Neo Hungary Kft. Project: Construction of the Production Facility
in ISD Dunaferr, Dunaújváros, Hungary
Beginning of the construction: June 2010Finish of the construction: January 2010Total Investment: 2,100,000 EUR
![Page 2: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/2.jpg)
Original Layout, Year 2009
![Page 3: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/3.jpg)
Area before start of the construction works, June 2010
![Page 4: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/4.jpg)
Area before start of the construction works, June 2010
![Page 5: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/5.jpg)
Area before start of the construction works, June 2010
![Page 6: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/6.jpg)
The beginning of the excavation, June 2010
![Page 7: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/7.jpg)
Excavation works, June 2010
![Page 8: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/8.jpg)
Excavations, June 2010
![Page 9: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/9.jpg)
Beginning of the concrete work, July 2010
![Page 10: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/10.jpg)
Beginning of the concrete work, July 2010
![Page 11: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/11.jpg)
Concrete skeleton of the pit, July 2010
![Page 12: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/12.jpg)
Positioning of the concrete skeleton, July 2010
![Page 13: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/13.jpg)
Positioning of the concrete skeleton, July 2010
![Page 14: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/14.jpg)
Metal flashing of the pit, August 2010
![Page 15: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/15.jpg)
Reinforcement of the EDT Machine foundation, August 2010
![Page 16: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/16.jpg)
Overall view, August 2010
![Page 17: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/17.jpg)
Staircase into the pit, August 2010
![Page 18: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/18.jpg)
Overall view, August 2010
![Page 19: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/19.jpg)
EDT Machine foundation, August 2010
![Page 20: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/20.jpg)
Overall view, August 2010
![Page 21: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/21.jpg)
Plating tanks, September 2010
![Page 22: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/22.jpg)
Installation of the plating line, September 2010
![Page 23: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/23.jpg)
Installation of the plating line, September 2010
![Page 24: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/24.jpg)
Overall view , September 2010
![Page 25: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/25.jpg)
Crane 8t, September 2010
![Page 26: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/26.jpg)
Overall view, October 2010
![Page 27: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/27.jpg)
Rectifier 15 000 A, October 2010
![Page 28: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/28.jpg)
Scrubber and ventilator, October 2010
![Page 29: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/29.jpg)
Operator’s room, October 2010
![Page 30: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/30.jpg)
Installation of the EDT Machine, November 2010
![Page 31: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/31.jpg)
Dielectric plant, November 2010
![Page 32: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/32.jpg)
Installation of the EDT Machine, November 2010
![Page 33: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/33.jpg)
Installation of the EDT Machine, November 2010
![Page 34: Neo Hungary Kft. Project: Construction of the Production Facility in ISD Dunaferr, Dunaújváros, Hungary Beginning of the construction: June 2010 Finish](https://reader035.vdocument.in/reader035/viewer/2022070307/551a4295550346a4248b5b85/html5/thumbnails/34.jpg)
March 2011