news notes 2014
TRANSCRIPT
-
8/13/2019 News Notes 2014
1/12
news notesms consultants, inc. engineers, architects, planners
New reservoir projects will satisfy current water demands andin the future serve an additional 200,000 central Ohioans.
See story starting on page 2.
Columbus South Innerbelt wins ACEC Award ... 6Rehabilitated Bridge Dedicated ... 8YSU STEM Study Completed ... 10ms Supports STEM ... 11ms 50th Anniversary Update ... 12
The Future of Water for the City of Columbus
Also in th is issue
-
8/13/2019 News Notes 2014
2/12
2
A new water supplyfor central Ohio
This aerial view shows the R-2 reservoir under construction in May 2013. With a footprint of 850 acres, it will impound more than 9.3 billion gallonsof water at the normal pool. The embankment (dam) that forms the reservoir is almost five miles long and will be the longest dam in Ohio.
-
8/13/2019 News Notes 2014
3/12
The city of Columbus public water system provides
drinking water to Columbus, Ohio, and 22 communities in
the metropolitan region from its three water treatment
plants, which have a combined capacity of 240 million
gallons per day (mgd). The distribution system, which
consists of more than 3,600 miles of waterlines, numerous
booster stations and storage tanks, serves approximately
1.1 million people.
In recent years, severe droughts have occurred in many parts of the United States, resulting in the drastic curtail-
ment of nonessential water uses and, in some instances,
water rationing. Rationing occurred in central Ohio during
a severe drought in the Midwest in 1987-88 when
Columbuss largest reservoir (Hoover) was within 50 days
of depletion. City leaders realized that additional water
supplies were needed, and in 1989 initiated a study called
Water Beyond 2000.
That study evaluated several options to supply the
additional water needed to meet central Ohios growingdemands, including on-stream reservoirs, upground reser-
voirs, quarries and groundwater. Public input was gathered
during evaluation of the options. Completed in 1998, the
study recommended developing additional groundwater
wells for the Parsons Avenue Water Plant, and to construct
three upground reservoirs within the Scioto River water-
shed to augment the existing OShaughnessy and Griggs
reservoirs. They serve as the raw water supply for the
Dublin Road Water Plant located some 30 miles down-
stream. More than 2,500 acres of land in northwest
Delaware County needed for the three reservoirs was
purchased during the next several years.
In 2005, the city of Columbus selected ms consultants
to conduct detailed investigations and prepare a prelimi-
nary design report outlining an implementation plan for all
three reservoirs, as well as the associated pumping and
raw water transmission facilities. ms developed a long-
range, multiple-phase strategy to provide an adequate and
dependable raw water supply to the citys Dublin Road
Water Plant for current and future use, as completion of all
three reservoirs will provide an additional safe yield of at
least 53 mgd during a 50-year drought condition.
More recent studies, including the City of Columbus
Comprehensive Water Master Plan, have reinforced the
need for these improvements.
So what is an upground reservoir? It is an
engineered water basin, separate, or off-stream of its water
source. These reservoirs are typically comprised of
earthen embankment walls and a clay-lined bottom, and
are classified as a dam by regulators.
(Continued on next page.)3
-
8/13/2019 News Notes 2014
4/12
4
Unlike on-stream reservoirs which receive runoff from an
upstream watershed, water must be pumped from a nearby river and
directed to an upground reservoir. Water stored in the reservoir is
then released for use during drought or prolonged dry periods.
When sizing the reservoirs for Columbus, the safe yield of the
existing water supplies had to be evaluated. The city has developed
its water supplies using the concept that the 1:50 safe yield, or the
available water from water sources
during a 50 year drought, be adequateto meet or exceed projected potable
water demands.
A major benefit of this project is
that it will assist another major water
utility north of Columbus. During a
prior settlement agreement regarding
the issue of water boundaries, it was
decided that the upground reservoirs
would also support the Del-Co Water
Company, Inc., which supplies water tomuch of Delaware County. Under this
settlement, Del-Co is participating in
the cost of construction and operations.
Construction began on the first
reservoir (known as R-2) in May 2011.
R-2 has a footprint of 850 acres and
will impound more than 9.3 billion gallons of water at the normal
pool. When all three reservoirs are completed they will hold
approximately 18.3 billion gallons.
The embankment that forms R-2 is about five miles in length
and ranges in height from 35-45 feet. When filled with water, its
size and unique design will make it the largest single upground
reservoir Ohio, and the largest synthetically lined reservoir in the
United States.
Due to the presence of shallow sand and gravel deposits
overlying karst limestone geology and high groundwater in the
area, the reservoir bottom was constructed using 37 million square
feet of a polypropylene geomembrane overlying 18 inches of Com-
pacted Clay Liner, and protected with geotextile and 18 inches of
cover soil. This composite bottom liner design will result in negli-
gible seepage of stored water into the underlying karst limestone
beneath the reservoir, which minimizes the potential for formation
of sinkholes or cavities in this type of geology.
It was anticipated that dewatering activities required during the
liner installation would lower groundwater levels for extended
periods well beyond the project work limits, and such conditions
could adversely affect nearby residential and agricultural water
supplies. The project team identified and assisted in the execution
of a multi-step, proactive program to address this issue.
First, a pre-construction assessment program was initiated
during the design phase, with more than 260 residential and agricul-
tural wells surveyed to determine the condition, quantity and
quality of the water in those wells before construction dewatering
began. Local residents were provided with a city representative to
contact should they experience operational problems with their well
during construction. Once contacted by a homeowner, the represen-
tative conducted a site visit to investi
gate current well condition and waterlevels in relation to the pre-construction
assessment information. When dat
indicated that the dewatering activities
caused operational problems or a well to
go dry, the city directed the construction
contractor to remedy the impact by
providing temporary, potable water to
the affected residence, modifying the
existing well or drilling a new well.
A drainage system utilizintwo-stage ditches with underlying storm
sewers was installed around the perim-
eter of the reservoir to intercept numer-
ous agricultural field tiles and direc
surface runoff around the reservoi
embankments. The perimeter ditch
system not only preserved existing surface and subsurface drainage
patterns, but also qualified as a post-construction stormwater best
management practice, since it will act as a vegetated filter reduc-
ing the amount of total suspended solids carried by the stormwater
flow and ultimately discharged to the Scioto River.
The need to relocate Ottawa Creek was eliminated by adjusting
the configuration of the northern embankment. Some wetlands
present on the site could not be avoided and the city was obligated
to mitigate for those wetlands.
Although nearby state routes were designed to accommodate
them, the significant number of vehicles carrying heavy loads
needed for construction had a high probability of damaging most
county or township roads in the project area. So, a limited number
of these roadways were established as dedicated haul routes for use
by construction vehicles not only for the reservoir, but also for the
new pump station on the Scioto River nearly four miles away and a
72inch raw water transmission main linking them. The existing
pavement was strengthened through pavement reclamation or
reconstruction before construction vehicles began using them, and
will receive new asphalt at the conclusion of the project. Contrac-
tors were penalized when drivers delivering products or materials
to/from the project work sites were observed traveling on roadways
not authorized as dedicated haul routes.
A new pump station was built nextto the Scioto River to divert waterto the reservoir as needed.
-
8/13/2019 News Notes 2014
5/12
The second component of the initial project was
construction of a new intake and pump station adjacent to the
Scioto River to divert water from the river to R-2 and the
other reservoirs when they are constructed. The pump station
is equipped with four vertical turbine style pumps that can
each deliver 40 million gallons of water per day to fill the
reservoirs. To build up a pool of water in the Scioto River,
intake and wet well to provide adequate pump submergence,
a 152-foot inflatable weir was designed and constructed inthe Scioto River. The weir will be inflated during times of
high flow so the pump station can be activated to fill the
upground reservoir, and will remain deflated at other times
and lay flat in the bottom of the river.
Federal and state regulators required that no construc-
tion occur within the Scioto River during spawning season
April 15 to June 30 and that operation of the proposed
inflatable weir be limited to two successive weeks during
this period. Additionally, an upstream low-head dam on the
river near Prospect, Ohio, was removed as a mitigationcondition to facilitate construction of the new inflatable weir.
The design solutions implemented in response to these
regulatory requirements will not only improve in-stream
water quality, but also minimize impacts to aquatic organ-
isms and allow migration upstream to foster redevelopment
of species in the upper reaches of the Scioto River.
Even though public access and recreational activities
such as fishing and boating will not be permitted on R-2
because of the risk of potential damage to the liner system,
recreational opportunities are included as part of the overall
project. This includes construction of an adjacent park in
conjunction with Preservation Parks of Delaware County
that will provide passive recreational activities such as walk-
ing, running, biking, picnicking and a natural playground
area for children. Additionally, a portage was built that can
be used by canoeists when the inflatable weir is raised, and a
new canoe access point was constructed downstream of the weir
near the confluence of Ottawa Creek and the Scioto River.
Currently, local fire departments in the area must withdraw
water from the Scioto River or nearby ponds to fill their tanker
trucks during fire runs. The Thompson Township Trustees asked if
the local fire departments could access stored water in the reser-
voirs to improve response time and refill tanker trucks.
In response, several non-potable hydrants with appropriate
hose connections will be installed along the Phase 1 raw water
pipeline that can be accessed by local fire departments.
The successful implementation of these initial projects has
been a direct result of the collaboration with our partners and
various governmental officials, regulators and affected/interested
5
residents, which began at the inception of the project and have
continued throughout the construction phase.
Key partners in this project include the adjacent counties of
Union, Marion and Delaware, the Ohio Department of Natural
Resources (ODNR) and the state legislature, which allowed this
project to pilot new bonding requirements and inspection costs for
large upground reservoirs. This reduced the cost of the project and
provided inspection funds for ODNR.
At the conclusion of this project, Columbus and central Ohio
will have a new water supply to satisfy the regions thirst for drink-
ing water for many decades to come.
For more information about this project, contact Ken Ricker
at 614.898.7100 or email [email protected].
Water cascades through the new inlet during the first fill test, held in July 2013.
-
8/13/2019 News Notes 2014
6/126
Columbus Innerbelt projectreceives national recognition
Work on the first phases of the I-70/I-71 reconstruction are wellunderway. The massive project is rebuilding the entire corridor wherethe two interstates merge through downtown Columbus, Ohio.
-
8/13/2019 News Notes 2014
7/12
The massive and complex reconstruction of the I-70/I-71
corridor through downtown Columbus, Ohio, has been underwayfor more than two years.
The engineering study that was completed to come up withalternatives and solutions to the traffic problems occurring within
the merge area of the two interstates started years before that.That effort, the I-70/I-71 Columbus South Innerbelt Study,
earned a National Recognition Award in the American Council of
Engineering Companies 2013 Engineering Excellence Awards(EEA) competition the Academy Awards of the engineering
industry, according to ACEC. The National Recognition Awardis a prestigious distinction honoring projects that demonstrate
exceptional achievement in engineering. ms consultants (project designer) and the Ohio Department of
Transportation, District 6 (project client) were recognized duringthe black-tie EEA gala awards program and dinner, held in April
2013 at the Grand Hyatt Washington Hotel in Washington, D.C.The I-70/I-71 Columbus South Innerbelt reconstruction is a
more than $1 billion project rebuilding the merging of two of themain interstates through Ohio. They come together on the south
and east sides of downtown Columbus.
When completed, the project will rebuild three freewaysystem interchanges, consolidate ramps to city streets and add
lanes improving the safety and increasing the capacity of theinterstate network through downtown.
The project is designed to reduce crashes by reducing weavingtraffic and increasing traffic capacity to meet future needs.
The first phase in rebuilding the corridor is the I-71/I-670interchange.
7
That particular interchange averages approximately137,000 vehicles per day.
Construction of the first phase is estimated to cost $200million. That portion of the project started in 2011.
A little farther to the south, Phase 2 has now started which
will rebuild the I-70/I-71 East Interchange, near NationwideChildrens Hospital.
The second phase will cost an estimated $260 million for
construction.More phases are planned, including reconstruction of the
I-70/I-71/State Route 315 interchange to the west and I-70/I-71
along the southern edge of downtown.Periodic updates will be published in this newsletter and at
www.msconsultants.com as the projects progress.For more information, please contact project manager Tom
Hibbard in the Columbus office at 614.898.7100, or [email protected].
Project manaTom Hibbardnext to the awexhibit at the
ACEC EnginExcellence AwGala, held at Grand HyattWashington Hin Washingto
-
8/13/2019 News Notes 2014
8/128
Rehabbed bridgededicated to
engineer whohelped save it
-
8/13/2019 News Notes 2014
9/12
The Standardsburg Road Bridge, originally built in 1926,
spans the West Branch Huron River in Ridgefield Township,
Ohio. The bridge is a steel Warren Through Truss having a single,
124-foot span.
The bridge was in very poor condition when ms consultants
was hired by Huron County officials to inspect it. That inspection-
resulted in a rating of 3 and a maximum load limit of 20 tons. The
existing bridge and approach roadway were approximately 20 feetwide with no sidewalks.
ms long-time structural engineer, Wade Harvey, conducted an
initial structural analysis that showed the bridge could be salvaged
through key rehabilitation strategies. His load rating analysis
identified the limiting capacity bridge members. His design tactics
evaluated ways to strengthen or replace key members and studied
alternate floor systems to lighten the floor loads so that the struc-
ture could once again carry full legal truck loads.
Rehabilitating the bridge involved dismantling the existing
truss by removing key rivets and shipping it to a fabricator, wheredeteriorated truss members including stringers, floor beams,
gusset plates and bottom chords were either rehabbed or
replaced. All steel members were sand-blasted and galvanized.
The rehabilitated truss members were then shipped back to the
site where the bridge was reassembled over the river onto recondi-
tioned abutments.
The project also included replacement of the rocker and
bolster bearings with new elastomeric bearing assemblies fitted to
the truss, a new waterproofed timber floor system with asphalt
wearing surface, new bridge and approach guardrails, along with
minor improvements to the existing wing walls and approach
roadway drainage systems.
The bridge was officially opened to traffic in November 2012,
and now carries full Ohio legal loads.
On July 30, 2013, Huron County officials dedicated the
Standardsburg Road Bridge to Mr. Harvey, who succumbed to the
advanced stages of cancer before the project was completed.
For more information about this project, please contact Brian
Hughes in the Youngstown office at 330.744.5321, or email
Project manager Wade Harvey recognized earlyin the analysis of the bridge that it was possible
to save much of the structure. Sadly, hesuccumbed to the advanced stages of cancer
before the project was completed.
f Wades three sons, Kevin (left) andn, unveiled the plaque dedicating theardsburg Road Bridge in his honor.wd of more than 40 attended the ceremony,ding his wife Kathy and other son Mark.
-
8/13/2019 News Notes 2014
10/12
10
Youngstown State University (YSU), with an enrollment of
more than 15,000 students, is an urban research university located
adjacent to downtown Youngstown, Ohio.
The university recently restructured its academic divisions to
include the College of Liberal Arts and Social Sciences (CLASS),
the College of Science, Technology, Engineering and Mathemat-
ics (STEM), the Williamson College of Business Administration,
the Bitonte College of Health and Human Services, the College of
Creative Arts and Communication, the Beeghly College of Educa-
tion, and the School of Graduate Studies.
The YSU STEM Outreach Initiative is a collaborative effort
between the YSU STEM College, the Youngstown City Schools,
the Youngstown-Warren Regional Chamber of Commerce and
area employers of STEM graduates.
The fundamental objective of this multi-faceted initiative is to
enlighten and encourage pre-college students to pursue post-
secondary STEM degrees, as well as mentor and prepare them for
future careers in STEM related fields. The result should be an
increased number of highly skilled and talented engineers entering
the workforce, thereby meeting the employment needs of
Youngstown and the Mahoning Valley.
With realignment of the colleges came the necessity to
perform planning for the various STEM facilities. ms consultants,
in collaboration with BHDP Architecture, provided master
planning for the STEM College.
Campus facilities evaluated in the study include Moser Hall,
Ward Beecher Hall, Meshel Hall, the Phelps Building, the Lincoln
Building, the Garfield Building and the AT&T Building.
STEM study completed for YSU
analysis of various existing structures on theU campus addressed their suitability for currents, and the feasibility for additional uses.
-
8/13/2019 News Notes 2014
11/12
11
ms supports STEMWorking with the students, staff and administra-tors, and guided by the university's Strategic Plan,
Campus Master Plan and the STEM Strategic Plan andMission Statement, the ms/BHDP team evaluated and
analyzed the university's facility needs and usage ofthe current STEM related facilities. These included
Moser Hall, Ward Beecher Hall, Meshel Hall and the
Lincoln Building. Analysis of these existing structuresaddressed suitability for current uses as well asfeasibility for additional uses.
The Phelps Building, the Garfield Building and theAT&T Building were also considered and evaluated as
potential space for STEM functions.
The project team identified logistical/phasingissues by building and department to allow for continu-
ous academic operations. Special consideration wasalloted to issues related to Hazmat, EPA and OSHA
regulations and requirements relative to specificlaboratory activities and functions.
ms/BHDP proposed various facility configurationsand adjacencies, and developed a matrix of space
configuration options, giving consideration to avail-able facilities and structures. The concept of enclosed
pedestrian connectivity between the various structureswas also addressed.
Any necessary relocation of departments currently
occupying proposed spaces was considered.The team budgeted construction costs for the
referenced options, as well as recommendations(including pros and cons) for the various alternatives.
The total concept envisions restructuring and/orreconfiguration of existing campus facilities, as well as
construction of a new building that will accommodatethe STEM College. The final project budget may range
from $100 million to $125 million.ms/BHDP developed the final master plan, which
includes development of site master plans, designgraphics and design narratives that were presented to
YSU Administration and the STEM Planning Team
(made up of the dean, faculty and Facilities Planningdepartment).
The final step is a recommendation to moveforward with funding options and implementation of
the plan.For more information about this project, please
contact project manager David Kiraly in Youngstownat 330.744.5321, or e-mail [email protected].
ms consultants supports STEM programs in a number of ways, fromoffering engineering and architecture internships to students interested inthose technical fields, to hosting Engineer for a Day activities for highschool students and sponsoring a robotics competition.
Jay Thorne, the branch manager of ms Indianapolis office, serves onthe steering committee for the City of Indianapolis and Mayor Greg Ballards
VEX Robotics Championship.This annual event, of which ms consultants is a sponsor, took place inNovember 2013 and was scheduled to be attended by 48 high schools and40 middle schools.
Each team of students worked to design, build and program a robot tocompete against robots from other teams in a sports-like game. Teams wonawards for completing tasks in a timed competition, along with creatingbusiness plans, developing cohesive team brands, cooperating with otherteams, forging suitable initiatives, and enhancing civic awareness andpassion for STEM fields in modern communities.
The top team qualifies for the 2013 VEX Robotics World Championship. Additionally, Rose-Hulman Institute of Technology committed to provide full
college scholarships to the members of the winning team.Please contact Jay Thorne at 317.566.0050 for more information about
this program. He has been on the steering committee since the programsinception and also serves on the ACEC Education Committee, which worksto increase awareness in schools. He visits high schools and middleschools throughout the year to discuss careers in engineering.
ms consultants also promotes careers in engineering by sponsoring anannual Engineer for a Day event at its Columbus and Youngstown offices.High school students from various school districts that offer the ProjectLead the Way program are given tours of the facilities and shadowengineers and architects in each technical group - transportation, waterresources, structural, mechanical and electrical engineering, etc.
Project Lead the Way (PLTW) is a nationwide, non-profit organizationdedicated to increasing the quality and quantity of science and technologygraduates in the United States.
A high school program championed by PLTW offers a four year series ofcourses which, when combined with traditional mathematics and sciencecourses in high school, introduces students to the scope, rigor anddiscipline of engineering prior to entering college.
Contact Michelle Murphy in Columbus at 614.898.7100 for moreinformation about the Engineer for a Day and PLTW programs.
Students and ms staff from Engineer for a Day 2013.
-
8/13/2019 News Notes 2014
12/12
2013 marks ms consultants 50 th year in business, havingbeen founded in Youngstown, Ohio, in 1963.
Thats the same year that Martin Luther King, Jr., gave hisfamous I have a dream speech, the same year the very firstJames Bond movie (Dr. No) arrived in theaters and the sameyear the first album by some rock group named The Beatles hitrecord store shelves in America.
The company has come a long way since the early dayswhen Thomas F. Mosure and Thomas Fok worked out of thebasement of a small building on Market Street in Youngstown.
ms consultants now has four offices in Ohio and hasexpanded into Indiana, Pennsylvania, West Virginia and North
Carolina.To celebrate our 50 th year, weve been having parties and
social events at all office locations. Weve also added a page toour website with a timeline of our history and other majorevents and fun facts that have occurred since 1963.
To visit the website, go to: www.msconsultants.com/timeline/Were proud of the service weve been able to provide during the past 50 years, but couldnt have done it without the support of our many
clients, business associates, friends and employees.So a very special thank you to everyone involved, and were already looking forward to the next 50 years!
ms is celebrating our 50th anniversary!
PRSRT STDU.S. POSTAGE
PAIDPERMIT NO. 225
YOUNGSTOWN, OH
Guests and ms staff crowd the lobby during the Columbus anniversary party.