4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS IN THE STATES OF PUNJAB , HARYANA& HIMACHAL PRADESH ON BOT BASIS (PPP) UNDER NHDP - PHASE-IIIA Independent Engineer TPF GETINSA EUROESTUDIOS S.L. in association with Segmental Consulting & Infrastructure Advisory (P) Ltd. Executive Summary MONTHLY PROGRESS REPORT No. 24 FOR THE MONTH OF NOVEMBER-2017

Upload: duongkhanh

Post on 26-Mar-2018

247 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

IN THE STATES OF PUNJAB , HARYANA& HIMACHAL PRADESHON BOT BASIS (PPP) UNDER NHDP - PHASE-IIIA

Independent Engineer

TPF GETINSA EUROESTUDIOS S.L.

in association with Segmental Consulting & Infrastructure Advisory (P) Ltd.

Executive Summary

MONTHLY PROGRESS REPORT No. 24FOR THE MONTH OF NOVEMBER-2017

Page 2: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

INDEX

S. No. Contents Page Nos.

1 CHAPTER – 1

Location Map 1

Schematic Layout 2

Project Background 3

Project Details 4-5

Executive Summary 6-8

I.E. Staff Mobilization 9

2 CHAPTER – 2

Maintenance Issues 10

Emergency Services Locations 11

IC’s Advice/Instructions 12

3 CHAPTER –3Monthly Joint Inspection (Appendix -A) 13-14

Summary of Compliance of O&M observations 15

Status of Encroachments 16

Accident Report 17

4 CHAPTER-4Month wise Toll Collection (Appendix – B) 18

Tollable Traffic Volume (Appendix-C) 19

Composition of Tollable Traffic (Appendix-D) 20

Total Traffic Volume (Appendix-E) 21

Composition of Total Traffic (Appendix-F) 22

Comparison of Tollable Traffic Volume for Last Two Months (Appendix-G)

23

Comparison of Total Traffic Volume for Last Two Months (Appendix-H)

24

Toll Transactions ( by Toll Category) 25

Page 3: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

CHAPTER–1

1Location Map

Page 4: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

2

Page 5: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

Schematic Layout

3

Page 6: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

PROJECT BACKGROUND

The Govt. of India (GOI) through Ministry of Road Transport & Highways (MoRT&H) is contemplating to enhance the traffic capacity and safety for efficient transshipment of goods as well as passenger traffic on the heavily trafficked National Highways. GOI has entrusted National Highways Authority India (NHAI) with the responsibility of developing and maintaining the entrusted sections of the National Highways network.

National Highway No - 5 originates from Ferozepur in Punjab, passes through hinter land of Punjab including industrial township of Ludhiana and ends at China Border in Himachal Pradesh. This is one of the most important roads connecting Shimla (Capital of Himachal Pradesh) with Chandigarh (Capital of Haryana and Punjab) and New Delhi (Capital of India).

The Project road "Zirakpur to Parwanoo including Pinjore-Kalka-Parwanoo Bypass” is a section of NH-5 starting at km 39.960 (just after the Yadvendra Bridge at Zirakpur in State of Punjab) and terminating at the end of Pinjore- Kalka - Parwanoo Bypass at Km 67.550. The total length of Project Highway is 27.590 Km. On its way, it passes through the township of Zirakpur and Panchkula with developing commercial activity. Project road follows the existing alignment of NH-5 from Km 39.960 to Km 57.400. Thereafter, it follows a new alignment for bypass of Pinjore - Kalka - Parwanoo to meet NH - 5 again at Km 67.550 (just short of TTR).

Zirakpur - Pinjore Section had crossed the level of service (LOS) 'E'. The condition of the existing pavement was poor to good. Generally the existing road was having 2-lane with paved shoulders. Thus, in order to provide a better 1evel of service to the vehicular traffic, it was decided to augment the capacity of Zirakpur to Parwanoo section of NH-5 from Km 39.960 (end of Ambala - Zirakpur section) to Km 67.550 by widening the existing 2 lane road to 4 lane dual carriage way facility on Build, Operate and Transfer (BOT) basis.

4

Page 7: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

PROJECT DETAILS

1 Name of Project

4/6 laning of Zirakpur-Parwanoo section of NH-5 including Pinjore-Kalka-Parwanoo ByPass on BOT basis under NHDP- Phase III A in the state of Punjab, Haryana & Himachal Pradesh

2 Package Number (NHDPIIIA/BOTII/VI/002)

3 Consultancy Package No.NHAI/RO/CHD/11077/IE APPOINTMENT/34

4 Type of Project BOT(PPP)

5 Estimated Project Cost295 Crores + 117 Crores (Grant) = 412 Crores

6 Client National Highways Authority of India

7 Concessionaire Himalayan Expressway Limited

8 Independent Engineer Getinsa-Payma, S.L. in association withSegmental Consulting & Infrastructure (P) Ltd.

9 Date of Concession Agreement 31st August 200710 Development Period 180 Calendar days11 Appointed Date 28th February 200812 Concession Period 20 years13 Construction 30 months15 Start of Concession Period 28th February 200816 Commencement of services of

IC (O&M period)December 6, 2015

17 Commencement of Construction

March 1, 2008

18 Financial Close June 9, 200819 Construction completion date March 21, 201220 PCC March 22, 201221 Commencement of Toll

OperationApril 6, 2012

22 End of Concession Period February 28, 2028 + 374 days i.e. upto 08 March 2029

23 Project length 27.590 Km25 Pavement 4 lane divided carriageway with raised

median26 Carriageway width 7.25m wide either side

Page 8: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

27 Paved shoulder 1.5m wide either side (in plain section only)

28 Hard earthen shoulder 1.0 m29 Median width 4.5m in rural section and 1.5m in urban

section.30 MCW Composition

GSB 200 mm WMM 250 mm DBM 150 mm BC 50 mm

31 Service road Composition GSB 200 mm WMM 250 mm DBM 85 mm BC 40 mm

32 Service Road Width 5.5/7.0 m33 Major Intersections/ Junctions 434 Bridges Major bridge – 1 , Minor bridges -235 Viaducts 736 ROB 137 Flyovers 238 Culverts Pipe culverts – 25 , Box culverts - 2339 VUPs 740 PUPs 341 Bus Bays 1942 Truck Lay Byes 443 Toll Plaza 1 at Ch. 51.400

6

Page 9: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

EXECUTIVE SUMMARY

This executive summary presents the activities of the Concessionaire and the Independent Consultant during the month November 2017. Matters related to the implementation of the Project are as under:

1.Major Events: Nil

2. ROW Acquisition and Handling Over:

Concessionaire has been handed over 100% land required for the project. It is obligatory on part of the Concessionaire to keep ROW free from encroachments.

Concessionaire has reported that locals have illegally constructed structures within ROW from Ch. 60.800 to Ch. 61.400 (RHS). Concessionaire is obliged to protect land within ROW and has been advised to remove these encroachments with the help from Police / District administration if need be, at the earliest.

ROW demarcation at Maheshpur market from Ch. 44.200 to 44.280 (RHS) still pending. Same is to be expedited.

3.Safety Measures:

Maintenance of pavement, road marking, kerb painting, blinkers is not being done by the Concessionaire in a satisfactory manner. The state of street lights is given below-

Date of Inspection

ChainageNo. of lights not working

No. of High Masts not working

From TO

20-11-2017

39.960 42.300 5 0

42.300 47.200 4 0

47.200 49.000 1 0

49.000 51.000 0 0

51.000 52.000 0 0

57.400 57.550 0 0

67.300 67.550 2 0Total 12 0

7

Page 10: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

4. Highway Cleaning The cleaning of Highway is to be carried out regularly and efforts are lacking in this respect. Clogged drains, open channels, parking areas, road signs, road furniture, lay byes etc require regular cleaning and maintenance. Litters and debris are to be cleaned on ongoing basis from the highway. This activity is not up to the mark and more resources are needed to be deployed. The water kiosks and litter bins have not been placed at way side amenities and highway as per provisions of CA.

5. Pavement Shoulders:-Earthen Shoulders need maintenance all along the highway.

6. Pavement Condition and Periodic Maintenance:-The pavement condition of MCW and Service Road has deteriorated due to non-maintenance. Large alligator cracks have developed on the pavement. Pot holes have also been noticed on MCW and Service Road. Depressions due to settlement of the Pavement exist at a number of locations. The poor condition of the pavement does not meet the minimum acceptable intervention levels given in table L-2 of Schedule- “L”. The project Highway needs immediate overlay as per clause 3.3.7(i) of Schedule-“L”. As per CA, periodic maintenance of the highway is to be done at least once in five years commencing form the COD. Hence the overlay was to be completed on or before 21 March 2017. The Concessionaire has not completed this activity. Damages from 22-3-2017 onward up to 31 October 2017 for the delay in completing periodic maintenance have already been recommended as per CA provisions.

7. Structural Strength of Pavement. The results of BBD test conducted from 07 -01- 2016 to 21-01-2016 indicate that the characteristic deflection has exceeded permissible limit in a fairly large number of stretches. These have not been treated with appropriately designed overlay as per IRC: 81. Kindly also refer to IC’s letter No. GP-SCIA/IE/ZP/HEL/51 dated 20-4-2017. The damages have already been intimated to NHAI vide IC’s letter No GP-SCIA/IE/ZP/NHAI/196 dated 01-6-2017.

8. BBD Test. As per clause 3.4.2.3 of Schedule “L” of CA, BBD test is to be carried out once a year. The last test was carried out during Jan 2016. The BBD Test for the year 2016-2017 has not been done. The damages up to 31-10-2017 have already been intimated to NHAI.

9.Encroachments. It is observed that encroachments continue to exist in the ROW. No appreciable efforts are visible for their removal.

10. Meetings & Site Visits - Nil

11. Incomplete Items of Punch List . 02 Nos. Septic tanks and Bitna service Road have not been completed till date. Service road work has been taken up during last week of August 2017 . The same is in progress. Till the end of current month, DBM has been completed from Ch.60.140 to Ch. 61.045. The work was at stand still from 07 Nov 2017 to 28-11-2017 . BC work was done on 29-11-2017 and 30-11-2017 from Ch.60.140 to 60.750 .The service road is required to be constructed from Ch. 60.140 to Ch. 61.440.

8

Page 11: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

12. Construction of Toilets at Toll Plaza.

As per NHAI policy guidelines, separate toilets for Ladies and Gents are to be constructed at the Toll Plaza in both directions .i.e. LHS and RHS. Change of Scope Order has been issued by NHAI vide letter NoNHAI/PIU/CHD/11107/Z-P/Conc./1242 dated 20-11-2017.

13.COS Order for Implementation of ETC Hybrid Lanes.

The COS proposal for Implementation of ETC Hybrid Lanes in all the lanes of toll plaza has been submitted to NHAI vide IC’s letter No.GP-SCIA/IE/ZP/NHAI/250 dared 18-10-2017. The same is awaited.

14.COS Order for Construction of VUP at Amravati Enclave (Ch. 63.550).

COS Order for construction of VUP at Amravati Enclave (Ch. 63.550) has been approved and intimated to the Concessionaire vide NHAI letter No.NHAI/PIU/CHD/11107/ Z-P/Conc./1238 dated 08-11-2017. Concessionaire is advised to take construction work at the earliest.

15.. Repair to HUDA Water Pipe Line at Ch. 44.450

HUDA has completed the repairs of leaking water line from underneath the structure. The pipe line has now been shifted and laid over surface in the RE wall portion.

16.Road Safety Training.

A workshop on the road safety was organized by NHAI on 10 th and 11th Nov 2017. The same was attended by representatives IC and Concessionaire.

17. Overlay Work as Part of Periodic Maintenance.

The Concessionaire carried out the overlay of the service road from 23 Nov 2017 to 27-11-2017. Till the end of the reporting month, overlay has been completed over following stretches-

a. Ch 42.350 (LHS) to 42.720 (LHS

b. Ch. 43.600 (RHS) to 43.950 (RHS). BC work from 43.580 to 43.600 is defective and not approved.This has been shown to the Concessionaire.

18. Stretghening of Pavement.The Concessionaire has been instructed to provide BC overlay on the service road from ch.45. 640 (LHS) to ch.47.150 (LHS) since this stretch is showing visible signs of distress.The Concessionaire is further advised to strengthen the MCW and Service road in the stretches where BBD results are unsatisfactory.

9

Page 12: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

STAFF MOBILIZATION : IC

S. No. Designation Name Date of Joining/ Mobilization

KEY PROFESSIONAL STAFF1 Team Leader cum Senior

Highway EngineerCol (Retd) Parikshit Sharma

07.12.2015

2 Pavement Specialist S L Mahipal 15.12.20153 Quality-cum-Material

ExpertVishal Koul 17-12-2015

4 Bridge/Structural Engineer Arun Kumar Pandey 16-04-20165 Road Safety Expert Dr. M.M. Krishna 19-01-20166 Bharat Goel Toll/ HTMS Expert 30-12-2015

SUB-PROFESSIONAL STAFF6 Assistant Highway

Maintenance EngineerVinod Kumar Pandey 28-12-2015

7 Survey Engineer Ambresh Tripathi8 Horticulture Expert Kuldeep Kumar

Sharma28-12-2015

9 Quantity surveyor Vidhu Bhushan Sundaray

30-5-2016

SUPPORT STAFF10 Lab. Assistant Guru Dutt 04-10-201711 Technical Supervisor

(construction/maintenance)

Prasant Rana 25-05-2016

12 Technical Supervisor(construction/maintenance)

Manish Rana 20-06-2016

13 Office Manager/Accountant-cum-Cashier

Ashok Kumar 07-12-2015

14 Steno-cum-computer Operator

Gurpreet Singh 16-12-2015

15 Office Boy Rahul Kashyap 05-08-2017

Page 13: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

CHAPTER – 2

Page 14: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

10

Maintenance Issues

Routine Maintenance:

Routine maintenance of the highway is not being carried out to conform to standards and specifications as per Concession Agreement.

Pavement Marking

Pavement marking is lacking on the MCW and service road. Marking is to be provided for lanes, pedestrian crossing, bus stop and intersections etc. as per the guide lines given in IRC: 35-1997. Service road marking is in very poor condition. The same has not been done till now despite repeated instructions.

Periodic Maintenance: As per the Concession Agreement, the periodic maintenance of the project road was due to be completed by the end of 5 th year from COD, i.e. by 22 March 2017. Concessionaire has not completed the work so far. Damages for the delay have been recommended up to 31-10-2017.

Page 15: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

11

EMERGENCY SERVICE LOCATIONS ALONG THE PROJECT HIGHWAY

S. No. Description Contact No.

A. Major Hospitals & Ambulance Services

1 Government Hospital, Sector-6 , Panchkula 01881 - 221141

2 108 Services 108

3 Government Hospital, Pinjore 01881-225537

4 Government Hospital, Kalka 01881-222225

B. Police Station

1 Chandimandir 0172-6532990

2 Pinjore 0173-3231403

3 Kalka 0173-32208754 SHO,Sector-20 , Panchkula 81466300165 SHO , Zirakpur 9592916063

C. Fire Station

1 Sector-5 Panchkula 101

D. Toll Plaza Vehicles

1 Control Room 8558860502/98889877772 Ambulance3 Patrol Vehicle 8558860508

4 Crane

Page 16: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

12

Independent Consultant’s Advice/Instructions

1. The activity of removal of wild grass and vegetation from the median is being carried out. The same must be extended to road side in the ROW.

2. All signage should be cleaned regularly.

3. Trimming of median plantation should be done at regular intervals. Missing/dead plants should be replaced with plants other than Kaner as its use has been prohibited.

4. Concessionaire is advised to undertake speedy drive in liaison with District Administration and police authorities to remove encroachments from the ROW.

5. Cleaning of MCW, Service road, truck lay byes and bus bays to be done regularly.

6. Toilets at both trucks lay bays at Haryana / Punjab border should be made functional on priority. This has not been done despite of repeated instructions.

7. High masts and street Lights should be checked daily and defects ,if any, should be rectified immediately and timings of switching on/off be adjusted on weekly basis as per sun rise / sun set timings. This assumes greater importance during winter season when dense foggy conditions prevail and visibility is restricted.

8. NHAI circular on Swatchh Bharat Abhiyan should be complied in letter and spirit.

9. Periodic maintenance must be completed expeditiously as the same is now under damages.

10. BBD test is overdue and under default. The same should be conducted as per provisions of Concession Agreement.

Page 17: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

CHAPTER – 3

Page 18: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

13

Monthly Inspection

A joint inspection was carried out by IC and the Concessionaire on 15 November 2017. The inspection report is appended as Appx ‘A’.

Appendix-A

No: GP-SCIA/IE/ZP/HEL/ Dated: 16-11-2017

To M/s. Himalayan Expressway LimitedToll Plaza, Chandimandir, Kalka-Shimla RoadPanchkula (Haryana)

Sub: Independent Engineer Services during operation & Maintenance period for “4/6 laned Zirakpur - Parwanoo section from KM 39.960 to KM 67.550 of NH-22 including Pinjore – Kalka – Parwanoo bypass in the states of Punjab, Haryana & Himachal Pradesh under NHDP - Phase-IIIA on BOT Basis. Monthly Joint Inspection of Project Road for November 2017.

Dear Sir,

Monthly joint inspection of the project road was carried out on 15 November 2017 from 11.00 A.M. onward by the undersigned along with Lt Col KJS Sandhu (Retd.). The compliance of observations of inspection report for October 2017 was also checked. The issues observed during the inspection are given in succeeding paragraphs.

1. Pavement condition. The pavement condition of MCW and Service Road has further deteriorated. Large number of alligator cracks and depressions has developed on the

pavement. Depressions due to settlement of the pavement exist at a number of locations. The poor condition of the pavement does not meet the minimum acceptable intervention levels given in table L-2 of Schedule- “L”. This is being observed and reported for the last many months. The project Highway needs immediate overlay as per clause 3.3.7(i) of Schedule-“L”. No action has been taken to rectify the defects as well as no overlay has been started.

2. Periodic Maintenance. Scheduled completion date of overlay as part of periodic maintenance has expired on 21-3-2017. The same has not yet been completed. Also, the road marking on the stretches treated with micro seal have not been done. Damages for the default are being levied from 22-3-2017 onward.

3. Bitna Service Road (Punch List Item). Progress is alarmingly slow. DBM has been done from Ch.60.140 to Ch. 61.045. No work has been done since 07 Nov 2017.

4. BBD Test. As per clause 3.4.2.3 of Schedule “L” of CA, BBD test is to be carried out once a year. The last test was carried out during Jan 2016. The BBD Test for the year

14

Page 19: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

2016-2017 has not been done by you. The damages have already been levied from 01- 04-2017 to 31 -10 -2017.

5. Encroachments. It is observed that encroachments continue to exist in the ROW. No appreciable efforts are visible for their removal. Please take actions in close liaison with distt. and civil police authorities.

6. Water Leakage under Service Road at Ch.44.494(RHS). Repair of leaking water pipeline under service road at ch.44.494 (RHS) has been commenced by HUDA. The work was in progress.

7. Median Maintenance. This is being done.

8. Road Safety Measures. In view of the oncoming foggy conditions, all necessary road safety measures must be completed immediately. Following need special attention of the Concessionaire –

(a) All street lights on MCW and Service Roads including High masts should be repaired and made functional.

(b) Road marking should be redone wherever it has faded or covered with micro-surfacing.

(c) Hazard markers should be repainted and missing ones re-erected.

(d) Missing cat eyes, sparkling studs and delineators are made good.

(e) Traffic signals and blinkers should always be in working condition.

(f) Speed breakers and Rumble strips be properly painted with thermo-plastic paint.

(g) Shoulders should be made good and kept obstruction free.

(h) Unauthorised road side parking of vehicles and vendor rehris should not be allowed.

It is advised to carry out rectification of above observations at the earliest as per CA provisions and submit compliance.

Thanking You Yours sincerely,Sd/-Col. Parikshit Sharma (Retd.)Team Leader

Cc:- Project Director NHAI, PIU Chandigarh -----For information please.

Page 20: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

15

Summary of Compliance to O&M Observations

Month Total No. of O&M

observations

No. of observations

cured

Balance O&M observations

yet to be cured

Remarks

October-2017 9 - 9

Novenber-2017 8 2 6

Page 21: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

16

STATUS OF ENCROACHMENTS - NH-5 (Zirakpur-Parwanoo section)Month: November 2017

Sr. No.

Ch. (RHS/LHS) Description of Encroachment Name of Encroacher Remarks

1

41+830 Sekhon Banquet

hall

LHSA Kiosk has been constructed within our ROW by an individual for general items.

------

2 44.200 RHS "Chardi Kalan" tyre puncture shop Sh. Bachna Ram Maheshpur market

3 44.230 RHS Extension of Shop in the ROW Raj Kumar Maheshpur market

4 44.200- 44.292 RHS Temporary sheds in

front of shops Various shop owners Maheshpur market

5 61.000 RHS Water Storage tank owned by M/s Lord Shiva Marble & Tiles ------

6 61.200 RHS Tea Stall -cum-Dhaba Sh. Sanju Sharma Dispute in ownership of land

7 61.220 RHS "Highway Punjabi Dhaba" Sh. Sanju Sharma Dispute in ownership of land

8 61.320 RHS Tea Stall -cum-Grocery Shop

Sh. Phool Chand Sharma

Dispute in ownership of land

9 61.330 RHS Sant Ram motatrsEngg. Workshop

Sh. Phool Chand Sharma

Dispute in ownership of land

10 62.850 LHS Unauthorised temporary Shed ------

11 62.900 LHSUnauthorized Liquor Shop owned by Bittu S/o Sh. Bhagar Singh R/O Village Paploa

Bittu S/o Sh. Bhagar Singh

12 63.190 RHS Residential House Sh. Raja Ram

13 63.170 RHS Residential House Sh. Kumar

14 63.130 RHS Residential House Achhru Ram

15 62.800 LHS Residential House Smt. Sandhya Devi

Page 22: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS
Page 23: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS
Page 24: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

CHAPTER – 4

18

Page 25: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

Month-wise Toll Collection for Financial Year 2017-18Appendix-B

Zirakpur - Parwanoo Section (NH-5)

Sr. No. Name of The Plaza Month of Collection Amount

1 Himalaya Expressway Ltd. April-17 32826747

2 Himalaya Expressway Ltd. May-1730580910

3 Himalaya Expressway Ltd. June-1734785260

4 Himalaya Expressway Ltd. July-1733579086

5 Himalaya Expressway Ltd. August-1733460147

6 Himalaya Expressway Ltd. September-1738252904

7 Himalaya Expressway Ltd. October-1736726413

8 Himalaya Expressway Ltd. November-1733408196

19

Appendix-C

Page 26: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

Tollable Traffic Volume for November 2017

Date Car/Jeep/Van LCV Bus /Truck MAV Total1-Nov-17 23505 2160 4296 1530 314912-Nov-17 23283 1967 4216 1537 310033-Nov-17 25365 1985 4341 1535 332264-Nov-17 27067 1836 3731 1426 340605-Nov-17 26769 1291 3084 1278 324226-Nov-17 24299 1639 3439 1422 307997-Nov-17 23494 1921 4265 1580 312608-Nov-17 23588 1971 4266 1494 313199-Nov-17 23065 1442 3283 1208 28998

10-Nov-17 25666 1803 3292 1305 3206611-Nov-17 28094 1984 4131 1337 3554612-Nov-17 27668 1356 2995 1224 3324313-Nov-17 25674 1647 3509 1286 3211614-Nov-17 24962 1995 4199 1567 3272315-Nov-17 25196 1873 4161 1439 3266916-Nov-17 24430 2015 3957 1561 3196317-Nov-17 25427 2009 4329 1566 3333118-Nov-17 27976 2189 4045 1585 3579519-Nov-17 27655 1482 3292 1360 3378920-Nov-17 25155 1712 3661 1441 3196921-Nov-17 24581 2039 4287 1549 3245622-Nov-17 25476 2153 4359 1603 3359123-Nov-17 25827 2019 4371 1433 3365024-Nov-17 26890 2088 4200 1584 3476225-Nov-17 28254 2011 4044 1517 3582626-Nov-17 27466 1392 3274 1360 3349227-Nov-17 25268 1648 3690 1483 3208928-Nov-17 25352 2043 4304 1554 3325329-Nov-17 25834 2067 4322 1576 3379930-Nov-17 26722 2083 4335 1488 34628

Total 770008 55820 117678 43828 987334Avg. Daily

Traffic 25667 1861 3923 1461 32911PCU 25667 2791 11768 6574 46800

20

Appendix-D

Composition of Tollable Traffic for November 2017

Page 27: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

Zirakpur-Parwanoo Section (NH-5)

Car/Jeep LCV Bus/Truck MAV770008 55820 117678 43828

Car/Jeep78%

LCV6%

Bus/Truck12%

MAV4%

Car/JeepLCVBus/TruckMAV

21

Appendix-E

Total Traffic Volume for November 2017

Page 28: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

Zirakpur-Parwanoo Section (NH-5)

Date Car/Jeep LCV Bus/Truck MAV Total1-Nov-17 24147 2345 4587 1647 327262-Nov-17 23946 2152 4487 1635 322203-Nov-17 26123 2166 4597 1678 345644-Nov-17 27920 1984 3888 1549 353415-Nov-17 27564 1443 3143 1403 335536-Nov-17 25008 1819 3661 1551 320397-Nov-17 24142 2069 4542 1644 323978-Nov-17 24259 2124 4510 1559 324529-Nov-17 23666 1583 3470 1260 29979

10-Nov-17 26312 1961 3533 1366 3317211-Nov-17 28816 2116 4316 1412 3666012-Nov-17 28484 1483 3131 1281 3437913-Nov-17 26324 1784 3708 1333 3314914-Nov-17 25673 2128 4419 1654 3387415-Nov-17 25898 2020 4415 1520 3385316-Nov-17 25046 2139 4202 1618 3300517-Nov-17 26038 2141 4551 1647 3437718-Nov-17 28727 2337 4296 1658 3701819-Nov-17 28424 1610 3372 1417 3482320-Nov-17 25776 1853 3951 1505 3308521-Nov-17 25189 2151 4504 1624 3346822-Nov-17 26097 2292 4572 1681 3464223-Nov-17 26494 2124 4592 1494 3470424-Nov-17 27565 2207 4394 1679 3584525-Nov-17 28990 2129 4284 1609 3701226-Nov-17 28235 1526 3349 1421 3453127-Nov-17 25876 1775 3938 1575 3316428-Nov-17 25987 2157 4533 1630 3430729-Nov-17 26482 2182 4542 1656 3486230-Nov-17 27461 2208 4585 1581 35835

Total 790669 60008 124072 46287 1021036Avg. Daily

Traffic 26356 2000 4136 1543 34035PCU 26356 3000 12407 6943 48706

22

Appendix-F

Composition of Total Traffic for November 2017

Page 29: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

Zirakpur-Parwanoo Section (NH-5)

Car/Jeep LCV Bus/Truck MAV790669 60008 124072 46287

Car/Jeep77%

LCV7%

Bus/Truck12%

MAV5%

Car/JeepLCVBus/TruckMAV

23

Appendix - G

Page 30: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

Comparison of Tollable Traffic Volume for Last Two MonthsZirakpur - Parwanoo Section (NH-5)

Date Car/Jeep LCV Bus/truck MAV

October-17 801996 61033 122113 48765

November-17 770008 55820 117678 43828

Car/Jeep LCV Bus/truck MAV0

100000

200000

300000

400000

500000

600000

700000

800000

900000

24 Appendix - H

Comparison of Total Traffic Volume for Last Two Months

Page 31: nhai.org.innhai.org.in/spw/IEReport/MPR Nov 2017.docx · Web view4 /6 LANING OF ZIRAKPUR-PARWANOO SECTION OF NH-5 FROM KM 39.960 to KM 67.550 INCLUDING PINJORE-KALKA-PARWANOO BYPASS

Zirakpur - Parwanoo Section (NH-5)

Date Car/Jeep LCV Bus/truck MAVOctober-17 825041 70438 128888 51575

November-17 790669 60008 124072 46287

Car/Jeep LCV Bus/truck MAV0

100000

200000

300000

400000

500000

600000

700000

800000