nfl naya nangal six monthtraining report

35
NATIONAL FERTILIZERS LIMITED (Naya Nangal Unit) 14 th May, 2015 CERTIFICATE OF TRAINING Institute’s name: Beant College of Engineering & Technology, Gurdaspur (Pb) Branch: B.Tech (Mech) –4 th year Training Period: January 15, 2015 to May 14, 2015 Submitted to: Submitted By: Ashish Kumar

Upload: passionabhinav

Post on 17-Sep-2015

258 views

Category:

Documents


73 download

DESCRIPTION

This is the training report for NFL Nangal

TRANSCRIPT

  • NATIONAL FERTILIZERS LIMITED

    (Naya Nangal Unit)

    14th

    May, 2015

    CERTIFICATE OF TRAINING

    Institutes name: Beant College of Engineering & Technology, Gurdaspur (Pb)

    Branch: B.Tech (Mech) 4th year

    Training Period: January 15, 2015 to May 14, 2015

    Submitted to: Submitted By: Ashish Kumar

  • Contents

    1. Introduction

    2. Steam Generation Plant

    3. Mechanical Workshop

  • Introduction

  • 1.0 INTRODUCTION TO ORGANIZATION

    A VIEW OF NATIONAL FERTILIZER LIMTED NANGAL

    Figure 1.1 view of NFL NANGAL

    1.1 INTRODUCTION TO NFL NANGAL

    My training was at NFL Nangal. Nangal is a beautiful town situated in Distt. Ropar (PB). This is

    the first key industry set up by Govt. Of INDIA with coming up of Bhakhra Dam & surplus

    power available from the project at the time. It was derived by Govt. Of India to set a fertilizer

  • plant at Nangal, which went to production in 1961.The plant at that time produce Ammonium

    Nitrate (25% Nitrogen) and heavy water.

    Subsequently In 1978 went an Ammonia Plant based on fuel oil gasification which added Urea

    (46% Nitrogen) to its main product in 1990.

    In 1978, In urea formation the hydrogen was available from electrolysis of the water which on

    electrolysis treatment produce hydrogen and oxygen & from this hydrogen further ammonia is

    formed, but after short time of gap Electrolysis plant was replaced with Front End Plant(NMP-I)

    based on reforming of Naphtha production of hydrogen and reducing the electrical power

    consumption.

    1.2 NFL PLANTS

    NFL has several plants in all over India and the location of various fertilizer plants In India as:-

    1. National Fertilizer Limited Vijaipur (MP)

    2. National Fertilizer Limited Panipat(HR)

    3. National Fertilizer Limited Bathinda (PB)

    4. National Fertilizer Limited Naya Nangal (PB)

    1.3 PRODUCTS OF NFL

    NFL Nangal mainly deals with production of Urea but there are several by products which get

    produce

    Products Capacity( in MTPD)

    Urea 1450

  • Methanol 67

    Sulphur 24

    Ammonium Nitrate As per Reqd.

    Liquid Carbon Dioxide 24

    Sodium Nitrite 9

    Sodium Nitrate 6

    Nitric Acid 554

    Ammonia 900

    Table 1.1 products of nangal

    There is also the formation of poisonous gases such as CO, CO2, CH4, H2, & H2S etc.

    The NFL, Nangal Unit has been broadly classified into two parts:-

    a) UGP ( UNIT GROUP OF PLANT):-

    WTP - WATER TREATMENT PLANT

    NAP- NITRIC ACID PLANT

    urea

    methanol

    sulphur

    Ammonium Nitrate

    Liquid Carbon dioxide

    Sodium Nitrite

    Sodium Nitrate

    Nitric Acid

    Ammonia

  • b) EGP (EXPANSION GROUP OF PLANT):-

    SGP- STEAM GENERATION PLANT

    UREA BAGGING PLANT

    Statistic Data

    The input and output data of company is as in which it informs about the name of the

    product and the consumption of raw material

    Raw material Name of The

    Product

    Consumption

    Fuel oil Ammonia 832.04 MT/Unit

    Coal Steam 191.25 MT/Unit

    Caustic Soda NOx 1547 MT/Annum

    Water Consumption

    River Satluj is the exclusive source of raw water to NFL, Nangal unit.

    1. Process Water (m3) for EGP 5538481

    2. Process Water (m3) for UGP 307010

    3. Domestic Water 4042120

  • Raw water Analysis

    S. No. Parameters Range Value

    1. pH 7.8-8.0

    2. Total Hardness (as CaCO3

    mg/L)

    29-34

    3. Magnesium hardness, mg/L 4-6

    4. Sulphates (as SO4 mg/L) 2-4

    5. Chloride (as Cl, mg/L) 6-20

    6. KMnO4 Value, mg/L 4-6

    7. Calcium Hardness (as

    CaCO3, mg/L)

    46-52

    pH

    Total Hardness (as CaCO3

    mg/L)

    Magnesium hardness,

    mg/L

    Sulphates (as SO4 mg/L)

    Chloride (as Cl, mg/L)

  • 1.4 COMPANY OUTPUT

    Overall Turnover of NFL is 3800 crores.

    The employee strength is as:

    Total Employee 1542

    Officers 232

    Workers 1310

    Main Product & its Objective:-

    Kisan Urea Specifications:-

    Moisture Less than 1%

    Nitrogen on Dry Basis- More than 46%

    Biurate by weight 1%

  • Physical and chemical properties of urea:-

    S.No. Property Assigned Value

    1. Formula Weight 60.06

    2. Melting Point 132.7oC

    3. Boiling Point Decomposes at atmospheric

    pressure (

  • soil colloids for longer duration. Urea is available in granular form and can be applied by

    drill and broadcasting. Kisan urea is ideally suitable for all types of crops and for foliar

    spray which instantly removes nitrogen deficiency. Kisan also has a strong and long

    lasting effect on crops resulting in bumper crops. Carbonic acid present in kisan urea help

    in absorption of other nutrients like phosphate and potash by roots crop.

  • STEAM GENERATION PLANT (SGP)

  • 2.0 STEAM GENERATION PLANT

    2.1 Objective of SGP:-

    In NFL, Nangal Unit Plant, all the basic unit operations need steam for their work and must of

    the industrial equipment are driven by steam such as Turbo Compressors, Steam jet ejectors,

    preheater etc.

    In unit operations

    1) For evaporation supply the steam to evaporate

    2) For crystallizations supply the steam to crystallizer

    3) To create the negative suction pressure mostly supply in the steam jet ejector

    4) For combustions purpose such as gasification process

  • 5) To exchange the heat of desire product by use of steam.

    SGP starts from-

    1) Handling &Storage of Coal ,Fuel Oil ,LHSH , LDO & Methanol

    2) Boilers-

    a) Coal Fired Boiler

    b) Gas Fired Boiler

    3) Pollutions Control Sections

    4) Steam Network Section

  • Figure 2. Unloading of coal

    a) - COAL UNLOADING THROUGH TRIPLER

    Tippler Wing Conveyor

    Vibrators, ET-1(Underground)

    (Cap. =550-600 MT/hr) ET-2 Coal Yard

    ET-3

    Coal Yard Storage Capacity = 30,000 Tons

    b) - COAL FEEDING SYSTEM

    Feeding Hopper Magnetic Belt

    Vibrators Magnet Magnet

    ET-4 (Underground) ET-5 ET-6

    (Cap. =110-130 MT/hr)

    Mill Bunkers (6 Nos.)

    Coal from Wagon

    Coal from Yard

    Crusher

  • 2.2 COAL FIRED BOILER

    2.2.1 INTRODUCTION:-

    The integrated service boilers for the Nangal Expansion Fertilizer Project are different from

    conventional boilers. These boilers are radiant, outdoor, bidrum, high head, non-reheated type &

    pulverized coal is used as principal fuel

    These boilers are designed to heat up external high pressure saturated steam from heat boilers,

    along with generated steam coal is used as principal fuel

    These boilers are designed to heat up external high pressure saturated steam from waste heat

    boilers, along with generated steam in the boiler to the same final superheated steam

    These boilers generated 117t/hr of steam and 65t/hr external import steam. The final superheated

    steam generated 182t/hr will have a pressure of 91kg/cm2 & temperature of 510

    2.2.2 MAIN BOILER STRUCTURE:-

    The boiler designed of the top supported type & allowed to expand downwards. The main boiler

    is supported four rows of column on either side of the boiler (S1, S2, and S3 &S4)

    Boiler feed water which is coming from NH3-II plant which is preheated to 145 & then passing

    through the economizer where its temperature is rises to 182-188 then it is transferred to the

    steam drum. In the steam drum it is converted to the saturated steam & remaining water is not

    converted to steam is transferred to mud drum through bank tubes

    In the mud drum temperature of the condensed water is raises by the flow of the flue gases from

    the mud drum through bank tubes.

  • In the mud drum temperature of the condensed water is rises by the flow of the flue gases. From

    the mud drum preheated water is then transfer through the tubes along the sides of furnace and

    recirculated to the steam drum and the above processes continuously running. The purpose of

    recirculation is that, we cant leave the steam drum empty.

    The temperature of the saturated steam leaving the steam drum is around 310 to 315C. The

    saturated steam is then given to platin super heater where its temperature is rises to about 405 to

    410C. The temperature of the platen super heater is 905C

    2.2.3 COAL PULVERSIZING SECTION;-

    In this section ball mill is used to pulverize the coal. Firstly coal which is crushed in the hammer

    crusher to the size about size 25 mm is then transferred to the coal bunkers & from coal bunkers

    & from coal bunkers through feeder to the centre of revolving ball of the ball mill. Hot air is

    given to the Ball which is coming by passing through the air heater for the following two

    purposes:-

    1. for the drying of the pulverized coal

    2. for the movement of the pulverized coal to the furnace

    Hot air enters the mill housing below the ball and is directed upward passes through the classifier

    vanes. The rising hot air around the ball picks up the pulverized coal, the lighter particles carried

    by the air passes through the classifier & heavier particles are returned from the classifier to the

    ball for additional grinding. Finally the pulverized coal having particle size 200 meshes & air

    leaves the Ball Mill through classifier

  • 2.2.4 COAL COMPOSITION

    MOISTURE 6-10%

    VOLATILE MATTER 16-20 %

    FIXED CARBON 39-45%

    ASH 30-35%

    Table 2.1 coal composition

    2.2.5 COMBUSTION CHAMBER OR BIOLER FURNANCE

    At the four corner of the combustion chamber or boiler furnace one wind box is installed. At

    each corner one burner is located. Each burner will comprise of four streams which are given to

    the furnace, these are coal +Air, Tail Gas, LDO+ steam & hot air nozzles arranged vertically in

    an insulated wind box

    Moisture

    Volatile matter

    fixed carbon

    ash

  • Air is sucked from the atmosphere by the forced draft fans & supplied to the air heater. After

    passing through the heater temperature of the air is increased and then it is passed through the

    heater temperature of the air is increased and then it is transferred to the wind box. For the

    burning of the coal oil gun is used & all the other streams are given for the complete combustion

    of the coal & unburned coal particles are dropped to the bottom where screen is used to transfer

    them to bottom ash hopper

    The flue gases which are produced after the combustion of the fuel moves upward to the furnace

    with centrifugal force. Centrifugal force is developed when all the streams from the four corners

    will meet at a single where the burning is taking place

    The temperature of the combustion chamber, where burning of the coal is done is 1070C.

    During the upward movement of the flue gas temperature difference between lower and upper

    part of the of boiler which is going to be in between 100C to 150C

    2.2.6 TAIL GAS COMPOSITION

    H2 7.00%

    Ar 3.80%

    N2 16.10%

    CO 27.90%

    CH4 3.30%

  • H2O 41.90%

    Table 2.2 tail gas composition

    Tail gas which is coming out from ammonia II plant contains an appreciable amount of CO

    which is not directly disposed to the atmosphere because of its harmful effects. So this gas is

    ignite in the furnace and convert the CO to CO2 and reduced the content of the gas

    Due to the large content of non-combustion of gases i.e. N2 & H2O, the ignition of the CO gas is

    difficult& is not self sustaining. After ignition is converted to the flue gases and are disposed to

    the atmosphere

    2.2.7 PROCEDURE FOR DISPOSAL OF ASH:-

    We used coal as a fuel for the running of the boiler, approximate 1000MT/day of coal is used

    and huge amount of ash is generated. For efficient running of the boiler continuous removal of

    H2

    Ar

    N2

    CO

    CH4

    H2O

  • ash contents is essential .Heavier particles of burned coal are retained in the bottom ash hopper

    of the boiler and the light particles are collected in the Electrostatic Precipitator

    Finally the mixture of ash & water is discharged through feed gate & clinker, grinder, which

    reduces the size of the clinker to about 50 mm to the ash slurry pit. Then ash slurry is disposed to

    ash pond area

    2.2.8 BOILER FEED WATER SPECIFICATIONS:-

    TEMPERATURE 145C

    TOTAL HARDNESS AS CaCo3 0.3ppm

    SILCA 0.1 ppm

    O2 0.02ppm

    IRON 0.02ppm

    COPPER 0.005ppm

    pH 7.5-9.0

    Import steam which is coming from the NH3-II plant at a temperature 313C and pressure105ata

    is given to the import steam super heater where we get superheated steam whose temperature is

    around 510-520C. The temperature of the final super heater is 872C

    For controlling the temperature of the superheated steam, one desuperheater is used whose

    temperature is ling in between 370-400C. So after desuperheater finally we get superheated

    steam whose temperature is 500C and pressure is 91 ata, which is then given to different

    sections in the plant. It produces 182 Ton/hr of superheated steam.

    The flue gas which leaves from the furnace is leaving at the temperature of 530-540C, so

    arrangement is made for the waste heat recovery. Firstly the flue gases pass through import

  • steam super heater where some amount of heat is recovered and temperature of the flue gas

    reduces to 430C.

    Then it passes to economizer where the temperature is reduced to 338C and then it is passed

    through air heaters which are used for preheating the air sucked by forced draft fan the

    temperature of the flue gases are sucked by force draft fans and are given to the ESP for the

    removal of fly ash or dust.

    2.3 Main Boiler Structures

    The boiler design of top supported type &allowed to expand downwards. The main boiler

    supported four rows of the column on either side of the boiler (S1.S2, S3AND S4)

    Boiler feed water which is coming from NH3-2 Plant which is preheated to 125c &then passing

    through the gilled tube economizer where temperature is rise to 182-188c then it is given to

    steam drum & in the steam drum it is converted to saturated steam.

    The temperature of the saturated steam leaving the steam drum is around 320-325c the water

    which is remaining in steam drum is transfer through the tube along the side of the furnace and

    recirculated to the steam drum & the above process continuously running .the purpose of

    recirculation is that, we cant leave the steam drum empty .the saturated steam is then given to

    the platen super heater where its temperature rises to about 405-410c. The temperature of platen

    super heater is 920c.

    Import steam which is coming from the NH3-2 plant at a temperature 313c and pressure 105 ata

    is given to the import steam super heater where its temperature is rises around 405 -410c.then

    finally mix both stream i.e. saturated steam & import steam &given to the final super heater

  • from where we get superheated steam whose temperature is around 510-520c. The temperature

    of final super heater is 872c.

    For controlling the temperature of the superheated steam ,one desuperheater is used to

    whose temperature is lies in between 370-400c so after desuperheater finally we get superheated

    steam whose temperature is 510&pressure 91ata ,which is then given then to different section in

    the plant .it produces 140T/hr of superheated steam

    The flue gas which leaves from the furnace is leaves from the furnace is leaves at a temperature

    of 660-670c ,so arrange is made for waste heat recovery .firstly the flue gases pass through bare

    tube economizer and then from import steam superheater where some amount of heat is

    recovered &temperature of flue gas reduced to 360c

    Then it is passes through gilled tube economizer where temperature is reduced to 299c 7 then it

    is passed through rotary air heater is 121c

    The flue gas after passing through rotary air heater is going to the chimney & from the chimney

    it is disposed to atmosphere the height of the chimney is 80m &flue gas from other source of the

    plant are also disposed from the same chimney the flue gas which is disposed to atmosphere with

    following compositions (SO2=500-600mg/Nm3, SPM=110mg/Nm3)

    2.4 POLLUTION CONTROLL SECTION

    2.4.1 Electrostatic Precipitator:-

    Flue gas are sucked by the Forced Draft Fan and supplied to ESP .Fly ash or dust is collection is

    done in the Electrostatic Precipitator by imparting the negative charge to the dust particles &

  • attracting them towards positive plate disposal of the collected dust is done by rapping the

    electrode.

    The ash or dust which is collected in ESP is coming to hydrovecter then this ash is transfer red

    along with water which is coming from NH3-2 plant to the ash slurry pit. Then ash slurry is

    disposed to ash pond area.

    2.4.2 Stack:-

    The flue gas after removal of dust id thrown to the outside the chimney to atmosphere by the use

    of induced draft fan .the height of the chimney is 80m &flue gas from the other source of the

    plant is also disposed to same chimney the flue gas which is disposed to atmosphere with

    following composition (SO2=500-600mg/Nm3, suspended particles=110mg/Nm3)

  • MECHANICAL WORKSHOP

  • Mechanical workshop at NFL unit mainly committed to the maintenance and repair work.

    Various maintenance jobs are done here as per the job orders given by different plants of NFL

    unit. The mechanical department has futher different workshops namely-:

    Machine shop

    Fabrication shop

    Fitting shop

    Earthmoving shop

    Refrigeration shop

    Details of the different workshops is given as following.

    Machine shop

    Fitting shop

    Fabrication shop

    Earthmoving shop

    Refrigeration shop

    MACHINE SHOP

    Machining of a material involves repeated removal of material from the job to give away the

    required shape and size.

    Machine shop has various machines that are being used for the machining processes of the jobs

    from the plant. Some of the machines in the shops are

  • SLOTTER MACHINE

    LATHE MACHINE

    GRINDER MACHINE

    BORING MACHINE

    DRILLING MACHINE

    MILLING MACHINE

    PLANNER MACHINE

    SHAPER MACHINE

    SHEARING MACHINE

    SHEET CUTTING MACHINE

    LATHE MACHINE

    Lathe is a power driven, genral purpose machine used for producing mostly

    cylindrical jobs or work pieces. As the piece of metal to be machined is rotated on the lathe, a

    single point cutting tool is advanced racially in to the work

    piece,removing the metal marterial in forms of chips.Main difference between

    lathes where as in the the other machines cutting tools is moved an the work

    piece remains stationary.

    Parts of Lathe Machine

    HISTORY OF LATHE

    Most versatile machine tool in the machine shop

    Oldest ancestor is the potters wheel(4000B.C)

  • Next came pole lathe

    This was developed into current lathe which are able to make threads

    Father of modern lathe HENRY MAUD SLAYS

    Types of lathe machines found in the NFL mechanical workshop-

    Central lathe

    Turret lathe

    Capstan lathe

    Centre lathe or engine lathe

    It is most important and widely used machine in the lathe family.its name is derived from the fact

    that the earliermachine tools were driven by separate engines or from the central engine with

    over head belt and shafts .The stepped cone pulley or gear head are often used for varying the

    speed of the lathe machine

    Turret lathe

    It is a production machine used to perform a lot of task or operation on a single job with

    minimum wastage of time.Indexable square tool is Provided on the cross slide or the mounting

    turning and parting of tool. The Turret usually accommodates tools for different operations like

    drilling ,counter sinking etc

    Capstan lathe

    These are similar to turret lathe and incorporate capstan slide which moves on a clamped in any

    position.It is the best suited for the large scale production of small parts because of its light

    weight and short stroke of capstan slide

  • SLOTTER MACHINE

    Slotter machine is also called as vertical shaper machine .the difference being that the ram is in

    vertical direction instead of horizontal position.Also the table or bed is mounted on a heavy base

    and provided with mechanism that make possible forward backward and side to side movement

    . it also has adjusted head mechanism .

    Advantages of vertical shaper or slotter machine :-

    1. Setting of the job is more convenient because it is easier to see, align, measure, clamp

    2. Press generated by the cutting stroke is better supported by the table bed

    3. Circular and hollow jobs can be worked upon

    4. Ram of vertical shaper can be adjusted up to 10 degrees.

    Main functions of slotting machine :-

    Internal key ways

    Tapered key ways

    Slots

    Centric slots

    Internal gear

    SHAPER MACHINE

    Shaping machine is generally called as shaper. Shaper is being used for both

    production and tool room work. The shaper can machine a flat surface on a

    horizontal , vertical , angular plane. On this tyoe of machine ,many types of work pieces can be

    machined depending upon the tools used and the manner of

    adjusting the various parts of the machine . Size of the shaper is determined by

  • the largest sized cube that can be machined on it. Working principal is quick

    return mechanism and forward stroke is cutting stroke and backward is idle

    stroke.

    Difference in shaper and lathe machine :-

    In shaper straight cutting is done where as in lathe circular cutting is done In shaping machine

    the tool moves in reciprocator fashion whereas in the lathe machine the tool remains stationary

    and the work piece moves.

    Parts of Shaping Machine are :-

    BASE : it is the reservoir for supply of oil circulated to the moving parts of machine

    ARPON: it supports the table

    RAM: It is the main moving part of the shaper machine. It holds and

    drives the cutting tool back and forth across the work .

    This is attached to rocker arm which is given an oscillating motion by

    turning of a large driving gear .this also has an adjustable pin attached to

    driving gear which acts as a crank which determines the length of the ram

    TOOL HEAD: it holds the cutting tool. it is attached to the front of the

    ram. Tool post is fastened to the clapper box

    Main functions of the shaping machine :

    Making slots

    Tapered slots

    external key on shaft

    Hexagonal nut heads

    Square nut head

  • MILLING MACHINE

    Milling machine is one of the most versatile and widely used machine tool for

    tool room and production purposes.

    Milling is the process of removal of the material with the help rotating multiple cutting tools

    called as milling cutter. In general the work piece is fed into the rotating milling cutter

    Parts of the milling machine :-

    Column

    Knee

    Saddle

    Table

    Spindle

    Over arm

    COULMN: It includes the base which I the main casting which supports the other parts of

    machine . The front of the column, the column face is machined to provide an accurate guide for

    the vertical travel of the knee

    KNEE: It supports the saddle .feed change gearing is enclosed within the

    knee.knee can be raised or lowered on the column face.it is supported and can

    be adjusted with a elevating screw.

    SADDLE: It supports the table . It is supported by the surfaces of the knee

    TABLE: It holds the workpiece. It has T-slots and is used to hold the

    jods .bolts fit loosely in the T-slots and are used to clamp the vice.

    SPINDLE: it holds and diverts various cutting tools.it has the shaft mounted

    on the bearing supported by the column.

  • OVER ARM: it is mounted on the top of the column. It is guided by the

    machined dovetail surfaces

    GRINDING MACHINE

    Grinding is the process of finishing surface by means of revolving abrasive wheel

    In order to finish the job piece efficiently one must not only be able to operate

    The grinder but also understand abrasive and grinding wheels ,their shapes and

    sizes for different type of work

    ABRASIVE: An abrasive is any material that can wear material softer than

    itself .sand and sandstone are perhaps the oldest abrasives known to mankind.

    Abrasives can be natural or manmade.

    Natural Abrasives: Emergy and corundum are two commonly used in the

    Industry to sharpen tool edge They occur as a miner deposit in the earth crust .Aluminum oxide

    is the best suited for grinding material that has high tensile strength such as high spee steel and

    high carbon steel.

    Man made Abrasives: these are better than natural ones because in these

    purity and grain size can be controlled.

    GRINDING WHEELS: Grinding wheel are formed by using a suitable material to cement, bond,

    abrasives grains together in the desired shape and size. Hardness of the wheel is dependent upon

    the amount and kind of binding

    material being used. Hardness of wheel is always understood by means of

    strength of bond.

  • TYPES OF GRINDING MACHINES

    Surface Grinder

    Cylindrical Grinder

    Internal Grinder

    Thread Grinder

    SURFACE GRINDER: Surface grinding is the process of producing a finished flat surfaces by

    means of grinding machine employing revolving abrasive wheel. Surface grinder machine

    consist of spindle mounting a grinding wheel and table or magnetic chuck for holding the work

    piece

    Uses of Abrasive Grinding : -

    Sharpening cutting

    Snagging

    Finishing

    PLANNER MACHINE

    Planer is one of the basic machine tools used in machine shop. Main function is

    to produce flat surface on piece of work. The main difference between planer

    and shaper is that in planer machine the work piece moves In reciprocating

    motion while tool is fixed where as in the shaper machine it is other way

    round. It can be distinguished in two either Hydraulic or Mechanical.

    Main parts of Planer Machine are:

    Bed

    Table

  • Saddle

    Tool head

    FABRICATION The process of joining metals or non-metal to from an object which has specific

    shape .This process is known as fabrication. Different types of machines and welding are used in

    the fabrication process or to fabricate an object.

    THE WORKDONE AT THE SHOP ARE CLASSIFIED AS :

    1) Metal cutting method :-

    Oxy fuel gas cutting

    Plasma cutting

    2) Metal joining method :-

    Oxy-acetylene welding

    Arc welding

    Tungsten inert gas welding

    Oxy-acetylene Gas welding:

    This process is particularly suitable for joining metal sheet and plates and having thickness 2

    to 50mm.

    The filler metal is the addition metal, which is added to weld in the form of welding rod.

    The composition of the filler rod is usually the same or nearly the same as that of the part

    being welded.

    To remove the impurities and oxides present on the metal to be joined and to obtain stationary

    bond flux is always implied during the welding expect sheet.

    Various gas combustions can be used for producing a hot flame for welding metals. Common

    mixture of gases oxygen and other fuel gases.

  • The oxy-acetyl welding mixture is used to a much greater extent than other in the welding

    industry.

    The temperature of this welding flame in its hottest region is about 3200 C.

    CaC2 + 2H2O C2H2 + Ca(OH)2

    ARC WELDING METHODS

    Metal arc welding: In the arc welding metal rod is used as an electrode,

    while the work being welded is used as another electrode. The temperature

    produced is about 2400C and 2600C on the ve and +ve electrode

    respectively. During the welding operations, this metal electrode is melted

    by the heat of the arc and is fused with the base metal, thus forming a

    solid union after the metal has been cooled. Both AC and DC can be

    used .Adjusting the machine to correct amperage, which is determined by

    then size of the rode to be used ,start the welding operations. The correct

    welding speed is important.

    SPECIFICATION OF ELECTRODES:

    Where

    1. E is used for covered electrode that is for coated electrode.

    2. Next two XX multiplies with 1000spin shows the tensile strength.

    3. Next X shows the position of joint to be welded in current condition i.e. it may horizontal,

    vertical or inclined

    4. Last X shows the types of coating.