AGENDA
# ITEM ACTION
1.1 Welcome and Introductions Superintendent Tracy Hayhurst
1.2 Project History and Costing ReviewSenior Manager, Major Capital
Projects & Building Partnerships Jeff Latto
1.3 Project Update Snyder Architects
1.4 Schedule Update Snyder Architects
1.5 Q&A
2
PROJECT UPDATEPERSPECTIVE VIEWS
view of addition from playground
view of addition and renovation area from parking lot
8
SCHEDULE UPDATE
Construction Documents: April 2017 - November 2017
Site Plan Approval: March 2017 - February 2018
Building Permit: October 2017 - March 2018
Construction: February 2018 - July 2019
Occupancy: July 2019