non-proprietary regulatory gap analysis results ...gap analysis results – regulations summary...

108
TM © 2012 NuScale Power, LLC TM Regulatory Gap Analysis Results: Regulations Requiring Further Consideration Derick Botha and Gary Becker December 3, 2012

Upload: others

Post on 12-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TM© 2012 NuScale Power, LLC

TM

Regulatory Gap Analysis Results:Regulations Requiring Further Consideration

Derick Botha and Gary Becker

December 3, 2012

Page 2: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC2

Agenda• Purpose• Background• Regulatory gap analysis process• Gap analysis results – regulations• Summary• Feedback and next steps

Page 3: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC3

Purpose• Review gap analysis approach in assessing regulations• Discuss regulations requiring further consideration

– 17 regulations identified in summary report

– 3 regulations added after summary report submittal

• Obtain NRC feedback on proposed resolution for regulatory gaps

• Obtain NRC feedback on additional pre-application interactions planned for selected regulatory gaps

Page 4: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC4

Background• Design-Specific Review Standard (DSRS) approach

(from SECY-11-0024)– update of introduction of Standard Review Plan (SRP) describing

risk-informed review and integrated review process

– DSRS contains selected sections modified for NuScale design

– DSRS references the unchanged SRP sections

• Pre-application outcomes (October 2011 meeting) – agreement on applicability of requirements and guidance

• Gap analysis process and scope presented (May 2012 meeting)

• Submitted gap analysis summary report (July 2012)

Page 5: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC5

Background

DSRS & SRP

sections

Gap analysis summary report• Proposed DSRS section

roadmap• Regulatory gaps

Gap analysis tables in electronic reading room• Regulations• SRP acceptance criteria

and sub-tier guidance• Regulatory guides

Design description• Design overview• Categorization of

structures, systems, and components (SSCs)

Content outline(covered in DSRS engagement as

needed)

Page 6: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC6

Gap Analysis Process – Scope• 10 CFR Parts 1 through 199, with particular focus on

– 10 CFR 52– 10 CFR Parts 20, 50, 51, 73, and 100 as specified in 10 CFR 52.48

• Standard Review Plan (NUREG-0800) including sub-tier guidance– regulatory guides (RGs), including RG 1.206– NUREGs– TMI requirements and unresolved / generic safety issues– NRC documents (SECYs and associated SRMs)– NRC generic communications – industry codes and standards

• Interim Staff Guidance relevant to applicants for design certification

• Regulatory guides – Division 1, 4, 5, and 8 in addition to RGs referenced in SRP

Page 7: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC7

Gap Analysis Process – Regulations

Adequate level of safety

Functional purpose of

LWR requirements,

guidance

Functional purpose and

design criteria for NuScale

Compare

Existing regulation

applies

Existing regulation partially applies

Existing regulation does not

apply

NuScale unique feature/

requirement

Resolution

SMR reactor safety functions,

functional analysis,SSCs design criteria,

safety analysis, LBEs DID

Existing LWR requirements,

GDCs, guidance

SMR reactor design and PRA use

Page 8: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC8

Gap Analysis Process – Regulations• Summary report identified17 regulations requiring further consideration

– Regulations that would not apply to NuScale as it would for current light-water reactor (LWR) designs

– Considering literal language of rule

• Design literally meets rule: specific approach warrants pre-application interaction

• Departures: Applicable to design certification or combined license application but not appropriate to apply to NuScale design

• Propose resolution taking into account

– regulatory intent

– NuScale design considerations

– regulatory history including statements of consideration

– regulatory precedent

• Feedback on proposed resolution to meet regulation or form of departure

Page 9: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC9

Gap Analysis Results – Regulations Summary Table

Proposed resolution Future 

engagement  10 CFR  Subject

1 50.54(m)(2)(i) and (iii) Minimum Licensed Operator Staffing Requirements   Exemption  Y 2 50.62(c)(1)   Reduction of Risk from ATWS Events   Potential Exemption  Y 3 50.44(c)(2)   Combustible Gas Control   Complies with rule Y 4 50, App. K   ECCS Evaluation Models   Complies with rule Y 5 50.34(f)(2)(vi)   Reactor Coolant System Venting   Complies with rule6 50.46a   Reactor Coolant System Venting   Complies with rule7 GDC 17   Electric power systems    Departure  Y 8 GDC 27 Combined reactivity control systems capability    Departure9 GDC 33   Reactor coolant makeup / inventory control Departure  Y 10 GDC 55 Containment isolation Departure  Y 11 GDC 56 Containment isolation Departure  Y 12 GDC 57 DHR / Containment isolation Departure  Y 13 GDC 40   Testing of containment heat removal system    Not applicable14 GDC 41   Containment atmosphere cleanup   Complies with rule15 GDC 42   Inspection of containment atmosphere cleanup systems   Not applicable16 GDC 43   Testing of containment atmosphere cleanup systems   Not applicable17 50.34(f)(2)(xv)   Containment Purging/Venting Capability and Isolation   Not technically relevant18 50.34(f)(2)(xii)   Auxiliary Feedwater System Actuation and Flow Indication   Not technically relevant19 50.34(f)(1)(ii)   Evaluation and Design Review of AFW System   Not technically relevant20 50.34(f)(2)(iv)   Safety Parameter Display System (SPDS)   Complies with rule

Changed from gap analysis summary reportAdded to list in gap analysis summary report submittal

Page 10: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC10

Gap Analysis Results – RegulationsFramework for presenting gaps• Regulatory requirement summary• Regulatory purpose• NuScale design considerations• Statement of regulatory gap• Pre-application plan

– proposed resolution

– future interactions

• Gap analysis impact

Page 11: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC11

50.54(m)(2)(i), (iii) – Staffing Requirements

Regulatory Requirement Summary• Each licensee shall meet the minimum licensed operator staffing

requirements in the following table: [50.54(m)(2)(i)]

Pre-Application PlanProposed resolution: exemption required

• Define appropriate staffing requirements for NuScale design

Future interactions:• HFE Program Plan submittals

• Planned HFE workshops

Page 12: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC12

50.62(c)(1) - Reduction of Risk from ATWS Events

Regulatory Requirement Summary and Purpose• Each pressurized water reactor must have equipment from sensor

output to final actuation device, that is diverse from the reactor trip system, to automatically initiate the auxiliary (or emergency) feedwater system and initiate a turbine trip under conditions indicative of an ATWS.

• ATWS rule was written for specific plant designs

NuScale Design Considerations• Have to consider AOOs, plant response, and I&C implementation

appropriate to address ATWS conditions for NuScale design

Page 13: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC13

50.62(c)(1) Reduction of Risk from ATWS Events

Pre-Application PlanProposed resolution: Potential exemption required

• To be discussed in future pre-application interactions

Future interactions: Present ATWS approach as part of DSRS engagement on chapters 15.8 and 7

Page 14: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC14

50.44(c)(2) – Combustible Gas Control

Regulatory Requirement Summary• All containments must have an inerted atmosphere, or

must limit hydrogen concentrations in containment …

Regulatory purpose• Section 50.44 provides requirements for the mitigation of

combustible gas generated by a beyond-design-basis accident.

Page 15: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC15

50.44(c)(2) – Combustible Gas Control

NuScale Design Considerations

}}3(a)

• Convective mixing of containment atmosphere, no sub-compartments

{{

Page 16: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC16

50.44(c)(2) – Combustible Gas Control

Statement of Regulatory Gap

{{

}}3(a)

Containment must have an inerted

atmosphereGAP?

Page 17: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC17

50.44(c)(2) – Combustible Gas Control

Pre-Application PlanProposed resolution: no exemption required

}}3(a)

• Complying with portions of the rule that apply to inerted containments

Future interactions: Cover along with other requirements of 50.44 as part DSRS engagement on Chapter 6.2.5

{{

Page 18: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC18

50.44(c)(2) – Combustible Gas Control

Gap Analysis Impact• Different approach from Gap Analysis Summary Report

– Previously proposed partial exemption for 10 CFR 50.44(c)(2)

• SRP sections that address rule– Section 6.2.5, “Combustible Gas Control in Containment”

– Section 3.8.1, “Concrete Containment”

– Section 3.8.2, “Steel Containment”

Page 19: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC19

10 CFR 50, Appendix K – ECCS Evaluation Models

Regulatory Requirement Summary• 10 CFR 50.46: ECCS cooling performance during LOCAs

must be calculated with an acceptable evaluation model using either– a best-estimate evaluation model or

– a conservative evaluation model (10 CFR 50, Appendix K)

• Appendix K provides required and acceptable features of a conservative ECCS Evaluation Model for example– The rate of energy release… from the metal/water reaction shall

be calculated

– shall include a provision for predicting cladding swelling and rupture

Page 20: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC20

10 CFR 50, Appendix K – ECCS Evaluation Models

NuScale Design Considerations• ECCS active components: vent valves and recirculation

valves• Containment wall facilitates ECCS heat removal • Core remains covered for design basis events - no large-

break LOCA• Integral reactor with no piping loops – no cold leg break• Natural circulation flow – no reactor coolant pump trip

Page 21: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC21

10 CFR 50, Appendix K – ECCS Evaluation Models

Statement of Regulatory Gap

{{

}}3(a)

Appendix K identifies required and acceptable features of ECCS evaluation models for large PWRs

GAP?

Page 22: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC22

10 CFR 50, Appendix K – ECCS Evaluation Models

Pre-Application PlanProposed resolution: No exemption required• NuScale ECCS evaluation models for small-break

LOCAs only need to address technically relevant features required by Appendix K

Future interactions: present implementation as part of DSRS engagement on Chapter 6.3

Page 23: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC23

10 CFR 50, Appendix K – ECCS Evaluation Models

Precedent

• ABWR – SAFER application methodology - Appendix K peak cladding temperatures (PCT) calculated

compared to a statistically calculated 95% probability value

• ESBWR has no core uncovery– simplified statistical approach based on chimney height, not PCT

• AP1000 – voluntary use of statistical uncertainty analysis to justify relaxation of all but the required

conservatisms contained in current ECCS evaluation models

– small-break LOCA response using Appendix K

• EPR– methodology used to analyze LBLOCA is a best-estimate EM based on non-parametric

statistics.

– small-break LOCA response using Appendix K

Page 24: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC24

10 CFR 50, Appendix K – ECCS Evaluation Models

Gap Analysis Impact • Gap Analysis Summary Report did not propose a

resolution for Appendix K• SRP sections that address rule

– Section 4.2, “Fuel System Design”

– Section 6.2.1.3, “Mass and Energy Release Analysis for Postulated Loss-of-Coolant Accidents (LOCAs)”

– Section 6.2.1.5, “Minimum Containment Pressure Analysis for Emergency Core Cooling System Performance Capability Studies”

– Section 6.3, “Emergency Core Cooling System”

– Section 15.0.2,” Review of Transient and Accident Analysis Method”

– Section 15.6.5, “Loss-of-Coolant Accidents Resulting From Spectrum of Postulated Piping Breaks Within the Reactor Coolant Pressure Boundary”

Page 25: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC25

50.34(f)(2)(vi), 50.46a – Reactor Coolant System Vents

Regulatory Requirement Summary*

• Each reactor must provide high point vents for – the reactor coolant system (RCS)

– the reactor vessel head

– other systems required to maintain adequate core cooling if accumulation of noncondensible gases would cause loss of function of these systems

*Both 50.34(f)(2)(vi) and 50.46a are applicable to design certification applicants and are substantively similar

Page 26: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC26

50.34(f)(2)(vi), 50.46a – Reactor Coolant System Vents

Regulatory Requirement Summary

• Design requirements– remotely operated from control room

– vents and associated components must meet GDCs and Appendix B

– designed to ensure • vents will perform safety functions

• no inadvertent or irreversible actuation of a vent

– operation shall not lead to unacceptable increase in probability of LOCA or challenge to containment integrity

Page 27: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC27

50.34(f)(2)(vi), 50.46a – Reactor Coolant System Vents

Regulatory Purpose

• Accumulation of noncondensible gases in RCS could interfere with adequate core cooling

• Ability to vent gases supports long-term core cooling via natural or forced circulation

• Provides assurance that vents maintain reactor coolant pressure boundary integrity

Page 28: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC28

50.34(f)(2)(vi), 50.46a – Reactor Coolant System Vents

• Integral reactor pressure vessel – core, steam generators, pressurizer

– the reactor vessel high point is also the RCS and pressurizer high point

– no other systems require venting to support core cooling

• ECCS reactor vent valves– at reactor vessel high point

– vent to containment

NuScale Design Considerations

Containment

Reactor vent valves

Reactor recirculation valves

Page 29: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC29

50.34(f)(2)(vi), 50.46a – Reactor Coolant System Vents

NuScale Design Considerations• ECCS vent valves provide inherent RCS venting capability

– vent noncondensible gases to containment when ECCS actuated

– vented gasses will not interfere with ECCS cooling

– will not challenge containment integrity

• ECCS vent valves meet design requirements– safety-related system

– operable from control room

• Does not affect LOCA probability– no additional components or controls

– failure and inadvertent actuation are analyzed events

Page 30: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC30

50.34(f)(2)(vi), 50.46a – Reactor Coolant System Vents

Statement of Regulatory Gap

ECCS valves serve as RCS high point vents in NuScale

design without separate vents

Must provide high point vents for

reactor, RCS, and other systems as

necessary

GAP?

Page 31: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC31

50.34(f)(2)(vi), 50.46a – Reactor Coolant System Vents

Pre-Application PlanProposed resolution: no exemption required• NuScale ECCS vent valves meet requirement for high

point vents

Precedent:• BWRs: inherent venting capability via SRVs• AP1000: ADS first stage credited as pressurizer high

point vent

Future interactions: DSRS development only

Page 32: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC32

50.34(f)(2)(vi), 50.46a – Reactor Coolant System Vents

Gap Analysis Impact

• Different approach from Gap Analysis Summary Report

– Previously proposed normal RPV vent line met literal language of high point vent rules, with no safety function related to core cooling

• SRP sections that address rule

– Section 5.4.12, “Reactor Coolant System High Point Vents”

Page 33: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC33

Appendix A to Part 50

General Design Criteria for Nuclear Power Plants

Page 34: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC34

GDC 17 – Electric Power SystemsRegulatory Requirement Summary

Electric power from the transmission network to the onsite electric distribution system shall be supplied by two physically independent circuits…designed and located so as to minimize to the extent practical the likelihood of their simultaneous failure under operating and postulated accident and environmental conditions.

Page 35: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC35

Regulatory Purpose

• Ensure reliable power to accomplish safety functions

– SAFDLs and RCPB design conditions not exceeded as a result of AOOs

– core cooling, containment integrity, etc. maintained for postulated accidents

• Traditional LWRs require A/C power for safety system function

– either onsite or offsite A/C necessary

– independent offsite circuits increase reliability

GDC 17 – Electric Power Systems

Page 36: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC36

GDC 17 – Electric Power SystemsNuScale Design Considerations

• A/C power not required for safe shutdown, core cooling, or containment integrity

}}3(a)

– nonsafety-related onsite and offsite power sources provided

• Redundant circuits from transmission network not necessary to ensure safety

{{

Page 37: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC37

GDC 17 – Electric Power SystemsStatement of Regulatory Gap

NuScale design does not require

two offsite circuits

Two physically independent offsite

electrical power circuits required to

ensure safety functions are accomplished

GAP

Page 38: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC38

GDC 17 – Electric Power SystemsPre-Application Plan

Proposed resolution: departure from GDC 17

• Design certification scope will include one offsite circuit

• Underlying purpose of the rule met without need for two offsite circuits

Precedent:• SECY-94-084: evaluate LOOP challenges against

coping capability

• AP1000 (exemption)

Page 39: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC39

GDC 17 – Electric Power SystemsPre-Application Plan

• Future interactions:– Upcoming engagement on Class 1E power system approach

– Discuss departure implementation in DSRS Ch. 8 engagement

Gap Analysis Impact

• Identified in Gap Analysis Summary Report• SRP sections that address rule

– Section 8.2, “Offsite Power System”

– Section 8.3.1, “AC Power Systems (Onsite)”

Page 40: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC40

GDC 27 – Reactivity Control SystemsRegulatory Requirement Summary

The reactivity control systems shall be designed to have a combined capability, in conjunction with poison addition by the emergency core cooling system, of reliably controlling reactivity changes to assure that under postulated accident conditions and with appropriate margin for stuck rods the capability to cool the core is maintained.

Page 41: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC41

GDC 27 – Reactivity Control Systems

Regulatory Purpose• GDC 27 provides assurance reactor can be shut down

and core coolability maintained in event of an accident• “In conjunction with poison addition by the emergency

core cooling system” – large LWR ECCS inject large volumes of borated water to control

inventory

– any poison added by ECCS injection can be credited in accident response for meeting reactivity control

Page 42: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC42

GDC 27 – Reactivity Control Systems

NuScale Design Considerations• ECCS has no makeup function

– no RCS inventory added by actuation– no poison addition via borated makeup

}}3(a)

{{

Page 43: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC43

GDC 27 – Reactivity Control Systems

Statement of Regulatory Gap

{{

}}3(a)

GDC 27 includes “poison addition by the emergency core cooling system” among the reactivity control systems

GAP?

Page 44: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC44

GDC 27 – Reactivity Control Systems

Pre-Application PlanProposed resolution: no departure required• NuScale design will meet regulatory requirements

}}3(a)

Future interactions: DSRS development only

{{

Page 45: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC45

GDC 27 – Reactivity Control Systems

Gap Analysis Impact

• Different approach from Gap Analysis Summary Report based on design change

}}3(a)

• SRP sections that address rule

– Section 4.3, “Nuclear Design”

– Chapter 15, “Transient and Accident Analysis”

{{

Page 46: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC46

GDC 33 – Reactor Coolant MakeupRegulatory Requirement Summary

A system to supply reactor coolant makeup for protection against small breaks in the reactor coolant pressure boundary shall be provided. The system safety function shall be to assure that specified acceptable fuel design limits (SAFDLs) are not exceeded….

Page 47: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC47

GDC 33 – Reactor Coolant MakeupRegulatory Purpose

• Protection against small breaks in the RCPB

• Provide sufficient reactor coolant makeup capacity to maintain reactor coolant system (RCS) water inventory and prevent the violation of SAFDLs

Page 48: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC48

GDC 33 – Reactor Coolant MakeupNuScale Design Considerations

• Reactor coolant from leaks and breaks is retained within containment vessel

• ECCS actuation returns water accumulated in containment vessel to the core through natural circulation

• Steam generator tube leaks are retained through feed and steam isolation

• For breaks inside containment, integrated module design– retains total reactor coolant inventory

– keeps core covered

– provides adequate core cooling

Page 49: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC49

GDC 33 – Reactor Coolant MakeupNuScale Design Considerations

• Chemical and volume control (CVC) system provides nonsafety-related reactor coolant makeup and letdown capability

– accommodates minor RCS leakage during normal operation

– maintains level during reactor heatup and cooldown

– not relied upon to prevent core uncovery or provide core cooling in the event of a postulated leak or break in the RCPB

Page 50: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC50

GDC 33 – Reactor Coolant MakeupStatement of Regulatory Gap

For small breaks, integral module

design with ECCS to retain reactor coolant inventory

For protection against small

breaks, makeup system required to

maintain core coolant inventory

and prevent violation of SAFDLs

GAP

Page 51: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC51

GDC 33 – Reactor Coolant MakeupPre-Application Plan

Proposed resolution: departure from GDC 33• alternative design-specific principal design criterion

– assurance of adequate reactor coolant inventory

Precedent:• Safety evaluation report for Clinch River Breeder Reactor (NUREG-0968)

• Pre-application safety evaluation report for PRISM (NUREG-1368)

Future interactions: present implementation as part of DSRS engagement on Chapter 9

Page 52: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC52

GDC 33 – Reactor Coolant MakeupGap Analysis Impact

• Identified in Gap Analysis Summary Report

• SRP sections that address rule

– Section 9.3.4, “Chemical and Volume Control System”

Page 53: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC53

GDCs 55, 56 – Containment Isolation

Regulatory Requirement Summary

• Each line that is part of RCPB (GDC 55) or connectsdirectly to containment atmosphere (GDC 56) must havetwo containment isolation valves (CIVs), in series– combinations of locked closed and/or automatic CIVs, (simple

check valves allowed only inside containment)

– one inside and one outside containment

– outside valve “as close to containment as practical”

– take position of greater safety upon loss of power

Page 54: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC54

GDCs 55, 56 – Containment Isolation

Regulatory Requirement Summary

• Additional provisions– Allows for “demonstrat[ion] that the containment isolation

provisions for a specific class of lines . . . are acceptable on someother defined basis”• SRP 6.2.4 accepts some other configurations with criteria and

requirements (instrument lines, ESF, and safe shutdown lines)

– “Other appropriate requirements to minimize the probability orconsequences of an accidental rupture…shall be provided asnecessary to assure adequate safety.” (GDC 55 only)

Page 55: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC55

GDCs 55, 56 – Containment Isolation

Regulatory Purpose

• Allow normal or emergency fluid passage through containment boundary while preserving ability to limit escape of fission products from postulated accidents

• Provisions are intended to increase isolation reliability

– two-barrier philosophy to account for single failure

– diverse locations (leakage inside containment, common-cause failure of both CIVs)

– prescriptive requirements draw from large LWR experience (many penetrations, large valves, normal containment leakage)

Page 56: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC56

GDCs 55, 56 – Containment Isolation

NuScale Design Considerations }}3(a)

• Small lines and isolation valves• Very low-leakage containment vessel• Harsh containment vessel (CNV) conditions

}}3(a)

{{

{{

Page 57: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC57

GDCs 55, 56 – Containment Isolation

NuScale Design Considerations• Proposed design: {{

}}3(a)

Page 58: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC58

GDCs 55, 56 – Containment Isolation

NuScale Design Considerations

}}3(a)

{{

Page 59: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC59

GDCs 55, 56 – Containment Isolation

Statement of Regulatory Gap

{{

}}3(a)

GDCs 55 and 56 require one CIV inside containment and one outside containment

GAP

Page 60: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC60

GDC 57 – Containment Isolation

Regulatory Requirement Summary

• GDC 57 “closed system”

– line penetrating containment that is not part of RCPB and notconnected directly to containment atmosphere

• Must have– one containment isolation valve outside containment

– locked closed, automatic, or remote manual

– located “as close to containment as practical”

Page 61: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC61

GDC 57 – Containment Isolation

Regulatory Purpose

• Same purpose as GDCs 55 and 56.

• Follows the same “two isolation barrier” approach– for closed systems, first barrier is the closed system itself

– failures must occur in system inside containment and the CIV forrelease outside containment

Page 62: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC62

GDC 57 – Containment Isolation

• Most closed systems will meet GDC 57 (MS and FW)

}}3(a)

NuScale Design Considerations

{{

Page 63: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC63

GDC 57 – Containment Isolation

Statement of Regulatory Gap

{{

}}3(a)

GDC 57 requires one CIV outside containment

GAP

Page 64: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC64

GDCs 55-57 – Containment Isolation

Pre-Application PlanProposed resolution: departures from GDCs 55, 56 & 57

}}3(a)

– detailed design information required to support departures

Future interactions: specific engagement as design progresses

{{

Page 65: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC65

GDCs 55-57 – Containment Isolation

Gap Analysis Impact

• Not addressed in Gap Analysis Summary Report

– new gap due to design progression

• SRP sections that address rule

– Section 6.2.4, “Containment Isolation System”

Page 66: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC66

GDC 40 – Testing of Containment Heat Removal System

Regulatory Requirement SummaryThe containment heat removal system shall be designed to permit appropriate periodic pressure and functional testing to assure (1) the structural and leaktight integrity of its components, (2) the operability and performance of the active components of the system, and (3) the operability of the system as a whole…

Page 67: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC67

GDC 40 – Testing of Containment Heat Removal System

Regulatory Purpose• Ensures reliable performance of containment heat

removal system (required by GDC 38)

• Contemplates testing of active systems such as

– containment spray system

– fan cooler system

Page 68: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC68

GDC 40 – Testing of Containment Heat Removal System

NuScale Design Considerations • No active containment heat removal system as

contemplated by GDC 40– containment vessel submerged in the reactor pool (UHS)

– heat removal by passive heat transfer through the containment vessel steel walls

– no reliance on electrical power, valve actuation, cooling water flow, or other active systems or components

• Passive heat removal performance established as part of design and test program for design certification

Page 69: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC69

GDC 40 – Testing of Containment Heat Removal System

Statement of Regulatory Gap

NuScale design has no active

containment heat removal systems

The containment heat removal

system shall be designed to permit

appropriate periodic pressure

and functional testing

GAP

Page 70: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC70

GDC 40 – Testing of Containment Heat Removal System

Pre-Application PlanProposed resolution: no departure required• GDC 40 does not apply to the NuScale design

Future interactions: DSRS development only

Page 71: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC71

GDC 40 – Testing of Containment Heat Removal System

Gap Analysis Impact

• Identified in Gap Analysis Summary Report

• SRP sections that address rule– Section 6.2.2, “Containment Heat Removal Systems”

Page 72: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC72

GDC 41 – Containment Atmosphere Cleanup

Regulatory Requirement Summary

Systems to control fission products, hydrogen, oxygen, and other substances which may be released into the reactor containment shall be provided as necessary to

• reduce… the concentration and quality of fission products released to the environment following postulated accidents

• control the concentration of hydrogen or oxygen and other substances in the containment atmosphere following postulated accidents to assure that containment integrity is maintained

Page 73: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC73

GDC 41 – Containment Atmosphere CleanupRegulatory Purpose

• Provide for containment atmosphere cleanup systems “as necessary” to

– reduce fission product release from containment leakage

– reduce hydrogen or oxygen if required to protect containment integrity from hydrogen combustion

• Contemplates systems such as

– containment spray system

– engineered safety feature (ESF) ventilation filtration system

– hydrogen igniters and hydrogen and oxygen monitors

Page 74: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC74

GDC 41 – Containment Atmosphere Cleanup

NuScale Design Considerations

• Fission product release passively controlled by– reactor module configuration

– containment vessel design leakage rate

• Containment integrity assured by – robust containment vessel design

– low oxygen content

• Systems to control fission products and combustible gasses not anticipated to be necessary

Page 75: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC75

GDC 41 – Containment Atmosphere Cleanup

Statement of Regulatory Gap

Containment atmosphere

cleanup systems are not necessary

for NuScale design

Containment atmosphere

cleanup systems shall

be provided as necessary…

GAP?

Page 76: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC76

GDC 41 – Containment Atmosphere Cleanup

Pre-Application Plan

Proposed resolution: no departure required

• absence of atmosphere cleanup systems in the NuScale design is consistent with the “as necessary” provision of GDC 41

Precedent: AP1000 similar approach (fission products)

Future interactions: DSRS development only

Page 77: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC77

GDC 41 – Containment Atmosphere Cleanup

Gap Analysis Impact

• Identified in Gap Analysis Summary Report

• Related SRP sections

– Section 6.2.5, “Combustible Gas Control in Containment”

– Section 6.5.1, “ESF Atmosphere Cleanup Systems”

– Section 6.5.2, “Containment Spray as a Fission Product Cleanup System”

– Section 6.5.3, “Fission Product Control Systems and Structures”

– Section 6.5.5, “Pressure Suppression Pool as a Fission Product Cleanup System”

Page 78: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC78

GDCs 42 and 43 – Inspection and Testing of Containment Atmosphere Cleanup Systems

Regulatory Requirement Summary

The containment atmosphere cleanup systems shall be designed to permit appropriate periodic• inspection of important components...to assure the

integrity and capability of the systems. [GDC 42]• pressure and functional testing to assure structural and

leak-tight integrity of components, operability and performance of active components, and operability of the systems as a whole. [GDC 43]

Page 79: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC79

GDCs 42 and 43 – Inspection and Testing of Containment Atmosphere Cleanup Systems

Regulatory Purpose

• Ensures performance and reliability of containment atmosphere cleanup systems provided to meet GDC 41

• Contemplates systems such as

– containment spray system and pressure suppression devices

– ESF ventilation filtration system

– hydrogen igniters and hydrogen and oxygen monitors

Page 80: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC80

GDCs 42 and 43 – Inspection and Testing of Containment Atmosphere Cleanup Systems

Statement of Regulatory Gap

Containment atmosphere

cleanup systems are not included in

the NuScale design

Containment atmosphere

cleanup systems shall

be designed to permit inspection

and testing

GAP?

Page 81: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC81

GDCs 42 and 43 – Inspection and Testing of Containment Atmosphere Cleanup Systems

Pre-Application PlanProposed resolution: no departure required

• Do not anticipate the need for atmosphere cleanup systems per GDC 41

• GDCs 42 and 43 do not apply to NuScale design

Precedent: AP1000

Future interactions: DSRS development only

Page 82: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC82

GDCs 42 and 43 – Inspection and Testing of Containment Atmosphere Cleanup Systems

Gap Analysis Impact

• Identified in Gap Analysis Summary Report

• Related SRP sections

– Section 6.2.5, “Combustible Gas Control in Containment”

– Section 6.5.1, “ESF Atmosphere Cleanup Systems”

– Section 6.5.2, “Containment Spray as a Fission Product Cleanup System”

– Section 6.5.3, “Fission Product Control Systems and Structures”

– Section 6.5.5, “Pressure Suppression Pool as a Fission Product Cleanup System”

– Section 6.6, “Inservice Inspection and Testing of Class 2 and 3 Components”

Page 83: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC83

50.34 – Contents of applications; technical information

(f) Additional TMI-related requirements

Page 84: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC84

50.34(f)(2)(xv) – Containment PurgingRegulatory Requirement Summary

Provide a capability for containment purging/venting designed to minimize the purging time consistent with ALARA principles for occupational exposure.

Provide and demonstrate high assurance that the purge system will reliably isolate under accident conditions.

Page 85: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC85

50.34(f)(2)(xv) – Containment PurgingRegulatory Purpose

• Large LWRs: containment personnel access during operations necessitates containment purging/venting

• Post-TMI concern over radiological consequences of containment purging/venting

– balance occupational and public exposure from normal purging

– risk of accident while purging system open

• Requires actions to restrict purging/venting and reliably isolate on demand

Page 86: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC86

50.34(f)(2)(xv) – Containment PurgingNuScale Design Considerations

• No containment purging/venting system as contemplated by rule– Compact containment vessel does not allow for personnel access

during operation

– Containment only opened during cold shutdown

– NuScale containment remains sealed during operations, no direct path to the environs

Page 87: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC87

50.34(f)(2)(xv) – Containment PurgingStatement of Regulatory Gap

NuScale design does not include a

purging/venting system

Provide purging designed to

minimize purging time, reliable

isolation

GAP?

Page 88: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC88

50.34(f)(2)(xv) – Containment PurgingPre-Application Plan

Proposed resolution: no exemption required• Containment purging/venting requirements are not

technically relevant to NuScale design

Future interactions: DSRS development only

Page 89: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC89

50.34(f)(2)(xv) – Containment PurgingGap Analysis Impact

• Identified in Gap Analysis Summary Report

• SRP sections that address rule

– Section 6.2.4, “Containment Isolation System”

– BTP 6-4, “Containment Purging During Normal Plant Operations”

Page 90: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC90

50.34(f)(2)(xii) – AFW System Actuation and Flow Indication

Regulatory Requirement Summary Provide automatic and manual auxiliary feedwater (AFW) system initiation, and provide auxiliary feedwater system flow indication in the control room (TMI Action Item II.E.1.2)

Page 91: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC91

50.34(f)(2)(xii) – AFW System Actuation and Flow Indication

Regulatory Purpose• Ensure timely initiation of the AFW system with loss of feedwater

(GDC 20)

• Provide instrumentation and controls for direct verification of AFW system performance (GDC 13)

NuScale Design Considerations• NuScale design does not include an AFW system

Page 92: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC92

50.34(f)(2)(xii) – AFW System Actuation and Flow Indication

Statement of Regulatory Gap

NuScale design does not include an AFW system

PWR designs are required to have automatic and manual AFW

system initiation and AFW system flow indication in the control room

GAP

Page 93: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC93

50.34(f)(2)(xii) – AFW System Actuation and Flow Indication

Pre-Application PlanProposed resolution: no exemption required• 50.34(f)(2)(xii) is not technically relevant to NuScale

designFuture interactions: DSRS development only

Page 94: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC94

50.34(f)(2)(xii) – AFW System Actuation and Flow Indication

Gap Analysis Impact• Different approach from Gap Analysis Summary Report

– Previously proposed AFW requirement would apply to DHR

– DHR actuation and indication designed will be for NuScale-specific transients and system characteristics

• SRP sections that address rule– DSRS Section 7.2, “System Characteristics”

– Section 10.4.9, “Auxiliary Feedwater System (PWR)”

– Chapter 15, “Transient and Accident Analysis”

Page 95: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC95

50.34(f)(1)(ii) – Auxiliary Feedwater Design Evaluation

Regulatory Requirement SummaryPerform an evaluation of the proposed auxiliary feedwater

system (AFWS), to include (applicable to PWRs only): (A) A simplified AFWS reliability analysis using event-tree

and fault-tree logic techniques. (B) A design review of AFWS.(C)An evaluation of AFWS flow design bases and criteria.

Page 96: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC96

50.34(f)(1)(ii) – Auxiliary Feedwater Design Evaluation

Regulatory Purpose• Post-TMI requirement to ensure reliable AFW capability

for large PWRs• Reliability requirement based on CE, B&W, and

Westinghouse plant-specific design bases • Design basis functions were intended to prevent and

mitigate small-break loss-of-coolant accidents (LOCAs)

NuScale Design Considerations• NuScale design does not include an AFW system

Page 97: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC97

50.34(f)(1)(ii) – Auxiliary Feedwater Design Evaluation

Statement of Regulatory Gap

NuScale design does not include an AFW system

Perform an evaluation of the

proposed auxiliary feedwater system

GAP?

Page 98: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC98

50.34(f)(1)(ii) – Auxiliary Feedwater Design Evaluation

Pre-Application PlanProposed resolution: no exemption required• 50.34(f)(1)(ii) is not technically relevant to NuScale

designFuture interactions: none anticipated

Page 99: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC99

50.34(f)(1)(ii) – Auxiliary Feedwater Design Evaluation

Gap Analysis Impact• Different approach from Gap Analysis Summary Report

– Previously proposed AFW requirement would apply to DHR

• SRP sections that address rule– Section 10.4.9, “Auxiliary Feedwater System (PWR)”

– Chapter 15, “Transient and Accident Analysis”

Page 100: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC100

50.34(f)(2)(iv) – Safety Parameter Display System

Regulatory Requirement SummaryProvide a plant safety parameter display console that will display to operators a minimum set of parameters defining the safety status of the plant, capable of displaying a full range of important plant parameters and data trends on demand, and capable of indicating when process limits are being approached or exceeded.

Page 101: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC101

50.34(f)(2)(iv) – Safety Parameter Display System

Regulatory Purpose• Post-TMI requirement to ensure reliable data capability

for operators• New consoles were necessary for existing plants• Most newer plants have integrated safety parameter

display system (SPDS) capabilities into the control room design and displays

Page 102: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC102

50.34(f)(2)(iv) – Safety Parameter Display System

NuScale Design Considerations• The NuScale SPDS will be integrated into the control

room human-system interface design• Dedicated SPDS display, but not a physically separate

SPDS console

Page 103: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC103

50.34(f)(2)(iv) – Safety Parameter Display System

Statement of Regulatory Gap

The NuScale design does not

include a separate SPDS console

Provide a plant safety parameter

display console. . .GAP?GAP?

Page 104: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC104

50.34(f)(2)(iv) – Safety Parameter Display System

Pre-Application PlanProposed resolution: no exemption required• Rule does not require a separate, stand-alone SPDS

console• 10 CFR 50.34(f)(2)(iv) is applicable and NuScale design

meets regulatory requirementsPrecedent: EPR (pending)

Future interactions: DSRS development only

Page 105: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC105

50.34(f)(2)(iv) – Safety Parameter Display System

Gap Analysis Impact

• Identified in Gap Analysis Summary Report

• SRP sections that address rule– Section 7.0, “Instrumentation and Controls - Overview of Review Process”

– Section 7.5, “Information Systems Important to Safety”

– Section 13.3, “Emergency Planning”

– Section 18, “Human Factors Engineering”

Page 106: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC106

SummaryRegulations that do not require departures• Design meets rule (9): specific approach warrants pre-application

interaction

• Not applicable (3): requirements addressing systems or features that are not present in the NuScale design

Departures from regulatory requirements• Exemptions (2): design does not literally meet regulatory requirement

• Other departures (6): GDCs or specific aspect of GDC that are not appropriate to apply to the NuScale design

– identify and justify departure in NuScale FSAR (i.e., DCD)

– consistent with introduction in 10 CFR 50, Appendix A

– no exemption required under 10 CFR 52.7 and 10 CFR 50.12

Page 107: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC107

Summary Table

Changed from gap analysis summary reportAdded to list in gap analysis summary report submittal

Proposed resolution Future 

engagement  10 CFR  Subject

1 50.54(m)(2)(i) and (iii) Minimum Licensed Operator Staffing Requirements   Exemption  Y 2 50.62(c)(1)   Reduction of Risk from ATWS Events   Potential Exemption  Y 3 50.44(c)(2)   Combustible Gas Control   Complies with rule Y 4 50, App. K   ECCS Evaluation Models   Complies with rule Y 5 50.34(f)(2)(vi)   Reactor Coolant System Venting   Complies with rule6 50.46a   Reactor Coolant System Venting   Complies with rule7 GDC 17   Electric power systems    Departure  Y 8 GDC 27 Combined reactivity control systems capability    Departure9 GDC 33   Reactor coolant makeup / inventory control Departure  Y 10 GDC 55 Containment isolation Departure  Y 11 GDC 56 Containment isolation Departure  Y 12 GDC 57 DHR / Containment isolation Departure  Y 13 GDC 40   Testing of containment heat removal system    Not applicable14 GDC 41   Containment atmosphere cleanup   Complies with rule15 GDC 42   Inspection of containment atmosphere cleanup systems   Not applicable16 GDC 43   Testing of containment atmosphere cleanup systems   Not applicable17 50.34(f)(2)(xv)   Containment Purging/Venting Capability and Isolation   Not technically relevant18 50.34(f)(2)(xii)   Auxiliary Feedwater System Actuation and Flow Indication   Not technically relevant19 50.34(f)(1)(ii)   Evaluation and Design Review of AFW System   Not technically relevant20 50.34(f)(2)(iv)   Safety Parameter Display System (SPDS)   Complies with rule

Page 108: Non-Proprietary Regulatory GAP Analysis Results ...Gap Analysis Results – Regulations Summary Table Proposed resolution Future engagement 10 CFR Subject 1 50.54(m)(2)(i) and (iii)

TMNonproprietary

© 2012 NuScale Power, LLC108

Feedback and Next Steps• 11 regulatory gaps require no further pre-application

discussion• 9 regulatory gaps are subjects of ongoing or future pre-

application discussions• Schedule for future interactions