Snowy 2.0 update The new generators on the block Snowy under the stars

The future is bright

NEWSAUTUMN 2021ISSUE 52

Page 2: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

INSIDE3 CEO’smessage4 Snowy2.0update6 TBMnamingcompetition7 DieselgeneratorsatTumut38 Newtraineeslearningthebusiness9 Tunnelling1.010 Astrophotography12 RedEnergyturnspink13 Supportingourcommunity14 Education

2

For more information, please visit our website snowyhydro.com.au and sign-up to our e-newsletter.

1800 623 776 [email protected]

We welcome your feedback:

Follow us

@snowyhydroltd

@snowyhydroofficial

Page 3: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

things,forhostinghundredsofAustraliansandoverseasvisitorsthroughouttheyearsofconstruction.

YoumaynotknowthereisatraditionforallTBMstohavefemalenames,andwe’relaunchingacompetitionacrossSnowyMountainsschoolstogivelocalkidsachancetonameourtwootherSnowy2.0TBMs,inspiredbyground-breakingAustralianwomeninSTEM.

AcrosstheSnowyScheme,theSnowyHydroteamisbusynotonlykeepingthelightsonforelectricityconsumers,butcarryingoutarangeofprojectsandactivitiestomaintainandimproveourassets.

OneongoingprojectattheTumut3(T3)andBloweringpowerstationsinvolvesreplacingdieselstandbygenerators,whichkickintogearifthestationneedsback-uppowerwhenthemainsupplyislost.Thevalueofthesegeneratorscan’tbeunderestimated-formonthstheT3intakehasbeenoperatingontheseback-upsuppliesbeforeanewpowerlineiscommissioned.

SnowyHydrocontinuestosupportthecommunitythrougheventssponsorship-suchasthesuccessfulTumutCycleClassicwhichdirectlybenefitsthelocalhospital-andemploymentandtrainingopportunitiesfortheregion’syoungpeople.

InJanuarywewelcomedonboard12newbusinessadministrationtraineesandit’sbeenfantastictoseetheenthusiasmandtalenttheyhavebroughttothebusiness.

Paul BroadManagingDirectorandCEO

Ihavealwaysbelieveddreamingbighasitsrewards!Andatthemomentthereisnothingbiggerthanthehugetunnelboringmachine(TBM)thatwillexcavatethefirstmountaintunnelforourSnowy2.0project.

Itseemslikeonlyyesterdaywewereplanningthisnation-building,cleanenergypumped-hydroexpansionoftheSnowyScheme.Nowwearewitnessingrealaction,includinga2,000-tonne,11-metrediametermachinethatwilldigoutthemainaccesstunnelatLobsHoleandlineitwithconcretesegmentsmadeatthenewfactoryinPoloFlat,Cooma.

Moreoverhundredsofnewjobshavebeencreatedandlocalbusinessesarebooming.

Thisisjustoneofmanyexcitingmilestonesacrosstheproject.

LastmonthinCoomaweturnedthefirstsodontheconstructionofthe126-bedworkeraccommodationknownasJouleRidge.IwaspleasedtojoinrepresentativesfromourSnowy2.0principalcontractorFutureGenerationJointVenture,SnowyHydrodirectorsandtheSnowyMonaroRegionalCouncilMayorPeterBeertomarkanimportantdevelopmentthatwilleaselocalhousingdemand.

Itwasanothergreatdaywhenthe400-tonnecutterheadwasliftedontotheTBM(verycarefully!)inamajoroperationthatrequireda750-tonnecraneandmanyhoursofpre-planning.

We’veproudlynamedthisTBMtheLadyEileenHudson,apioneeringwomanineveryrespect,andwhowasawardedanOBEinrecognitionofhercommitmentasanambassadorfortheSnowyScheme.LadyEileen,whosehusbandwasthefirstSnowySchemeComissioner.SirWilliamHudson,wasknown,amongmany

3

CEO UPDATEA message from Managing Director and CEO Paul Broad

Page 4: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

PROJECT UPDATE

SNOWY 2.0

4

Tantangara and Marica

ProgressontheSnowy2.0projectcontinuestopickupspeed,withthenumberofworkersrampingupacrossmultiplesites.AtTantangara(picturedabove),theupperreservoirontheeasternsideoftheproject,workhasbegunonexcavationoftheaditfortheheadracetunnel.

ThissitewillsoonstarttolooksimilartothemainaccesstunnelatLobsHole,withaportalbigenoughtoenablesafeaccessforthethirdofthreetunnelboringmachines(TBMs)tobegintunnelling.ConstructionofaccessroadscontinueshereandoveratMarica,locatedabovewheretheundergroundpowerstationwillbebuilt.WorkhasalsostartedontheMaricacamp,inreadinessforworkerswhowillbebasedinthisarealaterintheproject.

Lobs Hole

WehaveseenthefinalassemblyofthefirstTBMtobeginthetunnellingrequiredtoprovidethefirstaccesstotheundergroundpowerstation.ThisTBMhasbeennamedLadyEileenHudsonafterthewifeofSirWilliamHudson,theSnowyScheme’sfirstcommissioner.

Itwasanexcitingmomentwhenthe400-tonnecutterheadwasliftedintoplace-thisoperationwasverycarefullyplannedandexecutedusingthe750-tonnecranebasedatthemainaccesstunnelportal.Priortothis,thefront,middleandtailshieldswereassembled,alongwithgantries1,2and3andtheconnectionbridgeintotheTBMcradle.

Gantry1containstheoperatorcabinandthegroutingsystem,gantry2hasthetransformersandthesegmentunloader,andgantry3hasthehydraulicpowerpacksandaircompressors.Allup,thisTBMisequippedwithsevengantriesandoneconnectionbridgetoholdtheauxiliarysupplysystems.

Thespoilconveyorhasbeeninstalledfromthefrontofthemachinetotheendofgantry3andwillcarrydebrisfromthecutterheadtoapileoutsidethetunnel,wheretruckswilltransportittodesignatedspoillocations.Alsoonboardaretwoprobedrillswhichwillcollectcoresamplesoftherock,andifrequired,groutaheadofthetunnellingtoaddstrengthandstabilitytothesurroundingrockpriortoexcavation.

ECVT

Theportalfortheemergency,cableandventilationtunnel(ECVT)isstartingtotakeshape.Excavationhasbeenprimarilythroughblasting,withmorethan40,000kilogramsofexplosivesusedandapproximately100loadsofmaterialfromthesitemovedperdayforuseonothersitesaroundLobsHole.

Page 5: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

TheLadyEileenHudsontunnelboringmachine,whichat137metresislongerthanastandardfootballfield,willborethemainaccesstunnelinpreparationforexcavationofthecavernthatwillhousethepowerstation.Theentire2,300-tonnemachinewillthenbedisassembledandrebuiltattheTalbingoadittoexcavatethetailracetunnel.Picturedleftisthetailskinbeinginstalled.

5

Exploratory Camp

ItwasabusyfewmonthsoversummerfinalisingconstructionoftheExploratoryCampatLobsHole.Thecampnowhasaround330workerslivingthere,withgeneratorsupandrunningtopowerthekitchen,dinerandlaundry.Thegym,accommodationandwetmessbuildingareinthelaststagesofcommissioning.

NewworkfrontsopeningupacrosstheSnowy2.0projectmeanmorejobsfortheregion.Snowy2.0principalcontractorFutureGenerationJointVentureislookingtofillhundredsofrolesacrossplantandequipment,construction,administrationandmore.WithtunnellingactivitiesrampingupatLobsHole,dozensofTBMmechanicalrolesmustbefilledinthecomingmonths.WorkersarealsowantedtobuildtheaccommodationcampsatMaricaandTantangara,andatthesegmentfactoryatPoloFlat.

ProjectsafetyremainsournumberonepriorityandFutureGenerationJointVentureisrecruitinghealth,safetyandenvironmentofficers,advisorsandmanagerswhowillbedeployedacrossprojectsites.

Therearenowmorethan1,000peopleworkingontheSnowy2.0project,withhundredsofjobsgoingtolocalapplicants.

Formoreinformationonvacantroles,ortoapply:futuregenerationjv.com.au/job-opportunities-1

EMPLOYMENT OPPORTUNITIES

Page 6: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

6

WHO WANTS TO NAME A TBM?

The27kilometresoftunnelslinkingTantangaraandTalbingodamswiththenewSnowy2.0underground

powerstationwillbeexcavatedusingthreetunnelboringmachines,orTBMs.

ThemammothmachineshavebeenshippedinpiecesfromGermanyandChinaandtransportedtotheSnowyMountainsbyroad.Onceassembledandreadytolaunch,thereisatraditiontonameeachmachine,whichissaidtobestowgoodluckontheprojectbeforetunnellingcommences.

Likeshipsandhurricanes,TBMsarenamedafterwomen-acustomthatdatesbacktothe1500sandStBarbara,thepatronsaintofminers,engineersandtunnels.

OneoftheSnowy2.0TBMshasbeennamedtheLadyEileenHudson.LadyEileen’shusband,SirWilliamHudson,wasconsideredthe‘father’oftheSnowyScheme.LadyEileenplayedanimportantroleasambassadorfortheSchemeandshealsocuttheribbonattheofficialopeningoftheGuthegaTunnel.Almostsevendecadeson,theTBMnamedinherhonourisstartingthetunnellingforSnowy2.0atLobsHole.

TheremainingtwoTBMswillbenamedafterAustralianwomenleadinginthefieldsofscience,technology,engineeringandmathematics(STEM),withthehelpofschoolsfromaroundtheSnowyMountainsregion.Studentsfromyears5to12willcomeupwithaselectionofnamesforconsiderationwiththenamesshortlistedbySnowyHydroandFutureGenerationJointVenture,beforegoingtoapubliconlinevote.

KeepaneyeonSnowyHydro’swebsiteandsocialmediaaccountsfordetailsonhowtovote.WordonthestreetisthatDrillyMcDrillface-definitelynotanAustralianwomanofSTEM-willnotmaketheshortlist!

TBM NAMING COMPETITION

Page 7: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

7

THE NEW GENERATORS ON THE BLOCK

Afteralmost50yearsofoperation,theoriginalstandbygeneratorsatTumut3PowerStation

andintakestructurehavereachedtheir‘endoflife’,andhavebeenreplacedwiththelatesttechnologytoensurethestation’songoingreliability.

Asapeakenergyprovider,SnowyHydromustbereadytogeneratepowerintotheelectricitygridatanygiventime.Thismeansourpowerstationsneedtobeavailabletoproduceclean,renewableenergy24/7,365-days-a-year.

TosupportourmarketpositionandensurethestabilityofelectricitysupplytotheNational

ElectricityMarket,ourassetshaveback-uppowersystems.

Duringthe2020bushfires,theincomingpowersuppliestoJounamaSmallHydroPowerStationandtheTumut3intakestructurewerecutoffwhenthetransmissionlinesburntdown.Theback-updieselgeneratorswerekeytoJounamaandTumut3powerstationsbeingabletocontinuetooperateuntilregularpowersupplieswererestored.

ReplacingtheoriginaldieselgeneratorshasbeenanimportantprojectforSnowyHydro.

ThegeneratorsatTumut3-installedduringconstructionofthepowerstationin1973-wereunabletobesupportedbythe

originalsuppliersandsparepartswerenolongeravailable.

Wetakeprideinmaintainingourassetstokeepthemintopcondition,andakeypartofourstrategyistomoderniseequipmentwhenmaintenanceisnolongereconomicallyfeasible.

Thesafetyofourstaff,contractors,visitorsandthecommunityisournumberonepriority,andwepartnerwithlocalorganisationswhichsharethesevalues.Forthisjob,theSnowyteamhasappreciatedthegreatworkfromlocalelectricalcontractor,PHETumut.

BloweringPowerStation’sstandbygeneratorwillalsobereplacedinthecomingmonths.

REGIONAL WORKS

PHE’sAdamBoyd,left,withSnowyHydroSiteSupervisorJohnCafferyandLowerTumutManagerPlantEngineeringJohnDoidge

Page 8: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

88

New recruits

SNOWY TRAINEES

Forlocalschool-leaversfeelingdauntedbytheall-importantnextstepsontheircareerpath,joiningSnowyHydro’s

traineeprogramcanprovideavaluableentrytotheworldofwork.

Launched30yearsago,theprogramhasintroducedhundredsofyoungpeoplefromlocalcommunitiestoarangeofemploymentexperiences,fromtheapplicationandinterviewprocess,throughtoacceptingafull-timeposition.SuccessfulcandidatesareembeddedinteamsacrosstheSnowyHydrobusiness.

ManytraineeshavesecuredfurthercareeropportunitiesatSnowyHydrowithcadetships,permanentandcasualpositions,andsomehavetakenonanapprenticeship.Othersheadofftouniversity,oftenreturningtoworkatSnowyduringtheirholidays.

In2021,10traineeswillbeemployedatthemainofficeinCooma,withoneeachinTalbingoandKhancoban.AylahRiceisoneofthesuccessfulnewrecruits,andhassomefamilyexperiencetodrawon-hergrandfatherwasadieselmechanicduringtheconstructionoftheoriginalSnowyScheme.Aylah,picturedabove,

wenttoschoolinTumutandisexcitedaboutherfirstfull-timerole.Sheistakingtheyeartolearnnewskills,gainexperienceandconsiderherfuturecareer.OneoptionsheiskeentoexploreisjoiningtheRoyalAustralianAirForce.

ThetraineeprogramispartofSnowyHydro’scommitmenttosupportingthelocalcommunitythrougheducationandemploymentopportunities,andhelpingthenextgenerationgetstartedintheircareers.Around10%oftheSnowyworkforceisindevelopmentroles,withtraineesactivelycontributingtotheday-to-dayrunningofthebusiness.Havingenthusiastic,interestedyoungworkersalsobenefitsthecompanybybringingfreshperspectivesandenergytoexistingteams.

CandidatesfortraineepositionsmusthavecompletedYear12,andbewillingtostudyBusinessAdministrationatTAFEaspartoftheirprogram.CoomatraineesattendTAFEweeklyandregionaltraineesstudyonline,withamonthlyvisittoCooma.Twooflastyear’strainees,NicolasStibbardandMariaTarasyuk,arecompletingatwo-yearITtraineeship,whichisanewofferingandincludes18monthsofTAFEstudyalongsidefull-timeemployment.

Recruitmentforthenextintakeoftraineeswillbegininmid-2021,withrepresentativesfromSnowyHydrovisitinglocalschoolstopresentinformationsessionsandanswerquestionsabouttheprogram.

Page 9: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

99

As we begin tunnelling for Snowy 2.0 using state-of-the-art tunnel boring machines, we take a look back at how they used to do it in the days of the Snowy Scheme construction.

FortheoriginalSnowyScheme,builtbetween1949and1974,the145kilometresofinterconnectedtunnelswereexcavatedusingthedrillandblastmethod.Heavypneumatic

drillsfittedtoathree-levelsteelframeworkcalledthe'jumbo'simultaneouslydrilledupto12holesintherockface.Eachholewasmanuallyfilledwithexplosivesbeforecrewsretreatedasafedistance.Whenthesmokeanddusthadsettledaftereachblast,amotorisedshovelcollectedthespoilanddumpeditintoa‘muck’train.Thejumbowaspropelledonrailsalongthetunnelfloor,movingfurtherintothemountainaftereachblast.

TheScheme’sfirsttunnelwasthe4.7kmGuthegatunnel,completedin1955.ThelongesttunnelsaretheEucumbene-Snowytunnel(23.5km)completedin1965,andtheEucumbene-Tumuttunnel(22.2km)completedin1959.

Theexcavationswerepermanentlysupportedusingrockbolting,amethodologydevelopedandrefinedbytheSnowyMountainsHydro-electricAuthorityinthe1950sand‘60sandstillusedinmoderndaytunnellingaroundtheworld.

BLAST FROM THE PASTTUNNELLING 1.0

9

Eucumbene-Snowytunnel‒–1962

MachinehallexcavationatTumut1–‒1957

Tumut1tunnelshowingrockbolting

Page 10: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

10

ASTROPHOTOGRAPHY

Snowy under the stars

Thedams,powerstationsandpenstocksoftheSnowySchemehavelongbeenin

thespotlight,withhundredsoficonicimagescapturedovertheyears.Theassetsandtheirbackdrop,themajesticSnowyMountains,areanidealsubjectforphotographerswithaneyeforuniquelandscapes.

SnowyHydroelectricalapprenticeandkeenphotographerIanGrant(picturedright)iscontinuallylookingforinterestingscenestoshoot,andaroundtheSnowyScheme,there’snoshortageofoptions.AnumberofIan’sphotoshavebeenselectedtoshowcasetheScheme,includingwinteryshotsaroundGuthegaPowerStationandaspectacularnightshotofJindabyneDamwall,

usingapopularstyleknownasastrophotography.

Whileastrophotographyisnothis‘goto’style,Iansayssomeimageslendthemselvestothetechniquewhich,asthenamesuggests,isallaboutthestarsandthenightsky.Whenalocationstrikeshimasapotentialcandidateforthestarrystyle,hemakestheextraefforttomonitorconditionsandorganiseashoot.

Astrophotographyrequiresaclearsky,ideallywithanewmoon,nocloudsandminimallightpollution.ThelocationoftheMilkyWayisanotherkeyconsideration.IntheSnowyMountains,Iansayslookingsouthtosouth-eastintheautumnmonthswillprovidethebestangleforgalaxyshots.

TheJindabyneDamphoto(topright)wastakeninMarch2020,notlongafterIanstarted

a12-monthtraineeshipwithSnowyHydroandjustbeforeCOVIDrestrictions.Theset-upandshoottookhalfanhour,withIan’sfatherMartin,amaintenancemanageratSnowyHydro,on-handtoshinethecar’sheadlightsonthedamwall.Iantookaroundadozenshots,experimentingwithframingandexposure.Longexposurescreatearcsoflightasthestarsmoveacrossthesky,whileashorterexposurecapturesthesprayofcountlessstarsoftheMilkyWay.

IancompletedatraineeprogramwiththeInformationManagementteamatCoomain2020andhasbegunhisfour-yearapprenticeshipthisyearatTalbingo.Onthephotographyside,heisalreadyplanninghisnextnightshootwithSnowy’sbiggestpowerstation,Tumut3,takingcentrestage.

JINDABYNE DAM PHOTO DETAILS

Exposure:20secondsIso:F4.5Camera:Canon90DLens:CanonEF-S10-18mmF4.5-5.6ISSTM

1. PorcupineRocks,PerisherValley

2. CuriosityRocksarea,LakeJindabyne

3. MountGladstoneLookout,Cooma

4. JacksLookout,Jindabyne

5. RainbowLake,PerisherValley

TOP SPOTS FOR ASTROPHOTOGRAPHY

Page 11: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

11

Page 12: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

12

RED ENERGY TURNS PINK

How you can help support Breast Cancer Network Australia Sign up your residential electricity and/or gas with Red Energy on a Red BCNA Saver plan and Red Energy will contribute $5 per fuel to BCNA for each month you remain on that plan*.

To find out more, or switch to the Red BCNA Saver plan, call Red Energy on 131 806 or visit redenergy.com.au/bcna/offer

*ContributionsstartfromthedateRedEnergybecomesresponsibleforacustomer’selectricityand/orgassupply.Eligibilitycriteriaandconditionsapply.Basicplaninformationdocumentsandfactsheetsavailableatredenergy.com.au/bpid.

Red Energy has a long-standing relationship with Breast Cancer Network Australia (BCNA) which will be further boosted in 2021 through a new customer plan that contributes up to $120 to BCNA per household each year.

TheRedBCNASaverplanisanextensionofRedEnergy’ssevenyearsofsupportforBCNAinitiativestohelpraiseawarenessofbreastcancerinthecommunity.

RedEnergy’sGeneralManagerBusinessDevelopmentDavidHolmanbelievescontributionsfromthenewplanwillhelpBCNAcontinuewiththeirvisiontoensureno-oneaffectedbybreastcancergoesthroughitalone.

Onaverage,55Australianswillbediagnosedwithbreastcancereverydaythisyear.BCNAprovidesinformation,support,connectionandavoiceforthoseaffectedbybreastcancerandtheirfamilies.Formorethantwodecades,theorganisationhasadvocatedtoensurethatallAustralianswhoare

affectedbybreastcancerreceivetheverybestcare,treatmentandsupport.

InadditiontocontributionsfromtheRedBCNASaverplan,RedEnergyisalsoamajoreventpartneroftheannualAFLPinkLadymatch,turningallbrandingandlogospinkforthedayinfrontofthousandsoffansattheMCG.

TheopportunitytojoinRedEnergyintheirsupportforBCNAisavailabletoanyhouseholdthatsignsupasaresidentialcustomerunderRedEnergy’snewRedBCNASaverplan.

RETAIL

Page 13: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

13

SUPPORTING OUR COMMUNITY

Organisers of community events around the Snowy Mountains have high hopes for 2021, following an unpredictable year of rescheduling and cancellations due to bushfires and COVID restrictions. Snowy Hydro remains a great supporter of local communities and has invested millions of dollars in sponsorship for targeted community initiatives and events.

Tumut Cycle Classic

Aftermissingoutin2020duetotheDunnsRoadbushfire,theTumutCycleClassicreturnedinJanuarywithmorethan440cyclistsparticipatinginsupportofTumutHospital.

Experiencedridersinthelongdistanceevents(100kmand75km)setofffromTumut’sBullParkjustaftersunrise,followedbythemoresocial40kmgroupandthe20kmfamilyride.

Sinceitsinauguralracein2015,moneyraisedbyeventsponsorsincludingSnowyHydro,participantsandlocalsupporters

hasfundedthepurchaseofmuchneededhospitalequipmentandhelpedattractmedicalstaffwithessentialskills.Thisyear’sgoalof$50,000willgotowardstheupgradeofanaestheticequipment.

Snowy Trout Challenge

RecreationaltroutfishingisapopularsportintheriversandlakesoftheSnowyMountains,andnotonlyforthebraggingrights.FromOctober2020toApril2021,anglershavethechanceofreelinginoneof430trouttaggedwithcashandprizes.Thepinktagshaveauniqueidentifyingnumberwhichcorrespondstoaneventsponsor.Prizesrangefromafreemealatthelocalpubtofishingequipment,giftcertificatesandcash.

TheNSWDepartmentofPrimaryIndustry(DPI)andlocalchambersofcommercedevelopedthechallengetopromotefishingandtourismduringspringandsummer.ThebrownandrainbowtroutweretaggedbyDPIandreleasedintoSnowywaterways.SnowyHydroisthemajorsponsoroftheSnowyTroutChallenge,providingtwocashprizesof$4,500andfivemerchandisepacksworth$200each.

AlburyfishermanDirkColvillecaughtoneofthecompetitiontroutinLakeJindabyneand

almostthrewitbackbeforenoticingthepinktag.HevisitedtheDiscoveryCentreinJanuarytocollecthis$4,500cashprize.

Tumbatrek and Tumbafest

FamilyfunisalwaystopoftheagendaatTumbafestandwhileCOVIDsafetymeasuresarenowinplaceatallcommunityevents,festivalfavouritesincludinglivemusic,marketstallsandwinetastingcontinuetoattractlocalsandvisitors.

HeldoverthelastweekendinFebruary,Tumbafestisamuch-lovedregionalcelebrationshowcasingdeliciousfreshlocalproduce,coolclimatewines,artsandcraftsandagreatline-upofmusicaltalentonthemainstage.SnowyHydroisaproudsponsorofTumbafest.

AlsoinFebruary,TumbatrekwasanothergreatopportunitytosupportTumbarumbaandgetadecentworkoutatthesametime.HostedbySnowyValleysCouncil,theeight-kilometrebushwalkwoundupthroughthehillsbehindthetownshipandwasclassedasamedium-difficultyhike.

AteamfromSnowyHydrojoinedthetrekkersagainthisyear,enjoyingplentyofspectaculardistrictviewsalongtheway.

Page 14: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

14

EDUCATION

Science of the Snowy Scheme

AcommunitypartnershiptobringtheScienceoftheSnowySchemetothePoliceCitizensYouthClubs(PCYC)

launchedinJanuary,offeringeducationalactivitiesandplentyoffuntomorethan65clubsacrossNSW.

ThepopularprogramencourageskidsattendingPCYCOutsideSchoolHours(OOSH)vacationcaretorolluptheirsleevesandgetinvolvedinscienceandengineering-basedminiprojects.Oversummer,730PCYCchildrentookpartinSnowyHydro’sSTEM-focusedlearningmodule,developedfortheNextGenerationEducationHub.

Childrenwerealsoinvitedtodesignafuturisticrenewableenergypowerstationandentertheirdesigninthe2021PCYCScienceoftheSnowyScheme

competition.Theirimaginedpowerstationmustgenerate100%Australian-basedelectricity,buttheiroperationsareopenforinterpretation,withcreativitystronglyencouraged.PastentrantshavedesignedpowerstationspoweredbyVegemite,kangaroosandofcourse,water–inspiredbythemightySnowyScheme.

CompetitionwinnersreceiveatriptotheSnowyMountainsfortheirfamiliesandavisittoAustralia’slargesthydro-powerstation,aswellas$500fortheirlocalPCYCclubforartandcraftsuppliesorsportingequipment.

Just add water

Schoolmayhavebeenoutforsummer,butforSnowyMountainskids,thelearningneverstops.Snowy’sH2Oholidayprogramwasbackwithfivesessionsofthe

STEM-basedinitiativedeliveredacrosslocalOOSHandvacationcarecentres.

Thistimearound,childrenatcentresinTumut,Berridale,CoomaandJindabyne(Gidgillys)tookpartintheprogram,withallsortsofscienceandengineeringactivitiesonoffertostimulatetheirminds.

OneofSnowy’sgraduateengineers,VardonRobson,gaveademonstrationofamodelturbineandbasichydropowerset-up.Childrenalsolearnthowtomakeandtesttheirownturbines.Othersdiscoveredtheinsandoutsoftunnelboringusingplaydough,whileonegrouphadtheopportunitytovisitTumut3PowerStation.

H2OKidswillbebackfortheEasterschoolholidays–checkwithyourlocalOOSHproviderfordetails.

Page 15: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

Next Generation Education Hub WeareexcitedtoofficiallylaunchourAustraliancurriculum-alignedonlineeducationplatform.TheNextGenerationEducationHubisadigitallearningplatformcreatedtoinvolvepeopleofallagesinlearningandlovingSTEM(science,technology,engineeringandmaths)subjects.

TheNextGenerationEducationHubprovideseasy-to-accessmaterialsdesignedtoinspirechildrentoexploreallaspectsofSTEM.Thelearningmodulesprovidecriticalthinkingopportunitiesthroughreal-life,practicalactivitiessuitablefortheclassroomorathome.

Thedownloadablefactsheetsandactivitysheetsalltietogetherwithlessonplansandinteractivefun.Discoverhowtobuildyourownpaperturbine,makesnow,conductexperimentswhile

delvingintothewatercycleandengagewiththeinteractiveSnowy2.0digitalpop-upbook,allthroughthelensofthepast,presentandfutureoftheSnowyScheme.

Theeasy-to-navigatemodulescoverelementsofengineeringandpowergeneration,thehistoryoftheSnowyScheme,Snowy2.0andmuchmore.

SnowyHydrohasaproudhistoryofsupportingthenextgenerationofinnovatorsbyprovidinganin-personeducationprogramattheDiscoveryCentreinCooma.TheNextGenerationEducationHuballowsustotaketheseexperiencesonlineandprovidenewopportunities.

15

Page 16: NEWS ISSUE 52 AUTUMN 2021 - Home - Snowy Hydro

Red Energy has partnered with Breast Cancer Network Australia since 2014 to help support Australians affected by breast cancer. Our partnership enables us to contribute, support and collaborate with BCNA on what is a very personal cause to many Australians.

How we will contribute to BCNA on your behalf When you sign up as a residential customer to a Red BCNA Saver plan, we will contribute up to $10 every month to BCNA. That’s $5 for electricity and $5 for gas accounts for every month that you remain on the Red BCNA Saver plan up to the value of $120 each year.*

We’re here to helpOur Customer Solutions team is based in Melbourne so our customers benefit from dealing one on one with a locally based, award-winning team and the economy benefits from keeping Aussie jobs here. To find out more or switch to the ‘Red BCNA Saver plan’ call us 131 806.

RED

229

07

131 806

Another great way to support Breast Cancer Network AustraliaAnother great way to support

Breast Cancer Network Australia

*Offer available to residential customers signing up to the Red BCNA Saver plan. Red Energy will contribute $5 per fuel to Breast Cancer Network Australia (ABN 16 087 937 531) for each calendar month you are on the Red BCNA Saver electricity and/or gas plan, starting from and including the date Red Energy becomes responsible for your electricity and/or gas supply. Eligibility criteria and conditions apply. Basic Plan Information Documents and Fact Sheets available at redenergy.com.au/bpid.