Rangiriri project update PART OF THE WAIKATO EXPRESSWAY November 2016 Rangiriri section Wayside Rd TO AUCKLAND TO TE KAUWHATA Te Kauwhata bridge Plantation Rd Te Kauwhata Rd Wayside Road Rodda Road New timetable for completion The project team would like to update road users and stakeholders on progress on the Rangiriri section. A wet winter and spring has delayed some activities but there is now more certainty about the timing of the next stages as we work towards project completion. The new timetable for completing works at the Te Kauwhata and Rangiriri interchanges is outlined below. Please note that over the Christmas holiday period, the Expressway at Rangiriri will remain open to one lane of traffic in each direction with a speed limit of 70km/h. The project team is targeting mid-March to have the Expressway open with four lanes of traffic at 100km/h. 22 November 28 November Murphy St Te Wharepu bridge Churchill East Rd Glen Murray Rd Rangiriri Rd RANGIRIRI HOTEL Te Wharepu Rd Old SH1 (closed) TO AUCKLAND TO HAMILTON Te Wharepu Road Te Wharepu Road Completion of Rangiriri south-bound on-ramp On 28 November the section of on-ramp between Murphy Street and Rangiriri Road will be open. Access to the on-ramp is via Te Wharepu or Glen Murray Roads, or from Murphy Street and Rangiriri Road within Rangiriri township. Wharepu Road one-way From 9 January Te Wharepu Road will be one-way heading north for approximately seven weeks. Only north-bound traffic from Rangiriri will be able to use this link road. South-bound traffic from Te Kauwhata, wanting to get to Rangiriri, will need to use the Expressway and exit at Rangiriri. The reason for this one-way is so the contractor can work on the new alignment of the intersection at Te Kauwhata and carry out work to turn this road into a local road which will be managed by Waikato District Council in the future. 28 November 09 January Connections open One way Connections open One way New connections at Te Kauwhata On 22 November the south-bound on-ramp at Te Kauwhata will open to traffic. 08 December The south-bound off-ramp at Te Kauwhata will open to traffic on 8 December. Then on 28 November the Te Kauwhata north-bound on-ramp will close for approximately two months to allow completion of surfacing work on the main alignment at the northern end of the project. 28 November From 28 November northbound traffic from Te Kauwhata will detour via Rodda Road (which will remain two-way) to access the expressway while the on-ramp is closed. NZ Transport Agency November 2016

Upload: others

Post on 09-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: November 2016 New timetable for completion · 2016. 11. 18. · Paul Nimmo Fletcher Construction, Traffic and stakeholder manager Mobile: 027 206 4212 Email: PaulN@fcc.co.nz It’s

Rangiriri project updatePART OF THE WAIKATO EXPRESSWAY

November 2016

Rangiriri section

Old SH1 (closed)

Wayside Rd

Mur

phy

St

Te Onetea Rd

RANGIRIRI

Realigned Te Onetea Rd

TE ONETEA

STREAM

TO AUCKLAND

TO HAMILTON

TO TE KAUWHATALAKE KOPUERA

Churchill East Rd

Glen Murray Rd

Rangiriri RdRANGIRIRI

HOTEL

Te Kauwhata bridge

Plantation Rd

Te Kauwhata Rd

Wayside Road

Te Wharepu Road

Te Wharepu bridge

Rangiriri intersection permanently

closed

Rodda Road

New timetable for completionThe project team would like to update road users and stakeholders on progress on the Rangiriri section. A wet winter and spring has delayed some activities but there is now more certainty about the timing of the next stages as we work towards project completion.The new timetable for completing works at the Te Kauwhata and Rangiriri interchanges is outlined below. Please note that over the Christmas holiday period, the Expressway at Rangiriri will remain open to one lane of traffic in each direction with a speed limit of 70km/h. The project team is targeting mid-March to have the Expressway open with four lanes of traffic at 100km/h.

22November 28

November

Te Kauwhata bridge

Te K

auw

hata

Rd

Plantation Rd

Wayside Rd

Mur

phy

St

Te Onetea Rd

RANGIRIRI

Realigned Te Onetea Rd

TE ONETEA

STREAM

TO AUCKLAND

TO HAMILTON

TO TE KAUWHATA

TE KAUWHATA INTERCHANGE

LAKE KOPUERA

ALL south-bound tra�c to Te Kauwhata,

Rangiriri and Glen Murray

Exit at Wayside Road

Te Kauwhata Rangiriri Link Rd

Te Wharepu bridge

Churchill East RdGlen M

urray Rd

Rangiriri RdRANGIRIRI

HOTEL

Te Wharepu RdOld SH1 (closed)

Way

side R

d

Mur

phy

St

RANGIRIRI Realigned Te Onetea Rd

TE ONETEA

STREAM

TO AUCKLAND TO HAMILTON

TO TE KAUWHATA

LAKE KOPUERA

Rangiriri

bridge

Churchill East R

d

Glen Murray Rd

Rangiriri Rd

RANGIRIRI

HOTEL

Te Kauwhata

bridge

Plantation Rd

Te Kauwhata Rd

Te Wharepu RoadTe Wharepu Road

Completion of Rangiriri south-bound on-rampOn 28 November the section of on-ramp between Murphy Street and Rangiriri Road will be open. Access to the on-ramp is via Te Wharepu or Glen Murray Roads, or from Murphy Street and Rangiriri Road within Rangiriri township.

Wharepu Road one-way From 9 January Te Wharepu Road will be one-way heading north for approximately seven weeks. Only north-bound traffic from Rangiriri will be able to use this link road. South-bound traffic from Te Kauwhata, wanting to get to Rangiriri, will need to use the Expressway and exit at Rangiriri.

The reason for this one-way is so the contractor can work on the new alignment of the intersection at Te Kauwhata and carry out work to turn this road into a local road which will be managed by Waikato District Council in the future.

28November 09

January

Connections openOne way

Connections openOne way

New connections at Te KauwhataOn 22 November the south-bound on-ramp at Te Kauwhata will open to traffic.

08December

The south-bound off-ramp at Te Kauwhata will open to traffic on 8 December.

Then on 28 November the Te Kauwhata north-bound on-ramp will close for approximately two months to allow completion of surfacing work on the main alignment at the northern end of the project.

28November

From 28 November northbound traffic from Te Kauwhata will detour via Rodda Road (which will remain two-way) to access the expressway while the on-ramp is closed.

NZ Transport Agency November 2016

Page 2: November 2016 New timetable for completion · 2016. 11. 18. · Paul Nimmo Fletcher Construction, Traffic and stakeholder manager Mobile: 027 206 4212 Email: PaulN@fcc.co.nz It’s

4 | Waikato Expressway Rangiriri section | Project update | November 2016

Longswamp section under way Work has started on the Longswamp section after Transport Minister Simon Bridges turned the first sod at a ceremony on 14 October. The Longswamp section will see the expressway between Rangiriri and Hampton Downs upgraded to two lanes in each direction, with improved local road connections.

In order to minimise disruption to travellers on SH1 while work is completed at the Rangiriri section, Longswamp contractor Downer NZ will conduct most of the initial work at the northern end of the section near Hampton Downs.

Turning the first sod on the Longswamp section are Waikato District Mayor Allan Sanson, Waikato-Tainui representative Tom Roa, Transport Minister Simon Bridges and Waikato MP Lindsay Tisch.

Expressway overview mapThe Waikato Expressway is one of the Government’s seven Roads of National Significance. The Expressway will improve safety and reliability and reduce travel times and congestion on State Highway 1 by delivering a four-lane highway from the Bombay Hills to south of Cambridge. It is being built in seven sections.

2

2

27

26

23

393

1

25

1B

Huntly

Raglan

Rangiriri

Te Kauwhata

Ohaupo

Meremere

Tuakau

Pukekohe

Hamilton

Cambridge

Taupiri

NgaruawahiaMorrinsville

Completed sectionsIn progressTerritorial authority boundaryExisting state highwayOther roadsHamilton urban area

OHINEWAI7.0km

TE RAPA7.3km

OpenedDecember 2012

Opened December 201516km

CAMBRIDGE

NGARUAWAHIA12.3km

OpenedDecember 2013

TAMAHERE INTERCHANGE2.4km

MERCER11.0km

POKENO11.6km

Under constructionHAMILTON

21.8km

Construction 2016-20

Under construction

HUNTLY15.2km

Construction 2016-20

Under construction

LONGSWAMP5.9km

Construction 2016-18

Under constructionRANGIRIRI

4.8kmConstruction

2013-2017

Any questions?Adrian BathgateNZ Transport Agency, Communications and stakeholder liaisonPhone: 07 958 7260 Email: [email protected]

Paul NimmoFletcher Construction, Traffic and stakeholder managerMobile: 027 206 4212 Email: [email protected]

It’s important to the project team we keep you informed as the project progresses.

These works are key steps towards final project completion connecting local roads to the new expressway. We appreciate your patience as drivers become accustomed to the new layouts.

Follow us on Facebook facebook.com/Waikatoexpressway

Visit our website www.nzta.govt.nz/rangiriri

Email us with [email protected]

Keeping you informed We will be providing updates to the local community about specific works through letter drops and information flyers.

To sign up for our email newsletters go to www.nzta.govt.nz/rangiriri