new construction above ground storage tanks - matcor, inc_.pdf
TRANSCRIPT
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
1/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 1/16
WORLDWIDE 1 215 348 2974 [email protected] Search
ABOUT NEWS RESOURCES CONTACT A CORROSION EXPERTHome Resources Technical Papers New Construction
Above Ground Storage Tanks
New Construction Above Ground
Storage Tanks
OVERVIEW:
This technical bulletin addresses the design and installation
of cathodic protection systems fornew construction above
ground storage tanks (ASTs). Cathodic protection (CP) is
typicallyapplied to all above ground storage tanks built on a
ring wall foundation to protect the externaltank bottom incontact with the soil/sand foundation. Smaller tanks built on
concrete slabfoundations typically do not have cathodic
protection applied to them.
In many locations, cathodic protection is mandated by local
regulations for tanks storinghydrocarbons orhazardous
materials; however, even in theabsence of such mandates,
goodengineering practice would generally dictate cathodic
protection.
Summary/Conclusion:
MATCOR typically recommends the use of linear anodes in a
concentric ring configuration asthe most reliable system
design for new construction above ground storage tanks,
combiningeconomy of material requirements with ease of
ALLSERVICES
ALL
PRODUCTS
http://www.matcor.com/products/http://www.matcor.com/products/http://www.matcor.com/services/http://www.matcor.com/companiescategory/company/http://www.matcor.com/news-releases/http://www.matcor.com/resources/case-studies/http://www.matcor.com/contact-corrosion-expert/http://www.matcor.com/http://www.matcor.com/http://www.matcor.com/products/http://www.matcor.com/services/http://www.matcor.com/resources/technical-papers/http://www.matcor.com/resources/http://www.matcor.com/http://www.matcor.com/contact-corrosion-expert/http://www.matcor.com/resources/case-studies/http://www.matcor.com/news-releases/http://www.matcor.com/companiescategory/company/http://www.matcor.com/mailto:[email protected] -
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
2/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 2/16
installation.
Galvanic vs. Impressed Current
Historically, various configurations of galvanic anodes,
including discreet anodes and ribbontype anodes, have beenused to protect AST bottoms. Experience has shown that
these systemsdo not provide the uniform current distribution
necessary over the entire CP system design lifeand result in
premature failure as the galvanic anodes consume. ASTs
require significantcurrent, which generally precludes the use
of galvanic anodes. Almost all AST CP systemstoday are
designed with impressed current systems to provide the
current required over a longperiod of time.
Design Information:
The following information is required to develop a CP design
for ASTs:
Tank Diameter
This is necessary to calculate the surface area to be
protected.
Tank Bottom Coating
Typically tank bottoms are bare plate steel, but in
some cases the plate steel may becoated on the bottom,
which reduces the current required for cathodic protection.
CP isstill recommended for tanks with coated bottoms.
Current Density Required
Typical design current density requirements of 1
mA/ft2 (10 mA/m2) are sufficient toachieve NACE criteria forcathodic protection (see discussion on operating
temperature).
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
3/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 3/16
Depth of Anode
The separation distance between the anode and the
tank bottom affects current spread andanode spacing.
Sand/Soil Resistivity
This information is necessary to estimate overall
system resistance necessary to properlysize the rectifier
voltage. In many cases, it may make sense to install the
anode systemand test the actual circuit resistance using a
portable rectifier or car battery beforecommitting to a
specific rectifier size.
Tank Operating Temperature
Corrosion rates increase significantly with elevated
temperature, necessitating morecurrent. MATCOR uses the
following temperature correction formula for its CP
designsfor heated tank bottoms: for every 10 C above 30 C
the current requirement increases25%.
Area Classification
Rectifiers and junction boxes must be designed with
suitable enclosures for the areaclassification where they will
be installed. Often, these can be located in non-
classifiedareas with minimal additional cost of cable while
saving significantly on the cost of theenclosures and classifiedcomponents.
Secondary Containment Liners
If polyethylene or other such plastic liners are to be
placed underneath the tank, theseliners act as a barrier to the
flow of current and the anodes must be placed between
theliner and the tank bottom. If Claymax or other conductive
type liners are to be used, theanodes do not have to be
placed between the liner and the tank bottom.
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
4/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 4/16
Design Life
Typical design life for new construction ASTs is 25 to
30 years. It is important to notethat the actual operating life
of ASTs often exceeds this value and depending on
thedesign of the tank, its location, and the selection of a
containment liner. Replacement ofthe CP system may be
difficult to impossible so some consideration should be given
tothe economic value of extending the design life. For
MATCORs SPL-FBR concentricring configuration, the
incremental anode cost to go from 30-year design life to 50-
yeardesign life is approximately 25% additional anode cost,
with no increase in installationcosts, making this a very
attractive alternative.
CP Configurations for New Construction ASTs
Shallow Distributed Anodes around Tank Periphery:
One common design approach to AST bottom CP is to installa shallow distributed pointanode system around the
periphery of the tank (Figure 1). These are typically augured
into depths of 5-10 feet. This design approach only works
when there is no electricallyisolating secondary containment
liner under the tank.
For these designs, the critical issue is assuring that sufficient
current reaches the center ofthe tank. Above ground storage
tank bottoms are large bare surfaces requiring a lot ofcurrent.
To assure that current distributes properly, the anode depth
and distance fromthe tank are critical. Shallow peripheral
anodes are not able to throw current to the centerof all but
the smallest of ASTs.
MATCOR generally does not recommend shallow
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
5/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 5/16
peripherally distributed anodes forASTs with tank diameters
exceeding 20 ft (6 m) due to the quantity of anodes
requiredand the risk of poor current distribution to the center
of the tank.
Deep Well Anode SystemsThis approach is based on using one or more deep
well anode systems located well belowthe tank bottom to
provide current uniformly to the tank bottom. This approach
has somelimitations in heavily congested plant environments
where current can flow to otherburied structures. When
multiple deep wells are employed to protect more than one
tankin a cluster, care must be taken to assure proper current
distribution.
As with any deep well, there are concerns with drilling
(typically 150+ feet to bottom ofhole) including access issues
for a drill rig, environmental concerns, permitting
andhandling of drilling spoils. Even with a deep wellapproach, when dealing with newconstruction, reference
electrodes should be installed under each tank.
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
6/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 6/16
Many operators prefer a close coupled dedicated CP system
for each tank rather than theblanket coverage afforded by a
deep well system.
Should the design for the new construction tank utilize a
containment liner that shieldscurrent (i.e. polyethylene liner),
the deep well anode system cannot be used.
Distributed Anodes Below Tank Bottom
While not as common today, many older designs utilized
individual anodes laidhorizontally along the tank bottom and
connected parallel to header cables exiting thering wall. The
economics of this design, both in terms of installation costs
and materialcosts, are not favorable and this design has been
dropped in favor of either a grid systemor linear anodes in a
parallel concentric ring arrangement.
The Grid System
Developed, patented and heavily promoted by Corrpro, this
proprietary system involveslaying out parallel titanium
conductor bars and then running mixed metal oxide
(MMO)ribbon anode perpendicular to the conductor bars.
The MMO ribbon anode is field spotwelded to the titanium
conductor bar to provide both mechanical andelectricalconnections. Wherever the titanium conductor bars
cross, they too must be field weldedtogether. Power feeds
(preassembled cables with a flat plate to connect to the
conductorbar) are secured to the titanium bar in multiple
locations and routed to the ring wallpenetration.
Patented in 1991, this system continues to be used by
Corrpro; however, it is a labor andQA/QC intensive
installation process requiring significant field welding and on-
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
7/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 7/16
sitetesting to assure electrical continuity. The attachment of
the power feeds to the titaniumgrid is critical to the system
reliability. From a design perspective, the spacing of
theanodes and conductor bars must be sufficient to assure
even current distribution.
SPL-FBR Linear
Anode Systems
Unlike the Grid
system promoted
byCorrpro,
MATCORs SPL-
FBR linearanode
system for AST
tanks can be
factoryassembled
to eliminate the
need for anyfield
fabrication, which
greatly
simplifiesinstallation and reduces QA/QC issues,eliminating
field welds and power feedconnections that are relied upon
with theGrid system to assure electricalcontinuity andsystem integrity.
The principal advantage of the linearsystem is that everything
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
8/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 8/16
under the tank isfactory assembled and tested prior
toinstallation and the only installation effortis to lay the
anode assemblies in accordancewith the design drawings and
installationinstructions. This provides for anexceptionally
simple installation whileassuring the highest system
reliability;installation costs are minimal. Please referto
MATCORs Installation, Odperation andMaintenance (IOM)
Manual for a detailedinstallation description with pictures.
There are two primary configurations forlinear anodes under
tank bottoms as shownin Figure 2. The parallel linear
anodearrangement has multiple parallel anodesegments,which are fed from each end ofthe anode. The anode
connections are fieldspliced to loop cables, which terminate
attwo anode junction boxes.
The use of concentric rings offers two keyadvantages over
parallel anode segments. The first advantage is that this
configurationdoes require junction boxes on both sides of
the tank, thus eliminating one of the anodejunction boxes
and reducing the cabling required to run from two anode
unction boxesback to the transformer/rectifier unit. The
second key advantage to this configuration isthat it
eliminates the need for two field splices for each anode
segment. Each ring can bemanufactured with the appropriate
length of header cable to run each end directly to thesingle
anode junction box. These field splices are weak links subject
to premature failureover the life of the anode system.
As with any system, spacing between anode segments is
another key design element.MATCORs experience with ring
configurations is extensive and we have determinedthrough
numerous installations and our own in-house testing that for
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
9/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 9/16
tank bottomapplications with bare bottom plates and an
anode depth of 1 foot, concentric rings with aspacing of 10
feet provide thorough current distribution. When the anodes
can be placeddeeper than 1 foot, the anode spacing can be
extended. Based on the 1 foot depth, typicalambient
temperature tanks can be protected for 30+ years with 16
mA/ft linear anode,while a 50+ year design life is typically
achieved with a 25 mA/ft rated anode with amodest 25%
increase in the anode cost.
Provisions for Testing
With any CP system for tank bottoms, it is critical that
provisions for testing be installed with theanode system.
Once the tank is erected, making accurate potential
measurements at variouslocations along the tank can only be
accomplished if reference electrodes have been
installedbelow the tank. Typically, copper-copper sulfate (Cu-
CuSO4) reference electrodes are installedin strategic
locations underneath the tank. These reference electrodes
are often mistakenly calledpermanent reference
electrodes; however, they are not permanent as over timethe coppercoppersulfate solution becomes contaminated
and ceases to provide accurate information. Oncea baseline
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
10/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 10/16
for performance is established over asufficient operating
period, maintaining theappropriate current output to achieve
NACEcriteria is all that is required.
In some cases,
clients may also
specify
dualreference
electrodes such
as both zinc and
coppercoppersulfate. While the zinc reference electrodesare
not as consistent, they provide a much longeroperating life
and can be calibrated against the copper-copper sulfate
electrodes.
In addition to the fixed reference electrodes, it isalso
common to provide a reference electrodetube/conduit
underneath the tank bottom to allowsliding of a calibrated
reference electrode throughthe monitoring tube to take
potential readings.These can also function as leak detection
tubes.
Maintenance/Inspection
MATCOR typically recommends annual testing/inspection of
the tank CP system by a qualifiedNACE CP level 1 or higher
technician familiar with testing CP systems for ASTs. As with
anyimpressed current system, monthly rectifier checks should
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
11/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 11/16
be performed by plant maintenance toassure that the
rectifier is on and that the voltage and current outputs remain
stable.
Appendix A MATCORS DESIGN PROGRAM
System Design:
Once all of the design parameters have been established,
MATCORs design program uses thefollowing process to
create a completed design.
1. Basic Calculations
a. Tank Bottom Surface Area simple geometric calculation
of the area of acircle. If the tank bottom is coated MATCOR
assumes a 75% coatingefficiency (25% bare) as some coating
degradation can be expected at allof the weld seams. b.
Current Requirement the bare surface area times the
temperaturecorrected current density requirement provides
the total design currentrequired.
2. Anode Spacing MATCOR typically assumes that the
anode will be located aminimum of 1 foot below the tank
bottom. Based on 1 foot depth, MATCORuses 10 foot
spacing between anodes. This is not based on any
theoreticalmodeling but has been derived empirically by
testing performed by MATCORand validated on numerous
actual applications. MATCOR has researched theavailable
literature and has not found any published data or theoretical
modelingthat can be used to determine current distribution
for concentric rings beneath astorage tank bottom. For
depths greater than 1 foot, MATCOR increases theanode
ring spacing at a rate of 0.5 feet/additional foot of depth.
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
12/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 12/16
Occasionally, clients have askedMATCOR to provide a
theoreticalbasis or some sort of calculation toconfirm the
spacing of the anodes.NACE, in its CP3 design
course,provides a geometric guideline of2*tan60 for spacing
of galvanic ribbonanodes under a tank bottom to
assuredistribution; however, we have foundno reasonable
scientific or
theoreticalexplanation as
to how this value
wasselected (Figure 4).
We have discussed thiswith NACE instructors
and Senior Corrosion
Engineersand they cannot
provide any justification for this calculation. It just makes for
anice geometric value.
MATCOR has tested numerous tanks with impressed current
CP systems using 10foot spacing between anodes with a
depth (d) of 1 foot. This equates to ageometric equation of
2d tan(78.7), which is not as elegant a number as 60. Butwe
know from our testing using reference electrodes that have
been placed inclose proximity to the tank bottom that
current distributes sufficiently to meetNACE criteria between
ring segments.
3. Current Capacity once the preliminary anode spacing is
determined, the totalnumber of rings can be calculated with
the rings spaced equally apart inconcentric circles. The total
anode length is then calculated. The current rating ofthe
anode is a function of the total current required divided by
the anode length.For ambient temperature tanks, using 10
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
13/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 13/16
foot spacing, the typical design requiresMATCORs SPL-
FBR-16 mA/ft anode and yields a 30+ year design life.
Thesame design using MATCORs 25 mA/ft anode will
generally provide for a 50+year design life for only a modest
increase in material cost.
For elevated temperatures MATCOR calculates a
temperature correction factorbased on increasing the current
required 25% for every 10 C above 30 C. Toaccommodate
the higher current requirements at elevated temperatures,
either ahigher output anode is necessary or tighter spacing
with more anode length isrequired. MATCORs designprogram allows for the anode spacing to beadjusted to
optimize the anode length and anode rating as needed to
meet thedesired design life requirements.
4. Anode Resistance Calculations each anode ring is
connected parallel to oneanother through the anode junction
box to the rectifier. The resistance of eachanode ring is
calculated using Dwights equation for a ring of wire:
where:
R= resistance of each ring
? = soil resistivity
D = diameter of ring
d = diameter of anode
s = twice the depth of anode
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
14/16
-
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
15/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
http://www.matcor.com/resour ces/technical- papers/new-construction-ground- stor age- tanks/ 15/16
Current Density
Current Required amps 11.3
Total Number of
Rings
6
Anode Spacing ft 10
Anode Selection 16 mA/ftAnode Life (est) yrs 32
Total Resistance ohms 2.8
Rectifier Sizing voltage 40
amperage 15
Total Anode
Length
ft 1130.9
Total CableLength
ft 600
Ring
#
Diameter
ft
Linear
ft
Total
ft
Cable Tail Length
ft
1 10 31 31 150
2 30 94 126 1303 50 157 283 110
4 70 220 503 90
5 90 283 785 70
6 110 346 1131 50
Typical AST Tank Ring Cathodic Protection System
AST Cathodic Protection System Detail Drawing
ollow Us
Ring Configuration
http://twitter.com/#!/TweetMATCORhttp://www.facebook.com/pages/Matcor-Inc/161353057208798http://www.youtube.com/user/MATCORmediahttp://www.linkedin.com/company/1149301http://www.matcor.com/matcor-kynex-technology/http://www.matcor.com/company/manufactured-usa/http://www.matcor.com/company/matcor-quality/http://www.matcor.com/matcor-celebrates-40-years-protecting-worlds-infrastructure-corrosion/http://matcor.com/wp-content/uploads/2015/01/ast-cathodic-protection-system-detail-drawing.pdfhttp://matcor.com/wp-content/uploads/2015/01/typical-ast-cathodic-protection-system-tank-rings.pdf -
7/25/2019 New Construction Above Ground Storage Tanks - Matcor, Inc_.pdf
16/16
21/5/2016 New Constr uction Above Gr ound Storage Tanks - Matcor, Inc.
2016 MATCOR, Inc.