Nedbank Styldrift I Site Visit
9 November 2016
9 November 2016 – Nedbank Site Visit 2
BRPM JV location relative to neighbouring mines
9 November 2016 – Nedbank Site Visit 3
Mineral resources and reserves – 4E Moz
4.44(4.47g/t)
1.93(4.2g/t)
6.19(4.50g/t)
2.77(4.21g/t)
Merensky reserve classification
Proven Probable
5.83(3.87g/t)
1.40(3.65g/t)
UG2 reserve classification
Proven Probable
15.56(7.42g/t)
9.61(6.77g/t)
5.48(7.34g/t)
18.79(7.46g/t)
11.09(6.82g/t)
7.45(7.57g/t)
Merensky resource classification
Measured Indicated Inferred
BRPM JV
SD
8.09(5.07g/t)
9.51(4.99g/t)
3.58(5.13g/t)
15.87(5.22g/t)
12.08(4.99g/t)
5.03(4.95g/t)
UG2 resource classification
Measured Indicated Inferred
BRPM JV
SD
SD
BRPM JV
No SD UG2
resources
converted to
reserves
9 November 2016 – Nedbank Site Visit 4
Styldrift I Project
High quality
Merensky
• Shallow dip 40 - 60
• Resource grade of 6.94g/t 4E
• Resource of 72.90Mt
• LOM 30 years – Merensky only
Shallow Merensky
mine
• Twin vertical shaft system:
› 10.5mØ Main# - 758m deep
› 6.5mØ Services# - 723m deep
• Mean mining depth of 680m
Key operating
statistics
• Mechanised bord and pillar
• ±3100 employees - steady state
• 230ktpm – 2.7Mt/annum
• 4.33g/t 4E delivered grade
• 320koz 4E/annum in
concentrate
• 2020 steady state opex:
› 15% lower than BRPM
Production ramp up
• First ROM production Q3 2015
• Start of ramp-up Q1 2017
• 36 month ramp-up
• Steady state Q1 2020
High grade, long life Mechanised, low costShallow Near term
9 November 2016 – Nedbank Site Visit 5
Styldrift I – a brief history….
2009 2010 2011 2012 2013 2014 2015 YTD Q3 2016
• Site establishment
and commenced
with:
› Terrace bulk
earthworks
› Manufacture of
Main & Services
shaft winders
• Focus on placing of
long lead item
orders
• Bulk earthworks
completed
• Bulk civils
completed:
› Shaft collars
› Winder houses
› Headgear
foundations
• Pre-sink Main and
Services shafts
• Pre-sink completed
April
• Main and Services #
headgears erected
• Commenced with
main sink in July
› Main# 219m bc
› Service# 152m bc
• Shaft sinking on-
going
• 600L Merensky reef
intersection
achieved in August
• Commenced with
lateral
development
• Optimisation study
• Sinking progressed
to 708L on Main
and Services shafts
• 2,300m lateral
development
completed
• Commenced with
construction of key
surface
infrastructure
• Surface & U/G ore
handling
infrastructure
construction
• Primary &
secondary fleet
orders placed
• Commenced with
Main # equipping
• Start o/land belt
construction
• Sinking contract
terminated
• Main #
commissioned
• Surface silo’s
completed &
commissioned
• Vent # 1
completed
• Commenced with
250ktpm plant
• H2-2015 slow down
of construction
• Completed 250ktpm
in plant upgrade
• Silo 2 construction
completed
• 3.7km lateral
development
• Commenced with:
› Upfront Service#
equipping works
› Silo 3,4 & Settler1
preparation work
• 290kt ore delivered
@ 3.18g/t
Progressive CAPEX
R212 million
Progressive CAPEX
R689 million
Progressive CAPEX
R1 257 million
Progressive CAPEX
R1 883 millionProgressive CAPEX
R2 686 million
Progressive CAPEX
R3 818 million
Progressive CAPEX
R5 490 million
Progressive CAPEX
R6 086 million
9 November 2016 – Nedbank Site Visit
0.55 0.54
0.82
0.26
0.07 0.120.17 0.14 0.11 0.09
0.070.00
0.10
0.20
0.30
0.40
0.50
0.60
0.70
0.80
0.90
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020
SIFR
Zero Serious injuries in
7 Years
(20% YOY reduction)
6
Safety – LTIFR & SIFR
Safety
• Full compliance of Safety Strategy > YOY 20% improvement in SIFR and LTIFR
> Training programme on safety strategy
• Zero harm> People selection and assessment
> Tshwarelela Wall
• Road to resilience > Emotional Fitness (profiling as we employ)
> Knowledge: Anglo School of Mines & Standard Testing
> Technology: PDS, VDS, TRAKA key control system, CAS (Collision
avoidance system), Electronic explosives key control, CCTV monitoring,
LHD Camera
Health
• Annual percentage hearing loss difference <2.5%
• ZERO TB deaths for persons on the RBPlat TB program
• Contractors onto Platinum Health medical aid
Environment
• Improved closure action plan
• No overflow of any polluted water into the natural
environment
• Obtain ISO 14001 certification at Styldrift
0.66
1.17
1.64
0.76
0.53 0.60
0.35 0.28 0.22 0.18 0.14
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
1.80
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
LTIFR
Zero Harm in 7 Years
(20% YOY reduction)
9 November 2016 – Nedbank Site Visit 7
ZERO Harm & Road to Resilience
Tshwarelela Wall SILO Station CAS System
9 November 2016 – Nedbank Site Visit 8
General shaft and level layout
Shaft bottom ramp
708 Level – Shaft Loading and Pumping level
Silos (2x Merensky, 1x Waste & 1x UG2)
Main shaft – Ø10.5m
Services shaft – Ø6.5m
642 Level – Top of silos and Section Ore
Handling
600 Level – Main Production level (on-
reef)
Settlers
Vent shaft No.1
9 November 2016 – Nedbank Site Visit 9
Post slow down progress to date
• 9 Mining production crews:
› 600 level = 4 x development and 2 x stoping
crews
› 642 level = 2 x development crews
› 708 level = 1 x development crew
• 3 Mining production construction crews
• 4 Infrastructure construction crews
› Services shaft equipping
› Silo construction
› Settler construction
Two sections
pre-established
West
Two sections
pre-established
East
Services # Trackless Workshops
Main #
Vent #
No.3
Vent # No.1
LEGEND
Mined Out − Sept 2015
Progress Sept’15-Sept’16
Remaining
Key production stats:
• 290kt ore delivered to concentrator
YTD
• 3.7km of development completed YTD
• 354kt ore delivered since Aug 2015
• 4.8km development completed post
Aug 2015
Mining and construction continue to progress steadily and remain aligned with our revised construction programme – commence ramp-up Q1 2017
9 November 2016 – Nedbank Site Visit
0 2 4 6 8 10 12 14 16
-160
-150
-140
-130
-120
-110
-100
-90
-80
-70
-60
-50
-40
-30
-20
-10
0
10
20
30
40
50
60
70
80
90
100
110
120
130
140
4E (g/t)
Sam
pling r
ange
Mining Cut : 210cm
MRM Evaluation : 4.20 g/t (60 Sections)
Resource Model : 4.10 g/t
10
Grade reconciliation – face samples vs. resource model
9 November 2016 – Nedbank Site Visit 11
Styldrift I - 150ktpm ramp-up strategy
Execution risk mitigation strategies
• Early adoption and implementation of technology - CAS
• Focus on asset creation efficiency
• Optimised designs – workshops, bulkheads and twin declines
• Improve operational efficiency by “de-coupling” management structures related to infrastructure development/construction and ramp-up
• Create ore-handling flexibility through the introduction of dump trucks during the construction of Silo 3 and 4
Underground Infrastructure
• 600 Level
> Stores
> Trackless workshops (32 mined, 24 equipped)
> Ancillary workshops (fuel bays, tyre bays, wash bays etc.)
> Extend on-reef declines to establish 12 sections (8 stoping and 4
spare IMS)
> Vent shafts No.2 and 3
• 642 Level
> Access and develop twin declines North and South
> Level ore handling infrastructure (section ore-pass installations,
decline conveyor and top of silo construction)
> Access and establish East declines
• 708 Level
> Water handling infrastructure
> Shaft ore handling infrastructure
Surface Infrastructure
• Complete 250ktpm concentrator upgrade – “Dry scope”
> ROM ore silo
> Crusher and mill silo feed conveyors
• Overland belt to BRPM concentrator complex
All key LOM infrastructure installed and commissioned during the 150ktpm phase able to support 230ktpm
9 November 2016 – Nedbank Site Visit 12
600 Level mining and construction activities – 150ktpm
Main #
Service #
Vent # No.1
Vent # No.2
Vent # No.3
Underground
consumable
stores
TM3
Workshops
South 01 Tip
South 02 Tip
North 01 Tip
North 02 Tip
Ancillary workshops:
Refuelling
Tyre bays
Wash bays
TM3 stores
Key focus
• Mining and equipping of trackless equipment
workshops
• Access and advance reef declines North and South
• Establish section tips No.1 and No. 2 to the North and
South – ore handling for 8 stoping sections
• Equip required workshop infrastructure
• Establish and equip underground trackless and
consumable stores
LEGEND
Current workings – Oct 2016
150ktpm Infrastructure to be completed
9 November 2016 – Nedbank Site Visit 13
642 Level mining and construction activities – 150ktpm
Key focus
• Mining and equipping of trackless equipment
workshops
• Access and advance twin declines North and South
• Establish No.1 and No. 2 ore passes to the North and
South – ore handling for 8 Stoping sections
• Top access for silo and settler reaming and
construction
• Construct and commission North and South decline
conveyors and top of silo (TOS) infrastructure
North 01 Ore
pass
South 01 Ore pass
LEGEND
Current workings – Oct 2016
150ktpm Infrastructure to be completed
Main #
Services #
TM3
Workshops
Top of
Settlers
North 02 Ore pass
South 01 Ore pass
Top of
Settlers
South Decline conveyor – TOS3
North Decline conveyor - TOS4
9 November 2016 – Nedbank Site Visit 14
708 Level development and construction activities – 150ktpm
Main #
Services #
Shaft Bottom Spillage Ramp
Bottom of Vent # No 1
Silo 1
Silo 2
Silo 4
Silo 4
Sett
ler
1
Sett
ler
2
Silo 3
Bottom Silo Conveyor
Drive
Shaft Loading
Box
Main Pump
Station Mud Filter
Press
LEGEND
Current workings – Oct 2016
150ktpm Infrastructure to be completed
Key focus
• Ore handling infrastructure
› Silo 3 and 4 commissioned
› Bottom of silo conveyor extended to silo 4 and
commissioned
• Water handling infrastructure:
› Settler 1 commissioned
› Settler 2 excavation completed
› Main pump station and filter press
commissioned
• Installed water and ore handling capacity can
support 230ktpm
9 November 2016 – Nedbank Site Visit 15
150ktpm Production profile
• Capital cost of 4.75 billion
• Ramp-up to 150ktpm over the next 2.5 years reaching 150ktpm
Q4 – 2018
• Lower capital requirement in current market environment
• 230ktpm Phase II ramp-up market dependant
> 100ktpm concentrator module
> Additional section development
> Associated fleet and infrastructure
0
500
1 000
1 500
2 000
2 500
3 000
2017 2018 2019 2020 2021
kt
Styldrift delivered tonnes
Phase I - 150 ktpm Phase II - 230 ktpm
0
50
100
150
200
250
300
350
400
2017 2018 2019 2020 2021
koz
Styldrift recovered ounces
Phase I - 150 ktpm Phase II - 230 ktpm
9 November 2016 – Nedbank Site Visit 16
Visit route
9 November 2016 – Nedbank Site Visit 17
Induction Video
Induction Video
9 November 2016 – Nedbank Site Visit 18
Thank You