new south africa enterprise development pilot project · 2019. 6. 29. · access to technology...
TRANSCRIPT
AFRICAN DEVELOPMENT BANK
SOUTH AFRICA
ENTERPRISE DEVELOPMENT PILOT PROJECT
APPRAISAL REPORT
OSHD/SARC DEPARTMENTS
April 2015
TABLE OF CONTENTS
Currency Equivalents – Weights and Measures – Acronyms and Abbreviations – Grant
Information – RB Log-frame
i – iv
1. INTRODUCTION ......................................................................................................................................... 1
1.1 Background........................................................................................................................................... 1 1.2 Project Goal and Objective ................................................................................................................... 2 1.3 Sector Responsible for Preparing the Request ...................................................................................... 3 1.4 Justification........................................................................................................................................... 3
2. SUMMARY DESCRIPTION OF THE PILOT PROJECT ........................................................................... 5 2.1 Project Components .................................................................................................................................. 5 2.2 Expected Outputs .................................................................................................................................. 6
3. COST AND FINANCING OF THE PILOT PROJECT ................................................................................ 6 3.1 Project Cost .......................................................................................................................................... 6 3.2 Financing Plan ...................................................................................................................................... 7 3.3 Cost Estimates by Components ............................................................................................................ 7
4. PROCUREMENT .......................................................................................................................................... 7 4.1 Procurement of Services ....................................................................................................................... 7 4.2 Procurement of Goods .......................................................................................................................... 8 4.3 Procurement of Training ....................................................................................................................... 8
5. IMPLEMENTATION OF THE PILOT PROJECT ....................................................................................... 8 5.1 Implementation Schedule ..................................................................................................................... 8 5.2 Annual Work Programme and Procurement Schedule ......................................................................... 9 5.3 Executing Agency ................................................................................................................................ 9 5.4 Supervision and Monitoring ............................................................................................................... 10
6. FINANCIAL MANAGEMENT AND DISBURSEMENT ARRANGEMENTS ........................................ 10 6.1 Terms of Financing ............................................................................................................................. 10 6.2 Suspension of Disbursement .............................................................................................................. 10 6.3 Legal Instruments and Authority ........................................................................................................ 11
7. CONCLUSIONs AND RECOMMENDATIONS ........................................................................................... 11
ANNEX 1: MIC GRANT REQUEST .................................................................................................................... I ANNEX 2: Detailed Description of Project and ToRs .......................................................................................... V ANNEX 3: Detailed Cost Estimates ................................................................................................................. XIV ANNEX 4: FINANCIAL MANAGEMENT AND DISBURSEMENT ARRANGEMENTS ........................... XV ANNEX 5: PROCUREMENT ARRANGEMENTS AND OUTLINE PROCUREMENT PLAN ................ XXIII ANNEX 6: SOUTH AFRICA DISTRICT MAP ........................................................................................... XXVI
i
CURRENCY EQUIVALENTS
As of July 2014
1 Unit of Account (UA) = 16.3903 South Africa Rand (ZAR)
FISCAL YEAR
1 April – 31 March
WEIGHTS AND MEASURES
1 metric ton = 2204 pounds (lbs)
1 kilogram (kg) = 2.200 lbs
1 meter (m) = 3.28 feet (ft)
1 millimeter (mm) = 0.03937 inch
1 kilometer (km) = 0.62 mile
1 hectare (ha) = 2.471 acres
ii
ACRONYMS AND ABBREVIATIONS
AfDB : African Development Bank
BDS Business Development Services
DPIS : Detailed Pre-Investment Study
DPE : Department of Public Enterprise
FC Foreign Currency
dti Department of Trade and Industry
GoSA : Government of South Africa
ICT : Information and Communication Technologies
LTSP Long Term Strategic Plan
LC Local Currency
LED Local Economic Development
MIC : Middle Income Countries
RFP : Request for Proposal
SADC : Southern African Development Community
SIF Specialized Industrial Facility
SIP Specialized Industrial Platform
SIPS : Strategic Infrastructure Projects
SLA : Service Level Agreement
SMME Small Micro and Medium Enterprises
ToR : Terms of reference
UA : Unit of Account
ZAR : South African Rand
SA : South Africa
iii
GRANT INFORMATION
Client’s Information
RECIPIENT: Republic of South Africa
IMPLEMENTING AGENCY: The Department of Trade and Industry
Financing Plan
Source Amount Instrument
ADB UA 1, 200,000 MIC Grant
Government UA 258,000 GoSA
Total Cost UA 1,458,000
ADB’s Key Financing Information
MIC Grant Currency UA
Timeframe – Main Milestones (expected)
Submission of MIC Grant to Country teams : 31/07/2014
MIC Grant Approval : 25/02/2015
Effectiveness : 31/03/2015
Last Disbursement : 30/06/2018
iv
RESULTS-BASED LOGICAL FRAMEWORK
Country and project name: South Africa: Enterprise Development Support Project
Purpose of the project: To contribute towards job creation, social inclusion and the reduction of the gender poverty
gap, through supporting skills, infrastructure and enterprise development in South Africa.
RESULTS CHAIN
PERFORMANCE INDICATOR MEANS OF
VERIFICATION
RISKS/MITIGATION
MEASURES Indicator (including CSI)
Baseline Target
IMP
AC
T Reduced unemployment
and poverty incidence
a) Poverty Incidence
b) Gender poverty gap
c) Unemployment rate d) Gender gap in labour
force participation
a) 45.5% (2011)
b) 30% (2013)
c) 25.2% (2013)
d) 14% (2012)
a) 35% (2020)
b) 20% (2020)
c) 18% (2020)
d) 9% (2020)
Statistics South
Africa Reports.
OECD Reports
National Treasury
Annual reports
OU
TC
OM
ES
1. Improved capacity of
Local Municipalities in
planning and
implementing LED
Programmes.
1.a: % increase in target
Municipalities integrating
LED in their budgets;
1.b: % increase in target
Municipalities
implementing LED plans
jointly with Mining
Companies
0% (2013)
0% (2013)
25% in 2017
25% in 2017
Quarterly Progress
Reports;
dti Annual Reports
Risk: Priority of Local
Economic Development
(LED) reduces.
Mitigation: the dti will
use the stakeholder events
under the Project to
promote LED.
Risks: Inadequate
financial resources for the
maintenance of
Specialized Industrial
Facilities (SIF) set up in
pilot FET Colleges.
Mitigation: Cost recovery
approach will be
developed under the
Project for SME access to
Facilities.
2. Improved SMME
access to innovative
production technology in
pilot districts
3. Increased SME
participation in
manufacturing
% increase in SMMEs
accessing innovative
production technologies
(Specialized Industrial
Facilities) in pilot
districts
Increase in manufacturing
output from SMEs
0% (2013)
45% (2013)
30% female-
headed
SMMEs in
2017
30% male-
headed
SMMEs in
2017
55% (in 2017)
OU
TP
UT
S
1. Supporting LED:
Quarterly Progress
Reports;
dti Annual Reports
Risk: Inadequate
coordination between the
numerous stakeholders.
Mitigation: Project design
includes regular
stakeholder coordination
meetings with monitoring
by the dti.
Risk: Non-readiness of
Pilot FET Colleges to
receive SIFs.
1.1 Municipal
Authorities trained on
LED strategies
1.2 LED Maturity
Assessments reports
prepared
1.1 N° of Municipalities
trained in LED strategies
1.2 N° of LED Maturity
Assessments reports
prepared.
0 (2013)
0 (2013)
6 n° (by 2017)
31 n° (by 2017)
1.3 Regional business
activity profiles prepared
1.4 Participative
Appraisal of
Competitive Advantage
reports prepared
1.5 Business Retention
and Expansion
Strategies prepared
1.6 District Growth
Coalitions established
1.3 N° of Regional
business activity profiles
prepared
1.4 N° of Participative
Appraisal of Competitive
Advantage reports
prepared
1.5 N° of Business
Retention and Expansion
Strategies prepared
1.6 N° District Growth
Coalitions established
0 (2013)
0 (2013)
0 (2013)
0 (2013)
6 n° (by 2017)
6 n° (by 2017)
6 n° (by 2017)
6 n° (by 2017)
v
RESULTS CHAIN
PERFORMANCE INDICATOR MEANS OF
VERIFICATION
RISKS/MITIGATION
MEASURES Indicator (including CSI)
Baseline Target
2. Developing Pilot
SIFs:
2.1 SIFs set up in pilot
FET Colleges
2.2 Pilot FET Colleges
provide BDS to SMMEs
2.3 New SMMEs set up
to exploit innovative
technologies at the Pilots
2.4 Jobs created in the
SMME sector
3. Assessing the
Feasibility of Industrial
Parks:
3.1 Industrial Parks
Programme Long- Term
Strategic Plan approved
3.2 Detailed Pre-
Investment Study
(including a bankable
project with detailed
designs and financing
options) undertaken
2.1 N° of SIFs set up in
pilot FET Colleges
2.2 N° SMMEs receiving
mentoring and
counselling from Pilots
2.3 New SMMEs set up
to exploit innovative
technologies at the Pilots
2.4 N° of new jobs
created in the SMME
sector under the Project
3.1 Existence of approved
Industrial Park Strategic
Plan
3.2 Existence of approved
Detailed Pre-Investment
Study Report.
0 (2013)
0 (2013)
0 (2013)
0 (2013)
No Plan (2013)
No Report
(2013)
4 n° (by 2017)
100 n° (by
2017)
40 n° (by 2017;
40% female-
owned)
1000 (2017)
Strategic Plan
approved (by
2017)
Detailed Pre-
Investment
Study Report
approved (by
2017)
Quarterly Progress
Reports;
dti Annual Reports
Mitigation: Final
selection of pilot FET
colleges to be based on
complete readiness to
receive the Specialized
Industrial Facilities (SIFs)
Risk: Delays in recruiting
the consulting firms to
conduct pre-investment
studies and prepare the
strategic plan.
Mitigation: Bank to
provide training and
support to the dti in the
process of procuring
consulting services.
KE
Y A
CT
IVIT
IES
COMPONENTS INPUTS
1. Supporting LED::
Conduct various LED Studies with a gender perspective.
Establish Coalitions and prepare LED strategies
2. Developing Pilot SIFs:
Set up Specialized Industrial Facilities (SIFs) in pilot FET Colleges
Provide Business Development Services (BDS) to SMMEs and promote the
establishment of new SMMEs to exploit facilities.
3. Assessing Feasibility of Industrial Parks:
Prepare Industrial Parks Programme Long- Term Strategic Plan
Conduct detailed Pre-Investment Study (including a bankable project with detailed
designs and financing options)
4. Project Management:
Conduct Annual Audits of the Project
Organize stakeholder workshops and coordination meetings
Prepare quarterly progress reports
Procure Project goods and services.
INPUTS (UA) :
MIC FUND: 1,200,000
GoSA: 258,000
TOTAL: 1,458,000
1
REPORT AND RECOMMENDATION OF THE MANAGEMENT OF THE ADB GROUP TO
THE BOARD OF DIRECTORS ON A PROPOSED MIC GRANT TO THE REPUBLIC OF
SOUTH AFRICA FOR THE FOLLOWING PROJECT: ENTERPRISE DEVELOPMENT PILOT
PROJECT
Management submits the following Report and Recommendation on a proposed MIC Grant of UA 1.2
million to the Government of the Republic of South Africa to support Enterprise Development through
Local Economic Development Strategies, pilot Specialized Industrial Platforms and a Detailed Pre-
Investment Study for Industrial Parks.
1. INTRODUCTION
1.1 Background
1.1.1 It its efforts to foster inclusiveness in the socioeconomic development of the country, the
Government of South Africa (GoSA) identified 23 district municipalities as poverty nodes in
2001. These areas, which were described as the spatial manifestation of the second economy, were
characteristically underdeveloped, contributed little to the national GDP, absorbed the largest
percentage of the country’s population and incorporated the poorest of the rural and urban poor. They
were also structurally disconnected from the relatively more developed economy of the country, and
the municipalities were incapable of self-generated growth. The GoSA later reprioritized the 23 poverty
nodes municipalities and placed mining towns at the top of the list for urgent intervention.
The mining towns face particular challenges because there is little or no economic activity planning
beyond the activities of the mining companies; most of the mining companies have now reached the
end of their lifespan and have started shutting down their operations resulting in a large number of
people who have no alternative employment opportunities after losing their jobs. It is now imperative
to build the capacity of the mining town municipalities in formulating Local Economic Development
(LED) strategies and in implementing LED programmes jointly with mining companies. The capacity
of local Small, Micro and Medium Enterprises (SMMEs) in these poverty nodes also needs to be
strengthened to enable them improve their share of goods and services provided to the mining
companies and thereby support job creation. The development of LED strategies and plans and the
capacity building initiative will be piloted in the 6 mining towns that have been identified for
immediate intervention. Youth unemployment in some of the targeted poverty nodes exceeds 60%.
With an overall lower labour force participation rate than men and a gap of about 14% (2012), the
unemployment rate for women and female youth in these poverty nodes is even higher.
1.1.2 Access to technology is one barrier that is still keeping SMMEs in the second economy in
South Africa, where they remain inefficient and less competitive. Efficient equipment and
machinery are expensive for individual SMMEs, and a large proportion of these entrepreneurs do not
have access to capital to invest in the equipment and machinery to improve their productivity,
contributing to the poverty incidence in the populations living in the second economy. On average,
women are up to 30% poorer than men in the country as a whole, and particular efforts need to be made
to ensure women participate more in entrepreneurial activities and benefit from the lowering of the
access to technology barrier envisaged under the proposed pilot project. SMMEs and self-employed
people remain a driving force for development, economic growth and the creation of apprenticeship
opportunities and jobs. They shoulder a great deal of social responsibility in their communities, where
they make a major contribution to economic and social stability. In the National Development Plan
(NDP, 2011 – Vision 2030), the GoSA counts on the job creation potential of SMMEs to contribute to
its target of creating 4.5 million jobs by 2020 aimed at reducing the high unemployment rate of 25.2%
(2013). The GoSA, through the Department of Trade and Industry (dti), has prioritized the setting up of
Specialized Industrial Facilities (SIF) within certain municipalities in order to address the access to
technology constraint faced by SMMEs in improving their productivity and competitiveness.
Specialised Industrial Facilities (SIFs) are small production facilities with equipment and machinery
that enable different users in the same sector to produce products, processes and services with ease,
2
thus increasing productivity. These equipment and machinery are expensive for individual SMMEs to
acquire but can be easily shared among a number of SMMEs. Under the proposed Enterprise
Development project, SIFs will be piloted in 4 Further Education and Training (FET) colleges and
improve access to technology and innovation to SMMEs in the surrounding communities. The targeted
SMMEs will equally receive business development services support from the FETs in order to grow
their businesses sustainably. SMMEs in the target communities will be sensitized to make use of the
SIF facilities in their communities for a minimal cost recovery fee to be determined by the dti and the
FET colleges in order to ensure sustainability.
1.1.3 The revival of industrial parks that were established in former homelands and town ships
prior to 1994 holds a potential for job creation and poverty reduction in depressed communities
in South Africa. The former homeland governments offered significant incentives such as lower taxes,
free infrastructure and premises as well as subsidized wages to investors operating in the industrial
parks. However, after 1994 the incentives were withdrawn by the GoSA and the investors abandoned
the industrial parks, the majority of which are now dilapidated. The GoSA has now prioritized the
revival of these industrial parks, aiming to ensure that they play the role they were initially designed to
play, namely in boosting manufacturing by SMMEs, job creation and poverty reduction in targeted
municipalities. The feasibility study support under the proposed Pilot Project will target a sample of the
industrial parks and enable the development of a focussed industrial clustering and planning strategy in
line with the industrialisation programme of South Africa and thereby promote inclusive economic
growth by strengthening industrial linkages, fostering value-addition activities and enhancing the
productivity of SMMEs in particular. The GoSA, through the Department of Trade and Industry,
intends to conduct a comprehensive revitalisation of the State-owned Industrial Parks that demonstrate
viability as well as to facilitate the establishment of logistics hubs to support the functioning of the
Industrial Parks.
1.1.4 The proposed Enterprise Development Pilot Project will promote an integrated approach
to SMME development by supporting demand-side and supply-side interventions in the sector.
The feasibility study for the revitalization of the Industrial parks and integration of Local Economic
Development (LED) in Municipal Development Plans will enable the generation of economic activities
that will increase the demand for goods and services from SMMEs in the second economy. On the
other hand, improving access to technology and skills to these SMMEs in the second economy will
improve their ability to efficiently supply the goods and services demanded in their municipalities. The
synergies from these interventions will improve job creation, lead to reduced poverty amongst the
youth in particular and foster inclusive growth in the economy as a whole, through increased
participation from the second economy. Furthermore, training for district municipalities shall include
aspects of managing industrial relations, which are currently having a negative impact on the
competitiveness of the South African economy.
1.2 Project Goal and Objective
The overall goal of the proposed Enterprise Development Pilot Project is to contribute to job
creation, social inclusion and the reduction of the gender poverty gap, through supporting skills,
infrastructure and enterprise development in South Africa.
Objectives:
The specific objectives of the intervention are to:
i) Improve the capacity of local municipalities in planning and implementing Local Economic
Development Programmes;
ii) Improve SMME access to innovative production technology in pilot districts; and
iii) Increase SME participation in manufacturing
3
1.3 Sector Responsible for Preparing the Request
1.3.1 The Human Development Department of the Bank is responsible for preparing the proposal.
1.4 Justification
1.4.1 The Industrial Park Revitalisation and Resuscitation Programme is anchored in South
Africa’s New Growth Path (NGP, 2010) and the Industrial Policy Action Plan (IPAP, 2014-2017) and the Programme is formulated to contribute to the attainment of the goals of the country’s Industrial
Policies and Strategies in synergy with other initiatives under these strategies. In order to achieve the
GoSA’s objective of creating 5 million jobs and reducing the unemployment rate to 15% by 2020, the
NGP aims to increase annual economic growth to sustainable rates of between 6% and 7% between
2010 and 2020. The New Growth Path identified job drivers to which the provinces of the country are
to align their development plans in accordance with their comparative and competitive advantages. The
role of women, particularly in leadership positions, in these sectors will have to be strengthened, as
their employment, for the majority, tends to remain within either the traditional female occupations or
within the domestic and farming sectors. By mainstreaming gender equality, interventions in these
sectors can thus contribute to reducing the gender gap in youth unemployment, which stands at 54% for
young women and 45% for young men (2012).
1.4.2 In order to migrate from the resource-based economic development and growth, the
GoSA has recognized the need to strengthen the manufacturing sector of the economy and to
provide the required socioeconomic infrastructure. Also, the limited skills and access to technology
of SMMEs needs to be addressed, in order to limit the constraints they face in meeting market
demands. The promotion of Industrial Parks contributes to the attainment of this objective through the
implementation of industrialisation, diversification and regional development of the country. The
support to be provided under the proposed project will enable the development of a blue print and a
model to guide the revitalization of state-owned Industrial Parks in South Africa and thereby contribute
towards sustaining industrial growth, accelerating industrial restructuring and raising the level of
competitiveness of the economy. The support will enable the conducting of a Detailed Pre-Investment
Study for the upgrade and expansion of State Owned Industrial Parks located in the former homelands
and townships of South Africa; and the development of a Long- Term Strategic Plan (Implementation
Model) for the revitalization of the Industrial Parks. The Strategic Plan shall include a sustainable
capital investment programme (bankable subprojects) and define options for revitalising existing
Industrial Parks and developing new ones.
1.4.3 Local Economic Development (LED) is a principal tool in the implementation of the
National Development Plan (NDP), 2011 (Vision 2030), which aims at creating 11 million jobs by
2030 and address the current high levels of unemployment, particularly amongst the youth. However, the analysis of competitiveness of the municipalities, market opportunities, requirements and
existing capacity, including gaps need to be conducted in order to design measures that improve the
effectiveness of municipal authorities in implementing and supporting LED programs. LED contributes
to the attainment of a number of objectives of the NDP, including Economy and employment – which
targets the proportion of working adults in rural areas from 29 percent to 40 percent by 2030; Inclusive
rural economy – which aims at creating an additional 643 000 direct jobs and 326 000 indirect jobs in
the agriculture, agro-processing and related sectors by 2030; and Building a capable and developmental
state – which aims to develop a state that is capable of playing a developmental and transformative
role, and staff at all levels have the authority, experience, competence and support they need to do their
jobs. Support to be provided under the proposed project for LED will contribute in assisting the GoSA
in implementing some NDP recommendations on improving social inclusion such as ensuring that
South Africa’s rural communities have greater opportunities to participate fully in the economic, social
and political life of the country; institutional capacity building for local governments particularly
strengthening their planning capabilities; developing neighbourhood spatial compacts to bring civil
society, business and the state together to solve problems; and strengthening local governments’
4
implementing capacity, while ensuring equitable participation of women at all levels. Training sessions
and workshops shall be conducted under the proposed Pilot Project in order to contribute to addressing
the skills gaps of the officials in targeted municipalities on LED.
1.4.4 Local authorities constitute a critical component of GoSA service delivery system and
implementation capacity constraints have led to increasing service delivery protests targeting
local municipalities. Municipal officials in the country also face capacity challenges in dealing with
local economic development issues, which hamper the generation of economic opportunities for local
SMMEs. For the mining towns in particular, the Minerals and Petroleum Resources Development Act
(2002) has made it a requirement for the mining companies in the municipalities to participate in local
economic development activities; however, the low skills levels of municipal officials impede any
meaningful collaboration with the mining companies to design and implement local economic
development programmes. Therefore, there is an urgent need to capacitate municipal officials in long
term participatory economic development planning in partnership with mining companies for the
mining period and the post-mining period in order to capitalize on all the economic opportunities of the
municipalities and develop a vibrant SMME sector that generates job opportunities and contributes to
the attainment of the manufacturing targets of the country.
1.4.5 The National Development Plan, 2011 (Vision for 2030) puts innovation and technology
development at the core of South Africa’s economic growth and notes the importance of ensuring
that Small, Micro and Medium Enterprises (SMMEs), home-based enterprises and self-employed
individuals enhance their competitiveness by increasing value-addition and productivity. SMMEs
and the self-employed are important drivers of development, economic growth and the creation of
apprenticeship opportunities and jobs. In line with the NDP, 2011, Specialized Industrial Facilities
(SIFs) assist SMMEs to improve their business performance, quality and productivity, and to adopt
appropriate technology, thereby ensuring a greater level of success as well as increased output and job
creation. SIFs further reduce duplication in financial support of similar equipment for the enterprises in
close proximity and are now an effective platform to broaden the production base, activate growth and
redress regional economic imbalances.
1.4.6 The concept of the Specialised Industrial Facilities is informed by the Informal Business
Development Strategy and aims to put the most vulnerable SMMEs to a sustainable, long-term
economic growth trajectory. A Specialised Industrial Facility is a shared small production facility
with production equipment and machinery, which is made accessible to SMMEs operating in the 2nd
economy for a competitive fee. SIFs constitute an important long-term approach for building
competence in innovation as well as competitive advantage and productivity in the informal business
sector. The proposed intervention involves the creation of tangible assets such as design and testing
centres, production and processing units, raw material depots, product display centres, training and
information centres in 4 pilot Further Education and Training (FET) colleges with priority given to
access by female-headed SMMEs, rural communities, townships and the poorer regions of South
Africa.
1.4.7 The proposed pilot project is consistent with the Bank’s 2013-2022 Strategy, and will
contribute to the implementation of the Strategy’s and the attainment of its inclusive growth
objective. The proposed intervention is also in line with the Bank’s Country Strategy Paper (CSP
2013-2017) for South Africa, which identifies support to infrastructure development, and regional
integration as its two main pillars. The pilot project is equally aligned to the Bank’s Human Capital
Strategy (2014 – 2018), which prioritizes skills development, technology and innovation. Lastly, the
intervention will contribute to the implementation of the Bank’s Gender Strategy (2014 – 2018),
especially under the women’s economic empowerment pillar through the mainstreaming of gender
equity in all the activities of the project.
5
2. SUMMARY DESCRIPTION OF THE PILOT PROJECT
2.1 Project Components
2.1.1 Project Objectives: The overall development objective is to contribute towards job creation,
social inclusion and the reduction of the gender poverty gap, through supporting skills,
infrastructure and enterprise development in South Africa.
2.1.2 Project Components: The major activities under each of the three mutually reinforcing
components of the pilot project are summarized in the sections below while further details are found in
Annex 2.
2.1.3 Component 1: Supporting Local Economic Development (LED)
Six key activities shall be conducted under this component, to support LED in six pilot District
Municipalities and provide development opportunities for SMME growth. The six pilot District
Municipalities shall be following: Sekhukhune, Lejweleputswa, West Rand, Nkangala, Waterberg and
Bojanala – these six districts have been selected by the Government as requiring immediate attention,
out of the 23 prioritised poverty node municipalities in the country, given lack of resources to cover all
23 nodes at the same time. The six District Municipalities comprise a total of 31 Local Municipalities
with a total population of 6,020,461.001. With a focus on mainstreaming gender equality in all the
activities, the following are the main activities under this component:
Conduct LED maturity assessments studies and prepare reports for the 6 District Municipalities
and the 31 Local Municipalities; the study will evaluate the capacity of Municipalities in
formulating LED strategies as well as their readiness in implementing them; municipality staff
will participate in these studies, in order to build their capacity.
Prepare regional business activity profiles, which will capture the economic potential of the
target District Municipalities and the extent to which the potential has been developed.
Carry out participative appraisal of competitive and comparative advantage studies and prepare
reports for the target District Municipalities.
Prepare business retention and expansion strategies for the 6 District Municipalities.
Establish District growth coalitions, which will constitute forums for regional economic actors;
and
Conduct District LED summits and workshops in order to provide training and address the
skills gap of the officials in targeted municipalities on LED.
In addition, the Department of Trade and Industry (the dti) will conduct a review of existing LED
strategies in the country and their alignment to national policies, using counterpart funds. The review
will contribute to the integration of the marginalised communities into the mainstream economy;
industrial decentralisation; improving local beneficiation in mining municipalities; and the
improvement of the competitiveness of marginalised regions.
2.1.4 Component 2: Developing Pilot Specialized Industrial Facilities (SIFs) with a perspective to
ensure gender equality.
Under this component, Specialized Industrial Facilities (SIFs) shall be set up in 4 pilot Further
Education and Training (FET) colleges to support skills development for students and provide
technology access to SMMEs to improve their productivity. The pilot SIFs shall be set up in the
following FET colleges: Northern Cape Urban FET College – Kimberly, Northern Cape Province;
Lovedale PFET College – King Williams Town, Eastern Cape Province; Sekhukhune FET College –
Sekhukhune, Limpopo Province; and Ekurhuleni West FET College – Germiston, Gauteng Province.
The areas of focus that will be supported with efficient SIF equipment within the colleges under the
pilot project include: construction, metal fabrication; jewellery manufacture; agro-processing; and
vehicle maintenance – these sectors have been selected due to their job creation potential. The
following principal activities shall be conducted under the intervention: 1 Statistics SA, 2011
6
Set up SIFs in 4 pilot FET Colleges, which shall include design centres and production units in
order to improve SMMEs’ business performance and productivity.
Review and develop entrepreneurship curriculum modules adapted to SIFs set up in the FET
colleges.
Create testing facilities, within the SIFs, for appropriate technologies that are accessible to
SMMEs to enhance quality of products.
Provide Business Development Services (BDS) within training and information centres set up
along with the SIFs in the target FET colleges.
2.1.5 Component 3: Assessing the Feasibility of Industrial Parks
A Detailed Pre-Investment Study (DPIS) on the upgrade and expansion of State-Owned
Industrial Parks and the Development of a Strategic Plan shall be carried out under this
component. The DPIS will include an analysis for the upgrade and expansion of a pilot of 5 State-
Owned Industrial Parks located in the former homelands and townships of South Africa, while the
Strategic Plan will include an Implementation Model for the Industrial Parks Programme aimed at
increasing the rate of industrialization and the participation of SMMEs in the manufacturing sector.
The DPIS will comprise technical, environmental, institutional, financial and economic analysis as well
as the design of bankable Industrial Park Development subprojects to facilitate investment decisions.
The DPIS will equally address the following issues: increasing the productivity of industries; fostering
inclusive economic growth considering poorer regions and gender equality; reducing the cost of doing
business and increasing the creation of employment by SMMEs.
2.1.6 Component 4: Project Management
Under the Project Management component, the following activities shall be carried out:
Conduct Annual Audits of the Project
Organize stakeholder workshops and coordination meetings
Prepare quarterly progress reports
Procure Project goods and services.
2.2 Expected Outputs
The expected outputs are detailed in Annex 2 and some are outlined hereunder:
Municipal Authorities are trained on LED strategies
LED Maturity Assessments reports prepared
Participative Appraisal of Competitive Advantage reports prepared
SIFs set up in pilot FET Colleges
Pilot FET Colleges provide BDS to SMMEs
Industrial Parks Programme Long- Term Strategic Plan approved
Detailed Pre-Investment Study (including a bankable project with detailed designs and
financing options) undertaken.
3. COST AND FINANCING OF THE PILOT PROJECT
3.1 Project Cost
The cost estimates for the pilot project are shown in Tables 1 and 2 below. The total estimated cost
of the pilot project is UA 1,458,000 (equivalent to South Africa Rand (ZAR) 23,897,037). A price
contingency of 4.5% and a physical contingency of 3% have been included in the cost estimate. The
detailed cost estimate is found in Annex 3.
7
Table 1: Project Cost Estimates
Component ZAR Cost (UA) %
Total Local Foreign Total Foreign Base
Component 1: Supporting Local
Economic Development 9,426,672 431,888 143,249 575,137 24.91 41.97
Component 2: Developing Pilot
Specialized Industrial Facilities (SIFs) 3,902,206 172,772 65,308 238,080 27.43 18.47
Component 3 – Assessing the
Feasibility of Industrial Parks 5,000,000 228,794 76,265 305,058 25.00 22.26
Component 4: Project Management 3,655,088 236,957 - 236,957 - 17.29
Total Base Cost 21,983,966 1,070,411 284,822 1,355,233 21 100
Physical Contingency (3%) 666,895 32,562 8,545 41,107
Price Contingency (4.5%) 1,000,342 48,843 12,817 61,660
TOTAL 23,651,202 1,151,816 306,184 1,458,000
Table 2: Summary of Estimated Costs by Expenditure Categories
Disbursement categories Cost in UA
Local Foreign Total Cost
Civil Works - - -
Goods 143,000 57,000 200,000
Services 479,409 160,552 639,961
Operating Cost 278,907 81,132 360,039
Total cost 901,316 298,684 1,200,000
3.2 Financing Plan
The pilot project shall be financed by a MIC grant allocation of UA 1,200,000 under the MIC Technical
Assistance Fund (TAF) and a Government of South Africa (GoSA), in-kind, counterpart fund of UA
258,000. The MIC TAF will finance 82.480% of the total cost of the project, while 17.52% will be
supported by the GoSA contribution, which will mainly cover the review of existing Local Economic
Development (LED) strategies in the country (§2.1.3) and will be reflected in the Agreement. Table 3
presents the estimated project costs by financing source.
Table 3 Estimated cost by source of financing Sources of Financing
(UA) FE % LC % Total %
ADB MIC Grant 306,184 100.00 893,816 77.60 1,200,000 82.30
GoSA Contribution - - 258,000 22.40 258,000 17.70
Total 306,184
1,151,816
1,458,000 100
Percentage 21.00
79.00
3.3 Cost Estimates by Components
The cost estimates by components is shown in Table 4 hereunder:
Table 4: Cost estimates by components Component Cost Estimate (UA)
Component 1: Supporting Local Economic Development 575,137
Component 2: Developing Pilot Specialized Industrial
Facilities (SIFs) 238,080
Component 3 – Assessing the Feasibility of Industrial Parks 305,058
Component 4: Project Management 236,957
Total Base Cost 1,355,233
Physical Contingency (3%) 41,107
Price Contingency (4.5%) 61,660
TOTAL 1,458,000
4. PROCUREMENT
4.1 Procurement of Services
The acquisition of consulting services financed by the Bank will be in accordance with the Bank’s
Rules and Procedures: “Rules and Procedures for the Use of Consultants”, dated May 2008 (revised
8
July 2012); as amended from time to time, using the relevant Bank Standard Request for Proposals
Documents, and the provisions stipulated in the Financing Agreement. The Department of Trade and
Industry (dti), the Executing Agency, through the Broadening Participation Division (BPD) will be
responsible for the implementation of the project and procurement of goods, consulting services, and
training. Given its experience in using the Bank’s Procurement Rules, the Supply Chain Management
Unit at the National Treasury, will support the Procurement Unit at the dti in conducting procurement
activities for the Project. The procurement arrangements are presented in Table 6. All selections of
consultants shall be carried out using the shortlisting process. For the consultancy services (studies), the
selection procedure will be based on Quality-and-Cost Based Selection (QCBS). The external annual
audits of the operation shall be conducted by the Office of the Auditor General of South Africa
following national procedures. However, provisions have been made for the procurement of an external
auditing firm to carry out the annual auditing of the project accounts in case the Office of the Auditor
General authorizes the recruitment of an external audit firm to conduct the exercise.
4.2 Procurement of Goods
The procurement of goods financed by the Bank will be in accordance with the Bank’s Rules and
Procedures: “Rules and Procedures for Procurement of Goods and Works”, dated May 2008 (revised
July 2012), using the relevant Bank Standard Bidding Documents, and the provisions stipulated in the
Financing Agreement. National Competitive Bidding (NCB) procedures shall be used for goods.
4.3 Procurement of Training
The procurement of training activities including seminars, workshops, travels, meetings and
communications shall be carried out using Government of South Africa procedures (“other” in
Table 6). Further information on the procurement arrangements for goods, services and training
activities is found in Annex 5.
5. IMPLEMENTATION OF THE PILOT PROJECT
5.1 Implementation Schedule
The project will be implemented over a period of three years between January 2015 and
December 2017, following its approval by the Bank. The indicative timeframe is presented in Table
5, which shows the key activities and the indicative dates for their completion.
Table 5: Indicative implementation plan
Action by
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Project Processing and Management
Grant approval AfDB
Signing Protocol of Grant
Agreement/Effectiveness
AfDB & the
GoSA
Supervision and Monitoring AfDB
Project Completion Report AfDB & the
dti
Component 1: Supporting Local
Economic Development
Procurement of Consulting Services the dti
Conduct Local Economic Development
(LED) Studiesthe dti
Review existing LED strategies and align to
national policiesthe dti
Conduct LED Workshops and National
Conference on LEDthe dti
Component 2: Developing Pilot
Specialized Industrial Facilities (SIFs)
Procurement of Goods (equipment) the dti
Set up fo SIFs in FET Colleges the dti
Providing Business Development Support
Services to SMMEs in FET Collegesthe dti
Component 3 – Assessing the
Feasibility of Industrial Parks
Procurement of Consulting Services the dti
Conduct Detailed Pre-Investment Study
(DPIS) on the upgrade of Industrial Parks the dti
Develop Industrial Parks Programme
Implementation Strategic Plan the dti
Component 4: Project Management Support the dti
Activities/Years2015 2016 2017
9
5.2 Annual Work Programme and Procurement Schedule
The draft annual work programme is summarized in Table 5, which shows the key activities and
the indicative dates for their commencement and completion within the timeframe of the Project.
The Procurement schedule is shown in Table 6.
Table 6. The Procurement Arrangement (UA) for the activities financed under the MIC-TAF Grant Categories
NCB Shortlist Shopping Other*
Non-
Bank
Funded
Total
1 GOODS
1.1 SIF Equipment & machinery (tech. Specs
prepared by FET colleges) 200,000
200,000
2 WORKS
-
3 SERVICES
-
3.1 Local Economic Development Study
Consultancy (LED maturity assessments; Business activity profiles; Competitive advantage appraisal;
Business retention & expansion strategies)
255,332
255,332
3.2 Detailed Pre-Investment Study (DPIS) on the
upgrade and expansion of State-Owned Industrial Parks and the Development of a Strategic Plan -
Consultancy
321,379
321,379
3.3 Review of existing LED strategies and alignment to national policies (GoSA)
258,000 258,000
3.4 Annual Auditing of Project (OAG-SA)
42,853
42,853
3.5 Procurement Consultant – IC**
13,118
13,118
3.6 Project Completion Report Mission (Individual Consultant)
7,279
7,279
4 OPERATING COSTS
-
4.1 District LED Workshops / Seminars
65,588
65,588
4.2 National conference on LED
32,794
32,794
4.3 Field monitoring of activities (travel, DSA, field accommodation etc.)
134,983
134,983
4.4 Advertisements & publicity (Tender documents
and other project activities) 11,806
11,806
4.5 Project Steering Committee Meetings (quarterly)
15,741
15,741
4.6 Reporting (preparation, reproduction and dissemination; quarterly)
3,935
3,935
4.7 Project communication costs (telephone;
internet; etc.) 5,337
5,337
4.8 Validation / dissemination workshops &
seminars 32,794
32,794
4.9 Review and Design of Teaching and learning
material (Entrepreneurship curriculum development for SIFs) - MoU with FET Colleges
12,462
12,462
4.10 SIFs Facilitation (Business Development
Support and mentorship of SMMEs) - MoU with FET Colleges
44,600
44,600
TOTAL 200,000 632,682 - 410,171 258,000 1,458,000
*Other: Gov’t of South Africa procedures and Individual Consultant (IC**).
5.3 Executing Agency
5.3.1 The Department of Trade and Industry (the dti) will be the Executing Agency of the MIC
technical assistance grant.
5.3.2 Broadening Participation Division (BPD) team of the dti will be responsible for the
management and supervision of the project and for reporting to the Bank (MIC fund) on its
implementation. The team will work closely with focal points in the targeted Municipalities,
Provincial Economic Development Agencies and FET Colleges. The principal person in the BPD team
will be the Director of Innovation and Technology, who will manage the day-to-day activities of the
Project and the preparation of quarterly progress reports. The implementation of the Local Economic
Development component of the Pilot Project shall be supported by the newly created Department of
Small Business Development (DSBD). In addition, the team will be supported by Financial
Management and Procurement services of the dti that will be responsible for procurement,
disbursement and financial control and reporting. The Supply Chain Management Unit of the National
Treasury will support the Procurement Unit at the dti in conducting procurement activities for the
10
Project. The Procurement Unit at the dti will equally be strengthened with a Procurement Consultant to
support the implementation of the project. Monitoring and evaluation of the Project will be undertaken
by the BPD with support from the M&E services of the dti.
5.3.3 Strategic guidance in the implementation of the Project will be provided by a Project Steering
Committee comprised of the dti (BPD), the DSBD, the National Treasury, the Department of Higher
Education; Department of Cooperative Governance and Traditional Affairs; Private Sector
representatives ; representatives of targeted Provincial Economic Development Agencies;
representatives of targeted Provincial Economic Development Departments; and representatives of the
targeted District Municipalities.
5.3.4 To enable the effective implementation of the Specialized Industrial Facilities (SIFs)
component of the Project, Memorandums of Understanding (MoUs) shall be entered into by the
dti and the targeted FET colleges. Under the MoUs, the FETs will be responsible for developing the
technical specifications of the equipment and machinery to be procured for the pilot SIFs and for the
review and design of teaching and learning material (entrepreneurship curriculum development for
SIFs) as well as for SIFs facilitation (providing Business Development Support and mentorship to
SMMEs that access the SIFs).
5.4 Supervision and Monitoring
5.4.1 During the project implementation period, the BPD team will prepare and forward to the Bank,
within 45 days of the end of each quarter, Quarterly Progress Reports highlighting the status of
activities, disbursements made and anticipated, problems encountered and solutions envisaged, as well
as the schedule of activities for subsequent quarters. The Bank will monitor the implementation of the
project through reviews of key outputs of the project (Inception Reports, Interim & Final Reports for
studies and quarterly progress reports for SMME support activities under the SIFs and capacity
building for Municipalities under LED). The Bank will equally conduct annual supervision of the
Project.
6. FINANCIAL MANAGEMENT AND DISBURSEMENT ARRANGEMENTS
6.1 Terms of Financing
6.1.1 The Dti, through the Broadening Participation Division (BPD) will be responsible for the overall
financial management aspects of the project including budgeting, recording, accounting, reporting and
audit coordination. The division will also ensure that at all times, a sound system of internal controls
governs the operations of the project to ensure that the project objectives are achieved, and that funds
are used solely for intended purposes with due care to economy and efficiency.
6.1.2 The National Treasury oversees all funds flows from ODA, and has sufficient controls around
expenditure management, payment process and bank account management. Under the project, the
Grant Funds will be disbursed to an already existing account (The Public Investment Account-PIA)
through a process outlined in Annex 4. The PIA is a Donor-pool account held with the Reserve Bank of
South Africa and the National Treasury manages and tracks funds deposited per Donor by use of GL
Accounts. 6.1.3 Disbursements to DTi (from National Treasury) will be based upon periodic requests.
Disbursements to FET colleges by the Dti shall be made from funds deposited into Dti’s account by the
National Treasury. Replenishments of both the Dti and FET colleges’ accounts shall be based on duly
submitted 6 months budgets and conditional upon full justifications of funds previously advanced. The
Direct Payment Disbursement Method could also be used for some disbursement applications. Details
of the Financial Management Arrangements are provided in Annex 4.
6.2 Suspension of Disbursement
Suspension of disbursement of MIC grant funds can take place in accordance with the Bank’s
disbursement regulations contained in the Disbursement Handbook.
11
6.3 Legal Instruments and Authority
6.3.1 The legal instrument for the grant shall be a letter of agreement between the Republic of South
Africa and the African Development Bank.
6.3.2 The letter of agreement shall become effective upon its counter-signature by the Bank.
6.3.3 The obligation of the Bank to make the first disbursement of the Grant shall be conditional upon
effectiveness of the letter of agreement in accordance with clause 6.3.2 above and the fulfilment, in
form and substance satisfactory to the Bank, of the following conditions:
a. creation of a separate portfolio (the “Special Account”) for the Grant in the South African
Government’s Reconstruction and Development (RDP) Fund; and
b. establishment of a Project Steering Committee with terms of reference and composition
acceptable to the Bank.
7. CONCLUSIONS AND RECOMMENDATIONS
7.1 Given the key role of the Small, Micro and Medium Enterprises (SMME) in supporting inclusive
growth, job creation and poverty reduction in South African, the Government has prioritized, SMME
development, Industrial Parks and Local Economic Development as essential tools for the
implementation of the New Growth Path and the National Development Plan.
7.2 In this regard, the Government of South Africa has endorsed the Department of Trade and
Industry’s MIC Grant Request towards enterprise development in support of SMMEs, Municipalities
and the Industrial Parks Programme. The intervention will, in particular, enable the conducting of a
detailed pre-investment study that will lead to bankable investment projects under the Industrial Parks
Revival Programme.
7.3 Considering the foregoing, it is recommended that a grant not exceeding UA 1,200,000 from the
ADB MIC Technical Assistance Fund be extended to the Department of Trade and Industry, through
the Government of South Africa for the purpose of co-financing the above mentioned pilot project. The
grant will enter into force immediately after the signing of the Letter of Agreement by the parties.
I
ANNEX 1: MIC GRANT REQUEST
II
III
IV
V
ANNEX 2: DETAILED DESCRIPTION OF PROJECT AND TORS
A: Component 1: Supporting Local Economic Development
TERMS OF REFERENCE FOR LOCAL ECONOMIC DEVELOPMENT STUDY
Background
Mainly due to poor planning during the apartheid regime, mining towns were planned as dormitories
for migrant labourers and they were not set up as places where people can sustainable live in. This
resulted in little or no economic activity planning beyond the activities of those mining companies.
Unfortunately most of the mining companies have reached their lifespan and have started shutting
down their operations in these areas, resulting in big number of people who have no alternative
employment opportunities that they can look into.
The introduction of the requirement by mining companies to include Social Labour Plans has not had a
huge impact in ensuring that these mining companies engage in other economic activities that will
benefit the local economies. This could be due to the fact the Social Labour Plans are only done with
the purpose of securing mining rights by the private or also by the fact that the local municipalities who
are supposed to engage the mining companies and ensure that proper plans are put in place for the
benefit of the local economy have no capacity to do that.
The four studies that have been conducted on the mining companies-municipality interface indicate that
there has been a significant increase in the engagements between the two institutions since the
introduction of the Mineral and Petroleum Resources Development Act (MPRDA). Even though there
are these positive developments but there are a still a number of negative aspects that affect the
relationship between municipalities and mining companies which include:
Distrust, suspicion and a lack of understanding between mining companies and municipalities of
‘the world of the other’;
Weak and absent intergovernmental relations in and between spheres of government;
A lack of shared long-term visions and accompanying long-term strategic planning and plans for
municipalities with strong mining economies;
A tendency on the side of the State and mining companies to delay the tackling of major issues in
mining areas, with both hoping that ‘someone else’ will take care of these;
A lack of strategic leadership and a passion for development, coupled with a prevalence of political
infighting and a disconnect between officials, councillors and communities, which often leads to
disillusionment amongst mining companies;
A lack of alignment between (1) mining companies’ CSI and SLPs and (2) municipalities’ IDPs and
LED plans and strategies;
In the current context of Industrial unrest, which is having a negative impact on the competitiveness
of the economy as a whole, training to district municipalities in aspects of industrial relations
management are required; and
A lack of planning and preparation for cyclical mining cycles, the scaling down of mining
operations and the inevitable post-mining phase
To try and turn around this unfortunate situation and built a better relationship between the
municipalities and mining companies amongst other things the studies made the following proposals2:
Undertake capacity-building for municipal officials, officials involved in/with the mining
industry/sector in other spheres of government, municipal councillors and local communities to
strengthen their skills sets, deepen their understanding of how mining companies operate, and
enhance their ability to meaningfully engage mining companies
Strengthen skills development initiatives in local host communities to facilitate greater (1) entrance
of community members into job opportunities in mining companies and (2) procurement by mining
2 Mining company-Municipality engagements and relations in South Africa: Status Quo and Recommendations for
improvement: IDC, 2013
VI
companies of local providers of goods and services
Prioritisation of municipalities
In year 2001 the government identified twenty three (23) district municipalities as Presidential Poverty
Nodes. These poverty nodes were described as the spatial manifestation of the second economy. These
areas are characterised by underdevelopment, contributing little to the GDP, absorbing the largest
percentage of the country’s population, incorporating the poorest of the rural and urban poor,
structurally disconnected from both the First World and the global economy, and incapable of self-
generated growth. Out of the 23 prioritised poverty nodes municipalities the government has since
further reprioritised and identified mining towns as the ones that should be attended to on an urgent
basis given lack of resources to cover all 23 nodes at the same time. Therefore this capacity building
initiative will be piloted in the six mining towns that have been identified for immediate intervention.
Brief socio-economic profile of Mining Towns
The analysis below will give a brief background on the current situation in these mining areas which
will in the end be used to measure the impact of the intervention at the end of the programme.
District Municipality Population Unemployment Youth
Unemployment
GDP
Sekhukhune (5 LMs) 1 076 840 50.9% 60.6% 14 378 960 669
Lejweleputswa (5
LMs)
627 626 36.5% 48.7% 31 282 588 030
West Rand (4 LMs) 820 995 26.3% 35.2% 45 950 292 287
Nkangala (6 LMs) 1 308 129 30.0% 39.6% 82 944 205 351
Waterberg (6 LMs) 679 366 28.1% 35.5% 53 816 027 479
Bojanala (5 LMs) 1 507 505 30.7% 39.1% 89 420 962 614
Source: Statistics SA, 2011
Capacity building
Rationale
Local authorities are a very key component of government delivery system, which could be one of the
reasons why many service delivery protests target them. It is a well-known fact that there is a also a
challenge in the country when it comes to the capacity of municipal officials in dealing with economic
development issues. For the mining towns in particular, the Minerals and Petroleum Resources
Development Act has made it a requirement for the mining companies to get involved in local
economic development activities and the studies mentioned above shows that there is a change in
attitude of the mining companies but this is not matched by the skills level of municipal officials.
Therefore there is an urgent need to capacitate municipal officials in long term participatory economic
development planning in partnership with mining companies for the mining period and post-mining
period.
The capacity building programme will take mainly the form of ‘hands-on’ mentorship of local
government officials and politicians to enable them to plan and implement local economic development
initiatives in partnership with other stakeholders in their localities.
Deliverables
Inception report
50 x people who will be trained on Local Economic Development Planning and
Implementation. The combination of municipal officials and councillors, private sector
bodies and the academic sector
31 x LED Maturity Assessments reports
6 x Regional business activity profiles
6 x Participative Appraisal of Competitive Advantage reports
6 x Business Retention and Expansion Strategies
6 x Centre for entrepreneurships/Incubators
VII
6 x District LED Summits/Workshops
6 x District Growth Coalitions (Forum for regional economic actors)
1 x National conference to share lessons learnt from the intervention
Policy environment
The Local Economic Development Programme is governed by a host of legislative and regulatory
framework which the service provider must fully understand and review. These legal frameworks
include amongst others:
The Local Economic Development Policy
Industrial Policy Action Plans
Provincial Employment, Growth and Development Plans
Manufacturing Development Act No. 187 of 1993
National Development Plan
National Infrastructure Development Strategies
Project Timing
The work break down structure (WBS) of the project is expected to cover all possible and required
activities. The final report of the project is expected to be tabled not later than 6 months after the
appointment of the service provider.
Expertise Required
The team of experts of specialized service providers shall be required with the knowledge of local
economic development need an understanding of the socio economic dynamics of South Africa with
special reference to spatial economic regions. Strategies designed in the regions should take
consideration of the regional context and stage of development per district.
Qualifications and Professional Experience
The team should display the talent in this particular field of study. Recognized qualification with
documented proof might be required as well as work done in the related field of local economic
development and business development. The table hereunder indicates the key experts that should be in
the team.
Experts Estimated Time
Input (Months)
Socio-economist (Team leader) 6
Local Economic Development expert 4
Business Development and retention expert 4
Entrepreneurship development expert 3
Micro economist 3
a) Review of LED Strategies and alignment to national policies
Rationale
This component is necessitated by the fact that most of the municipalities in the country have existing
strategies but these were mainly developed by service providers and most of them are not
implementable and were developed on behalf of the municipalities and without any transfer of skills. In
addition the strategies that have been developed in the past have not taken into account the specific
challenges that are faced by individual municipalities and in the context of this project the mining
towns. Mining towns have unique challenges that need to be addressed through the development of
strategies that takes into account the current situation (when there are still mining operations) and post-
VIII
mining situation.
The Department of Trade and Industry will develop these strategies internally. The component is
expected to have the following outputs:
Credible LED Strategies
Alignment of regional economic/industrial development with provincial and national policies
Customised strategies that responds to challenges in the municipality, reflects on the changes in the
local economy and acknowledges quick economic gains (low hanging fruits);
B: Component 2: Developing Pilot Specialized Industrial Facilities (SIFs)
Summary and Background
Innovation and technology development are at the core of the country’s economic growth while
ensuring that enterprises, SMME’s and self-employed individuals enhance their competitiveness by
increasing their value-add and productivity. Therefore, competence building in innovation is an
important long-term approach for creating a competitive advantage for the economy and improving the
quality of people’s lives.
The concept of the Specialised Industrial Facilities is based on the assumption that for SMME’s to
improve productivity, the needs and dynamics in specific sectors differ, thus each sector requires a
specific innovation approach to address the needs and challenges specific to the sector.
Specialised Industrial Facility is a shared small production facility with equipment and machinery
which is made available free or at a minimum fee to small enterprises, self-employed people, street
vendors, and developing entrepreneurs. The Specialised Industrial Facilities (SIFs) are proposed to
assist small, medium and micro enterprises (SMMEs) mostly operating in the 2nd economies to be
innovative and competitive and offer these SMMEs opportunities to access appropriate technologies
and skills to exploit technology.
These SMMEs are committed to improving their competitiveness however, they need appropriate
information to keep abreast of all changes and a supporting infrastructure which can help them select
and apply the techniques and technologies best suited to their own businesses. The key thrust of the
SIFs is to encourage enterprises to carve out new markets, expand their level of business and hence
their contribution to the wider economy including the creation of new employment opportunities.
The role of the Specialised Industrial Facilities (SIFs) in promoting economic growth has been
significantly recognised both in developed and developing countries. The SIFs are now widely
considered as an effective platform to broaden production base, activate growth and re-dress regional
economic imbalances. However, access to technology is one barrier that is still keeping SMMEs in the
2nd economy to make businesses more competitive, faster and simpler than before. Many of these
entrepreneurs do not have own capital to invest in the equipment and machinery to improve their
productivity.
1. DESCRIPTION
The Specialised Industrial Platform/Facility (SIF) is defined as a small production facility with
equipment and machinery which enables different users in the same sector to produce
products/processes/services with ease thus increasing productivity. These equipment and machinery are
extremely expensive for individual SMME to acquire, however they may be easily shared among a
number of users.
IX
The SIF involves the creation of assets like testing facility, design centre, production unit, training and
information centre. These SIFs will be established at the FET Colleges, to mitigate the risk of
escalating costs associated with the management and maintenance of such centres and leverage on the
expertise that exist in these institutions for the benefit of emerging and established small enterprises.
Priority will be given to rural communities, townships and poor regions. This intervention aims to put
the SMMEs to sustainable, long-term economic growth; and to reduce the burdens on SMMEs.
The main beneficiaries of this intervention are the small and medium-sized enterprises as well as self-
employed people who are the driving force for development, economic growth and the creation of
apprenticeship opportunities and jobs. Such enterprises are not only at the heart of our country’s
economic capacity, they also shoulder a great deal of social responsibility in their communities. They
make a major contribution to economic and social stability.
2. RATIONALE AND OBJECTIVES
The main objectives of the project are to:
Establish design centre and production units in order to improve SMMEs business performance
and productivity
Create testing facilities for low technologies that are available for SMME’s to enhance quality
of products
Establish and facilitate the use of training and information centre for SMME’s in the specific
sector
Adopt appropriate technology ensuring a greater level of success; and increased turnover and
job creation.
The establishment of SIF’s will further reduce duplication in financial support of similar
equipment for SMMEs in close proximity. SIFs will enable the growth of SMMEs which are
able to create more employment.
X
Logic Model for establishment of SIF
Machinery for Acquisition Sekhukhune FET
College
Lovedale PFET College Northern Cape
Urban FET College
Ekurhuleni West
FET College
Static Brick making
machine
Spray booth Welding tools Sewing machines
Marula processing
machines for skin
products
Spray booth
Chassis straightener (to straighten
accident-damaged vehicles)
Carpentry machine Fabrication machine
Vehicles diagnostic
machine
Paint-mixing bank Jewellery
manufacturing tools
Oven for bakery
Furniture making
machine
Air compressor (to supply air under
pressure to preparation and
finishing spray booths
Carpentry machine
Mig brazer/aluminium welder (to
braze and weld body parts)
Electrical tools
Button machine
M7 EX Block making machine
Inputs Outcomes
Long-term
Activities Outputs Short-term
Entrepreneurial
Training
Courses
Business
Skills
Development
SMME
Training and
Mentoring
Manufacturing/
Production
Facilities
Increased number of
sustainable business
Development Employment
Creation
Improved production
processes for SMME
Infusion of
Technologies into
small business
New Technologies
New/Improved
product design and
manufacturing
Technology
development
and adaptation Leveraging on
Municipal Tenders
Reduced production
cost for SMME
Increased number of
emerging SMME
Increased number of
SMME in a specific
sector
Formation of Large
Industries
Business growth and increased
revenue for SMME
XI
C: Component 3: Assessing the Feasibility of Industrial Parks
TERMS OF REFERENCE FOR RESUCITATION AND REFURBISHMENT OF INDUSTRIAL PARKS
1. INTRODUCTION
The Department of Trade and Industry seeks the services of a multi- disciplinary firm(s) of service provider professionals to develop a blue print for the implementation of the Industrial Parks Programme. This Programme includes the resuscitation and refurbishment of the Industrial Parks in South Africa with special reference to Industrial Parks located in the former homelands and townships as well as developing a model for national intervention for creation of new Industrial Parks in order to promote industrialisation and improving spatial economic growth with specific focus on the manufacturing sector. This document will contribute to the development of a focussed industrial clustering and planning and target the industrialisation programme of South Africa, thus promoting inclusive economic growth by strengthening industrial linkages, increasing value-added activities and enhancing productivity. The Department of Trade and Industry in collaboration with the Provincial Economic Departments in South Africa intend to do comprehensive revitalisation of the State owned Industrial Parks that demonstrate viability and facilitate the establishment of Logistics Hubs to support the functioning of the Industrial Parks. 2. BACKGROUND South Africa is faced with underlying economic structural weaknesses, which include the consumption driven growth path and the relatively low competitiveness of manufacturing industries compared to service sectors. The New Growth Path and Industrial Policy Action Plan (IPAP) provided an intensified industrial development direction and strategic thrust for the South African economy. The new growth path identified job drivers which the country should align their plans to and customises them as per comparative and competitive advantages. Furthermore both IPAP and the New Growth Path re-emphasised the key sectors which provinces should prioritise their efforts on in order to support employment creation. These sectors are namely;
Infrastructure
The agricultural value-chain
The mining value-chain
The green economy
Manufacturing sectors which are included in the IPAP2, and
Tourism and certain high-level services. In order to improve competitiveness, there is a need to develop robust industrial policies and strategies which can be implemented as projects and programmes that will improve both the rate of industrialisation and the quality of the outputs ensuring inclusive industrial growth. One of the ways to achieve this objective, is through the promotion of Industrial Parks so as to contribute in the industrialisation, diversification and regional development of the country. The economy hasn’t optimised the utilisation of the Industrial Parks to promote investment growth and spatial development especially at a municipal or metro level. The challenges facing the existing Industrial Parks in the country range from poor infrastructure, dilapidated buildings, poor management, not aligned to municipal and provincial economic strategies and lack of investment. These challenges can be alleviated by providing assistance to management agencies, in this case Provincial Development Agencies, to refurbish the Industrial Parks/Estates. It is therefore in the same sentiment that the he promotion of industrial development has become an integral part of South Africa’s industrial policy as enshrined in Industrial Policy Action Plan, National Industrial Policy Framework and the Provincial Employment, Growth and Development Plans.
XII
3. RATIONALE The purpose of the Industrial Park Revitalisation and Resuscitation Programme is to ensure that all the Industrial Policies and Strategic imperatives are attained. The Revitalisation and Resuscitation Programme should lead to the following: 3.1. Promoting growth in the manufacturing sector and value addition, migrating from dependency on
primary sectors; 3.2. Promoting participation of the SME’s in the manufacturing sector; and 3.3 Promoting regional and spatial development through the industrialisation process of previously
marginalised areas.
4. PROBLEM STATEMENT There is limited availability and/or access to economic infrastructure (such as (1) financial
systems, (2) business logistics, (3) manufacturing infrastructure, and all other support
infrastructure (power and energy, transport, communication, water reticulation, sewerage and
sanitation) for those who need to get involved in value addition of natural resources.
However government through its fiscus is struggling to allocate its limited resources to provide
assistance for manufacturing and value addition. In order to migrate from the resource based
economic development and growth, Government need to strengthen the manufacturing sector of
the economy to provide effective economic infrastructure and all support infrastructure.
It must be borne in mind that an attempt to provide such infrastructure was made but its state
and ability to attract investors, grow the economy and create jobs is minimal. It is therefore
important to device a big bang approach to turn around the status quo.
5. OBJECTIVES
The primary objective of these terms of reference is to develop a blue print and a model to
guide the establishment of an effective Industrial Park that shall facilitate the attainment of the
South African Industrial Policy and Strategic Objectives, which will contribute towards
sustaining industrial growth, accelerating industrial restructuring and raising the level of
competitiveness of the economy through:
• Restoring areas that might be old, unsuitable or unusable; • Expanding supply of services and well-developed industrial area; • Increasing property values and their attractiveness; • Encouraging existing businesses to stay; • Attracting new investment; • Providing opportunities and incentives for current businesses expansion; • Stimulating local economy; • Creating new jobs; • Increasing availability of land and buildings satisfying specific quality standards and regulatory
standards; and • Addressing spatial economic challenges and inequalities.
6. LIMITATIONS
There is currently no blue print as to how the then Government Industrial Parks were
established except that they were intended to achieve separate development objectives of the
previous dispensation which are not sustainable. And there is also no model to utilise in the
conceptualisation of new Industrial Parks in pursuing industrialisation and regional
development.
XIII
7. DELIVERABLES
Inception report
Scoping report including an assessment of the performance of the existing SEZ/FTZ in SA and the lessons learnt.
Industrialization Resuscitation and Revitalisation Programme based on amongst others o Regional Industrial Comparative advantage o Regional Industrial Competitive advantage o Industrial Clustering alternatives o Market Analysis report o Financial Analysis report o Skills Requirement report
8. POLICY ENVIRONMENT
The Industrial Development Programme is governed by a host of legislative and regulatory
framework which the service provider must fully understand and review. These legal
frameworks include amongst others:
The New Growth Path: The Framework
Industrial Policy Action Plans
Provincial Employment, Growth and Development Plans
Regional Industrial Development Strategy
Provincial Industrial Development Strategies
National Industrial Policy Framework
Manufacturing Development Act No. 187 of 1993
National Development Plan
National Infrastructure Development Strategies
9. PROJECT TIMING
The work break down structure (WBS) of the project is expected to cover all possible and required activities. The final report of the project is expected to be tabled not later than 10 months after the appointment of the service provider. 10. EXPERTISE REQUIRED
The team of experts of specialized service providers shall be required with the knowledge of economic and financial modelling that shall need understanding of the socio economic dynamics of South Africa with special reference to spatial economic regions. Models replicated in the regions should take consideration of the regional context and stage of development per region. 11. QUALIFICATIONS AND PROFESSIONAL EXPERIENCE
The team should display the talent in this particular field of analysis. Recognized qualification with documented proof might be required as well as work done in the related field of economic development and investment. The table hereunder indicates the key experts that should be in the team.
Experts Estimated Time Input (Months)
Economic & Financial Analyst (Team leader) 10
Socio-economist and gender expert 8
Industrial Development expert 4
Market Analyst 3
Skills development expert 3
XIV
ANNEX 3: DETAILED COST ESTIMATES Item N°
Description Units Q'ty Unit Cost Total Base Cost Source of Financing
Component 1: Supporting Local
Economic Development
ZAR UA ZAR UA
1 1.1 Local Economic Development Study Consultancy (LED maturity assessments;
Business activity profiles; Competitive
advantage appraisal; Business retention & expansion strategies)
u 1 3,893,000 237,519 3,893,000 237,519 ADB
2 1.2 District LED Workshops / Seminars u 6 166,666.67 10,169 1,000,000 61,012 ADB
3 1.3 National conference on LED u 1 500,000 30,506 500,000 30,506 ADB
4 1.4 Review of existing LED strategies and alignment to national policies
(GoSA)
u 1 3,933,672 240,000 3,933,672 240,000 GoSA
Sub-total Component 1 - 9,326,672 569,036
Component 2: Developing Pilot
Specialized Industrial Facilities (SIFs)
-
5 2.1 Review and Design of Teaching and
learning material (Entrepreneurship curriculum development for SIFs) - MoU
with FET Colleges
u 1 190,000 11,592 190,000 11,592 ADB
6 2.2 SIFs Facilitation (Business
Development Support and mentorship of SMMEs) - MoU with FET Colleges
u 1 680,000 41,488 680,000 41,488 ADB
7 2.3 SIF Equipment & machinery (tech.
Specs prepared by FET colleges)
u 1 3,278,060 200,000* 3,278,060 200,000 ADB
Sub-total Component 2 - 4,148,060 253,080 ADB
Component 3 – Assessing the
Feasibility of Industrial Parks
-
8 Detailed Pre-Investment Study (DPIS)
on the upgrade and expansion of State-Owned Industrial Parks and the
Development of a Strategic Plan -
Consultancy
u 1 4,900,000 298,957 4,900,000 298,957 ADB
Sub-total Component 3 - 4,900,000 298,957
Component 4: Project Management -
9 Field monitoring of activities (travel, DSA, field accommodation etc.)
u 1 1,943,710 125,566 1,943,710 125,566 ADB
10 Advertisements & publicity (Tender
documents and other project activities)
U 1 180,000 10,982 180,000 10,982 ADB
11 Project Steering Committee Meetings (quarterly)
U 12 20,000 1,220 240,000 14,643 ADB
12 Reporting (preparation, reproduction and
dissemination; quarterly)
u 12 5,000 305 60,000 3,661 ADB
13 Project communication costs (telephone; internet; etc.)
month 36 2,260.5 138 81,378 4,965 ADB
14 Validation / dissemination workshops &
seminars
u 1 500,000 30,506 500,000 30,506 ADB
15 Annual Auditing of Project yr 3 200,000 13,288 600,000 39,863 ADB
Procurement Consultant - Individual yr 1 200,000 13,118 200,000 13,118 ADB
16 Project Completion Report Mission
Individual Consultant
u 1 50,000 6,772 50,000 6,772 ADB
Sub-total Component 4 - 3,855,088 249,159
Total Base Cost - 22,229,820 1,370,233
Physical Contingency (3%) 666,895 33,607
Price Contingency (4.5%) 1,000,342 54,160
TOTAL 23,897,057 1,458,000
* Max amount: contingency inclusive.
XV
ANNEX 4: FINANCIAL MANAGEMENT AND DISBURSEMENT ARRANGEMENTS
FINANCIAL MANAGEMENT ASSESMENT REPORT
Summary description of Project
The EDP project aims to contribute towards job creation and poverty reduction through supporting
enterprise development in South Africa. This will be achieved through three interlinked components,
namely; Supporting Local Economic Development (LED), Developing Pilot Specialized Industrial
Facilities (SIFs) and Assessing the Feasibility of Industrial Parks. The total estimated cost of the pilot
project is UA 1,458,000 (inclusive of contingencies) and shall be financed by a MIC grant allocation of
UA 1,200,000 under the MIC Technical Assistance Fund while the Government of South Africa shall
finance the rest.
Summary Country Issues
The Government of South Africa has over the years been reforming its Public Financial Management
(PFM) systems focusing upon among other things, the establishment of a legal and regulatory
framework to strengthen and improve upon the transparency, comprehensiveness and credibility of the
budget, debt management and external scrutiny and oversight. This has continued to yield significant
benefits as indicated in the last PEFA (2008) that showed that South Africa has generally well
performing PFM systems at the national level. A 2014 PEFA assessment is currently underway.
Overall, fiduciary risk is deemed low, with a sound Public Financial Management system in place at
central Government level as enforced by the Public Finance Management Act of 1999. However there
still remains room for improvement at the municipal and provincial governments which has been
characterized by some unfavorable audit reports from the Office of the Auditor General. These
weaknesses in the municipal and provincial governments have been mainly attributed to capacity
constraints, both in terms of human skill and systems; staff turnover amongst the skilled FM personnel
also remains a contributory factor. Other concerns at all levels of Government include budgetary
disclosure deficiencies by some departments and in accuracy of in-year reporting, both which have a
negative impact on the transparency indicators.
The Government of South Africa is working on all the currently existing gaps through two major
instruments, 1) A comprehensive PFM reform program which includes the improvement of the ICT
environment; and 2) A PFM Capacity Development Strategy which now targets both the National and
Provincial Governments. Success in delivering on these will go a long way in minimizing impact of
existing gaps and even further narrow them down. There is a PFM Capacity Building Unit within the
National Treasury that is coordinating these reforms and quarterly meetings are held with the PFM
Donor Coordination group that provide opportunities for development partners to share experiences
related to the various PFM disciplines. The project will be implemented at the Central level and hence
will use the existing country systems.
Risk assessment and mitigation
The Bank’s principal concern is to ensure that project funds are used economically and efficiently for
the purpose intended. Assessment of the risks that the project funds will not be so used is an important
part of the financial management assessment work. The risk features are determined over two elements:
the risk associated to the project as a whole (inherent risk) and the risk attached to a weak control
environment of the project implementation (control risk). The content of these risks is described below.
XVI
Risk Type Risk
Ratin
g
Risk Mitigating Measures
Incorporated into Project
Design
Conditionali
ty (Y/N)
Residua
l Risk
Rating
Inherent risk H
Country level
Various diagnostic work
reports (including the
2008 PEFA) have pointed
out major concerns on
PFM at provincial and
municipal levels of
Government. The project
is mainly intended for
beneficiaries within
municipality and
provincial governance.
H
The project implementation
will be centralized/
concentrated at the Central
Government level, the Dti
will be the implementing
agency whilst the National
Treasury will play a key role
in funds management and
reporting. A comprehensive
PFM reforms program is
underway and have been
expanded to include
municipalities particularly in
areas of training and system
development.
N
M
Entity level
The day to day
implementation of the
Project will rest with the
Broadening Participation
Division (BPD), which is
currently under the Dti,
and uses all the shared
systems, personnel and
procedures of the Dti.
However, following a
Cabinet reshuffle in May
2014, the BPD will
migrate to a newly
formed Department
(Ministry) of Small and
Medium Enterprises,
modalities and logistics
remain largely unknown.
M
The project implementation is
based entirely on central
Government systems, which
are uniform across all
Government departments
(ministries). The Dti has
assured the migration, should
it happen during project
implementation, will be well
managed to avoid disruptions.
Further, the involvement of
the National Treasury will
provide the necessary
continuity.
N
L
Project level
The project, despite its
small size will be
implemented with
involvement of multiple
partners; i.e. National
Treasury, BPD, and at
least three FET colleges
across different provinces
of South Africa
The Dti also has no
experience with Bank
funded projects
M
The Dti will assume the
central coordinating role as
well as the overall
responsibility over the project.
There will be training and
support provided by the Bank
during the implementation of
the project
Y
L
XVII
Risk Type Risk
Ratin
g
Risk Mitigating Measures
Incorporated into Project
Design
Conditionali
ty (Y/N)
Residua
l Risk
Rating
Control Risk M L
Budgeting: The Project
resources are immaterial
from the perspective of
the National Budget of
South Africa, although
implementation will
follow the National
Budget execution
mechanisms. This could
lead to non-alignment in
budget vs. expenditures
for the project.
M
At the point of receiving
funds, budget lines shall be
introduced into the IFMIS,
against which expenditures
shall be posted as and when
payments take place. The
system will not allow
payments against codes to
which no budget allocation
exist.
N
L
Accounting:
No material risks
identified
N/A
N/A
Internal Control:
No material risks
identified
N/A
N
N/A
Funds Flow:
The National Treasury’s
procedures for ODA’s
funds are not fully
consistent with Bank’s
rules on use of Special
Accounts as they call for
commingling of funds.
Commingled funds face
risk of diversion to
purposes other than the
intended.
The project design is such
that funds for some
operating expenditures
will be disbursed to the
FET colleges, where
monitoring mechanisms
may need to be
reinforced.
M
An assessment into the
procedures reflect that despite
the commingling, the systems
in place adequately maintain a
visible trail of funds flow with
minimal chances of
undetectable diversion of
funds. The disbursement
division (FFCO.3) have
agreed to the procedures on
an earlier project and Bank
funds have already been
disbursed under the same.
Dti is already working with
FET colleges on a Project
under which they disburse
funds to FET colleges, the
established monitoring
mechanisms will be
applicable to the project.
Confirmation
of PIC and
related Grant
specific GL
account
details to the
Bnk
L
XVIII
Risk Type Risk
Ratin
g
Risk Mitigating Measures
Incorporated into Project
Design
Conditionali
ty (Y/N)
Residua
l Risk
Rating
Financial Reporting
The project will be
implemented entirely via
Government PFM
systems. The National
accounts of the Republic
may render some projects
transactions/amounts
immaterial for disclosure,
thus resulting in deficient
reporting for Bank’s
purposes.
M
The Project’s financial
reporting will be prepared on
a separate basis in accordance
with the Bank’s information
requirements.
N
L
Auditing:
Whilst the financial
statements will be
prepared for the Project
on a ring fenced basis, the
Auditor General audits
the Department’s
Accounts as a whole. And
due to immateriality, the
Project funds may fall
outside the scope on the
AG’s work.
M
A specific request will be
made to the AG for the
Project, and resources have
been earmarked for an
independent external auditor
should the AG decide to
outsource the Audit. There is
a sufficient number of
competent audit firms in
South Africa.
N
L
OVERALL FM RISK M L
Strengths and Weaknesses
Strengths
The Implementing Entity has experience of implementing Donor funded projects, and the proposed
implementation mechanism with the FET colleges have been adopted and applied in ongoing projects
funded by other donors
Weaknesses
The Project implementation team is not familiar with the Bank’s project implementation procedures
(including those for Financial Management and Procurement).
Description of the Implementing Entity
The Project will be implemented by the Department [Ministry] of Trade and Industry (Dti), under
which the Broadening Participation Division (BPD) will be responsible for the day to day operations.
The Dti is headed by a Director General, who reports to the Minister of the Department (Ministry). An
executive board exists to provide strategic direction of the department and this comprises the Heads of
Divisions (at Deputy Directors-General level), Group Chief Financial Officer (GCFO), Chief Financial
Officer (CFO), Group Chief Operations Officer (GCOO), Head of Ministry, and Head of
Communications and Marketing, and is chaired by the Director-General. In addition to the Executive
Board, the following specialized sub committees also exist: Operations Committee, the Bid Evaluation
Committee and Bid Adjudication Committee, the ICT committee, the Audit Committee and Risk
Management Committee.
XIX
Reporting to the Director General are nine Deputies, each heading a specialized division, including the
BPD under which the project will be implemented. The Dti recruits its own finance personnel for
posting to different divisions, but all remaining under the Chief Financial Officer’s Directorate.
Although vacancies exist under this Directorate, the project implementation will not be directly
affected as the BPD has already identified suitably qualified individuals to assume responsibility over
the Project transactions who are expected to be in place for project implementation
Some activities will be conducted at identified beneficiary institutions, i.e. Sekhukhune, Lovedale,
Northern Cape Urban and Ekurhuleni West Further Education Training Colleges FET). These colleges
are colleges are established and governed in terms of the Further Training Colleges Act of 2006 (As
amended by the Higher Education and Training Laws Amendment Act of 2010. Each of the FET
colleges have a council, which appoints a number of sub committees including Finance and Audit &
risk committees. During appraisal, a visit was undertaken to the Ekurhuleni FET College, the largest of
the four. The Deputy Principal Academic Affairs will assume overall responsibility of the project at
college level, where funds will be managed through the CFO’s office. The CFO heads the finance
department, which is adequately staffed with persons of consummate qualifications and skills. The
accounting environment is fully computerized (making use of Integrated Tertiary Solutions - ITS) and
bank accounts are managed through cashbooks based on this system. The ITS also incorporate other
generic sub modules – creditors, debtors, procurement and assets. The College adopts the Treasury
Instructions as issued by the National Treasury and on its basis, bank reconciliations are conducted and
reviewed timely on a monthly basis. All other colleges operate on these basis, which are adequate for
the purposes of managing the grant funds.
Budgeting Arrangements
In terms of Section 52 of the PFMA, the annual budgets are due for submission to the Treasury not
later than thirty (30) days before the commencement of the relevant financial year. Such budgets are
policy based and based on national priorities at Central Government level. However, due to the Grant
amounts and nature of the pilot project, the Project budgets will not necessarily be consolidated to the
National Budgets, hence the preparation process will also be project specific. The Dti will prepare work
and procurement plans for the entire project, which will be subject to the approval of the Bank on the
basis of which project annual budgets shall be prepared for approvals following the Dti established
Governance process.
Key Accounting Policies and procedures
The South African Government’s public finances are guided by the Public Finance Act No.1 of 1999,
which is complemented by the Treasury Regulations of 2005 which cover all key areas of PFM
including planning and budgeting, expenditure management, internal control, accounting and reporting.
The regulations are reviewed every four years following established procedure and are widely
distributed through both the web and intranet. Staff have sufficient levels of understanding. The
Government’s financial systems are computerized and make use of an Integrated Financial
Management Information System, i.e. the Basic Accounting System (BAS) which is based on the
Government’s standard Chart of Accounts.
BAS allows transaction origination and/or entry to be directly posted to the appropriate function or
project (including ad-hoc ones), the system also allows for activation of additional GL accounts and
sub accounts based on strict approval by the National Treasury. This will allow for the project budgets
and associated transactions to be captured in an identifiable manner within the system. To ensure
integrity of the system and its content, there is sufficient segregation of duties between system users
and administrators, and any direct entries to the GL are subject to approvals of journal entries.
Passwords are issued with level of security controls depending on ‘view only’ or view and post’
requirements, this therefore ensures integrity of sub GL accounts. Supporting documents are neatly
filed away and retained for a period of up to 7 years. Accounting is on cash basis and adopts IPSAS.
The Government’s accounting policies, procedures and systems in application at the Dti are sufficient
for the purposes of implementing the project, as such no additional requirements will be placed. The
XX
FET colleges, which will receive some funds for operations expenses (once of workshops and
seminars) are also governed by the PFMA and the Treasury Regulations.
Internal Control and Internal Auditing
Based on the Government’s legislative framework, Treasury Instructions and systems in place (see
above), the Dti’s internal control environment is assessed as adequate. Most key processes are bases on
the IFMIS. The payment system is computerized, such that any payment has to be allocated from a
‘pulled up’ invoice already input into the system and different users are involved in this process.
However, manual supporting documents are still maintained in a systematically arranged filing system
for ease of reference as and when needed. Such supporting documents are part of submissions for
payments authorizations, and are stamped ‘PAID’ once processed to eliminate possibilities of double
payment.
Banking, Cash and Investment framework of the Government are governed by Section 7 of the PFM
Act, whose provisions guided the drafting of the relevant policy and its procedures enshrined in both
the Treasury Instructions and BAS. The Dti currently maintains a single Bank account with a
commercial Bank, into which the National Treasury disburses the department’s allocated funds. It is
also the account from which funds for other Dti’s units (including the FET colleges intended to benefit
under the EDP pilot project) are disbursed3. This account is well managed with monthly reconciliations
performed and approved not later than 11 days after month end.
Payments are all based on an Electronic Funds Transfer (EFT) platform with which controls are strict,
the officer loading payment requests is different from the ones authorizing payments and this is made
possible through the use of access rights passwords.
The Dti has a fully-fledged Internal Audit Department in house, headed by an appropriately qualified
Chief Internal Auditor reporting directly to the Director General. The findings and recommendations of
the internal audit department are timeously acted upon through departmental heads and there is regular
feedback reporting on progress, which the internal audit department cross checks. From time to time,
the Internal Audit department does include ad hoc projects in their annual work plans based on timely
requests received from project managers. It has been agreed that the Internal Audit department will be
requested to conduct the EDP pilot project at least at its mid-term.
Funds Flow and Disbursement Arrangements
The National Treasury oversees all funds flows from ODA, and has sufficient controls around
expenditure management, payment process and bank account management (See sections above on
accounting policies and internal controls). This will permit an exclusive use of the Special Account
method as requested by the Dti, being the preferred method by the National Treasury for smaller
Grants.
However, as per agreed procedures (in prior grant funded operations currently ongoing), the Bank has
exceptionally acceded to a request that the Grant Funds will be disbursed to an already existing account
(The Public Investment Account). The process will be as follows: 1) The Bank disburses funds to the
Public Investment Account held with the Reserve Bank of South Africa 2)The National Treasury
manages and tracks funds deposited per Donor by use of GL Accounts 3) As and when the Dti is to
spend, they place a request with the National Treasury, which then disburses the required funds to the
Dti’s Bank account held with a commercial Bank (currently Standard Bank of South Africa). The rest
of the justification process follows Bank procedure, and interim reporting between the National
Treasury and the Dti will take place on a monthly basis, outlining the status of the funds held in the
Public Investment Accounts.
Disbursements to FET colleges by the Dti shall be made from funds deposited into Dti’s account by the
National Treasury. Replenishments of both the Dti and FET colleges accounts shall be based on duly
submitted 6 months budgets and conditional upon full justifications of funds previously advanced.
In addition, the reimbursement method shall remain available for use in accordance with Bank rules.
3 The finalization of procedures relating to funds transfers to FET colleges, as well as their management will be subject to a
review of systems at the FET colleges, which is planned to take place before final approvals of the Grant.
XXI
The entire disbursement process will be in accordance with Bank’s disbursement rules which will be
outlined at Project launching.
Below is a graphic illustration of the proposed funds flow.
Financial Reporting
There is regular financial reporting at the Dti as guided by standing Treasury Regulations applicable at
central Government level. Quarterly management accounts are prepared by the for use by the Dti
management as well as the National Treasury, however, these does not ordinarily contain sufficient
details of smaller ad hoc projects funded through the ODA mechanism.
The Government’s fiscal year runs from 1st April to 31
st March. In accordance with the PFMA, annual
financial statements are due for submission to the Auditor General (who has been assessed as
competent in prior Bank assessments) not later than 31st May each year. The Auditor General has a
statutory timeline of 2 months within which to complete his audit and issued an audit report. By the 31st
August, an annual report (that include audited financials) is due for submission to the Minister in the
Dti, who then tables it to Parliamentary Portfolio committee on Public finances not later than the 30th
of
September. A review of past audited financial statements of the have not revealed any material
malpractices in the preparation of annual financial statements.
However, due to the size of the EDP pilot project, as well as the quantum of expected transactions, the
project financial reports (both quarterly and annual) will be prepared on a ‘stand alone’ basis. This is
mainly due to the fact that the project amounts could be below the disclosure thresholdsfor the Dti’s
own financial statements.
Formats of the financial reports will be developed and agreed during project launching but in any
event, the financial statements will include (i) a Statement of Financial Position that shows Assets and
Liabilities ; (ii) a Statement of Sources and Uses of Funds showing all the sources of Project funds,
expenditures analyzed by Project component and or category; (iii) a Summary of Withdrawals using
SOE, listing individual withdrawal applications by reference number, date and amount; and (iv) Notes
related to significant accounting policies and accounting standards adopted by management and
underlying the preparation of financial statements. These will be due not later than six (6) months after
the end of the financial year and project closure.
ODA Investment GL Level
Accounts
FET
College
FET
College
FET
College
SERVICE PROVIDERS
ADB PIC Ac
(NT)
Dti Bank
Account
XXII
On a quarterly basis, the Dti shall ensure that the overall Interim Project Progress Report contains
sufficient financial management information, reflecting among others sources and uses of funds, total
expenditures classified by Project component, against associated quarterly budgets as well as budget
forecasts for the next quarter. The Interim Project Progress Report shall be due not later than 45 days
after the end of the quarter.
External Audit
The Dti is audited annually by the Auditor General, as required by the PFMA. The statutory limits as
outlined in this annex (see section on ‘Financial Reporting’) are well complied with, i.e. the Auditor
General receives unaudited financials by 31st May each year and issues the audit reports not later that
31st July each year. The 2013 audited report was issued on the 31
st July 2013. The Auditor General
conducts his audit in terms of the Public Audit Act of South Africa, 2004 (Act No. 25 of 2004) (PAA),
the General Notice issued in terms thereof and International Standards on Auditing and has not brought
any accountability issues in his audits for the past three years. The Auditor General’s recommendations
are timeously implemented and the Internal Audit department periodically monitors progress.
To this end, the Project’s separate annual financial statements, fully disclosing project receipts and
associated expenditures by component be the responsibility of the Auditor General, and copies of the
audited statements and audit reports shall be submitted to the Bank not later than 30th
September each
year. However, should the Auditor General approves the audit to be outsourced, a competitive selection
process complying with the Bank’s procurement rules shall be undertaken, and associated costs shall
be paid from the Grant resources. In either case, the audit shall comply with bank approved Terms of
Reference.
Condition to first Disbursement
Confirmation of Special Account details (i.e. The Public Investment Account details plus the relevant
Grant GL Account details) in a form and manner acceptable to the Bank.
Supervision plan
Based on the current risk assessment, on site financial management supervision shall take place at least
once a year supplemented by another desk review based supervision which will be undertaken at least
once a year as well.
XXIII
ANNEX 5: PROCUREMENT ARRANGEMENTS AND OUTLINE PROCUREMENT
PLAN
1. All procurement of goods, and acquisition of consulting services financed by the Bank will be
in accordance with the Bank’s Rules and Procedures: “Rules and Procedures for Procurement of
Goods and Works”, dated May 2008 (revised July 2012); and “Rules and Procedures for the Use of
Consultants”, dated May 2008 (revised July 2012); as amended from time to time, using the relevant
Bank Standard Bidding Documents, and the provisions stipulated in the Financing Agreement. The
Department of Trade and Industry (dti), the Executing Agency, through the Broadening Participation
Division (BPD) will be responsible for the implementation of the project and procurement of goods,
consulting services, and training. Given its experience in using the Bank’s Procurement Rules, the
Supply Chain Management Unit at the National Treasury, will support the Procurement Unit at the dti
in conducting procurement activities for the Project. The procurement arrangements are presented in
Table 5 hereunder. All selections of consultants shall be carried out using the shortlisting process. For
the consultancy services (studies) the selection procedure will be based on Quality-and-Cost Based
Selection (QCBS) and National Competitive Bidding (NCB) for goods.
Table 5. The Procurement Arrangement (UA) for the activities financed under the MIC-TAF Grant
Categories
NCB Shortlist Shopping Other*
Non-
Bank
Funded
Total
1 GOODS
1.1 SIF Equipment & machinery (tech.
Specs prepared by FET colleges) 200,000
200,000
2 WORKS
-
3 SERVICES
-
3.1 Local Economic Development Study
Consultancy (LED maturity assessments;
Business activity profiles; Competitive
advantage appraisal; Business retention &
expansion strategies)
255,332
255,332
3.2 Detailed Pre-Investment Study (DPIS)
on the upgrade and expansion of State-
Owned Industrial Parks and the
Development of a Strategic Plan -
Consultancy
321,379
321,379
3.3 Review of existing LED strategies and
alignment to national policies (GoSA) 258,000 258,000
3.4 Annual Auditing of Project (OAG-
SA) 42,853
42,853
3.5 Procurement Consultant – IC**
13,118
13,118
3.6 Project Completion Report Mission
(Individual Consultant) 7,279
7,279
4 OPERATING COSTS
-
4.1 District LED Workshops / Seminars
65,588
65,588
4.2 National conference on LED
32,794
32,794
4.3 Field monitoring of activities (travel,
DSA, field accommodation etc.) 134,983
134,983
4.4 Advertisements & publicity (Tender
documents and other project activities) 11,806
11,806
4.5 Project Steering Committee Meetings
(quarterly) 15,741
15,741
4.6 Reporting (preparation, reproduction
and dissemination; quarterly) 3,935
3,935
4.7 Project communication costs
(telephone; internet; etc.) 5,337
5,337
4.8 Validation / dissemination workshops
& seminars 32,794
32,794
4.9 Review and Design of Teaching and
learning material (Entrepreneurship
curriculum development for SIFs) - MoU
12,462
12,462
XXIV
Categories
NCB Shortlist Shopping Other*
Non-
Bank
Funded
Total
with FET Colleges
4.10 SIFs Facilitation (Business
Development Support and mentorship of
SMMEs) - MoU with FET Colleges
44,600
44,600
TOTAL 200,000 632,682 - 410,171 258,000 1,458,000
*Other: Gov’t of South Africa procedures and Individual Consultant (IC**).
2 To enable the effective implementation of the Specialized Industrial Facilities (SIFs)
component of the Project, Memorandums of Understanding (MoUs) shall be entered into
between the dti and the targeted FET colleges. Under the MoUs, the FETs will be responsible for
developing the technical specifications of the equipment and machinery to be procured for the pilot
SIFs and for the review and design of teaching and learning material (entrepreneurship curriculum
development for SIFs) as well as for SIFs facilitation (providing Business Development Support and
mentorship to SMMEs that access the SIFs).
3 Documents to be approved by the Bank during procurement:
6.2.1 General and Specific procurement notices;
6.2.2 Short-list of consultancy firms;
6.2.3 Letter of invitation to Consultants (RFPs);
6.2.4 Technical and Financial/Final evaluation reports;
6.2.5 Bidding documents for goods;
6.2.5 Draft contracts, if these have been amended from the drafts included in the tender
invitation documents;
6.2.6 Amendments to the signed contracts, if any; and
6.2.7 TOR for annual audit.
4 For the procurement of services estimated to cost UA 200,000 and above, the Request of
Expression of Interest (REoI) shall be published in the UN Development Business (UNDB online)
and Bank’s website. For the procurement of services below UA 200,000, the announcement shall be
published in local and regional newspapers.
5 The external annual audits of the operation shall be conducted by the Office of the Auditor
General of South Africa following national procedures. However, provisions have been made for
the procurement of an external auditing firm to carry out the annual auditing of the project accounts in
case the Office of the Auditor General authorizes the recruitment of an external audit firm to conduct
the exercise.
Goods Contracts with Procurement Methods and Time Schedule:
Package description
Estimated
Amount in
UA
Procurement
Method
Pre-or Post-
Qualification
Dom. or
Regional
Preference
Prior or
Post
Review
SPN
Publication
Date
Contract
Start
Date
SIF Equipment &
machinery (tech. Specs
prepared by FET
colleges)
200,000 NCB Post N/a Prior Feb 2015 May
2015
XXV
Services Contracts with Procurement Methods and Time Schedule:
Description Selection
Method
Lump sum or
Time-Based
Estimated
Amount in
UA (‘000)
Prior/Post
Review
EOI
Publication
Date
Contract
Start Date
Local Economic Development Study
Consultancy (LED maturity
assessments; Business activity profiles;
Competitive advantage appraisal;
Business retention & expansion
strategies)
QCBS Lump sum 255,332 Prior Feb 2015 June 2014
Detailed Pre-Investment Study (DPIS)
on the upgrade and expansion of State-
Owned Industrial Parks and the
Development of a Strategic Plan -
Consultancy
QCBS Lump sum 321,379 Prior Feb 2015 July 2014
Annual Auditing of Project (OAG-SA) OAG or LCS Lump sum 42,853 Post Sept 2015 March
2015
Procurement Consultant - IC IC Lump sum 13,118 Post Feb 2015 April 2015
Project Completion Report Mission
(Individual Consultant) IC Lump sum 7,279 Post Dec 2016 April 2017
XXVI
ANNEX 6: SOUTH AFRICA DISTRICT MAP
Project Districts:
Sekhukhune (47); Lejweleputswa (18); West Rand (48);
Nkangala (31); Waterberg (36);
and Bojanala (37).