new horizons online project management … 3/pmp day 3.pdf(pmp®) - fifth edition pmbok day 3...
TRANSCRIPT
NEW HORIZONS ONLINE LIVE
Project Management Professional
(PMP®) - Sixth Edition PMBOK
DAY 3
2
3
4
5
6
7
8
WP
WP
Activities
9
10
11
12
13
Precedence Diagramming
methods
Activity on Node (AON)
A B
C
D
14
Precedence Diagram
15
Precedence Diagram
1
16
Precedence relationships
17
18
19
20
21
Three point estimating
Optimistic Most Likely Pessimistic
Three point estimating
Optimistic Most Likely Pessimistic
Triangular Distribution
(O+ML+P)/3
Three point estimating
Optimistic
Most Likely
Pessimisticσ1 σ1 σ2σ2
σ2 = 95%
Three point estimating
Optimistic
Most Likely
Pessimisticσ1 σ1 σ2σ2
Beta Distribution
(O+4ML+P)/6
σ2 = 95%
Bottoms Up Estimating
26
27
28
29
Critical Path Method
A
2
K
2
J
7
I
2
H
5
G
3
F
4
E
5
D
4
C
3
B
2
Critical Path Method
A
2
K
2
J
7
I
2
H
5
G
3
F
4
E
5
D
4
C
3
B
213
16
13
14
18
Critical Path Method
A
2
K
2
J
7
I
2
H
5
G
3
F
4
E
5
D
4
C
3
B
213
16
13
14
18
Critical Path
Lead
• A lead is a change in a logical
relationship that allows the successor
activity to start before the predecessor
activity ends in a FS relationship. A lead
is implemented when you need to
accelerate a successor activity in order
to shorten the overall project schedule.
33
Effects of Lead in an FS
Relationship
34
Lag
• A lag is a delay in the start of a
successor activity. Some relationships
require a lag before a subsequent
activity can begin. Lags are determined
by an external or mandatory dependency
and may affect activities with any of the
four precedence relationships.
35
Effects of Lag in an FS
Relationship
36
37
39
40
41
42
43
44
45
46
Other PMP® Topics – Cost Ranges
Rough Order of Magnitude (ROM) (often
done in the initiating process group):
-25% to +75%
Definitive (also called Control, often done late
in the planning process group):
-5% to +10%
48
49