navitus bay wind park order pins ref: en010024 statement ...... · pins ref: en010024 statement of...
TRANSCRIPT
Navitus Bay Wind Park Order
PINS Ref: EN010024
Statement of Common Ground
(1) Navitus Bay Development Limited
(2) Hanson Aggregates Marine Limited
(2) Lafarge Tarmac Marine Limited
Signed
Name Louise Mann
Position Marine Licensing Manager
For Hanson Aggregates Marine Limited
Signed
Name Dr Andrew Bellamy
Position Resources Manager
For Larfarge Tarmac Marine Limited
Date
Signed
Name Stuart Grant
Position Senior Project Manager
For Navitus Bay Development Limited
Date
Contents
1 Introduction
2 The Development
3 Application elements of interest to Hanson Aggregates Marine Limited and
Lafarge Tarmac Marine Limited
4 Consultation with Hanson Aggregates Marine Limited and Lafarge Tarmac
Marine Limited
5 Matters agreed
6 Matters for discussion
7 Matters not agreed
Appendices
1 Chart of marine aggregate license / application areas in relation to project
boundaries
2 HAML letter 1st Oct 2013
3 LTML Letter 24th Sept 2013
1 Introduction
1.1 This Statement of Common Ground (SOCG) has been prepared in respect of Navitus Bay
Development Limited’s (the Applicant) application for development consent to the Planning
Inspectorate (PINS) under the Planning Act 2008 (the Application).
1.2 This SoCG with Hanson Aggregates Marine Limited (HAML) and Lafarge Tarmac Marine Limited
(LTML) is a means of clearly stating any areas of agreement and disagreement between the
three parties in relation to the Application. The SoCG has been structured to reflect topics of
interest to the HAML AND LTML on the Application.
1.1 The structure of the SoCG is as follows:
Consultation with the HAML and LTML
Matters agreed;
Matters for discussion; and
Matters not agreed.
1.2 Throughout this SOCG the phrase “It is agreed…” is used as a precursor to any point of
agreement that has been specifically stated by agreement between the Applicant and HAML and
LTML. The phrase “It is not agreed…” is used as a precursor to any point that the Applicant and
the HAML and LTML wish to clearly state as not yet agreed. Points that are “not agreed” will be
the subject of ongoing discussion wherever possible to resolve, or refine, the extent of
disagreement between the parties.
2 The Development
2.1 The Application is for development consent to construct and operate the proposed Navitus Bay
Wind Park, which comprises up to 194 wind turbine generators and associated infrastructure,
with an installed capacity of up to 970 MW (the Project). The proposed wind farm will cover an
offshore area of approximately 153 km2 and will connect to the National Grid via underground
cables to the power station at Mannington in Dorset.
2.2 The DCO, if made, would be known as the Navitus Bay Wind Park Order. It will comprise the
following elements:
2.2.1 Offshore wind turbines and foundations (up to 194 wind turbines to provide an
installed capacity of up to 970 MW).
2.2.2 Up to one meteorological mast.
2.2.3 Up to three offshore substations.
2.2.4 Undersea cables between the wind turbines, meteorological mast and offshore
substations.
2.2.5 Up to 6 offshore undersea export cables to transmit electricity from the offshore
substations to the shore.
2.2.6 A landfall located at the Taddiford Gap between Barton-on-Sea and Milford-on-Sea
with onshore transition joint bays to connect the offshore and onshore cables.
2.2.7 Up to 6 onshore underground cable circuits with joint bays to transmit electricity to a
new onshore substation.
2.2.8 An onshore substation on land in the vicinity of the existing National Grid substation
at Mannington, Dorset and up to 2 underground cable circuits to connect the offshore
wind farm to the National Grid.
2.2.9 The permanent and/or temporary compulsory acquisition of land and/or rights for the
Project.
2.2.10 Overriding of easements and other rights over or affecting land for the Project.
2.2.11 The application and/or disapplication of legislation relevant to the Project including
inter alia legislation relating to compulsory purchase.
2.2.12 Such ancillary, incidental and consequential provisions, permits or consents as are
necessary and/or convenient.
2.3 The Application was submitted to the Planning Inspectorate on 10 April 2014 and accepted for
examination on 8 May 2014.
3 Application elements covered by this Statement of Common Ground
3.1 HAML and LTML jointly extract aggregates from active licensed marine aggregate extraction area 127 to the north of the Turbine Area and have the rights set out below to 6 new application areas for potential future extraction operations to the east of the Turbine Area
Area 500/1 (under joint option by LTML and HAML);
Area 500/2 (under joint option by LTML and HAML)
Area 500/3 (under option by LTML);
Area 500/4 (under option by LTML);
Area 500/5 (under option by HAML);
Area 500/6 (under option by HAML).
Refer to Appendix 1 for chart of license areas.
4 Consultation with HAML and LTML
Pre-Application
4.1 The Applicant engaged with the HAML and LTML on the Project during the pre-application
process, both in terms of informal non-statutory engagement and formal consultation carried out
pursuant to section 42 of the Planning Act 2008.
4.2 During formal consultation, HAML and LTML issued letters confirming agreement that the project
boundary took into consideration aggregate industry safety buffers and highlighted mitigation
required for two areas of the export route that did not meet the 500m buffers. HAML letter is
included in Appendix 2 and LTML letter in Appendix 3.
4.3 Pre application stakeholder engagement with the HAML and LTML relevant to Navitus Bay is
detailed in the table below.
Date Form of Consultation Summary
Tarmac Marine
Dredging Ltd
(Tarmac), July
2011 to May
2013
Meeting Meetings have been held to discuss the
existing licensed and application aggregates
areas and also the buffer zone applicable to
marine aggregate extraction areas
Hanson
Aggregate
Marine
Ltd (HAML),
January 2012 to
May 2013
Meeting Meetings have been held to discuss the
existing licensed and application aggregates
areas, and also the buffer zone applicable to
marine aggregate extraction areas.
Post Application Position
4.4 LTML made a relevant representation on the Application to the Planning Inspectorate on 10th
June 2014 (the Relevant Representation). A summary of the comments contained in the
Relevant Representation with the Applicant’s response is set out in the table below.
4.5 HAML have not submitted a representation to the Planning Inspectorate.
LTML Comment Applicant
Response
LTML Position HAML Position
LTM is satisfied with the
mitigation proposed by NBD
with regards to aggregate
extraction.
Agreed Accepted Accepted
It should be noted however
that LTM stresses the
importance of cables being
laid a suitable distance
away from aggregate
licence boundaries to
ensure that they are not
snagged by the dredging
activities. Furthermore LTM
requests the following
points are considered as
appropriate mitigation:
Agreed Accepted Accepted
1) Cables should be
appropriately buried or
armoured to avoid them
from being snagged and
dragged into the aggregate
licence areas where they
overlap the buffer zone
Agreed Accepted Accepted
2) GIS shapefiles to be
provided to LTM displaying
the location of the cable in
relation to the licence
areas. These files will be
kept up to date as and
when maintenance occurs.
. Agreed Accepted Accepted
LTML Comment Applicant
Response
LTML Position HAML Position
3) If maintenance work is
required on the cables post-
construction, when relaying
the cable all effort to be
made to ensure that any
excess cable is laid away
from the aggregate licence
areas and not closer to
them
Agreed Accepted Accepted
5 Matters Agreed
Matter LTML HAML Applicant
For the turbine area the
boundary takes into account the
required aggregate industry
safety buffers and no further
mitigation is required.
Agreed Agreed Agreed
For the export cable area the
boundary takes into account the
required aggregate industry
safety buffers for the majority of
the active/planned extraction
areas save for two locations on
Area 127 where only a 400m
buffer is achieved. This is
acceptable provided the 3
mitigations listed in 4.4 Post
Application Position are
implemented.
Agreed Agreed Agreed
6 Matters for Discussion
6.1 There are not any matters still undergoing discussion between HAML and LTML and the Applicant.
7 Matters Not Agreed
7.1 There are not any matters not agreed between HAML and LTML and the Applicant
Appendix 1
Appendix 2
Appendix 3