Network Change Request Form Requester Name and Department Zhengyucan Change Owner LTE RF Team Change Title Throughput Test at Microwave Swapped Sites Date of Request: 18 th May,2013 Planned Change Date & Time: From 21 th May,2013 to 23 th May,2013 9:00AM to 06:00PM Priority of Change: High Medium Low Impact of Change: Major Minor None Impact Details: System Impact: None Service Impact: None, throughput test at Microwave swapped sites where adequate bandwidths are available. Motivation of Change: # Description of Change: # No parameter change, only throughput Test. 1 | Page

Upload: sami-doha

Post on 17-Dec-2015

5 views

Category:

Documents


0 download

DESCRIPTION

a CR format

TRANSCRIPT

Network Change Request Form

Requester Name and DepartmentZhengyucan

Change Owner LTE RF Team

Change TitleThroughput Test at Microwave Swapped Sites

Date of Request:18th May,2013Planned Change Date & Time:From 21th May,2013 to 23th May,20139:00AM to 06:00PM

Priority of Change:|_|High |_| Medium|X|Low

Impact of Change:|_| Major |_| Minor|X| None

Impact Details: System Impact: None Service Impact: None, throughput test at Microwave swapped sites where adequate bandwidths are available.

Motivation of Change: #

Description of Change:# No parameter change, only throughput Test.

Details of Proposed Change Products Product NameMGMT IP

EnodeB/M2000 N/A

Resources

Resource NameContact

Zhengyucan33519843

Expected Duration From 21th May 2013 to 23th May 20139:00 AM 6:00PMPlan of Action

We will test below 85 MW link upgrade Site to throughput, During test we need to download files from the FTP server. Maxmimum 80 Mbps from 1 sector.Site IDSite Nameplan date

21782178BAR21th May

21812181BAR21th May

22052205BUQ21th May

22232223JAN21th May

22782278JAN21th May

22552255JEB21th May

22182218JID21th May

21712171JNB21th May

21762176SAR21th May

20382038SHE21th May

22242224SHK21th May

22432243BNJ21th May

20542054BUD21th May

23272327BUD21th May

23372337BUD21th May

21172117DRZ21th May

22142214DRZ21th May

20332033MRK21th May

21822182MRK21th May

21872187MUG21th May

22702270MUG21th May

23392339QUR21th May

20972097AMJ21th May

22042204ARD21th May

23252325BUS21th May

20012001HID21th May

20472047MHQ21th May

21182118MHQ21th May

21192119MHQ21th May

22252225MHQ21th May

22612261MHQ21th May

22812281MHQ21th May

21322132SMJ21th May

22292229SMJ21th May

22482248ALI22th May

22922292ALI22th May

20782078BOO22th May

21772177HML22th May

23232323HML22th May

20412041RIF22th May

21472147RIF22th May

22282228RIF22th May

20952095TUB22th May

21312131TUB22th May

21792179TUB22th May

20562056ISA22th May

22212221ISA22th May

23342334ISA22th May

20222022SIT22th May

20582058SIT22th May

22022202SIT22th May

22162216SIT22th May

22312231SIT22th May

22852285SIT22th May

23162316SIT22th May

20032003JUF22th May

20042004JUF22th May

20052005JUF22th May

20902090JUF22th May

22272227JUF22th May

22422242JUF22th May

21082108KRB22th May

20492049MHZ22th May

23102310SNB22th May

21152115ZNJ22th May

23172317LZI23th May

23352335MLK23th May

23042304DAR23th May

23222322DUM23th May

21802180JAS23th May

20202020KMS23th May

23292329MEQ23th May

20392039HMD23th May

20642064HMD23th May

21112111HMD23th May

23192319HMD23th May

23302330HMD23th May

20442044KRZ23th May

20662066KRZ23th May

20792079SAD23th May

21212121SRK23th May

22262226SRK23th May

20112011UMH23th May

23282328UMH23th May

22952295WDI23th May

Method for Verification of ChangeNo change for site.Rollback CriteriaNone