newport city council local impact report · st brides, wentlooge, newport . page 2 of 26 1.0...

26
Page 1 of 26 NEWPORT CITY COUNCIL LOCAL IMPACT REPORT PINS Reference Number DNS/3216558 Wentlooge renewable energy hub Applicant Wentlooge Farmers’ Solar Scheme Limited Applicants’ Agent Savills LPA Reference Number 20/0407 Application Type Development of National Significance Proposed Development Erection of a Renewable Energy Hub comprising ground mounted solar panels, battery storage units (160 units) with a combined installed generating capacity of up to 125MW, underground cabling, grid connection hub, associated infrastructure, landscaping and environmental enhancements for a temporary period of 40 years. Application Site Land North Of Greeacre Farm, Coast Road St Brides, Wentlooge, Newport

Upload: others

Post on 20-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

  • Page 1 of 26

    NEWPORT CITY COUNCIL LOCAL IMPACT REPORT PINS Reference Number DNS/3216558 – Wentlooge renewable energy hub

    Applicant Wentlooge Farmers’ Solar Scheme Limited

    Applicants’ Agent Savills

    LPA Reference Number 20/0407

    Application Type Development of National Significance

    Proposed Development Erection of a Renewable Energy Hub comprising ground

    mounted solar panels, battery storage units (160 units)

    with a combined installed generating capacity of up to

    125MW, underground cabling, grid connection hub,

    associated infrastructure, landscaping and

    environmental enhancements for a temporary period of

    40 years.

    Application Site Land North Of Greeacre Farm, Coast Road

    St Brides, Wentlooge, Newport

  • Page 2 of 26

    1.0 Preamble

    1.1 This Local Impact Report (LIR) has been prepared to meet the requirements of

    Section 62K of the 1990 Act, and Regulation 25 of the Developments of National

    Significance (Procedure) (Wales) Order 2016.

    1.2 Limitations: This LIR is reliant upon information available within the submitted

    documents and prior knowledge of the site. Limited internal consultation has been

    undertaken within the Council but no specialist or technical consultee outside of the

    Council has been consulted. Further limitations are placed by the prescribed

    timescales for response. This LIR takes note of the relevant procedural guidance

    contained at Appendix 5 of the Welsh Government’s ‘Guidance on Developments of

    National Significance’.

    1.3 We understand the LIR is a factual document that should not weigh evidence or

    make recommendations but should state whether impacts are anticipated to be

    positive, negative or neutral. As such this LIR will not qualify impacts beyond those

    words since to do so would be to apply weighting which is expressly excluded in the

    relevant advice.

    1.4 This LIR considers the solar hub and battery storage as a single development.

    2.0 RELEVANT SITE HISTORY

    Ref. no. Description Decision & date

    PN/18/0213 SCOPING OPINION FOR PROPOSED SOLAR FARM

    AND WIND TURBINE DEVELOPMENT (49.9MW)

    ACCOMPANIED BY BATTERY STORAGE UNITS,

    SUBSTATION BUILDINGS AND ASSOCIATED PLANT

    Scoped

    10/12/2019

    3.0 LOCAL PLANNING POLICY

    3.1 Adopted Local Development Plan 2011-2026

    Policy Wording

    SP1 – Sustainability Proposals will be required to make a positive contribution to

    sustainable development by concentrating development in

    sustainable locations on brownfield land within the settlement

    boundary. They will be assessed as to their potential contribution

    to:

    i) the efficient use of land;

    ii) the reuse of previously developed land and empty properties in

    preference to greenfield sites;

  • Page 3 of 26

    iii) transportation systems, as well as encouraging the co-location

    of housing and other uses, including employment, which together

    will minimise the overall providing integrated need to travel, reduce

    car usage and encourage a modal shift to more sustainable modes

    of transport;

    iv) reducing energy consumption, increasing energy efficiency and

    the use of low and zero carbon energy sources;

    v) the minimisation, re-use and recycling of waste;

    vi) minimising the risk of and from flood risk, sea level rise and the

    impact of climate change;

    vii) improving facilities, services and overall social and

    environmental equality of existing and future communities;

    viii) encouraging economic diversification and in particular

    improving the vitality and viability of the city centre and district

    centres;

    ix) conserving, enhancing and linking green infrastructure,

    protecting and enhancing the built and natural environment;

    x) conserving and ensuring the efficient use of resources such as

    water and minerals.

    SP3 – Flood Risk Newport’s coastal and riverside location necessitates that

    development be directed away from areas where flood risk is

    identified as a constraint and ensure that the risk of flooding is not

    increased elsewhere. Development will only be permitted in flood

    risk areas in accordance with national guidance. Where

    appropriate a detailed technical assessment will be required to

    ensure that the development is designed to cope with the threat

    and consequences of flooding over its lifetime. Sustainable

    solutions to manage flood risk should be prioritised.

    SP4 – Water

    Resources

    Development proposals should minimise water consumption,

    protect water quality during and after construction and result in no

    net increase in surface water run-off through the sustainable

    management of water resources by:

    i) the use of sustainable drainage systems;

    ii) the reuse of water and reduction of surface water run-off through

    high quality designed developments;

    iii) careful consideration of the impact upon finite water resources,

    particularly in terms of increased pressures on abstraction and the

    impact of climate change;

    iv) ensuring development is appropriately located and phased so

    that there is capacity in the waste water, sewerage and water

    supply as well as the protection of water quality.

  • Page 4 of 26

    SP5 – Countryside Development in the countryside (that is, that area of land lying

    beyond the settlement boundaries shown on the proposal and

    inset maps) will only be permitted where the use is appropriate in

    the countryside, respects the landscape character and biodiversity

    of the immediate and surrounding area and is appropriate in scale

    and design. Housing development, rural diversification and rural

    enterprise uses, beyond settlement boundaries, will only be

    appropriate where they comply with national planning policy.

    SP7 – Green Wedges Green Wedges have been identified in order to prevent

    coalescence between the following settlements:

    i) Newport and Cardiff;

    ii) Rogerstone and Risca;

    iii) Bettws, Malpas and Cwmbran;

    iv) Caerleon and Cwmbran.

    Within these areas development which prejudices the open nature

    of the land will not be permitted. An increase in size of a dwelling

    of more than 30% of the volume of the original size of the dwelling,

    or as existed in 1948, will not be approved.

    SP8 – Special

    Landscape Areas

    Special Landscape Areas are designated as follows within which

    proposals will be required to contribute positively to the area

    through high quality design, materials and management schemes

    that demonstrate a clear appreciation of the area’s special

    features:

    i) North of Bettws

    ii) West of Rhiwderin

    iii) Wentlooge Levels

    iv) River Usk

    v) Caldicot Levels

    vi) Wentwood

    SP9 – Conservation

    of the Natural, Historic

    and Built Environment

    The conservation, enhancement and management of recognised

    sites within the natural, historic and built environment will be

    sought in all proposals.

    GP1 – Climate

    Change

    Development proposals should:

    i) be designed to withstand the predicted changes in the local

    climate and to reduce the risk of flooding on site and elsewhere by

    demonstrating where appropriate that the risks and consequences

    of flooding can be acceptably managed, including avoiding the use

    of non-permeable hard surfaces;

  • Page 5 of 26

    ii) be designed to minimise energy requirements and incorporate

    appropriate renewable, low or zero carbon energy sources,

    including on site energy provision where practicable;

    iii) be designed to reuse or recycle existing construction materials

    present on the site;

    iv) meet the relevant breeam or code for sustainable homes level.

    GP2 – General

    Amenity

    Development will be permitted where, as applicable:

    i) there will not be a significant adverse effect on local amenity,

    including in terms of noise, disturbance, privacy, overbearing, light,

    odours and air quality;

    ii) the proposed use and form of development will not be

    detrimental to the visual amenities of nearby occupiers or the

    character or appearance of the surrounding area;

    iii) the proposal seeks to design out the opportunity for crime and

    anti-social behaviour;

    iv) the proposal promotes inclusive design both for the built

    development and access within and around the development;

    v) adequate amenity for future occupiers.

    GP3 – Service

    Infrastructure

    Development will be permitted where, as applicable:

    i) necessary and appropriate service infrastructure either exists or

    can be provided;

    ii) in areas served by the public foul sewer, there is capacity for the

    development within the system or, if not, satisfactory

    improvements are provided by the developer;

    In areas served by the public foul sewer, development will not be

    permitted with connections to private facilities unless there are

    exceptional circumstances that prevent connection to the public

    sewer.

    GP4 – Highways and

    Accessibility

    Development proposals should:

    i) provide appropriate access for pedestrians, cyclists and public

    transport in accordance with national guidance;

    ii) be accessible by a choice of means of transport;

    iii) be designed to avoid or reduce transport severance, noise and

    air pollution;

    iv) make adequate provision for car parking and cycle storage;

    v) provide suitable and safe access arrangements;

    vi) design and build new roads within private development in

    accordance with the highway authority’s design guide and relevant

    national guidance;

  • Page 6 of 26

    vii) ensure that development would not be detrimental to highway

    or pedestrian safety or result in traffic generation exceeding the

    capacity of the highway network.

    GP5 – Natural

    Environment

    Development will be permitted where, as applicable:

    i) the proposals are designed and managed to protect and

    encourage biodiversity and ecological connectivity, including

    through the incorporation of new features on or off site to further

    the uk, welsh and/or newport biodiversity action plans;

    ii) the proposals demonstrate how they avoid, or mitigate and

    compensate negative impacts to biodiversity, ensuring that there

    are no significant adverse effects on areas of nature conservation

    interest including international, european, national, welsh section

    4232 and local protected habitats and species, and protecting

    features of importance for ecology;

    iii) the proposal will not result in an unacceptable impact on water

    quality;

    iv) the proposal should not result in the loss or reduction in quality

    of high quality agricultural land (grades 1, 2 and 3a);

    v) there would be no unacceptable impact on landscape quality;

    vi) the proposal includes an appropriate landscape scheme, which

    enhances the site and the wider context including green

    infrastructure and biodiversity networks;

    vii) the proposal includes appropriate tree planting or retention

    where appropriate and does not result in the unacceptable loss of

    or harm to trees, woodland or hedgerows that have wildlife or

    amenity value.

    GP6 – Quality of

    Design

    Good quality design will be sought in all forms of development. The

    aim is to create a safe, accessible, attractive and convenient

    environment. In considering development proposals the following

    fundamental design principles should be addressed:

    i) context of the site: all development should be sensitive to the

    unique qualities of the site and respond positively to the character

    of the area;

    ii) access, permeability and layout: all development should

    maintain a high level of pedestrian access,

    Connectivity and laid out so as to minimise noise pollution;

    iii) preservation and enhancement: where possible development

    should reflect the character of the locality but avoid the

    inappropriate replication of neighbouring architectural styles. The

    designer is encouraged to display creativity and innovation in

    design;

  • Page 7 of 26

    iv) scale and form of development: new development should

    appropriately reflect the scale of adjacent townscape. Care should

    be taken to avoid over-scaled development;

    v) materials and detailing: high quality, durable and preferably

    renewable materials should be used to complement the site

    context. Detailing should be incorporated as an integral part of the

    design at an early stage;

    vi) sustainability: new development should be inherently robust,

    energy and water efficient, flood resilient and adaptable, thereby

    facilitating the flexible re-use of the building. Where existing

    buildings are present, imaginative and sensitive solutions should

    be sought to achieve the re-use of the buildings.

    GP7 – Environmental

    Protection and Public

    Health

    Development will not be permitted which would cause or result in

    unacceptable harm to health because of land contamination, dust,

    instability or subsidence, air, heat, noise or light pollution, flooding,

    water pollution, or any other identified risk to environment, local

    amenity or public health and safety.

    CE4 – Historic

    Landscapes, Parks,

    Gardens and

    Battlefields

    Sites included in the register of landscapes, parks and gardens of

    special historic interest and identified historic battlefields should be

    protected, conserved, enhanced and where appropriate, restored.

    Attention will also be given to their setting.

    CE6 – Archaeology Development proposals will normally be required to undertake an

    archaeological impact assessment before the proposal is

    determined:

    i) where groundworks and/or the installation of services are

    proposed within the archaeologically sensitive areas of caerleon,

    the levels, lower machen and the city centre , or;

    ii) within other areas of recognised archaeological interest.

    CE9 – Coastal Zone Development will not be permitted in the coastal area or adjoining

    the tidal river unless:

    i) in the undeveloped coastal area such development is required

    to be on the coast to meet an exceptional need which cannot

    reasonably be accommodated elsewhere;

    ii) the area is not itself at risk nor will the proposed development

    exacerbate risks from erosion, flooding or land instability

    Development which requires a coastal location should be sited

    within the developed coastal zone.

    CE10 – Renewable

    Energy

    Renewable energy schemes will be considered favourably, subject

    to there being no over-riding environmental and amenity

  • Page 8 of 26

    considerations. Small scale micro-generation will be encouraged

    within the settlement boundary. Large scale proposals may be

    more appropriately located outside of the defined settlement

    boundary if no appropriate brownfield sites exist. The cumulative

    impacts of renewable energy schemes will be an important

    consideration.

    T2 Heavy -

    Commercial Vehicle

    Movements

    Developments which generate heavy commercial vehicle

    movements will be favoured in those locations which allow access

    to a railway line, wharf or dock. Where it can be demonstrated that

    this is not appropriate, locations readily accessible to strategic and

    principal routes will be favoured. Elsewhere, such development will

    not be permitted.

    T3 – Road Hierarchy In order to facilitate the effective and safe use of the highway

    network a hierarchy of roads will be established. This road

    hierarchy will be used to determine the principle of access for new

    developments, it comprises the following:

    i) strategic routes – these consist of the M4 motorway, trunk roads

    and the A4051 from the M4 to the Woodlands roundabout, Malpas.

    These roads carry a substantial element of traffic to and around

    the city to major centres of population and commerce elsewhere.

    To facilitate the free movement of through traffic, strategic routes

    should have a limited number of junctions with parking limited to

    designated laybys or service areas. Only in exceptional

    circumstances and having regard to the strategic importance of a

    development will new direct access be permitted.

    ii) principal routes – these consist of all principal routes which link

    the major population and employment areas in the sub-region to

    each other and to the strategic routes. As a general principle, the

    provision for on-street parking, new frontage access and turning

    movements will be restricted in the interests of road safety and the

    efficient movement of traffic.

    iii) local roads – these provide for the main movements within

    urban and rural areas, as well as giving access to the strategic and

    principal road network. Where appropriate, and especially in order

    to facilitate public transport, parking and turning movements may

    be restricted and the number of frontage accesses limited in the

    interests of road safety and the efficient movement of traffic.

    iv) access routes – these provide access to residential areas,

    industrial areas, the city centre and small rural communities and

    businesses. If necessary, and for reasons of safety and amenity,

    traffic movements and speed will be restricted. Walking, cycling

  • Page 9 of 26

    and bus routes will be incorporated into layouts where appropriate.

    These roads will often give greater priority to pedestrians and

    cyclists.

    T4 – Parking Development will be required to provide appropriate levels of

    parking, within defined parking zones, in accordance with adopted

    parking standards.

    T7 – Public Rights of

    Way and New

    Development

    Any public footpath, bridleway or cycleway affected by

    development proposals will require retention or the provision of a

    suitable alternative. Provision of additional routes, where

    appropriate, will be sought in new developments, with linkages to

    the existing network.

    T8 – All Wales Coast

    Path

    Development proposals should protect and enhance the all wales

    coast path. The provision of additional routes to link to the coast

    path will be encouraged.

    3.2 Supplementary Planning Guidance

    • Wildlife and Development SPG (Aug 2015)

    • Archaeology and Archaeologically Sensitive Areas SPG (Aug 2015)

    • Trees, Woodland, Hedgerows and Development Sites SPG (Jan 2017)

    • Air Quality SPG (Feb 2018)

    • Parking Standards (August 2015)

    • Draft Sustainable Travel SPG (October 2019)

    4.0 ASSESSMENT OF LIKELY IMPACT OF THE PROPOSAL

    4.1 The applicant confirms the proposal is for a solar farm of 125 MW covering an area of

    155 hectares.

    The Location of the Development

    4.2 The site is part of a complex landscape of historic, archaeological, ecological and

    recreational value. It has significant designations as follows:

    • Sites of Special Scientific Interest (St Brides) – extensive areas of reclaimed wet, rich

    flora and fauna;

    • Adjacent to other statutory designations with significant bird interest, namely the River

    Severn Estuary (SSSI, SAC / SPA & Ramsar Site)

    • Archaeological Sensitive Area;

    • Landscape of Outstanding Historic Interest;

  • Page 10 of 26

    • Special Landscape Area;

    • Important Recreational Route (All Wales Coastal Path)

    • Countryside and Green Wedge

    • Undeveloped Coatal Zone

    • The site is within Flood Risk Zone C1;

    • The records show the site to be located within Agricultural Land Classification 4.

    4.3 The key Issues relating to the development as proposed are considered to be:

    • Landscape & Visual Impact (character & appearance);

    • Impact on Bio-diversity issues – Gwent Levels SSSIs and bird assemblages in the

    Marine SAC / Ramsar Site / SPA (River Severn);

    • Impact on Historic Landscape;

    • Impact on Archaeological Sensitive Area;

    • Flooding;

    • Undeveloped Coastal Zone;

    • Highways Issues;

    • Rural Character / Mitigation;

    • Noise; and

    • Glint and Glare

    4.4 Landscape and Visual Impact

    4.4.1 The key landscape documents submitted are:

    • Landscape and Visual Impact Assessment (within the Environmental Statement)

    • Landscape and Ecological Management Plan (LEMP) report and plan

    There are some gaps in the LVIA: not all elements of the proposal are assessed;

    local (within 100m) impacts are underplayed; and landscape mitigation is insufficient.

    The LEMP is focussed on ecological enhancement. No site-based landscape

    appraisal has been submitted and no detailed landscape mitigation plan.

    LVIA comments

    4.4.2 The operational phase is for a period of 40 years and across an area of 155ha within

    a number of local and national landscape, heritage and biodiversity designations,

    however there is no strategic capacity study for solar farm development within the

    Wentlooge Levels to be able to assess the proposal against.

  • Page 11 of 26

    4.4.3 The LVIA follows the industry standard and has a computer generated Zone of

    Theoretical Visibility which has been ground tested through the use of eight

    ‘representative’ viewpoints.

    4.4.4 All elements of the proposal should be incorporated into the LVIA. It is

    understandable given the scale of the solar arrays, but there are a number of gaps.

    The LVIA should also include a description and assessment of smaller elements

    which may have a more local landscape impact:

    • Proposed 16m high telecoms tower and CCTV poles; 2m high boundary fencing;

    battery storage unit; Grid Yard

    • The proposal to remove 1.5km of hedgerow along reens within the site (to meet

    ecological objectives) is not assessed; the existing vegetation within the site helps to

    visually break-up the expanse of the solar farm and is clearly shown in the

    photomontage for viewpoint 1

    • The LEMP includes 22.1ha of grassland for lapwing as compensatory habitat. No

    information on this is included other than removal of hedges, scrub, trees will be

    undertaken to create open habitat. This may be conditioned, but the impacts of

    vegetation removal on landscape character and visual amenity should be assessed

    within the LVIA.

    • There is no assessment of existing poor views. New boundary planting would not only

    soften views of the solar arrays, but could also have a positive benefit in softening

    existing poor views outside the site, for example views from the B4239 to highly

    reflective farming and industrial buildings.

    4.4.5 There is no cross referencing to other related documents:

    • The ASIDOHL identifies a severe impact for the landscape character area Maerdy

    HLCA21 which includes the majority of the site.

    • The Glint and Glare report identifies mitigation is required for five dwellings (ref 8.5)

    but this is not in either the LVIA or LEMP

    4.4.6 The LVIA plan reference L31 shows photomontages from all 8 of the selected

    viewpoints.

    • The greatest impact is evident at viewpoint 1. It is not clear whether this is intended to

    be ‘representative’ of views adjacent to the site and a ground- level viewpoint from

    Broadway or the B4239 may have been more representative as viewpoint 1 is elevated

    in the otherwise flat landscape.

    • There are no photos taken from within the site looking out to demonstrate the extent

    of views.

    • Viewpoint 1 photomontage shows the landscape character impact will be more than

    minor-negligible (10.6.54 and 10.6.55) and visual effects more than minor for all user

    groups including overlooking residents (10.6.102).

  • Page 12 of 26

    • The impact of a minor change from the Wales Coast Path may also be underplayed

    (10.6.39). Although the closest point to the site is 600m, photomontage 4 at 950m

    distance appears to show more than a minor change may be experienced. The detail

    on several photomontages is difficult to view. Showing the wireframe separately from

    the rendered image may help better understand the impacts.

    4.4.7 The operational phase landscape character and visual amenity impacts are generally

    underplayed for the site and immediate setting. Examples include:

    • 10.6.42 mentions the lack of boundary vegetation and the open views from Hawse

    Lane, B4239 and Broadway, but concludes a minor-negligible adverse landscape

    character impact.

    • 10.6.45 states the impact of the character change for local residents will be minor

    adverse.

    • 10.6.49 identifies the magnitude of change is identified as small within 1km.

    • 10.6.55 Landscape Effects during the 40 year operational phase are identified as

    minor adverse to negligible

    • 10.6.102 Visual Effects during the 40 year operational phase are identified as minor

    adverse (moderate adverse for walkers and cyclists)

    The photomontage from viewpoint 1 demonstrates there will be more than a minor

    impact on neighbouring residential properties and from drivers using all boundary

    roads, in particular Broadway and the B4239 which are frequently used.

    4.4.8 Paragraph 10.7.1 – recognises that to meet local authority polices, landscape

    enhancement measures are required, but none have been proposed.

    • 10.5.1 states the grid yard and battery storage to be screened with additional

    hedgerow

    • 10.6.13 states new hedgerow to strengthen existing boundaries

    • 10.6.100 identifies visual effects as Moderate Adverse within 100m but no mitigation

    is proposed

    • The mitigation section of the Environmental Statement (17.2) mentions the need for

    new planting under Cultural Heritage and Landscape and Visual.

    • Constraints on new planting have not been fully explored in the LVIA or shown on a

    site analysis plan. In contradiction to sections highlighting the need for new planting,

    other sections mention constraints to maintain the historic open character and to

    conserve rush pasture habitat. As the existing baseline information for the site and

    boundaries has not been fully assessed and there are no new planting proposals, it is

    difficult to judge whether a balance has been struck between the need for new planting

    and the constraints.

    4.4.9 There is a lack of detail for the following elements which are urban elements that will

    be introduced into a flat rural landscape:

    • 16m high telecoms tower

  • Page 13 of 26

    • battery storage unit, no dimensions or materials are confirmed, the colour is identified

    in the LVIA as ‘green’ and elsewhere in the ES [17.2 Landscape and Visual summary

    of mitigation measures] as green or brown. A colour assessment is recommended to

    ensure the hue selected blends in with the natural colour palette of the Wentlooge

    Levels.

    • 5m high CCTV pole – materials, colour, locations are not clear.

    4.4.10 There are insufficient landscape mitigation measures:

    • The LVIA should include a detailed assessment of local visual impacts and the

    potential for mitigation both within the site and at the site boundaries.

    LEMP comments

    4.4.11 The document contains no detail of landscape mitigation measures and landscape

    objectives are missing from section 4. The mitigation is entirely ecological: hedge

    removal to improve SSSI condition, bird and dormice boxes, habitat piles.

    4.4.12 The mitigation proposals from a landscape viewpoint do not meet the Local

    Development Plan policy GP5 General Development Principles – Natural Environment

    vi: ‘the proposal includes an appropriate landscape scheme………’.

    4.4.13 No management prescriptions for boundary reens are included. Both reed and hedge

    management regimes should be specified with the objective of maintaining the limited

    screen.

    4.4.14 A site based analysis and landscape plan response is required and a long term

    maintenance/management plan covering both new and existing hedge and reed

    planting.

    4.4.15 The Council considers that the Landscape & Visual impact of the proposal would be

    negative. The Council also considers the impact on the Wentlooge Levels Special

    Landscape Area to be negative. See SLA3: Wentlooge Levels; Special Landscape

    Areas Background Paper (June 2013) and the submitted LVIA.

    4.5 Ecological Impact

    4.5.1 Insufficient information has been provided for the Welsh Government to consider the

    ‘Three Tests’ under the Conservation of Habitats and Species Regulations 2017 and

    appropriately fulfil the wider duties under that same legislation and the Wildlife and

    Countryside Act 1981 and Environment (Wales) Act 2016.

    4.5.2 The surveys of the proposed development site have been comprehensive and

    followed the requirements detailed in the NRW scoping opinion. However there have

    been no surveys undertaken of the off-site lapwing mitigation area.

  • Page 14 of 26

    Off-site Lapwing Mitigation Area

    4.5.3 The Environmental Statement (ES) and Landscape and Ecological Management Plan

    (LEMP) refer to a 22 ha area off-site that will be enhanced and managed for wintering

    lapwing to compensate for on-site loss of habitat. Only a blue line boundary is

    provided of this off-site compensation area, with other details promised in a Lapwing

    Management Plan. No details of the current habitats or species present in the off-site

    mitigation area have been provided, but Section 5.1.3 of the LEMP states that

    grassland created for lapwing through the “removal of hedges, scrub and trees to

    create an open habitat”. This is likely to result in the loss of priority habitat, potentially

    including habitat supporting European protected species (dormice and bats).

    Furthermore, the site may potentially already support lapwing, and cannot be

    enhanced to provide space for the numbers displaced from the development site.

    4.5.4 The Council considers that the absence of sufficient information would result in a

    negative impact on the local overwintering lapwing population. As an interest feature

    of the Severn Estuary Special Area of Conservation (SAC) and Ramsar site, further

    information on mitigation for overwintering birds is needed to inform Habitat

    Regulations Assessment required by Regulation 63 of the Conservation of Habitats

    and Species Regulations 2017, in accordance with the EC Habitats Directive (Council

    Directive 92/43/EDC) before the ‘Competent Authority’ under the Regulations can

    grant permission for the project.

    4.5.5 The proposed “enhancements” of the mitigation area would result in the loss of habitat

    with potential to support European Protected Species. There is insufficient data to

    consider the whether the proposals will be detrimental to the maintenance of the

    population of European Protected Species at a favourable conservation status in their

    natural range. The assessment can therefore not fulfil the “three tests” requirements,

    under Regulation 55 of the Conservation of Habitats and Species Regulations 2017.

    Development Site

    4.5.6 The development site lies wholly within the Gwent Levels St Brides Site of Special

    Scientific Interest (SSSI). The surveys have confirmed that the development site is of

    national importance for wildlife as would be expected of a SSSI designated site.

    Almost all the site is classified as Coastal and Flood Plain Grazing Marsh priority

    habitat, which is defined by proximity to water, topography and management rather

    than the underlying substrate or the vegetation. The habitat is not often botanically

    diverse but is important for the range of bird and invertebrate species supported by

    seasonally inundated pastures. On site, the habitat comprises a range of grassland

    from marshy grassland to improved grassland, and the reen and ditch system which

    varies in condition. The ES would benefit from providing a quantitative analysis of how

    many of the reens and ditches of the Gwent Levels St Brides SSSI will be affected by

    the proposal, and the extent of ditches that will be brought back in to favourable

    condition by the mitigation.

  • Page 15 of 26

    4.5.7 Invertebrate surveys confirm that the site supports nationally important assemblages

    of species including nationally notable species such as the shrill carder-bee and

    brown-banded carder-bee. In addition to this, surveys have confirmed the presence

    of other protected and priority species such as dormouse and grass snake. Many bird

    species were recorded with 30 species confirmed or probable breeding and

    overwintering birds which are associated with the Severn Estuary, including 300+

    lapwing.

    4.5.8 A LEMP is provided which provides a summary of the existing ecological features,

    recommendations to be included in a CEMP to protect features during construction,

    and recommendations for future management. To avoid and mitigate impacts during

    construction a Construction Environmental Management Plan (CEMP) is

    recommended in the ES and LEMP, but has not been provided to date and therefore

    will need to be secured with a condition.

    4.5.9 The ES predicts that with mitigation the development will result in a neutral or positive

    impact on most of the wildlife supported by the site, as a result of reduced fertilizer

    input and more sensitive management practices. However, the LEMP is not robust

    enough to secure enforceable actions that will result in protection of species and

    enhancement of habitats, for the reasons summarised below:

    • Habitat creation/enhancement

    o How many ‘cattle watering features’ will be retained and created? How will they

    be maintained as open features? Locations should be shown on a map.

    o What species will be used to plant up gaps in hedgerows? Which hedgerows

    will be enhanced? Specification of planting stock should be provided.

    o The area of habitat created for shrill carder bee does not correspond between

    the ES (2.6 ha) and the LEMP (3.2 ha).

    o The LEMP states that one of the reen buffers will be managed for invertebrates

    to link with the fields around the fishing ponds; this is not shown on the plan.

    o It is unclear if the fields around the fishing ponds will be enhanced/managed for

    invertebrates; it should be highlighted on the map.

    o The detail of how species-rich grassland will be created is insufficient.

    o See comments above on the creation of the off-site Lapwing mitigation area.

    Habitat management

    o The detail on how reen casting will be carried out should be included.

    o The LEMP states that the “selected buffers” will be managed for shrill carder

    bee; the minimum length of buffer that will be managed each year and their

    location (on a rotational basis if required) should be provided.

    o No details on how the fishing ponds and the surrounding fields will be managed

    are included.

    o It is recommended that rotational management of hedgerows is reduced to 2-3

    years and the cutting time is restricted to winter months to retain the berry

    resource throughout the autumn.

  • Page 16 of 26

    o No details on the stocking density of the solar array fields has been provided

    o No fertiliser is specified on the fields managed for shrill carder bee, but this

    implies it can be used on fields housing the solar arrays.

    4.5.10 The LEMP refers to a forthcoming Monitoring and Contingency plan. BS 42020

    specifies that the LEMP should include details of monitoring and remedial areas.

    Without this detail, it is not possible to assess whether appropriate mitigation and

    contingency is feasible should there be negative impacts as a result of the

    development. Additionally, section 7.2.2 of the LEMP refers to actions relating to wind

    turbine blades with regards to bat fatalities, which are obviously not applicable here.

    4.5.11 The species assemblage of Coastal and Flood Plain Grazing Marsh is likely to change

    as a result of shading from the solar arrays. Whilst this does not affect the priority

    habitat designation, it is likely to have consequences for the invertebrate species

    supported by it. At present, due to the wording of the LEMP, it is only possible to

    enforce habitat management suitable for invertebrates on the area of created habitat

    on the west boundary of the site. Although managing “selected buffers” and the fields

    around the fishing ponds is referred to (Sections 6.2.3 and 6.3.3 respectively), the

    detail is insufficient to compare the area of post-development habitat available to

    invertebrates, and also to ensure that suitable management practices are followed in

    these areas. Given that 128 ha of Coastal and Flood Plain Grazing Marsh will be

    modified a significant increase in the area of habitat managed for invertebrates should

    be secured.

    4.5.12 Planning Policy Wales requires that “development should not cause significant loss of

    habitats or populations of species, locally or nationally and must provide a net benefit

    for biodiversity”. The information provided to date does not provide certainty that

    suitable management can be enforced to guarantee that the development does not

    result in a loss for biodiversity. Furthermore, management in compensation for habitat

    loss does not equate to an overall enhancement, and the opportunity to create new

    habitats by making the fishing pond suitable for wildlife should be considered.

    4.6 Historic Landscape

    4.6.1 The site lies entirely within the Gwent Levels Historic Landscape. The site partially

    covers two character areas within the wider Gwent Levels HLW: Western St Brides

    and Maerdy. An assessment using the Assessment of the Impact of Development on

    Historic Landscapes 2 methodology has been undertaken. Whilst comments from

    the Glamorgan Gwent Archaeological Trust and CADW will be critical the Council

    notes that the ASIDOHL 2 carried out by the Archaeology Collective concludes that

    the overall significance of impact on the Western St Brides HLCA is moderate and

    on the Maerdy HLCA is severe.

    4.6.2 The Council concludes that the impact would be negative.

  • Page 17 of 26

    4.7 Archaeological Impact

    4.7.1 The site lies within an Archaeological Sensitive Area. Impacts on the archaeological

    resource could be permanent and irreversible depending on the extent of ground

    intrusion. It is noted that the ES concludes that there is a moderate to major adverse

    significance of effect if archaeological remains are found; and there is a moderate to

    high potential for this to happen during the construction phase. It is also noted that

    the ES states that a programme of archaeological works can be conditioned,

    comprising an archaeological watching brief with contingencies. The Council notes

    that there is ongoing work with GGAT to agree the programme of works. Without agree

    mitigation there would be a negative impact.

    4.8 Flooding

    4.8.1 The site lies within a defended floodplain (C1) as identified in the Welsh Government’s

    Development Advice Maps. It will be necessary to show that the effects of tidal flooding

    can be acceptably managed on the site.

    4.8.2 Technical Advice Note 15 requires that location of the development within the flood

    plain is justified. The test at Paragraph 6.2 of the TAN reads as follows:

    i. Its location in zone C is necessary to assist, or be part of, a local authority

    regeneration initiative or a local authority strategy required to sustain an existing

    settlement; or,

    ii Its location in zone C is necessary to contribute to key employment objectives

    supported by the local authority, and other key partners, to sustain an existing

    settlement or region;

    and,

    iii It concurs with the aims of PPW and meets the definition of previously developed

    land (PPW fig 2.1); and,

    iv The potential consequences of a flooding event for the particular type of

    development have been considered, and in terms of the criteria contained in sections

    5 and 7 and appendix 1 found to be acceptable.

    4.8.3 The test requires that the scheme is necessary in the proposed location which

    suggests that no other site was suitable or available. Notwithstanding the negative

    ecological, landscape and historic impacts idenitifed above, which need to be weighed

    in the balance, the Council notes that the submission includes a Site Selection

    Sequential Test, which concludes that there are no suitable, viable or available

    alternative sites in the search area that are capable of accommodating the proposed

    development.

  • Page 18 of 26

    4.8.4 The site is not Previously Developed Land for the purposes of PPW and on its face

    the proposal cannot be justified in the chosen location.

    4.8.5 The Council notes that the applicant has submitted a Flood Consequences

    Assessment and we defer to Natural Resources Wales for their advice on that

    matter. Notwithstanding this, if the proposal is unjustified development within a flood

    plain then the impact would be negative. If the development can be justified and the

    submitted flood Consequences Assessment shows a flood event is manageable,

    consideration should be given to the impact of power loss from the grid. Subject to

    justification the impact of the scheme in flooding terms is likely to be negative due to

    the replacement of a less vulnerable use with a more vulnerable use.

    4.9 Coast

    4.9.1 The site is located within the undeveloped coastal zone and this designation requires

    that only development which is required to be on the coast to meet an exceptional

    need which cannot be met elsewhere. If the site is in a flood risk area, this must not

    exacerbate erosion, land instability or flood risk. An exceptional need should be

    demonstrated to satisfy NLDP policy CE9 (Coastal Zone).

    4.9.2 The Welsh National Marine Plan will need to be satisfied. It is noted that this plan is

    not mentioned in the planning statement. It is considered that it should be considered

    if only to screen it out.

    4.10 Access and Highways

    4.10.1 The development would have its biggest impact during the construction and de-

    commissioning phases. The impacts are considered to be negative without mitigation

    under conditions.

    4.10.2 The chosen route set out for all construction traffic, except abnormal loads, is from the

    A48, onto the A4232 to Lamby Way, Wentloog Avenue (B4239) then finally onto

    Broadway. The construction traffic will need to be controlled so as to avoid any peak

    hour flows. The maximum number of HGV movement is typically 23 per day, this will

    be on weeks 8 and 9 only of the 12-week construction phase.

    4.10.3 For the occasional abnormal load, the route will be from junction 28 of the M4, along

    the A48 to Castleton, turning onto Marshfield Road. Using this route reduces the time

    an abnormal load is on the highway network. An abnormal load travelling through the

    Castleton area should do so when the school (Marshfield Primary) is closed. It is noted

    that there is not expected to be many, if any abnormal load movements.

    Existing Highways

    4.10.4 A road condition survey will need to be carried out jointly by the applicant and the

  • Page 19 of 26

    Council. This will identify any locations where the highway may be substandard, so it

    can be monitored and/or repaired as necessary. This can be set out within a

    planning condition.

    Access onto the Development Site

    4.10.5 Within the construction phase the main access will be off Broadway. Drawing 194740-

    A0-01 sets out tracking diagrams for a maximum legal length HGV. The tracking

    shows that the vehicle uses all the available road and access space. There is no

    leeway for error and this could lead to verge damage. This access point may be subject

    to improvement works, with part of this works carried out within the highway. Long

    term, other entry points are expected to be required for maintenance purposes.

    Parking

    4.10.6 Sufficient parking space should be allowed for onsite with strict instruction that no on-

    road parking will be allowed. This should form part of a Construction Transport

    Management Plan (CTMP) detail. A CTMP should be a requirement set out in a

    planning condition.

    4.10.7 All highway entry points must meet the required construction and visibility standards.

    These details can be controlled through a condition.

    Transport Assessment

    4.10.8 The traffic count information for Marshfield Road contained within the Environmental

    Statement is considered to be dated (table 8.3). This should be updated to reflect a

    year within 5 years of the date of the submission.

    4.10.9 Table 8.1 sets out two traffic surveys however, the ATC location plan sets out three

    ATC count locations. The anomaly should be addressed.

    4.11 Rural Character / Mitigation

    4.11.1 Consideration should be given to any proposed mitigation to protect the rural character

    of the area. Proposed planting and use of materials in trackways should be

    considered. The scale and location of any structures to house switch gear etc. should

    be assessed and sited sensitively. Proposed lighting and signage should be fully

    cognisant of the site’s rural location as should any work to improve access, for example

    opening of field gates or the improvement of visibility splays.

    4.11.2 Mitigation secured under condition is likely to reduce adverse impacts but there will be

    a significant and prolonged change in the character of the area should the proposal

    go ahead. This will be negative in landscape and visual terms. However large solar

    facilities are not atypical in rural areas and there is no presumption against them.

    4.12 Noise

  • Page 20 of 26

    4.12.1 There are residential properties adjacent to and opposite the development site. Upon

    review of the submitted noise assessment, it is noted that there are many unknowns;

    site layout isn’t known, plant type isn’t known, location of plant isn’t known, quantities

    of plant aren’t known and therefore a lot of assumptions are made.

    4.12.2 Tonality Factor - the report states that tonality isn’t possible to determine from the

    manufacturers data and it is not expected to be tonal however, if the plant isn’t

    selected yet we can’t be sure there is no tonal element. Once the plant has been

    selected, the manufacturers data sheets could be obtainable (and therefore the 1/3rd

    octave data).

    4.12.3 Intermittency factor - the noise report also assumes the plant will run continuously,

    however it is possible that the fans would cut in and out for cooling. Again, this is

    unknown at this stage.

    4.12.4 All of the above could vastly change the outcome of the assessment as no correction

    factors have been applied. The impact on residential properties could be negative

    without mitigation, which should be controlled by condition.

    4.13 Glint and Glare

    4.13.1 The technical assessment of glint and glare concludes that potentially glint and glare

    could occur at 5 dwellings. However, through the subsequent detailed assessment it

    was determined that the nature of these effects would be reduced due to a range of

    mitigating factors. Consequently, it was considered that only a low significance of

    effect would occur in respect of all identified receptors. The impact of glint and glare

    is considered to be neutral.

    4.12 Power Generation

    4.12.1 The scheme would generate 49.9MW of electrical power sufficient to power 15,000

    homes and prevent the release of 21,000 tonnes of CO2 per year. This would be

    positive.

    5.0 Publicity

    5.1 This is attached to this LIR (see Appendix A).

  • Page 21 of 26

    SUGGESTED CONDITIONS

    PLANS: This proposal shall be carried out in accordance with the following plans:

    Drawing 4929574/01/E Site Location Plan

    Drawing 4929574/02/F Site Layout Plan

    Drawing 4929574/04/D Field Numbering Plan

    Drawing 1045592/07 Typical Details – Sheet 1

    Drawing 1045592/08 Typical Details – Sheet 2

    Reason: to comply with Paragraph 4.16 of Welsh Government Circular 016/2014

    (Conditions).

    LIFETIME OF THE PROPOSAL: The permission hereby granted shall expire 40 years from

    the date when electrical power is first exported (‘first export date’) from the solar farm to the

    electricity grid network, excluding electricity exported during initial testing and commissioning.

    Written confirmation of the first export date shall be provided to the Local Planning Authority

    no later than one calendar month after the event.

    Reason: the proposed scheme has a 40 year lifespan.

    CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN: No development shall

    commence until a construction environment management plan has been submitted to and

    approved in writing by the Local Planning Authority. The construction environmental

    management plan shall set out details of all on-site construction works; post-construction

    reinstatement; drainage; mitigation; and other restoration, together with details of their

    timetabling. It shall include details of, and measures to secure:

    (a) the phasing of construction works;

    (b) the formation and position of the temporary construction compounds;

    (c) contractor and operational on-site vehicle parking;

    (d) dust management and suppression;

    (e) cleaning of site entrance, facilities for wheel washing and cleaning the adjacent public

    highway;

    (f) pollution control, including the protection of water courses and ground water; subsoil

    surface water drainage; bunding and siting of fuel storage areas; sewage and foul water

    drainage and disposal; and emergency procedures and pollution response plans;

    (g) temporary site illumination during the construction period;

    (h) the methods to be adopted to reduce the effects of noise occurring during the construction

    period to the lowest practicable levels and in accordance with BS 5228: Noise control on

    construction and open sites;

    (i) storage of materials and disposal of surplus materials;

    (j) the construction of the accesses into the site, the erection of any entrance gates and the

    creation and maintenance of associated visibility splays;

    (k) access tracks and other areas of hardstanding, including areas of temporary road matting;

    (l) the carrying out of foundation works, including the foundation of the solar arrays and any

    other structures to be installed on the site;

  • Page 22 of 26

    (m) method of working cable trenches, including soil storage and back-filling; and details of

    cable boring methodologies below reens / ditches / other water courses and below hedges;

    (n) general soil storage and handling;

    (o) post-construction restoration/reinstatement of the working areas, including cable trenches

    and area covered by any matting or other areas where the soil has been disturbed or

    compressed;

    (p) the sheeting of all heavy goods vehicles construction materials to, or spoil from, the site

    to prevent spillage or deposit of any materials on the highway;

    (q) details of the vehicles to be used on the site during construction activities

    (r) details of control of surface water to prevent it entering the public highway or carrying

    sediment to the surface water drainage network in the vicinity of the site.

    (s) identification of buffer strips adjacent to water courses or retained vegetation features

    such as hedges or trees and sites where birds are nesting;

    (t) means to exclude small animals from excavations.

    The works shall proceed in full accordance with the agreed construction method statement.

    Reason: to protect the interests of the rural character of the area, the integrity and safety of

    the highway network and to protect the amenity of residents, ecological interests and to

    ensure the site is appropriately restored.

    ANALYSIS OF LANDSCAPE ENHANCEMENT: Notwithstanding the information submittied

    no development shall commence until a site based analysis and landscape plan has been

    submitted to and approved in writing by the Local Planning Authority. The analysis shall

    consider the balance of providing appropriate landscape enhancement and maintaining the

    historic open character. In accordance with the outcome of that analysis the landscape plan

    shall detail a scheme of landscape enhancement. Any new planting shall be implemented by

    the end of the first full planning season (October to March inclusive) available after the first

    export date.

    Reason: to protect the historic and special landscape character of the area.

    LANDSCAPE MANAGEMENT AND MAINTENANCE: Notwithstanding the information

    submitted no development shall commence until a long term maintenance/management plan,

    which covers both new and existing hedge and reed planting, shall be submitted to an

    approved in writing by the Local Planning Authority. All landscape features shall be

    maintained and managed in accordance with the approved plan.

    Reason: to protect the special landscape character of the area.

    HEDGEROW REMOVAL: Notwithstanding the information submitted full details of any

    hedgerow, scrub and tree removal shall be submitted to and approved in writing by the Local

    Planning Authority. The details shall include:

    • Precise location of hedges to be removed

    • Removal methodology

    • Timing of Removal

    • Mechanism to prevent disturbance to nesting birds and other fauna

  • Page 23 of 26

    No hedge, scrub or trees shall be removed until the details are agreed in writing. No hedge,

    scrub or tree shall be removed that has not been identified for removal.

    Reason: to provide ecological enhancement, to protect landscape features and to protect the

    interests of fauna and the relevant SSSIs.

    DETAILS OF ANCILLARY PLANT AND EQUIPMENT: Prior to their installation details of

    materials, colour and position of the battery storage unit, 16m high telecoms tower and 5m

    high CCTV poles shall be submitted to and approved in writing by the Local Planning

    Authority. The storage unit and equipment shall be finished in accordance with the approved

    details.

    Reason: to reduce their visual impact and to protect the special landscape character of the

    area.

    LIGHTING: There shall be no permanent illumination on the site unless otherwise agreed in

    writing by the local planning authority.

    Reason: to protect the rural character of the site.

    HABITAT CREATION/ENHANCEMENT: Notwithstanding the information submitted no

    development shall commence until the Landscape and Ecological Management Plan (LEMP)

    is updated and submitted to and approved in writing by the Local Planning Authority. The

    LEMP shall include the following details:

    • The number of ‘cattle watering features’ to be retained and created. How they be

    maintained as open features and their locations shown on a map.

    • The species to be used to plant up gaps in hedgerows and a specification of planting

    stock.

    • Confirmation of the area of habitat to be created for shrill carder bee.

    • A plan showing the position of the reen buffer to be managed for invertebrates to link

    with the fields around the fishing ponds.

    • A plan highlighting the field around the fishing ponds to be enhanced/managed for

    invertebrates.

    • How species-rich grassland will be created.

    • How reen casting will be carried out.

    • The minimum length of buffer that will be managed for Shrill carder bee and their

    locations.

    • Management of fishing ponds and the surrounding fields.

    • Stocking density of the solar array fields

    • The use, if any, of fertiliser to be used on fields housing the solar arrays.

    Reens, ditches and associated buffers, fields containing solar panels and Shrill Carder Bee

    mitigation and enhancement area shall be managed and monitored in accordance with the

    updated LEMP. Invertebrate surveys; and Water Vole and Otter mitigation strategies shall

    also be carried out in accordance with the updated LEMP.

    Reason: to ensure ecological mitigation and enhancement is achieved.

  • Page 24 of 26

    LAPWING MANAGEMENT PLAN: No development shall commence until a Lapwing

    Management Plan for the off-site compensation area (as shown in 0475/LEMP Fig 1

    Landscape and Ecological Management Plan) has been submitted to and approved in writing

    by the Local Planning Authority. The Lapwing compensation area shall be provided and

    managed in accordance with the approved plan.

    Reason: to ensure ecological mitigation and enhancement is achieved.

    MONITORING AND CONTINGENCY PLAN: No development shall commence until

    monitoring and contingency plans for bats and Water Vole have been submitted to and

    approved in writing by the Local Planning Authority. The development shall be carried out in

    accordance with the approved plans.

    Reason: to ensure ecological mitigation is achieved.

    TREES: No trees shall be removed other than identified in the Arboricultural Impact

    Assessment (Savills, March 2020). No tree shall be removed until it has been confirmed it

    does not contain nesting birds or a bat roost.

    Reason: to protect the ecological interests, protected species and the landscape character

    of the area.

    ARCHAEOLOGY: No development, to include demolition, shall take place until the

    implementation of a programme of archaeological work has been secured in accordance with

    a written scheme of investigation which has been submitted by the applicant and approved

    in writing by the Local Planning Authority.

    Reason: To identify and record and features of archaeological interest discovered during the

    works, in order to mitigate the impact of the works on the archaeological resource within an

    Archaeologically Sensitive Area.

    FOUNDATION DETAILS & LEVELS: Prior to the installation of the battery storage units

    details of the platforms they will be sited on and the slab level of those platforms shall be

    provided in writing to the Council. Following the Council’s written agreement the platforms

    will be built as agreed.

    Reason: to protect visual amenity and to limit ground intrusion in the interests of archaeology.

    ROAD CONDITION SURVEY: No development shall commence until a road condition survey

    has been submitted to and approved in writing by the Local Planning Authority. The survey

    shall identify any locations where the highway may be substandard; and jointly with the

    Council’s City Services set out a timetable for monitoring and/or repairs. The monitoring

    and/or repairs shall be carried out in accordance with the approved timetable.

    Reason: To protect the integrity and safety of the highway network.

    DETAILS OF ACCESS: No development shall commence until details of the main access off

    Broadway have been submitted to and approved in writing by the Local Planning Authority.

    The details shall include track testing and improvement works to ensure HGV’s do not cause

  • Page 25 of 26

    damage to the highway verge. The access shall be provided in accordance with the approved

    details.

    Reason: To protect the integrity and safety of the highway network.

    DETAILS OF TRACKWAY CONSTRUCTION: No tracks shall be constructed on the site until

    details of their construction have been provided in writing to the Local Planning Authority.

    Following the Local Planning Authority’s written agreement any tracks shall be constructed

    fully in accordance with the agreed details.

    Reason: to ensure any tracks are constructed in a fully reversible way in the long-term

    interests of appropriately restoring the site to reduce the risk of increased rates of run-off.

    TRAFFIC MANAGEMENT PLAN: No HGV shall access the site until details of a traffic

    management plan (TMP) has been submitted to and approved in writing by the Local

    Planning Authority. The TMP shall include details of:

    • Signage;

    • Details of temporary traffic management measures, such as traffic lights;

    • HGV routes and timings to avoid peak hour flows; and school drop off/pick up times.

    Reason: to protect the integrity and safety of the highway network.

    NOISE ASSESSMENT: Notwithstanding the information submitted no development shall

    commence until an updated noise assessment has been submitted to and approved in writing

    by the Local Planning Authority. The assessment shall . The assessment (which should be

    carried out in accordance with BS4142 :2014) should include full details of all plant and

    equipment, manufacturers data upon which they rely, full details of calculations, corrections

    and predictions and details of any enclosures. Any mitigation shall be identified, agreed and

    implemented prior to the operation of the plant.

    Reason: to protect residential amenity.

    CONTAMINATION: Any unforeseen ground contamination encountered during development,

    to include demolition, shall be notified to the Local Planning Authority as soon as is

    practicable. Unless otherwise agreed in writing by the Local Planning Authority as

    unnecessary, an appropriate ground investigation and/or remediation strategy shall be

    submitted to and approved in writing by the Local Planning Authority, and the approved

    strategy shall be implemented in full prior to further works on site. Following remediation and

    prior to the occupation of any building, a Completion/Verification Report, confirming the

    remediation has being carried out in accordance with the approved details, shall be submitted

    to and approved in writing by the Local Planning Authority.

    Reason: To ensure that any potential risks to human health or the wider environment which

    may arise as a result of potential land contamination are satisfactorily addressed.

    DECOMMISSIONING: Decommissioning and restoration: Not later than 12 months before

    the expiry of this permission, a decommissioning and site restoration scheme shall be

    submitted for the written approval of the Local Planning Authority. The scheme shall make

    provision for the removal of the solar panels and all other associated equipment &

  • Page 26 of 26

    paraphernalia and the subsequent restoration of the site. The scheme shall include details

    of:

    • the extent of equipment and foundation removal and the site restoration to be carried

    out;

    • the management and timing of any works;

    • a traffic management plan to address likely traffic impact issues during the

    decommissioning period;

    • an environmental management plan to include details of measures to be taken during

    the decommissioning period to protect wildlife, habitats and tree features on the site;

    • identification of access routes;

    • location of material laydown areas;

    • full details of the removal of the solar arrays, associated buildings and plant, any

    trackways and sub-surface cabling and all associated works of ground restoration

    including trench backfilling;

    • full details of all works to restore the land to allow for agricultural production following

    the removal of structures from the site;

    • a programme of implementation.

    The approved scheme shall be implemented within 6 months of the expiry of this permission

    and then proceed fully in accordance with the agreed details in accordance with the

    decommissioning programme.

    Reason: to ensure the site is fully restored and to maintain the rural appearance of the area.

    REPAIR, REPLACEMENT AND REMOVAL OF SOLAR FARM: If the solar farm hereby

    permitted fails to produce electricity for supply to the grid for a continuous period of 6 months,

    a scheme shall be submitted to the Local Planning Authority for its written approval within 3

    months of the end of that 6 month period for the repair or removal of the solar farm. Where

    repairs or replacements are required the scheme shall include a proposed programme of

    remedial works. Where removal of the solar farm is required the scheme shall include the

    same details required under the decommissioning condition of this permission. The relevant

    scheme shall thereafter be implemented in accordance with the approved details and

    timetable.

    Reason: to ensure the solar farm beneficially generates electricity or is otherwise removed to

    the benefit of the character and appearance of the area.