noise oversight committee · presentation: msp 2035 long term ... 2035 long-term comprehensive plan...

60
Noise Oversight Committee March 18, 2015 Audio recordings are made of this meeting

Upload: others

Post on 12-Jul-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Noise Oversight Committee

March 18, 2015

Audio recordings are made of this meeting

Page 2: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Noise Oversight CommitteeMarch 18, 2015

Item 1

Review and Approve Draft Meeting Minutes

• Minutes from January 21, 2015 Noise Oversight Committee Meeting

Page 3: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Noise Oversight CommitteeMarch 18, 2015

Item 2

Review of Operations Report Summary

• January 2015

• February 2015

Page 4: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

January February2015 6,054 6,976

2014 4,974 4,070

MSP Complaints

Technical Advisor’s Report Summary

01002003004005006007008009001000

02,0004,0006,0008,000

10,00012,00014,00016,00018,00020,000

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F

2010 2011 2012 2013 2014 2015

Com

plai

nant

s Tot

al

Com

plai

nts T

otal

Complaints Complainants

Page 5: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Total Aircraft OperationsJanuary February

2015 31,371 29,033

2014 33,048 29,772

Technical Advisor’s Report Summary

33,04829,772

36,31833,827 34,377 35,659

37,306 36,68933,085 34,595

31,256 32,613

31,37129,033

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

Ope

ratio

ns To

tal

2014 2015

Page 6: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Air Carrier Jet OperationsJanuary February

2015 29,248 27,012

2014 30,422 27,602

January February

Regional Jet

ModifiedStage 3 Other Regional

JetModifiedStage 3 Other

2015 48.5% <0.0% 51.5% 47.1% <0.0% 52.8%

2014 51.4% <0.0% 48.6% 50.7% <0.0% 49.3%

Air Carrier Jet Fleet Composition

Technical Advisor’s Report Summary

Page 7: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Source: Metropolitan Airports Commission’s Finance Department Monthly Passenger and Operations Reports

MSP Passenger Data

0

5,000

10,000

15,000

20,000

25,000

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

Jan

Feb

Mar Ap

rM

ay Jun Jul

Aug

Sep

Oct

Nov De

cJa

nFe

bM

ar Apr

May Jun Jul

Aug

Sep

Oct

Nov De

cJa

nFe

bM

ar Apr

May Jun Jul

Aug

Sep

Oct

Nov De

cJa

nFe

bM

ar Apr

May Jun Jul

Aug

Sep

Oct

Nov De

cJa

nFe

bM

ar Apr

May Jun Jul

Aug

Sep

Oct

Nov De

cJa

nFe

bM

ar Apr

May Jun Jul

Aug

Sep

Oct

Nov De

cJa

n

2009 2010 2011 2012 2013 2014 2015

Ope

ratio

ns

Pass

enge

rs

Major Air Carrier Operations and PassengersPassengers Operations

0

5,000

10,000

15,000

20,000

25,000

0100,000200,000300,000400,000500,000600,000700,000800,000900,000

1,000,000

Jan

Feb

Mar Ap

rM

ay Jun Jul

Aug

Sep

Oct

Nov De

cJa

nFe

bM

ar Apr

May Jun Jul

Aug

Sep

Oct

Nov De

cJa

nFe

bM

ar Apr

May Jun Jul

Aug

Sep

Oct

Nov De

cJa

nFe

bM

ar Apr

May Jun Jul

Aug

Sep

Oct

Nov De

cJa

nFe

bM

ar Apr

May Jun Jul

Aug

Sep

Oct

Nov De

cJa

nFe

bM

ar Apr

May Jun Jul

Aug

Sep

Oct

Nov De

cJa

n

2009 2010 2011 2012 2013 2014 2015

Ope

ratio

ns

Pass

enge

rs

Regional Air Carrier Operations and PassengersPassengers Operations

Page 8: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

All Nighttime Use

PercentagesRunway January

2015February

2015

Departures 4 0% 0.6%

12L 12.5% 11.2%

12R 29.2% 17.6%

17 13.9% 10.6%

22 0.3% 0.6%

30L 33.1% 40.7%

30R 11.1% 18.5%

35 0% 0%

All Nighttime Use

PercentagesRunway January

2015February

2015

Arrivals 4 0% 0.4%

12L 10.3% 8.5%

12R 23.1% 24.2%

17 0% 0%

22 0% 0.9%

30L 46.7% 51.5%

30R 17.6% 14.2%

35 2.3% 0.3%

January February

All Nighttime Operations

2015 1,511 1,487

2014 1,404 1,250

Nighttime Operations(10:30pm - 6:00 am)

Technical Advisor’s Report Summary

Page 9: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

0

100

200

300

400Sc

hedu

led

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

A D A D A D A D A D A D A D A D

22:30 23:00 00:00 01:00 02:00 03:00 04:00 05:00

Ope

ratio

nsJanuary 2015 Nighttime Scheduled Vs Actual Carrier Jet Operations

10:30 pm - 6:00 amAAL DAL FDX FFT NKS SCX SWA UAL UPS Other AWE

Airline Code Airline NameScheduled

Modified Stage 3

Actual Modified Stage

3

Scheduled Manufactured

Stage 3

Actual Manufactured

Stage 3Scheduled Total Actual Total

DAL Delta 0 0 67 296 67 296SCX Sun Country 0 0 89 294 89 294NKS Spirit 0 0 111 140 111 140AWE US Airways 0 0 88 113 88 113AAL American 0 0 90 93 90 93SWA Southwest 0 0 47 67 47 67UPS UPS 0 0 60 64 60 64FFT Frontier Airlines 0 0 14 48 14 48UAL United 0 0 50 28 50 28FDX Fedex 0 0 38 30 38 30

Other Other 0 3 0 264 0 267Total 3 654 1437 654 1440

Page 10: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

0

100

200

300

400

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

Sche

dule

d

Actu

al

A D A D A D A D A D A D A D A D

22:30 23:00 00:00 01:00 02:00 03:00 04:00 05:00

Ope

ratio

nsFebruary 2015 Nighttime Scheduled Vs Actual Carrier Jet Operations

10:30 pm - 6:00 amAAL DAL FDX FFT NKS SCX SWA UAL UPS Other AWE

Airline Code Airline NameScheduled

Modified Stage 3

Actual Modified Stage

3

Scheduled Manufactured

Stage 3

Actual Manufactured

Stage 3Scheduled Total Actual Total

DAL Delta 0 0 77 334 77 334SCX Sun Country 0 0 170 303 170 303NKS Spirit 0 0 112 126 112 126AWE US Airways 0 0 79 123 79 123AAL American 0 0 76 83 76 83SWA Southwest 0 0 51 58 51 58UPS UPS 0 0 57 63 57 63FFT Frontier Airlines 0 0 56 47 56 47UAL United 0 0 40 31 40 31FDX Fedex 0 0 40 33 40 33

Other Other 0 3 0 213 0 216Total 3 758 1414 758 1417

10

Page 11: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

January February

Runway 17 Carrier Jet Departures 4,116 3,297

Compliance with Runway 17 Carrier Jet Departure

Procedure99.5% 99.5%

Runway 17 Departure Analysis Summary

Page 12: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

January February

Runways 12L and 12R Carrier Jet Departures 2,683 2,144

Carrier Jets Remaining in Corridor 94.1% 96.9%

Eagan-Mendota Heights Departure Corridor Analysis Summary

Page 13: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

January February

Carrier Jet Departures Crossing-in-the-Corridor Nighttime (23:00-06:00)

54(56%)

37(50%)

Carrier Jet DeparturesCrossing-in-the-Corridor Daytime (06:00-23:00)

878(34%)

646(31%)

Crossing-in-the-Corridor Analysis Summary

Page 14: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Noise Oversight CommitteeMarch 18, 2015

Item 3

Presentation: Runway Use System and RNAV STAR Update

Elaine Buckner, FAA Air Traffic Manager

Page 15: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing
Page 16: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

MSP Area Navigation (RNAV) Standard Terminal Arrival Routes (STARs) were published by the FAA on March 5, 2015.

Use of the RNAV STARs at MSP is anticipated to begin on March 24, 2015.

Implementation of the MSP Required Navigation Performance (RNP) portion of the STARs is anticipated to begin on April 30, 2015.

RNAV STAR Update

Page 17: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Noise Oversight CommitteeMarch 18, 2015

Item 4

Presentation: MSP 2035 Long Term Comprehensive Plan (LTCP)

Neil Ralston, MAC Airport Planner

Page 18: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

2035 Long-Term Comprehensive Plan

18 March 2015 Noise Oversight Committee (NOC)MSP 2035 LTCP Status Update

Page 19: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Briefing Agenda

• Purpose• Planning Process• Goals & Objectives• Stakeholder Outreach• Planning Parameters• Timeline

MSP – 2014 Aerial Photo

Page 20: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Purpose• Purpose

– Identify future facility needs for the next 20 years

– Serve as the “road map” to guide our development strategy for MSP over the next 5-10 years

• 2030 LTCP (July 2010)• Rapid pace of change

Page 21: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Process

• Activity Forecasts– Passenger and aircraft operations

projections to 2035• Includes non-passenger aircraft operations

(Cargo, GA, MIL)

– Preview: ~27m passenger boardingsand ~511k aircraft operations by 2035

– Forecast scenariosHistorical vs. Forecast Aircraft Operations

Source: HNTB Draft Forecast Technical Memorandum

Page 22: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Process, cont’d

• Facility Requirements– Areas of Emphasis

• Entrance/Exit Roadways• Departures & Arrivals Curbs• Public Parking• Passenger Hold Rooms• Aircraft Gates

– Incorporating ongoing improvement programs

Page 23: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Process, cont’d

• Development Alternatives– Examples

• Gate Configurations on Concourses A & B

• Arrivals Curbfront

– Recommended Development Program

– Environmental Considerations

Recommended Plan from 2030 LTCP

Page 24: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Goals & Objectives

• Goals– Overall aspirations for planning process– 3 Primary Goals

• Objectives– Specific, actionable items– Contribute to goal achievement

• Provides focus and direction when evaluating planning concepts

Page 25: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Goals & Objectives, cont’d

Goal #1: Plan for future facilities that will maintain and enhance the customer service experience while promoting operational efficiency and flexibility throughout the entire MSP campus.

Objectives include:• Reduce curbside congestion • Providing a consistent departure hold

room experience• Enhance aircraft gate availability and

flexibility • Consider changing passenger

demographics, trends, and behaviors

Page 26: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Goals & Objectives, cont’d

Goal #2:Produce a plan that promotes fiscal viability, incorporates environmental stewardship, and infuses sustainable thinking – while at the same time enhancing the Airport’s competitive position in the marketplace.

Objectives include:• Ensure that the development program

is fiscally responsible • Consider building life-cycle and

longevity in decision making

Page 27: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Goals & Objectives, cont’d

Goal #3:Through the planning process, expand effectiveness through strengthened external relationships and partnerships with customers, tenants, neighboring communities, and governmental agencies.

Objectives include:• Seek to foster consensus among key

stakeholders• Employ a focused public involvement

program to inform, educate, and receive feedback

Page 28: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Stakeholder Outreach Strategy• Prior to Completion of Draft LTCP (April – June)

– Municipal Planning Departments• Plan Commissions/City Councils if recommended

– Other External Stakeholders (FAA, MnDOT, Met Council)– Internal Tenant Groups– Public Information Meeting

• Formal Draft LTCP Public Review Period (July - August)– Written comment period (30 days)– Public Information Meetings– Met Council

• LTCP Final Draft/Adoption (September – December)– Additional stakeholder outreach as needed

Page 29: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Planning Parameters• Planning Parameters

– Operational factors

• Level of Service Standards– Desired performance criteria

– Identifying facility “gaps” and “trigger points” for future development phases Terminal Modeling (T1)

Source: Ricondo & Associates

Page 30: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Planning Parameters, cont’d

• EXAMPLE:Planning Basis –Terminal Departure Flows

Departure Curb AircraftDepartureLandside

Concessions

Airside Concessions Holdroom

Area:65% Pax Seated

35% Pax Standing17 ft2 per Seated pax

12 ft2 per Standing pax

Outbound Bag Makeup

40 bags/cart

Check-In

Process Rate:Kiosk: 2-3 min/pax

Bag Drop: 1-5 min/pax

14 ft2/pax in Queue

Wait:U.S. Airline: 0-12 min

Foreign Airline: 0-20 min.

Security

Process Rate:Standard - 160 pax/hrPre✓™ - 250 pax/hr

*50% of Pax in Pre✓™

10.8 ft2/pax in Queue

Wait:0-10 min.

Outbound Bag Screening

Source: Ricondo & Associates

Page 31: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Planning Parameters, cont’d

• EXAMPLE:Planning Basis –Terminal Departure Flows

Departure Curb AircraftDepartureLandside

Concessions

Airside Concessions Holdroom

Area:65% Pax Seated

35% Pax Standing17 ft2 per Seated pax

12 ft2 per Standing pax

Outbound Bag Makeup

40 bags/cart

Check-In

Process Rate:Kiosk: 2-3 min/pax

Bag Drop: 1-5 min/pax

14 ft2/pax in Queue

Wait:U.S. Airline: 0-12 min

Foreign Airline: 0-20 min.

Security

Process Rate:Standard - 160 pax/hrPre✓™ - 250 pax/hr

*50% of Pax in Pre✓™

10.8 ft2/pax in Queue

Wait:0-10 min.

Outbound Bag Screening

Source: Ricondo & Associates

Page 32: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Planning Parameters, cont’d

• EXAMPLE:Planning Basis –Terminal Departure Flows

Departure Curb AircraftDepartureLandside

Concessions

Airside Concessions Holdroom

Area:65% Pax Seated

35% Pax Standing17 ft2 per Seated pax

12 ft2 per Standing pax

Outbound Bag Makeup

40 bags/cart

Check-In

Process Rate:Kiosk: 2-3 min/pax

Bag Drop: 1-5 min/pax

14 ft2/pax in Queue

Wait:U.S. Airline: 0-12 min

Foreign Airline: 0-20 min.

Security

Process Rate:Standard - 160 pax/hrPre✓™ - 250 pax/hr

*50% of Pax in Pre✓™

10.8 ft2/pax in Queue

Wait:0-10 min.

Outbound Bag Screening

Source: Ricondo & Associates

Page 33: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Planning Parameters, cont’d

• EXAMPLE:Planning Basis –Terminal Departure Flows

Departure Curb AircraftDepartureLandside

Concessions

Airside Concessions Holdroom

Area:65% Pax Seated

35% Pax Standing17 ft2 per Seated pax

12 ft2 per Standing pax

Outbound Bag Makeup

40 bags/cart

Check-In

Process Rate:Kiosk: 2-3 min/pax

Bag Drop: 1-5 min/pax

14 ft2/pax in Queue

Wait:U.S. Airline: 0-12 min

Foreign Airline: 0-20 min.

Security

Process Rate:Standard - 160 pax/hrPre✓™ - 250 pax/hr

*50% of Pax in Pre✓™

10.8 ft2/pax in Queue

Wait:0-10 min.

Outbound Bag Screening

Source: Ricondo & Associates

Page 34: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Planning Parameters, cont’d

• EXAMPLE:Show-Up Profile

Source: Ricondo & Associates

Page 35: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Planning Parameters, cont’d

• EXAMPLE:Show-Up Profile

Source: Ricondo & Associates

Page 36: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Planning Parameters, cont’d

• EXAMPLE:Show-Up Profile

Source: Ricondo & Associates

Page 37: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

LTCP Planning Parameters, cont’d

• EXAMPLE:Show-Up Profile

Source: Ricondo & Associates

Page 38: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Adopt Final Plan

IncorporateFeedback

intoFinal Plan

LTCP Timeline

JAN FEB MAR APR MAY JUN

Public Review

Draft LTCP Report

EnvironmentalConsiderations

Recommended Development

Program

DevelopmentAlternatives

FacilityRequirements

Forecasts

StakeholderOutreach

StakeholderOutreach

JANUARY – APRIL MAY – JUN JULY – AUGUST SEPTEMBER –DECEMBER

Page 39: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Adopt Final Plan

IncorporateFeedback

intoFinal Plan

LTCP Timeline

JAN FEB MAR APR MAY JUN

Public Review

JANUARY – APRIL MAY – JUN JULY – AUGUST SEPTEMBER –DECEMBER

StakeholderOutreach

StakeholderOutreach

Draft LTCP Report

EnvironmentalConsiderations

Recommended Development

Program

DevelopmentAlternatives

FacilityRequirements

Forecasts

Page 40: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Upcoming Briefings• PD&E Committee

• April – Forecast & Facility Requirements Summary• May – Development Alternatives Overview• June – LTCP Recommended Plan Overview• July – Request to Circulate Draft LTCP Report• November – Request to Submit Final Draft LTCP to Met Council

• Noise Oversight Committee (NOC)• May – LTCP Update• July – LTCP Update

** Planned briefing schedule and content subject to change pending LTCP timeline and status**

Page 41: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Noise Oversight CommitteeMarch 18, 2015

Item 52014 Annual Noise Contour Report

The Noise Mitigation Consent Decree requires the MAC to prepare a annual noise contour report using the FAA’s Integrated Noise Model (INM).

On February 27, 2015 MAC staff completed the eighth Annual Noise Contour Report consistent with the requirements laid out in the Consent Decree.

The Consent Decree was amended in October 2013 to establish a three-consecutive year mitigation eligibility requirement, compared to the 2007 DNL forecast contours.

Page 42: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

2014 Annual Noise Contour Report (continued)

The MAC retained the services of HNTB for the preparation of the INM inputs and to run a quality check on the noise contours.

2014 is the second year of actual noise mapping to establish mitigation eligibility, per the Consent Decree Amendment. The only residential properties that meet the mitigation eligibility criteria are located in the City of Minneapolis.• 285 single-family homes meet the 1st year of eligibility.• 137 single-family homes and 89 multi-family units meet the 2nd year of

eligibility (all homes that met the 1st year in 2013 moved into the 2nd

year in 2014).

Page 43: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

• The 2014 total operations were 29.3% below the 2007 forecast mitigated total operations.

• The 2014 total operations are down 4.6% from 2013.

• Modified (“hushkitted”) Stage 3 average daily operations in 2014 were down 99.9% from the 2007 forecast mitigated number.

• Nighttime operations in 2014 decreased by 28 average daily operations from the 2007 forecast mitigated number.

Table 3.1MINNEAPOLIS-ST. PAUL INTERNATIONAL AIRPORT

2007 Mitigated Forecast vs. 2014 ActualAnnual Total Operations Summary

Operations Category 2014 Actual* 2007 ForecastedScheduled PassengerAir Carrier (a)

375,072 523,472

Cargo 12,199 21,158Charter 190 5,766GA 21,862 28,846Military 2,437 3,124TOTAL 411,760 582,366Notes:(a) Includes both air carrier and regional carrier operations(b) Includes both GA and non-scheduled air taxi operations* Based on actual 2014 MACNOMS data adjusted to match FAA ATADS data (to account for unavailable MACNOMS operations data).

2014 Annual Noise Contour Report (continued)

Page 44: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing
Page 45: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

• The 2014 actual noise contour is smaller than the 2007 forecast mitigated contour by 6,949.9 acres (44.2% reduction) in the 60 DNL contour and by 3,755.5 acres (51.9% reduction) in the 65 DNL contour.

• The predominant contraction in the contours from the 2007 forecast mitigated to the 2014 actual noise contour is driven largely by fleet mix changes, including a significant reduction in Modified (“hushkitted”) Stage 3 aircraft operations, and a significant reduction of total annual operations.

• The small area where the 2014 actual noise contour extends beyond the 2007 forecast mitigated noise contour can largely be attributed to nighttime runway use variances between what was forecasted and what was occurring in 2014, particularly an increase in nighttime arrival operations on Runway 12R.

2014 Annual Noise Contour Report (continued)

Page 46: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

2014 Annual Noise Contour Report (continued)

1st Year of Mitigation Eligibility• 120 single-family homes moved from the 60-62 DNL contour into the 2014 63 DNL contour• 39 single-family homes previously eligible for homeowner reimbursement moved into the 2014 60-62

DNL contour • 126 single-family homes previously outside the mitigation area moved into the 2014 60-62 DNL

contour 2nd Year of Mitigation Eligibility

• 119 single-family homes previously eligible for homeowner reimbursement moved into the 2014 60 DNL contour

• 18 single-family homes previously outside the mitigation area moved into the 2014 60 DNL contour • 89 multi-family units previously outside the mitigation area moved into the 2014 60 DNL contour

If these blocks remain within a higher noise impact area for 3 consecutive years, they will be eligible for additional mitigation in accordance with the First Amendment to the Consent Decree.

Page 47: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing
Page 48: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing
Page 49: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Noise Oversight CommitteeMarch 18, 2015

Item 6

Nighttime Operations Assessment

The 2015 NOC Work Plan includes an assessment of nighttime operations at MSP.

Resident concerns and comments are one of the primary catalysts for the continuing

evaluation of nighttime operations at MSP.

Federal policy virtually prohibits mandatory nighttime restrictions at public-use airports,

such as MSP.

Page 50: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Analysis focuses on the following:• Average daily nighttime operations at MSP from 2005 to 2014• Annual average daily INM nighttime operations from 2005 to 2014 compared to the

2007 forecast annual average daily nighttime operations• MSP all nighttime and carrier jet nighttime operations runway use summary for 2014

and 2013• MSP INM nighttime (10:00 p.m. to 7:00 a.m.) operations runway use summary for

2014 and 2013• A breakdown of the top 15 nighttime carrier jet operators for 2014 and 2013• A breakdown of the fleet mix for the top 15 nighttime airlines for 2014 and 2013• Average daily MSP nighttime operations by hour for 2014 and 2013• A comparison and breakdown of scheduled nighttime operations and the fleet mix of

the scheduled operations for 2014 and 2013• A comparison of the scheduled nighttime operations vs. actual nighttime operations

for 2014 and 2013

Nighttime Operations Assessment(continued)

Page 51: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

65.3

67.9

73.272.6

56.4

44.7

48.6

43.5

46.2

51.2

40

45

50

55

60

65

70

75

80

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

Aver

age

Dai

ly O

pera

tions

Average Daily Nighttime Operations 10:30pm - 6:00am

Page 52: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

127.1127.2

131.5127.1

107.8

94.5

107.2

99.1 98.294.5

19.8 18.6 18.912.0

6.82.1 1.2 0.3 0.1 0.0

0

20

40

60

80

100

120

140

160

2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

Aver

age

Dai

ly O

pera

tions

Average Daily INM Nighttime Operations 10 pm - 7 am

Average Daily 2007 Forecast (123.3) Average Daily Hushkits 2007 Forecast Hushkits (21.7)

Page 53: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

MSP Nighttime Runway Usage Summary of All Operations (10:30 p.m. to 6 a.m.)

20142013

0.00.0

20142013

0.0%0.0%

Total Nighttime Operations Percentage by Runway

Average Daily NighttimeOperations Count by Runway

2014ARR = 14,770DEP = 3,912

TOTAL = 18,682

2013ARR = 12,868DEP = 4,011

TOTAL = 16,879

2014ARR = 40.5DEP = 10.7

TOTAL = 51.2

2013ARR = 35.3DEP = 11.0

TOTAL = 46.2

Page 54: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

MSP Nighttime Runway Usage Summary of Carrier Jet Operations (10:30 p.m. to 6 a.m.)

20142013

0.00.0

20142013

0.0%0.0%

Total Nighttime Operations Percentage by Runway

Average Daily NighttimeOperations Count by Runway

2014ARR = 13,929DEP = 3,367

TOTAL = 17,296

2013ARR = 11,569DEP = 3,505

TOTAL = 15,074

2014ARR = 38.2DEP = 8.0

TOTAL = 46.2

2013ARR = 31.7DEP = 9.6

TOTAL = 41.3

Page 55: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

MSP Nighttime Runway Usage Summary of All

20142013

0.00.0

20142013

0.0%0.0%

Total Nighttime Operations Percentage by Runway

Average Daily NighttimeOperations Count by Runway

2014ARR = 54.2DEP = 40.3

TOTAL = 94.5

2013ARR = 51.6DEP = 46.6

TOTAL = 98.2

2014ARR = 19,795DEP = 14,714

TOTAL = 34,509

2013ARR = 18,834DEP = 17,008

TOTAL = 35,842

Operations INM Hours (10:00 p.m. to 7 a.m.)

Page 56: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

• In 2014, all nighttime operations increased 10.7% from 2013 (carrier jet nighttime ops increased 14.7% over the same time period)

• The top 15 nighttime jet operators represent 95.7% of the total nighttime carrier jet operations in 2014 (Top three carriers: DAL, SCX, NKS). In 2013 the top 15 represented 94.3%. (Top three carriers: DAL, SCX, AWE).

• Of the top 15 nighttime jet operators, 100% of the operations were flown with Stage 3 Manufactured aircraft in 2014.

• The most prevalent time period for nighttime operations in 2014 was 23:00 to 00:00 (15.1 average daily night ops – 29.8%) and 05:00 to 06:00 (14.0 average daily night ops – 25.2%)

Nighttime Operations Assessment(continued)

Page 57: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

• 9,595 scheduled nighttime flights for 2014 vs. 7,466 scheduled nighttime flights for 2013 (28% increase)

• Top three carrier scheduled night ops for 2014 • DAL – 1,837• SCX – 1,608 • UAL – 1,046

• Actual nighttime carrier ops for 2014 (MACNOMS) – 17,296 vs. scheduled nighttime ops for 2014 (OAG) – 9,595

Nighttime Operations Assessment(continued)

Page 58: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Noise Oversight CommitteeMarch 18, 2015

Item 7Review of the January 27, 2015 Public Input Meeting

On January 27, 2015 at 7:00 pm MAC Noise Program Office staff conducted the first quarter 2015 public inputmeeting at the Richfield Municipal Building, 6700 Portland Avenue South. There were 7 people who attendedthe meeting, 4 individuals made comments at the meeting, 1 individual submitted comments via the PublicInput Meeting Form on the Noise Program website and no comment forms were submitted at the meeting. Thecomments and associated responses can be found on the MAC Noise Program’s website, accessible on theInternet at www.macnoise.com. Specifically, comments/questions focused on:

• Frequency of aircraft overflights• RNAV arrival procedure implementation• Public involvement in the MSP Long Term Comprehensive Plan• Nighttime curfew at MSP

The next quarterly public input meeting is planned for April 28, 2015, 7:00 p.m., at the Richfield MunicipalBuilding, 6700 Portland Avenue South.

Page 59: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Noise Oversight CommitteeMarch 18, 2015

Item 8

Public Comment Period

Page 60: Noise Oversight Committee · Presentation: MSP 2035 Long Term ... 2035 Long-Term Comprehensive Plan 18 March 2015 Noise Oversight Committee (NOC) MSP 2035 LTCP Status Update. Briefing

Noise Oversight CommitteeMarch 18, 2015

The next NOC Meeting is scheduled for May 20, 2015, 1:30 p.m., at the MAC General Offices at 6040 28th Avenue South, Minneapolis