Pembersihan Lapangan
Start: Mon 6/8/15 ID: 2
Finish: Mon 6/8/15Dur: 1 day
Res:
Pekerjaan Pondasi
Start: Thu 6/11/15 ID: 5
Finish: Sat 7/25/15 Dur: 27 days
Comp: 0%
Pekerjaan Lantai 1
Start: Mon 7/27/15ID: 9
Finish: Tue 11/10/15Dur: 89 days
Comp: 0%
Pekerjaan Beton
Start: Mon 7/27/15ID: 10
Finish: Wed 9/2/15Dur: 32 days
Comp: 0%
Pekerjaan Dinding
Start: Fri 10/9/15 ID: 15
Finish: Tue 11/3/15Dur: 21 days
Comp: 0%
Pekerjaan Plafon
Start: Fri 10/9/15 ID: 18
Finish: Fri 10/23/15Dur: 12 days
Comp: 0%
Pekerjaan Persiapan
Start: Mon 6/8/15 ID: 1
Finish: Thu 6/11/15Dur: 4 days
Comp: 0%
Page 1
Pekerjaan Lantai
Start: Sat 10/24/15ID: 21
Finish: Wed 11/4/15Dur: 10 days
Comp: 0%
Pekerjaan Cat
Start: Thu 11/5/15 ID: 23
Finish: Tue 11/10/15Dur: 5 days
Comp: 0%
Pekerjaan Lantai 2
Start: Thu 9/3/15 ID: 26
Finish: Wed 11/11/15Dur: 58 days
Comp: 0%
Pekerjaan Beton
Start: Thu 9/3/15 ID: 27
Finish: Thu 10/8/15Dur: 30 days
Comp: 0%
Pekerjaan Dinding
Start: Fri 10/9/15 ID: 31
Finish: Mon 11/2/15Dur: 20 days
Comp: 0%
Pekerjaan Plafon
Start: Fri 10/9/15 ID: 34
Finish: Tue 11/10/15Dur: 27 days
Comp: 0%
Pekerjaan Cat
Start: Thu 11/5/15 ID: 38
Finish: Tue 11/10/15Dur: 5 days
Comp: 0%
Page 2
Pekerjaan Atap
Start: Fri 10/9/15 ID: 41
Finish: Wed 11/11/15Dur: 28 days
Comp: 0%
Page 3
Membuat Gudang/Los
Start: Tue 6/9/15 ID: 3
Finish: Thu 6/11/15Dur: 3 days
Res:
Menggali Tanah
Start: Thu 6/11/15 ID: 6
Finish: Tue 6/16/15Dur: 5 days
Res:
Menurunkan Sumuran
Start: Wed 6/17/15ID: 7
Finish: Tue 6/30/15Dur: 12 days
Res:
Bouplank dan Pengukuran
Start: Tue 6/9/15 ID: 4
Finish: Wed 6/10/15Dur: 2 days
Res:
Page 4
Page 5
Page 6
Timbunan Kembali
Start: Wed 7/1/15 ID: 8
Finish: Sat 7/25/15 Dur: 10 days
Res:
Mencor Sloof
Start: Mon 7/27/15ID: 11
Finish: Fri 7/31/15 Dur: 5 days
Res:
Mencor Kolom
Start: Sat 8/1/15 ID: 12
Finish: Sat 8/22/15 Dur: 18 days
Res:
Page 7
Page 8
Page 9
Mencor Tangga
Start: Sat 8/29/15 ID: 14
Finish: Wed 9/2/15Dur: 4 days
Res:
Mencor Balok
Start: Mon 8/24/15ID: 13
Finish: Fri 8/28/15 Dur: 5 days
Res:
Page 10
Mencor Kolom
Start: Thu 9/3/15 ID: 29
Finish: Wed 9/23/15Dur: 18 days
Res:
Page 11
Page 12
Memasang Bata
Start: Fri 10/9/15 ID: 16
Finish: Mon 11/2/15Dur: 20 days
Res:
Memasang Rangka
Start: Fri 10/9/15 ID: 19
Finish: Wed 10/14/15Dur: 5 days
Res:
Page 13
Mencor Lantai 2
Start: Fri 9/25/15 ID: 28
Finish: Fri 10/2/15 Dur: 7 days
Res:
Mencor Balok
Start: Sat 10/3/15 ID: 30
Finish: Thu 10/8/15Dur: 5 days
Res:
Memasang Bata
Start: Fri 10/9/15 ID: 32
Finish: Mon 11/2/15Dur: 20 days
Res:
Memasang Rangka
Start: Fri 10/9/15 ID: 35
Finish: Wed 10/21/15Dur: 10 days
Res:
Page 14
Memasang Kuda-kuda
Start: Fri 10/9/15 ID: 42
Finish: Mon 10/26/15Dur: 14 days
Res:
Page 15
Plesteran
Start: Mon 10/19/15ID: 17
Finish: Tue 11/3/15Dur: 14 days
Res:
Memasang Penutup Triplek
Start: Fri 10/16/15 ID: 20
Finish: Fri 10/23/15Dur: 7 days
Res:
Page 16
Memasang Keramik dan Tegel
Start: Sat 10/24/15ID: 22
Finish: Wed 11/4/15Dur: 10 days
Res:
Mencat Dinding
Start: Thu 11/5/15 ID: 24
Finish: Tue 11/10/15Dur: 5 days
Res:
Plesteran
Start: Mon 10/26/15ID: 33
Finish: Mon 11/2/15Dur: 7 days
Res:
Memasang Penutup Triplek
Start: Thu 10/22/15ID: 36
Finish: Thu 10/29/15Dur: 7 days
Res:
Pekerjaan Lantai Keramik dan Tegel
Start: Fri 10/30/15 ID: 37
Finish: Tue 11/10/15Dur: 10 days
Res:
Page 17
Gording,Rusuk,Reng,Genteng dan Talang
Start: Tue 10/27/15ID: 43
Finish: Wed 11/11/15Dur: 14 days
Res:
Page 18
Page 19
Mencat Plafon
Start: Thu 11/5/15 ID: 25
Finish: Tue 11/10/15Dur: 5 days
Res:
Mencat Dinding
Start: Thu 11/5/15 ID: 39
Finish: Tue 11/10/15Dur: 5 days
Res:
Page 20
Mencat Plafon
Start: Thu 11/5/15 ID: 40
Finish: Tue 11/10/15Dur: 5 days
Res:
Page 21
Critical
Noncritical
Critical Milestone
Milestone
Critical Summary
Summary
Critical Inserted
Inserted
Critical Marked
Marked
Critical External
External
Project Summary
Highlighted Critical
Highlighted Noncritical
Page 22
Project: Triadi Bagus Gumilar 121Date: Sun 6/7/15