Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014 April 2019 NEP: Kathmandu Valley Wastewater Management Project Core Area Sewer Network of Lalitpur (SN03) PART B Prepared by the Project Implementation Directorate, Kathmandu Upatyaka Khanepani Limited, Ministry of Water Supply, Government of Nepal for the Asian Development Bank. This draft due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Upload: others

Post on 05-May-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Land Acquisition and Involuntary Resettlement Due Diligence Report

Document Stage: Draft for consultation

Project Number: 43524-014

April 2019

NEP: Kathmandu Valley Wastewater Management

Project – Core Area Sewer Network of Lalitpur (SN03) PART B

Prepared by the Project Implementation Directorate, Kathmandu Upatyaka Khanepani Limited, Ministry of Water Supply, Government of Nepal for the Asian Development Bank.

This draft due diligence report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “terms of use” section of this website. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 65

Notes of meeting discussions and agreed points between Lalitpur Metropolitan City

(LMC), NEA and PID regarding underground cabling of electric line

Date: July 22, 2018 Venue: NEA Head office Purpose of the meeting A meeting was called between Lalitpur Metropolitan City (LMC), Nepal Electricity Authority (NEA) and Project Implementation Directorate (PID) to discuss the issue about laying of underground electric cable from Lagankhel of Patan till Shankamul. The sewer rehabilitation project of Patan core area is in the final stage of completion of the DPR.Management of the existing utilities is one of the key issues within this project too. Many rounds of meeting have been held with the local office of NEA in regard to underground laying of the old electric cable so as to provide an improved system in the narrow alleys and roads of Patan falling within the sewer pipe route. The local unit of NEA had expressed their desire to have this system in place but due to the limitation of funds, had shown their inability to move forward. Visualizing the ground reality of doing any civil construction in these area without the support of the local authorities is going to be a herculean and near to impossible task to accomplice. So LMC has not only taken up the lead role in executing this project jointly with PID but is also sharing the project cost. Thus, all the agencies have understood the importance of this project and have acknowledged the working modality too. This also serves as a golden opportunity for all related utility owners to improve all their worn out and outdated utilities during the execution of this project. It was also informed by NEA officials that they are likely to execute the work of underground cabling of all electricity cable within the Kathmandu valley in near future. LMC and PID made aware to all about the likely timing of the actual construction work of the sewer project which is January 2019.The sewer route map and the related details were presented at meeting The following were present in the meeting: Attendees: 1.Mr.Chiri Babu Maharjan Mayor, LMC 2 Mr.Kul Man Gheising MD/NEA 3 Mr.Surat Bam PM/PID 4.Mr. Manoj Silwal Act.DMD 5. Mr.Rudra Adikari Senior Engineer/LMC 6.Mr. BharatMaharjan Engineer DSC04 7. Mr.Birendra Kumar Singh Chief, NEA Lagakhel Unit 8.MrJay Kumar Yadav Senior Engineer NEA Lagankhel Unit 9. Rajesh Pd Singh WME/PID 10.Mr. Ramji Bhandari Director, NEA Head office Discussions and Agreed Actions: There was discussion among all participants and final conclusions and agreed points are as follows:

(i) LMC and PID will proceed ahead in preparation of the DPR with close consultation with the local unit of NEA.

(ii) To have a safe and reliable underground system in place, NEA head office will assist and guide the local unit of NEA in preparation the required cost estimate with proper specifications.

(iii) LMC and PID will execute the single package contract with the civil works for the underground cable included.

(iv) The cost of the civil works for the electrical component will be borne by PID and LMC.

Page 3: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

66 Appendix 4

(v) Realizing the opportunity of working with LMC in the forefront, NEA principally agreed to supply all the material required for the underground cabling work and will also explore and manage the budget for the same.

(vi) The supply of materials will be synchronized with the timing of the civil contractor being on board i.e. January 2019

(vii) NEA will also support the project with its expertise in this field and supervise the entire cable laying work.

Page 4: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 67

Page 5: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

68 Appendix 4

Page 6: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 69

Page 7: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

70 Appendix 4

Page 8: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 71

Page 9: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

72 Appendix 4

Page 10: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 73

English Translation Minute

Consultation with stakeholders

A meeting is organized today on 26 Magh 2075 (10 Feb 2019) on Lalitpur Metropolitan City, for the public discussion for IEE of Sewer Rehabilitation from Lagankhel bus station (LMC ward no 5) to Sankhamul through Patan Durbar Square (SN03) under Kathmandu Valley Wastewater Management Project (KVWWMP), Project Implementation Directorate, Kathmandu Upatyaka Khanepani Limited (KUKL). From this sewer rehabilitation project, the problem of sewer flowing around the area Lagankhel bus station, Mahapal chowk, Mangal Bazar and Patan Bazar area would be solved. Regarding this, discussion for the suggestion and opinion of people for IEE and possible impact that the project may cause is being held today in presence of Lalitpur Metropolitan and concerned authority/stakeholers. Following is the list of candidates present in the meeting.

SN Name of Participants Organization

1 Chiri Babu Maharjan Mayor LMC

2 Geeta Satyal Deputy Mayor LMC

3 Raju Maharjan Ward chairman -9

4 Suprava Sakya Ward member 16 no ward

5 Pancha Bajra Bajracharya Ward member 16 no ward

6 Bu lal Maharjan Ward member

7 Nuchhche Ratna Khadgi Ward member

8 Dikshya Dhakal PID/DSC-6

9 Raj Lal Thakur PID/DSC-5

10 Hera Kaji Maharjan Nepal Telecom

11 Surat Malla Nepal Telecom Patan

12 Krishna Govinda Joshi Treasurer Tole committee

13 Bhagwan Maharjan Secretary Tole committee

14 Kaji Pyakurel Patan Durbar Squre office

15 Sarika Gharana DSC-6/PID

16 Rajesh Pd .Singh PID

17 Bharat Maharjan Network Eng./DSC-6 /PID

18 Min Dahal FC/CASSC/PID

19 Shisir Gautam SDE /DSC-6/ PID

20 Rudra Pd Adhikari LMC

Decision

SN03 project would be started considering the suggestions obtained from discussion for the possible impacts of the project and for IEE.

Page 11: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

74 Appendix 4

Feedback/ consultation with stakeholders

Page 12: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 75

Page 13: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

76 Appendix 4

Page 14: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 77

English Translation Minute

Feedback/ consultation with stakeholders

Opinion/Feedback of public required in (10 January 2019) for the preparation of IEE report of Sewer Rehabilitation in the core city area of Lalitpur Metropolitan City under Kathmandu Valley Wastewater Management Project (KVWWMP), Project Implementation Directorate, Kathmandu Upatyaka Khanepani Limited is as follows. The project is 2.8 km sewer system that is proposed in Lalitpur Metropolitan City ward no 5, 9, 11, 12, 16 and 19 from Lagankhel, Patan Durbar Square to Sankhamul Area.

S.N Name Opinion

1. Raju Maharjan Ward chairman LMC-9

In present situation, it is highly necessary to improve the

condition road from Mangalbazar to Gapuhiti. If the road cannot

be improved then it is difficult to convince the public of this area.

2. Suprava Shakya Stone pavement should be made along the area of the

heritage site as it is done in present condition. Project should be

completed in time as it is necessary to satisfy the public

otherwise it would be difficult to the concerned people.

3. Pancha Bajra

Bajracharya

The condition of sewer and drinking water within the Lalitpur

Metropolitan City should be taken into consideration and

work should be completed without creating any difficulties to the

concerned people.

4. Nhuchhe Ram Khadgi,

ward no 19

I request you to work efficiently to finish the project in time.

5. Surat Malla, Nepal

Telecom office , Patan

I hope for the successful completion of the SN03 project.

During the construction phase of this project, facilities given by

Nepal Telecom to the public would be interrupted. So,

considering this and the government revenue, it is necessary to

run this project by side with NTC. Moreover, to continue to give

the service of NTC, provision of additional budget is not available

at present with NTC. Hence the additional budget would be

incorporated for damaged line by project side.

6. From the side of Lalitpur

Metropolitan City office

1. Design should be made considering the worst condition of site such as narrow road and in such situation construction methodology should be recommended for carrying out the construction activities.

2. For the safety of the people during the construction phase, hard cover fence and blinking light should be kept around the project area. Work schedule should be prepared considering the festivals according to Nepali, Newari and English calendar and also considering the ‘Visit Nepal 2020’.

3. As the section from Bhimsen temple to Sankhamul and Mahapal Iti road are tourist areas, there should be a provision for the pavement of the roads in that area should with high quality stone.

4. A maintenance manual containing maintenance plan, technology, and equipment should be recommended such that the project runs smoothly after the construction and completion of project.

Page 15: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

78 Appendix 4

Opinion/Suggestion collected for SN03 project during Focus Group Discussion

Page 16: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 79

Page 17: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

80 Appendix 4

Page 18: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 81

Page 19: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

82 Appendix 4

Page 20: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 83

Page 21: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

84 Appendix 4

Page 22: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 85

English Translation of focus group discussion 24th March 2019

Opinion and suggestion of public required for the preparation of IEE report of Sewer Rehabilitation in the core city area of Lalitpur Metropolitan City was collected on 24th March 2019. The list of people who were consulted are as follows:

NAME PLACE

1. Saru Rai K.K Mart- Department Store

2. Hari Humagain K.K Mart- Cloth shop

3. Kalpana Silwal K.K Mart- Cloth shop

4. Sabita Nepal Shoes shop

5. Bijay Raj Chirag Sweets

6. Umesh Duwal Umesh store- Owner of a house

7. Bhawani Timalsina MBS Fancy

8. Devraj Karki Dev Cloth shop

9. Prachanda Raj Jibi Cloth Shop

10. Nutan Tamrakar Nutan Kitchen Store

11. Dipak Adhikari Worship Utensils shop

12. Narayan Lal Shrestha Beans shop

13. Suresh Singh Gift shop- Owner of a house

14. Sanu Hira Shakya/Sharmila Maharjan Owner of a house/ Owner of a Tailor Shop

15. Bipin Bajracharya Patan Durbar Square Museum

16. Prem Lama Art Gallery

17. Dikesh Maharjan Tea Shop-Owner of the house

18. Yogendra Maan Bajracharya Owner of a house

19. Bishnu Limbu Little City Kids School

20. Amit Shah Bagmati Multi-Speciality Clinic

21. Bharat Bhujel Shoes Shop-Vendor

22. Laxmi Shrestha Vendor

23. Krishna Bahadur Shrestha Vendor

24. Subachandra Mandal Mixed things Vendor

25. Shahbaj Ansari Chatpate/Paanipuri Vendor

26. Babita Chitrakar Handicraft Vendor

27. Durga Dahal Chatpate/Paanipuri Vendor

Page 23: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

86 Appendix 4

Meeting for discussion of SN03

Page 24: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 87

Page 25: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

88 Appendix 4

English Translation of the minutes of meeting 31st March 2019

A meeting is organized today on Sunday, 31st March 2019 (16 Chaitra 2075) on Lalitpur Metropolitan City in presence of Mayor of LMC. With the budget of Government of Nepal, LMC and ADB, a 2.8 km sewer line will be constructed from Lagankhel bus station to Sankhamul through Patan Durbar Square (SN03) that will manage the storm water and sewer line. In this regard, group of people from different organization as well as public people had a discussion, interaction and exchange of information. The list of people present in the meeting is listed as

follows:

SN Name of Participants Organization

1 Chiri Babu Maharjan Mayor LMC

2 Geeta Satyal Deputy Mayor LMC

3 Surendra Govinda LMC

4 Prayag Lal Johari Expert

5 Kiran Man Pradhan Mangaltol

6 Rudra Adhikari LMC

7 Narayan Lal Awale Ward chairman -12

8 Saafale Amatya

9 Prafulla Man Singh Pradhan LMC-Adviser

10 Rohit Ranjitkaar LMC-Adviser

11 Suresh Saras Shrestha Department of Archaeology

12 Sandeep Khanal In charge of heritage site

13 Devendra Bhattrai Department of Archaeology

14 Surat Kumar Bam KUKL/PID

15 Rajesh Pd .Singh KUKL/PID

16 Vidhya Bhandari PID

17 Madhav Prasad Ghimire Media LMC

18 Rama Luitel Media LMC

19 Ramiya Maharjan Ward member 19 no ward

20 Ram-Bhakta Thapa Ward member 4 no ward

21 Bharat Prasad Acharya CASSC/PID

22 Pushpa Koirala CASSC/PID

23 Sarika Gharana DSC-6/PID

24 Bharat Maharjan DSC-6 /PID

25 Min Dahal CASSC/PID

26 Bijay Karki Naya Patrika

27 Gopal Man Shrestha Cultural organisation

28 Bishweshor Koirala LMC

29 Pramod Ward no 3

Page 26: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 89

Presentation to LMC and LCCC on 31 March 2019

Page 27: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

90 Appendix 4

Page 28: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 91

Page 29: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

92 Appendix 4

Page 30: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 93

Page 31: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

94 Appendix 4

Page 32: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 95

Page 33: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

96 Appendix 4

Page 34: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 97

Page 35: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

98 Appendix 4

Page 36: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 99

Page 37: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

100 Appendix 4

Page 38: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 101

Page 39: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

102 Appendix 4

Summary of public consultation (Brief Translation of Minutes of Meetings)

S.N. English

Date Nepali Date

No of

participants Male Female Location Participants Major issues/Translation

1. 6 Feb

2018 2074/10/23 55 51 4

Assembly

Hall, Lalitpur

Metropolitan

city

Mayor, House of

representative member,

state assembly member,

ward representatives, ADB

consultant, PID,KUKL,

CASSC, DSC, LMC staffs

other concerned

stakeholders

Presentation and discussion on

Dhobighat waste water treatment

plant and sewer system

rehabilitation

2. 24 May

2018 2075/02/10 34 29 5

Assembly

Hall, Lalitpur

Metropolitan

city

Mayor, PD, ward

representatives, PID,KUKL,

CASSC, DSC, LMC staffs

other concerned

stakeholders

Presentation on DPR at LMC to

different stakeholders; Discussion

on DPR of the trunk line for SN-03

3. 6 June

2018 2075/02/23 38

Assembly

Hall, Lalitpur

Metropolitan

city

Mayor, PD, ward

representatives, PID,KUKL,

CASSC, DSC, LMC staffs

Presentation on DPR and Design

Revision and Discussion on SN-03

4. 25 June

2018 2075/03/11 12 7 5

Ward no 5 Ward chairperson, ward

secretary, local people,

CASSC

Information dissemination of the

project. Coordination with ward

committee and local community

members and further discussion

on the combined sewerage line of

SN-03 and underground utilities

over the planned stretch.

5. 26 June

2018 2075/03/12 21 6 15

Ward no 12 Ward chairperson, ward

secretary, local people,

,CASSC

Information dissemination of the

project. Coordination with ward

committee and local community

members and further discussion

on the combined sewerage line of

SN-03 and underground utilities

over the planned stretch.

Page 40: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 103

S.N. English

Date Nepali Date

No of

participants Male Female Location Participants Major issues/Translation

6. 26 June

2018 2075/03/12 15 11 4

Ward no 19 Ward chairperson, ward

secretary, local people,

,CASSC

Information dissemination of the

project. Coordination with ward

committee and local community

members and further discussion

on the combined sewerage line of

SN-03 and underground utilities

over the planned stretch.

7. 29 June

2018 2075/03/15 28 23 5

Ward no 9 Ward chairperson, ward

secretary, local people,

,CASSC

Information dissemination of the

project. Coordination with ward

committee and local community

members and further discussion

on the combined sewerage line of

SN-03 and underground utilities

over the planned stretch.

8. 29 June

2018 2075/03/15 16 14 2

Ward no 11 Ward chairperson, ward

secretary, local people,

CASSC

Information dissemination of the

project. Coordination with ward

committee and local community

members and further discussion

on the combined sewerage line of

SN-03 and underground utilities

over the planned stretch.

9. 29 June

2018 2075/03/15 19 14 5

Ward no 16 Ward chairperson, ward

secretary, local people,

CASSC

Information dissemination of the

project. Coordination with ward

committee and local community

members and further discussion

on the combined sewerage line of

SN-03 and underground utilities

over the planned stretch.

Page 41: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

104 Appendix 4

S.N. English

Date Nepali Date

No of

participants Male Female Location Participants Major issues/Translation

10. 19 July

2018 2075/04/03 21

Assembly

Hall, Lalitpur

Metropolitan

city

Mayor, Chief Administrative

officer, ward

representatives, PID,KUKL,

CASSC, DSC, LMC staffs,

NEA representative, NTC

representative

Discussion on the existing

underground utilities from and their

reinstatement after dislocation.

1. The project will provide civil cost

for the relocation of underground

electricity cables and conduit.

2. Nepal electricity authority will

supply all required underground

cables and conduit and civil cost

will be included in the project

BOQ.

3. It is agreed that MOA between

KUKL (PID) and LMC will be

signed on 31 July 2018.

4. KUKL (PID) will provide all

discussed topics and particulars to

all stakeholders by email within 22

July 2018.

11. 22 July

2018 2075/04/06 10

NEA Head

office

Mayor, KUKL-PID, DSC, NEA staffs and LMC staffs

Preparation of the DPR, cost of the civil works

12. 18 Nov

2018 2075/08/02 34 30 4

L

MC Ward no

Ward Chairperson 12,19 and 5 ward LMC Tole committees leaders, Shopkeepers, venders, Community members and

Information dissemination of the project. Coordination with ward committee and local community members The excavation work for this section will be 50-100 meters which will be backfill immediately after finishing work. Therefore, there will be no disturbance on local business.

Page 42: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 4 105

S.N. English

Date Nepali Date

No of

participants Male Female Location Participants Major issues/Translation

12 office KUKL /DSC-6/ PID Project will inform shopkeeper and vender at least one week prior to the excavation so that the street vendors could manage their business for that time. Locals including vendors shopkeepers agreed to provide their support by clearing the construction area and construction activities will be carried with protecting public assets and small temples.

13. 10 Feb

2019

27 Magh

2075 20 16 4

LMC office

Meeting Hall

Mayer, Deputy Mayer, Ward Chairperson of LMC tole committee member of LMC Tole committee leaders ,Nepal Telecom, DOA Patan Darbar Office and PID/DSC-6,and CASSC DSC-5

Public consultation with different stake holders in presence of Lalitpur Municipality Project SN03 would be continued to incorporate of IEE mitigation measures (Please refer minute which is attached in this minute Report)

Page 43: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

106 Appendix 5

Appendix 5: List of Participants

SN. Name of participants Organization

Meeting at LMC Assembly Hall on 6 February 2018

1. Chiri Babu Maharjan Mayor, LMC

2. Pampha Bhusal House of representative member

3. Jiwan Khadka State assembly member

4. Raj Kaji Maharjan State assembly member

5. Ashish Ghimire HPCIDBC

6. Kishor Thapa Bagmati Cleaning Campaign

7. Bijaya K Shrestha ADB consultant

8. Rahul Muni Bajracharya ADB consultant

9. Ajar Man Joshi Lalitpur Chamber of Commerce

10. Rudra Gautam LMC

11. Dilendra Raj Shrestha Advisor, LMC

12. Sabin Shrestha Lalitpur Chamber

13. Nabin Mangal Joshi Kebhal Tole Sudhar Samittee

14. Birendra Lal Shrestha Mangal Bazar Tole Sudhar Samittee

15. Binod Tamrakar Ward Chairperson; ward no 19

16. Prayag Joshi Engineer, ward no 19

17. Kiran Man Pradhan Mangal Bazar Tole Sudhar Samittee

18. Gyanu Raja Shrestha Mangal Bazar Tole Sudhar Samittee

19. Sunil Shakya Mahapal Tole Sudhar Samittee

20. Suvendra Raj Joshi Swothe Tole Lalitpur

21. Garinets Safbon water

22. Dinesh Maharjan Choba Gahitee tole

23. Narayan Lal Awale Ward Chairperson; ward no 12

24. Suresh Maharjan Ward Chairperson; ward no 26

25. Indraman Maharjan Ward Chairperson; ward no 11

26. Nirmal ratna shakya Ward Chairperson; ward no 16

27. Bishow mani Jyawali Executive Director; SWMTSC

28. Kishor Shakya Nepal Engineering Association

29. Sanjib Bikram Rana Executive Director; KVWMSB

30. Diwakar Pd Dhakal DPD; PID

31. Nanda lal Banjade

CDE; Department of water supply &

Sewerage

32. Dipak Puri DSC -04/PID

33. Dhurba Bd Shrestha ADB/PPTA

34. Himesh Anand Baidya DPD/PID

35. Dhurba Raj Regmi PMD/PID

36. Suman Pd Sharma PID/ADB

37. Mahesh Bhattarai KUKL

38. Tiresh Pd Khatri EDPID

39. Anil Bhadra Khanal Joint Secretary; Ministry of Water supply

40. Jhanj Honglogn PID Consultant

41. Bharat Maharjan DSC04/ PID

42. Raju Maharjan Ward no 9

43. Krishna Lal Maharjan Lalitpur Metropolitian City

Page 44: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 5 107

SN. Name of participants Organization

44. Suranjan Ghimire Ba rakhari.com

45. Narayan K.C Ward Chairperson; ward no 4

46. Rikesh Chitrakar Envt. Expert; DSC04

47. Kishor Pantee Engineer/ PID

48. Sangitanjali Koirala Engineer/ PID

49. Rukesh Bataju SARBON/ Engineer

50. Bhagwan Maharjan

51. Pushpa Koirala Envt. Expert; CASSC

52. Bharat K.C CSE; DSC04

53. Bharat Acharya CME; CASSC; DSC 04

54.

55.

56.

57. Mahesh Bhattarai KUKL

58. Tiresh Pd Khatri PID

59. Suman Pd Sharma PID/ADB

60. Arjun babu Dhakal LMC

61. Dhurba Raj Regmi PMD/PID

62. Pinky Bijayananda Social Development Expert/DSC04

63. Rikesh Chitrakar Envt. Expert; DSC04

64. Surat Bd Malla Nepal Telecom

65. Ram Sundar Hamal Nepal Telecom

66. Kaji Pyakural Patan Durbar Square

67. Krishna Lal Maharjan LCCI

68. Indra Man Maharjan Ward Chairperson; ward no 11

69. Niran Man Pradhan

Ward No 11

70. Chanda lal Maharjan Ward Chairperson; ward no 20

71. Narayan Lal Awale Ward Chairperson; ward no 12

72. Binod Tamarkar Ward Chairperson

73. Nabin Mangal Joshi TLO; Mangalbazar

74. Gyanendra Kalauni Engineer, Lalitpur

75. Prayag Joshi Engineer, ward no 19

76. Nirmal ratna shakya Ward Chairperson; ward no 16

77. Birendra K Singh NEA; Pulchowk

78. Mohamad Rayan NEA; Pulchowk

79. Jay K Yadav NEA; Lagankhel

80. Munny pradhan Consultant ADB

81. Vivan Castro ADB

82. Rajesh Pd Singh PID

83. Bipul Das PID

84. Surak K Bam PID/KUKL

85. Jhang Hong Kyu PID Consultant

Meeting at 16 Ward Office, 29 June 2018

Page 45: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

108 Appendix 5

SN. Name of participants Organization

86. Nirmal Ratna Sakya, Chief, 16 Ward LMC

87. Dilip Joshi, Advisor, 16 Ward LMC

88. Bal Krishna Maharjan, 16 Ward LMC

89. Prabin Bahadur Shakya, DMC, 16 Ward LMC

90. Narayan Maharjan CDMC, 16 Ward LMC

91. Sapina Karki, 16 Ward LMC

92. Anusha Karki, 16 Ward LMC

93. Sarita Shakya, 16 Ward LMC

94. Deepak Pokharel, Secretary, 16 Ward LMC

95. Puskar Kumar Thapa, 16 Ward LMC

96. Sabin Narayan, 16 Ward LMC

97. Khushi Shakya, 16 Ward LMC

98. Sandeep Budhathoki, 16 Ward LMC

99. Yanalal Maharjan, 16 Ward LMC

100. Raskumar Nepali, 16 Ward LMC

101. Nutana Shrestha, Enumerator, CASSC CASSC/PID

102. Ramesh Deuba, CASSC CASSC/PID

103. Bharat Acharya, CASSC CASSC/PID

Meeting at 5 Ward Office, 25 June 2018

104. Ashok Kumar Shrestha, Ward 5, Chief LMC

105. Manju Rijal, 5 Ward, Member LMC

106. Shova Devi Pradhan Shrestha, 5 Ward, Member LMC

107. Punam K.C. Niraula, 5 Ward, Member LMC

108. Sangita Maharjan, 5 Ward LMC

109. Raghab Dangol, 5 Ward LMC

110. Krishna Ram Shrestha, 5 Ward LMC

111. Bharat Acharya, CASSC PID

112. Min Dahal, CASSC PID

113. Radha Krishna Shrestha, 5 Ward LMC

114. Ravi Kumar K.C. 5 Ward LMC

115. Raj Kumar K.C. 5 Ward LMC

Meeting at 12 Ward Office, 26 June 2018

1. Sarita Maharjan, Ward 12 Representative LMC

2. Sanu Awale, 12 Ward Chief LMC

3. Nidhi Tamrakar, 12 Ward LMC

4. Astalaxmi Shrestha, 12 Ward LMC

5. Mohan Laxmi Shakya, 12 Ward LMC

6. Jayenti Maharjan, 12 Ward LMC

7. Budha Laxmi Awale, 12 Ward LMC

8. Rama Maharjan, 12 Ward LMC

9. Gita Tamrakar, 12 Ward LMC

Page 46: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 5 109

SN. Name of participants Organization

10. Keshari Shakya, 12 Ward LMC

11. Komal Shakya, 12 Ward LMC

12. Laxmi Dangol, Secretary, 12 Ward office LMC

13. LMC

14. LMC

15. Shreejana Bhaidya, 12 Ward office, Member LMC

16. Maiya Bista, Secretary, 12 Ward office LMC

17. Maiya Maharjan, Chief LMC

18. Indu Bajracharya, 12 Ward LMC

19. Min Dahal, CASSC KUKL/PID

20. Bharat Acharya, CASSC KUKL/PID

Meeting at 19 Ward Office

1. Binod Tamrakar, 19 Ward, Chief LMC

2. Bulal Maharjan, 19 Ward, Representative LMC

3. Ramiya Maharjan, 19 Ward, Representative LMC

4. Renu Maharjan, 19 Ward LMC

5. Nhuche Ratna, 19 Ward LMC

6. Prem Lal Maharja, 19 Ward LMC

7. Devi Chaulagai, 19 Ward LMC

8. Asha Lal, 19 Ward LMC

9. Bhai Krishna, 19 Ward LMC

10. Asta Bahadur Nemkul, 19 Ward LMC

11. Dibesh Maharjan, 19 Ward LMC

12. Ramesh Shrestha, 19 Ward LMC

13. Bharat Acharya, CASSC/PID KUKL-PID

14. Min Dahal, CASSC/PID KUKL-PID

24 May 2018 meeting at LMC hall

1. Chiribabu Maharjan, Mayor (Chairman) LMC

2. Gita Satyal, Vice Chairman LCM

3. Mahesh Bhattarai, Coordinator KUKL

4. Suman Prashad Aryal, Consultant

5. Arjun Babu Dhakal,

6. Dhurba Raj Regmi, PID Consultant KUKL,PID

7. Pinky Bijayanand, Social Development Expert DSC04, KUKL, PID

8. Rikesh Chitrakar, Environment Specialist DSC04, KUKL, PID

9. Surat Bahadur Malla, Office Chief, Representative NTC

10. Ram Sundar Hamal, Technical Officer,

Representative

NTC

11. Kaji Pyakurel, Chief Palace Officer, Representative DOA

12. Krishna Lal Maharjan, Chief, Representative LCCI

13. Indraman Maharjan, 11 Ward, Chief LMC

Page 47: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

110 Appendix 5

SN. Name of participants Organization

14. Raju Maharjan, 9 Ward, Chief LMC

15. Kirna Man Pradhan, 19 Ward, Chief LMC

16. Chandra Lal Maharjan, 20 Ward, Chief LMC

17. Narayan Lal Awale, Ward Chief LMC

18. Binod Tamrakar, 2 Ward Chief LMC

19. Nabin Mangal Joshi, Coordinator, Area

Development Committee

LMC

20. Gyanendra Kalauni, Engineer, LMC

21. Prayag Joshi, Drainage Engineer, Local

Representative

LMC

22. Nirmal Ratna Shakya, 16 Ward Chief LMC

23. Birendra Kumar Singh, Chief, Representative NEA, Lagankhel

24. Kul Mohammad Rayem, Engineer, Representative NEA, Pulchowk

25. Jay Kumar Yadav, Envineer, Representative NEA, Lagankhel

26. Amy, Consultant ADB

27. Munny Pradhan, Consultant ADB

28. Vivian Casteo.Wooldridge, Consultant ADB

29. Rajesh Prasad Singh, WME KUKL, PID

30. Bipul Kumar Lal Das, SDE KUKL, PID

31. Surat Kumar Bam, PM KUKL, PID

32. Jhang Hong Kyu, TL DSC/PID/KUKL

33. Bishnu P. Joshi KUKL

19 July 2018 meeting at LMC hall

1. Chiri Babu Maharjan, Mayor LMC

2. Gita Satyal, Vice Mayor LMC

3. Hari Prashad Dahal, Chairman of Administrative

Office

LMC

4. Rudra Prashad Gautam, Chief of Infrastructure

Development Unit

LMC

5. Kumar Yadav, Engineer, Representative NEA

6. Pradip Adhakari, Engineer, Representative NEA

7. Surat Bahadur Malla, Office Chief, Representative NTC

8. Ram Sundar Dhakal, Representative NTC

9. Sumita Ghimire, Representative NTC

10. Rabindra Amatya, Representative KUKL

11. Rajendra Desar, Representative KUKL

12. Hiranya Prashad Parajuli, Under Secretary, Account LMC

13. Surat Bam, PM KUKL (PID)

14. Laxmi Pant, SDE KUKL (PID)

15. Rajesh Prasad Singh, WME KUKL (PID)

16. Dhurba Raj Regmi, FMC KUKL (PID)

17. Jhang Hong Kyu, TL DSC/PID/KUKL

18. Rikesh Chitrakar, Env. Specialist DSC04/PID/KUKL

19. Ramesh Deuba, Community Mobilizer CASSC/PID

20. Bharat Maharjan, Network Engineer DSC04/PID

Page 48: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 5 111

SN. Name of participants Organization

21.

18 November 2018 meeting at LMC Ward no 12 office

SN Name of Participants Organization

1 Narayan Lal Awale Ward Chairman ward no12 Ward no 12, LMC

2 Sarita Maharjan ,Ward female member ward no12 Ward no 12, LMC

3 Tirth Raj Bajracharya,Chairman Te tole committee Ward no 12, LMC

4 Hira Man Pradhan, Chairman Mangal tole committee Ward no 12, LMC

5 Gyan Lal Maarjan, Member Heugal tole committee Ward no 12, LMC

6 Hari Narshing Amatya,Treasurer Mangal tole committee Ward no 12, LMC

7 Sambhu Prashad Baral, Secretary Mangal tole committee Ward no 12, LMC

8 Ram lal Maharjan, Member Heugal tole committee Ward no 12, LMC

9 Asok Maharjan Businesman, Mangal Bazar committee Ward no 12, LMC

10 Sunil Maharjan Member Heugal tole committee Ward no 12, LMC

11 Surje Bausar Member Heugal tole committee Ward no 12, LMC

12 Santa Man Maharjan Heugal tole committee Ward no 12, LMC

13 Binod Shilpakar Member Lagan khel tole committee Ward no 12, LMC

14 Raju Kapali, Office Assistant Mangal tole committee Ward no 12, LMC

15 Suresh Maharjan, Vice chairman Mangal tole Committee Ward no 12, LMC

16 Dharma Raj Lama, Businessman, Prayg Pokhari tole Ward no 12, LMC

17 Laxman Awale, Businessman Prayg Pokhari tole Ward no 12, LMC

18 Sanu Awale, Ward member ward no12 Ward no 12, LMC

19 Kedar Bahadur Shrestha, Chairman Prayg Pokhari tole

20 Rajesh Shrestha,, MD Om Apartment

21 Jiwan Jimin Badiya ,Ward member ward no12 Ward no.12, LMC

22 Bikash Man Shrestha, Ward Chairman ward no 5 Ward no.5, LMC

23 Indra Bahadur Kunwar, Businessman Prayg Pokhari Kumaripati 19, LMC

24 Nisha Shrestha, Student Ward no 5, LMC

25 Punam Niroula, Ward member ward no 5 Ward no 5, LMC

26 Sudeep Aryal, Businessman ward no 5

27 Paru Aryal, Businessman ward no 5 Ward no 5 LMC

28 Sangita Maharjan Social Mobilizer Ward no 5 LMC

29 Brijendra Bikram Thapa Businessman ward no 5 Ward no 5 LMC

30 Ram Singh Basnet, Businessman ward no 5 Ward no 5 LMC

31 Kumar Shrestha

32 Binod Tamrakar, Ward Chairman ward no 19 Ward no.19, LMC

33 Shisir Gautam , SDE DSC-6/ KUKL/PID

34 Min Dahal FC CASSC KUKL/PID

10 February 2019 meeting at LMC Office Hall for IEE

Consultation

SN

Name of Participants

Organization

1 Chiri Babu Maharjan Mayor LMC

2 Geeta Satyal Deputy Mayor LMC

Page 49: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

112 Appendix 5

3 Raju Maharjan Ward Chairman -9

4 Suprava Sakya Ward member 16 no ward

5 Pancha Bajra Bajracharya Ward member 16 no ward

6 Bu lal Maharjan Ward member

7 Nuchhche Ratna Khadgi Ward member 19

8 Dikshya Dhakal DSC-6/ PID

9 Raj Lal Thakur DSC-5/ PID

10 Hera Kaji Maharjan Nepal Telecom

11 Surat Malla Nepal Telecom Patan

12 Krishna Govinda Joshi Treasurer Tole committee

13 Bhagwan Maarjan Secretary Tole committee

14 Kaji Pyakurel Patan Durbar Square office

15 Sarika Gharana DSC-6/PID

16 Rajesh Pd .Singh PID

17 Bharat Maharjan Network Eng./DSC-6 /PID

18 Min Dahal FC/CASSC/PID

19 Shisir Gautam SDE /DSC-6/ PID

20 Rudra Pd Adhikari LMC

Page 50: NEP: Kathmandu Valley Wastewater Management …...Land Acquisition and Involuntary Resettlement Due Diligence Report Document Stage: Draft for consultation Project Number: 43524-014

Appendix 6 113

Appendix 6: List of Major Festivals SN Name of festival Affected date Affected alignment/Chainage

1 Rato Macchindra Nath Jatra Baisakh (15-April-15 May)

Pulchowk-Gabahal-sundhara-lagankhel-Jawlakhel

2 Krishna Asthami Shrawan (15 July-15 August)

Inside Mangalbazar

3 Bhimshen Jatra Shrawan (15 July-15 August)

Mangalbazar-Sundhara-Okhu bahal- Tangal- Kumbeswori- Mangalbazar

4 Matiya Jatra Shrawan (15 July-15 August)

People visit whole Patan area for puja organized by gabahal (patan)

5 Gai Jatra Shrawan-Bhadra (15 July-30 August)

Throughout the alignment

6 Janaipurnima Shrawan-Bhadra Bhadra (15 July-30 August)

Patan Darbar Square -Baglamukhi