next level schedule analytics & automation
TRANSCRIPT
![Page 1: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/1.jpg)
Next Level Schedule Analytics & Automation
![Page 2: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/2.jpg)
Speaker Name
• Speaker bio:– SmartPM Technologies, Inc– Industrial Engineer– 20 yrs experience in construction schedule analysis– PSP, CCE Certified– Fun fact: I Love Soup!
www.smartpmtech.com 2
Insert Photo
![Page 3: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/3.jpg)
Topic Outline
3www.smartpmtech.com
• Announcement • History of Scheduling• Current State of Construction Scheduling• The Future of Scheduling• How will we need to Evolve as Schedulers• Man vs. Machine - Who will be better at what?• Questions & Comments
![Page 4: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/4.jpg)
Announcement – Schedule Quality Contest
4www.smartpmtech.com
Sign up today!
**Schedules graded using SmartPM’s default DCMA based grading structure
![Page 5: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/5.jpg)
HINT – SmartPM’s Quality Grading Criteria
5www.smartpmtech.com
![Page 6: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/6.jpg)
THE HISTORY OF SCHEDULING
![Page 7: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/7.jpg)
In the Beginning
7
![Page 8: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/8.jpg)
1896: The Workers Harmony Graph
8
![Page 9: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/9.jpg)
1912: Early Versions of a Graphic Bar Chart
9
![Page 10: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/10.jpg)
1957: The First Computerized Scheduling Program
10
![Page 11: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/11.jpg)
1983: Primavera Developed the First CPM Scheduling Program
11
![Page 12: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/12.jpg)
THE CURRENT STATE OF SCHEDULING
![Page 13: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/13.jpg)
The Schedule Analytics Age is Upon Us
13
Schedule Quality
Schedule Delay
Schedule Recovery
Schedule Risk
Schedule Feasibility
Schedule Predictive
![Page 14: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/14.jpg)
14
Analyzing Schedule QualityPreferred Technique: DCMAHow Often: Every ScheduleTechnologies: SmartPM™, Acumen Fuse, Schedule Analyzer, Steel Ray, Rubix, Schedule CrackerChallenges: Most tools lack intelligence & require specialized ExperienceTips: Enforce Best Practices; Don’t accept bad schedules to avoid confrontation
Analyzing RecoveryPreferred Technique: Comparison, Half Step How Often: Every UpdateTechnologies: SmartPM™, Claimdigger, Acumen Fuse, Schedule Analyzer, RubixChallenges: Manual Process is specialized & time consuming / Most tools are archaic, lack intelligence and
require a specialist. Tips: Focus on Critical and Near Critical Changes; Perform What – If Scenarios; Don’t fear the discussion
about this
Schedule Analysis Techniques and Technologies
![Page 15: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/15.jpg)
15
Analyzing Critical Path DelayPreferred Technique: Windows AnalysisHow Often: Every UpdateTechnologies: SmartPM™Challenges: Manual Process is specialized, time consuming, subjective and arguableTips: The more analysis the better; Document Assumptions; Objectivity Wins; Graphics need to Speak
Analyzing Feasibility, Risk & Predictive Analytics
Preferred Technique: Compression Analysis & Monte CarloHow Often: Every UpdateTechnologies: Primavera Risk, SmartPM™Challenges: Manual Process is specialized & time consuming / Most tools lack intelligence and require a specialistTips: Use Project Actuals to estimate Activity Distributions in Simulator; Use Critical Path Sensitivity data
proactively; Reject overly compressed schedules. Be Objective.
Schedule Analysis Techniques and Technologies
![Page 16: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/16.jpg)
16
Cloud Based Scheduling
![Page 17: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/17.jpg)
17
Complex Schedule Analytics Automation
![Page 18: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/18.jpg)
THE FUTURE OF SCHEDULING
![Page 19: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/19.jpg)
19
Mass Schedule Data Aggregation
![Page 20: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/20.jpg)
20
Machine Learning & Artificial Intelligence
![Page 21: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/21.jpg)
21
Scheduling Automation
![Page 22: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/22.jpg)
THE EVOLUTION OF THE SCHEDULER
![Page 23: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/23.jpg)
23
Preparing for the Future – Knowledge and Understanding
![Page 24: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/24.jpg)
24
The Next Generation of Scheduling: Schedule-centric Analytics
![Page 25: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/25.jpg)
25
Man vs Machine – Who will be better at what?
![Page 26: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/26.jpg)
26
My Prediction(s) – The industry will become Enlightened through Technology
1. The Schedule and the data behind it will be recognized for what it is: The most important data set in Construction.
2. Schedulers will be doing less busy work and more strategic work
3. There will be more Scheduling and Project Analyst roles, not less.
![Page 27: Next Level Schedule Analytics & Automation](https://reader031.vdocument.in/reader031/viewer/2022012100/6169e64011a7b741a34c99bc/html5/thumbnails/27.jpg)
QUESTIONS/ COMMENTS?