Leicester SchoolBuilding ProjectAugust 5, 2020
(Virtual) Community Forum # 5Leicester School
NEWSCHOOL
![Page 2: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/2.jpg)
Welcome
Zoom Meeting Instructions:
•To save on bandwith, video and audio will turned off for all participants during the presentation.
•Please hold questions until after the presentation, unless you need clarification of something that was said. If you need clarification, please submit a question through the “chat” feature or text 508.859.0080.
•To ask a question: You can type a question through the “chat” feature at the bottom of your screen. Questions submitted through “chat” will be read when the presentation is over. All questions should be submitted to Jeff Berthiaume.
•Questions can be submitted after the meeting via the “Contact” tab on the project website: https://leicesterbuildingproject.com/contact/
![Page 3: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/3.jpg)
Agenda
Mission
Schedule Overview
Building Design
Site Design
Cost
*This 25-30 minute presentation will be followed by 30 minutes for questions and answers.
![Page 4: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/4.jpg)
Mission - Education
![Page 5: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/5.jpg)
Mission - Building
![Page 6: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/6.jpg)
School Building Committee Members
Mark Armington Community Member and EngineerJeff Berthiaume Director of Technology and Digital LearningTina Boss School Principal, Elementary School Harry Brooks SBC Chair, Member Board of SelectmenChris Clark Community Member and ParentBrian Cooper Facilities DirectorChris Fontaine School Principal, Leicester Middle SchoolDavid Genereux Town Administrator, SBC who is MCPPO certifiedTom Lauder School Committee Kristina Looney Leicester MS Teacher, Music Education Cady Maynard Director of Finance and OperationsDennis McGrail Finance Advisory Board and Parent Paul McCarthy Community Member and ParentJim Reinke Committee Member/ContractorMarilyn Tencza School SuperintendentEileen Boisvert Community Member and ParentTim Hickey Community Member and Parent
![Page 7: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/7.jpg)
Schedule Overview - Next Steps
August 28, 2019
August 2019
February 2020
April 2020
September 26, 2020
November 3, 2020
MSBA Board Vote: Preferred Alternative
Begin Schematic Design
Complete Schematic Design to MSBA
MSBA Board Vote:Project Scope and Budget Agreement
Town Meeting – Funding Approval
Election
![Page 8: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/8.jpg)
Building Design
![Page 9: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/9.jpg)
Exterior View Towards Main Entry
![Page 10: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/10.jpg)
Exterior View at Courtyard
![Page 11: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/11.jpg)
Preferred Solution Key Concepts
2 Schools, 1 Roof Grade NeighborhoodsFlexible Learning Space
![Page 12: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/12.jpg)
N
First Floor Plan
![Page 13: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/13.jpg)
N
First Floor Plan
Outdoor Learning
![Page 14: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/14.jpg)
N
Second Floor Plan
![Page 15: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/15.jpg)
N
Third Floor Plan
20
as a base for Citizen Science program which invites the public to participate in events such as Explore the Shore, Spot the Swallows and a 24-hour BioBlitz where the public joins with Zoo volunteers and Naturalists to range throughout the park and identify specific forms of life as they seek to catalogue how many different living organisms make their home in the park.
Educational Results
The facility elevates the partnerships between SAMi, PDZA and Metro Parks Tacoma. Students are connecting with the school’s partners and the surrounding resources. The facility provides a home base for students to range out and learn through exploration.
“We’re central in the park so it’s very helpful. We’re not too far from the main headquarters for the Metro Parks in the Park. Then also, we’re right next to the zoo so we have a very good relationship. The Zoo actually has some office spaces in the ELC so we’re able to walk by and build a strong relationship.
All the nooks are very helpful. They give you small little areas to get out of the classroom and go work with your group.” - Zion Welton, Senior, SAMi
“There are windows all around us and so since you can look directly out and see the trees, it still feels like you’re part of the forest. The ELC is within walking distance from a lot of places where SAMi kids go, like the portables you can walk to, down to the marina you can walk to, you can walk to the pagoda and it’s right next to the zoo. It doesn’t take away from the park feeling at all, it just adds to it.
SAMi has become much, much more sociable because of the new building. It’s a really cool thing to see.” - Greg Smith, Sophomore, SAMi
“The big steps are like a seating area. The presenter stood at the bottom of the stairs and the students could sit and watch the presenter, so it is a really versatile space.
The ELC Commons is a really cool space because it is really open and accessible to everyone.” - Huyen-Tram Nguyen, Sophomore, SAMi
![Page 16: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/16.jpg)
Benefits to the Community
•Increased classroom size
•Flexible learning spaces
•Special education spaces that meet the needs of the district
•Community use: Regulation size gym, health and wellness studio, cafetorium
•Dedicated outdoor air and exhaust to each space with building management system controls
•Increased safety and security features
![Page 17: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/17.jpg)
Site Design
![Page 18: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/18.jpg)
N
Site Plan - Site Entrances
![Page 19: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/19.jpg)
N
Site Plan - Building Entrances
![Page 20: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/20.jpg)
N
Site Plan - Primary Circulation
![Page 21: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/21.jpg)
N
Site Plan - Secondary Circulation
![Page 22: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/22.jpg)
N
Playing Fields
![Page 23: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/23.jpg)
N
Playing Fields Football, Soccer, Field Hockey, Track and Field
![Page 24: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/24.jpg)
N
Playing Fields Youth Soccer, Basketball, Baseball, Varsity Soccer, Track and Field
![Page 25: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/25.jpg)
N
Playing Fields Softball, U-12 Soccer, Football Practice, Track and Field
![Page 26: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/26.jpg)
N
Playing Field AnalysisTennis
![Page 27: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/27.jpg)
N
Accessible Pedestrian Paths
![Page 28: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/28.jpg)
N
Outdoor Learning
![Page 29: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/29.jpg)
N
Play Areas
![Page 30: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/30.jpg)
Subsurface Exploration Plan
![Page 31: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/31.jpg)
Geotechnical Analysis
•The Geotechnical Engineer has noted that the readings are normal for the site given the soil type and grading.
•One additional reading is scheduled to be taken during the week of October 19th.
•Ground Water Monitoring Performed to Date:
Date Time Elapsed Time
Depth from Road Box
(feet)
Groundwater EL. (feet)
12/06/19 1:30 PM Initial 6.0 +987.7
01/02/20 4:45 PM 27 Day(s) 4.8 +988.9
01/06/20 4:20 PM 31 Day(s) 1.2 +992.5
04/23/20 4:22 PM 139 Day(s) 1.7 +992.0
07/23/20 3:00 PM 230 Day(s) Unreadable
Date Time Elapsed Time
Depth from Road Box
(feet)
Groundwater EL. (feet)
12/06/19 2:30 PM Initial 5.0 +986.8
01/02/20 5:05 PM 27 Day(s) 1.9 +989.9
01/06/20 4:30 PM 31 Day(s) 1.0 +990.8
04/23/20 4:24 PM 139 Day(s) 1.6 +990.2
07/23/20 3:05 PM 230 Day(s) 6.3 +985.5
MA-104 MA-106
![Page 32: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/32.jpg)
KEY:
D Stormwater Discharge Point
![Page 33: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/33.jpg)
NEWSCHOOL
![Page 34: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/34.jpg)
![Page 35: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/35.jpg)
![Page 36: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/36.jpg)
KEY:
A
B
C
D
Underground Detention
Bioretention Basin
Infiltration Trenches for Roof Drains
Stormwater Discharge Point
![Page 37: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/37.jpg)
BETA Peer Review Summary
•At the schematic design phase, the design provides sufficient detail regarding the disposition of site-generated stormwater runoff and will satisfy MassDEP Stormwater Management Regulations.
•The proposed utility layouts (sewer/water/drain/electric) are shown schematically and appear reasonable. Additional information including invert elevations will be provided during later design phases to verify that no conflicts exist between the various utilities.
•The Geotechnical study of the site, while performed for foundation analysis, sufficiently
identifies the existing soil conditions that have likely contributed to the surface saturation issues encountered during wet weather periods.
•The proposed site grading plans demonstrate that the proposed surface grading of the site
will allow it to drain properly, and that surface stormwater runoff can be effectively managed.
![Page 38: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/38.jpg)
Benefits to the Community
•Improved site and water drainage
•Safe and secure bus, vehicle, and pedestrian circulation around the site
•Improved playing fields
•Outdoor Learning
![Page 39: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/39.jpg)
Cost
![Page 40: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/40.jpg)
MSBA School Construction Costs
![Page 41: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/41.jpg)
Anticipated Taxpayer Cost
![Page 42: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/42.jpg)
Ineligible vs. Eligible Costs
![Page 43: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/43.jpg)
MSBA Total Project Costs
![Page 44: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/44.jpg)
Site Costs
![Page 45: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/45.jpg)
“No” Vote Scenario
What happens if the Project is not approved at the Special Town meeting on September 26, 2020?
•Restart the MSBA process – likely 8+ years before new building occupied
•Leicester will lose this opportunity for State finding, which is currently close to 65% of eligible project costs
•Leicester Public Schools will need to submit a new Statement of Interest to the MSBA and await a second invitation to re-enter the Feasibility Study phase
•Renovations of existing elementary and middle schools will need to be done, with no MSBA financial support: +/- $31M (State share = $0) *
•All costs will only increase in the future at a rate of 3% - 4% per year
•Annual maintenance and depreciation costs continue to increase and will need to be addressed
*from Johnson Roberts Maintenance Report 2014 with project cost for 2019, 3% escalation/year
![Page 46: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/46.jpg)
Benefits of Building a New School
Efficiency
Safety
Community Improvement
Increased Property Value
Community Use
Financially Responsible Choice
![Page 47: NEW SCHOOL - leicester.projects.nv5.com · 8/5/2020 · Welcome Zoom Meeting Instructions: • To save on bandwith, video and audio will turned off for all participants during the](https://reader034.vdocument.in/reader034/viewer/2022052001/6013e78f12f4aa77180cf8c9/html5/thumbnails/47.jpg)
More Information: leicesterbuildingproject.com
Questions: leicesterbuildingproject.com/contact