no. date by description revisions 8/18/2014...contents . executive summary 1 . section 1.0 – codes...
TRANSCRIPT
Project80' Wide x 70' Long Century Tent with 30' Middle Bays10' Side Poles and 30' Center PolesB3-80M
Prepared ForAnchor Industries Inc.1100 Burch Dr.Evansville, IN 47725 2 8/13/14 JAV REV HGHT/DL
1 8/11/14 JAV REV LOAD
No. Date By Description
Prepared ByHodge Structural Engineers22 Chestnut StreetEvansville, IN 47713(812) 422-2558 – phone(812) 422-3337 - faxHSE No.: 14061Date: 8-1-14
HODGE STRUCTURAL ENGINEERS22 Chestnut Street Evansville, Indiana 47713 tel: 812.422.2558 fax: 812.422.3337 www.hodgedesign.com
REVISIONS
Contents
Executive Summary 1
Section 1.0 – Codes and Design Criteria 2
1.1 – Design Codes 2
1.2 – Design Criteria 2
Section 2.0 – Summary of Maximum Loads and Components 2
2.1 – Anchor Design Load 2
2.2 – Guy Wire Design Load 2
2.3 – Side Poles Design Load 2
2.4 – Center Pole Design Load 2
Section 3.0 – References and Warnings 3
3.1 – Calculation Reference 3
3.2 – Warnings 3
Section 4.0 – Structural Calculations 3
Executive Summary
These calculations were performed for Anchor Industries, Inc. for their 80 foot wide x 70 foot long Century Tent product with 30’ Middle Bays (10’ Side Poles and 30’ Center Poles).
All data and information contained in or disclosed by this document is confidential and proprietary information of Anchor Industries, Inc and Hodge Structural Engineers and all rights therein are expressly reserved. By accepting this material the recipient agrees that this material and the information contained therein is held in confidence and in trust will not be used, copied, reproduced in the whole or in part, nor its contents revealed in any manner to others except to meet the specific purpose for which it was delivered.
Reference the Anchor Industries Inc. installation instructions for this product. See www.anchorinc.com for instructions.
Section 1.0 – Codes and Design Criteria
1.1 – Design Codes
a – ASCE 7-10: Minimum Design Loads for Buildings and Other Structures
b – International Building Code (IBC) 2012
1.2 – Design Criteria
a – Temporary Structure (Intended for use for time interval not to exceed 180 days) b – Return Period is 2.5 years c – 50-Year Return Non-Hurricane Wind Speed of 115 mph per ASCE 7-10 reduced to 80.5 mph based on Return Period of 2.5 years d – Wind Exposure C per ASCE 7-10 e – Open Structure (ASCE 7-10)
Section 2.0 – Summary of Maximum Loads and Components
2.1 – Anchor Design Load: The maximum anchor design load is 7,185 lbs. A safety factor of two (2) is recommended on the anchor capacity.
2.2 – Guy Wire Design Load: All guy wires must have a minimum working load of 21,555 lbs (safety factor of three (3) included).
2.3 – Side Pole Design Load: The maximum side pole design load is 4,931 lbs.
a) 2 1/2” Sch. 40, 6061-T6 Aluminum Pipe has an allowable load of 5,417 lbs.
2.4 – Center Pole Design Load: The maximum center pole design load is 13,533 lbs.
a) 7” Fluted, 6061-T6 Aluminum Pipe has an allowable load of 15,111 lbs.
Section 3.0 – References and Warnings
3.1 – Reference Structural Calculations (Section 4 of this report) by Hodge Structural Engineers.
3.2 – Warnings: This structure is to be dismantled if winds in excess of 70 mph are forecasted during the temporary use of the structure.
Section 4.0 – Structural Calculations
Alum. pole allow. load chart
Size 1 1/2" OD 3" OD 1 1/2" 2" 2 1/2" 10 Ga Purch 103 schd. 40 schd. 40 schd. 40(0.134) (0.070) (0.145) (0.154) (0.203)
Pole Length (in inches) 120Pole Outside Dia. (in inches) 1.5 3 1.9 2.375 2.875Pole Inside Dia. (in inches) 1.232 2.839 1.61 2.067 2.469Safety factor for Wilkie Eng. Only. 1.95 1.95 2.95 1.95 1.95
Radius of gyration (calulated) 0.485 0.880 0.623 0.787 0.947Cross sectional area (calulated) 0.575 0.986 0.799 1.075 1.704Slenderness Factor 247.3 136.4 192.7 152.5 126.7
FTL Fomula (kips) (calulated) 0.480 2.704 1.098 2.358 5.417from Alum. Asso.
Wilkie Eng. (kips) (calulated) 0.481 2.711 0.727 2.363 5.430from UBC alum.guide lines.
Tube
Page 1
Alum. pole allow. load chart
3 1/2"Flt 3 1/2"KF 3" 3 1/2" 4" 5" 6" Flute 6" 08-476-3 08-476-4 schd. 40 schd. 40 schd. 40 schd. 40 Purch schd. 40(0.085) (0.080) (0.216) (0.226) (0.237) (0.258) (0.220) (.280)
3.488 3.488 3.5 4 4.5 5.563 6.225 6.6253.389 3.389 3.068 3.548 4.026 5.047 5.708 6.0651.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95
1.197 1.054 1.164 1.337 1.510 1.878 2.106 2.2450.921 1.523 2.228 2.680 3.174 4.300 4.164 5.581100.3 113.9 103.1 89.8 79.5 63.9 57.0 53.4
4.674 5.992 10.686 16.957 25.615 12.148 13.021 13.466
4.685 6.006 10.711 16.996 25.675 53.825 65.562 99.904
Pipe
Page 2
Alum. pole allow. load chart
7" Flute 8" 8" 10" 12" Purch 91 schd. 40 schd. 80 schd. 40 schd. 40(0.270) (.322) (.500) (0.365) (0.406)
7.435 8.625 8.625 10.75 12.756.832 7.981 7.625 10.02 121.95 1.95 1.95 1.95 1.95
2.506 2.938 2.878 3.674 4.3776.114 8.399 12.763 11.908 14.57947.9 40.8 41.7 32.7 27.4
14.167 15.053 14.946 16.085 16.746
136.319 257.334 375.289 570.601 991.629
Page 3
Alum. pole allow. load chart
Size 1 1/2" OD 3" OD 1 1/2" 2" 2 1/2" 10 Ga Purch 103 schd. 40 schd. 40 schd. 40(0.134) (0.070) (0.145) (0.154) (0.203)
Pole Length (in inches) 360Pole Outside Dia. (in inches) 1.5 3 1.9 2.375 2.875Pole Inside Dia. (in inches) 1.232 2.839 1.61 2.067 2.469Safety factor for Wilkie Eng. Only. 1.95 1.95 2.95 1.95 1.95
Radius of gyration (calulated) 0.485 0.880 0.623 0.787 0.947Cross sectional area (calulated) 0.575 0.986 0.799 1.075 1.704Slenderness Factor 741.9 409.1 578.2 457.4 380.0
FTL Fomula (kips) (calulated) 0.053 0.300 0.122 0.262 0.602from Alum. Asso.
Wilkie Eng. (kips) (calulated) 0.053 0.301 0.081 0.263 0.603from UBC alum.guide lines.
Tube
Page 1
Alum. pole allow. load chart
3 1/2"Flt 3 1/2"KF 3" 3 1/2" 4" 5" 6" Flute 6" 08-476-3 08-476-4 schd. 40 schd. 40 schd. 40 schd. 40 Purch schd. 40(0.085) (0.080) (0.216) (0.226) (0.237) (0.258) (0.220) (.280)
3.488 3.488 3.5 4 4.5 5.563 6.225 6.6253.389 3.389 3.068 3.548 4.026 5.047 5.708 6.0651.95 1.95 1.95 1.95 1.95 1.95 1.95 1.95
1.197 1.054 1.164 1.337 1.510 1.878 2.106 2.2450.921 1.523 2.228 2.680 3.174 4.300 4.164 5.581300.8 341.6 309.4 269.3 238.5 191.7 170.9 160.3
0.519 0.666 1.187 1.884 2.846 5.967 7.268 11.074
0.521 0.667 1.190 1.888 2.853 5.981 7.285 11.100
Pipe
Page 2
Alum. pole allow. load chart
7" Flute 8" 8" 10" 12" Purch 91 schd. 40 schd. 80 schd. 40 schd. 40(0.270) (.322) (.500) (0.365) (0.406)
7.435 8.625 8.625 10.75 12.756.832 7.981 7.625 10.02 121.95 1.95 1.95 1.95 1.95
2.506 2.938 2.878 3.674 4.3776.114 8.399 12.763 11.908 14.579143.6 122.5 125.1 98.0 82.2
15.111 28.526 41.601 63.252 109.924
15.147 28.593 41.699 63.400 110.181
Page 3
Hodge Structural Engineers 80' Wide x 70'-0" Century Tent (30' Middle Bays)G. Hodge
≔ProjectID “ 80' Wide x 70'-0" Century Tent Design Check (30' Middle Bays)”
≔Location “KY”
≔Date “8-13-14”
≔Engineer “G. Hodge”
BASIC DESIGN ASSUMPTIONS:1. Consider only the fabric weight for dead load (no collateral loading considered)
2. Ignore snow load. The temporary structure is intended to stand for a time interval not to exceed 180 days. If snow with an accumulation in excess of the design live load is anticipated while the structure is in place, the structure will be dismantled.
3. Ignore rain loads - adequate drainage is provided.
4. Ignore atmospheric ice loading. The shape of the structure and the fabric material to not promote the accumulation of ice.
5. Ignore seismic effects. The extremely low mass of the structure is minimally affected by ground acceleration.
6. Use a reduced design wind speed. The temporary structure is intended for use during a time interval not to exceed 180 days. The structure will be dismantled if winds in excess of 70mph are forecast during the temporary use of the structure.
CODESASCE 7-10 Minimum Design Loads for Buildings and Other StructuresIBC 2012
Risk Category: II (ASCE 7-10, Table 1.5-1)
LOADS
≔D 0.2 psf Dead Load - Fabric Weight
≔LL 5 psf Live Load - ASCE 7-10 Table 4-1
≔S 0 psf Snow Load - Not considered. Temporary structure intended for use less than 180 days and will not be erected when heavy snow fall is predicted
≔I 0 psf Ice Load - Not considered. Temporary structure intended for use less than 180 days and will not be erected when icing loads may develop
Hodge Structural Engineers 80' Wide x 70'-0" Century Tent (30' Middle Bays)G. Hodge
≔R 0 psf Rain Load - Not considered. Drainage adequate so rain water cannot accumulate
≔E 0 psf Seismic Load - Not considered. Lightweight temporary structure not sensitive to ground motion.
WIND LOADS:
Determine the appropriate basic design wind speed (V).
≔T 2.5 yrs Return period
≔V50 115 mph 50-Year Return Non-Hurricane Wind Speed (ASCE 7-10 Figure 26.5-1B)
≔VT ⋅V50 (( +0.36 ⋅0.1 ln (( ⋅12 T)))) ASCE 7-10 Equation C26.5-2
=VT 80.5 Design Wind Speed based on 2.5 return period and temporary structure.
≔Kd 0.85 Wind directionality factor (ASCE 7-10 Table 26.6-1)
≔Kzt 1.0 Topographic Effect (ASCE 7-10 26.8.2)
≔Kz 0.90 Velocity Pressure Coefficient (at 20' - ASCE 7-10 Table 27.3-1)
≔G 0.85 Gust Factor (ASCE 7-10 26.9.1)
≔Exposure Exposure Category (ASCE 7-10 26.7.3)
≔Enclosure “Open” Enclosure Classification (ASCE 7-10 26.10)
≔GCpi 0 Internal Pressure Coefficient (ASCE 7-10 Table 26.11-1)
≔qz ⋅⋅⋅⋅0.00256 Kz Kzt Kd VT2 Velocity Pressure (ASCE 7-10 Eq. 27.3-1)
=qz 12.695 psf
Hodge Structural Engineers 80' Wide x 70'-0" Century Tent (30' Middle Bays)G. Hodge
APPLIED WIND LOADS (Refer to ASCE 7-10 Figures 27.4-5 and 27.4-7)
≔H 30 ft Overall height of the structure
≔H1 10 ft Pole Height
≔H2 20 ft Fabric Height
≔h 20 ft Mean roof height
≔Ω ⋅45 degrees Roof angle
≔S 10 ft Typical Pole Spacing
≔Ao 7.5 ft Typical Anchor Offset
≔L 70 ft Building Length
≔B 80 ft Building Width
≔θ ⋅36.87 Angle of Guys from Vertical
Hodge Structural Engineers 80' Wide x 70'-0" Century Tent (30' Middle Bays)G. Hodge
Figure 27.4-5 - Wind Perpendicular to "Ridge" - Clear Wind Flow
≔γ “0, 180 degrees”
Load Case A
≔CNLA 0.6 Net Pressure Coefficient - Leeward
≔CNWA 1.3 Net Pressure Coefficient - Windward
Load Case B
≔CNLB −0.6 Net Pressure Coefficient - Leeward
≔CNWB −0.2 Net Pressure Coefficient - Windward
Figure 27.4-7 - Wind Parallel to "Ridge" - Clear Wind Flow
≔γ “90 degrees”
Load Case AHorizontal Distance from Windward Edge, d
≔CN1A −0.8 ≤d h Net Pressure Coefficient
≔CN2A −0.6 ≤<h d 2 h Net Pressure Coefficient
≔CN3A −0.3 >d 2 h Net Pressure Coefficient
Load Case BHorizontal Distance from Windward Edge, d
≔CN1B 0.8 ≤d h Net Pressure Coefficient
≔CN2B 0.5 ≤<h d 2 h Net Pressure Coefficient
≔CN3B 0.3 >d 2 h Net Pressure Coefficient
Hodge Structural Engineers 80' Wide x 70'-0" Century Tent (30' Middle Bays)G. Hodge
≔γ “0, 180 degrees”
Load Case A
≔pLA ⋅⋅qz G CNLA Leeward Wind Pressure
=pLA 6.47 psf
≔pWA ⋅⋅qz G CNWA Windward Wind Pressure
=pWA 14.028 psf
≔FvA ⋅⋅⎛⎝ +⋅⎛⎝pWA⎞⎠ cos ((Ω)) ⋅pLA ((cos ((Ω))))⎞⎠ ―B
2L Vertical Wind Component
=FvA 40594 lb
≔FhA ⋅⋅⎛⎝ −⋅pWA sin ((Ω)) ⋅pLA sin ((Ω))⎞⎠ H2 B Horizontal Wind Component
=FhA 8546 lb
Load Case B
≔pL ⋅⋅qz G CNLB Leeward Wind Pressure
=pL −6.47 psf
≔pW ⋅⋅qz G CNWB Windward Wind Pressure
=pW −2.158 psf
≔FvB ⋅⋅⎛⎝ +⋅⎛⎝pW⎞⎠ cos ((Ω)) ⋅pL ((cos ((Ω))))⎞⎠ ―B
2L Vertical Wind Component
=FvB −17092 lb
≔FhB ⋅⋅⎛⎝ −⋅pW sin ((Ω)) ⋅pL sin ((Ω))⎞⎠ H2 B Horizontal Wind Component
=FhB 4883 lb
Hodge Structural Engineers 80' Wide x 70'-0" Century Tent (30' Middle Bays)G. Hodge
≔γ “90 degrees”
=h 20Load Case A
≔FvA90 ⋅⋅⋅qz G L ⎛⎝ ⋅⎛⎝ ++⋅h CN1A ⋅h CN2A ⋅(( −B ⋅2 h)) CN3A⎞⎠ cos ((Ω))⎞⎠
=FvA90 −21365 lb
Load Case B
≔FvB90 ⋅⋅⋅qz G L ⎛⎝ ⋅⎛⎝ ++⋅h CN1B ⋅h CN2B ⋅(( −B ⋅2 h)) CN3B⎞⎠ cos ((Ω))⎞⎠
=FvB90 20297 lb
LOAD COMBINATIONS (ASCE 7-10 2.4.1)
≔LC1 D
≔LC2 +D L
≔LC3 “D+0.6W”
≔LC4 “D+0.75L+0.75(0.6W)”
≔LC5 “0.6D+0.6W”
Hodge Structural Engineers 80' Wide x 70'-0" Century Tent (30' Middle Bays)G. Hodge
ANCHOR REACTIONS AND POLE FORCES
** For vertical loads, determine the tributary area for each pole
≔CPtw ⋅27.5 25
SP = Side Pole (H1 tall)
CP = Center Pole (H tall)
=CPtw 687.5 ft2
≔SPtw ⋅10 12.5
=SPtw 125 ft2
For Poles, Determine Vertical Force Due to Initial Tension in Anchor StrapAssume the Initial Strap Tension = 2200lb
≔Tint 2200 lb
Dead Load - SIDE POLE
≔FF ―――――⎛⎝ ⋅Tint sin ((θ))⎞⎠
cos ((Ω))
=FF ⋅1.867 103
lb Tension Force in the Fabric
Hodge Structural Engineers 80' Wide x 70'-0" Century Tent (30' Middle Bays)G. Hodge
≔FP −⎛⎝ ⋅Tint cos ((θ))⎞⎠ ⋅FF sin ((Ω))
=FP 439.994 lb Axial Force in the Tent Side Pole (Dead Load)
Dead Load - MAIN POLE
≔FPmp ⋅6.5 ⎛⎝ ⋅FF sin ((Ω))⎞⎠
=FPmp 8580 lb Axial Force in Tent Main Pole (Dead Load)
DETERMINE THE ANCHOR STRAP AND POLE FORCES FOR WIND LOAD
Wind Load - SIDE POLE
≔γ “0, 180 degrees”
Load Case A
≔Fhperpole ――FhA
6
=Fhperpole ⋅1.424 103
――lb
Pole
≔Fvperpole ―――⋅FvA 0.51
26
=Fvperpole 796.259 ――lb
pole
≔FA ⋅―――Fhperpole
sin ((θ))3.5
=FA ⋅8.309 103
lb
≔Fp +Fvperpole ⋅FA cos ((θ))
=Fp ⋅7.443 103
lb
Load Case B
≔Fhbpp ――FhB
6
=Fhbpp 813.906 ――lb
pole
Hodge Structural Engineers 80' Wide x 70'-0" Century Tent (30' Middle Bays)G. Hodge
≔Fvbpp ―――⋅FvB 0.51
26
=Fvbpp −335.267 ――lb
pole
≔FAB ―――Fhbpp
sin ((θ))
=FAB ⋅1.357 103
lb
≔FPB +⋅FAB cos ((θ)) Fvbpp
=FPB 749.938 lb
Wind Load - MAIN POLES
≔γ “0, 180 degrees”
Load Case A
≔Fvmp ―――⋅FvA 0.49
4
=Fvmp 4973 ――lb
pole
Load Case B
≔Fvbmp ―――⋅FvB 0.49
4
=Fvbmp ⋅−2.094 103
――lb
pole
Wind Load - Side Poles
≔γ “90 Degrees”
Assume 250lb lateral load at each side pole
Load Case A
≔FASP90 ―――250
sin ((θ))
=FASP90 416.666 lb
Hodge Structural Engineers 80' Wide x 70'-0" Century Tent (30' Middle Bays)G. Hodge
≔FPSP90 +⎛⎜⎝
⋅――FvA90
26((0.51))
⎞⎟⎠
⋅FASP90 cos ((θ))
=FPSP90 −85.751 lb
Load Case B
≔FASP90B ―――250
sin ((θ))
=FASP90B 416.666 lb
≔FPSP90B +⎛⎜⎝
⋅――FvB90
26((0.51))
⎞⎟⎠
⋅FASP90 cos ((θ))
=FPSP90B 731.461 lb
Wind Load - MAIN POLES
≔γ “90 degrees”
Load Case A
≔Fvmp90 ――――⋅FvA90 0.49
4
=Fvmp90 −2617 ――lb
pole
Load Case B
≔Fvbmp90 ――――⋅FvB90 0.49
4
=Fvbmp90 ⋅2.486 103
――lb
pole
Hodge Structural Engineers 80' Wide x 70'-0" Century Tent (30' Middle Bays)G. Hodge
MAXIMUM LOADS
Anchor Straps:Initial Strap Tension (2200lb Assumed) to resist dead (D) and dead + live (D+L) load, therefore D = D+L = 2200lb
≔DA 2200 lb
≔LC1A =+DA ⋅0.6 FA ⋅7.185 103lb
≔LC2A =+DA ⋅0.6 FAB ⋅3.014 103
lb
≔LC3A =+DA ⋅0.6 FASP90 ⋅2.45 103
lb
≔LC4A =+DA 0.6 FASP90B ⋅2.45 103
lb
Side Poles:
≔DSP =+⋅D SPtw FP 464.994 lb
≔LSP =⋅LL SPtw 625 lb
≔LC1SP =+DSP LSP ⋅1.09 103
lb
≔LC2SP =+DSP ⋅0.6 Fp ⋅4.931 103
lb
≔LC3SP =+DSP ⋅0.6 FPB 914.957 lb
≔LC4SP =+DSP ⋅0.6 FPSP90 413.544 lb
≔LC5SP =+DSP ⋅0.6 FPSP90B 903.871 lb
≔LC6SP =++DSP 0.75 LSP ⋅0.45 Fp ⋅4.283 103
lb
≔LC7SP =++DSP 0.75 LSP ⋅0.45 FPB ⋅1.271 103
lb
≔LC8SP =++DSP 0.75 LSP ⋅0.45 FPSP90 895.156 lb
≔LC9SP =++DSP 0.75 LSP ⋅0.45 FPSP90B ⋅1.263 103
lb
≔LC10SP =+⋅0.6 DSP ⋅0.6 Fp ⋅4.745 103
lb
≔LC11SP =+⋅0.6 DSP ⋅0.6 FPB 728.959 lb
≔LC12SP =+⋅0.6 DSP ⋅0.6 FPSP90 227.546 lb
≔LC13SP =+⋅0.6 DSP ⋅0.6 FPSP90B 717.874 lb
Hodge Structural Engineers 80' Wide x 70'-0" Century Tent (30' Middle Bays)G. Hodge
Center Poles:
≔DMP =+⋅D CPtw FPmp ⋅8.718 103
lb
≔LMP =⋅LL CPtw ⋅3.438 103
lb
≔LC1MP =+DMP LMP ⋅1.216 104
lb
≔LC2MP =+DMP ⋅0.6 Fvmp ⋅1.17 104
lb
≔LC3MP =+DMP ⋅0.6 Fvbmp ⋅7.461 103
lb
≔LC4MP =+DMP ⋅0.6 Fvmp90 ⋅7.147 103
lb
≔LC5MP =+DMP ⋅0.6 Fvbmp90 ⋅1.021 104
lb
≔LC6MP =++DMP 0.75 LMP ⋅0.45 Fvmp ⋅1.353 104
lb
≔LC7MP =++DMP 0.75 LMP ⋅0.45 Fvbmp ⋅1.035 104
lb
≔LC8MP =++DMP 0.75 LMP ⋅0.45 Fvmp90 ⋅1.012 104
lb
≔LC9MP =++DMP 0.75 LMP ⋅0.45 Fvbmp90 ⋅1.241 104lb
≔LC10MP =+⋅0.6 DMP ⋅0.6 Fvmp ⋅8.214 103
lb
≔LC11MP =+⋅0.6 DMP ⋅0.6 Fvbmp ⋅3.974 103
lb
≔LC12MP =+⋅0.6 DMP ⋅0.6 Fvmp90 ⋅3.66 103
lb
≔LC13MP =+⋅0.6 DMP ⋅0.6 Fvbmp90 ⋅6.722 103
lb
Hodge Structural Engineers 80' Wide x 70'-0" Century Tent (30' Middle Bays)G. Hodge
=ProjectID “ 80' Wide x 70'-0" Century Tent Design Check (30' Middle Bays)”
=Date “8-13-14”
=Engineer “G. Hodge”
MAXIMUM LOADS
Anchor Strap: =LC1A 7185 lb
Side Poles: =LC2SP 4931 lb
Main Poles: =LC6MP 13533 lb