bank was modified to movethe bend in the bankline farther upstream than in theoriginal design.
b. The exit from the stilling basin was excavated to eleva-tion 64.0 for a distance of 100 ft downstream of the basin.
c. The lock-emptying outlet was pointed more downstream so asto form a 60-degree angle with the lock wall instead of the80-degree angle utilized in the original design.
d. A 188-ft wing wall with three 10-ft openings spaced on 44-ft centers was added to the upper end of the upper guardwall. The wing wall was placed at a 15-degree angle withthe main wall.
25. Plan B1 was the same as plan B except that the wing wall was
276 ft long with five 10-ft openings spaced on 44-ft centers.
26. Plan B2 was the same as plan Bl except that 13 ports, 3 ft
high by 25 ft wide and spaced on 35-ft centers, were installed in the
upper guard wall. The tops of the ports were at elevation 86.0.
Results
27. Upper approach. Velocities and current directions (shown in
plates 6-10) and observations of the model tow indicated that the modifica-
tions incorporated in plan B effected some improvements in navigation con-
ditions in the upper lock approach over those obtained with the original
design. The modifications of plan B did not appreciably affect the cur-
rents moving from the left riverbank toward the end of the wing wall, and
downbound tows would still encounter difficulty negotiating the bend along
the left bank upstream of the lock. During lower flows, tows would en-
counter essentially the same conditions as with high flows, but because of
the lower velocities, the effects of the adverse currents could be over-
come with less difficulty.
28. The increase in the length of the wing wall in plan Bl made
15
little difference in direction or velocity of the currents moving from the
point of the bend toward the end of the wing wall (see plate 11). Naviga-
tion conditions were somewhat better, however, because of the greater
maneuver area provided by the longer wall, and tows would be provided
greater protection from currents moving toward the spillway.
29. Installation of ports in the guard wall in plan B2 permitted
some flow landward of the guard wall and reduced considerably the in-
tensity of crosscurrents at the end of the wing wall (plate 12). Tests
with the model towboat and tow indicated that tows could navigate the
reach from the bend to the lock with less difficulty than was encountered
with either plan B or Bl. The flow through the ports was not sufficient
to permit tows to be flanked around the bend along the left bank and into
the approach. However, tows could drive into the lock approach with less
power and steerage than with plan Bl.
30. Lower approach. No serious navigation difficulties were en-
countered in the lower approach to the lock with either plan B, Bl, or B2
installed. The intensity of the eddy in the lower lock approach below the
end of the guard wall was generally low. The upstream currents along the
left side of the eddy were close to the left bank, either out of the
navigation channel or in a position where they could be easily avoided.
Crosscurrents at the upstream and downstream ends of the eddy were less
than 1 fps and would not have any appreciable effect on the movement of
a tow.
Miscellaneous Tests
Effects of spillway gate openings
31. Tests on a model of a section of the gated spillway, which were
in progress at this time, indicated that during certain controlled river
discharges, waves would be generated in the stilling basin and might ex-
tend into the lock approach. The conditions were set up in the navigation
model with plan B installed, and the highest waves were obtained with a
discharge of 36,000 cfs, a tailwater elevation of 97.8, and the four
spillway gates open 10 ft. These waves extended downstream into the lower
lock approach, where their maximum height was about 0.5 ft. The waves
16
bending around the end of the lower guard wall would tend to move the bow
of a tow landward as the tow approached the lock wall. The height of the
waves was reduced to about 0.2 ft by opening the two center spillway gates
4.0 ft and the two end gates 14.5 ft, and the tendency for tows to be
moved landward was practically eliminated. The effects of the waves on
current directions in the lower approach are shown in plate 13.
Headwater-tailwater relation
32. The headwater-tailwater rating curve, shown in plate 14, in-
dicates that the swellhead over the dam will vary from about 1.3 ft at a
discharge of 45,000 cfs to about 0.7 ft at a discharge of 86,000 cfs.
Lock-emptying operations
33. A typical flow pattern obtained during lock-emptying opera-
tions at minimum tailwater elevation and no river discharge is shown in
photograph 8. The direction of flow from the outlet was diverted toward
the right bank where a clockwise eddy formed upstream and a counterclock-
wise eddy formed downstream of the point of impingement. The flow pat-
tern and the maximum velocity measured along the right bank opposite the
outlet were about the same as in the original design. Velocities along
the right bank were in the order of 5 to 6 fps. The flow pattern during
lock emptying would be altered considerably with discharge through the
dam gates, and the impingement of currents against the right bank would
be reduced.
Lock-filling operations
34. Lock-filling operations were simulated in the model by opening
the upper lock gate in accordance with a lock-filling curve furnished by
the Mobile District. Currents, indicated by floats as shown in photograph
9, indicated that an eddy would form just downstream of the end of the
landside lock wall, but that it would not be of sufficient intensity to
affect appreciably the capacity of the lock intake manifold. It should
be realized that if the lock is filled by means of an intaike manifold in
the landside wall, the current pattern during a lock-filling operation
might be somewhat different, and the intensity of the eddy might be
reater than indicated in this test in which filling was accomplished
thrug the lock gate.
17
Plan C
Description
35. Plan C was designed in a further effort to obtain satisfactory
navigation conditions without the training dike of plan A and effect
economies in construction. Plan C was the same as plan A (plate 1) with
the following exceptions:
a. The alignment of the lower end of the dredge cut along theleft bank was modified slightly so that the 400-ft lengthof cut above the end of the lands ide lock wall was thesame as in the original design.
b. The upper end of the dredge cut above the bend was warpedfrom a 1-on-3 to a 1-on-6 slope.
c. The training dike was eliminated, and the 300-ft guard-wall extension was replaced by the 188-ft wing wall ofplan B (see plate 5).
d. Ports in the guard wall were eliminated.
e. The landside wing wall was eliminated.
Results
36. Velocities and current directions for the maximum navigable
flow, shown in plate 15, indicated little difference in the alignment
and velocity of currents from those obtained during the test of plan B
(see plate 10). Navigation conditions were better than with plan B because
the bend in the bank was farther upstream, and because of the increased
maneuver area landward of the guard wall. Therefore, tows could begin
the turn for the approach farther upstream where more speed and steerage-
way could be maintained.
Plan D
Description
37. Plan D involved the modification of the left bank, as in-
dicated by the normal upper pool lines in plate 15. The left bank was
straightened from a point about 800 ft above the end of the landside lock
wall to a point about 1800 ft upstream, where it intersected the existing
bankline. All other conditions were the same as with plan C.
Results
38. Velocities and current directions in the upper lock approach
for the maximum navigable flow (shown in plate 15) revealed that the size
and intensity of the eddy in the upper approach were increased, and cur-
rents from the left bank moved farther riverward of the lock wall than
with plan C. Tows would have less difficulty in negotiating the bend up-
stream of the lock than with plan C, but because of the intensity of the
eddy and irregularities in the alignment of currents within the eddy,
more difficulty would be experienced in maintaining the alignment of the
tow.
Plans E and El
Description
39. Plans E (plate 16) and El included the excavation of the left
bank as in plan B together with modifications of the guard wall as follows:
a. Plan E. The guard wall was 484 ft long and contained 32ports, each 3 ft high by 5 ft wide, spaced on 15-ft centerswith their tops at elevation 86.0. The wing wall was 200ft long, was placed at a 15-degree angle with the guardwall, and contained three ports, each 10 ft high by 20 ftwide spaced on 60-ft centers with their tops at elevation93.0.
b. Plan El. This plan was the same as plan E, except that 16ports on -the downstream end of the guard wall wereeliminated.
Results
40. Current directions and velocities indicated that ports in the
upper guard wall would facilitate the movement of downbound tows approach-
ing the lock, particularly during lower flows (plate 17). During higher
flows (plate 18) the amount of flow through the ports was relatively small,
and the effect of the ports on navigation conditions was not as great as
during the lower flows. Eliminating ports in the lower half of the guard
wall (as in plan El, see plate 19) decreased the flow landward of the
guard wall and increased the intensity of the crosscurrents near the end
of the wall, thus increasing the difficulty tows would encounter in ap-
proaching the lock.
19
PART IV: DISCUSSION OF RESULTS, CONCLUSIONS AND RECOMMENDATIONS
Limitations of Model Results
41. The analysis of the results of this investigation is based
principally on a study of currents and velocities in the upper and lower
approaches to the lock, and the effects of these currents on the behavior
of the model towboat and tow. In evaluating test results, it should be
borne in mind that small changes in direction of flow or in velocities are
not necessarily changes produced by a change in plan, since several floats
introduced at the same point may follow slightly different paths and move
at slightly different velocities. Current directions as shown in the
photographs and plates, except for those obtained during lock-emptying
operations, were obtained with floats submerged 9 ft (prototype) and
should be indicative of currents that will affect the behavior of tows.
Because of the small model scale, it was difficult to reproduce accurately
the hydraulic characteristics of the prototype structures or to measure
water-surface elevations within an accuracy greater than +0.1 ft (proto-
type). For this reason, data showing the swellhead produced by the lock
and dam structure and the amounts of gate openings should be considered
only as approximations. Also, the rate of damping of waves in the model
is greater than would be the case in the prototype because of the effect
of surface tension. The wave heights measured in the model in the lower
approach therefore are probably lower than those to be expected in the
prototype.
Conclusions
42. The results of tests of navigation conditions at the Columbia
Lock and Dam indicate that, because of the arrangement of the lock and dam
with respect to the alignment of the channel, currents moving toward the
dam from along the left bank cross the approach to the lock. In order to
enter the lock, downbound tows must change direction of approach. While
negotiating the turn, a tow would have its stern in high-velocity currents
with its bow in relatively slack water, resulting in a strong tendency for
20
the tow to be rotated counterclockwise and moved toward the dam. The tow
therefore must maintain sufficient speed and steerageway to overcome the
effects of these currents at a time when it should begin to reduce speed
for the approach. Since the location and arrangement of the lock and dam
were fixed by other considerations, the plans tested were designed to
minimize the effects of the crosscurrents and to develop methods which
would facilitate the movement of tows into the lock approach. The re-
sults of these tests are the basis for the following conclusions:
a. No difficulties should be encountered by navigation in thelower approach. With certain tailwater conditions, waveswill develop within the stilling basin of the gated spill-way and extend into the lower lock approach. The waveswill tend to move the bow of a tow landward as it ap-proaches the lock wall. However, the height of the waveswill be generally less than 1 ft, and their effect ontows approaching the lock will be slight. Also, the heightof the waves can be reduced by proper manipulation of thespillway gate openings.
b. It would not be possible for tows to drift into the upperlock approach with any of the plans tested because of theset of the currents and the eddy along the left bank abovethe lock. Also, tows would not be able to negotiate theturn into the upper approach to the lock by flanking, sincecurrents would not follow the alignment of the left bankexcept with plan A, which utilized a training dike to de-flect flow into the approach.
c. Navigation conditions in the upper approach can be im-proved by the following:
(1) Excavation of the left bank so as to place the bendin the left bankline far enough upstream to permittows to negotiate the turn before beginning to losesteerageway following reduction in speed to enterthe lock approach.
(2) Extension of the guard wall with a wing wall so as toprovide a larger maneuver area and greater protectionfrom crosscurrents for tows moving close to the endof the wall.
(3) Installation of ports in the upper guard wall. Flowthrough ports in the lock guard wall would tend tofacilitate the movement of downbound tows into thelock approach. Because of the location of the lockand dam with respect to the bend upstream, flowthrough the ports would be small unless a favorablehead differential is developed by deflecting flow intothe lock approach by a training dike or dikes, or by
21
extension of the guard wall into the currents movingfrom the left bank toward the gated dam. Normally,as flow through the ports is increased, the speed atwhich a downbound tow would drift toward the guardwall and the difficulty an upbound tow would encounterin pulling away from the wall will be increased unlessthe tops of the ports are well below the bottom of aloaded barge. Since flow through the ports was gener-ally small, no difficulty would be expected with anyof the ports tested in the main wall. Lowering thetops of the ports in the wing wall to elevation 93.0would reduce the difficulty tows would encounter inmaneuvering near the end of the guard wall withoutadversely affecting navigation conditions in otherareas within the approach.
d. No difficulties should be encountered in the upper approachby upbound tows leaving the lock with any of the planstested.
e. Flow from the lock-emptying system will not produce veloc-ities along the right bank greater than those which wouldresult from normal riverflows.
Recommendations
43, Based on the results of this investigation it is recommended
that the following minimum modifications of the original plan be included
in the design of Columbia Lock and Dam:
a. Excavation along the left bankline as provided by plansB and E.
b. Extension of the guard wall with a wing wall about 200 ftlong.
c. Installation of ports in the guard-wall extension (wingwall) and in the main wall.
Photograph 1. Velocities and current directionsin upper lock approach, original design.
Discharge, 20,000 cfs; upper pool el 102.0
Photograph 2. Velocities and current directionsin upper lock approach, original design.
Discharge, 45,000 cfs; upper pool el 102.0
Photograph 3. Velocities and current directionsin upper lock approach, original design.
Discharge, 86,000 cfs; upper pool el 114.0
Photograph 4. Velocities and current directionsin lower lock approach, original design.Discharge, 20,000 cfs; tailwater el 87.9
Photograph 5. Velocities and current directionsin lower lock approach, original design.
Discharge, 45,000 cfs; tailwater el 100.17
Photograph 6. Velocities and current directions
in lower lock approach, original design.
Discharge, 86,000 cfs; tailwater el 113.3
4,
Photograph 7. Typical flow pattern during lock-emptying operation, orig-inal design. Discharge through dam, none; tailwater el 77.0; upper pool
el 102.0; lock-emptying time, 7 minutes
Photograph 8. Typical flow pattern during lock-emptying operation, plan B.Discharge through dam, none; tailwater el 77.0; upper pool el 102.0; lock-
emptying time, 7 minutes (compare photographs 7 and 8)
Photograph 9. Plan B2:tion. River discharge,
lock-filling time, 7
Typical flow pattern during lock-filling opera-none; upper pool el 102.0; tailwater el 77.0;minutes. Lock filled through upper lock gate
fi :ytt:
/O' 65' /0' 465'
/3 PORTS /0'X25' SPACED ON 35' CENTERS
00 D 30 0 90FT
LEGEND4@ GAGE NUMBER AND LOCATION
CONTOURS BELOW POOL ELEVATION-- " CONTOURS ABOVE POOL ELEVATION
IEL 1150
EL /030
TYPICAL SECTION THROUGH PORT
PLAN APLAN A
SCALES IN FEET
PROT7TYPE 200 0 200 400 a00 9.MODEL 4 0 2 A4 a0
rU
-oS
Nk\ RIO
~~g -- Z ~ ~R15 R20
0. 0 -g
NORMAL UPPER POOL EL /02.0 _ -
SCALES IN FEET
PROTOTYPE 200 0 200 400 600 800
MODEL 1 0 1 3 4 5 6 7 8
LEGEND
68 --- - FLOAT VELOCITY IN FPS
NOTE; VELOCITY AND CURRENT DIRECTIONFLO~ATS SUBMERGED 9.0 FT.
VELOCITIES ANDCURETDRCIN
DISCHARGI 500 F
. A
R1O
R20
NORMAL UPPER POOL EL 102 . -~~
POOL EL 1140 SL
SCALES IN FEET
4 244 40MODEL o f 4 5s 7 6
LEGEND
---- "-. FLOAT VELOCITY IN FPS
NOTE: VELOCITY AND CURRENT DIRECTIONFLOATS SUBMERGED 1O FT.,EOIISADCRETDRCIN
VELOCIPLAN AAPI ~~DISCHARGI 600 F
AAA AMGuy ___duowearnrvoir Aw %,
RZ
r
I Rq
7 1
W~c = $
N.~.e U,~4- -'3Cllqr
NORMAL U4PPER POOL EL /02.0-W--.
SCALES IN FEET
PROTOTYPE 200 0 200 400 800 800
MODEL I0 l2 3 45 6 7 8
LEGENDAL-.. FLOAT VELOCITY IN FPS
NOTE; VELOCITY AND CURRENT DIRECTIONFLOATS SUBMERGED 9.0 FT.
VELOCITIES ANDCURETDRCIN
DISCHARG 600 F
LEGEND
4e GAGE NUMBER AND LOCATION- CONTOURS BELOW POOL ELEVATION
-- CONTOURS ABOVE POOL ELEVATION
TYPICAL SECTION THROUGH PORT
PLAN S2
SCALEipO 0 10 20 30 FTT
PLANS B,BI, AND B2SCALES IN FEET
PROTOTYPE 29Q 0 200 400 600 X00
MODEL 2 0 2 4 6 S
00
-4
LEGEND---- FLOAT VELOCITY IN FPS
NOTE : VELOCITY AND CURRENT DIRECT IONFLOATS SUBMERGED 9.0 FT.
NORMAL LOWER A 00L L776 -35 UPPER POOL- EL /020 FT MSL -' - $ ^
S.L A.CEK4
_ - _r - ' ._-
--.- 32.9
__ ,NOMLLOWER POOL ESL 770.~* ~ _______
zz 2
SCALES IN FEET
0 200 400 600 800
I 0 1 2 3 4 5 6 7 8 VELOCITIES AND CURRENT DIRECTIONSPLAN B
DISCHARGE, 20,000 CFS
rz:
PROTOTYPE 200
MODEL
- 'p.. 10
'p 'pO
NORMAL UPPER POOL EL 102.015 20
V 'N.,
fi .1.. ~ --- N
'.
- "4 - ~
- - -'p7 ~
NORMAL UPPER POOL EL /02.0UPPER POOL EL /02.0 ~r AISL
'N.N.~.
N.-.'N.
N.-
SCALES IN FEET
04 200 400
//
600 800
I 0 I 2 3 4 6 7 8
LEGENDa-+ FLOAT VELOCITY IN FPS
NOTE : VELOCITY AND CURRENT DIRECTIONFLOATS SUBMERGED 9.0 FT.
VELOCITIES AND CURRENT DIRECTIONSPLAN B
DISCHARGE 30.000 CFS
N
PROTOTYPE 20
MODEL
-Ur>1'-I
a
- .00
NORMALLIPPRPPOOLPELL02.0 /02.S
4 -"-FLOT-ELOIT-INFP
SCLE I-FE
PRTOYPN20 - o 40 08 04 E OCTESAMODL 0 I 3 4 40
2/ L, o~- - 2 =~~&=~= 3DISCHA *
NORMAL UPPER POOL EL /02.0 FT MSL
5 20
38
'499 -iL46 40 l ,-
LEGEND
8--FLOAT VELOCITY IN FPS
NOTE : VELOCITY AND CURRENT DIRECTIONFLOATS SUBMERGED 9.0 FT.
NORMAL UPPER POOL EL
NORMAL LOWER POOL EL 770, UPPER POOL EL /020 PT M;SL35 - \ - -
S LA C K)40
500
- - ---. 50-47
NORMAL LOWER POOL EL 770_- -"-1 ,, ' -+ SO -_ .
SCALES IN FEET
0 200 4 1 40 600 800VELOCITIES AND CURRENT DIRECTIONS
PLAN BDISCHARGE 45, 000 CFS
Vr-Irr,(0
PROTOTYPE 200
MODEL
mom=
I V t L . 4 O
LEGENDa 00-. FLOAT VELOCITY IN FPS
NOTE : VELOCITY AND CURRENT DIRECTIONFLOATS SUBMERGED 9.0 FT.
3$
NORMAL LOWER POOL; EL 7735
O. 29
54 5
48 4- 7 so ____4__
54 4
NORMAL LOWER POOL EL 770 ----.----- 4,0- - 4
SCALES IN FEET
PROTOTYPE 2000 200dI C40T0 600 800l IRF
I 0 I 2 3 4 5 6 7 8NT iIRFCTIONS
PLAN BDISCHARGE 86,000 CFS
r
-40'
MODEL
LEGEND
-- - FLOAT VELOCITY IN FPS
NOTE: VELOCITY AND CURRENT DIRECTIONFLOATS SUBMERGED 9.0 FT.
PROTOTYPE zoo
MOEL
DISCHARGE 86,000 CFS
SCALES IN FEET
0 00 400 ago 800
I 2 2 4 s a i a
MODEL STUDY OF COLUMBIA LOCK AND DAMCHATTAHOOCHEE RIVER
VELOCITIES AND CURRENT DIRECTIONSPLAN B I
DISCHARGES 32,000 AND 86,000 CFS
mUr
I; , I--- I
NORMAL UPPER POOL EL
20
LIPPER POOL EL 960 Fr MSL
DISCHARGE 32,000 CFS . -
-o - FLOAT
NOTE : VELOCIT
~'..~ -~-~ ~ ~NORMAL UPPER POOL EL /02.0 -.
iv .d
LEGEN
VELOITY N FP
NOMA PPRPOL L/0.
rYAN CRRNTDIECIO DSCARE 6,00CF
FLOATS SUBMERGED 9.0 FT.
UPPER POOL EL /14.0 FT AMSL
SCALES IN FEET
0 200 400 600 800
1 0 1 2 3 4 5 6 7 8
VELOCITIES AND CURRENT DIRECTIONSPLAN 82
DISCHARGES 32,000 AND 86,000 CFS
mUro
PROTOTYPE 200
MODEL
.
MINMUM30MINIMUM LOWER POOL EL f7O35
S L A C K s2:035
14..S-f _alTZ=:-~ -cf'-
M/NFMUM LOWER POOL EL 77
. ' ;GATES I AND 4 OPEN 145 FT
-"'~GATES 2 AND 3 OPEN 4.0 FT
SCALES IN FEET
0 a 00 40
MODEL
LEGEND. FLOAT VELOCITY IN FPS
Q( GATE NUMBER
NOTE: VELOCITY AND CURRENT DIRECTIONFLOATS SUBMERGED 9.0 FT.UPPER POOL EL 102.0 FT MSL
EFFECT OF GATE OPENINGS ONVELOCITIES AND CURRENT DIRECTIONS
PLAN BDISCHARGE 36,000 CFS
Din
t
R R 7
I
mZRJ1OS UTY - - Y IIII v--
09 goo-- 60ebnwwrr to 7,2 --
F v L z " a L2 --- ~ S--~
I- -- -II - I
M inn .n i
A
r
4505055 657007
60DISCHARGE IN 1000 CFS
80 85
HEADWATER -TAILWATERRATING CURVE
00- -000-
01
09
z10 5 - -- 1-J104--- ------ 4
W 0 - - - ~ - - 1 1 1---------------------------------------
45 50 55 85 70 75
N\ ergto
N. - PE PO L 0.
6 ~ ~=~= -=:01 Am == r~
- .- ~ ~NORMAL UPPER PO
, 9 .2 5 1ZZ
LEGE0D
T ELCIY N PS, - 0-r-i3?-NORML UPER OOL L /0.0 .
UPPER .POOL EL /14.0 FT /4SL
OOL EL (02.0
15 20
UPPER POOL EL /14.0 PT MSL
NOTE;$ VELOCITY AND CURRENT DIRECTIONFLOATS SUBMERGED 9.0 FT.
PROTOTYPE
MODEL
PLAN D
SCALES IN FEET
r 0 r 2 a 4 s5Z8_7
VELOCITIES AND CURRENT DIRECTIONSPLANS C AND D
DISCHARGE 88,000 CFS
UPPER POOL EL 10OEO
6--°-.-.F LOA
rtvv v rvv Aviv Qyv avv
2
TYPICAL SECTION THROUGH PORT
SCALE0 0 t0 20 0 FT
PLAN E.SCALE
30 0 30 0 90FT
r1 EL 1/.0
0 910
faimlowQlk5 11 v \ Q770
TYPICAL SECTION THROUGHWING WALL
SCALE10 0 10 20 30OFT
LEGEND
4 9 GAGE NUMBER AND LOCATIONCONTOURS BELOW POOL ELEVATIONCONTOURS ABOVE POOL ELEVATION
PLAN ESCALES IN FEET
PROTOTYPE 20) 0 200 400 600 5o
MODEL 2 0 2 4 6 a
NORMAL UPPER POOL EL /020
- .o , -°s 2-0
-s -0-C K
0108
\ ;' - 6 _ 3,3 ^ ^x.,26
NORMAL UPPER POOL EL /020
LEGEND
°- FLOAT VELOCITY IN FPS
NOTE: VELOCITY AND CURRENT DIRECTIONFLOATS SUBMERGED 9.0 FT.
SCALES IN FEET
P oo o1 200o o 00 400 60 800 VELOCITIES AND CURRENT DIRECTIONSr MODEL I I 2 4 7 PLANE
DISCHARGE 32,00 CFS
K o-"-~ DISCHARGE 45,000 CFS ,"
- -~ NORMAL UPPER POOL EL /G.' ., -1
LEG ND " . - - - -
LEGETY ND RRNTDIECIO
DSHRE8,0CFOATS
SUBMERGED 9.0 FT.
SCALES IN FEET
PROTOTY 20P0 20E40 00 80
I 0 1 2 3 4 5 6 7 8
VELOCITIES AND CUR~RENT DIRECTIONSPLAN E
DISCHARGES 45,000 AND 86,000 CFS
r
'a
NOTE; VE
FL
MODEL
NORMAL UPPER POOL EL /020 FT MSL
C-j 0~L~ 2
0
LEGENDasw- FLOAT VELOCITY IN FPS
NOTE : VELOCITY AND CURRENT DIRECTIONFLOATS SUBMERGED 9.0 FT.
SCALES IN FEET
L 2 I 2 3 4a 5s 8 s
VELOCITIES AND CURRENT DIRECTIONSPLAN El
DISCHARGES 45,000 AND 88,000 CFS
TUrmom MODEL
eww aww
IPROTTYPE
"wvMML~O
rrvse 200 goo am