north commuter parkway project functional … · north commuter parkway project page 2 d r a f t...
TRANSCRIPT
2013
5/7/2013
North Commuter Parkway Project Functional Planning Study
North Commuter Parkway Project
Page 2
DRAFT
Executive Summary
In June 2012, City Council adopted the Integrated Growth Plan. One strategy within
that plan is the need to identify additional infrastructure (new roads and bridges) to
address the growing demands throughout the city.
A discussion about river crossings identified:
“The Perimeter Highway will serve a strategic role as a component of the
National Highway system and will serve some commuter traffic demand.
However it is also necessary to provide an additional river crossing to adequately
provide for commuter traffic between east side neighbourhoods and the north
end employment area. Likewise, a new route for traffic between west side
neighbourhoods and north end employment will also be required.”
The North Commuter Bridge crossing the South Saskatchewan River is required to
assist in addressing the travel demand of our rapidly growing city to the 500,000
population. The North Commuter Bridge will link the Marquis Industrial area with the
University Heights area, providing relief to the existing Circle Drive Bridge. The North
Commuter Bridge is not intended to function as a designated truck route; rather,
commercial trucks will utilize the Circle Drive bridges or the future Perimeter Highway.
This functional planning study is the initial step of planning this crossing. This study
evaluates the relative merits of crossings at particular locations, and how each crossing
contributes to transportation system performance in the future. Once a set of possible
alignments are identified, the merits and constraints of each alignment are examined
during different traffic projection scenarios (based on population growth projections).
Finally, the details of the required road network are planned.
Construction of the bridge will occur over a minimum of 2 full years. In order for the
bridge construction to be completed by 2016, all planning work, approvals and land
acquisition will be required to be completed by the end of 2013 in order to prepare
proper documentation to secure a contractor.
North Commuter Parkway Project
Page 3
DRAFT
The estimated cost of the bridge-only component of the project is $102.5 Million. This
cost estimate includes all planning and design, as well as the land acquisition for both
the bridge itself and the connecting roadways. The construction costs include only
those for the bridge itself.
The estimated cost of the connecting roadways on the east side of the river is $58.0
Million. It is expected that the construction can be staged over several years; although,
poor traffic operations along staged roadways may advance completion of some
segments.
The estimated cost of the entire project, at final build-out is $160.5 Million.
Depending on the exact configuration and staging of the connecting arterial roads,
opening day average daily traffic volumes (ADT) for the North Commuter Bridge are
expected to be between 14,600 and 21,700 vehicles/day.
North Commuter Parkway Project
Page 4
DRAFT
Table of Contents
Executive Summary ........................................................................................................ 2
Table of Contents ............................................................................................................ 4
1. Introduction ........................................................................................................... 5
2. Route Selection .................................................................................................... 9
3. Proposed Arterial Cross Sections & Design Elements ....................................... 12
4. Northeast Swale Crossing .................................................................................. 16
5. River Crossing Details ........................................................................................ 17
Horizontal Alignment .......................................................................................... 17
Vertical Alignment ............................................................................................... 17
Plan & Profile ...................................................................................................... 18
Staging Opportunities ......................................................................................... 18
6. Property Impacts ................................................................................................ 20
7. Initial Budget Estimate ........................................................................................ 22
8. Projected Traffic Operations ............................................................................... 24
300,000 Population ............................................................................................. 24
400,000 Population with Perimeter Highway ...................................................... 25
400,000 Population without Perimeter Highway ................................................. 25
9. Public Consultation ............................................................................................. 28
10. Recommendations .............................................................................................. 29
List of Figures .......................................................................................................... 31
North Commuter Parkway Project
Page 5
DRAFT
1. Introduction
In June 2012, City Council adopted the Integrated Growth Plan. One strategy within
that plan is the need to identify additional infrastructure (new roads and bridges) to
address the growing demands throughout the city.
The discussion about river crossings identified:
“The Perimeter Highway will serve a strategic role as a component of the National
Highway system and will serve some commuter traffic demand. However it is also
necessary to provide an additional river crossing to adequately provide for commuter
traffic between east side neighbourhoods and the north end employment area.
Likewise, a new route for traffic between west side neighbourhoods and north end
employment will also be required.”
The North Commuter Bridge crossing the South Saskatchewan River is required to
assist in addressing the travel demand of our rapidly growing city to the 500,000
population. The North Commuter Bridge will link the Marquis Industrial area with the
University Heights area, providing relief to the existing Circle Drive Bridge. The North
Commuter Bridge is not intended to function as a designated truck route; rather,
commercial trucks will utilize the Circle Drive bridges or the future Perimeter Highway.
Four alignments were examined using a travel demand model and a 300,000 population
scenario. In this 300,000 population scenario, Circle Drive South is complete, as well
as the Kensington, Stonebridge, Rosewood, Evergreen, Willowgrove, and Hampton
Village neighbourhoods. The first neighbourhood in the Holmwood sector is complete,
as well as the second Blairmore (north of 33rd St) and second University Heights
(northeast of Evergreen) neighbourhoods.
The four north bridge options examined (see Figure 1):
• Pinehouse Drive, 2-lane minor arterial (50 km/hr) bridge
• Lenore Drive, 4-lane major arterial (50 km/hr) bridge
• Marquis Drive, 4-lane major arterial (60 km/hr) bridge
• Perimeter Highway, 4-lane controlled access highway (110 km/hr) bridge
North Commuter Parkway Project
Page 6
DRAFT
Of the four possible alignments for a north river crossing, the connection at Marquis
Drive is superior and is recommended.
Table 1 shows the relative merits and impacts on the transportation network of adding a
bridge at each location. The estimated total user delay and fuel savings in the peak
hours represents the expected system-wide improvements provided by that connection.
This aggregates such things as intersection delay and improved travel times (reduced
delay) at a network-scale; individual links and nodes in the model can be expected to
receive different outcomes depending on the connection tested.
Three locations provide similar returns on investment; Perimeter Highway provides the
smallest return for the largest investment.
Table 2 summarizes the relative merits of each proposed crossing location. In general,
the greatest advantage for the Marquis Drive location is the leveraging of existing
transportation infrastructure relative to current development plans. The biggest
disadvantage is the impact on a single private industrial site. The extension of
McOrmond Drive also will require an amendment to the University Heights Sector Plan
(to accommodate the new roads), a crossing of the Northeast Swale for the extension of
McOrmond Drive, and re-alignment of the intersection of McOrmond Drive and Fedoruk
Drive (under construction in 2012).
Traffic projections for the 300,000 population (based on the “old” growth plan) show the
proposed bridge significantly supplementing the available capacity for trips between the
employment center developing in the Marquis Industrial Area and the suburban
expansion in the University Heights and Holmwood sectors.
The Perimeter Highway river crossing is a Saskatchewan Ministry of Highways &
Infrastructure project, the two advantages of this crossing are the early start to the
development of Perimeter Highway, and the very high-capacity river crossing that would
be constructed. However, the City of Saskatoon may have little input on project timing,
Perimeter Highway is a controlled access highway and by design will have limited
integration with City of Saskatoon road infrastructure, and ultimately, it would provide a
North Commuter Parkway Project
Page 7
DRAFT
less direct route between the Marquis Industrial Area and University Heights and
Holmwood Sectors.
Table 1: Corridor Screening at 300,000 Population Bridge Location
Estimated Total Delay & Fuel Savings
(in the Peak Hours)
Initial Cost
Estimate
Pay-back period (years)
Estimated
ADT Pinehouse Drive, 2-lane minor arterial, 50 km/hr (Central Ave. to Spadina Cres.)
$14.9M $52.6M 3.5 23,200
Lenore Drive, 4-lane arterial, 50 km/hr (Central Ave. to Whiteswan Dr.)
$20.2M $59.6M 3.0 27,800
Marquis Drive, 4-lane arterial , 60 km/hr (Central Ave. to Wanuskewin Rd.)
$21.9M $78.7M 3.6 21,200
Perimeter Highway, 4-lane highway, 110 km/hr (Central Ave. to Wanuskewin Rd.)
$20.6M $243.0M 11.8 19,200
North Commuter Parkway Project
Page 8
Table 2: Relative Merits of Each River Crossing Corridor Pinehouse
Drive (Central Ave. to Spadina Cres.)
Lenore Drive (Central Ave. to Whiteswan Dr.)
Marquis Drive (McOrmond Dr. to Wanuskewin Rd.)
Perimeter Highway (Central Ave. to Wanuskewin Rd.)
Traffic impact on adjacent
residential neighbourhoods
High High (school zones)
None None
Leverages existing road infrastructure
Yes Yes Some No
Impact on private property
Little Little Yes High
Requires new roads to be
constructed
Little Some: extend Central Avenue
Significant: extend Central Avenue, McOrmond Drive
Extensive: extend Central Avenue, McOrmond Drive, build Perimeter Highway
Provides good network
connectivity
No Yes Yes Limited
Traffic impacts on 51 st St. &
Wanuskewin Rd.
Little Increased traffic
Little Little
Traffic impacts on Central Ave. &
Attridge Dr.
Increased traffic
Increased traffic
Decreased traffic, improved traffic operations
Increased traffic
Traffic impacts on McOrmond Dr.
& College Dr.
None None Improved operations
None
Impact on Northeast Swale
None None Yes Yes
North Commuter Parkway Project
Page 9
DRAFT
2. Route Selection
Originally identified as a river crossing connecting Central Avenue to Wanuskewin
Road, the Marquis Drive river crossing provided some benefit to Circle Drive; however,
at the 300,000 population scenario much of the utility of the river crossing is not realized
from the expanding University Heights and Holmwood Sectors. University Heights
traffic would likely be concentrated on Central Ave at either Attridge Drive or Fedoruk
Drive; Holmwood traffic would likely be concentrated on McOrmond Drive, and then
dispersed along College and Attridge Drives, some traffic would be diverted from Circle
Drive to Central Avenue and connections to the east abutment.
The utility of the Marquis Drive bridge connection is completely captured by extending
McOrmond Drive from Fedoruk Drive to Central Avenue and the east abutment of the
proposed bridge. This provides a direct link between the Holmwood Sector and the
Marquis Industrial Area via McOrmond Drive. This direct connection is both shorter in
distance and in travel time. As well, the provision of an alternate river crossing to Circle
Drive should help accommodate the increasing traffic demands on that bridge.
Figures 2 and 3 show the expected traffic volumes on the corridor at a population
projection of 300,000 people.
The 300,000 population scenario of the “old” suburban growth plan completes all
neighbourhoods currently planned and in progress. At the current annual population
growth rate of 2.5%; the 300,000 population may be reached as soon as 2024.
Confidence in the 300,000 scenario should be relatively high, as this assumes the City
will continue to grow in the ways Saskatoon has been growing recently.
Impacts on Attridge Drive & Central Avenue:
• In both the AM and PM peak hours, the existing problematic movements (the
southbound right-turn and eastbound left-turn) are marginally improved by the
diversion of demand (compared to the no bridge operation). Further intersection
improvements may be required to improve operation.
North Commuter Parkway Project
Page 10
DRAFT
Impacts on McOrmond Drive & Highway 5:
• McOrmond Drive through movements increase in expected volumes (compared
to the no bridge operation) and both left- and right-turn demand volumes
decrease in the peak hours simplifying traffic operations.
• In particular, the southbound right-turn demand in both AM and PM peak hours is
reduced, and northbound left-turn demand is reduced and eliminates the need for
a loop in the northeast quadrant; instead a basic left turn phase at a signalized
intersection should be adequate.
Impacts on Circle Drive:
• The proposed North Commuter Bridge provides a more direct travel path
between the North Industrial Area and the developing neighbourhoods within the
University Heights and Holmwood Sectors; the impacts of this additional river
crossing are shown in Table 3. In general, all existing river crossings are
expected to benefit from reduced traffic demand with the proposed North
Commuter Bridge. The largest impacts are expected on the Circle Drive South
crossing.
• Within the transportation model, the proposed North Commuter Bridge “unloads”
demand on Circle Drive between Idylwyld Drive and Attridge Drive; however,
these improvements in travel time “pull” trips towards the improved corridor,
further unloading each river crossing. It appears the utility of the Circle Drive
South river crossing was highest with a congested Circle Drive bridge but with
the alignment of desire lines and the network north of Circle Drive, trips and
travel demand more closely align to the growth and development plan.
Confidence in the 400,000 population scenario of the “old” suburban growth plan is
much lower. This growth plan does not include a significant infill component; nor does it
incorporate the impacts of changing the way Saskatoon grows as described by the
Strategic Plan, the Vision or the implementation of the policies of the Integrated Growth
Plan. However, until the policies and plans in those documents are developed, the “old”
North Commuter Parkway Project
Page 11
DRAFT
suburban grow plan will be a “worst-case” scenario for planning the North Commuter
Bridge.
Table 3: Relative Impacts on River Crossing Traffic Volumes at 300,000 and 400,000 Populations with the North Commuter Bridge (relative to no North Commuter Bridge) Bridge
300,000 Population
400,000 Population
Circle Drive -11% -18% University -7% -15% Broadway -8% -17% Traffic n/a -9% Buckwold -6% -16% Circle Drive South -27% -27%
At the 400,000 population scenario, the extension of McOrmond Drive to the east
abutment of the bridge provides significantly shorter (quicker) routes than the original
College Drive-to-Circle Drive and McOrmond Drive-to-Attridge Drive-to-Central Avenue
routes.
Figures 4 and 5 show the expected traffic volumes on the corridor at a population
projection of 400,000 people, without Perimeter Highway.
Figures 6 and 7 show the expected impacts on traffic volumes on the corridor at a
population of 400,000 people, if Perimeter Highway were available. Perimeter Highway
has the potential to divert enough traffic from the proposed river crossing to suggest a
four-lane cross section is adequate; however, if Perimeter highway is delayed or
relocated, the river crossing may require six driving lanes. Table 4 summarizes the
projected Average Daily Traffic (ADT) for the North Commuter Bridge corridor.
Table 4: Projected Average Daily Traffic on Proposed North Commuter Bridge (veh./day) 300,000
Population without
Perimeter Highway
400,000 Population
without Perimeter Highway
400,000 Population
with Perimeter Highway
North Commuter Bridge 35,400 65,700 49,600
North Commuter Parkway Project
Page 12
DRAFT
3. Proposed Arterial Cross Sections & Design Elements
McOrmond Drive south of Fedoruk Drive is a controlled access arterial road, with a
raised centre median and sound attenuation berms on either side adjacent to residential
areas. Controlled access arterial roads serve the mobility demands of drivers quite well;
however, they do not serve the needs of transit patrons, pedestrians and cyclists very
well. Nor do they facilitate neighbourhood development; instead they function to
separate neighbourhoods,
McOrmond Drive north of Fedoruk Drive is proposed to be an urban arterial road with
frontage, running through the centers of the future University Heights neighbourhoods.
Access management will be an important element of this type of arterial road to
maintain the mobility needs of its users; driveway access to McOrmond Drive should be
prohibited. Frontage, which may or may not include on-street parking, will have to be
designed carefully to meet the needs of pedestrians, cyclists and transit users.
Figure 8 shows the proposed McOrmond Drive arterial road alignment from Fedoruk
Drive to the proposed river crossing. Figure 9 shows the proposed arterial cross
sections along McOrmond Drive from Fedoruk Drive to the proposed river crossing.
The traffic projections at both the 300,000 and 400,000 population scenarios show the
need for a four-lane arterial cross section between Fedoruk Drive and Central Avenue.
In the absence of Perimeter Highway, the river crossing should allow expansion from a
four-lane to a six-lane bridge; this will require the development of a six-lane arterial on
the east-bank between Central Avenue and the east bridge abutment. The proposed
cross section sets aside a wide boulevard for possible expansion in the future to six-
lanes.
The intersection of Central Avenue and McOrmond Drive is projected to have large turn
and through traffic demands in the peak hours in the 400,000 population scenario with
or without Perimeter Highway. An unconventional high-volume intersection will be
considered – a “town center” appears to be a promising solution (a set of intersecting
one-way couplets separating opposing traffic by at least one city block). The
intersection configuration will be determined through a subsequent functional planning
North Commuter Parkway Project
Page 13
DRAFT
process. The “town center” may also be the appropriate solution to support the
adjacent land use. Within the University Heights Sector Plan, the area around this
intersection is described as “mixed-use core area”. Street-oriented commercial
developments are expected, requiring on-street parking, wider sidewalks and well-
planned crosswalks.
The residential neighbourhoods within the University Heights Sector are expected to be
designed with McOrmond Drive as a major roadway near the centre of each
neighbourhood. The arterial road is expected to have frontage, but also have access
management.
As a commuter system, the operating speed of the proposed roadway and bridge west
of Central Avenue is expected to be 70 km/hr. The curves along this section of
McOrmond Drive are superelevated by removing the crown; wide intersection spacing,
no driveways and strict access management will be required to ensure high operating
speeds and safety.
The operating speed of the proposed roadway east of Central Avenue is expected to be
50 km/hr. The curves along this roadway are not superelevated to permit roadside
development and discourage higher driving speeds. This lower-speed zone is intended
to operate as the center of adjacent residential neighbourhoods and will fully embrace
the principles of Complete Streets and the Integrated Growth Plan.
Most of the proposed roadway will be centered within residential neighbourhoods,
therefore the road should be designed to accommodate infrequent large trucks, but the
extension of McOrmond Drive is not intended to operate as a truck route.
Transit is expected to use some or the entire proposed road network in the future.
The combination of bikeway and sidewalk is provided along the entire length of the
proposed arterial road. Marquis Drive, west of Wanuskewin Road has the path on the
north side; along the west bank, the owner of the adjacent parcel has requested the
sidewalk be located only on the south side of the road. Through the University Heights
residential neighbourhoods, a sidewalk and bikeway will be provided on both sides of
North Commuter Parkway Project
Page 14
DRAFT
the roadway. Through the Northeast swale, the sidewalk may be expanded in width to
accommodate recreational uses within the swale.
Off-street bikeways will be provided on all arterial roads north of Fedoruk Drive and
extending across the bridge. The bikeways will terminate at the intersection of Marquis
Drive and Wanuskewin Road and tie-in to the existing bike lanes and multi-use
pathways along Wanuskewin Road and Marquis Drive.
Table 5 shows the design criteria used to develop the proposed cross sections.
North Commuter Parkway Project
Page 15
DRAFT
Table 5: Design Criteria Element Value Design Speed 80 km/hr west of Central Avenue,
60 km/hr east of Central Avenue, 60 km/hr along Central Ave
Desired Posted Speed 70 km/hr west of Central Avenue, 50 km/hr east of Central Avenue, 50 km/hr along Central Ave
Vertical Curb & Gutter 200mm Separate Sidew alk 1.5m wide both sides of arterial road,
No sidewalk provided on north side of river crossing
Separate Bike way 2.0m wide, both sides Access Management No driveways, on-street parking permitted Street -oriented Development Frontage encouraged east of Central
Avenue Design Vehicle COS Transit Bus Control Vehicle WB-20 Not intended to be a truck route Maximum Bridge Grade 3.0% Driving lanes 3.6m Crossfall 2.5% Super -elevation Remove crown west of Central Avenue,
None east of Central Avenue Minimum centreline radius curve 400m Perimeter Highway Offset Approximately 450m Concept b ridge abutments Maximum 8.0m McOrmond Drive Central Ave. – Wanuskewin Rd.
4-lane cross section, wide ROW
McOrmond Drive Central Ave. – Fedoruk Dr.
4-lane cross section
Central Ave nue McOrmond Dr. – Fedoruk Dr.
4-lane cross section
North Commuter Bridge (River Crossing)
4-lane cross section Raised centre median 1.0m left and right outside shoulders 2.0m bikeways, both sides 1.5m sidewalk, south side only
North Commuter Parkway Project
Page 16
DRAFT
4. Northeast Swale Crossing
In all population scenarios, the extension of McOrmond Drive (through the swale) to the
east abutment of the bridge (Figure 8) provides significantly shorter (quicker) routes
than the alternatives: Fedoruk Drive-to-Central Avenue or McOrmond Drive-to-Attridge
Drive-to-Central Avenue routes for residents in the University Heights sector.
The Northeast Swale is an important ecological resource and has a specific
management plan. The extension of McOrmond Drive through the Northeast Swale
was located after extensive discussions with the Meewasin Valley Authority (MVA) to
reduce the impact of the crossing on the swale and to preserve the largest continuous
blocks of grasslands and wetlands. Development Guidelines and a Resource
Management Plan for the Northeast Swale were produced by the MVA in 2013.
The cross-section of the arterial road has been chosen to reduce the attractiveness of
the right-of-way to wildlife by eliminating the center median. The driving lanes are
narrowed to reduce the entire paved surface and encourage drivers to lower their
vehicle speeds. At both ends of the parkway cross section “Wildlife Crossing” and “No
Stopping” signs should be installed. The MVA will be designing observation areas
along the multi-use trail in one or more locations within the swale; “Pedestrian Crossing”
signs will have to be installed along with enhanced pedestrian crossing facilities.
The MVA desires dark-sky compliant street lighting through the swale.
North Commuter Parkway Project
Page 17
DRAFT
5. River Crossing Details
Horizontal Alignment
Four options were examined (see Figure 10):
A. Continuation of Marquis Drive; this is the preferred option. Wanuskewin Road
will be an at-grade intersection. This option leverages almost all the existing
road infrastructure on Marquis Drive and Wanuskewin Road. A simple 90°
intersection can be constructed on Wanuskewin Road. One parcel of private
property would be impacted (on the west side of the river).
B. Southward deflection of Marquis Drive east of Arthur Rose Avenue, an at-grade
intersection could be constructed at Wanuskewin Road; the intersection
geometry would be skewed and accommodation of pedestrian crossings and
right-turns would be more complex. Several parcels would be impacted.
C. Southward deflection of Marquis Drive at Arthur Rose Avenue, an at-grade
intersection could be constructed at Wanuskewin Road; the intersection
geometry is more complex because it would have to be constructed and operate
on a curve. Several parcels would be impacted.
D. Re-alignment of the river crossing to 71st Street was considered, but rejected
because of its proximity to proposed Perimeter Highway and the lack of
connecting road infrastructure. One parcel of private property would be
impacted.
Vertical Alignment
An at-grade intersection of Marquis Drive and Wanuskewin Road is preferred; it can
provide full access between the connecting roadways.
A grade-separation (Marquis Drive below Wanuskewin Road) was examined; it would
be highly disruptive to existing land access from Wanuskewin Road (which would be
raised) and completely disconnect land access from Marquis Drive (which would be
lowered) east of Arthur Rose Avenue.
North Commuter Parkway Project
Page 18
DRAFT
• The resulting interchange cannot provide full access, and Arthur Rose Avenue
would have to be upgraded between Wanuskewin Road and 71st Street to
accommodate larger traffic volumes and signalized traffic control.
• The original intention for this bridge and connecting roadways is to provide an
arterial roadway; an interchange would introduce the expectation that the bridge
and roadways would function as an expressway with higher operating speeds.
Plan & Profile
Figure 11 shows the plan and profile of the proposed North Commuter Bridge.
Establishing existing ground at the intersection of Marquis Drive and Wanuskewin Road
controls the start of any possible vertical curves, essentially maintaining the west
abutment at or near existing ground elevation; the east abutment elevation can vary,
although to reduce embankment volumes it is also likely to be near the existing
elevation. This will require a grade on the proposed river crossing. For pedestrian and
cyclist use, a grade of less than 3% is desirable.
Staging Opportunities
Traffic projections for the 300,000 and 400,000 population show the need for a four-lane
cross section for the entire length of McOrmond Drive and the river crossing; given
recent population growth the entire proposed system of connecting roadways should be
available on opening day. Constructing a 4-lane arterial road connecting to
Wanuskewin road and Marquis Drive and a 4-lane arterial bridge will require 4-lane
connecting arterial roads on the east bank; there are limited opportunities to stage the
arterial roads (the typical 2-lane and later expansion to 4-lane) without creating traffic
bottlenecks and very vulnerable connections.
The recommendation for a 4-lane bridge and McOrmond Drive is based on the
assumption that the Proposed Perimeter Highway is completed by the Province of
Saskatchewan before the City of Saskatoon reaches the 400,000 population. That said,
it is recommended that the right-of-way be set aside to accommodate a later expansion
of McOrmond Drive (between Wanuskewin Road and Central Avenue) to 6-lanes. The
bridge foundations and piers should also be designed and constructed to support a
possible future expansion to 6-lanes, if Perimeter Highway is delayed.
North Commuter Parkway Project
Page 19
DRAFT
The Opening Day (November 2016) traffic projection corresponds to a population of
approximately 260,000 people (Table 6). The projected ADT for opening day is 21,700
veh./day, assuming that all arterial connections are completed and available.
Table 6: Relative Impacts on River Crossing Traffic Volumes at 260,000 with the North Commuter Bridge (relative to no North Commuter Bridge) Bridge
Relative Traffic Impacts
Circle Drive -9% University -5% Broadway -3% Traffic n/a Buckwold -3% Circle Drive South -17%
The river crossing should be designed to accommodate a possible future expansion to
six lanes from four, on the assumption that Perimeter Highway may not be available as
quickly as the traffic demands require.
Marquis Drive between Wanuskewin Road and the river crossing should be designed
and constructed as a four-lane cross section on opening day.
McOrmond Drive between Central Avenue and the river crossing should be constructed
with four lanes at opening day and the later expansion to six lanes if required. The
staging of the remaining arterial roads within the University Heights sector reduce the
utility of the crossing for opening day traffic volumes for the North Commuter Bridge
(see Table 7). If both McOrmond Drive and Central Avenue north of Fedoruk Drive are
provided, two-lanes should be adequate for opening day, although completion of
McOrmond Drive may be required relatively soon afterward, depending on the build-out
of the adjacent residential neighbourhoods. Staged construction of these arterial roads
(initial 2-lane and later expansion to 4-lane) should be planned about the median, that
is, build the median and a driving lane on either side, include street lighting in that
median.
If only two-lanes of Central Avenue north of Fedoruk Drive are built for opening day
(McOrmond Drive is not), traffic volumes on the bridge are expected to be relatively
North Commuter Parkway Project
Page 20
DRAFT
modest (14,600 ADT), and during the peak hours individual lanes may be operating at
reduced levels of service.
If only two-lanes of McOrmond Drive north of Fedoruk Drive are built for opening day
(Central Avenue is not), traffic volumes on the bridge are expected to be modest
(16,100 ADT), and during peak hours individual lanes will be operating at reduced levels
of service.
Table 7: Projected Traffic Volumes (veh./day) at 260,000 population (Opening Day), for Staged Development of the University Heights Arterial Roads
All four-lane
arterials,
four-lane
bridge
All two-lane
arterials,
four-lane
bridge
Two-lane
McOrmond
Drive,
NO Central
Avenue
Two-lane
Central
Avenue,
NO
McOrmond
Drive
North Commuter
Bridge
21,700 20,700 16,100 14,600
McOrmond
Drive
14,400 13,00 16,100 n/a
Central
Avenue
7,300 7,700 n/a 14,600
The functional plan for the intersection of Marquis Drive and Wanuskewin Road is
shown in Figure 12; expansion to accommodate a 6-lane Marquis Drive and North
Commuter Bridge is shown in Figure 13.
6. Property Impacts
Figure 14 shows the preliminary property acquisition plan from Wanuskewin Road to
McOrmond Drive. The right-of-way shown in Figure 14 will have to be modified to
incorporate toe-of-slope estimates, depending on the ultimate vertical alignment of the
proposed river crossing. Construction easements will be required, but are not shown.
North Commuter Parkway Project
Page 21
DRAFT
On the west approach to the proposed bridge, the entire proposed right-of-way for the
recommended alignment is currently owned by Akzo Nobel.
• An Offer to Purchase has been made by the City of Saskatoon, but not yet
accepted by Akzo Nobel.
• Akzo Nobel has cooperated fully with the City of Saskatoon and has provided
copies of Environmental Site Assessments (ESA’s). A former waste disposal site
is identified within the ESA’s provided. The material within the site has been
characterized.
• An Environmental and Geotechnical Engineering Consultant has been retained
to review the documents provided by Akzo Nobel; to act as the City’s
representative to the Saskatchewan Ministry of Environment; and to work with
Akzo Nobel and the Ministry of Environment to develop a corrective action plan.
On the east approach and arterial road alignment, the required right-of-way is owned by
a number of entities. Offers to Purchase and/or discussions have begun.
North Commuter Parkway Project
Page 22
DRAFT
7. Initial Budget Estimate
The scope of this project estimate includes the property acquisition, environmental
clean-up, detailed design and construction of a new North Commuter Bridge.
The estimated cost of the bridge-component of the project is $102.5 Million (see Table
8). This cost estimate includes all planning and design, as well as the land acquisition
and environmental cleanup for both the bridge itself and the connecting roadways. The
construction costs include only those for the bridge.
Table 8: Preliminary North Commuter Bridge Budget
2012
2013
2014
2015
2016
Total
Budget
Functional Planning Study $100K $100K
Preliminary Environmental &
Geotechnical Investigation
$500K $500K
Land Acquisition $7.1M $7.1M
Environmental clean-up $5.0M $5.0M
Detailed Design $2.0M $2.0M
Bridge Construction $87.8M $87.8M
Total $100K $7.6M $7.0M $87.8M $102.5M
A funding plan for the connecting roadways on the east side of the river must be
developed. Typically, arterial roadways are funded through the Arterial Road Reserve.
However, given that there will be limited development along the roadways for a number
of years; an alternative plan will be required (Table 9). The estimated cost for the
arterial roads component of this project is $58.0M. This cost estimate includes all
anticipated planning, design and construction costs.
North Commuter Parkway Project
Page 23
DRAFT
Table 9: Preliminary Arterial Road Budget
Length
2016
Total
Budget
McOrmond Drive
Fedoruk Dr. to Central Ave.
4,077m $25.2M $25.2M
Central Avenue
Fedoruk Dr. to McOrmond
Dr.
2,891m $17.9M $17.9M
McOrmond Drive
(4-lane, wide ROW)
Central Ave. to east bridge
abutment
2,123m $13.2M $13.2M
Marquis Drive
Wanuskewin Rd. to west
bridge abutment
273m $1.7M $1.7M
Total 9,364m $58.0M $58.0M
North Commuter Parkway Project
Page 24
DRAFT
8. Projected Traffic Operations
300,000 Population
At the 300,000 population, Marquis Drive will have a 4-lane cross section, as does
Wanuskewin Road. All left-turns are accomplished with single-lane bays. The
westbound Marquis Drive right turn (on to Wanuskewin Road northbound) has a right-
turn bay; as does the Wanuskewin Road northbound right-turn to Marquis Drive
eastbound. In the morning peak hour the intersection is expected to operate reasonably
well, with an overall level of service (LOS) of “B”. However, the afternoon peak hour is
not expected to operate as well, with an overall level of service of “D”. These results
are based on projected traffic volumes and an un-optimized signal timing plan; it can be
expected that actual operation will be better through the coordination of traffic signals
up- and downstream of this intersection. See Tables 10 and 11 for the summary of
these results.
Table 10: Traffic Operations at Marquis Dr. & Wanuskewin Rd., PM Peak Hour, 300,000 Population Projection NB SB EB WB
LT Thru RT LT Thru RT LT Thru RT LT Thru RT
Vol. 325 515 355 330 165 5 70 1,425 110 70 305 75
LOS C D A C D A D E D B C A
Overall LOS: D
Table 11: Traffic Operations at Marquis Dr. & Wanuskewin Rd., AM Peak Hour, 300,000 Population Projection NB SB EB WB
LT Thru RT LT Thru RT LT Thru RT LT Thru RT
Vol. 105 165 50 35 190 5 5 125 150 245 1,320 315
LOS C C A C D A C C A B C A
Overall LOS: B
North Commuter Parkway Project
Page 25
DRAFT
400,000 Population with Perimeter Highway
At the 400,000 population, with Perimeter Highway, Marquis Drive and all the
associated roadways and intersections can continue to operate acceptably without
substantial modification from their opening day configurations. See Tables 12 and 13
for a summary of these findings. In the evening peak hour, eastbound traffic volumes
are expected to increase by at least 40%; northbound volumes will more than double.
The projected level of service for individual movements is highly dependent upon future
signal operation and optimization should be able to balance the demands and improve
level of service beyond what is shown in Tables 12 and 13.
Table 12: Traffic Operations at Marquis Dr. & Wanuskewin Rd., PM Peak Hour, 400,000 Population Projection with Perimeter Highway NB SB EB WB
LT Thru RT LT Thru RT LT Thru RT LT Thru RT
Vol. 60 1,105 650 240 430 5 20 2,000 105 290 545 125
LOS E E B C D A D E C B B A
Overall LOS: D
Table 13: Traffic Operations at Marquis Dr. & Wanuskewin Rd., AM Peak Hour, 400,000 Population Projection with Perimeter Highway NB SB EB WB
LT Thru RT LT Thru RT LT Thru RT LT Thru RT
Vol. 70 315 265 52 525 5 5 320 70 561 1,945 135
LOS D D A C D A A C A D D C
Overall LOS: D
400,000 Population without Perimeter Highway
At the 400,000 population, without Perimeter Highway, Marquis Drive will require a 6-
lane cross section; Wanuskewin Road will remain a 4-lane arterial roadway.
Wanuskewin Road northbound (on to Marquis Drive westbound) is a single-lane left-
turn bay; all other left-turns are accomplished with dual-lane bays. The westbound
Marquis Drive right turn (on to Wanuskewin Road northbound) has a right-turn bay; as
North Commuter Parkway Project
Page 26
DRAFT
does the Wanuskewin Road northbound right-turn to Marquis Drive eastbound. In the
morning peak hour the intersection is expected to operate with an overall level of
service of “D”. The afternoon peak hour is expected to operate with an overall level of
service of “E”. These results are based on projected traffic volumes and an un-
optimized signal timing plan; it can be expected that actual operation will be better
through the coordination of traffic signals up- and downstream of this intersection. See
Tables 14 and 15 for the summary of these results. An innovative signal timing plan
and/or operation may be able to improve the level of service for this intersection and
should be explored as traffic volumes develop.
Table 14: Traffic Operations at Marquis Dr. & Wanuskewin Rd., PM Peak Hour, 400,000 Population Projection NB SB EB WB
LT Thru RT LT Thru RT LT Thru RT LT Thru RT
Vol. 90 750 720 580 660 5 5 2,315 35 295 695 495
LOS E D A E D B F F F E C A
Overall LOS: E
Table 15: Traffic Operations at Marquis Dr. & Wanuskewin Rd., AM Peak Hour, 400,000 Population Projection NB SB EB WB
LT Thru RT LT Thru RT LT Thru RT LT Thru RT
Vol. 20 480 255 315 360 5 5 435 70 540 2,205 595
LOS F E A E D A E D A E D B
Overall LOS: D
The potential impact of Perimeter Highway on the expected traffic operations at
Wanuskewin Road and Marquis Drive is significant: Through the diversion of demand,
Perimeter Highway can delay or negate the need for a 6-lane North Commuter Bridge
with substantial savings; The reduced demand may also eliminate the need to expand
Marquis Drive from 4- to 6-lanes; The reduced demand may also maintain traffic
operations at the intersection of Marquis Drive and Wanuskewin Road at a reasonable
level of service.
North Commuter Parkway Project
Page 27
DRAFT
Table 16: Level of Service Standards Average Control Delay (sec./veh.)
Level of Service
General Description
<= 10 A Free Flow >10 - 20 B Stable Flow (slight delays) >20 - 35 C Stable Flow (acceptable delays) >35 - 55 D Approaching unstable flow (tolerable delay, occasional
wait through more than one signal cycle before proceeding)
>55 - 80 E Unstable flow (intolerable delay) >80 F Forced flow (jammed)
North Commuter Parkway Project
Page 28
DRAFT
9. Public Consultation
The public consultation for this project occurred Wednesday March 6, 2013. An Open
House was held in association with other planning activities in the area. More than 200
people attended the Open House. The information presented at the Open House was
also available at www.saskatoon.ca. Comments forms were received from 24 people at
the Open House, and 5 people commented via the project webpage:
• 3 comments were submitted indicating full support for the proposed North
Commuter Bridge project. 3 comments indicated the need to provide high-quality
pedestrian and cyclist facilities on the proposed North Commuter Bridge.
• There is confusion between the proposed North Commuter Bridge and the
proposed Provincial Perimeter Highway. As this project advances, the distinction
between the two projects will need to be clearly identified.
• There is a desire for a high speed connection (i.e. to complete the Provincial
Perimeter Highway); an arterial road (with traffic signals) is not viewed
favourably. 5 comments were submitted indicating a preference for Perimeter
Highway instead of the proposed North Commuter Bridge.
• There is a great deal of confusion about how the system of connecting roads and
the arterial bridge are intended to operate: “just like Broadway” was not viewed
favourably. 2 comments were submitted indicating a preference for an
uninterrupted facility.
• There is a great deal of apprehension from members of the Wildlife Federation
whose facility will be on the south side of the proposed McOrmond Drive. They
want a deflection of the proposed McOrmond Drive to the south of their facility, to
postpone the relocation of their facility. 6 Comments were submitted indicating a
desire to deflect the proposed McOrmond Drive to the south of the firing range.
• The Saskatoon Police Service also expressed concern with the proposed
alignment of McOrmond Drive and the continued operation of the firing range.
They want a deflection of the proposed McOrmond Drive to the south of the
Wildlife Federation, to allow time for planning and relocation of a new firing
range.
North Commuter Parkway Project
Page 29
DRAFT
10. Recommendations
The North Commuter Bridge will link the Marquis Industrial Area with the University
Heights area, providing relief to the existing Circle Drive Bridge, and will function as an
arterial bridge, operating similar to the existing University and Broadway Bridges. It is
not intended to function as a designated truck route, nor as a freeway.
• The preferred alignment for the North Commuter Bridge river crossing extends
Marquis Drive across the South Saskatchewan River and connects to the
extension of McOrmond Drive at Fedoruk Drive.
• The North Commuter Bridge should be constructed initially as a four-lane bridge;
the foundations and piers should be designed to accommodate a possible
expansion to six-lanes in the future, if needed.
• McOrmond Drive between the river crossing and Central Avenue should be
constructed initially as a four-lane arterial roadway, with a wide right-of-way to
permit the possible future expansion to six-lanes in the future, if needed.
• McOrmond Drive through the Northeast Swale should be constructed as a
narrow arterial roadway with special considerations for reducing the impact on
wildlife and the natural resources along the crossing through the swale.
• McOrmond Drive between Central Avenue and Fedoruk Drive should be
constructed as a four-lane arterial roadway. Because of the residential and
commercial development along the roadway, very effective access management
requirements will be necessary to maintain the utility of the roadway.
• Central Avenue between McOrmond Drive and Fedoruk Drive should be
constructed as a four-lane arterial roadway, access management will be
important to maintain the utility of the roadway.
• All arterial roads should initially have a posted speed limit of 60 km/hr, and as
development proceeds along the roads, the posted speed limit should be
reduced to 50 km/hr. Through the Northeast Swale, the posted speed limit
should remain at 50 km/hr.
• If required, staged arterial roads can be provided. The center median with street
lighting is required, 1 driving lane and shoulder will be necessary on each side.
North Commuter Parkway Project
Page 30
DRAFT
• The intersection of McOrmond Drive and Central Avenue will require special
design considerations; a “town center” intersection should be designed to support
the “mixed-use” core area identified in the University Heights Sector Plan.
North Commuter Parkway Project
Page 31
DRAFT
List of Figures
Figure 1: North Bridge Alignments Examined
Figure 2: Projected Peak Hour Traffic Volumes (300,000 Population)
Figure 3: Projected Intersection Traffic Volumes (300,000 Population)
Figure 4: Projected Peak Hour Traffic Volumes (400,000 Population) Without
Perimeter Highway
Figure 5: Projected Intersection Traffic Volumes (400,000 Population) Without
Perimeter Highway
Figure 6: Projected Peak Hour Traffic Volumes (400,000 Population) With Perimeter
Highway
Figure 7: Projected Intersection Traffic Volumes (400,000 Population) With
Perimeter Highway
Figure 8: Marquis Drive to McOrmond Drive Arterial Road Alignment
Figure 9: Typical Arterial Road Cross Sections
Figure 10: Horizontal Alignments Examined for North Commuter Bridge
Figure 11: Proposed North Commuter Bridge Plan & Profile
Figure 12.1: Marquis Drive & Wanuskewin Road Intersection – Initial, Part 1
Figure 12.2: Marquis Drive & Wanuskewin Road Intersection – Initial, Part 2
Figure 12.3: Marquis Drive & Wanuskewin Road Intersection – Initial, Part 3
Figure 13.1: Marquis Drive & Wanuskewin Road Intersection – Final, Part 1
Figure 13.2: Marquis Drive & Wanuskewin Road Intersection – Final, Part 2
Figure 13.3: Marquis Drive & Wanuskewin Road Intersection – Final, Part 3
Figure 13.4: Marquis Drive & Wanuskewin Road Intersection – Final, Part 4
Figure 14.1: Preliminary Property Acquisition, Part 1
Figure 14.2: Preliminary Property Acquisition, Part 2
MANAGEMENT AREAU OF S LANDS - EAST
Attridge
25th
Circle
Lenore
Wan
uske
win
College
51st
60th
War
man
Kerr
Ber
ini
McOrmond
Cen
tral
71stSp
adin
a
7th
Cre
s
115th
Street
Street Roa
d
Roa
d
Street
Dr
Pinehouse Dr Whi
tesw
anD
r
Cre
s
Spadina
Street
Drive
DriveDrive
Ave
nue
Cen
tral
Ave
nue
Dr
Road
Ave
Drive
Street
Dr
Pre
ston
Ave
108th St W
105th St W
CollegeDrive
Ave
Ave
St
Ran
ge R
oad
3045
Ave
Circ
leD
rive
Agra
Colleg
e Driv
e
25 30
23 24 19
13 18
Low
e R
oad
374Twp. Road
Ran
ge R
oad
Ran
ge R
oad
Ran
ge R
oad
3051
Ran
ge R
oad
3050
McO
rmon
dDr
ive
Attridge
CP Rail
Marquis Drive
Fedoruk Drive
McOrmond Drive
Cen
tral
Avenu
e
Perimeter Highway
Proposed Provincial PerimeterCP Rail
N
Proposed Provincial
Wan
uske
win
Roa
d
LENORE DR
PINEHOUSE DR
McO
RM
ON
D D
R
NORTH BRIDGE ALIGMENTS EXAMINED
MARQUIS DR
PERIMETER HWY
ARegistered Plan 78S31217
65S22382
CC
Registered Plan 96S22416
MR3
LSD 11LSD 12
LSD 14LSD 13
Reg'd Plan
Fleury Road
Connects to
Kernan Farms
MARQUIS DR
WA
NU
SK
EW
IN R
D
McORMOND D
R
RA
NG
E R
OA
D 3
051
RA
NG
E R
OA
D 3
045
FEDORUK DR
PERIMETER HIGHWAY
ROADWAY ALIGNMENT
PEAK HOUR TRAFFIC VOLUMES
ESTIMATED AVERAGE DAILY TRAFFIC
4-LANE DIVIDED (ARTERIAL CLASS B WIDE ROW)
4-LANE DIVIDED (ARTERIAL CLASS B)
4-LANE DIVIDED (ARTERIAL CLASS B)
4-LANE UNDIVIDED(ARTERIAL "PARKWAY")
PROPOSED ARTERIAL
RA
NG
E R
OA
D 3
051
AGRA ROAD
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
045
LOW
E R
OA
D
AGRA ROAD
LOW
E R
OA
D
CE
NTR
AL
AV
E
PROPOSED PROVINCIAL
ADT (NOT OPEN)
2,110
445ADT 32,160
CE
NTR
AL
AV
E
480 160ADT 7,
345
255
100
ADT 5,015
3051,615
280
ADT 8,400
LEGEND
(CO
NC
EP
T)
ADT 24,810
(VEHICLES / HOUR)PM (AM) (250)
(1,880)
(200)
(75)
(365)
(1,505)
(140)
(225)
(135)
(CONCEPT)McORMOND DR
INTERSECTION CONFIGURATIONTO BE DETERMINED
ARegistered Plan 78S31217
65S22382
CC
Registered Plan 96S22416
MR3
Reg'd Plan
Fleury Road
Connects to
MARQUIS DR
WA
NU
SK
EW
IN R
D
McORMOND D
R
CENTRAL AVE
RA
NG
E R
OA
D 3
051
RA
NG
E R
OA
D 3
045
FEDORUK DR
PERIMETER HIGHWAY
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
045
LOW
E R
OA
D
AGRA ROAD
LOW
E R
OA
D
CE
NTR
AL
AV
E
PROPOSED PROVINCIAL
LSD 11LSD 12
LSD 13 LSD 14
(CONCEPT)
1,425
108
70
355
325 51
5
305
75
70
165(5
)
330
1,605470
35
5
145
15
3055
5
15
5
10
1305
100
35
5
355
115105
5
1,185
235
125
LOCATION ALOCATION B
LOCATION C
A
B
C
ROADWAY ALIGNMENT
PEAK HOUR TRAFFIC VOLUMES
PROPOSED ARTERIAL
LEGEND
(VEHICLES / HOUR)876
5
(190
)
(35)
(1,320)
(315)
(245)
(5)
(125)
(150) (105
)
(165
)
(50)
(25)
(15)
(5)
(5) (135)(65)
(5)(1,500)
(5)
(355)
(5) (15
)
(115
)
(445
)
(60)
(115) (145) (5)
(80)(5)
(140)
(5)
(5)
(865)
(149) PM (AM)
(CONCEPT)McORMOND DR
INTERSECTION CONFIGURATIONTO BE DETERMINED
(NOT OPEN)
ARegistered Plan 78S31217
65S22382
CC
Registered Plan 96S22416
MR3
LSD 11LSD 12
LSD 14LSD 13
Reg'd Plan
Fleury Road
Connects to
Kernan Farms
MARQUIS DR
WA
NU
SK
EW
IN R
D
McORMOND D
R
RA
NG
E R
OA
D 3
051
RA
NG
E R
OA
D 3
045
FEDORUK DR
PERIMETER HIGHWAY
ROADWAY ALIGNMENT
PEAK HOUR TRAFFIC VOLUMES PM (AM)
ESTIMATED AVERAGE DAILY TRAFFIC
4-LANE DIVIDED (ARTERIAL CLASS B WIDE ROW)
4-LANE DIVIDED (ARTERIAL CLASS B)
4-LANE DIVIDED (ARTERIAL CLASS B)
4-LANE UNDIVIDED(ARTERIAL "PARKWAY")
PROPOSED ARTERIAL
RA
NG
E R
OA
D 3
051
AGRA ROAD
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
045
LOW
E R
OA
D
AGRA ROAD
LOW
E R
OA
D
CE
NTR
AL
AV
E
PROPOSED PROVINCIAL
ADT (NOT OPEN)
(1,005) 3,610
1,480 (3,335)ADT 65,720
CE
NTR
AL
AV
E
1,190 (190)
(780) 390ADT 17
,328
310 (285)
(340) 460
ADT 9,595
1,025 (1,935)
(610) 1,985
280 (250)
ADT 8,400
LEGEND
(CO
NC
EP
T)
ADT 38,675
(VEHICLES / HOUR)
(CONCEPT)McORMOND DR
4-LANE DIVIDED (ARTERIAL CLASS B)
INTERSECTION CONFIGURATIONTO BE DETERMINED
ARegistered Plan 78S31217
65S22382
CC
Registered Plan 96S22416
MR3
Reg'd Plan
Fleury Road
Connects to
MARQUIS DR
WA
NU
SK
EW
IN R
D
McORMOND D
R
CENTRAL AVE
RA
NG
E R
OA
D 3
051
RA
NG
E R
OA
D 3
045
FEDORUK DR
PERIMETER HIGHWAY
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
045
LOW
E R
OA
D
AGRA ROAD
CE
NTR
AL
AV
E
PROPOSED PROVINCIAL
LSD 11LSD 12
LSD 13 LSD 14
(CONCEPT)
2,315
35
5
(255
) 72
0
(20)
90
(480
) 75
0
695
495
295
660
5
580
(775) 2,355
(120) 915(45) 135
(30) 5
(580)
220
(175)
175
1,095 (2,390)
10 (5)10 (5)
275
(75)
70 (1
15)
5 (5)
(110) 180
(75) 95(240) 175
(5) 5
(35) 7
0
(970)
995
80 (85)890 (150)5 (5)
1,140
(700
)
170
(30)
145
(35)
LOCATION ALOCATION B
LOCATION C
A
B
C
ROADWAY ALIGNMENT
PEAK HOUR TRAFFIC VOLUMES
PROPOSED ARTERIAL
LEGEND
(VEHICLES / HOUR)876 PM (AM) (149)
(5) (3
60)
(315
)
(435)
(70)
(5)
(2,205)
(595)
(540)
(CONCEPT)McORMOND DR
INTERSECTION CONFIGURATIONTO BE DETERMINED
(NOT OPEN)
ARegistered Plan 78S31217
65S22382
CC
Registered Plan 96S22416
MR3
LSD 11LSD 12
LSD 14LSD 13
Reg'd Plan
Fleury Road
Connects to
Kernan Farms
MARQUIS DR
WA
NU
SK
EW
IN R
D
McORMOND D
R
RA
NG
E R
OA
D 3
051
RA
NG
E R
OA
D 3
045
FEDORUK DR
PERIMETER HIGHWAY
ROADWAY ALIGNMENT
PEAK HOUR TRAFFIC VOLUMES PM (AM)
ESTIMATED AVERAGE DAILY TRAFFIC
4-LANE DIVIDED (ARTERIAL CLASS B WIDE ROW)
4-LANE DIVIDED (ARTERIAL CLASS B)
4-LANE DIVIDED (ARTERIAL CLASS B)
4-LANE UNDIVIDED(ARTERIAL "PARKWAY")
PROPOSED ARTERIAL
RA
NG
E R
OA
D 3
051
AGRA ROAD
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
045
LOW
E R
OA
D
AGRA ROAD
LOW
E R
OA
D
CE
NTR
AL
AV
E
PROPOSED PROVINCIAL
800 (1,625)
ADT 35,450(545) 2,195
(640) 2,880
960 (2,645)ADT 49,615
CE
NTR
AL
AV
E
1,330 (220)
(925) 415ADT 19
,635
280 (255)
(325) 355
ADT 8,460
630 (1,330)
(310) 1,395
280 (250)
ADT 8,400
LEGEND
(CO
NC
EP
T)
(VEHICLES / HOUR)
ADT 25,410
(CONCEPT)McORMOND DR
4-LANE DIVIDED (ARTERIAL CLASS B)
INTERSECTION CONFIGURATIONTO BE DETERMINED
ARegistered Plan 78S31217
65S22382
CC
Registered Plan 96S22416
MR3
Reg'd Plan
Fleury Road
Connects to
MARQUIS DR
WA
NU
SK
EW
IN R
D
McORMOND D
R
CENTRAL AVE
RA
NG
E R
OA
D 3
051
RA
NG
E R
OA
D 3
045
FEDORUK DR
PERIMETER HIGHWAY
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
045
LOW
E R
OA
D
AGRA ROAD
CE
NTR
AL
AV
E
PROPOSED PROVINCIAL
LSD 11LSD 12
LSD 13 LSD 14
(CONCEPT)
2,000
105
20
(650
) 26
5
(60)
70
(1,1
05)
315
545
125
290
430
5
240
(455) 1,760
(80) 725(40) 230
(30) 5
5(150)
430
(240)
445
665 (1,780)
115 (80)30 (5)
580
(140)
60 (1
90)
90 (2
0)
(85) 150
75 (85)(245) 170
5 (5)
65 (4
5)
535
(700)
75 (55)95 (185)5 (5)
810
(420)
185
(25)
180
(35)
LOCATION ALOCATION B
LOCATION C
A
B
C
ROADWAY ALIGNMENT
PEAK HOUR TRAFFIC VOLUMES
PROPOSED ARTERIAL
LEGEND
(VEHICLES / HOUR)876 PM (AM) (149)
(5) (5
24)
(55)
(320)
(70)
(5)
(1,945)
(135)
(565)
(CONCEPT)McORMOND DR
INTERSECTION CONFIGURATIONTO BE DETERMINED
(OPEN)
RIDDELLPALEONTOLOGICALSITE
EVERGREEN
MARQUIS DR
WA
NU
SK
EW
IN R
D
McORMOND D
R
CENTRAL AVE
RA
NG
E R
OA
D 3
051
RA
NG
E R
OA
D 3
045
FEDORUK DR
PERIMETER HIGHWAY
LEGEND
ROADWAY ALIGNMENT
NORTH EAST SWALEAPPROVED CROSSING LOCATION
CR
EE
K
PROPOSED ARTERIAL
ROADWAY CROSS SECTIONCHANGE
RA
NG
E R
OA
D 3
051
AGRA ROAD
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
045
LOW
E R
OA
D
AGRA ROAD
CE
NTR
AL
AV
E
SEE DWG249-0061-102r002
PROPOSED PROVINCIAL
(CONCEPT)
R750
R1484.5
R1050
R614
R500
R15004-LANE DIVIDED
(ARTERIAL CLASS B WIDE ROW)
4-LANE DIVIDED (ARTERIAL CLASS B)
4-LANE DIVIDED (ARTERIAL CLASS B)
4-LANE UNDIVIDED(ARTERIAL "PARKWAY")
(CONCEPT)McORMOND DR
R500
R200
R200
R400
4-LANE DIVIDED (ARTERIAL CLASS B)
INTERSECTION CONFIGURATIONTO BE DETERMINED
ARTERIAL CLASS B (WIDE RIGHT OF WAY)
ARTERIAL CLASS B
ARTERIAL PARKWAY
ARTERIAL B DESIGN
ARTERIAL B DESIGN
1. POSTED SPEED = 50 km/h
2. NO SUPERELEVATION ON CURVES
3. FRONTAGE MAY BE PERMITTED DEPENDING ON REVISIONS TO SECTOR PLAN
4. MANAGED ACCESS
5. POSSIBLE EXPANSION TO ARTERIAL CLASS A
1. POSTED SPEED = 50 km/h
2. NO SUPERELEVATION ON CURVES
3. FRONTAGE MAY BE PERMITTED DEPENDING ON REVISIONS TO SECTOR PLAN
4. MANAGED ACCESS
ARTERIAL PARKWAY DESIGN
1. POSTED SPEED = 50 km/h
2. NO SUPERELEVATION ON CURVES
3. SIGNS: WILDLIFE CROSSING PEDESTRIAN CROSSING NO STOPPING
CONCEPT ALIGNMENT PLANS
71 ST STREET
MARQUIS DR EAST WA
NU
SK
EW
IN R
D
BR
OD
SK
Y A
VE
ARTHUR ROSE
AVE
RA
NG
E R
D 3
051
(CE
NTR
AL
AV
E)
KIN
NE
AR
AV
E
PROPOSED PROVINCIAL
PERIMETER HIGHWAY
PLAN A
PLAN B
PLAN C
PLAN D
MARQUIS DR
WA
NU
SK
EW
IN R
D
A
A
B
B
C
C
SECTION A-A SECTION B-B
FILL
FILL
FILLFILL
CUT
CONCEPTFOR DISCUSSION ONLY
CONCEPTFOR DISCUSSION ONLY
McORMOND DR
SECTION C-C
PROFILE VIEW SHOWN 10XVERTICAL EXAGGERATION
2007 LIDAR BARE-EARTH SURFACE2011 AERIAL IMAGE SHOWN
CONCEPT BRIDGE GEOMETRIC CROSS SECTIONSCALE 1:250
LEGEND
INITIAL FOUR LANE BRIDGE300,000 POPULATION FUNCTIONAL GEOMETRICSTEMPORARY LANE CLOSURE
BR
OD
SK
Y A
VE
WA
NU
SK
EW
IN R
D
MARQUIS DR EAST
≥
LEGEND
INITIAL FOUR LANE BRIDGE300,000 POPULATION FUNCTIONAL GEOMETRICSTEMPORARY LANE CLOSURE
WA
NU
SK
EW
IN R
D
MARQUIS DR EAST
MARQUIS DR EAST (CONCEPT)
WANUSKEWIN RD
WANUSKEWIN RD
MA
RQ
UIS
DR
EA
ST
LEGEND
INITIAL FOUR LANE BRIDGE300,000 POPULATION FUNCTIONAL GEOMETRICSTEMPORARY LANE CLOSURE
BR
OD
SK
Y A
VE
WA
NU
SK
EW
IN R
D
MARQUIS DR EAST
LEGEND
SIX LANE BRIDGE WIDENING400,000 POPULATION FUNCTIONAL GEOMETRICS
≥
MARQUIS DR EAST (CONCEPT)W
AN
US
KE
WIN
RD
LEGEND
SIX LANE BRIDGE WIDENING400,000 POPULATION FUNCTIONAL GEOMETRICS
MARQUIS DR EAST
≥
WANUSKEWIN RD
WANUSKEWIN RD
MA
RQ
UIS
DR
EA
ST
LEGEND
SIX LANE BRIDGE WIDENING400,000 POPULATION FUNCTIONAL GEOMETRICS
71 ST S
TRE
ET
WANUSKEWIN RD
LEGEND
SIX LANE BRIDGE WIDENING400,000 POPULATION FUNCTIONAL GEOMETRICS
34 ac.
MARQUIS DR
WA
NU
SK
EW
IN R
D
McORMOND D
R
CENTRAL AVE
RA
NG
E R
OA
D 3
051
RA
NG
E R
OA
D 3
045
FEDORUK DR
PERIMETER HIGHWAY
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
045
LOW
E R
OA
D
AGRA ROAD
LOW
E R
OA
D
CE
NTR
AL
AV
E
PROPOSED PROVINCIAL
SE 1/4 SEC 18-37-04-3ISC SURFACE PARCEL:165215819
OWNER: CITY OF SASKATOON
SITE AREA: 620847.439 sq.m
LSD 5-17-37-04-3ISC SURFACE PARCEL135827365
OWNER: CITY OF SASKATOON
SITE AREA: 161764.756 sq.m
LSD 6-17-37-04-3ISC SURFACE PARCEL135827376
OWNER: CITY OF SASKATOON
SITE AREA: 161764.627 sq.m
BLOCK A 101478821ISC SURFACE PARCEL135917747
OWNER: CITY OF SASKATOON
SITE AREA: 646686.019 sq.m
NW 17-37-04-3ISC SURFACE PARCEL135917747
OWNER: CITY OF SASKATOON
SITE AREA: 646686.019 sq.m
NE 1/4 SEC 18-37-04-3ISC SURFACE PARCEL 118558121
OWNER: CITY OF SASKATOON
SITE AREA: 648340.965 sq.m
LSD 11LSD 12
LSD 13 LSD 14
BLOCK A 78-S-31217ISC SURFACE PARCEL: 118974639
OWNER: SASKATOON WILDLIFE FEDERATION
SITE AREA: 40414.030 sq.m
SE 24-37-05-3ISC SURFACE PARCEL: 118975090
OWNER: CITY OF SASKATOON
SITE AREA: 604683.664 sq.m
LSD 11-24-37-05-3ISC SURFACE PARCEL: 135907375
OWNER: ROBERT GEORGE FINLEY
SITE AREA : 16102.244 sq.m
LSD 6-24-37-05-3ISC SURFACE PARCEL: 135806205
OWNER: CITY OF SASKATOON
SITE AREA: 161406.510 sq.m
LSD 5-24-37-05-3ISC SURFACE PARCEL: 135806182
OWNER: CITY OF SASKATOON
SITE AREA: 161507.146 sq.m
CITY OF SASKATOON CITY OF SASKATOON
CITY OF SASKATOONCITY OF SASKATOON
CITY OF SASKATOON
CITY OF SASKATOON CITY OF SASKATOON
AREA 1
AREA 2AREA 3
CITY OF SASKATOON AREA 4 AREA 5
(CONCEPT)
CONSTRUCTION EASEMENTS SHALL BEREQUIRED TO CONTAIN THE TOE OF FILLSLOPE AND TOP OF SHOULDER OF THECUT SLOPE
CONSTRUCTION EASEMENTS SHALL BEREQUIRED TO CONTAIN THE TOE OF FILLSLOPE
OWNERSHIP AREA 1
3910 WANUSKEWIN DRBLOCK A REG'D PLAN 63-S-09313ISC SURFACE PARCEL 118974651
OWNER: AKZO NOBEL CHEMICALS INC
SITE AREA : 93197.228 sq. m
PROPOSED PROPERTY ACQUISITION:
+ 43.0 m ROW 13789.0 sq.m1.379 ha3.407 ac
OWNERSHIP AREA 2
LSD 9-23-37-05-3 ISC SURFACE PARCEL: 131687769LSD 10-23-37-05-3 ISC SURFACE PARCEL: 131687747LSD 11-23-37-05-3 ISC SURFACE PARCEL: 131687758
OWNER: L&L GRAVEL & RANCHING CO LTD
SITE AREA : 385394.515 sq.m
PROPOSED PROPERTY ACQUISITION:
42.0 m ROW 41502.7 sq.m4.150 ha10.256 ac
OWNERSHIP AREA 3
LSD 12-24-37-05-3ISC SURFACE PARCEL 135907397
OWNER: ROBERT GEORGE FINLEY
SITE AREA : 140300.000 sq.m
PROPOSED PROPERTY ACQUISITION:
42.0 m ROW 16972.9 sq.m1.697 ha4.194 ac
OWNERSHIP AREA 4
SW 19-37-04-3ISC SURFACE PARCEL: 118558143
OWNER: CANADIAN CONF OF THE MENNONITE BRETHREN CHURCH OF NA
SITE AREA: 648357.837 sq.m
PROPOSED PROPERTY ACQUISITION:
35.0 m ROW 28262.9 sq.m2.826 ha6.984 ac
OWNERSHIP AREA 5
SE 19-37-04-03ISC SURFACE PARCEL: 118558132
OWNER: N & S CONSULTING INC101100639 SASKATCHEWAN LTD
SITE AREA: 648031.669 sq.m
PROPOSED PROPERTY ACQUISITION:
35.0 m / 32.0 m ROW 18775.9 sq.m1.877 ha4.640 ac
OWNERSHIP AREA 6
OWNER: CITY OF SASKATOON
ROW VARIES 117521.3 sq.m11.752 ha29.040 ac
WANUSKEWIN DR CORNER CUTOFFS
OWNER:
NW CORNER: 67.2 sq. m 0.0067 ha 0.0166 ac
SW CORNER: 50.0 sq.m 0.005 ha 0.012 ac
SEE FIGURE 14
.2
INTERSECTION CONFIGURATIONTO BE DETERMINED
34 ac.
MARQUIS DR
WA
NU
SK
EW
IN R
D
McORMOND D
R
CENTRAL AVE
RA
NG
E R
OA
D 3
051
FEDORUK DR
PERIMETER HIGHWAY
CR
EE
K
RA
NG
E R
OA
D 3
050
RA
NG
E R
OA
D 3
050
LOW
E R
OA
D
AGRA ROAD
LOW
E R
OA
D
CE
NTR
AL
AV
E PROPOSED PROVINCIAL
SE 1/4 SEC 18-37-04-3ISC SURFACE PARCEL:165215819
OWNER: CITY OF SASKATOON
SITE AREA: 620847.439 sq.m
LSD 5-17-37-04-3ISC SURFACE PARCEL135827365
OWNER: CITY OF SASKATOON
SITE AREA: 161764.756 sq.m
LSD 6-17-37-04-3ISC SURFACE PARCEL135827376
OWNER: CITY OF SASKATOON
SITE AREA: 161764.627 sq.m
BLOCK A 78-S-31217ISC SURFACE PARCEL: 118974639
OWNER: SASKATOON WILDLIFE FEDERATION
SITE AREA: 40414.030 sq.m
SE 24-37-05-3ISC SURFACE PARCEL: 118975090
OWNER: CITY OF SASKATOON
SITE AREA: 604683.664 sq.m
LSD 11-24-37-05-3ISC SURFACE PARCEL: 135907375
OWNER: ROBERT GEORGE FINLEY
SITE AREA : 16102.244 sq.m
LSD 6-24-37-05-3ISC SURFACE PARCEL: 135806205
OWNER: CITY OF SASKATOON
SITE AREA: 161406.510 sq.m
LSD 5-24-37-05-3ISC SURFACE PARCEL: 135806182
OWNER: CITY OF SASKATOON
SITE AREA: 161507.146 sq.m
CITY OF SASKATOON CITY OF SASKATOON
CITY OF SASKATOON
CITY OF SASKATOON CITY OF SASKATOON
AREA 1
AREA 2AREA 3
CITY OF SASKATOON
(CONCEPT)
CONSTRUCTION EASEMENTS SHALL BEREQUIRED TO CONTAIN THE TOE OF FILLSLOPE AND TOP OF SHOULDER OF THECUT SLOPE
CONSTRUCTION EASEMENTS SHALL BEREQUIRED TO CONTAIN THE TOE OF FILLSLOPE
OWNERSHIP AREA 7
OWNER: CITY OF SASKATOON
35.0 m ROW 22207.4 sq.m2.221 ha5.488 ac
CITY OF SASKATOON CITY OF SASKATOON
CITY OF SASKATOON CITY OF SASKATOON
CITY OF SASKATOON
CITY OF SASKATOONCITY OF SASKATOON
OWNERSHIP AREA 8
OWNER: CITY OF SASKATOON
35.0 m ROW 73249.2 sq.m7.325 ha18.100 ac
OWNERSHIP AREA 9
OWNER: CITY OF SASKATOON
35.0 m ROW 2023.6 sq.m0.202 ha0.500 ac
OWNERSHIP AREA 10
OWNER: CITY OF SASKATOON
35.0 m ROW 3750.7 sq.m0.375 ha0.927 ac
CENTRAL AVENUE (CONCEPT)
TO ACQUIRE A 35.0 m ROWTHE FOLLOWING AREAS AREREQUIRED
CITY OF SASKATOON
SCALE 1:7500
ENLARGEMENT
TO ACQUIRE A 35.0 m ROWTHE FOLLOWING AREAS AREREQUIRED
SEE ENLARGED AREA
INTERSECTION CONFIGURATIONTO BE DETERMINED