New Psychiatric Facility at Fulton State Hospital
A report to the Missouri Mental Health Commission10.09.2014
1
![Page 2: New fulton state hospital presentation to mental health commission](https://reader033.vdocument.in/reader033/viewer/2022042816/559417911a28ab9e468b47ce/html5/thumbnails/2.jpg)
2
![Page 3: New fulton state hospital presentation to mental health commission](https://reader033.vdocument.in/reader033/viewer/2022042816/559417911a28ab9e468b47ce/html5/thumbnails/3.jpg)
Scope
• 300-Bed High Security
Forensic Psychiatric
Hospital
• Infrastructure to support an
additional 258 Beds within
Existing Buildings
• Dietary
• Materials Management
• Environmental Services
• Computer Information
Systems
• Maintenance / Shops
• Energy Control Center
(ECC)
• Administration
3
![Page 4: New fulton state hospital presentation to mental health commission](https://reader033.vdocument.in/reader033/viewer/2022042816/559417911a28ab9e468b47ce/html5/thumbnails/4.jpg)
Schedule & budget
• Construction Start in Spring
2015 with the New Fulton
State Hospital ready for
occupancy before
December 31, 2017
Construction $176.5 M
Planning & Design $13.0 M
Other Project Costs $21.5 M
Total $211.0 M
4
![Page 5: New fulton state hospital presentation to mental health commission](https://reader033.vdocument.in/reader033/viewer/2022042816/559417911a28ab9e468b47ce/html5/thumbnails/5.jpg)
Goals• Safety and security with
dignity
• Design a “Building for Generations”
• Design for future flexibility
• High security environment
• Recovery-based psychiatric care environment that facilitates and communicates state-of-the-art treatment
• Attract and retain the best staff to work and train
5
![Page 6: New fulton state hospital presentation to mental health commission](https://reader033.vdocument.in/reader033/viewer/2022042816/559417911a28ab9e468b47ce/html5/thumbnails/6.jpg)
Program
• 300 Beds
• Deployed in 12 Living Units
of 25 Beds Each
• 2 to 4 Living Units per
Community
• Treatment Mall
• Dietary
• Materials Management
• Environmental Services
• Computer Info Systems
• Maintenance / Shops
• Energy Control Center
• Administration
413,000 Gross Square Foot Program that includes
6
![Page 7: New fulton state hospital presentation to mental health commission](https://reader033.vdocument.in/reader033/viewer/2022042816/559417911a28ab9e468b47ce/html5/thumbnails/7.jpg)
7
![Page 8: New fulton state hospital presentation to mental health commission](https://reader033.vdocument.in/reader033/viewer/2022042816/559417911a28ab9e468b47ce/html5/thumbnails/8.jpg)
8
![Page 9: New fulton state hospital presentation to mental health commission](https://reader033.vdocument.in/reader033/viewer/2022042816/559417911a28ab9e468b47ce/html5/thumbnails/9.jpg)
Site conceptStand Alone Boiler Plants for
DESE-School for the Deaf
and DOC-Cremer
Maintain Power Plant,
Dietary, Materials Mgmt and
Maintenance Services Until
Completion of Permanent
Replacements
9
![Page 10: New fulton state hospital presentation to mental health commission](https://reader033.vdocument.in/reader033/viewer/2022042816/559417911a28ab9e468b47ce/html5/thumbnails/10.jpg)
Site concept
Service Centers: Dietary,
Materials Management,
ECC, Maintenance
Start: Spring, 2015
10
Begin demolition
![Page 11: New fulton state hospital presentation to mental health commission](https://reader033.vdocument.in/reader033/viewer/2022042816/559417911a28ab9e468b47ce/html5/thumbnails/11.jpg)
Site conceptService Centers: Dietary,
Materials Management,
ECC, Maintenance
Complete:
Summer, 2016
Portions of Hospital Under
Construction in Spring,
2016
11
![Page 12: New fulton state hospital presentation to mental health commission](https://reader033.vdocument.in/reader033/viewer/2022042816/559417911a28ab9e468b47ce/html5/thumbnails/12.jpg)
Site conceptConstruct Northeast
Quadrant of Hospital
Complete:
December 2017
12
![Page 13: New fulton state hospital presentation to mental health commission](https://reader033.vdocument.in/reader033/viewer/2022042816/559417911a28ab9e468b47ce/html5/thumbnails/13.jpg)
Site conceptDemolish Biggs
Spring 2018
13
![Page 14: New fulton state hospital presentation to mental health commission](https://reader033.vdocument.in/reader033/viewer/2022042816/559417911a28ab9e468b47ce/html5/thumbnails/14.jpg)
Questions?