nerc lessons learned summary lls published in september 2015

13
NERC Lessons Learned Summary LLs Published in September 2015

Upload: godwin-dickerson

Post on 19-Jan-2016

217 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: NERC Lessons Learned Summary LLs Published in September 2015

NERC Lessons Learned Summary

LLs Published in September 2015

Page 2: NERC Lessons Learned Summary LLs Published in September 2015

Two NERC lessons learned (LL) to be published in September and one is pending • LL20150901- Loss of EMS Communications Due

to Lack of Validation on EMS Database RTU Configuration Parameter

• LL20150902 – Relay Design and Testing Practices to Prevent Scheme Failure

• Pending• Loss of EMS due to RTU LAN UPS failure

NERC Lessons Learned Published in 2015

Page 3: NERC Lessons Learned Summary LLs Published in September 2015

Commissioning new remote terminal unit (RTU) results in EMS outage

One point incorrectly configured results in termination of the remote communication server Process coordinates the polling and commands of RTUs and the

insertion of telemetry into the real time database

Automatic failover (from primary and back-up) did not correct issue since the error was in the database configuration

EMS lost communications with all RTUsState Estimator and Contingency Analysis had stale dataMost changes verified prior to execution but the database

configuration parameters were not checked

Loss of EMS Communications Due to Lack of Validation on EMS Database RTU

Page 4: NERC Lessons Learned Summary LLs Published in September 2015

Corrective ActionsParameter configuration was correctedScript was run to confirm the configuration error doesn’t exist

elsewhere Revised procedure to confirm EMS database RTU

configuration is correct in quality assurance prior to uploading a database change to production

Created a case with the EMS vendor documenting the defect Vendor will provide a new release with the defect resolved

Loss of EMS Communications Due to Lack of Validation on EMS Database RTU

Page 5: NERC Lessons Learned Summary LLs Published in September 2015

LessonsEvaluate parameters being checked by the

database editor to determine if there are any gaps in the parameter validation If so, establish procedures for manual validation

SCADA software should be designed to generate error messages and avoid termination upon an incorrect parameter

Recovery strategy and procedures should be developed for quick recovery from failed updates

Loss of EMS Communications Due to Lack of Validation on EMS Database RTU

Page 6: NERC Lessons Learned Summary LLs Published in September 2015

• Single-phase to ground fault occurred on a 230 kV three-terminal feeder

• Associated breakers tripped then the line reclosed at one end (as designed)

• Two protection equipment failures on two separate relay systems prevented the proper clearing after the automatic reclose

• 1: Loose connection in the trip aux relay coil cutoff contact string• 2: Believed to be intermittent connection issue

• Fault evolved to multi phase and remained on the system for 58 seconds

• Breaker Failure didn’t initiate since it was tied to same aux trip relay

• Fault cleared by backup ground protection on two 500 kV lines

Relay Design and Testing Practices to Prevent Scheme Failure

Page 7: NERC Lessons Learned Summary LLs Published in September 2015

Corrective ActionsTransmission Owner (TO) evaluated existing

procedures to align periodic relay testing with planned transmission outages and perform circuit breaker trip testing

52a contacts rewired in parallel rather than in series Replaced a relay as neededNew relay eliminates need for the 52a contacts in the

breaker trip circuit

Relay Design and Testing Practices to Prevent Scheme Failure

Page 8: NERC Lessons Learned Summary LLs Published in September 2015

LessonsKey issue: Breaker Failure Initiate (BFI) signal

originated from auxiliary trip relayOptions:

Use separate contact to provide BFI Use dedicated aux relay for BFI Connect protective relay trip contact directly to breaker

failure relay input if relay will accommodate voltage input

Avoid use of 52a contacts in seriesConsider periodic functional tests

Relay Design and Testing Practices to Prevent Scheme Failure

Page 9: NERC Lessons Learned Summary LLs Published in September 2015

• Rack mounted uninterruptible power supply (UPS) Failed resulting in loss of remote terminal unit (RTU) local area network (LAN) and then the loss of EMS and ICCP for 50 minutes

• UPS added to accommodate EMS/SCADA hardware upgrade• Remained in service as a dual layer UPS

• UPS battery pack failed and the UPS did not have an internal bypass to house power

• Failover was not available since the front end processor for the RTU LAN at the back-up was pointed at a replacement system’

• The entity was in transition to a new software for their EMS

Loss of EMS Due to RTU LAN UPS failure

Page 10: NERC Lessons Learned Summary LLs Published in September 2015

Corrective ActionsRTU LAN routers were plugged into another UPS and

rebooted, restoring EMS visibility and ICCP link connectivityFEP at the remote site was reconfigured to allow sending data

to both the replacement SCADA/EMS and the existing SCADA/EMS systems simultaneously by using additional IP addresses

Primary and Backup Routers at the Primary Site were plugged into alternate UPSs

Additional (temporary) rack mounted UPSs will be removed upon cutover to the replacement SCADA/EMS system (Vendor 1 to Vendor 2)

Loss of EMS Due to RTU LAN UPS failure

Page 11: NERC Lessons Learned Summary LLs Published in September 2015

LessonsUPS systems should be checked to verify they have

an internal bypass Periodic maintenance and monitoring on any UPS

system is beneficial Some UPS systems perform battery maintenance/cycling

internally but additional checks may be performed to verify functionality

Loss of EMS Due to RTU LAN UPS failure

Page 12: NERC Lessons Learned Summary LLs Published in September 2015

Directions to Lessons Learned:Go to www.NERC.com > “Program Areas & Departments”

tab > “Reliability Risk Management” (left side menu) > “Event Analysis” (left side menu) > “Lessons Learned” (left side menu)

NERC’s goal with publishing lessons learned is to provide industry with technical and understandable information that assists them with maintaining the reliability of the bulk power system. NERC requests that industry provide input on lessons learned by taking the short survey. The survey link is provided on each Lesson Learned.

Link to Lessons Learned

Page 13: NERC Lessons Learned Summary LLs Published in September 2015

Questions?