nc energy storage study · [2] jim eyer, garth corey, sand2010 -0815, energy storage for the...

109
NC Energy Storage Study Stakeholder Meeting October 2, 2018 1

Upload: others

Post on 27-May-2020

5 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

NC Energy Storage Study

Stakeholder MeetingOctober 2, 2018

1

Page 2: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Legislative Language

2

Page 3: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Faculty and Staff Team Members• Joe DeCarolis, Civil, Construction & Environmental Engineering• Jeremiah Johnson, Civil, Construction & Environmental Eng.• Christopher Galik, Public Administration• Harrison Fell, Agricultural and Resource Economics• Ning Lu, Electrical and Computer Engineering• David Lubkeman, Electrical and Computer Engineering• Wenyuan Tang, Electrical and Computer Engineering• Ken Dulaney, FREEDM Center• Anderson Rodrigo de Queiroz, NC Central• Steve Kalland, NC Cleantech Center• Autumn Proudlove, NC Cleantech Center• Isaac Panzarella, NC Cleantech Center

3

Page 4: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Student Team Members

• Shuchi Liu, Electrical and Computer Engineering• Yao Meng, Electrical and Computer Engineering• Asmaa Alrushoud, Electrical and Computer Engineering• David Mulcahy, Electrical and Computer Engineering• Catie McEntee, Electrical and Computer Engineering• Zachary Small, Agricultural and Resource Economics• Danny Sodano, Civil, Construction, and Environmental

Engineering• Dustin Soutendijk, Civil, Construction, and Environmental

Engineering• Lisha Sun, Electrical and Computer Engineering• Chris Gambino, Public Administration

4

Page 5: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Hypothetical Case Studies• We don’t have a single comprehensive model to examine all

relevant grid services• Instead, we’re conducting a series of hypothetical case

studies, organized by the category of service that storage can provide

• Our approach is use a suite of different models and datasets, each adapted to address a given case study

• Under each hypothetical case study, a set of relevant scenarios are considered

• Scenario assumptions include:–Presence of renewable investment tax credit–Storage cost and performance (present and 2030)–Future scenarios driving 2030 grid mix (bulk energy storage)

5

Page 6: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Definition of storage

Harmonized scenario

assumptions

Cost assessment

Identify applications and services

Identify technologies

Hypothetical Case Studies:Use models and data to

assess benefit

Deployment happening?Barriers? No

How much?

Yes

Break-even cost?

Other Barriers?

[Benefit – Cost]?

+

Policy options to increase value to NC consumers 6

Page 7: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Project Status

• Today we will be presenting preliminary results, with a focus on lithium-ion battery storage

• We have not completed all planned case studies• Additional time is required to synthesize results into a

broader set of insights• Draft report and benefit-cost spreadsheet for public

review on November 1, 2018• Final report on December 1, 2018

Project website: https://energy.ncsu.edu/storage/7

Page 8: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Storage Technologies Considered

Mechanical • Flywheels• Pumped storage• Compressed Air

Electrochemical • Lithium-ion batteries• Lead-acid batteries• High T sodium batteries• Flow batteries

Chemical• H2 electrolysis + storage

+ fuel cells

Thermal• Chilled water• Ice storage• Phase change materials• Water heaters

Electrical • Supercapacitors• Superconducting

magnetic energy storage

8

Page 9: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Cost SpreadsheetWe are developing a spreadsheet to assess storage costs. It includes:• A map showing compatibility between storage

technologies and grid applications• A separate worksheet for each storage technology• Parameters include capital costs, O&M costs, roundtrip

efficiency, lifetime, and degradation (if applicable)• Embedded references to data sources from which cost

and performance data derived• Will be made publicly available once completed

9

Page 10: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Li-ion Battery Cost• Considered the following scales residential (10 kW), commercial

(100kW), utility (1 MW)• And the following durations:

– 0.5 hr, 2 hr, and 4 hr for utility-scale batteries– 2 hr for residential and commercial batteries

Source Current Cost ($/kWhs) Projected 2030 Cost ($/kWhs)

Schmidt et al. (2017) 1250 450

McKinsey & Co. (2018) 587 170

GTM Research (2018) 525

NYSERDA (2018) 401 (2019 estimate) 180

EIA Market Trends (2018) 399

Lazard (2017) 291 (2018 estimate excludes EPC)

10

Assume: 525 $/kWhs; and 200 $/kWhs in 2030 (~60% reduction)

Page 11: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Revenue Requirements

11

Page 12: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Topic and Speaker Lineup

• End-User Services – Isaac Panzarella• Distribution Services – David Lubkeman• Transmission Services – David Mulcahy• Frequency Regulation – Ning Lu• Bulk Energy Time Shifting / Peak Capacity Deferral –

Anderson de Queiroz• Solar Clipping – Jeremiah Johnson• Baseline Policy Review and Survey Results –

Christopher Galik

12

Page 13: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

What to Expect in the Report• Detailed benefit-cost analysis for each service and scenario• A sense for the market size of each service (e.g., high,

medium, low)• An examination of opportunities for value stacking• A policy review that identifies potential barriers and solutions

to the deployment of energy storage

13

• Several applications show that Li-ion batteries are near parity with conventional alternatives; value stacking would likely produce positive net benefits.

• If 2030 projected battery costs realized, case for batteries is more compelling

Preliminary Insights

Page 14: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Process for Stakeholder Q&A• At the end of each presentation, you will have the opportunity to

write down questions or comments pertaining to the presentation• Scribes at each table will transcribe the feedback into a master

Google Sheet• Presenters will address a limited number of questions (time

permitting) as they appear on the screen• Complete compiled feedback will be reviewed and taken into

consideration as we work on the draft report

14

Page 15: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

NC Energy Storage StudyEnd-User Services

Isaac PanzarellaNC Clean Energy Technology Center

Stakeholder MeetingOctober 2, 2018

Page 16: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

End-User ServicesTime-of-Use/Energy Management • Shifting advantage of time-of-use Demand Charge Management• reduce monthly demand peak Backup Power• emergency backup power in the event of outagesDistributed Energy Resource Management• management of energy consumption and injection into gridPower Quality Management• Mitigate voltage fluctuation, voltage drop, and frequency

Page 17: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Demand Charge + DER Management• Demand Charge Management - Shifting electricity

consumption to reduce the customer’s highest peak consumption from the grid can reduce demand charges ($/kW). These are especially significant for industrial and commercial customers. This application can often be coupled with TOU rate reduction ($/kWh).

• Renewable Energy Management - For residential, commercial, industrial, and even utility distributed energy resource (DER) sites, ESS can enable the management of energy consumption and injection into grid. Depending on the objective of ESS control, DER management may respond to economic incentives for end-users or manage variability of power injection to avoid reliability issues.

Page 18: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

RESIDENTIAL

COMMERCIAL

INDUSTRIAL

ESS for Demand Charge + DER Management

Page 19: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

ESS for Demand Charge + DER Management• Applicable technologies

– Battery storage– Battery storage with solar PV– Thermal storage

• Scenarios presented– Large commercial/industrial (~ 1,500 kW monthly peak)– Coincident peak tariff

• Modeling tools– System Adviser from NREL– Excel based spreadsheet

Page 20: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Customer Peak Demand Requirement (kW)

Coincident Peak Demand Charge ($/kW/month)

Customer Peak Demand Charge ($/kW/month)

Energy Charge ($/kWh)

City of Wilson (Schedule FR-MGS-2)

>35 & <500

$23.39 $5.00 a $0.0650

City of Wilson (Schedule FR-1-1)

>500 & <10,000

$20.50 $4.10 a $0.0570

Fayetteville PWC (Pilot CP Rate) b

>1000 $20.11 $2.00 $0.04098

Greenville Utilities (Schedule MGS-CP)

>35 & <750

$17.00 $15.61 $0.03027

Greenville Utilities (Schedule LGS-CP)

>750 $22.20 $13.13 $0.02524

ESS for DCM+DER – Coincident Peak Rates

• Sample of coincident peak demand pricing from NC utilities

Page 21: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

800

900

1,000

1,100

1,200

1,300

1,400

1,500

1,600

1,700

1,800

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Monthly Coincident Peak Demand (kW) with Solar PV & ESS

Base Solar PV 500 kW

Page 22: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

800

900

1,000

1,100

1,200

1,300

1,400

1,500

1,600

1,700

1,800

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Monthly Coincident Peak Demand (kW) with Solar PV or ESS

Base Solar PV 500 kW 500kW 2-hr ESS 500kW 4-hr ESS

Page 23: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

800

900

1,000

1,100

1,200

1,300

1,400

1,500

1,600

1,700

1,800

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Monthly Coincident Peak Demand (kW) with Solar PV & ESS

Base Solar PV 500 kWSolar PV 500kW + 500kW 2-hr ESS Solar PV 500kW + 500kW 4-hr ESS500kW 2-hr ESS 500kW 4-hr ESS

Page 24: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and
Page 25: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and
Page 26: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and
Page 27: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Solar PV 500 kW

Solar PV 500kW + 500kW 2-hr ESS

Solar PV 500kW + 500kW 4-hr ESS

500kW 2-hr ESS

500kW 4-hr ESS

Coincident Peak Demand Savings & Payback with solar PV & ESS- Wilson Energy CP FR-1-1 tariff

Net Capital Cost $889,000 $1,396,500 $1,624,100 $725,000 $1,050,000

Annual Utility Savings $71,011 $173,079 $192,934 $102,632 $121,803

Benefit $/kW/yr $204 $244 $205 $244

Simple Payback 12.5 8.1 8.4 7.1 8.6

Time of Use Rate Savings Savings & Payback with solar PV & ESS- Duke Energy Carolinas Large General Service TOU rate LGS-TOU-50

Net Capital Cost $889,000 $1,396,500 $1,624,100 $725,000 $1,050,000

Annual Utility Savings $53,309 $145,158 $163,061 $92,290 $109,632

Benefit $/kW/yr $184 $220 $185 $219

Simple Payback 16.7 9.6 10.0 7.9 9.6

Page 28: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Still to Come and Future Research beyond this study

This Study• Residential and commercial models• Power quality management benefits of storage• Case studies on customer-sited storage projects in NC

Future Research• Benefits of storage for energy resilience in critical

infrastructure• Incentives for energy storage• Aggregation of customer sited storage for utility dispatch

Page 29: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

NC Energy Storage Study

Distribution ServicesDr. David Lubkeman

Analysis Contributors: Lisha Sun, Shuchi Liu

Stakeholder MeetingOctober 2, 2018

Page 30: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Analysis Scope

• Specific Applications Being Studied:–Distribution capacity deferral/peak shaving–Reliability enhancement–Voltage support and control (relates to distributed generation integration)

CB S

Substation

Battery energy storage

CB

VoltageRegulator

Substation

Voltage Controlled

Bus

S

Page 31: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Substation

Voltage Controlled

Bus

Feeder 1

Feeder 2

Feeder 4

Feeder 3.

Opt 1:Addition of Extra Capacity

Opt 2: Install Energy Storage

Capacity Deferral/Peak Shaving• Small capacity/duration

increase needed• Use energy storage instead of

significant substation/circuit upgrade

• Energy storage can also be used for monthly peak shaving

0

5,000

10,000

15,000

20,000

25,000

00:00 04:00 08:00 12:00 16:00 20:00 00:00

kW

Summer Peak Day

No ES With ES

Capacity Limit: 20 MVA

Page 32: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Capacity Deferral/Peak Shaving Approach

Setup Feeders

Hourly load shapes for each feeder

Load growth every year

ES Sizing and Control

Solve for added ES kW needed at each year

Calculate optimal monthly peak shaving settings for each year

Estimate Cost & Benefits

ES annual cost

Deferral benefits

Additional peak shaving benefits

Sensitivity analysis

Page 33: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Data and Assumptions

[1] Anderson Hoke, Randomized Hourly Load Data for use with Taxonomy Distribution Feeders, https://catalog.data.gov/dataset/randomized-hourly-load-data-for-use-with-taxonomy-distribution-feeders[2] Jim Eyer, Garth Corey, SAND2010-0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide[3] GTM, NYSERDA and Mckinsey[4] Duke Energy Rate, Large General Services, Schedule LGS-50

Feeder Simulation

Annual Load Curve Hourly from NREL [1]

Capacity 20 MVA

Number of Feeders 4

Load Growth Rate 1%

Coincident Peak (yr.1-10) 20.3 MW – 22.2 MW

Energy Storage Added in 500kW block

Energy Storage (Li-ion 4 hr.) [3]

Cost ($/kWh) 525 (200 for 2030)

O&M Cost 10 $/kW/yr.

Life 10 Years

Round trip efficiency 85%

Self discharge 5% (24 hr.)

Loan Rate 6%

Electricity Rate [4]

Demand Charge $ 11/kW

Energy Cost for ES Operation Losses $ 55/MWh

Deferral Benefits

T&D installed Cost 150 $/kVA [2]

Upgrade Option Add Substation Capacity in 10 MVA

Fixed Charge Rate 11%

Page 34: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Preliminary Results

Cost Benefit Analysis Unit $/kW-yr.

Benefit 130 - Deferral 66

- Deferral Peak Shaving 4

- Added Peak Shaving 60

Cost (2018) 170 Net (2018) -39Cost (2030) 68 Net (2030) 62

0

500

1,000

1 2 3 4 5 6 7 8 9 10

ES KW Needed for Every Year

$(800,000)

$(600,000)

$(400,000)

$(200,000)

$-

$200,000

$400,000

$600,000

1 2 3 4 5 6 7 8 9 10

Cost and Benefits By Year

Energy Storage O&MDeferral Deferral Peak ShavingAdded Peak Shaving

1 311 11

15

050

100150200250300350400

1 2 3 4 5 6 7 8 9 10

Energy Storage Operation Hours

Discharge Hr (Deferral Only) Discharge Hr (Add Peak Shaving)

Page 35: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

C S S S

Substation

400 customer 300 customer 200 customer 100 customer

OH 8 miles

Distribution Reliability

Assume no alternative back feed source

SS

Page 36: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Reliability Enhancement• Distribution Circuit Model

ES LocationFaults on …

Feeder Backbone Laterals

End of the feeder X

Along the feeder X

Customers X X

Compare to: Line upgrade to

reduce failure rate Backup generator

C S S S

SubstationEnergy storage

unit size 1MW,4MWh

Energy storage unit size

250kW,1000kWh

Energy storageunit size

100kW,400kWh400 customer 300 customer 200 customer 100 customer

Page 37: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Reliability Enhancement ApproachSize the ES

Needed

Apply load curve

Contingency analysis

Number of ES units placed

Calculate Reliability

Indices Improvement

SAIFI*

SAIDI*

Estimate Cost & Benefits

Cost for ES, line upgrade and backup generator

Avoided cost of interruptions

Sensitivity analysis

*System Average Interruption Frequency Index (SAIFI): Total number of sustained (>5 minutes)customer interruptions / Total number of customers served*System Average Interruption Duration Index (SAIDI): customer interruption duration (minutes) / Total number of customers served

Page 38: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Reliability Data and Assumptions

[1] Anderson Hoke, Randomized Hourly Load Data for use with Taxonomy Distribution Feeders, https://catalog.data.gov/dataset/randomized-hourly-load-data-for-use-with-taxonomy-distribution-feeders[2] Power/Forward Carolinas, Executive Technical Overview, Duke Energy, November 2017[3] Understanding the Cost of Power Interruptions to U.S. Electricity Consumers, LBNL, 2004[4] GENERAC, Home backup generator sizing calculator, http://www.generac.com/for-homeowners/home-backup-power/build-your-generator[5] Compare Commercial Generator Prices – Buyers Guide 2018, https://priceithere.com/commercial-generator-prices/

Feeder Simulation

Annual Load Curve Hourly from NREL [1]

Circuit Length 8 miles

# of Customers 1000

SAIFI Target 1.5 interrupt/customer [2]

SAIDI Target 150 minutes/customer [2]

Initial Index [SAIFI, SAIDI] = [2, 8 hrs.]

OH failure rate 0.5-0.8 /mile-yr. [2]

UG failure rate 0.03 – 0.2/mile-yr. [2]

Backup Generator Cost

Residential (10-20 kW) $300/kW [4]

Commercial(20-150 kW) $280/kW [5]

Installation $2000 – 8000 [4]

Cost of Interrupted Power [3]

Duration Residential Commercial Industrial

0 sec $2.18 $605 $1,893

1 hour $2.7 $886 $3,253

Sustained Interruption $2.99 $1067 $4,227

Feeder Conversion Cost [2]

OH to UG $400k – 500k/mile

Page 39: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Voltage Support and Control for PV

• Distribution Circuit Model

0.99

1

1.01

1.02

1.03

1.04

1.05

1.06

Voltage at Interconnection

Volt No ES Voltage with ES-3500-3000-2500-2000-1500-1000-500

0500

10001500

ES and PV Profile

ES PV

ANSI Limit: 1.05

Top of the Feeder Power

Power With ES Power No ES

Charge During PV

Peak Shaving

Substation

Voltage Controlled

Bus

Feeder

CircuitBreaker

PV

Page 40: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Voltage Support and Control Approach

Setup Model

Energy storage control + PV Case

Distribution feeder upgrades to accommodate PV

Power Flow Analysis

Analyze additional PV could be added

Quantify peak demand decrease

Quantify energy and loss reduction

Estimate Cost & Benefits

Cost for each case

Increase PV benefits

Avoided demand and energy cost

Sensitivity analysis

Page 41: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Voltage Support Data and Assumptions

[1] Anderson Hoke, Randomized Hourly Load Data for use with Taxonomy Distribution Feeders, https://catalog.data.gov/dataset/randomized-hourly-load-data-for-use-with-taxonomy-distribution-feeders[2] NREL, NSRDB, https://maps.nrel.gov/[3] NREL, The Cost of Distribution System Upgrades to Accommodate Increasing Penetration of Distributed Photovoltaic Systems on Real Feeders in the United States, April 2018[4] Duke Energy Rate, Large General Services, Schedule LGS-50

Feeder Simulation

Annual Load Curve Hourly from NREL [1]

PV data NREL NSRDB [2]

Feeder Length 6 miles

K factor 477 - 4/0 Conductor(%VD/kVA-mile)

0.03% - 0.055% (12.5 kV)0.009% - 0.011% (23 kV)

Load Level 5 MW/ 10 MW

Voltage Level 12.5 kV/ 23 kV

Distribution Line Re-conductor Cost [3]

Low $ 200 k/mile

Medium $ 400 k/mile

High $ 600 k/mile

Electricity Rate [4]

Demand Charge $ 11/kW

Energy Cost for ES Operation Losses $ 55/MWh

Page 42: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Still to Come• Improve the capacity deferral case based on feedback• Add sensitivity analysis to the capacity deferral study

• Complete the reliability enhancement analysis• Complete the voltage support analysis

• Final VBA-enabled Excel spreadsheet that can be customized for future use

Page 43: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

NC Energy Storage Study

Transmission ServicesDavid MulcahyDanny Sodano

Stakeholder MeetingOctober 2, 2018

Page 44: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Analysis Scope

• Transmission services fall into two categories:

– Transmission Investment Avoidance

– Transmission Congestion Relief

Page 45: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Transmission Investment Deferral

Page 46: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Transmission Deferral/AvoidanceService:

• Energy storage can be an alternative to address reliability issues which might otherwise require transmission build out

Benefit : Avoid transmission investment for reliability or economics

ESS Utilization: •ESS can be used to supplement reliability or contingency issues

• Enabling non-spinning resources for contingency response• Avoid congestion during contingency events • Reduce element overload

•Can be alternative to economic transmission investment.

46

Page 47: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Energy Storage as Alternative to Transmission

• Planning reliability requirements drive transmission investment

• Transmission expansion is system specific and difficult to compare from other studies beyond simple avoided cost factors

• Therefore, ESS’s value comes as alternativeto otherwise required transmission builds.

47

Page 48: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Compared to Proposed Projects

• Proposed projects from NC Transmission Planning Collaborative (NCTPC) and NC IRPs– NCTPC plan outlines why transmission is required– Can storage help mitigate any of the current issues?

• Without detailed power flow models or load forecasts, limited to simple calculations and determining if energy storage has any potential to mitigate reliability issue

• Examined current proposed projects and evaluate applicability of storage at high level and include more qualitative analysis

48

Page 49: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Criteria for Applicability

Potentially Applicable:• Line Capacity Violations• Low voltage• Double circuit

Not Applicable:• Reactive Support• Generator interconnection

Transmission projects are in response to contingency events in forecasted operating

conditions

Page 50: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Preliminary Results

Applicability of ESS to current transmission projects• Total potential as high as $283m

• Scale of investment is significant

• ESS should be considered as alternative to transmission for reliability

Note: Only shows upper bound to value. Does not show benefit nor sizing of ESS to projects

ESS Alternative Potential

Number of Projects Cost ($M)

No 4 142

Potential 11 283

Total 15 425

Page 51: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Next Steps and Future Work

Next steps:• Finalize classification and description of projects

Potential future work:• Include ESS in power flow model of contingencies

• Examine use cases of storage related to frequency and duration of contingency events

Page 52: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Transmission Congestion Relief

Page 53: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Transmission Congestion ReliefService:

• Energy storage can reduce transmission congestion during constrained periods

Benefits: •Allows cheaper generators to operate more•Lowers risk of line overloads•Potential alternative to economic transmission investment

ESS Utilization:•Charges when marginal generator is cheap•Discharges during congestion period •Allows cheaper generators to have higher capacity factor 53

Page 54: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Congestion Approach

Develop Supply Curve

• Use unit-level generator data from public sources

• Assume merit order for supply curve

Identify Congestion

• Compare hourly generation to merit order supply curve

• Identify hours with significant deviation in commitment from merit order

Calculate value

• Calculate avoided operational cost from storage

• Identify generator locations where storage has value

Page 55: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Method Assumptions

Avoided Cost of Congestion ($)

For hours with congestion:

• Calculate value of storage comes from the operational cost saved by dispatching cheaper generators

• Compare to cost of energy storage system located near constrained generators

Page 56: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Publicly Available Data Sources

Generator Data:

Source: EIA-860 Form Data

Includes: Operational units, nameplate capacities, and locations

Hourly Operation:

Source: U.S. EPA Air Markets Program Data

Operational data limited to thermal generators subject to emission reporting requirements

Page 57: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Method for Calculation1. Rank merit order by annual Capacity Factor (CF)

2. Determine committed generators at each hours

3. Find marginal generator (highest rank by CF)

4. Determine which generators are out of order

Page 58: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Preliminary Results

• Developed supply curve based on generator operation

• Many generators are operating frequently out of merit order based on annual CF

• Need to examine causes, frequency and verify results for these generators

Page 59: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Next Steps

• Establish marginal/operational costs of generators

• Examine if reason other than congestion is reason for out of merit order

• Use data longer timeframe (beyond 2017 data)

• Estimate sizing of ESS to determine cost for improvements

Page 60: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

NC Energy Storage Study

Generation Peak Capacity Deferral & Bulk Energy Time-shifting

Anderson R. de QueirozJoseph F. DeCarolisJeremiah X. Johnson

Dustin SoutendijkDanny Sodano

Stakeholder MeetingOctober 2, 2018

Page 61: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Introduction

• The overall goal is to evaluate how storage can contribute to Generation/Resource Adequacy, more specifically:

–Peak Capacity Deferral • How storage can contribute to postpone investments in generation

–Bulk Energy Time Shifting• How storage can contribute to better economic generation resources

Page 62: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Storage Technologies to be Considered

Mechanical • Flywheels• Pumped storage• Compressed Air

Electrochemical • Lithium-ion batteries• Lead-acid batteries• High T sodium batteries• Flow batteries

Chemical• H2 electrolysis + storage

+ fuel cells

Thermal• Chilled water• Ice storage• Phase change materials• Water heaters

Electrical • Supercapacitors• Superconducting

magnetic energy storage

Page 63: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Peak Capacity Deferral

• A spreadsheet calculation is developed first to estimate the break-even cost associated with a Li-ion battery

• Some simple assumptions: –1 MW, Natural Gas CT plant cost: $900/kW–Variable Operations & Maintenance (VOM) costs: $3/MWh–Natural Gas price: $4/MMBtu–Heat Rate: 6.5-11 MMBtu/MWh–1 MW, 4 MWh Li-ion Cost: $2100/kW–WACC: 10%–Technology Lifetime: 20 year lifetime for both

• Compare Cost of New Entry (CONE) and operating costs of both technologies at various capacity factors

Page 64: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Peak Capacity Deferral

• A battery needs a CF of 0.31 or more to be more cost-effective

• When used only for this application, the CONE of the Li-ion battery needs to be $96.6/kW-yr lower to be more cost-effective at CF of 0.1*CF proportional to battery MWh throughput

More rigorous results to come from additional modeling

• Benefit from charging with more efficient electricity (HR 6.5 vs 11)• Off peak → 3.5 ¢/kWh and Peak → 4.4 ¢/kWh

Page 65: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Analysis Scenarios

1. Base case

2. Duke IRP

3. Expanded RPS

4. Clean Energy Standard

5. Carbon Cap

6. Natural Gas Prices

7. Deployment of Residential Solar PV

8. Deployment of Plug-in Electric Vehicles

• 2017 Carolinas Power generation system• HB589 solar PV deployments• Fixed representation of the exchanges

• RPS expanded to 2030 with a target of 40% for renewables (solar, wind, biomass, small hydro)

• 60% target of clean energy sources by 2030

• Duke’s 2017 Climate Report to Shareholders: 40% reduction in 2005 CO2 emissions levels by 2030

• High and Low Projections from EIA AEO 2018

• Scenario matches the build-outs proposed by Duke’s 2018 IRP

Page 66: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Analysis scenarios … TEMOA run

(Capacity Expansion) …

Determine build out plans for the system

…*No energy storage is

considered in the initial operational dispatch runs

• hourly operations• operational marginal

prices [$/MWh]TEMOA run

(Operational Dispatch)

1 3 5 7 9 11 13 15 17 19 21 23

MW

Hour of Day

Nuke Coal Gas RE

0

10

20

30

40

50

1 3 5 7 9 11 13 15 17 19 21 23Mar

gina

l Pric

e ($

/MW

h)

Hour of the Day

Introduce Energy Storage

*Assume a fixed duration (energy to power ratio) and efficiency

• Run different storage-size configurations

• Determine cost-optimal build plan for storage

• Minimize operational costs with storage

• Calculate change in production costs [$/year]

Run sensitivities- Load- Storage costs- Storage efficiency

Approach, Data and Assumptions

Page 67: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Carolinas

25,606 MW actual demand

Data & Assumptions• System representation:

• Existing power generators represented as individual power plants• Future generators grouped by their respective generation class

• Sources:

Power Interchanges

EIA Annual Electric Generator data, form EIA-860EIA electric utility data survey, form EIA-923EIA's U.S. Electric System Operating Data Tool NREL Annual Technology Baseline - ATBNREL Solar and Wind Energy Resource Assessment - SWERA

19412 MW avg demand (2017)

Page 68: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

05

10152025303540455055606570

2017 2020 2025 2030

Inst

alle

d C

apac

ity [G

W]

Base Case - Installed Capacity [GW]

Energy EfficiencySolar PVBiomass - STLandfill Gas - Int. G.Landfill Gas - GTDieselNatural Gas - CCNatural Gas - CTHydro - PSHHydroCoal - STNuclear

Solar PV to reach 16.6 GW from 3.6 GW in the existing system

2.1 [GW]

Page 69: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

05

1015202530354045505560657075

BaseCase

DukeIRP

E-REPS CESTD CO2cap NG-L NG-H

Inst

alle

d C

apac

ity [G

W]

Base Case – 2030 Installed Capacity [GW]

Energy EfficiencySolar PVBiomass - STLandfill Gas - Int. G.Landfill Gas - GTDieselNatural Gas - CCNatural Gas - CTHydro - PSHHydroCoal - STNuclear

0.36 [GW]

6.8 [GW]

4.24 [GW]

2.03 [GW]

5.5 [GW]

0.29 [GW]

2.5 [GW]

Page 70: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Next Steps

• Finish the Operational model runs–We already a working model for the operational runs–Runtime: About 30 minutes of computing time in a cluster to run one year for 8760 hours

• Include energy storage and re-run Operational Models–Obtain hourly operations–Operational Marginal costs

• Compute benefits–Peak generation deferral–Bulk energy time shifting

Page 71: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Future Research• This is the first comprehensive open source modeling effort

to develop projections for the Carolinas power system• It can be used to assess economic, technical, and policy

futures and provide valuable insights to decision makers• Model and analyze other scenarios, e.g.:

–Bidirectional capabilities for EVs–100% of clean energy–Wider range of future fuel prices–Policies under consideration

• Analyze storage deployment directly in the capacity expansion model

Page 72: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

NC Energy Storage Study:Frequency Regulation Services

Professor Ning Lu and Yao Meng

Electrical and Computer Engineering Department

North Carolina State University

Page 73: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Regulation Service• Regulation services: balances generation and load in real-time to maintain

system frequency and tie-line power flows at the scheduled values.

• Inputs: Area Control Error(ACE) and Tie-line Flow Deviations.

• Signal resolution: 2-10 seconds

• Characteristics: mostly energy neutral, random in magnitude (very hard to forecast)

0 50 100

Time of the day(hr)

-400

-200

0

200

400

AC

E(M

W)

-400 -200 0 200 400

ACE Signal(MW)

0

0.02

0.04

0.06

0.08

0.1

Pro

babili

ty o

f O

ccurr

ence

NY-ISO ACE signal of June,2017 and its probability density function

Page 74: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Energy Storage for Regulation Service

Advantages

Energy storage systems are controlled by power electronics.

Excellent controllability allows them to follow regulation signals precisely.

1. Reduce the wear-and-tear of the traditional generators2. Reduce the amount of required regulation capacity3. Improve the quality of regulation services

Page 75: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

• Energy storage systems have energy limits. When regulation signals have significant DC components, energy storage devices will soon be fully charged/discharged

• Three approaches to deal with this issue

─ Design energy-neutral frequency regulation signal─ Design operation strategy to maintain the state-of-charge(SOC) levels─ Allow storage to adjust its committed regulation services in a shorter interval• The first method has been implemented by PJM and ISO-NE. Fast regulation signal: Applying a

high-pass filter to the AGC signal. • Signals with a fast ramping rate but energy neutral.

Technical Challenges

Page 76: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Enabling Factors

0 10 20 30 40 50 60

Time(mins)

-1

-0.5

0

0.5

1

Regu

lation

Sign

al

One hour PJM RegD signal

0 10 20 30 40 50 60

Time(mins)

-1

-0.5

0

0.5

1

Reug

lation

Sign

al

One hour NY-ISO regulation signal

Design Considerations: FERC Order 784 requires the improvement of signal design considering the state of charge constraint of energy storage system

Monetary Incentives: FERC Order 755 requires the implementation of pay-for-performance regulation market

PDF of PJM RegD

-1 -0.5 0 0.5 1

Hourly Energy Bias(MWh)

0

0.02

0.04

0.06

0.08

0.1

0.12

Prob

abilit

y of

Occ

urre

nce

PDF of PJM RegA

-1 -0.5 0 0.5 1

Hourly Energy Bias(MWh)

0

0.1

0.2

0.3

0.4

Prob

abilit

y of

Occ

urre

nce energy neutral

Page 77: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Pay-for-performance Market Mechanism

Regulation capacity: participating resource will be rewarded by the bidding capacity 𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏

𝑟𝑟𝑟𝑟𝑟𝑟, unit: $/MWh. Regulation-up and regulation down signals have the same power limit except in the CASIO control area

Regulation mileage 𝑴𝑴: the sum of the absolute values of the regulation control signal movements, unit $/∆MW, 𝑃𝑃𝑡𝑡

𝑟𝑟𝑟𝑟𝑟𝑟 is the power output of a regulation unit at 𝑡𝑡

Performance factor 𝝀𝝀: A value between 0 and 1, represent the response accuracy with respect to the regulation instructions. A general penalization format is as follows:

Payment = 𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏𝑟𝑟𝑟𝑟𝑟𝑟(ρ𝑐𝑐 + 𝛌𝛌Mρ𝑀𝑀)

where ρ𝑐𝑐, ρ𝑀𝑀 are capacity clearing price and mileage clearing price, respectively. In this analysis, we assume 𝜆𝜆 = 1.

𝑀𝑀 = �0

𝑇𝑇𝑃𝑃𝑡𝑡𝑟𝑟𝑟𝑟𝑟𝑟 − 𝑃𝑃𝑡𝑡−1

𝑟𝑟𝑟𝑟𝑟𝑟

𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏𝑟𝑟𝑟𝑟𝑟𝑟

Page 78: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Regulation Mileage

0 100 200 300 400 500 600 700 800 900 1000

Time Step

-5

-101

5

10

20

MW

regulation mileagepower outputreg-up capacity

reg-down capacity

Payment = 𝑷𝑷𝒃𝒃𝒃𝒃𝒃𝒃𝒓𝒓𝒓𝒓𝒓𝒓(ρ𝑐𝑐 + 𝛌𝛌𝑴𝑴ρ𝑀𝑀)

𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏𝑟𝑟𝑟𝑟𝑟𝑟 = ±1 𝑀𝑀𝑀𝑀

Mileage 𝑴𝑴

𝑀𝑀 = �0

𝑇𝑇𝑃𝑃𝑡𝑡𝑟𝑟𝑟𝑟𝑟𝑟 − 𝑃𝑃𝑡𝑡−1

𝑟𝑟𝑟𝑟𝑟𝑟

𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏𝑟𝑟𝑟𝑟𝑟𝑟

Page 79: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Modeling of Energy Storage Devices

Page 80: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Energy Storage Models

Modeling Parameters

𝐸𝐸𝑡𝑡 − 𝐸𝐸𝑡𝑡−1 = ∆𝑡𝑡𝜂𝜂𝑐𝑐𝑃𝑃𝑡𝑡𝑅𝑅𝑟𝑟𝑟𝑟𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅 − ∆𝑡𝑡𝜂𝜂𝑏𝑏𝑃𝑃𝑡𝑡

𝑅𝑅𝑟𝑟𝑟𝑟𝑅𝑅𝑅𝑅 − ∆𝑡𝑡𝑃𝑃𝑡𝑡𝑆𝑆𝑟𝑟𝑆𝑆𝑆𝑆𝑅𝑅𝑏𝑏𝑆𝑆𝑐𝑐

Discharged energy

Charging energy

Self-discharged energy

discharging efficiencycharging efficiency

self-discharging rate

0 ≤ 𝑃𝑃𝑡𝑡𝑅𝑅𝑟𝑟𝑟𝑟𝑅𝑅𝑅𝑅𝑅𝑅𝑅𝑅 ≤ 𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏

𝑟𝑟𝑟𝑟𝑟𝑟

0 ≤ −𝑃𝑃𝑡𝑡𝑅𝑅𝑟𝑟𝑟𝑟𝑅𝑅𝑅𝑅≤ 𝑃𝑃𝑏𝑏𝑏𝑏𝑏𝑏

𝑟𝑟𝑟𝑟𝑟𝑟

𝐸𝐸𝐿𝐿𝑅𝑅𝑅𝑅𝑟𝑟𝑟𝑟𝑆𝑆𝑏𝑏𝐿𝐿 ≤ 𝐸𝐸𝑡𝑡 ≤ 𝐸𝐸𝑅𝑅𝑅𝑅𝑅𝑅𝑟𝑟𝑟𝑟𝑆𝑆𝑏𝑏𝐿𝐿

Page 81: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

• Start-up nor shut-down costs are not considered• Actual annual revenue for year 2017 is calculated and we assume that the same revenue is

received over the entire lifetime.• Revenue includes two payments: mileages and capacity• Cost includes installation and O&M cost• NPV (Net Present Value) is calculated assuming the discount rate is 10%

Cost-benefit Study Models

𝑅𝑅 = 𝑅𝑅𝐿𝐿𝑏𝑏𝑆𝑆𝑟𝑟𝑚𝑚𝑟𝑟𝑟𝑟 + 𝑅𝑅𝑐𝑐𝑚𝑚𝑅𝑅𝑚𝑚𝑐𝑐𝑏𝑏𝑡𝑡𝑐𝑐

𝐶𝐶 = 𝐶𝐶𝑏𝑏𝑅𝑅𝑆𝑆𝑡𝑡𝑚𝑚𝑆𝑆𝑆𝑆 + 𝐶𝐶𝑂𝑂&𝑀𝑀

𝑁𝑁𝑃𝑃𝑁𝑁 = �𝑏𝑏=1

𝑁𝑁𝑁𝑁 𝑖𝑖

1 + 𝑟𝑟 𝑏𝑏

𝑷𝑷𝒓𝒓𝑷𝑷𝑷𝑷𝒃𝒃𝑷𝑷 = 𝑁𝑁𝑃𝑃𝑁𝑁𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑟𝑅𝑅𝑟𝑟𝑟𝑟 − 𝑁𝑁𝑃𝑃𝑁𝑁𝑐𝑐𝑅𝑅𝑆𝑆𝑡𝑡

Revenue

Cost-of-service

Net Present Value

Page 82: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

• Lifetime of a battery storage system can be estimated based on how many charging/discharging cycles it has completed at different depth of discharge(DOD)

• Rain-flow algorithm is used for estimating battery lifetime depreciation• The flywheel lifetime is assumed to be constant

Battery Lifetime Estimation Methods

20 30 40 50 60 70 80 90 100

Depth of discharge(%)

0

0.5

1

1.5

2

Num

ber o

f cyc

les

10 4

FlywheelBattery High

Battery Low

Page 83: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Two Types of Services MechanismOne directional service: Energy storage system only takes “up” signal when discharging, while only taking “down” signal when charging

Page 84: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Two Types of Services MechanismTwo directional service: Energy storage system can take both “up” and “down” signal when possible.

Page 85: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Performance CriterionTo evaluate the accuracy of following regulation signals, we calculated response rate as:

𝑅𝑅𝑅𝑅 =𝑛𝑛𝑆𝑆𝑟𝑟𝑆𝑆𝑆𝑆𝑏𝑏𝑆𝑆𝑆𝑆𝑟𝑟𝑏𝑏𝑛𝑛𝑡𝑡𝑅𝑅𝑡𝑡𝑚𝑚𝑆𝑆

× 100%

where 𝑛𝑛𝑆𝑆𝑟𝑟𝑆𝑆𝑆𝑆𝑏𝑏𝑆𝑆𝑆𝑆𝑟𝑟𝑏𝑏 is the number of regulation signals fully following by the ESS and 𝑛𝑛𝑡𝑡𝑅𝑅𝑡𝑡𝑚𝑚𝑆𝑆 is the total number of regulation signals.

To evaluate the lifetime depreciation when providing regulation services, we calculated the aging ratioas:

𝐴𝐴 =𝐿𝐿𝑏𝑏𝑟𝑟𝑆𝑆𝑚𝑚𝑟𝑟𝑆𝑆𝑡𝑡 − 𝐿𝐿𝑟𝑟𝑟𝑟𝐿𝐿𝑚𝑚𝑏𝑏𝑅𝑅

𝐿𝐿𝑏𝑏𝑟𝑟𝑆𝑆𝑚𝑚𝑟𝑟𝑆𝑆𝑡𝑡× 100%

where 𝐿𝐿𝑏𝑏𝑟𝑟𝑆𝑆𝑚𝑚𝑟𝑟𝑆𝑆𝑡𝑡 is the default lifetime of battery, 𝐿𝐿𝑟𝑟𝑟𝑟𝐿𝐿𝑚𝑚𝑏𝑏𝑅𝑅 is the remaining lifetime after certain period of service estimated by rain-flow algorithm.

Page 86: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Simulation Setup• Regulation signals and the corresponding price data were

downloaded from PJM and NY-ISO website, the data was collected from January 1, 2017 to December 31, 2017

• Designed lifetime of Li-ion battery is 10 years, while the designed lifetime of flywheel is 21 years

• The power and energy rating of Li-ion battery and flywheel is 1MW and 0.5 MWh, respectively

• Cost Parameters

Page 87: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Results

Page 88: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Results Summary: Service Quality & Lifetime

1. Regulation signal design makes a significant difference.2. When providing regulation services, battery lifetimes are shortened. 3. When providing RegD services, battery lifetimes can be further shortened but not by much. 4. When providing 1-directional services, battery lifetimes can be prolonged.5. As the flywheel can cycle as many times at low DOD as at high DODs, its lifetime is not affected by providing

the regulation services.

Page 89: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

NY RegD RegA RegD+RegA

Regulation Signal

0

1000

2000

3000

Rev

enue

($)

Comparison of daily revenue

NY RegD RegA RegD+RegA

Regulation Signal

40

60

80

100

Res

pons

e R

ate(

%)

Comparison of daily response rate

NY RegD RegA RegD+RegA

Regulation Signal

0.5

1

1.5

2

2.5

Agi

ng C

ost(

%)

Comparison of lifetime depreciate

Page 90: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

NY RegA RegD

Regulation Signal

-100

0

100

200

300

Annu

al P

rofit

($/k

Wyr

)

0.5hr

2hr

4hr

Profits comparison of different ESS technologies

Profits comparison of different battery sizesA larger size battery has a longer service life. When supplying RegD, the service life are 3.8, 5.5, 13.5 years for 0.5, 2 and 4 hours battery, respectively.

1-directional 2-directional

PJM RegD

0

200

400

600

800

Annu

al P

rofit

($/k

Wyr

)

Battery

Battery-2030

Flywheel

Now

Future

Flywheel

Now

Future

Flywheel

0.5

2 4

0.52 4

0.52 4

Page 91: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

What to come

• We have finished the following comparisons–Regular regulation signals v.s. storage-friendly signals–1-directional v.s. 2-directional services–Regional differences (PJM v.s. NYISO)–Different battery sizes–energy storage technologies (Li-ion Battery v.s. Flywheel; lifetime sensitive to DOD v.s. lifetime not sensitive to DOD)

• What to come–Market-based v.s. non-market based regulation services

• Need signals from non-market based systems–different energy storage control algorithms

• Optimize energy storage operation • Stack the regulation service with other type of services

Page 92: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

NC Energy Storage Study

Energy Storage to Reduce Solar ClippingJeremiah Johnson

Stakeholder MeetingOctober 2, 2018

Page 93: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Background• Solar photovoltaics use invertors to convert DC generation to AC

generation.• You can reduce inverter costs by “undersizing” to yield reductions in

delivered energy cost. This results in “clipping.”• Energy storage can reduce clipping and allow for higher invertor

utilization.

02468

101214

0:00

2:00

4:00

6:00

8:00

10:0

012

:00

14:0

016

:00

18:0

020

:00

22:0

0

Sola

r G

ener

atio

n M

W

Unclipped GenerationClipped

02468

101214

0:00

2:00

4:00

6:00

8:00

10:0

012

:00

14:0

016

:00

18:0

020

:00

22:0

0

Sola

r Gen

erat

ion

MW

ClippingDischarged from ESUnclipped generation

Page 94: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Approach, Data and Assumptions

• In this analysis, we will ultimately use solar resource data at a 1-minute resolution provided by Strata (under NDA).

• We assume crystalline silicon modules and test two configurations: south-facing fixed tilt at 20 degrees and single axis tracking (with the axis running north-south).

• The PV array DC output is calculated using the California Energy Commission performance model in NREL’s System Advisor Model with the Nominal Operating Cell Temperature (NOCT) method to estimate temperature impacts. We model inverter performance is modeling using an empirical method from Sandia National Laboratory.

Solar Array Model Inverter Model

Energy Storage Operations

Potential DC Output

System AC Output

Clipping Losses

Solar Resource Data

Page 95: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Planned Scenarios/SensitivitiesParameter Values Considered DescriptionLocation Multiple, throughout state • Minute-level data for one year

Array Design 10 MWDC fixed tilt10 MWDC single axis tracking

• Fixed tilt at 20 degrees, south-facing• Single axis (north-south) tracking with

backtracking, +60 degree rotationDC/AC Ratio 1.2 to 2.0, in 0.1 increments • Rated inverter capacities range from 5

MWAC to 8.3 MWAC

Energy Storage Rated Capacity

0% to 100% of the difference between inverter rating and module nameplate rating, in 10% increments

• Ten rated power capacities will be considered for each DC/AC ratio

Energy Storage Duration

1 hour to 4 hours at rated power, in 1 hour increments

• The rated MWh of the energy storage system will be varied between one and four hours of discharge at the battery’s rated power

Page 96: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

0%5%

10%15%20%25%30%35%

1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2

DC/AC Ratio

• For now, this uses 1-minute resolution data from Oak Ridge National Lab.

• Fixed tilt (20°), due south• The AC Capacity Factor represents the utilization based on the

invertor’s rated capacity

Clipped solar

Preliminary Results: Solar Clipping vs. DC/AC RatioAC

Cap

acity

Fac

tor

Page 97: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

• 10 MWdc solar PV, 5 MWac system 2.0 DC/AC ratio• Experiences 2,400 MWh of clipping annually (16% of potential

generation)

Preliminary Results: Reducing Clipping Using Li-ion Batteries

-

400

800

1,200

1,600

2,000

1 2 3 4 5 6

Clip

ping

Red

uctio

n fr

om

Ener

gy S

tora

ge (M

Wh/

yr)

Energy Storage Duration (hr)

5 MW4 MW3 MW2 MW1 MW

Reduction in Solar Clipping

Page 98: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

- 100 200 300 400 500 600 700 800

1 2 3 4 5 6

Reve

nue

Requ

irem

ent t

o Su

ppor

t Sol

ar C

lippi

ng

($/M

Wh)

Energy Storage Duration (hr)

5 MW4 MW3 MW2 MW1 MW

1 2 3 4 5 6

Energy Storage Duration (hr)

5 MW4 MW3 MW2 MW1 MW

Preliminary Results: Revenue Requirement for Li-ion Batteries to Reduce Solar Clipping

2.0 DC/AC ratio, Solar data from Oak Ridge, TN; linear interpolation to estimate Li-ion costs for all capacities

Breakeven Value of “Saved” Solar2018

Breakeven Value of “Saved” Solar2030

Min cost = $320/MWh4 hour durationRecovers ~one-third of clipped solar

Min cost = $180/MWh4 hour durationRecovers ~one-third of clipped solar

Page 99: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

In the coming months…• Update analysis using 1-minute resolution solar resource

data for North Carolina• Conduct analysis for single-axis tracking solar• Synthesize the findings

• Consider varying value of time of day of generation

Potential future work…

Page 100: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

NC Energy Storage Study

Current Policy and Potential OptionsChristopher Galik

Christopher GambinoAutumn Proudlove

Stakeholder MeetingOctober 2, 2018

Page 101: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Analysis Scope

• What is the regulatory structure that governs storage in NC?

• What changes are possible to increase value of energy storage to North Carolina Consumers?

• Among the list of possible interventions, which are the most feasible/practicable, and what are the associated implications for storage?

Page 102: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Approach and Data• Analysis, R&D, and Market Support: R&D and storage deployment,

analysis like this, worker training programs, etc.• Planning and Access: Define, reform, or refine utility planning processes

and/or the rules affecting access to, e.g., data, state/wholesale markets. • Business Models and Rate Reform: Changing how utilities are regulated

or operate, targeted changes to rates (e.g., time-of-use, demand charges).• Mandates: Policies establishing minimum deployment targets or

performance standards.• Process and Approvals: Policies that govern the process for storage

deployment (e.g., interconnection standards, compensation rules).• Incentives and Financing: Provide funding to or defray the cost of the

deployment of storage (e.g., loans, tax credits, rebates, exemptions).• Utility-Driven Demonstrations and Deployment Programs: Utility-led

programs to purchase, fund, or deploy storage.

Page 103: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Approach and Data• Review of existing regulatory context consisted of:

–NCUC Rules, energy-related legislation (e.g., Senate Bill 3, House Bill 589), as well as the regulations, rate cases, settlements, rulemakings, and/or orders that emerged as a result. Also included are policies or provisions explicitly referencing storage issued by PJM regulators or Tennessee Valley Authority (TVA);

–Third-party news alerts, policy briefs, issue analyses, and summary reports to identify provisions that our initial scan may have missed;

–Anonymous survey distributed to the energy storage project stakeholder group.

Page 104: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Preliminary Results

• Analysis, R&D, and Market Support:–Possible relevance of $1M REPS cost-recovery provision for R&D.

• Planning and Access:–Under PJM, FERC Orders 841, 845, 784, 819, and 890 have direct to storage wholesale markets. Storage already eligible to participate in PJM ancillary service (Reg D) market.

Page 105: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Preliminary Results

• Planning and Access:–Rule R08-41 (Emergency Load Reduction Plans and Emergency Procedures) requires demonstration of black start capabilities, which could conceivably include storage.

–Rule R08-60 (Integrated Resource Plannings and Filings) Requires identification of load requirements and resource options, conceivably including storage. Also requires identification of implications of smart grid deployment on planning, within which storage is mentioned.

Page 106: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Preliminary Results

• Business Models and Rate Reform:–In its 2017 avoided cost ruling (Docket No. E-100, SUB 148), NCUC signaled an intention to refine avoided cost calculations so as to provide clearer signals to qualifying facilities to further facilitate the deployment of advanced solar or storage applications.

• Mandates:–No storage-specific mandates, but unclear if storage qualify for muni/co-op REPS compliance (i.e., DSM)

Page 107: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Preliminary Results

• Process and Approvals:–May 2015 interconnection standards (Docket No. E-100 Sub 101; storage may be connected under same process as other small generating facilities). Revisions to interconnection standards are ongoing, with multiple provisions related to storage being debated under the auspices of the proposed Competitive Procurement of Renewable Energy (CPRE) program;

–At the county and municipal level, decisions regarding contracting, zoning, compliance with fire codes, and decommissioning requirements are likely

Page 108: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Preliminary Results• Incentives and Financing:

–NA• Utility-Driven Demonstrations and Deployment Programs: In a

June 2018 settlement agreement that was ultimately rejected, DEC pledged to deploy at least 300 MW of storage by 5/26, with 200 MW of that by 5/23. By the 2021 IRP, DEC proposed to include methodology for including DERs and NWAs in integrated system operations planning (ISOP) processes.

• Initial filings under the CPRE program discussed a modified power purchase agreement (PPA) to allow for pre-inverter storage. Storage must be included as part of a renewable project (i.e., no apparent provision for stand-alone storage).

Page 109: NC Energy Storage Study · [2] Jim Eyer, Garth Corey, SAND2010 -0815, Energy Storage for the Electricity Grid: Benefits and Market Potential Assessment Guide [3] GTM, NYSERDA and

Still to Come

• Currently reviewing a database of policies, programs, regulations, proceedings, etc., related to storage as deployed in other states, RTOs (October-November).

• Pairing of policy options to analytical findings will be, by design, conducted near the conclusion of the study (November).