north west london · case study 6: acos within medicare .....41 7. agreeing contract...

71
CRITICAL THINKING AT THE CRITICAL TIME TM 13 July 2016 Developing accountable care partnerships for North West London Finance, contracting and governance arrangements

Upload: others

Post on 09-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

CRITICAL THINKING AT THE CRITICAL TIMETM

13 July 2016

Developing

accountable care

partnerships for

North West London

Finance, contracting and governance

arrangements

Page 2: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

Contents

1. EXECUTIVE SUMMARY .............................................................................................................. 1

2. INTRODUCTION ........................................................................................................................ 4

BACKGROUND ......................................................................................................................................... 4 LIMITATIONS TO THE SCOPE OF OUR WORK .................................................................................................... 5 STRUCTURE OF THIS REPORT ....................................................................................................................... 5

3. ACCOUNTABLE CARE PARTNERSHIPS – AN INTRODUCTION ...................................................... 6

WHAT IS MEANT BY ‘ACCOUNTABLE CARE’? .................................................................................................. 6 ACCOUNTABLE VERSUS INTEGRATED CARE ..................................................................................................... 7 ACCOUNTABLE CARE IN THE US .................................................................................................................. 9 ACCOUNTABLE CARE IN THE UK .................................................................................................................. 9 ACCOUNTABLE CARE IN NORTH WEST LONDON ........................................................................................... 11 OUR WORK WITH NWL LOCALITIES ........................................................................................................... 11

West London ................................................................................................................................. 12 Hillingdon ...................................................................................................................................... 13 Hammersmith & Fulham ............................................................................................................... 13 Observations ................................................................................................................................. 14

4. PRINCIPLES UNDERPINNING AN ACP ...................................................................................... 15

INTRODUCTION ...................................................................................................................................... 15 DEVELOPING WORKING AGREEMENTS/PRINCIPLES ........................................................................................ 15

Principles relating to sharing of risks (and rewards) ..................................................................... 16 EXAMPLES OF PRINCIPLES/WORKING AGREEMENTS FROM OTHER ACOS/ACPS .................................................. 18

Case Study 1: West London Whole Systems Integrated Care Heads of Agreement ...................... 18 Case Study 2: NHS England template alliance agreement ............................................................ 18

5. DEFINING THE CONTRACTUAL RELATIONSHIP AND GOVERNANCE BETWEEN ACP PARTNERS 20

CONTRACT COVERAGE ............................................................................................................................. 22 CONTRACT VEHICLE ................................................................................................................................ 23 CONTRACT DESIGN ................................................................................................................................. 24 CONTRACT IMPLEMENTATION ................................................................................................................... 25 FOCUS OF THIS REPORT ........................................................................................................................... 25

6. MANAGING FINANCIAL RISK WITHIN THE ACP ........................................................................ 27

EX-ANTE FLOW OF FUNDS BETWEEN PARTIES ............................................................................................... 27 Overall funding flows between commissioners and the ACP ........................................................ 27 Funding flows between ACP partners ........................................................................................... 30 a) How much of the overall contract value is each provider entitled to? .................................. 30 b) What is the payment mechanism?........................................................................................ 31

RISK-SHARE AGREEMENTS ........................................................................................................................ 33 (1) Agree (where possible) allocation of risks between commissioner(s) and ACP ................ 34 (2) Agree risk share between CCG and provider for “residual risks” ...................................... 35 (3) Agree allocation of risks between providers ..................................................................... 35

Page 3: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

(4) Set KPIs for identifying and applying risk share ................................................................ 37 (5) Agree backstop sharing arrangements ............................................................................. 37

CASE STUDIES: CONTRACTING FOR FINANCIAL RISK IN OTHER HEALTH ECONOMIES ............................................... 38 Case Study 3: Kaiser Permanente, California, USA ........................................................................ 38 Case Study 4: Uniting Care contract, Cambridgeshire and Peterborough, UK .............................. 39 Case Study 5: MSK Collaboration .................................................................................................. 40 Case Study 6: ACOs within Medicare ............................................................................................ 41

7. AGREEING CONTRACT GOVERNANCE ...................................................................................... 43

OVERVIEW............................................................................................................................................ 43 CONTRACTUAL JOINT VENTURE (MOU OR ALLIANCE AGREEMENT) .................................................................. 46 CORPORATE VEHICLE (CORPORATE JOINT VENTURES (SERVICE INTEGRATOR OR SERVICE PROVIDER) AND WHOLLY OWNED

SUBSIDIARIES) ....................................................................................................................................... 48 LEAD PROVIDER MODEL ........................................................................................................................... 49 CASE STUDIES: ESTABLISHING GOVERNANCE ARRANGEMENTS IN OTHER HEALTH ECONOMIES ................................ 49

Case Study 7: Alliance contracting in the NHS .............................................................................. 49 Case Study 8: Northumbria Primary Care ..................................................................................... 52 Case Study 9: MSK Partnership Collaboration .............................................................................. 54

8. CONCLUSIONS ......................................................................................................................... 57

LOCALITY SITE EXPERIENCES ...................................................................................................................... 57

APPENDICES ................................................................................................................................... 61

APPENDIX 1 .......................................................................................................................................... 62 APPENDIX 2 .......................................................................................................................................... 63

Page 4: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

1

1. Executive summary

1.1 The North West London (NWL) collaboration of eight Clinical Commissioning Groups

(CCGs) is currently in the process of transforming the way in which healthcare is

delivered in NWL localities. Key to this transformation is the creation of Accountable

Care Partnerships (ACPs). These partnerships intend to bring together separate

healthcare organisations and, in so doing, encourage greater integration in the

delivery of healthcare between the currently separated providers.

1.2 Greater organisational integration, combined with the appropriate contractual

structures, holds out the prospect of delivering healthcare in ways which reduce the

need for hospital care. In turn, because hospital care, and particularly unplanned

care, is costly and tends to be associated with worse outcomes for patients, this

means that ACPs offer the prospect of delivering higher quality healthcare for lower

cost.

1.3 However, moving from the current pattern of delivery and contractual structures to

new ACPs is not straightforward. It requires changes to models of healthcare delivery,

underlying contracts and, perhaps most fundamentally, a reallocation of risks within

the healthcare system. A further complication is that within any healthcare system

there are a raft of different stakeholders, each with differing objectives and

underlying interests.

1.4 Given the overarching objective of moving to ACPs, NWL commissioned FTI Consulting

LLP (FTI Consulting) and DAC Beachcroft LLP (DAC Beachcroft) to assist with six

specific topics that NWL considered its constituent organisations were having

problems resolving in the transition to ACPs. These six areas related primarily to

financial and governance issues.

1.5 At the outset of our work, however, it became clear that, in practice, the NWL

localities were not at a stage of ACP development to consider, in a meaningful way,

the six issues that we were commissioned to assist on. Hence, we had to flex our

approach to focus on issues that were relevant to the three specific health economies

in the NWL region – Hillingdon, West London, and Hammersmith & Fulham (H&F) –

with a view to moving the debate forward.

1.6 This report presents our findings. As well as focusing on the specific issues in each

locality we also set out our views on the six issues we were originally commissioned to

consider.

Page 5: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

2

1.7 Our key findings are:

Before the localities can engage in meaningful discussion of the detail of the six

specific areas that are the focus of this engagement, further substantive

preparatory work is needed. This has two key aspects – first commissioners

need to clarify, specifically and unambiguously, the service they wish to

commission through the ACP and, second, they need to specify the nature, level

and proportion of risks within the system that will be reallocated to the ACP.

Whilst a great deal of preparatory discussion has been held with a wide group of

stakeholders in NWL, and there have been benefits to this in terms of raising

stakeholder awareness and understanding, it seems to us that this is rapidly

reaching the point of diminishing marginal benefits.

Instead, our very firm view is that each locality should move forward with a

“proof of concept” live running of an ACP and, most importantly, the underlying

contract to support the ACP. Only by actually working through the issues in

developing an ACP contract for real is any substantive progress, in our view,

likely to be made.

The localities that we worked with now appear ready to take this step – having

identified, at an initial level, the cohort of the population that they wish to be

served by an ACP. As such, we have developed a detailed work plan to enable

the localities to understand the steps that they need to take to deliver an ACP to

serve that cohort of the population. Our expectation is that, when the costs and

risks of serving that cohort of the population are fully identified, there may well

be a need to adjust the associated risk and cost profile. However, this in itself

will be a useful learning exercise.

1.8 There were three issues that arose in each of our locality discussions that are worth

emphasising in this executive summary:

First, there was extensive discussion of the need to develop a “model of care” to

deliver integrated care under a new contractual structure. There were some who

strongly advocated that this needs to be done prior to establishing the

appropriate contractual form. A significant advantage of this approach is that it

encourages clinical engagement in the new care model from the outset.

However, it became increasingly clear that the opposite approach may be

preferable in some circumstances. Indeed it can be argued that that the

contractual form is a prerequisite to move to an ACP, whereas the model of care

will, by necessity, evolve over time both in the run up to contract go-live and over

the course of the contract. The obvious and significant risk of requiring a fully

developed integrated model of care to be active prior to contract go-live is that

this goal is never agreed by the stakeholders and, hence, derails the whole

Page 6: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

3

process of moving to an ACP. By contrast, once the contract is in place,

development of a model care is financially incentivised and therefore much

more likely to deliver agreement by stakeholders. In short, a new contractual

form can be an important “agent of change” in the system to deliver a new

model of care.

Second, there was also discussion of “shadow running”, in which an ACP is

developed and the financial consequences in some way imagined what might

have happened had the contract actually been in place. The view proposed by

us and generally agreed upon was that this is potentially counterproductive for

two reasons. First, running a shadow programme means that incentives under

the new contract will not actually “bite”. This means that, in practice, the

contract cannot be the required “agent of change” to deliver the new model of

care. Second, and worse, because there are no new incentives in the system to

deliver new models of care, there is a risk that at the end of the shadow

programme when no improvement has occurred an incorrect conclusion is

drawn that ACPs are likely to be ineffective. Hence, running a shadow

programme risks derailing the entire ACP process. In short, there has to be

material change in the risks and financial flows around the system to deliver

change. A shadow programme, by definition, cannot do this.

Third, there will need to be greater understanding of each individual set of

stakeholders’ current financial status, risk appetite and likely impact of the

changes. For example, acute care providers might need to have financial

safeguards in place as activity reduces. Equally, the different contractual

financial position of GPs will need to be taken into account and to encourage

participation upside and downside risks may need to be adjusted

commensurately.

Page 7: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

4

2. Introduction

2.1 This report has been prepared by FTI Consulting LLP and DAC Beachcroft LLP for the

NWL collaboration of CCGs. We have been asked to advise on the development of

thinking in relation to ACPs. We set out our instructions in more detail below.

Background

2.2 The eight CCGs in North West London are aiming to commission via ACPs from 2018

(see paragraph 2.7). As such, there has been substantive consideration of some of

the financial and governance arrangements that would be used to underpin these

Partnerships.

2.3 FTI Consulting and DAC Beachcroft have been jointly commissioned by the NWL CCGs

to help three particular localities within the North West London area to develop

further their thinking on ACPs. We have been asked to consider six specific areas.

These are:

Internal funding flows and 'internal commissioning';

Risk and reward arrangements;

Collective decision-making (e.g. voting rights) and dispute resolution procedures;

Holding members of the partnership to account for both quality and outcomes;

Contribution of people/resources to manage the ACP; and

Liabilities of individual organisations should the ACP not succeed.

2.4 Considering these six areas for the three localities has allowed us to draw together

thinking that should be useful for other areas in England that are beginning to

consider commissioning via ACPs. This report summarises that thinking. Where

relevant, we include case studies and examples from our work with NWL and also,

case studies from other parts of England and internationally.

Page 8: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

5

Limitations to the scope of our work

2.5 This report has been written using work developed in assisting the three localities in

NWL in thinking about developing ACPs. It is not intended to be a comprehensive

guide to developing an ACP and our work has been limited to considering the six

areas commissioned by NWL.

Structure of this report

2.6 This report has six further sections. It is structured as follows:

Section 2: Accountable Care Partnerships – an introduction;

Section 3: Principles underpinning an ACP;

Section 4: Defining the contractual relationship and governance between ACP

partners;

Section 5: Managing financial risk within the ACP;

Section 6: Agreeing contract governance; and

Section 7: Conclusions.

2.7 Our report also has two Appendices:

Appendix 1, which sets out a high-level roadmap for establishing finance and

governance arrangements for an ACP; and

Appendix 2 details a workplan for establishing finance and governance

arrangements for ACPs.

Page 9: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

6

3. Accountable Care Partnerships – an introduction

3.1 This section introduces the concept of ‘accountable care’ and describes how it differs

from integrated care. We then discuss the development and nature of accountable

care organisations in the US and UK. Finally, we describe the development of ACPs in

NWL and how our work has supported this process.

What is meant by ‘accountable care’?

3.2 Under ‘accountable care’ a provider organisation (or group of organisations) that is

able to influence the type and volume of care delivered to patients undertakes – via

contractual arrangements with commissioners of healthcare – to deliver a set of

health outcomes for a defined population. This contrasts to other types of healthcare

commissioning which might, for example, contract for specified services (‘inputs’)

(often to an unspecified population).

3.3 By contracting for outcomes (rather than inputs) a provider organisation (or group of

organisations) that is able to influence the type and volume of care delivered to

patients is thus incentivised to stop providing unnecessary or duplicative services

that do not contribute towards the improvement of (contractually specified) patient

outcomes. A reduction in activity coupled with the development of preventative

interventions thus has the potential to reduce the cost of care while maintaining or

enhancing the quality of care provided to patients and improving the overall health of

the population.

3.4 Accountable care is typically underpinned by an outcomes-based contract (OBC) (also

referred to as a value-based contract (VBC)) for a specified population. This

population may be the entire population in a specified geographic area or a subset of

that population segmented by a characteristic of that population (such as age) or by

condition (such as diabetes) or both. Selecting appropriate outcome metrics for

inclusion in the contract is paramount to the success of the model to avoid placing

undue emphasis on costs and financial delivery of the accountable care organisation.

Including outcome measures allows commissioning organisations to measure delivery

of quality standards in addition to financial performance.

Page 10: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

7

3.5 Providers working within an accountable care framework can take different

organisational forms. In the USA, so-called Accountable Care Organisations (ACOs)

are typically integrated organisations led by primary care physicians and supported by

secondary and community care. In Valencia, Spain, Ribera Salud Grupo, which

operates Hospital de la Ribera in Alzira, is an integrated, population health

management organisation delivering under a 15 year capitated contract. The ‘Alzira

model’ retains the public nature of the health service by contracting out the running

and management of the health service to a concessionaire while retaining public

property, public financing and public control.

3.6 While the precise organisational form of accountable care organisations will vary,

most organisations will have a formalised structure that enables them to build

leadership, introduce governance, and pursue a joint strategy to serve the needs of

the cohort or population that they are responsible for. The organisations do not

necessarily merge or create new entities, but rather change the way in which they

work together to deliver healthcare services to meet the needs of the population that

they are responsible for and, importantly, the way in which they are reimbursed.

3.7 In North West London, the concept of an ACP has developed. This term describes a

group of organisations coming together to deliver care to a specified cohort of

patients under a capitated contract, whilst maintaining their separate organisational

forms and identities. We discuss the NWL vision further later in this section.

Accountable versus integrated care

3.8 While integration is a common element of accountable care, provider organisations

working within an accountable care framework are not equivalent to Integrated Care

Organisations (‘ICOs’). ICOs are care providers who deliver a wide range of health

services including primary, secondary, and community care through a single

organisational structure. ICOs are expected to deliver better quality care more

efficiently by integrating services and avoiding duplication and delays that may be

caused by hand-overs between multiple providers operating along the same patient

pathway. ICOs have typically been formed through vertical collaborations or mergers

of previously separate organisations offering distinct services. ICOs do not necessarily

operate under an outcomes-based or value-based contract. It is possible that the

formation of an ACP is a step towards creating an ICO that holds an outcomes-based

or value-based contract.

Page 11: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

8

3.9 One of the defining features of accountable care organisations is therefore

contractual responsibility and accountability for patient outcomes for a specified

population and payment based on achieved outcomes. In addition to a (vertically)

integrated model, subject to governance and scale, such organisations could also

take the form of an alliance, lead provider, or joint venture model, as illustrated

below.

3.10 Figure 1 illustrates the degree of integration associated with different organisational

forms. Importantly, whether an organisation is an accountable care organisation or an

ICO depends on the degree of accountability for outcomes adopted by the provider

organisation (subject to scale and governance arrangements).

Figure 1: Spectrum of organisational form within accountable care

Source: FTI Consulting.

Notes: ACO is used to denote any provider organisation working within the accountable care

framework (rather than an American-style ACO only). Alliance may also denote a

federation or a network. Prime provider may also denote a lead provider. A Managed

Care Organisation (‘MCO’) combines the functions of a provider and commissioner of

care in one.

Prime

provider

Joint

venture

Independent

providers

Vertically

integrated

provider

?

Providers

Providers

AllianceMCO

ACO(s.t. scale)

Prime

provider

Prime

provider

Accountable

for a defined

population

Value-based

contract

Fee-for-

service

ACO(s.t. gov.)

Federation

Federation

ICO(s.t. gov.)

ICO(s.t. gov.)

ACO

ICO

ICO

ACO

ICO

ICO

Degree of integration

Ac

co

un

tab

ilit

y fo

r o

utc

om

es ACO

(s.t. gov.)

Page 12: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

9

Accountable care in the US

3.11 Accountable care has received most prominence in the US, where ACOs developed in

the late 2000s and following the implementation of the Affordable Care Act (2010),

which encouraged the formation of ACOs to take on the care of Medicaid patients.1

However, models sharing some of the characteristics of ACOs (particularly managed

care) had been in use previously. American ACOs tend to be integrated organisations

led by primary care physicians and supported by secondary and community care

working within the accountable care framework. Primary care physicians have

typically been heavily involved in the development and management of ACOs given

their ‘gatekeeper’ role in delivering healthcare in the US.

3.12 Many ACOs have achieved improvements in care quality and reductions in costs. A

review of the Alternative Quality Contract (AQC) in Massachusetts, an ACO that

predates the Affordable Care Act, found a 2.8% saving in the first two years of the

programme in comparison with the control group driven by shifting procedures to

lower cost settings and reducing the overall utilisation of services and tests.2 The first

public performance report on ACOs established after the implementation of the

Affordable Care Act found that all pioneer ACOs were successfully meeting the

required quality measures; 25 had lower risk-adjusted admission rates compared to

the benchmark rate; and 18 out of 32 ACOs generated savings for Medicare.3

3.13 However, challenges for strong performance across the ACO cohort remain. Small-

scale ACOs have found it difficult to achieve economies of scale, spread overheads,

and achieve savings. Successful ACOs have been developing complex care

management approaches to address high care costs experienced by the frail and

elderly, patients with multiple chronic conditions, and those with mental illness, which

other organisations have been unable to replicate. Communication, cooperation, and

effective use of data analytics and IT have also been critical to the performance of

successful organisations.

Accountable care in the UK

3.14 In the UK, accountable care is a relatively new concept that builds on the vision to

deliver a more integrated, patient-centred NHS. The Five Year Forward View (2014)

set out a number of New Models of Care to help meet the changing needs of patients

1 See Case Study 6 in Section 5.

2 The Kings Fund (March 2014) Accountable care organisations in the United States and England:

Testing, evaluating and learning what works.

3 Ibid.

Page 13: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

10

and deliver more personalised, integrated and preventative care. These included

models that encouraged both service integration and increased provider

accountability, such as:4

Multi-specialty Community Providers (MCPs). MCPs are expanded GP practices

providing integrated out-of-hospital care, expected to run outpatient

appointments and ambulatory care pathways. MCPs could evolve to take on

delegated responsibility for managing NHS budgets for their population.

Primary and Acute Care Systems (PACS). PACS are vertically integrated

organisations that provide GP and hospital services, together with mental health

and community care services. PACS could form through the evolution of MCPs;

hospitals opening their own GP lists; or from the formation of US-style ACOs that

take accountability for the health needs of a population.

3.15 It is envisaged that in the UK commissioners (i.e. CCGs) and providers will work

together to introduce gradually more aspects of accountable care into current NHS

commissioning and contracting structures. In particular:

Commissioners will be responsible for developing the outcomes-based contract,

including the scope of the contract, the payment structure and the outcome

components;

Commissioners will be able to determine how much financial risk should be

transferred to the provider(s), and how to reward ‘success’ (i.e. meeting the

contractually specified metrics);

Commissioners will develop a way of monitoring the outcomes-based contract,

although they will not be expected to intervene in the day-to-day running of

service delivery;

Accountable providers will be contractually responsible for delivering agreed

health outcomes to a patient population over a period of time, within a financial

envelope;

As providers, they will have the ability to influence the type and volume of care

delivered, and can develop preventative interventions or integrate services to

reduce the cost of care. In this way, they are able to manage the financial risk

and cost of providing care; and

Accountable providers will be measured against contractually agreed outcome

metrics to ensure they do not restrict access to care or compromise on the

quality of services.

4 NHS England (October 2014) Five Year Forward View.

Page 14: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

11

Accountable care in North West London

3.16 In North West London, organisations have come together to evolve the way in which

care is delivered to patients. In 2014, organisations across NWL shared knowledge

and developed ideas to as to how to implement whole systems integrated care,

culminating in the development and publication of the Integration Toolkit. In 2015, an

additional ‘Toolbox’ providing a blueprint for implementing key elements of ACPs was

developed.5 The aim of implementing ACPs is to make a first step towards introducing

accountable care in the area.

3.17 The eight localities across NWL are now making the first steps towards developing

accountable care contracts, with a number of localities hoping to ‘go-live’ with a new

ACP-style contract in April 2017.

3.18 This is in line with commissioning intentions shared by NWL with providers in Autumn

2015 which stated:

“We believe that high quality, integrated services can best be delivered by

accountable care partnerships which have developed appropriate models of

care for their population; which are commissioned to deliver clear outcomes for

the different segments of the population; which share accountability for

achieving those outcomes and which share financial risks and benefits through

a capitated budget.

We do not believe that it is possible to move directly from a PbR environment to

a whole population capitated budget across an ACP. We wish to achieve the

latter by April 2018 at the latest, in line with our 5 year strategy.”

3.19 Each of the localities is now working on developing their response to NWL’s

commissioning intentions.

Our work with NWL localities

3.20 In light of the above context, FTI Consulting and DAC Beachcroft were commissioned

by NWL to support three localities in developing their approaches to ACPs. The three

localities who responded to NWL’s request for expressions of interest were:

Hammersmith & Fulham, Hillingdon, and West London.

5 The Integration Toolkit and Toolbox are available at:

http://integration.healthiernorthwestlondon.nhs.uk/chapters.

Page 15: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

12

3.21 These ‘early adopter’ localities in NWL had clearly spent a great deal of time focusing

on integrated care clinical models and the development of the concept of

accountable care, through work under the Whole Systems Integrated Care

programme. Whilst many of the financial, commercial and legal issues were

addressed in the Whole Systems Integrated Care Toolkit, such issues had not been

tackled to date in detail by any of the three early adopter localities. It was therefore

clear that the six areas of focus for the purposes of this report could not be

addressed in detail in the context of the three localities. We therefore flexed our

support to meet the needs of each locality, and their developmental need to take

the next step towards creating an ACP.

3.22 In this section, we touch upon the status of each early adopter that we worked with,

and areas where we consider they have developed as part of the support received in

this project.

West London

3.23 West London CCG has a number of different contracts in place with individual

providers that underpin two integrated hubs.6 This contracting model has developed

organically to ensure that integrated working can take place. This is a GP led model of

care for over 65s, with 23 GP practices contracted to deliver additional services.

Outcomes and evaluation work has been undertaken by West London including the

addition to and localisation of the NWL outcomes framework. However, the concept

of moving to a broader outcomes-based contract, whereby all of those services sit

within one contractual framework, and the providers are given one capitated budget

to deliver, and organise the delivery of services, had not been explored in detail.

3.24 On that basis, our support involved considering the types of services that West

London might focus on, as well as the challenges to providers to move from the

current contractual arrangements, to an Accountable Care Partnership model.

Consideration of the detailed steps that West London would need to take, as well as

different contractual options to enable an Accountable Care model were discussed in

depth, and a work plan setting out these key areas was produced, in order to

expedite progress.

6 The hubs work with the individual’s GP and home carers, who sit in the GP practices, and the

wider multi-disciplinary team to deliver the right interventions at the right time and in the right

setting

Page 16: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

13

Hillingdon

3.25 Providers in Hillingdon’s proposed Accountable Care Partnership have clearly

preferred ideas about the organisational form that they would like the ACP to take,

therefore the focus of development in Hillingdon was to find the critical path to an

outcomes based contract for particular services to be commissioned, and for the ACP

to be in a state of readiness to respond to the same.

3.26 One of the key issues that Hillingdon resolved during this engagement was to decide

which population cohort they would focus on for the purposes of contract coverage.

Whilst the clinical model for diabetes was most advanced, it was not considered

broad enough as a focus for the ACP. We understand that a great deal of work has

been undertaken to date with regard to the financial modelling for the over 65s

population, and therefore all parties agreed that this should be the initial focus for

the development of the ACP in Hillingdon.

3.27 There is a sense that Hillingdon would like the pace of ACP development to be faster.

As such, we developed a detailed work plan setting out the various steps and

decisions that need to be made, and assigned these to organisations, and where

possible, individuals.

3.28 Pending the resolution of national issues relating to the use of corporate joint

ventures and VAT recovery issues for NHS bodies, Hillingdon has decided to pursue

an alliance contracting model. This will allow for governance arrangements to be

contractually documented, as well as working through the detail of how providers will

work together, and the role of the CCG. Moving to an alliance contracting model is

seen as a natural stepping stone towards the utilisation of a corporate joint venture

with membership of each of the four providers in the ACP.

Hammersmith & Fulham

3.29 Hammersmith and Fulham made it clear at the outset that they are not yet in a

position to consider some of the six issues that are within scope of this report in any

detail, and wished to use this engagement as an opportunity to continue developing

relationships between providers. A Memorandum of Understanding (MoU) has been

signed between the GP Federation and Imperial College Healthcare NHS Trust, and it

is expected that Chelsea and Westminster Hospitals NHS Foundation Trust will also

sign up to the principles of a revised MoU soon. The MoU sets out aspirations of how

the parties will work together and some high level objectives and principles. Terms of

reference for an H&F Integrated Care Programme Board have also been agreed and

the partnership has agreed a methodology for agreeing which pathways should be

prioritised for re-design.

Page 17: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

14

3.30 We consider that H&F are in a position where they are deciding how best to test their

shared vision and principles in an applied manner, as a preliminary step to

considering how they can formally collaborate and respond to an opportunity to

become an Accountable Care Partnership. On that basis, H&F worked with us to

create a development session in order to explore issues focussed on how the

organisations will work with each other, how to address any potential barriers and

consider what success would look like, as a collaboration.

Observations

3.31 In each of the localities, there was a sense that the providers seeking to collaborate

did not have a clear idea as to what they were responding to, in terms of what was

going to be commissioned from them. This made it difficult for them to take detailed

conversations about risk and reward to the next level – as conversations were taking

place without a detailed contract proposal / tender process to respond to. The

responsibility to develop the contract proposal and/or tender process sits with the

commissioners.

3.32 We also noticed that there did not seem to be any “softer” enablers of integrated

working between the parties from the early adopters. For example, in other local

health systems, we have seen collaboration between providers being encouraged by

commissioners by agreeing collective performance incentives that wrap around

providers’ existing individual contracts for services. Such incentives are generally

released on the basis of the collective achievement of certain metrics, and allow

providers to build up trust and working relationships in a relatively safe environment,

in terms of risk exposure.

3.33 In general, there are some important decisions and agreements that must be made

early on, before organisations undertaking an ACO or ACP approach dive into the

detail on the issues described in this report. These early decisions will govern how

organisations relate to each other and interact over the life of the contract and are

important to get right. We discuss these in the following section of this report.

Page 18: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

15

4. Principles underpinning an ACP

Introduction

4.1 Before moving forward with detailed development of a new working partnership,

providers and commissioners will need to decide how to they wish to relate to one

another and agree working principles.

4.2 In addition, the role of the commissioners will need to change. Commissioners need

to clarify, specifically and unambiguously, the service they wish to commission

through the ACP and specify the nature, level and proportion of risks within the

system that will be reallocated to the ACO/ACP. As the ACO/ACP takes on

responsibility for population management, the CCG should look to manage the

ACO/ACP on the basis of the agreed outcomes enshrined in the ACO contract. As a

result this means that the CCG (and other commissioners involved in commissioning

from an ACP, e.g. the local authority) will become less involved in specifying inputs

and holding providers to account based on those inputs, in respect of services, and

instead take a role where they are involved in strategic oversight when

commissioning services. Understanding the principles that govern interaction

between the commissioners and the ACP is therefore also important and must be

agreed at the outset before detailed discussions about the ACO/ACP commence.

4.3 Clearly how the organisations in and outside an ACP interact with one another will

evolve over a time, as it would for any newly formed partnership. The purpose of

agreeing working principles upfront is to set expectations for how organisations will

relate to one another, in ways that support the goals of the ACP.

Developing working agreements/principles

4.4 We have set out in Figure 2 below some typical areas that should be covered when

setting working agreements and principles.

4.5 In our discussions with NWL localities we have seen varied levels of agreement on

principles, but all localities were clear on the need to get these agreements in place

before embarking on such an ambitious programme of work.

Page 19: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

16

Figure 2: Agreeing working principles – areas for agreement

4.6 In particular, these principles should state how providers intend to manage risks, as

one of the defining aspects of an ACP is the fact that it is taking on aspects of the

management of commissioning services for a cohort of patients, and therefore, most

likely, increasing the financial and clinical risks that it has responsibility for. How the

ACP responds to these increased risks will be a key factor in its success or failure.

Given the importance of this area, we have set out below some more detailed

principles that an ACP may wish to adopt in relation to financial and clinical risk.

Principles relating to sharing of risks (and rewards)

4.7 Detailed agreement on risk-sharing principles should be established at an early stage

before the commissioners and the ACP attempt to make detailed decisions as to

where the contract risks will fall. Some key principles relating to risk-sharing are set

out in Figure 3 and explained further below.

Agreeing working

principles

Evidence-based

decisionsSharing of risk

Transparency

Accountability

Integrated

delivery of care

Achieving cultural

change

Achieving better

outcomes for

patients

Open

engagement &

communication

Page 20: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

17

Figure 3: Risk-sharing principles

4.8 First, a key principle should be that risks, and the necessary resources to manage

are given to those best placed to manage them. The rationale for this is that this

incentivises the parties bearing the risks to manage it in an optimal way. This is the

overriding principle of an accountable care contract and will govern which risks the

commissioners pass to the providers. For example, in the case of an over-65s

contract where partners are targeting improvements in primary care provision to

prevent secondary care admissions, both the primary care and secondary care

providers will need to work together to deliver this improvement. Therefore the

commissioners choose to pass responsibility for the relevant services to the ACP

formed of the two primary and secondary care providers.

4.9 Second, where costs and benefits might arise through the operation of the ACP, it will

be important to agree ex ante how to share out such benefits and costs. For

example, it might be that the operation of an ACP leads to a surplus earned on the

contract through, say, an anticipated reduction in non-elective acute care as a result

of increased spending on community care. The benefit might be shared out on the

basis of costs incurred in provision or, potentially, in relation to revenues foregone

due to changes in the pattern of care. In any event, it will be important that all parties

understand what the likely financial flows that might occur will be and how these

will be allocated as this, in turn, is likely to influence behaviour of the parties within

the partnership. The converse, in which there is ambiguity on the way in which costs

and benefits are shared (and liabilities arise) will inevitably heighten the risk of non-

delivery within the partnership.

Key principle:

Risks should sit with

those best placed to

manage them

1

Key principle:

Risks and costs should

be shared to support

mutual accountability

and responsibility for

ACP goals

2

Key principle:

Incentives are aligned

across the system, not

only with the ACP

3

Page 21: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

18

4.10 Third, the agreement to share the costs and benefits arising within an ACP should

ensure that, overall, incentives are aligned appropriately across the system. For

example, given some acute care costs are likely to be fixed in nature, it is likely to be

the case that the benefits of a reduction in activity will need to be passed, in part, to

the acute provider to ensure the ongoing provision of the fixed costs of acute care are

still funded. The corollary, in which the acute provider’s financial position was

worsened as a result of the reduction in the volume of acute provision (as revenues

to the acute provider fell by more than the costs of provision) might serve to

undermine the financial viability of the provider.

Examples of principles/working agreements from other ACOs/ACPs

4.11 As part of our work with NWL and other health economies, we have researched the

principles and working agreements made by different health systems. We set out

below some relevant examples that can help guide UK health and care economies as

they form working relationships to support ACO/ACP development.

Case Study 1: West London Whole Systems Integrated Care Heads of Agreement

In West London, an integrated care system has been developed, focusing on improving

care and outcomes for the over-65s population. As part of this, a detailed ‘Heads of

Agreement’ has been developed which describes a set of behavioural commitments as

to the organisations involved will relate to one another. This Heads of Agreement was

signed by the CCG, primary care providers, community and mental health providers,

acute providers, social care and third sector organisations. The agreement was

supported by patients.

The main behavioural commitments agreed within the Heads of Agreement are:

Co-operation and innovation;

Sharing of information;

Disclosure of conflicts of interest;

Collective sharing of risks and opportunities; and

A ‘best for the delivery of care’ approach, governing future recruitment of partners.

Case Study 2: NHS England template alliance agreement

Alliance contracting is one of a number of legal forms that could be implemented as

part of an ACP (see section 6). Even if alliance contracting itself is not adopted, some of

the principles of alliance contracting may be relevant and/or useful for providers

seeking to collaborate.

Page 22: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

19

As set out in NHS England’s guidelines for alliance contracting, alliance principles “sit

at the heart of alliance contracting and define the relationship between alliance

members”7.

The template contract includes some draft principles that can be adopted by

organisations seeking to enter into an alliance contract. These are as follows:

Take responsibility to make unanimous decisions on a Best for Service basis;

Always demonstrate the service users’ best interests are at the heart of Our activities;

Adopt an uncompromising commitment to trust, honesty, collaboration, innovation

and mutual support;

Establish an integrated collaborative team environment to encourage open, honest

and efficient sharing of information, subject to competition law compliance;

Adopt collective ownership of risk and reward, including identifying, managing and

mitigating all risks in performing our respective obligations in this Agreement; and

Co-produce with others, especially service users, families and carers, in designing

and delivering the Services.

7 NHS Standard Contract Guidance to Template Alliance Agreement. Draft 1, August 2015, NHS

Standard Contract Team

Page 23: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

20

5. Defining the contractual relationship and governance between ACP

partners

5.1 Before project commencement, the NWL localities were asked to identify the key

issues relating to ACP contracts and governance that they were interested in

considering further. In practice, it is important to consider these items in the context

of the contract as a whole. Therefore whilst pursuing the six items described further

in Sections 5 and 6 of this report, we also set out our overall approach to developing

a new contract for an ACO/ACP.

5.2 Management of accountability within the partnership requires contractual structures

to be defined between each of the ACP partners. It is important to define the contract

in terms of:

(a) the relationship between commissioners and providers;

(b) the relationship between ACP partners; and

(c) the relationship between ACP partners and any sub-contractors.

5.3 These relationships are depicted in Figure 4 below.

Figure 4: Three contractual relationships to be defined

5.4 Our discussions with the three NWL localities focused on relationships (b) and (c) i.e.

contractual relationships between providers. However, defining the relationship

between the commissioning entities and the providers is the key first step in

developing the overarching contract structure. This relationship, in terms of the

nature of the fixed payment (e.g. capitated or block payment, amount of payment

Comm-unity

Commissioners

AcuteGP

Fed.

Mental health

Other providers

(b) How do the ACO/ACP providers contract with one

another?

(c) What is the contractual relationship between the ACO/ACP

and any sub-contractors?

(a) What is the contractual relationship

between the commissioner(s) and

the ACO/ACP?

a

b

c

Page 24: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

21

dependent on outcomes) has been considered by NWL in detail as part of its Toolkit

for Whole Systems Integrated Care.8

5.5 For each of these contractual relationships, there are a number of decisions that

have to be worked through, with the input of providers and commissioners. A

framework we have used successfully in other health economies is set out in Figure 5

below. This framework covers all three contractual relationships, as we believe that

they should be considered holistically in order for the ACO/ACP to understand the full

contractual landscape. We also used this framework in our discussions with

Hillingdon and West London.

Figure 5: Key decisions to be made in order to agree the contractual relationships

between all ACO/ACP partners, including commissioners

5.6 The above diagram sets out the four main areas of the contract and the sub-

questions that need to be considered when agreeing a new contract for an ACO/ACP.

In the remaining part of this section we outline these four areas in more detail –

namely:

details of contract coverage;

contracting vehicle;

contract design; and

contract implementation.

88 See chapter 8: http://integration.healthiernorthwestlondon.nhs.uk/chapters

Which outcomes?

Which patients are

covered?

Who are the

contracting parties?

Contract duration

Contract

design

What is the high-level

payment structure?

What is the detailed

payment mechanism?

How will funds flows

between parties?Contract

vehicle

Contract

coverage Which services are

included?

1

3

a

b

c

a

d

a

c

d

How is the contract

being procured?

b

What is current cost of

in-scope services?

b

What are the govern-

ance arrangements?

c

Contract implementation – i.e. what practical issues need to be resolved?

2

4

How will risks & gains

be shared?

d

Page 25: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

22

Contract coverage

5.7 Contract coverage is the first part of the ACP contract that needs to be agreed. Once

the ACP partners understand commissioning intentions and the overall vision for the

delivery of health (and, possibly, social care) services, detailed work can begin as to

who and what services the ACP will cover. Deciding which patients will be served by

the ACP and what services will be provided must be completed before detailed work

on the rest of the contract e.g. contract value, can take place. This is not a

straightforward decision as there may be a range of factors influencing the decision

on contract coverage e.g. who are the priority groups, what financial value do

commissioners want the contract to be?

5.8 The main decisions that need to be taken to agree contract coverage are:

Which outcomes do commissioners want to achieve as part of the contract?

The outcomes framework is a key part of the overall contract structure and will

be the main tool that commissioners use to hold the ACP to account for delivery

of quality for patients. As such, agreeing the outcomes to be delivered up-front is

key. NWL has already developed an outcomes framework for an over-65s

contract. Each outcome will also need to be supported by a metric (that allows

commissioners to measure whether progress has been made) and a target (that

is considered achievable by commissioners and providers).

Which patients will be covered by the contract? Deciding which patients will be

covered by the contract needs to be one of the first steps in the contractual

process. There are a number of different ways of segmenting the population –

NWL has created eight population segments. The contract will need to specify

which segment is included in the contract and how those patients are defined. In

the case of an age-segmented contract (such as those being discussed in NWL),

patients will be defined by age group e.g. over-65s. However, other ACPs are

developing for disease-specific cohorts such as cancer or other long term

conditions. It is also possible to define a cohort by age and condition – for

example, over 65s with one long term condition. In any event, providers and

commissioners need to ensure that the population is specified, unambiguous,

and identifiable. Many Vanguards are seeking to adopt a whole population

budget.

Which services are included in the contract? Defining which services the ACP

is responsible for delivering under the contract also needs to be undertaken at

an early stage so providers understand which of their current contractual flows

will be absorbed into the new contract. This also allows providers to begin

planning their service model for future care delivery. This will become

particularly important when valuing the contract and paying providers to ensure

that services are not paid for twice i.e. once through the capitated payment and

again through a payment for a specific service or treatment. As such, included

services should be specified at as granular level a level of detail as possible e.g.

by HRG for acute providers. It may be that other services are included in the

Page 26: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

23

contract by way of variation, over the course of the contract term.

What is the duration of the contract? A longer contract length offers security of

income for providers. This has the benefit of the ACP having greater certainty

about future revenue streams for a longer period of time, which might, in turn,

provide the ACP greater opportunities to invest resources in activities that might

improve outcomes for patients or reduce costs in serving the patient cohort over

a longer payback period. However, it locks the ACP and the CCG into greater

financial risk (albeit on the upside and the downside) – for example if costs were

to be significantly lower than anticipated, the extra revenue would fall to the

ACP. The pros and cons of a longer contract length (for both commissioners and

providers) should be considered and agreed up-front9. Typically, contract

durations are likely to be a minimum of 3 years and can extend to 7 or 8 years.

Contract vehicle

5.9 The contracting vehicle and related arrangements will depend on a number of factors

including legal requirements. Agreeing the contract vehicle will include deciding the

organisational form, as well as detailed governance arrangements for the ACP.

Providers need to consider the organisational form that they wish to adopt – this is

not a matter for commissioners to specify as part of any tender process, as to do so

may be discriminatory.

5.10 The main factors that need to be considered here are:

Who are the contracting parties? Whilst new members may join the ACO/ACP

over time, initial parties to the agreement will need to be agreed early on so that

progress can be made with deciding relevant contractual issues.

How is the contract being procured? The commissioners will need to decide on

a procurement route, taken into account relevant NHS and EU procurement

law10.

What are the governance arrangements? The governance arrangements will

allow the ACP to run effectively, enable parties to be clear on their roles and

responsibilities and allow decisions to be taken and disputes resolved. The

governance arrangements, to a large extent, will be informed by the proposed

9 For a review of the various considerations in deciding on the optimal duration of the contract,

please see the FTI Consulting report prepared for Monitor “Review of Multi-year tariff cycles”

31 March 2014. While this report considered the merits of a shorter and longer duration in

relation to the national tariff, many of the arguments are relevant in the context of ACP contract

design also.

https://www.gov.uk/government/uploads/system/uploads/attachment_data/file/381608/Multi

YearTariffFTI.pdf

10 NHS (Procurement, Patient Choice and Competition)(No. 2) Regulations 2013 and the Public

Contracts Regulations 2015.

Page 27: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

24

legal form of the collaboration between organisations. Governance

arrangements are explored in more detail in Section 6.

Contract design

5.11 The design of the contract includes the financial value and the flow of money

between ACP partners. This is where financial risks will be assigned to different

contracting parties. The areas set out below are difficult to consider in isolation from

each other as, for example, the overall contract value will have an impact on how

much risk the ACP parties are willing to take on. Therefore the contract design will

only be finalised once parties have reached agreement on each of the issues set out

below:

What is the high level payment structure? How will the ACP be paid? Whilst a

capitated payment structure has been selected by NWL as the most appropriate,

there are other payment mechanisms available including bundled payments and

block payments. The commissioners should also determine whether a

proportion of the contract value will be paid on achievement of outcomes. While

the amount that should be linked to outcomes will need to be considered

carefully, it is clear that it needs to be sufficiently material to ensure that it is

impacts on the behaviour of the ACP. In particular, it should be sufficiently high

to counteract any potentially perverse incentives (for example to reduce cost at

the expense of patient outcomes) that a block payment alone might create.

What is the contract value? The contract value will be negotiated between the

ACP and the commissioners. The historical cost of included services can be used

as a starting point, but other considerations must also be taken into account.

For example, costs might be expected to increase over the course of the

contract due to standard inflationary pressures or for epidemiological reasons

anticipated with that specific cohort of the population. Equally, offsetting

efficiency gains might be expected. Furthermore, a new model of delivery might

be expected to reduce the overall costs of serving the population and, under

certain circumstances, it might be deemed appropriate to claw back some of the

cost saving over the duration of the contract itself.

What is the detailed payment mechanism? The detailed payment mechanism

will describe the full mechanics of payment flows under the contract under a

range of different outcomes. For a capitated payment this needs to include how

the outcomes element of the payment will be determined e.g. how is the

outcomes payment element calculated? Are payments made for individual

outcomes or for achievement of all outcomes? Is achievement greater than the

outcomes target financially rewarded?

How will funds flow between the ACP members, and any sub-contractors?

This question relates to how the contract payment is shared between parties

within the ACP. Although it is likely to vary on a case-by-case basis, a working

assumption is that the overall payment structure (between the commissioner

Page 28: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

25

and the ACP) should, as far as possible, be replicated between the ACP

members and also between the ACP and any subcontractors so as to ensure

that all parties are equally signed up to the overall risks of the contract. We

explore this in more detail in Section 5 below.

How will risks and gains be shared? Agreeing and documenting how risks and

gains will be shared is vital to success of the ACP. This includes risk share

between commissioners and providers and between providers within the ACP.

We explore this in more detail in Section 5 below.

Contract implementation

5.12 As well as the issues set out above, there will be a number of other points of detail

that commissioners and providers will need to ensure is set out and documented

before contract go-live. This typically includes:

Ensuring that the new contractual arrangements operate effectively with other

contracts that are already in place. In particular, it will be important that there

are no gaps or overlaps with other contracts to mitigate against the risk of non

or overpayment;

Ensuring that data capture protocols are in place to capture data for both

activity and outcomes as this will feed into the payment and monitoring process

for the contract;

Developing a framework to evaluate the effectiveness of the contract; and

Defining performance thresholds that provide “step in” rights for the CCGs or

some providers in the case of poor performance.

Focus of this report

5.13 As part of this work for NWL, we have been asked to focus on a sub-set of the key

decisions set out in Figure 5 above. The rest of this report sets these area and

potential responses out in more detail, categorised under the headings “Managing

financial risk” and “Agreeing contract governance” as set out below:

Managing financial risk (Section 5):

Ex ante flow of funds between parties;

Risk and reward arrangements;

Agreeing contract governance (Section 6):

Collective decision-making (e.g. voting rights) and dispute resolution

procedures;

Holding members of the partnership to account for both quality and

outcomes;

Page 29: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

26

Contribution of people/resources to manage the ACP; and

Liabilities of individual organisations should the ACP not succeed.

Page 30: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

27

6. Managing financial risk within the ACP

6.1 In this section we set out how ACPs should consider two key finance and contracting

aspects that need to be agreed before ACP contracts become operational11. These

are:

Ex-ante flow of funds between parties.; and

Risk/gain share agreements.

Ex-ante flow of funds between parties

6.2 As described earlier in this report, there is a hierarchy of payment flows between

parties in an ACP. These are:

first, the overall funding flows between commissioner(s) and the ACP i.e. the

high-level payment structure of the contract;

second, funding flows between ACP partners; and

third, funding flows between the ACP and any sub-contractors.

6.3 In this subsection we describe some of the key issues that will need to be considered

in each of these topics.

Overall funding flows between commissioners and the ACP

6.4 The aim of the new partnership arrangements is to deliver changes in the pattern of

delivery that are beneficial to patients. The funding flows will therefore need to be

arranged in such a way to support this overall objective. Without this, the funding

flows would act as a barrier to changes across the system rather than an enabler

to the changes. The diagram below sets out how the current funding arrangements

act as a potential barrier to the integration of services.

11 As discussed earlier in the report, because of different demands in each locality most of the

issues discussed in this section were not actually raised in our discussions with them.

Page 31: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

28

Figure 6: Current funding arrangements

6.5 All things being equal and temporarily ignoring clinical imperatives, the contractual

incentives arising from current funding arrangements serve to incentivise acute

providers to deliver more care, and community and primary care providers to

deliver less care. That is to say that an activity-based contract e.g. Payment by

Results (PbR), encourages delivery of more care, whilst a block contract encourages

providers to perform less care. Given that primary care and community care tend to

be providers of preventative care that is cheaper to deliver and acute care is reactive

care applied when patients fall sick and more expensive to deliver, it is easy to

construct an argument that says that the current financial arrangements across the

system do not fully support the best interests of patients as it incentivises the

provision of more expensive care to patients when they get sick rather than provision

of cheaper care to patients before conditions worsen.

6.6 Changing to a fixed payment for care delivered in all care settings can align

contractual and clinical incentives, and support delivery of integrated care. As set out

in the diagram below, a fixed payment attempts to change fundamentally the

financial incentives created under a traditional payment mechanism, incentivising

providers to work together and focus resources in the most effective part of the

pathway to support best delivery of care for patients and overall improvement in

population health.

Late stagePrimary

careCommunity care Acute care

GP

contractBlock contract Pay by activity

Reduce

activityReduce activity Increase activity

Care

setting

Typical

contract type

Incentive

Diagnosis

District

nursing

services

Mental

health

services

Outpatient Inpatient

Cheaper More expensive

Falls

management

Better for patients Worse for patients

Cost of

healthcare

Patient

experience

Page 32: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

29

Figure 7: Funding arrangements under an ACP contract

6.7 As discussed in Section 2, this fixed payment contract must also make provision for

an amount of money to be paid on the basis of achievement of outcomes. The

inclusion of an outcomes-based payment embeds quality within the contract and

creates a safeguard against the financial incentive of a fixed payment to drive down

costs (and potentially quality as a result).

6.8 NWL has already undertaken a great deal of work with key stakeholders to develop a

set of outcomes that could be included in a ACP contract for over-65s care. These are

available as part of the NWL toolkit.12 We do not discuss development of outcomes in

this report but do emphasise its importance for ensuring both quality and financial

management are delivered through the new contract.

6.9 The fixed payment can take a number of forms. In the context of NWL, we are aware

that commissioning intentions are to pay via a single capitated payment and

therefore the options described below are predicated on a capitated payment

arrangement.

6.10 Clearly before the flow and share of funds between ACP partners can be established,

the commissioner(s) and ACP partners will have to agree an overall contract value.

This is a key part of the contracting process and will normally be iterative, as partners

analyse different scenarios regarding risk and outcomes achievement, and negotiate

the contract over a number of months.

12 http://integration.healthiernorthwestlondon.nhs.uk/Images/upload/MoC%

201e%20Outcomes%20menu.pdf

Primary

careCommunity care Acute care

Fixed payment (with ACP)

Reduce more costly activity

Care

setting

Contract type

Incentive

Early stage

Cheaper More expensive

Better for patients Worse for patients

Cost of

healthcareCheaper More expensive

Patient

experience

Diagnosis

District

nursing

services

Mental

health

services

Outpatient InpatientFalls

management

Page 33: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

30

6.11 Agreeing a whole population budget is a complex undertaking, made easier by

following a set process and ensuring regular and open communication between

commissioner(s) and providers. NHS England and NHS Improvement are working

intensively with six Vanguards to develop a ‘Whole Population Budget Handbook’ to

support local health economies undertaking this process. This is expected to be

published in autumn 2016.

6.12 For the purposes of this report, we assume that a budget for the ACP has already

been agreed and below we set out how the partners within the ACP should then

decide how funds should flow between them.

Funding flows between ACP partners

6.13 Once the nature of the overall fixed payment to the ACP has been established, the

ACP partners will need to agree the nature of the funding flows between themselves.

Agreeing these funding flows ex ante ensures that each provider is clear on the

financial envelope available to them and consequently the risks that they are

responsible for managing.

6.14 There are two main items to be considered:

a) How much of the overall contract value is each provider entitled to?

b) What is the payment mechanism?

a) How much of the overall contract value is each provider entitled to?

6.15 The overall contract value for the ACP should reflect the costs of the anticipated

service provision by each of the constituent ACP entities, and any relevant sub-

contractors. As described above, this value should be built up in conjunction with the

commissioning bodies.

6.16 The amount that each entity is entitled to, is however, not simply a product of the cost

of its current service delivery. The ACP will need to consider a number of other

potential costs in order to determine the available contract funds for each entity.

These issues are set out below:

What is the anticipated cost of service delivery by each provider within the ACP? A

factor to consider here is whether fixed costs need to be funded over a period of

time with the contract, even if activity is expected to decrease.

What are the known changes to the current cost of service delivery? e.g. demand

profile over contract period, cost inflation, national efficiency requirements,

demographic changes, impact of other reconfigurations.

Are providers expected to make any savings as part of the contract?

Are there existing CIP plans in place that reduce the funding requirement over the

contract period?

Is any investment required in order to change services provided by each provider?

Page 34: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

31

Is the ACP required to hold any contingency and if so, are individual providers

required to contribute to that contingency?

Are there any historical deficits, related to the relevant services, which require

funding?

6.17 Each of these questions should have been considered as part of setting the overall

contract value and therefore, should also be taken into account when deriving the

contract value for each of the providers within the ACP partnership.

b) What is the payment mechanism?

6.18 As far as possible, the flow of funds should support delivery of the contract aims, and

therefore allow providers to manage the risks that sit with them. As such, we set out

the following flowchart for considering the correct flow of funds for each party.

Figure 8: Flowchart for considering flow of funds between parties

Is the provider part

of the ACP?

Split costs as per

agreed contract value –

all accountable for

delivery of outcomes

1

Y

N

Is the provider

active in meeting

ACP aims?

2

Y

Split costs as per

agreed contract value –

including relevant

outcomes

N

It is a material

contract?

3

YDevelop contract that

can share value of

activity reductions

N

Pay on activity

basis, if possible

Capitated/block

payment with outcomes

Capitated/block

payment if possible,

including relevant

outcomes

Activity-based contract

with risk-share/volume

limiting agreement

RationaleSuggested payment

mechanismKey factor

Page 35: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

32

6.19 In general, the ACP should look to share responsibility for achievement of outcomes

between ACP partners so that all partners are bought into achieving the same goals.

This is particularly relevant where outcomes are related to whole population health

improvement, such as is the case with the NWL outcome measures for over-65s that

have been developed. Whilst particular ACP parties may have more influence over

some of these measures than others, the ACP will want to foster a sense of

collaboration and shared accountability. In general, the ACP contractual relationships

will want to reflect the overall ACP contractual relationship i.e. partners receive a fixed

payment according to their costs, along with a payment that varies based on ACP

outcomes achievement.

6.20 This rationale also holds true where a service provider is not part of the ACP

agreement, but is still key in delivering the aims of the ACP. Ideally, if a provider is key

to delivering the aims of the ACP, that provider would be part of the ACP. Where this is

not possible, any provider integral to delivering ACP goals should be incentivised in

the same way i.e. paid on a fixed basis and held to account for delivery of outcomes.

An example of this may be where social care is not part of the ACP but holds an

important role in changing the way that care is delivered to an over-65s population

cohort.

6.21 In some cases, providers outside of the ACP may not be willing to put some of their

contractual payments at risk. In this case, the ACP partners will need to jointly take

a decision as to how much of the risk they are willing to retain and how important

incentivising that provider to collaborate is to achievement of the ACP goals. It is

important to emphasis here that, the outcomes targets set between the

commissioner(s) and the ACP should not entail significant risk for providers, but

should be set at an achievable yet challenging level. This principle should also ideally

apply to agreements made within the ACP and with sub-contractors. The outcomes

payment is to guarantee quality, not to drive cost-cutting and discourage providers

from participating in the ACP.

6.22 For all other providers i.e. those who are necessary to service provision but not

necessarily integral for delivery of ACP goals, the ACP should try to manage the

financial risk it is exposed to by agreeing fixed payments, or capped payments where

possible. This may extend to providers that react to activity, rather than being able to

exercise control over demand e.g. out of hours providers. Any such agreements will

require negotiation with the relevant sub-contractors and in some instance, local

modifications to payment and therefore agreement with the appropriate regulatory

body i.e. NHS Improvement.

Page 36: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

33

Risk-share agreements

6.23 One of the key determinants of success for the ACP will be its ability to manage the

financial risk that it takes on as part of the capitated payment structure. Under this

arrangement, the ACP is signing up to managing all (or at least some) of the care

needs for a particular cohort for an agreed length of time. As such, if the costs of

caring for that population are greater or less than income received through the

capitated payment, the ACP will be responsible for that additional cost or surplus.

6.24 This risk is separate to the financial risk related to the achievement of outcomes. The

risk discussed here is that related to delivery of the services within the

established financial envelope. Under current contractual arrangements, each

individual provider, in conjunction with the commissioner(s) are responsible for their

own financial management and for delivering services within an agreed envelope.

Different providers will face different levels of risk, depending on the nature of the

payment mechanism e.g. block contract or activity-based contract.

6.25 Under a new capitated contract, the providers will agree to share the risk that the ACP

takes on by accepting a fixed payment (that varies only by the number of people in

the contract). Providers and commissioner(s) will therefore need to agree how

financial risks are allocated between them. The below diagram and following sub-

section sets out a process by which the commissioners and the ACP can seek to

allocate contractual financial risks.

6.26 This must be done before contract go-live so that all parties understand the risks that

they face and can put appropriate risk mitigation strategies in place. Each

organisation must understand the risks that it is agreeing to accept as part of the ACP

contracting process.

Figure 9: Process for allocating financial risks

Set KPIs for identifying and

applying risk share

Agree backstop sharing

arrangements

Agree (where possible)

allocation of risks between

CCG and provider

Agree risk share between

CCG and provider for

“residual risks”

Agree allocation of

risks between providers

1 2 3 4 5

Page 37: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

34

(1) Agree (where possible) allocation of risks between commissioner(s) and ACP

6.27 Under current contractual arrangements, the commissioners retain the majority of the

risks of financial overspend, particularly in relation to acute activity. If acute activity,

for example, is greater than planned, then the CCG is (in most cases) obligated to

cover the additional expenditure13. Under a new capitated payment, some risks (such

as demographic change) might remain with the CCG but a number of other risks

would move to the ACP to manage. The ACP therefore, needs to be clear as to the

risks that it is taking on in order to ensure that they are managed appropriately.

6.28 As an example, we have set out some of these risks in the figure below, along with

indicative risk owners. This will all be subject to negotiation and agreement between

the commissioners and provider.

Figure 10: Example risks to be borne by commissioners and providers

13 We note that such over-activity normally forms part of the contractual negotiation process and

both commissioners and providers are likely to take on parts of this over-expenditure in practice.

Cohort is larger

and/or older

than expected

Example risk Causes Suggestion as to owner of risk?

People within

the cohort are

more/less

healthy than

expected

Unexpected

extreme event

(e.g. severe flu

outbreak)

Average cost

per unit of care

is higher/lower

than expected

Demographics – Increase caused by

exogenous factors (e.g. migration).

Patient care – Better care results in

less mortality and a larger/older

population than expected.

Patient care – The level of care

received by providers will influence

the health of the cohort.

External factors – Other public

health factors will influence the

health of the cohort.

External factors – These are

unpredictable and exogenous events

(e.g. very severe winter, epidemic).

Provider efficiency – The unit cost

of care can be influenced by

providers.

External factors – Other variables,

such as general inflation, which are

outside of the control of providers

Commissioners – Demographic

changes can not be influenced by

providers, and providers should be

financially rewarded for better care.

Providers – Providers can influence

the health of the cohort by providing

more preventative and integrated

care.

Commissioners and providers – As

providers have limited ability to

control costs resulting from these

events, risk should be shared.

Providers – Providers can influence

the cost of care by improving

efficiency. As part of receiving the

benefits derived from a longer

contract, the providers may also

agree to take on external risks such

as inflation.

3

1

2

4

Page 38: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

35

6.29 At this stage, the commissioners and providers will seek to agree where the potential

risks will fall and codify this agreement in the ACP contract. For example, if the

commissioners agree to take on financial responsibility for changes to the

demography the ACP contract will make specific provision for increasing payment in

the event of demographic change e.g. through paying via a capitated rather than a

block payment.

(2) Agree risk share between CCG and provider for “residual risks”

6.30 At this stage of the contractual process, it is unlikely that the parties will be able to

identify all of the potential financial risks that might arise and make detailed

provisions. It will therefore be necessary to agree how any “residual risks” (or

benefits) might be allocated. In practice, this means making explicit agreement as

to how much risk the commissioner(s) are willing to be exposed to, in order to

incentivise providers to take part in the ACP arrangements.

6.31 In the early years, providers may be concerned about the risks of taking on population

management for an entire cohort for a significant period of time. As such, the

commissioner may wish to make provision to absorb some of the overspend should

the ACP fail to live within its financial envelope. As a quid pro quo of this risk share,

the CCG might demand that a share of any underspend be passed back to it. Again, it

is essential that this agreement is made ex ante to prevent disputes once the ACP is

up and running.

6.32 Whilst this ‘risk-sharing’ may have some benefits in terms of encouraging provider

participation in the new arrangement it is important to note that it comes at the cost

of dampening the incentives created by the new contract structure. Any agreement

made by the commissioner should therefore be to mitigate some of the financial risk

and not to remove the incentives created by an accountable care contract entirely.

(3) Agree allocation of risks between providers

6.33 Once the ACP partners are clear on the financial risks that must be managed within

the partnership, agreements can then be made as to how these risks are shared

between them. This means deciding what sort of costs providers will be responsible

for themselves and which will be subject to sharing between the ACP partners. For

example, if a provider has a cost overrun relating to its over-65s services, is it

responsible for that cost overrun or will the providers share the costs between them?

The answer to this question is not straightforward as shown in the example below.

Page 39: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

36

Figure 11: Cost expenditure scenario for an ACP

6.34 In the scenario shown above, ACP providers had initially estimated a contract spend

of £62m on in-scope services, split between the acute and community provider as

shown. However, the actual costs were £65m with the acute provider spending £35m

- £5m more than planned and the community provider £2m less than planned. There

are a number of reasons why this may have occurred, including (a) that the acute

provider was inefficient or (b) that the community provider’s new service model did

not work and as a result caused an increase in acute activity. Under either case, the

ACP must be clear as to how the increased costs will be allocated between

providers.

6.35 As set out in Section 3, the principle of shared risk will be a key underpinning of the

ACP. As such, making each provider solely responsible for any contract losses runs

contrary to the shared values of the ACP. However, it is important that providers are

still incentivised to provide cost effective care and minimise inefficiency.

6.36 As such, it will be necessary to establish guidelines for which costs are shared and

which are borne by the provider that incurred them. In the example above, ACP

partners may determine that any costs caused by “inefficiency” should be borne by

the provider that incurred them, but any costs caused by failure of the jointly agreed

ACP service model should be a cost to the ACP. These guidelines may be difficult to

establish but will set expectations within the ACP as to how costs will be assigned and

managed over the course of the agreement.

6.37 In the early years of the ACP, the partners may wish to set simpler rules such as that

overruns up to a certain value are met by individual providers and then met jointly by

the ACP. We cover this sort of arrangement in ‘(5) Agree Backstop sharing

arrangements’ below. This sort of arrangement can help encourage joint

accountability but can also create perverse incentives, as discussed below.

AcuteComm.

providerACP partners

Forecast cost of

ACP services£30m £32m £62m

£65m

Total

cost

Actual cost ACP

services£35m £30m £3m

Over-

spend

Page 40: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

37

(4) Set KPIs for identifying and applying risk share

6.38 Once guidelines have been set, detailed KPIs will be needed to allow the ACP to

establish which costs fall into which category of expenditure e.g. to be borne by

individual providers or to be borne by the ACP. In order to make these

determinations, it may be useful for the ACP to establish regular cost information

sharing, allowing ACP partners to monitor overall contract expenditure. This will also

allow the ACP to make any necessary risk mitigation plans as issues arise.

6.39 Each ACP will monitor contract expenditure by ACP providers differently, but we have

set out below some example KPIs.

Area Description Metric

Service line

expenditure

Providers service line

expenditure is as expected i.e.

reflects agreed service model

Expenditure/Planned

expenditure

Capital expenditure Providers have invested in

capital expenditure in line with

agreed profile

% of Capex invested vs

planned expenditure

Workforce expenditure Provider’s pay costs are as

expected with no significant

expenditure on temporary staff

e.g. agency staffing

Pay costs, temporary

staffing as a percentage of

pay costs

Cost savings Provider has made cost

savings in line with agreed

profile

Savings as a % of agreed

plan

6.40 These KPIs will allow the ACP to monitor expenditure for each of the partners and

then inform the decisions as to whether the expenditure should be met individually or

by the ACP.

(5) Agree backstop sharing arrangements

6.41 In reality, there are likely to be costs (or benefits) where it is not easy to determine

how the established rules should be applied and therefore which party is responsible

for those costs. We refer to these as ’unallocated costs’. In these instances, the ACP

should have ‘backstop’ arrangements in place which allow the ACP to share out these

costs without resorting to escalation/dispute resolution processes.

Page 41: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

38

6.42 These arrangements should be considered to be a ‘backstop’ as it is important that

ACP partners are incentivised to share risks as per the original agreement and not

rely on contingency arrangements. As such, it is important that these arrangements

do not create perverse incentives. For example, if the ‘backstop’ arrangement was

that all ‘unallocated’ costs were paid out of any risk-pool or contingency fund, then

providers might be incentivised to try and label as many costs as possible as

unallocated.

6.43 As such, the ACP may want to agree that each provider first bears an initial amount of

the ‘unallocated cost’ before funds from the risk pool are accessed. For example,

providers are responsible for bearing the first £250,000 of any unallocated cost, any

additional amounts are paid out of the risk pool/contingency monies.

6.44 Clearly a rule such as this can also create perverse behaviours i.e. once an

unallocated cost greater than £250,000 has been accumulated, there are no

incentives to minimise expenditure. However, the parties have access to escalation

and dispute resolution processes if they believe that any one party is failing to share

the values that have been agreed within the partnership.

6.45 The aim of these arrangements is to make sure that there are means of setting any

financial risks that have not been fully assigned. As such they should be documented

in the initial contractual agreements.

Case studies: Contracting for financial risk in other health economies

6.46 As part of our work with NWL and other health economies, we have researched the

contractual funding flows and financial risk management arrangements made by

other health systems. We set out below some relevant case studies.

Case Study 3: Kaiser Permanente, California, USA

Kaiser Permanente is a non-profit, nongovernmental managed care organisation

(‘MCO’) founded in 1945 and based in California, USA. It operates in nine states and

the District of Columbia and has 8.7 million members.14

As an MCO, Kaiser Permanente operates a health insurance plan (the Kaiser

Foundation Health Plan) as well as health care provision through its Private Medical

Groups (PMGs) and Kaiser Foundation Hospitals. Its innovative contracting, delivery,

reward, governance, and information arrangements have enabled it to improve the

quality of care and reduce cost as compared to other health plans.

14 Porter and Kellogg (2008) Kaiser Permanente: An Integrated Health Care Experience, RISAI

(1:1).

Page 42: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

39

Contracting for required medical services within Kaiser Permanente is done by the

Private Medical Groups, which share incentives with the Health Plan to keep members

healthy and the costs of care low. The entities are underpinned by mutual exclusivity,

meaning that the Private Medical Groups do not practice medicine under other health

plans and the Health Plan does not directly contract with other medical groups.

Clinical decisions are made by doctors instead of the Health Plan. (Notably, PMG

physicians have often advocated a comprehensive benefit package in the Health Plan

as this allows them to more easily coordinate an individual’s care.) PMGs deliver

outpatient and primary care and refer patients for secondary and specialist care.

Kaiser Permanente owns and operates its own hospitals in California, Oregon, and

Hawaii and contracts with community hospitals in other regions. It has 14,000 doctors

and 160,000 employees and runs 421 medical office buildings (for ambulatory care)

and 32 medical centres (hospitals). Health services are often co-located, encouraging

integration between different service lines.

PMGs receive a prepaid amount (per member per month) from the Health Plan to

deliver outpatient care. This is used to pay market-based salaries for doctors and

bonuses of up to 10% if the programme performs well against quality, access and

service measures.

Case Study 4: Uniting Care contract, Cambridgeshire and Peterborough, UK

In November 2014, Uniting Care Partnership LLP, a limited liability partnership (LLP)

between two NHS Foundation Trusts, entered into an innovative contract with

Cambridgeshire and Peterborough CCG. The contract was for the provision of all

community care for patients over 18 years old and acute emergency care for patients

over 65 years old together with older peoples mental health. It was novel for the NHS

as it required integration of services and a significant proportion of the payment was

based on outcomes.

The 5 year contract (valued at £725m) commenced on 1 April 2015. However, in

December 2015, the contract collapsed for financial reasons. While all parties to the

contract agree that it was the right approach for the provision of the services, NHS

England in its review identified a number of issues for the failure of the contract, a

number of which relate to financial risk.15 These include:

Insufficient information about the cost of providing existing community services;

Resistance to a ‘risk and gain share’ arrangement by the CCG while shortlisted

providers found it very difficult to accept the proposed level of risk;

15 NHS England Review of Uniting Care Contract, April 2016, Publications Gateway Reference

05072.

Page 43: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

40

Unforeseen VAT cost that was avoided under the NHS VAT arrangement but for which

the LLP did not qualify;

Lack of agreement on the final contract value at the time of commencement;

An insufficient mobilisation period that failed to enable the planned financial savings

that were required in the first year of the contract; and

Failure to obtain financial guarantees from both Foundation Trusts.

Case Study 5: MSK Collaboration

The providers established a risk pool, based on including the margins received on the

contract value (i.e. only paying the providers their costs plus overheads).

Treasury management functions were undertaken by a joint venture vehicle (for a

percentage of the contract value), and this involved ensuring that all partners and other

sub-contractors were paid for service delivery. The treasury management function also

involved the retention of the risk pool, and the provision of working capital if required in

the early stages of the contract. A support contract for treasury management services

was drafted and entered into by the lead provider and treasury management services

provider.

Furthermore, each of the partners invested £250k as working capital at the outset of

the contract, and provisions were included in the contractual arrangements as to what

would happen to such amounts on exit.

Of the providers involved, those provider who provided the services, and who were

ultimately able to influence the demand for the services, shared the lion’s share of the

risk relating to the management of cost overruns under the contract.

Page 44: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

41

Case Study 6: ACOs within Medicare

In 2011, the US Department of Health and Human Services (HHS) working with the

Centers for Medicare & Medicaid Services (CMS)16 published new proposals to support

providers of health care services to improve the quality and coordination of care for

Medicare patients through the formation of ACOs.17 In particular, The Medicare Shared

Savings Program (SSP) was set up to reward ACOs that lower health care costs while

meeting performance standards on quality of care and putting patients first.18

In this context, CMS described an ACO as “a group of health care providers in a care

delivery system who agree to accept joint responsibility for the medical care and

management as well as the cost and quality outcomes of a designated population of

patients”.19 An ACO transforms the organization, delivery, and financing of care by

replacing fragmented, uncoordinated care with an arrangement in which providers

work together to achieve shared goals of better care at a lower total cost. An ACO also

preserves the ability of patients to choose and form an active partnership with the

providers that best meet their own needs.

In practice, an ACO working with Medicaid is a separate legal entity capable of servicing

a minimum of 5,000 Medicare patients. While primary care physicians are locked into

a single ACO, secondary and specialist care providers can simultaneously participate in

multiple ACOs. An ACO must have its own governing body with representation from all

participating entities and include a community stakeholder and a Medicare beneficiary.

Once approved by Medicare, ACOs contract with the Medicare Shared Savings

Program.20 The contract includes quality initiatives predetermined by CMS, with a

concentration on primary care and mandatory inclusion of patient satisfaction scores.

16 CMS (part of the HHS) covers 100 million people in the USA through insurance programmes such

as Medicare, Medicaid, and the Health Insurance Marketplace. The strategic goals of CMS are: to

offer its beneficiaries high quality, coordinated, effective, efficient care in order to reduce costs;

to improve access to affordable health insurance options for all Americans; and to improve the

health of all Americans through the wide use of preventative benefits and necessary health

services. See: (1) CMS.gov. <https://www.cms.gov/>; and (2) CMS Strategy: The Road Forward

(March 2013), Available at: <https://www.cms.gov/About-CMS/Agency-Information/CMS-

Strategy/Downloads/CMS-Strategy.pdf>.

17 News release (31 March 2011) Available at: < http://wayback.archive-

it.org/3926/20140108162229/http://www.hhs.gov/news/press/2011pres/03/20110331a.ht

ml.

18 Ibid. See also: Shared Savings Program, CMS.gov. <https://www.cms.gov/Medicare/Medicare-

Fee-for-Service-Payment/sharedsavingsprogram/index.html?redirect=/sharedsavingsprogram/>.

19 ACO: Accelerated Development Learning Sessions (ADLS). CMS.gov. Available at:

<https://innovation.cms.gov/initiatives/ACO/ADLS/index.html>

20 Shared Savings Program ACO Agreement. CMS.gov. <https://www.cms.gov/Medicare/Medicare-

Fee-for-Service-Payment/sharedsavingsprogram/Shared-Savings-Program-ACO-Agreement.html>

[Accessed 12 May 2016].

Page 45: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

42

Regulations allow an ACO to choose one of three reimbursement tracks. The first track

is a ‘shared savings only’ arrangement available to the ACO for the duration of the first

and second agreement periods. The second and third tracks allow the ACO to share in

savings and losses for the duration of the agreement in return for a higher share of any

savings generated.21

When an ACO succeeds both in delivering high-quality care and in reducing its own

spending, it will share in the savings it achieves for the Medicare program. Eligibility for

shared savings is determined by comparing the ACO’s outturn expenditure to its own

specific updated expenditure benchmark. ACOs that choose to participate in a two-

sided performance-based risk model (i.e. those that are accountable for sharing gains

as well as losses) will repay Medicare for a portion of losses (expenditures above the

ACO’s updated benchmark by a specified percentage).

21 Summary of the June 2015 Final Rule Provisions for Accountable Care Organisations (ACOs)

under the Medicare Shared Savings Program (March 2016) ICN 907404. Available at

https://www.cms.gov/Medicare/Medicare-Fee-for-Service-

Payment/sharedsavingsprogram/Downloads/ACO_Summary_Factsheet_ICN907404.pdf

[Accessed 12 May 2015].

Page 46: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

43

7. Agreeing contract governance

Overview

7.1 In addition, we have explored some key aspects of contract governance which must

also be agreed ex ante. The governance arrangements, to a large extent, will be

informed by the proposed legal form of the collaboration between organisations.

7.2 As referenced earlier, the early adopter localities in NWL are seeking to move towards

a position where they are ready to formally collaborate with each other, in order to

hold a capitated budget and deliver integrated services on a population basis. In

some of these localities, work is required to build relationships alongside clinical and

operational strategies, prior to being in a position to consider legal documentation to

underpin a collaboration.

7.3 When groups of providers are ready to consider a formal collaboration, there are a

range of different legal options that they may wish to pursue (for ease of reference,

we refer to these as “legal forms”). These include:

Contractual joint venture model (MoU or alliance agreement);

Corporate vehicle (service integrator22, service provider or wholly owned

subsidiary); and

Lead provider model with sub-contracts.

7.4 An illustration of the different legal forms and different legal agreements involved in

each is set out below:

22 A service integrator is typically an entity that is set up to undertake functions to help integrate

various services being provided, rather than providing services itself. It might undertake

functions that are similar to commissioning management functions.

Page 47: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

44

Figure 12: Integration spectrum

Page 48: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

45

7.5 The four areas of contract governance that we have been asked to consider are as

follows:

Liabilities of individual organisations;

Holding providers to account for quality and outcomes;

Collective decision-making and dispute resolution; and

Contribution of people and resources to manage the ACP.

7.6 There is significant synergy between documenting the contribution of people and

resources to manage the ACP and detailing how to split liabilities of individual

organisations, and therefore we consider those two issues together in this report.

7.7 For each of those areas, we have set out the generic issues that providers need to

consider before reaching a recommended solution:

Contract

governance

issue

Key questions to be addressed

Liabilities of

individual

organisations

/ contribution

of people and

resources

What are the

providers contributing

to the collaboration

(e.g. workforce,

estate, IT, back office

services)?

What are the risks

associated with the

resource being

contributed (e.g.

employment tribunal

claims, information

governance breaches,

etc.)

How can those risks be

mitigated, and what are

the likely liabilities

associated?

Can those liabilities be

shared between

providers, and if so, in

what proportion?

Holding

providers to

account for

quality and

outcomes

Will individual

providers be

contracted to meet

certain specific

outcomes / parts of

outcomes, and how

measurable is this?

Have KPIs and

monthly reporting

against targets been

agreed? Are providers

operating on an open

book basis?

Consider frequency of

intra-provider reviews,

and what information

needs to be shared to

monitor the same.

Ensure that timely,

reliable information

about performance is

analysed and discussed

at relevant governance

forum between

providers.

Include contractual

mechanism allowing for

provider to provider

performance

management, where

certain trigger points

have been reached (e.g.

certain thresholds for

quality have been

breached)

Collective Where contractual Consider whether Where decisions cannot

Page 49: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

46

decision

making and

dispute

resolution

collaborations are in

place, what authority

do representatives of

any “Provider Board”

have to bind their

organisations?

Where a corporate

joint venture is in

place, decision

making can be

constructed and

designed with more

flexibility.

decisions are to be

made by (for example)

(i) unanimous

agreement (ii) votes

from various providers.

It is possible to agree

upon a mixture of these

two options, and

reserve certain

decisions for

unanimous approval by

the providers.

be made and there is a

deadlock, or a dispute

arises, a clear process of

escalation should be

included within the

contract / corporate

documentation. This

typically involves local

resolution, followed by an

alternative dispute

resolution procedure,

such as mediation or

arbitration.

7.8 In order to document principles in respect of the different contract governance

issues, the legal form being utilised has an impact upon the approach. We have

analysed each of the contract governance issues for each of the legal options within

our three different case studies below.

7.9 We have also considered each of the legal forms and the relevant contract

governance issues at a broader level, as follows.

Contractual joint venture (MoU or Alliance Agreement)

7.10 When setting up a contractual joint venture between providers, no new legal entity is

being formed, and each individual organisation remains. When seeking to create an

ACP, and with the objective to integrate care, the boundaries between individual

organisations need to be ignored in some circumstances. However, each of the

providers needs to clearly agree the terms of its participation from a legal

perspective, as each individual organisation will remain accountable for its acts

and/or omissions. A failure to clearly agree such terms may lead to a failure with

regard to contract performance, or indeed a breakdown of relationships between

those providers within the ACP.

Page 50: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

47

7.11 Under a contractual joint venture, the resources that each of the provider parties will

be contributing must be documented within the relevant contract. Where providers

are working under a light touch MoU (e.g. where certain incentive payments are

released for the achievement of certain performance metrics), it may be that there is

very little extra resource required – it may simply be extra staff to manage the

collaboration. The liabilities of each individual organisation will really depend upon

the resources that they are contributing to the collaboration, and what the exit

arrangements are.

7.12 Under an alliance contracting model a change is required to the traditional

commissioner-provider relationship in order that the commissioner allows the

collective of providers to develop the detail of how services are provided, within

certain parameters, rather than specifying, and holding providers to account for

inputs. When considering a full alliance contracting regime with multiple provider

organisations, there may be a range of resources that will be contributed by different

parties at the outset. This may include the costs of extra staff, estate, IT solutions

and third party contracts. There are also opportunities for the sharing of back office

functions, and potential efficiencies from collaborating and creating shared services

between the providers. Where there are long term contracts in place, the contract

should also anticipate how resources may change over time, and how the parties will

deal with it.

7.13 It may be the case that one of the providers agrees to “host” these resources, i.e.

employ all of the staff, enter into third party contracts on behalf of the alliance, etc.

From a legal perspective, providers would seek to set out a range of protections, such

as indemnities. See our case study on Alliance Contracting for further information.

NHS England has commissioned an example Alliance Contract to be drafted, with

accompanying guidance notes. This is available, in draft form, from

[email protected] and the principles included within it are referred to in

section 3.

Page 51: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

48

Corporate vehicle (corporate joint ventures (service integrator or service provider)

and wholly owned subsidiaries)

7.14 The set-up of corporate vehicles in the NHS for clinical service provision has not been

widespread to date. There are some models, such as pathology services, where

corporate joint ventures are more commonplace, however such services are relatively

discrete in scope. Recently, we have seen a corporate joint venture, Uniting Care LLP,

set up by two NHS Foundation Trusts for the provision of all community care for over

18 year olds, acute emergency care for the over 65s together with older peoples

mental health services in Cambridgeshire and Peterborough (see Case Study 4 in

section 5 of this report). The contract collapsed after 9 months of being in force, and

NHS England’s recent review acknowledged the VAT issues, which had not been

resolved by the time that the contract had been entered into. This relates to the

recovery by NHS bodies of contracted out services VAT, and is an issue being

discussed between Department of Health and HMRC, as part of the Vanguard

programme.

7.15 Whilst as a result of the current legal blockers and potentially the risk appetite in the

NHS, there are not a significant number of live examples of corporate joint ventures

for clinical services in operation in the UK. The set-up of a corporate vehicle (whether

as a corporate joint venture or wholly owned subsidiary) would still involve a number

of contractual interfaces between various collaborating members.

7.16 The corporate vehicle itself could be delivering services, employing staff, leasing

premises, holding CQC registration, etc. Alternatively it may be holding a head

contract with Commissioners and providing a service integrator role (similar to

commissioning management) to manage the flow of services that fall within the

capitated budget given to the ACP.

7.17 One of the key attractions of setting up a new corporate joint venture are that in most

cases, the liability can be ring fenced from other organisations. It can also engender

the sense of something “new” being created amongst partners, with separate

governance arrangements, rather than having numerous separate sets of governance

arrangements as part of an alliance arrangement, for example.

7.18 There are also opportunities to use corporate vehicles to set up a wholly owned

subsidiary of NHS Foundation Trusts, allowing a separate legal entity, wholly owned

by the FT, to focus on particular services. We have set out an example of the legal

mechanics of how this can work in our case study on Northumbria Primary Care,

below.

Page 52: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

49

7.19 It should be noted that there are many examples of GP providers setting up corporate

joint ventures for a range of different purposes, from services delivery to providing a

service integrator function. GP providers are not established under statute and are

therefore not subject to the same regulatory regime as, for example, NHS Trusts.

Lead provider model

7.20 Aside from contracting with individual organisations, the lead provider model is the

most tried and tested way of contracting for clinical services in the NHS. This model

involves one nominated organisation holding the relevant commissioning contract on

behalf of the ACP, and sub-contracting services to other providers.

7.21 This model does not generally include the set-up of a new corporate entity (though it

could involve a new corporate entity as lead provider), and therefore liabilities of

individual organisations are defined by the contractual obligations that they enter into

for the purposes of the ACP. On that basis, the lead provider will be liable for all of the

obligations set out in the head contract with commissioners, and sub-contractors are

likely to have to discharge some of these obligations by the lead provider “flowing

down” obligations in sub-contracts.

7.22 It is possible for a lead provider model to involve a contractual joint venture

agreement, often called a partnership agreement, as there may be many areas that

providers (both lead provider and sub-contractor) wish to take a partnership approach

to. We have set out details as to how providers hold each other to account, how

decisions are made and disputes are resolved, in our case study on the MSK

Partnership Collaboration, below.

Case studies: Establishing governance arrangements in other health economies

Case Study 7: Alliance contracting in the NHS

An alliance comprised of an acute NHS Trust, a mental health and community services

NHS Trust and GP Federation ("the Providers") were chosen as the preferred providers

in one of the first alliance contracting regimes in the NHS, for community based

elective care services.

This involved commissioners (two CCGs) and provider organisations working

collaboratively to ensure the delivery of services across two large CCG areas. In this

case study, we collectively refer to the commissioners and Providers as the "Alliance".

Key features

The alliance contract is for a 7 year term and included all of the Alliance as parties to it.

The key aims of the Alliance were to:

Page 53: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

50

•Develop integrated ways of working across the Alliance based on a shared risk and

reward framework, unanimous decision making, aligned objectives and a requirement

to act in a way that was 'Best for Project';

•Ensure that community based elective care is delivered in the most clinically

appropriate setting;

•Remove duplicate or unnecessary steps in existing patient pathways and improve

communication across health organisations within the region;

•Increase value for money of existing services and achieve cost savings across the

local health economy; and

•Make better use of existing real estate and facilities.

Looking at each of the relevant issues to this report in turn:

Contribution of people and resources to manage the ACP and liabilities of individual

organisations

The main resources that various Providers contributed were staff and equipment. The

Alliance Contract included specific provisions setting out how Providers would

indemnify each other in respect of any of the acts of their own staff in connection with

the Alliance. This is necessary to protect each of the Provider’s positions in terms of

acts and omissions of staff from other organisations, and fits with the insurance

arrangements of each Provider, as well as the concept of vicarious liability (i.e. each

employer is vicariously liable for those acts and omissions of its staff in the course of

their employment). There are also a range of staff related indemnities included in the

NHS Standard Contract between Commissioners and individual Providers, which

cannot be amended.

In terms of the use of equipment, an agreement was entered into by the acute NHS

Trust as agent for the Providers and one of the CCGs on behalf of the Commissioners,

which details the terms on which various assets owned by the CCGs and third parties

are leased to the respective Provider(s) delivering the services. This set out payment

terms as well as a range of warranties (e.g. as to how the state of the equipment and

how it will be used) and indemnities (e.g. in relation to issues arising from the use of

such equipment).

Holding providers to account for quality and outcomes

Page 54: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

51

In order to incentivise delivery of cost savings in line with the Alliance Objectives, the

model included an opportunity for incentive payments to be released where it can be

shown that the cost of providing particular services (utilising the NHS costing guidance)

is less than the amount paid under the National Tariff, with such incentive payments to

be re-invested into the services. This encouraged all of the Providers to work

collectively to achieve the best outcome for the Alliance, aligned to the best outcomes

for the population.

Separate KPIs were also included in the Alliance Contract that would require all of the

Providers to meet them in order for the performance incentive to be released to the

Providers. Again, these incentives included in the Alliance Contract fostered a collective

approach to service delivery amongst the Providers. The performance incentives were a

relatively small proportion of the overall contract value (less than 5%).

There are also levers in place whereby Providers have agreed a process to deal with

poor performance, involving the Commissioners who have the ability to issue

“rectification notices” or, where remedial action is not possible, an exclusion notice

(effectively ending their involvement in the Alliance, on notice). This would also mean

that the individual NHS Standard Contract held by that particular Provider would be

terminated at the same time.

Collective decision making and dispute resolution

An Alliance Leadership Board was set up amongst the Providers, tasked with

managing, directing and leading the Alliance in accordance with the Alliance Principles

(defined in the Alliance Contract) and setting overall strategic direction in order to meet

the Alliance Objectives (defined in the Alliance Contract).

The Alliance also involves an Alliance Management Board, whose role and remit is to

be responsible for the day to day management and support of the activities of the

Alliance in accordance with the Alliance Principles in order to meet the Alliance

Objectives. The various members of the AMB each had one vote and must exercise

such vote in a manner consistent with what is “Best for Project”.

Each of these governance structures involve representation from each of the Providers,

and the Alliance Contract includes defined responsibilities for both the ALB and AMB.

For example, the ALB is responsible for making decisions on matters of intra-Provider

performance, as to whether, based on review of performance, a particular Provider’s

performance is such that it needs to be escalated to the Commissioners, who would

then decide whether or not to effectively expel that Provider from the Alliance.

Page 55: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

52

An escalation process to resolve disputes between Providers was included within the

Alliance Contract. This included reference to the ALB in the first instance for resolution.

If no resolution was found at that forum, it would be escalated further to the Dispute

Resolution Panel. That DRP has the ability under the Alliance Contract to resolve the

dispute or put the dispute forward for mediation or arbitration for resolution.

Lessons learned

It is still relatively early in the term of this alliance contract, therefore it is not possible

to analyse the effectiveness of the arrangements in detail. However, initial feedback

from those involved in the operation of the alliance is that clarity on the Alliance's

goals, objectives, investment fund and KPIs (including the consequences of succeeding

or failing to deliver them) is crucial in order to minimise conflict between them and any

commissioners' rights to override the 'Best for Project' requirement in certain

circumstances.

It was also noted within the project that GP engagement is crucial and continues to be

challenging as the structure and organisations of primary care continues to change

with GPs belonging to an increasing range of organisations.

Case Study 8: Northumbria Primary Care

Northumbria Healthcare NHS Foundation Trust ("Northumbria") has created a wholly

owned corporate vehicle, Northumbria Primary Care Limited (“NPC”) in response to a

request from the local primary care market for support, creating a new model for the

delivery of primary care. In March 2015 Northumbria was selected as a Vanguard to

integrate primary and acute care systems (PACS) for Northumberland, with the aim of

creating closer ties and working relationships with primary care medical services. The

success of NPC will help to facilitate the progress of the PACS vanguard project.

Key features

The NPC project was built on a foundation of years of successful collaboration between

primary and acute care in Northumberland and North Tyneside, with fully engaged local

GPs. NPC provides strong clinical leadership and support to help GPs with meeting the

everyday challenges facing local practices.

This support allows for bespoke packages to be created, meeting the individual

requirements of different GP practices, which includes:

Page 56: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

53

Management support: providing general practices with back office support, expertise

and resources to reduce practice costs and place the practice in a stronger position to

win contracts and generate new income streams, allowing the practices to focus on

their clinical provision and improved outcomes for patients. This includes quality

governance and compliance, payroll management, financial services, human resources

and organisational development and estates maintenance; or

Full support: providing the full clinical service under the practice's primary care

commissioning contract by way of a sub-contract between the practice and NPC, with

the consent of NHS England.

NPC allows GPs to access substantial corporate expertise from Northumbria as a

successful Foundation Trust, but also retain control over the level of service they need

in order to run their practice effectively.

Contribution of people and resources / liabilities of individual organisations

Staff are the most important resource involved in this collaboration. Under the NPC

model, it was essential to clearly and concisely set out the "employment deal" for staff

once GPs and practice staff transferred to the employment of NPC. GPs in particular

required detailed information about the impact on income tax and national insurance

contributions, and any impact on pensions.

Holding providers to account for quality and outcomes

Under this model, the individual sub-contracts from GP providers’ core primary care

contracts to NPC set out the mechanism by which GP providers can hold NPC to

account for services delivered. These arrangements provided both the GP providers

and the overall commissioner (NHS England) with the assurance required.

Collective decision making and dispute resolution

The governance aspects required detailed planning as to the delegation of authority for

certain decisions. There were also matters to be considered relating to reporting lines,

holding to account and decision making between Northumbria as parent and NPC as

subsidiary. These matters were resolved within an Operational Agreement between

Northumbria and NPC, setting out the parameters within which NPC operates.

Escalation of risk management issues and the management of conflicts of interest

were also key governance areas to tackle and these were documented in the

Operational Agreement, with an escalation procedure to resolve any disputes arising.

Lessons learned

A key challenge within the project was the fact that NPC is not an eligible body to hold a

GMS Contract, therefore the design of a contractual structure that complied with the

GMS Contracts Regulations was key (see above regarding the sub-contractor model).

Page 57: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

54

Northumbria and NPC had to work hard on the perception challenge in the region to

ensure that GP Practices did not view NPC as a route for secondary care to "take over"

primary care. It is very much a partnership and collaborative approach. It was also

crucial to ensure NHS England were involved in the journey and were on board with the

concept.

Outcomes

As a result of the management support provided by NPC, early results have been very

impressive with one member practice recording a 76 % improvement in routine access

times. Another practice has saved £6,000 in monthly expenditure.

Case Study 9: MSK Partnership Collaboration

A primary care federation, Community NHS Trust, Foundation Trust and third sector

provider collaborated to provide an integrated, multi-disciplinary musculoskeletal

("MSK") service, under an outcomes based contract. Each of the participants held a

different role in contributing to the delivery of integrated MSK services.

The parties won a competitive process in order to take on the outcomes based

contract, and developed the details of their collaborative arrangements in the later

stages of the process.

Key features

•The primary care federation agreed to hold the head contract with the commissioners

on behalf of the MSK Partnership. It sub-contracted various clinical services to its

partners in the collaboration

• The providers within the MSK partnership entered into a partnership agreement

setting out how they will work collaboratively, and governance for joint decision making.

•Specific contracts for support services from individual providers were required. For

example, one of the providers agreed to provide treasury management services and

working capital for a period of the contract term

•The collaboration involved various organisations with different governance structures

and different commercial interests, but all focussed on seeking to integrate care, to

deliver care beyond organisational boundaries, and to create single teams with shared

purpose, single management structures and single performance frameworks

Contribution of people and resources / liabilities of individual organisations

Page 58: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

55

The providers had set out high level detail in their bid documentation as to how the

various organisations would work together to deliver the MSK services. On drilling in to

the detail as to how this would work in practice, further work was required to agree and

subsequently document the contributions.

The main resources in this project were staff and management from the primary care

federation and Community Trust, treasury management skills and the provision of

working capital from a joint venture company set up by the FT and third sector

organisation. Each of these contributions required documenting in the partnership

agreement (at a high level), and with more detail in individual support / sub-contracts.

Holding providers to account for quality and outcomes

The key services outcomes in this project were flowed into all sub-contracts (both

within the collaboration, and with those providers that were not part of the

collaboration, but were providing aspects of the MSK services). By including all of the

relevant KPIs and quality requirements in those sub-contracts, all providers were held

to account for delivering the same outcomes.

Within the collaboration of the providers, there were provisions whereby performance

between the providers would be monitored and discussed at Provider Board level, with

expulsion provisions included (though this was subject always to the consent of the

commissioner, given the terms of the NHS Standard Contract).

Collective decision making and dispute resolution

The providers agreed to document decision making in a jointly agreed scheme of

delegation. They also agreed certain key decisions that required unanimity of all or a

certain majority proportion of the Providers to agree before the decision would be

binding.

The providers set up a “Provider Board” where each of the providers was represented

with equal voting rights, though there was a commitment for the providers to reach

consensus where possible. The Provider Board was the forum for various decisions to

be made about the operation of the collaboration and management of the head

contract with commissioners.

Where there was a deadlock at Provider Board, a dispute resolution process was

entered into. The same dispute resolution process applied for other general disputes

between the providers. This involved the escalation of the issue to senior members of

each organisation for resolution. Where resolution could not be undertaken at that

level, the matter would go to mediation (by a CEDR nominated mediator). Following

that, there was one further step of escalation to expert determination, depending on

the type of dispute. Where the dispute related to the interpretation of the terms of the

partnership agreement, expert determination could be invoked.

Page 59: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

56

Lessons learned

Many of the critical discussions between providers, relating to risk share and

governance, took place after the tender had been won by the collaborative. This meant

that there was a great deal of pressure on the parties to reach decisions on potentially

significant risk areas at a late stage in a tender process, putting at risk the proposed

services commencement date, as well as straining the relationships between the

providers. It would have helped providers had they have agreed a number of the

headline issues at an earlier stage in the procurement process and documented them

in relatively detailed heads of terms.

Page 60: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

57

8. Conclusions

8.1 Our work with NWL covered a range of contractual and governance issues that

providers and commissioners will need to resolve before making detailed agreements

for forming ACPs.

8.2 Whilst there are relevant learnings from other health economies that can be drawn,

there is much that is new and innovative about these plans and therefore localities

will wish to carefully build up their plans, examining a number of possible scenarios

and outturns for the ACP.

8.3 The role of the commissioners is key. Whilst the role of the CCG will change and

evolve over time when commissioning from an ACP, in the early stages it is imperative

that commissioners are clear about what they want to commission, how they propose

to commission it and what their expectations are in terms of outcomes for patients.

8.4 Providers too must change behaviours and learn how to take decisions together,

focusing on best outcomes for patients rather than organisations. This is a difficult

area particularly given procurement law obligations of commissioners and

competition law obligations upon providers.

Locality site experiences

8.5 The tables below summarise the journey, challenges and next steps for each of the

localities that were part of this work process.

Page 61: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

58

West London

The journey The project confirmed

the objective of

focusing on the

successful WS IC

programme i.e. to

continue ‘Primary Care

led service delivery

focus in WL’ with

emphasis on ‘improving

integrated care across

organisational

boundaries’

We recognised

transformation change is

not achieved through

contracts but through the

development of

relationships; hence WL

approach to growing the

existing service delivery

model

A 4 week Journey of

discovery. We now

have shared

understanding of

process. And a

recognition of: ‘hard

questions’ and ‘lot of

work’

Challenges To move all parties

forward at same rate,

and to ensure system

wide leadership

To integrate GPs given the

GMS / PMS contracts with

NHS England for essential

services

To tender or not: risk

management, whilst

continuing the

dialogue with

partners, and

iterating a new

outcomes based

specification (patient

quality and

experience)

Next steps Having confirmed

patient cohort (over

65s?) produce data set

and confirm services

Once data set and services

are confirmed, carry out a

financial analysis of

services at HRG level

Present to individual

Boards of each

organisation for

approval of next steps

Hammersmith and Fulham

The journey The real benefit of focussing the project on the development session was

creating an opportunity for the leadership of the provider and commissioner

partners to discuss the principles of their planned, joint endeavour.

This served to reinforce the alignment of vision between provider partners and

crystallised the areas of consideration that are advanced (commitment to

whole population approach in the long term, primary care at scale, priority

pathways for proof of concept) versus those that will require considerably more

time (organisational form options, outcomes based contracting models,

Page 62: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

59

workforce development)

Undertaking the project jointly with commissioners helped provider teams to

gain assurance that the long term vision for whole population health

management by ACPs was shared, but raised questions about the robustness

of plans to transition to that model over time.

Challenges Securing sufficient transformational funding to resource change at

pace and scale

Articulating the role of Local Authorities and other health providers in

the system

Developing and executing consistent commissioning plans across

CCGs

Defining a meaningful role for commissioners once ACPs are

commissioned and agreeing transition plans that run in parallel with

extant contractual frameworks

Ensuring buy-in to change plans across all levels and disciplines of

provider organisations

Next steps Scope and execute proof of concept based on improving care for

“familiar faces” frequently attending A&E, followed by a gateway

review

Potential acceleration of the Payments, Pricing & Incentives work

stream

Develop and implement communications & engagement plan

Continue to develop patient and public involvement plans

Hillingdon

The journey Hillingdon have already got a foundation of strong relationships between the

CCG and the four providers who are seeking to work together in an ACP. The

four sessions were very well attended by the providers and CCG.

The greatest value of the engagement came in the final session when a much

wider group of representatives from the CCG attended and where the

opportunity for both provider and commissioner partners to discuss the cohort

and challenges of the next steps was discussed.

The lack awareness of the ACP development in some areas of the CCG was

Page 63: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

60

highlighted and the need for both commissioning integration was raised.

Challenges Financial scope of the contract continues to be an issue, with the

challenges of moving to the full capitation for the over 65’s

Lack of detailed information/data for understanding & separating

the current cohorts and modelling of the future

Gap in contract values and the Trust’s actual spend on the cohort

Defining the cohort and how to manage the overlaps in client groups

e.g. in long term condition and the over 65’s.

Need for awareness of the ACP goal and a consistent commissioning

plan across all parts of the CCG

Capacity of both CCG and the providers to resource change at pace

and scale

Risk share and especially the role of primary care GPs, their current

contracts and how they can become equal partners with less

individual risk

Defining the role for commissioners once ACPs are commissioned

and agreeing transition plans that run in parallel with extant

contractual frameworks

Ensuring buy-in to change plans across all levels and disciplines of

provider organisations

Keeping social care engaged whilst not full signed up partners

Defining measurable outcomes that give confidence in service

delivery and VFM.

Next steps CCG to work with providers to clarify the expectations in detail of

commissioning intentions for April 17

Provider awareness and sign up to the detail of the goal for April

2017 and what we would actually implement in October

Agree Heads of Terms to document shared commitments of the

providers

Use the draft FTI Consulting project plan into a PMO structure with

individuals taking accountability for each part

Page 64: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

61

Appendices

Appendix 1 – High-level roadmap for establishing finance and governance arrangements for an

ACP

Appendix 2 – Detailed workplan for establishing finance and governance arrangements for an

ACP

Page 65: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

62

Appendix 1

A high level roadmap for establishing the financing and governance arrangements of a new contract is shown below. This

timeline is over a 1 year period, however, this could be shortened significantly, depending on the resources available and

the size of the contract being agreed.

Months 1-3 Months 4-6 Months 10-12

Agree contract

coverage

Develop outcomes and detailed

metrics

Modelling of prospective contract value

Detailed contract design (payment mechanism & risk-share)

Final

nego-

tiations

3 clinical and

financial

workshops

typically required

Clinical reference group to

agree on outcomes –

commissioners and

providers

Finance teams

of relevant

providers

Fin

an

cia

l a

nd

co

ntr

ac

tin

g

arr

an

ge

me

nts

Go

ve

rna

nc

e

arr

an

ge

me

nts

Months 7-9

Establish parties to

contract and outline

governance

Legal set-up

Finalise contracts (reflecting agreements above)

Consider legal implications

Other legal responsibilities

Page 66: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

63

Appendix 2

A detailed workplan for establishing the financing and governance arrangements of a new contract is shown below. We

note that there are other workstreams that are necessary to formulating an ACP e.g. clinical model of care development,

organisational design, communications etc. These are not described here.

Workstream Work area Tasks Owner

Finance &

contractual

arrangements

Determine

contract

coverage

Review the different options for contract coverage

Review current services being provided to over-65s

across all care settings

Establish by relevant currency e.g. HRG for acute

providers, which elements of the service are in scope

Identify which patients are in scope and assess ability of

GPs and other organisations to flag and monitor patients

Compare contract options against contract objectives

e.g. frail vs elderly

Propose contract coverage

Clinical provider

group

Propose

contract

duration

Articulate pros and cons of different contract duration options.

Propose contract duration

Commissioner(s)

Page 67: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

64

Workstream Work area Tasks Owner

Finance &

contractual

arrangements

Estimate

contract value

Gather latest cost and expenditure data for each relevant

provider for at least the last 3 years of spend.

Apportion cost to relevant population cohort i.e. over-65s,

including relevant support services (where applicable).

Agree assumptions between providers and commissioners

regarding:

Likely demand

Demographic change

Cost inflation

Efficiency

Likely activity reductions

Reflect known allocation changes

Overlay any known changes e.g. ongoing QIPP/CIP schemes

Calculate forecast cost

Model scenarios as to flow of funds under different attainment of

activity reductions

Agree final contract value with ACP providers (see later slide for

further factors to be incorporated before final value is agreed).

Allocation growth

Clinical provider -

group (amended

membership)

Finance group

Page 68: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

65

Workstream Work area Tasks Owner

Finance &

contractual

arrangements

Discuss

additional

contract

negotiation

points

How will historical deficits be dealt with?

How will the ACP resolve any structural deficit issues that

currently exist in the system?

How much contingency should the system hold?

Which organisations should hold it?

Will the contingency be built over time or is there initial funding

available?

Are there incremental running costs for the ACP?

How will residual running costs of existing organisations be

affected?

Will the ACP need ‘one-off’ funding in the first year to cover

transition costs? Where would this funding come from?

How will existing savings plans be affected?

Can these saving plans be augmented?

Are any savings double-counted given activity reduction plans for

ACP?

Commissioner(s)/

Providers

Finance &

contractual

arrangements

Develop

contract

outcomes

Establish outcome indicators through a working group for

relevant contract cohort

Test outcomes measures with patient groups

Establish which metrics can be measured now, and which will

require improved data capture.

Establish targets and time profile based on current local

achievement.

Clinical provider

group

Page 69: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

66

Workstream Work area Tasks Owner

Finance &

contractual

arrangements

Agree payment

mechanism

Agree detailed payment mechanism as to how the capitated

payment will be structured. This includes:

How much will contingent on achievement of outcomes?

Should the reference contract value be paid for baseline

performance, or should some progress be required?

How large should the performance-linked element be?

Should performance greater than 100% of target be

financially rewarded?

Should performance worse than baseline be financially

penalised?

Should payments be calculated for individual outcomes,

or should an overall payment be made based on an

index?

Should payments be calculated on a continuous scale or

as discrete steps?

Commissioner(s)

Finance &

contractual

arrangements

Develop risk-

sharing

arrangements

Agree where possible allocation of risks between CCG and

provider i.e. seek to define some “non- controllable” risks ex ante

that should be borne by CCG e.g. capitation numbers,

epidemiological reasons

Agree risk share between CCG and provider for “residual risks”

Identification of non-controllable risks only likely to be

approximate and therefore will need to consider ways in which

cost under and overrun shared

Model different outturn scenarios and options for risk-sharing

arrangements e.g. upside only risk for some providers

Consider respective ability of providers to take on and manage

risk

Agree rules for identifying and allocating costs

Establish performance indicators for each party that, if there are

cost overruns, indicate whether the provider should take higher

share of cost

Agree final sharing arrangements for un- allocated costs and

benefits.

Joint finance group

Page 70: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

67

Workstream Work area Tasks Owner

Functions &

form

Establish

parties to

contract and

outline

governance

Constitute/Re-purpose necessary sub-groups

Agree the objectives and principles of the ACP

Agree what services (and types of contract) are initially envisaged

to be commissioned from the ACP

Agree the role of the CCG as a party to the ACP

Establish governance arrangements between the provider

organisations that will be party to the ACP (e.g. decision making

and dispute resolution)

Agree which party will be responsible for various matters (for

instance, will one of the parties hold funds received from the CCG

on trust for the others and act as “banker”?)

Agree how clinical governance is managed between the parties to

the Alliance

ACP shadow board

Functions &

form

Legal set-up Review options for organisational form and begin set-up

Review the proposed contracts that are envisaged to be

commissioned from the partnership organisation

Draft the partnership agreement for review and consideration by

CCG and providers

Agree what conditions need to be met prior to the partnership

agreement coming in to legal effect

Incorporate feedback into a revised partnership agreement for

signature

ACP shadow board

Functions &

form

Consider legal

implications to

existing

arrangements

Alliance to consider what other services can be added to the

partnership agreement in due course

ACP to consider what other organisations it wishes to be part of

the ACP and/or contract with more generally to deliver services

Implications of/interactions with other contracts

Implications of/interactions with other possible changes to

contracting? e.g. urgent care

ACP shadow board

Page 71: North West London · Case Study 6: ACOs within Medicare .....41 7. AGREEING CONTRACT GOVERNANCE.....43 OVERVIEW ... NWL commissioned FTI Consulting LLP (FTI Consulting) and …

68

Workstream Work area Tasks Owner

Functions &

form

Other legal

responsibilities

CCG to consider its procurement obligations, in light of 2015

regulations

Providers to consider their competition law obligations

Co-design of outcomes for inclusion in the services contract

Providers to set up company and consider what it can be used for

pending the removal of certain legal barriers (e.g. contracted out

VAT recovery)

Commissioner(s)

Providers