new technology leads to savings on underwater pile encasements
TRANSCRIPT
1 |1 |
New technology leads to savings on underwater pile encasements at Barron River BridgeStephen Day
Civil Engineer, Program Delivery and Operations |
Department of Transport and Main Roads
2 |2 |
Overview
1. Introduction/background2. Phase 1 – Initiation 3. Phase 2 – Options review 4. Phase 3 – Market exploration 5. Phase 4 – Monitoring 6. Phase 5 – Finding a solution 7. Phase 6 – Project delivery 8. Conclusion.
3 |3 |
Introduction
Purpose• Outline 15-year search for cost-effective treatment for
Alkali Silica Reaction (ASR) cracking in underwater piles• Provide information on Fibre Reinforced Plastic (FRP)
pile jackets• Highlight potential benefits of new technology
Cost savings Technical advantages.
4 |4 |
The structure
Barron River Bridge (ID 7779) on Captain Cook Highway• Seven-span prestressed concrete (PSC) bridge on
major arterial highway (16,000 vehicles per day)• Constructed in 1977• 176.5 m long, 10.4 m wide• Blade piers founded on driven PSC piles (10 per pier).
10 |10 |
Project initiation 2000-2003
Date Work Activity Outcome
Nov 2000 Concrete Technology (CT) Report No.1 Investigation
Chloride induced corrosion Cracking in Piles
Nov 2001 Level 2 Inspection Bridge in poor condition
Jun 2002 CT Report No. 2 Remedial Works
Pier Repairs and Cathodic Protection (-> 2006)
Nov 2002 Underwater Inspection (Eight piles)
Vertical/horizontal cracks Up to 15 mm
Dec 2002 Treatment Options reviewed (Principal Engineer (CT)
FRP – no underwater epoxyReinforced Concrete (RC) encasement preferred
Jan 2003 Underwater Inspection (Seven piles)
Similar crackingProblems with spacing of piles
11 |11 |
The issue
ASR cracking in PSC piles in marine environment• Potential for premature corrosion – loss of service life• Uncertainty with extent of corrosion in prestressed steel • Other piles likely to suffer same fate.
12 |12 |
Preferred treatment
• Pile encasement Seal existing cracks Inhibit Cl, H2O, O2 ingress Increase internal pressure to limit ASR.
• Pile encasement options Traditional Reinforced Concrete (RC) FRP jacket.
17 |17 |
Options review (2004-2005)
Date Work Activity OutcomeMar 2003 FRP Prototype Feasibility
Project concludedFRP prototype utilising mechanical (finger) locks not yet viable
May 2004 Options Review Meeting FRP Jackets preferredConsider staged repairs
Aug 2004 Remaining Piles Inspected 13 of 40 piles flagged for Stage 1 repairs
Aug 2005 2005 Technical Forum Paper by Carse/Hamilton
Awaiting market development in FRP Jackets
18 |18 |
Underwater inspections (2002-04)
• Three separate inspections summarised in a Defect Map
• 13 of 40 piles severely cracked
• Remedial treatment recommended for severely cracked piles.
19 |19 |
Benefits of FRP
• Potentially significant cost savings• Slimmer design (80 mm versus 200 mm)• No reinforcement• Simplified construction for placement of grout• Impermeable barrier • Excellent confinement strength.
23 |23 |
Market exploration (2006-2008)
Date Work Activity OutcomeMay 2006 Expression of Interest
(EOI) process proposedWorks package – four sites (Barron plus three other bridges)
Mar 2007 EOI Called Four submissions (No FRP)
Jun 2007 Design Development (Double ECI (Early Contractor Involvement))
Two companies engaged
Aug 2007 Design submissionsPreferred design selected
Pricing for Barron piles 0.50m v $1.4m
26 |26 |
Market explorationDate Work Activity OutcomeOct 2007 Project split into 2 Contracts:
1. National Highway (three bridges)
2. State roads (Barron River bridge)
National Highways Contract awarded and completed
Feb 2008 Tendered Price for Barron R increases 400% to $2.0m
Barron River Contract abandoned pending developments in FRP jackets
28 |28 |
Monitoring 2009-2014
Date Work Activity OutcomeVarious L2 Inspections
Aug 2014 Underwater Inspection 22 piles now crackedPiles cleaned
2014 Underwater Inspection• Total cost $0.15m
Installation of crocodile protection (30%) Cleaning (50%) Inspection (20%)
29 |29 |
Underwater inspection 2014
• Results overlaid on original Defect Map
• 22 piles now exhibiting severe cracking (previously 13)
• Other piles with minor cracks.
31 |31 |
Finding a solution 2014-2015
Date Work Activity OutcomeAug 2014 FRP Treatment Review PileMedic identified as a
candidate treatment
Oct 2014 PileMedic proposal Cost Estimate - $1.1m Project planning initiated
Feb 2015 Funding secured (Element 19 – Structure Rehab)
All 40 piles
Mar 2015 Structure Management Plan (SMP) submitted and approved
Project prioritisedFunding reallocated
32 |32 |
FRP solution – PileMedic
• Pilemedic jackets Thin preformed FRP laminate sheeting Seamless cylindrical shell (two layers) Underwater-curing epoxy
• Advantages• Rapid underwater installation• Impermeable barrier • High confinement strength• Cost savings
36 |36 |
Project delivery
Date Work Activity OutcomeApr 2015 Contract – Materials Supply
Sole InviteeBuilding Services Brisbane/ Quakewrap($0.284m)
May 2015 Contract – Construction Sole Invitee
Roadtek($0.51m)
June 2015 Site works commenced
Aug 2015 Site works completed
37 |37 |
Supplementary specification
• Work Items 9001.01P - Cleaning of Piles 9002.01P - Install PileMedic Pile Encasement 9003.01P - Supply and Deliver Pile Encasement Material 9004.01P - Install Grout
43 |43 |
The economicsEstimate Year Value 2015 ValueInitial SMP Estimate (FRP) 2007 $0.75m $0.95m
RC Encasement OptionEOI Preliminary Design
(Alternate Supplier)2008 $0.5m
($1.4m)$0.61m($1.72m)
Tendered Price 2008 $2.0m $2.46m
Final FRP OptionProject Estimate 2015 $1.1m $1.1mFinal Project Cost 2015 $0.95m $0.95m ($24k/pile)
Estimated Savings - $1.5m (160%) over tendered RC, - $0.77m (80%) over RC alternative
44 |44 |
The project teamGroup Role Team member
TMR Far North District Project initiation, development and management
Stephen DayKarl Alolod
Structures Branch Technical review and approval
Faisal Mir
Roadtek Works delivery Coordination of works
Andrew Schelberg
Commercial Divers (JD Marine)
Underwater works
Product Supplier (Building Solutions Brisbane)
Technical advice Training of works team
Tony White
Manufacturer (Quakewrap) Technical support Professor Mo Ehsani
45 |45 |
Conclusion
Learnings• Significant savings can be achieved by utilising new
technologies• FRP pile jackets are a cost-effective option for pile
encasement, particularly for: underwater installation where access is restricted.
46 |46 |
Conclusion (cont.)
Learnings• The “do nothing” option can be an effective asset
management strategy • Explore and embrace new technology – but do your
homework• A good team working together is essential when
introducing new technology.