november 9, 2009 - mpug - microsoft project training and ... · forecasting: - estimate to complete...

25
1 An overview of the core NOVEMBER 9, 2009 An overview of the core elements of the Earned Value Management technique Presenter: G M Ji Ad PMP Jim Anderson, PMP Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Upload: others

Post on 25-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

1

An overview of the core

NOVEMBER 9, 2009An overview of the core elements of the Earned Value Management technique

Presenter:

G M

Ji A d PMPJim Anderson, PMP

Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 2: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

2

Goal of the Presentation

A t ti d l th tA presentation on earned value that allows PM’s to come away with one or two new insights into how to think about and apply earned value.

3Atlanta PMI Presentation, Earned Value Management, 11/09/2009

What It Is Not

A ft t ti A software presentation Highly technical New A suggestion:gg Don’t worry about taking notes I will send you a copy of the slides

4Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 3: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

3

Earned Value Management

P id th t th tiProvides the answer to the question:“How are we doing on the project?”

The typical answers to this question offer comparisons of actualoffer comparisons of actual performance (cost and schedule) to planned performance.

5Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Earned Value Management

Wh t’ Mi i ?What’s Missing?

An assessment of how much of the project’s objectives (value) have been met versus how much was planned pto be complete by the status date

6Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 4: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

4

Earned Value Management

P id tit ti i fProvides a quantitative view of:

Cost and schedule variances,

Efficiency indexes (ratios) that are used to predict future cost and schedule performance,

Value created to the status date.

7Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Earned Value Management

C l i t b t th fCommon complaints about the use of earned value: It’s too complicated. It’s hard to implement (cost/time). Small projects don’t benefit from it.

8Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 5: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

5

Earned Value Management

T f t i d fi d i Types of cost variances defined in 1950’s

EV concepts emerged from the PERT movement of the 1960’s

Adopted as DoD policy in 1967

9Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Earned Value Management

Provides an early warning on cost and Provides an early warning on cost and schedule performance. Reliable long-term cost and schedule

performance indicators emerge as early as 15-20% into a new project’s lifecycle.

Allows for true management by Allows for true management by exception. Negative variances attract attention Large positive variances also attract attention

10Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 6: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

6

Core Elements of Earned Value ReportingCore:- Planned Value (BCWS) - Earned Value (BCWP)- Actual Cost (ACWP) - Budget at Completion (BAC)

Cost: Schedule:- Cost Variance (CV) - Schedule Variance (SV)- Cost Variance % (CV%) - Schedule Variance % (SV%)- Cost Performance Index(CPI) - Schedule Performance Index (SPI)- To Complete CPI (TCPI)p ( )

Forecasting:- Estimate to Complete (ETC) - Estimate At Completion (EAC)- Variance at Completion (VAC)

11Atlanta PMI Presentation, Earned Value Management, 11/09/2009

EVM View in MS Project

12Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 7: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

7

EVM Tables in MS Project

13Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Earned Value View [Earned Value Table]

14Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 8: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

8

Earned Value View [Cost Indicators Table]

15Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Earned Value View [Schedule Indicators Table]

16Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 9: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

9

Core Elements of Earned Value Reporting

Planned Value (BCWS) The estimated cost of work scheduled to the status date.

Earned Value (BCWP) The true value of work performed to the status date.

Actual Cost (ACWP) Actual cost of work performed to the status dateto the status date.

Budget at Completion The total budget allocated to a project

17Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Earned Value Reporting isreferenced to a status date

1. Status Date2. Actual Cost3. Earned Value

Planned Value

18Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 10: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

10

Planned Value(BCWS: Budgeted Cost of Work Scheduled)

BCWS is the cumulative cost of work scheduled to the status date.

A graph of cumulative planned values produces the well known S-curve.

Example: The budget for a 4-day task is $100.

If the status date is day three, BCWS is $75.

19Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Cumulative Planned Value Cost Curve

Res

ourc

es

20

Time

Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 11: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

11

Earned Value(BCWP: Budgeted Cost of Work Performed)

BCWP = the value of the work performed to the status date.

BCWP = Project value earned to the status date.

BCWP = Actual Cost (ACWP) +

Cost Variance (CV)

21Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Earned ValueThe True Value of Work Performed

Microsoft Project calculates earned value using:j g

%Complete or,

Physical-% Complete.

%-Complete - calculated automatically, or entered manually.

Physical % Complete is entered manually when the task'sPhysical-% Complete - is entered manually when the task s %-Complete value is not deemed to be an accurate measure of the true value of the work performed or of the work remaining.

22Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 12: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

12

Earned Value CalculationTools > Options > Calculations Page

23Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Microsoft Project Default is %-Complete for Earned Value

24Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 13: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

13

%-Complete

A %Complete value is required in MSP A %Complete value is required in MSP. %complete is the percent of work

completed relative to the amount of work scheduled to the state date.

An easy %Complete scheme: Have not begun work = 0% Working on the task = 50% Finished the task = 100%

25Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Actual Cost Data for EV

Oft ti t l t tOftentimes actual costs are not obtainable in a timely manner or not at all; when that is the case: Use estimated resource rates, or Use loaded labor rates, or Cost all resources at a $1 rate.

26Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 14: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

14

Earned Value = True ValueHow %-Complete and Physical-%Complete differ:

Example Project: Building Stone WallExample Project: Building Stone Wall

Project Goal: Build a stone wall consisting of 100 stones stacked 5 rows high.

The first row of 20 stones can be laid in 20 minutes.

The second row will take 25 minutes because you now have to lift the stones up one row higher, so it takes a little longer.

The third row will take 30 minutes.

The fourth row 35 minutes,

The last row will take 40 minutes to lay, for a total duration for the project of 150 minutes .

27Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Earned Value = True ValueUsing %-Complete vs. Physical-%Complete:

After laying the first three rows the project could beAfter laying the first three rows the project could be said to be 60% physically complete.

First row (20 min.) - 20 minutes total duration.

Second row (25 min.) - 45 minutes total duration.

Third row(30 min.) - 75 minutes total duration.

However, only 75 of the 150 minutes have been spent, so in terms of project duration, the job is 50% complete.

28Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 15: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

15

Earned Value = True ValueUsing %-Complete vs. Physical-%Complete:

fWhich method would you choose for calculating earned value: %complete or physical-% complete?

The answer is it depends.

Whether you are getting paid by the stone or by the minute.or by the minute.

Choose the measure that reflects the true value earned for the work completed.

29Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Actual Cost(ACWP: Actual Cost of Work Performed)

ACWP = Actual Cost of Work Performed to the status date.

Example:

A four day task has a planned value (BCWS) of $100.

The actual costs the first two days were $35/day The actual costs the first two days were $35/day,

If the status date is day three, the actual cost for the reporting period is $95, but the BCWS is still $75.

30Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 16: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

16

Relationships Between the Core EV Elements

Earned Value (BCWP) VS Planned Value (BCWS)Earned Value (BCWP) VS. Planned Value (BCWS)

BCWP VS. BCWS [Work Performed][Work Scheduled]

Earned Value (BCWP) VS. Actual Value (ACWP)a ed a ue ( C ) S ctua a ue ( C )

BCWP VS. ACWP [Budgeted Cost][Actual Cost]

31Atlanta PMI Presentation, Earned Value Management, 11/09/2009

BAC = Budget at Completion

BAC is the sum of the planned value of each task (total cost) in the project schedule.

BAC is the estimate of the final project cost.

BAC is the project’s baseline budget

32Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 17: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

17

Cost Performance Indicators

- Cost Variance (CV)

- Cost Variance % (CV%)

- Cost Performance Index (CPI)

T C l C P f I d (TCPI)- To Complete Cost Performance Index (TCPI)

33Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Cost Variance (CV)CV = (BCWP - ACWP)CV = (BCWP - ACWP)

CV is the amount that has been overspent or under spent for the work performed to the status date.

Answers the question, “By how much is the project is over or under budget?”project is over or under budget?”

0 (on-budget), Negative (over budget), Positive (under budget).

34Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 18: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

18

Cost Variance Per Cent (CV%)CV% = CV / BCWPCV% = CV / BCWP

Relative to planned value, CV% shows what % of planned value was spent to achieve the value earned to the status date.

Answers the question, “By what percent is the project over or under budget?”

The variance can be: CV-% > 0 (over budget), CV-% < 0 (under budget).

35Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Cost Performance Index (CPI)CPI = BCWP / ACWPCPI = BCWP / ACWP

Ratio of earned value to actual cost for the work performed to the status date.

This is a cost efficiency index that shows how efficiently resources are being utilized on the project. y g p j

CPI >= 1 (resources are being utilized well).

CPI < 1 (resources are not being utilized well).

36Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 19: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

19

Cost Performance Index (CPI)

Assumption:Assumption:

Resources on a project will perform at 100% efficiency to achieve the planned schedule, on time and on budget.

For every dollar spent relative to plannedFor every dollar spent relative to planned costs, CPI allows the project manager to monitor how efficiently the project’s budget is being consumed.

37Atlanta PMI Presentation, Earned Value Management, 11/09/2009

To Complete (TCPI)TCPI = (BAC - BCWP) / (BAC - ACWP)TCPI (BAC BCWP) / (BAC ACWP)

The ratio of [remaining work] / [remaining funds] as of the status date.

TCPI is an efficiency index that forecasts how efficiently project resources should be utilized for the remainder of the project to stay on budget or to get back on budgetback on budget.

TCPI > 1 (Resource utilization should be managed closely) TCPI < 1 (Resource utilization can be managed less

stringently)

38Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 20: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

20

Schedule Performance Indicators

- Schedule Variance (SV)

- Schedule Variance % (SV%)

- Schedule Performance Index (SPI)

39Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Schedule Variance (SV)

SV (BCWP BCWS)SV = (BCWP - BCWS)

Measures whether the project is ahead or behind schedule:

0 (on-schedule) 0 (on-schedule),

Negative (behind schedule),

Positive (ahead of schedule).

40Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 21: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

21

Schedule Variance % (SV%)

SV% = SV / BCWSSV% = SV / BCWS

Shows % of scheduled work that has slipped relative to the planned duration, or the % of work that is complete over and above the work scheduled to the status date.

Answers the question, “By what percent is the project behind or ahead of schedule?”

The variance can be: SV-% < 0 (% of work behind schedule), SV-% > 0 (% of work ahead of schedule).

41Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Schedule Performance Index (SPI)

SPI BCWP / BCWSSPI = BCWP / BCWS

This is a schedule efficiency index that shows how efficiently the project team is utilizing the time that is allotted to the project.

SPI >= 1 (good) SPI >= 1 (good).

SPI < 1 (not good).

42Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 22: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

22

Forecasting IndicatorsEstimate To Complete (ETC)Estimate To Complete (ETC) Answers the question, “From the status date forward,

how much will it cost to complete the remaining work?”

Estimate At Completion (EAC) Forecasts the likely final cost of the project at

completion; it includes actual cost to date plus the estimated cost of work remainingestimated cost of work remaining.

Variance At Completion (VAC) A forecast of the difference between the budget at

completion (BAC) and the estimate at completion (EAC)

43Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Estimate To Complete (ETC)

(BAC BCWP) E ti t d t f th k(BAC – BCWP) = Estimated cost of the work remaining from the status date

ETC is used when prior estimating assumptions have become invalid and you need a revised estimate of the cost to complete the remainingestimate of the cost to complete the remaining work.

44Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 23: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

23

Estimate At Completion (EAC)

EAC = ACWP + (BAC - BCWP) / CPI

EAC is an estimate of the likely cost of the project at completion. It accounts for the work already completed plus the cost of the remaining work from the status date

EAC lib t th j t d fi l t b d t EAC calibrates the projected final cost based on past cost performance to the status date.

45Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Variance At Completion (VAC)

VAC = (BAC – EAC)

VAC = the difference between the original project budget and the revised estimated final budget.

In MS Project, EAC is the Total Cost field and BACjis the Baseline Cost field.

46Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 24: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

24

Earned Value Performance Measures

47

PMI Practice Standard for Earned Value Management

Atlanta PMI Presentation, Earned Value Management, 11/09/2009

References: PMI Practice Standard for Earned Value PMI Practice Standard for Earned Value

Management Earned Value Management Using

Microsoft Office Project (Sham Dayal, PMP) Essentials of Project Controls

(Editors: Jeffrey K. Pinto and Jeffrey W. Trailer)( d o s e ey o a d e ey a e )

Applying earned value analysis to your project(http://office.microsoft.com/en-us/project/HA010211791033.aspx)

48Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Page 25: NOVEMBER 9, 2009 - MPUG - Microsoft Project Training and ... · Forecasting: - Estimate to Complete (ETC) - Estimate At Completion (EAC) - Variance at Completion (VAC) Atlanta PMI

25

Chart The Course

Thank You!

Jim Anderson, PMP, MSPM, [email protected]

49Atlanta PMI Presentation, Earned Value Management, 11/09/2009

Questions?

50Atlanta PMI Presentation, Earned Value Management, 11/09/2009