Internship Report on Northern Coalfields Limited
(A Miniratna Company)
Submitted By-Name: Aishwarya Mahajan
Saurabh Jadhav Course: PGP PEM, 4th Trimester
Batch: 2015-2017
Company Introduction
Type
Public
Industry Coal
Founded November 1985
Headquarters Singrauli, Madhya Pradesh,India
Key people Ms.Shantilata Sahu, Chairman-cum-Managing Director (Additional Charge)
Products Coal
Net income INR 21.5 billion (2006) or USD 524 million
Number of employees 16329 (2013)
Vision:To Emerge as a Global player in the primary energy sector committed to provided energy security to the country by attending environmentally and socially sustainable growth through best practices from mines to market.
Mission :The Mission of Northern Coalfields Limited is to produce and market
the planned quantity of coal and coal products efficiently and economically with due regard to safety conservation and quality
• ESTIMATION
• TENDERING
• CONTRACT
Khadia ProjectOngoing Projects in Khadia
• Coal Handling Plant Phase-II• B-Type Residential Quarters• Road Diversion• Khadia workshop & store• Rail line diversion
COAL HANDLING PLANT (Phase II)• Project Summary: CHP properly handles the coal from its receipt to transferring it to bunkers. It supplies the quanta of processed coal to bunkers of coal mills for Boiler operation & stack the coal to coal yard. Capacity of NCL’s CHP Phase II is 6 MT.• Client: NCL• Contractor: L&T (Metallurgical & Material Handling)• Type of Contract: Engineering Procurement Construction• Estimated Project Cost: 283crores• Site Engineer: Receiving Pit- Mr. Khemchand, Mr. Amit Singh• Project Start date: October 2014• Date of Completion as per agreement: October 2016
B-TYPE RESIDENTIAL QUARTERS PROJECT
• Project Summary:The project consists of construction of 66 residential quarters for the staff
members of NCL. The quarter consists of 2 bedrooms, 1 hall, 1 kitchen and 1 toilet.• Client: NCL• Contractor: V.P Jain • Type of Contract: Item Rate Contract• Estimated project cost: 10 crores• Site Incharge: Mr. K.K. Shrivastav and Mr. Pande• Project Start Date: 23rd November 2015• Date of Completion as per Agreement: 13th February 2017
JOB SAFETY ANALYSIS (JSA)Activity/ Observations Hazard Impact Preventive Action Requirements Concerned Person
1) Water transportation and
Stagnation
Slippery condition on
site
Accident due to
slipping
Pipe should be laid avoiding
the main road of movement
Pipes in good conditions Supervisor/ Safety
officer
2) Reinforcement not proper May cause injury to
workers
It may prove fatal to
workers on work
Reinforcement should be
covered or cut down
Cutters etc. Supervisor
3) Risky bridge between two
buildings for movement of
workers
Can result in freefall
of the worker
Resulting into serious
injuries and damages
Proper path should be provided
for movement
Platforms etc. Supervisor
4) Improper material
housekeeping
Can cause injury to
the workers
May prove fatal Proper storing required Storage Supervisor
5) Improper material handling Damage to the
material
May cause accidents
to passing by people
and may prove fatal
Installation of proper system Supervisor
Picture 1 Picture 2
Picture 3
Picture 4
Picture 5
ROAD DIVERSION• Client: NCL• Contractor: Ashoka Construction Company• Consultant: PWD• Type of Contract: Item rate• Estimated project cost: 11crores• Site Engineer: Mr. Giriesh Pateria• Project Start date: 22nd November 2015• Length of Road: 1700ms• Duration of project: 11 months
KHADIA WORKSHOP & STORE• Client: NCL• Contractor: S.K. Samanta & Company Private Limited• Type of Contract: Turnkey Contract• Estimated project cost: 45crores• Site Incharge: Colonel Vidhyasagar• Project Duration: 1year• Area: 350m*150m
RECOMMENDATIONS• Proper roads to be constructed on site to increase efficiency of
equipment.• Provide proper mask onsite.• Lack of spare parts.• Provide proper shelter for staff during storms.• Proper hygiene is to be maintained on site.
Site Photos