npdes pii small ms4 general permit annual report...the town has a seeclickfix ; general permits for...

24
p Municipality/Organization: Stoneham, Massachusetts EPA NPDES Permit Number: MA041062 MassDEP Transmittal Number: W-040960 Annual Report Number & Reporting Period: April 1, 2016-Marcb 31, 2017 NPDES PII Small MS4 General Permit Annual Report (Due: May 1, 2017) Part I. General Information Contact Person: Robert E. Grover, P .E. Title: Director, Dept. of Public Works Telephone#: 781-438-0760 Email: [email protected] Mailing Address: 16 Pine Street, Stoneham, MA 02180 Certification: I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief , true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possib. · y fine and imprisonment for knowing violations. / Signature: Director, Department of Public Works Date: 4-12 -/ ~ 1

Upload: others

Post on 26-Jun-2020

9 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

pMunicipality/Organization: Stoneham, Massachusetts

EPA NPDES Permit Number: MA041062

MassDEP Transmittal Number: W-040960

Annual Report Number & Reporting Period: April 1, 2016-Marcb 31, 2017

NPDES PII Small MS4 General Permit Annual Report (Due: May 1, 2017)

Part I. General Information

Contact Person: Robert E. Grover, P .E. Title: Director, Dept. ofPublic Works

Telephone#: 781-438-0760 Email: [email protected]

Mailing Address: 16 Pine Street, Stoneham, MA 02180

Certification:

I certify under penalty oflaw that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best ofmy knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possib. · y fine and imprisonment for knowing violations.

/ Signature:

Director, Department ofPublic Works

Date: 4-12-/~ • 1

Page 2: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

Part II. Self-Assessment

The Town of Stoneham has completed the required self-assessment and has determined that our municipality is in compliance with all permit conditions.

2

Page 3: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

Part III. Summary of Minimum Control Measures

1. Public Education and Outreach

BMPID# BMP Description Responsible Measurable Goal(s) Progress on Goal(s) ­ Planned Activities ­Dept/Person Permit Year 13 Permit Year 14 Name (Reliance on non-municipal

!Partners indicated, if anv) 1-1 Place Educational Dept. ofPublic Winter '03/04 - Winter 'I6/17 The Town has a new website. To be determined

Information on the Works • Post stormwater related information on the Links to EPA sites relating to (TBD) based on Town's Website Town's website stormwater will be added. issuances and review of

• Update website regularly proposed NPDES The Town has a SeeClickFix General Permits for button on its homepage for MS4 stormwater reporting problems. discharges in

Massachusetts.

1-2 Conduct Household Dept. ofPublic Fall '03 though '16 The Town is holding TBD Hazardous Waste Works • Continue to sponsor one household Household Hazardous Waste Collection Days hazardous waste collection day per year. Collection Days jointly with

• Annually send a press release advertising Melrose. the event to the Stoneham Independent and Stoneham Sun and track whether it was rrhis joint effort provides for at published. least two Household Hazardous

• Waste day per year. Advertise the event on the Town's website . Track the amounts and types ofwaste • collected each year. Track the number ofStoneham • vehicles/residents that participate in each

One occurred in October 2016 and the next one is planned for I.June 2017.

event

3

Page 4: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

1-3

BMPID# BMP Description Responsible Measurable Goal(s) Dept./Person Name

Progress on Goal(s)­Permit Year 13 (Reliance on non-municipal

Planned Activities ­Permit Year 14

Intensify the ExistinPet Waste Management Campaign

g Board ofHealth

Animal Control Officer

Spring '04 through ' 17

• Track the number of brochures distributed annually.

• Track the number of violations issued

loartners indicated, if any) lfhe brochure is available at the TBD library, Town Hall, DPW and ~hrough the Town Clerk.

Dept. ofPublic Works

annually.

• Develop an informational press release on pet waste management for the Stoneham

The Town's "Animals and Fowl" bylaw has a "duty to dispose" ofpet waste section

Independent and Stoneham Sun and track including fines for violations. whether it was published.

• Maintain and install information "Pet INew "Pet Waste" signs have Waste" signs been installed at parks and

other high volume areas. A k'Dogi-Pot" station has been installed at A.P Rounds Park.

1-4 Place Educational Information on Stoneham Community Access Television

Dept. of Public Works

Stoneham Community Access Television

Fall '04 through Spring '17

• Obtain "Oil Leak" and "Fertilizer'' PSAs from the Washington State Department of Ecology Water Quality Consortium.

• Track hoe frequently the PSAs are broadcast on Stoneham Community Access Television.

Stoneham TV broadcasted TBD stonnwater related PSAs during lPermit Year 13

1-5 Promote Water Conservation Practices for Homeowners

Dept. ofPublic Works

Spring '03 through ' 16

• Post water conservation posters at Town Hall and the public library.

• Include water conservation bill inserts with

Educational materials were available at the library, Town Hall, DPW and through the Town Clerk.

TBD

the water bill.

• Issue an annual press release to the Low-flow showerheads were Stoneham Independent and Stoneham Sun available to residents at no cost. to promote water conservation.

4

Page 5: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

BMP ID# BMP Description Responsible Measurable Goal(s) Progress on Goal{s)- Planned Activities ­Dept./Person Permit Year 13 Permit Year 14 Name (Reliance on non-municipal

partners indicated, if any)1-6 Develop a Press Dept. ofPublic Fall '05 & '07 No action planned for permit TBD Release and Flyer Works • Issue the press release to the Stoneham year 13. However, the site plan

Targeting Independent and Stoneham Sun and track review process includesCommunity whether it was published. requirements for onsiteBusinesses • Submit copies of the informational flyers to stormwater management.

the Stoneham Chamber ofCommerce(SCC). h'he site plan review process is

• Post the informational flyer on the Town's applicable to new developmentwebsite. and upgrades to existing

ldevelopment.

l a. Additions

BMPID# BMP Description Responsible Measurable Goal(s) Progress on Goal(s) ­ P lanned Activities ­Dept./Person Permit Year 13 Permit Year 14 Name (Reliance on non-municipal

1partners indicated, ifany)1-7 Develop a Dept. ofPublic Summer '05 through Spring '17 rrhe DPW made the EPA TBD

Stormwater Brochure Works • Develop and issue a brochure education the ~rochure "After the Storm -A!for General Public public on ways to prevent pollution in Citizen's Guide to

storrnwater runoff. Understanding Stormwater"available at the library, TownHall, DPW and through theTown Clerk.

5

Page 6: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

2-2

2. Public Involvement and Participation

BMPID# BMP Description Responsible Measurable Goal(s) !Progress on Goal(s)- Planned Activities ­Dept./Person Permit Year 13 Permit Year 14 Name (Reliance on non-municipal

partners indicated, if anv) 2-1 Public Access to !Dept. ofPublic

SWMP and Receipt Worlcs Fall '03 through Spring '17 A Copy ofthe Storm Water To be determined

• Make draft SWMP available to the public Management Program continues (TBD) based on ofComments for the review and comment period. to be available at the library, issuance and review of

Library • Finalize SWMP .

• Make the final SWMP accessible to the public at the library and Town's website.

Town Hall, DPW and through the Town Clerk.

proposed NPDES General Permits for MS4 stormwater discharges in !Massachusetts.

Public Access to !Dept. ofPublic Spring '04 through '17 IThe Annual Report for Permit ITBD Annual Report and Works Receipt ofComment

• •

Prepare an annual report . !Year 12 was completed and Annually send a press release advertising !submitted in 2016. the public comment period and the status of the Town's SWMP to the Stoneham IThe annual reports are available Independent and Stoneham Sun and track at the DPW office. whether it was published.

• Advertise the public comment period on the public cable access channel.

• Receive comments on the annual report .

• Submit an annual report to both the Environmental Protection Agency and MA Department ofEnvironmental Protection.

6

Page 7: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

2-3

2-4

BMPID# BMP Description Responsible Measurable Goal(s) Progress on Goal(s) ­ P lanned Activities ­Dept./Person Permit Year 13 Permit Year 14 Name (Reliance on non-municipal

loartners indicated, if any) Provide Assistance Dept. ofPublic Spring '03 through '17 An advertisement offering TBD to Local Cleanup Works • Post advertisement offering assistance with assistance with local cleanup Activities local cleanup activities on the Town's activities was placed in the

website and within the Stoneham Stoneham Independent and Independent and Stoneham Sun. Stoneham Sun and mentioned at

• Track the number ofcleanup activities that the Selectmen's meeting. the DPW assists annually.

During Permit Year 13 several• Track the number ofcleanup participants at these activities. community groups cleaned up

public grounds. • Track which areas ofTown are cleaned by these activities.

Additionally some local court • Track the quantity of waste collected as a ordered community service result ofthese cleanup activities. K>bligations are met through cleanup activities under the DPW.

The DPW provides personnel, trucks, bags, rakes, gloves and material disposal to groups performin~ cleanup activities.

Provide Assistance Dept. ofPublic Spring '04 through '17 Eagle Scouts stenciled storms TBD •o Storm Drain Works Post advertisement offering assistance with drains throughout the Town • Stenciling Activities storm drain stenciling activities on the during permit year 7. The

Town's website and within the Stoneham stenciling has begun to fade; no Independent and Stoneham Sun. stenciling activity occurred in Track the number ofdrains stenciled each ~ermit year 13. • year. Track the number of participants each year. In 2012, the Town applied for, •

but did not receive a grant for metal disks that can be epoxied to granite curbing headers.

Re-stenciling will continue to be included for public participation activities during 2017.

7

Page 8: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

2a. Additions

No additions to report at this time.

8

Page 9: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

3-2

3. Illicit Discharge Detection and Elimination

BMPID# BMP Description Responsible Measurable Goal(s) Progress on Goal(s) ­ Planned Activities ­Dept./Person Permit Year 13 Permit Year 14 Name (Reliance on non-municipal

partners indicated, ifany) 3-1 Field Verify Outfall Dept. ofPublic Spring ' 04 through ' 17 The DPW routinely visits the To be determined

Locations Works Develop a schedule for outfall verification • outfalls as part ofthe inspection (TBD) based on and outfall identification activities. and maintenance program. issuance and review of

• Perform and track the outfall verification proposed NPDES and outfall identification activities as Inspection and maintenance General Permits for scheduled. activities were recorded in a IMS4 stormwater

• Continuously update the storm drainage logbook. discharges in system map as new or correct information Massachusetts. is needed. The DPW updates the storm

drainage system as new or corrected information is added.

!Each outfall is labeled with a permanent plate.

Development and Planning Board Winter ' 04 through Spring ' 17 Rules and regulations regarding TBD Adoption ofa • Draft the Stormwater Bylaw, which will the use of storm drains in the Stormwater Bylaw Conservation address (1) illicit discharges, (2) erosion Town ofStoneham were adopted

Commission and sedimentation from construction by the Stoneham Stormwater activities, and (3) storm.water runoff from Board effective July 1, 2010.

Dept. of Public the new development and redevelopment Works projects. These rules and regulations are

• Present Stormwater Bylaw to Town available on the Town's website Building Meeting for adoption. and are being enforced. Department Post Stormwater Bylaw on Town's •

website. Compliance with the rules has

• Track the number ofenforcement actions been 100%.

taken. Some site plans complying with the regulations include rain 1gardens as their BMP

9

Page 10: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

BMPID# BMP Description Responsible Dept./Person

Measurable Goal(s) Progress on Goal(s) ­Permit Year 13

Planned Activities ­Permit Year 14

Name (Reliance on non-municipal

3-3 Implement an Illicit !Discharge Detection and Elimination Plan

Dept. ofPublic Works

Winter '04 through Spring '17

• Develop an IDDE Plan • Conduct dry-weather field screening of

!Partners indicated, if any) The DPW continually monitors its TBD open brooks for gray water and when found works to identify the

outfalls and track the number of surveys source. indicating a possible illicit connection.

• Trace the source ofpotential illicit The DPW has a contract with discharges. Arcadis and is working with the

• Track the number of illicit connections EPA regarding a Clean Water Act repaired/replaced. Administrative Order.

• Report on the success ofobtaining alternative funding to assist in illicit connection removal.

Stoneham coordinates with Todd Borci at the EPA's Office of Environmental Stewardship on compliance with the !Administrative Order.

3-4 Conduct Infiltration/Inflow Removal from Sanitary Sewer

Dept. ofPublic Works

Spring '03 through '17 • Perform I/I investigation ofthe sanitary

sewer system and track the results. • Perform capital improvement projects to

The DPW continues to propose and perform proj ects associated with I/I removal.

TBD

remove I/I. These capital improvement projects remove I/I through manhole sealing, pipe rehabilitation, pipe replacement and grouting.

3a. Additions

No additions to report at this time.

10

Page 11: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

4. Construction Site Stormwater Runoff Control

BMPID# BMP Description Responsible Measurable Goal(s) Progress on Goal(s) ­ Planned Dept./Person Permit Year 13 Activities ­Name (Reliance on non-municipal Permit Year 14

partners indicated, ifany) Development and See Section 3: Illicit Discharge To be determined Adoption ofa Detection and Elimination BMP (TBD) based on Stormwater Bylaw ID#3-2 issuance and

review of

4-1 proposed NPDES General Permits forMS4 stormwater discharges in [Massachusetts.

4-2 Develop a Site Dept. ofPublic Spring '05 through Spring '17 As part of the storm water rules ITBD Inspection Form and Works • Develop an ESC Site Inspection Form that and regulation, a stonnwater Conduct Site reflects the ESC requirements. Board was created to promulgate, Inspections • Track the frequency of inspections adopt, implement, enforce and

conducted for each site. amend stormwater regulations.

• Track the completion of inspection forms . rfhe Conservation Agent is a

• member ofthe Stormwater Board. Track the number of failed ESC BMPs Site ESC are consistent with the discovered on each site. ~equirements in Conservation Commission jurisdictional area. rrhe Town is presently revising its stormwater regulations.

11

Page 12: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

BMPID# BMP Description Responsible Measurable Goal(s) Progress on Goal(s) - Planned Dept./Person Permit Year 13 Activities ­Name (Reliance on non-municipal Permit Year 14

oartners indicated, ifany) 4-3 Develop and Dept. of Public Fall '05 through Spring '17 Residents current contact the TBD

Implement a Citizen Works • Establish the Citizen Tip Line . DPW during working hours and Tip Line • Advertise the Citizen Tip Line . the police during non-working

• Track the number ofcomplaints received via the Citizen Tip Line.

hours when stormwater related problems/incidents occur

Track the problems/incidents remedied as • a result ofthe Citizen Tip Line. Residents can also notify the

DPW through the Town's Website.

The Town has implemented a SeeClickFix button on its website for citizen tips.

The DPW maintains a computerized complaint log in which complaints are tracked by category.

4a. Additions

No additions to report at this time.

12

Page 13: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

5. Post-Construction Stormwater Management in New Development and Redevelopment

BMPID# BMP Description Responsible Measurable Goal(s) !Progress on Goal(s)- Planned Activities ­Dept./Person Permit Year 13 Permit Year 14 Name (Reliance on non-municipal

!partners indicated, if any) 5-l Development and See Section 3: Illicit Discharge To be determined

Adoption ofa Detection and Elimination BMP (TBD) based on Stormwater Bylaw ID#3-2 issuance and review

ofproposed NP DES General Permits for MS4 stormwater discharges in Massachusetts.

Sa. Additions

No additions to report at this time.

13

Page 14: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

6. Pollution Prevention and Good Housekeeping in Municipal Operations

BMPID# BMP Description Responsible Measurable Goal(s) Progress on Goal(s) ­ Planned Activities Dept./Person Permit Year 13 - Permit Year 14 Name (Reliance on non-municipal

oartners indicated, ifanv) 6-1 Develop a Formal Dept. ofPublic Fall '05 through Spring '17 DPW staffreceived hands-on To be determined

Training Program for Works • Develop the DPW employee training training for stormwater best (TBD) based on DPW Staff manual. management practices. issuance and review

• Conduct training sessions with all current ofproposed NPDES employees. Train all new DPW employees General Permits for in accordance with the training program MS4 stormwater requirements. discharges in

• Track the number of employees trained . Massachusetts.

• Conduct refresher training for employees after every two years ofemployment.

6-2 Catch Basin Cleaning Dept. ofPublic Spring ' 03 through '17 IThe DPW completes an annual TBD Program Works • Clean all catch basins on an annual basis . catch basin cleaning program.

• Document annual cleaning activities and keep all records through the pennit term. IThe DPW attempted to track

sources of illegal material in catch basins where identified.

6-3 Parking Lot and Dept. ofPublic Spring '03 through '17 The DPW completes an annual ITBD Street Sweeping Works • Track the streets and lots that are swept parking lot and street sweeping Program each year. program as scheduled.

Maintain a log ofthe disposed materials • Develop a Vehicle Dept. ofPublic Fall '05 through Spring '17 TBD

6-4 and Equipment Works • Develop and implement a Vehicle and The DPW enforced the Vehicle Maintenance Policy Equipment Maintenance Policy and and Equipment Maintenance

incorporate policy requirements into the Policy. DPW employee-training program.

DPW employees received hands-on training for this oolicv.

14

Page 15: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

BMPID# BMP Description Responsible Dept/Person

Measurable Goal(s) Progress on Goal(s) ­Permit Year 13

Planned Activities ..... Permit Year 14

Name (Reliance on non-municipal

6-5 Develop a Vehicle Dept. of Public Fall '05 through Spring '1 7 !Partners indicated, if any) The DPW enforced the Vehicle TBD

and Equipment Cleaning Policy

Works • Develop and implement a Vehicle and and Equipment Cleaning Policy. Equipment Cleaning Policy. DPW employees received hands­

Fire Department Place policy in the DPW employee-training on training for this policy. • manual and provide to the Town's Police

Police and Fire Department. Department • Review MADEP's vehicle rinsing policy

when issued and develop a plan to come into compliance with it.

6-6 Develop a Dept. ofPublic Spring ' 05 through '17 The Town requires that no TBD Landscaping and Works • Develop and implement a Landscaping and pesticides be used on Town Lawn Care Policy Lawn Care Policy. property.

• Place policy in the DPW employee-training manual. This policy was written into the Educate landscaping/lawn care service contracts for the landscaping/lawn • companies retained by the Town on this care service companies employed policy. by the Town

6-7 Maintenance ofTrash Dept. ofPublic Fall ' 05 through Spring '17 !The DPW inspected the outfalls TBD Racks and Outfalls Works • Develop an inspection and maintenance before heavy rainstorms are

plan for the trash racks and outfalls. tpredicted. When heavy rainstorms • Educate DPW employees on the proper deposited a large amount ofdebris

inspection and maintenance of the trash at the Town's drainage outfalls and racks and outfalls. inlets, the DPW removed this

• Maintain records ofinspection and maintenance activities.

!material and properly disposed of it. In addition, at the larger outfalls, silt was cleaned out once a year as part of routine maintenance. The inspection and maintenance activities were recorded in a loebook.

15

Page 16: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

6-8

BMP ID# BMP Description Responsible Dept./Person

Measurable Goal(s) Progress on Goal(s) -Permit Year 13

Planned Activities - Permit Year 14

Name (Reliance on non-municipal loartners indicated, if any)

Maintenance ofthe School Spring '04 through '17 lfhe detention basins were TBD Detention Basins at Department • Develop a maintenance plan for the lmaintained by the School Stoneham Public Schools

detention basins at the elementary schools. Educate school department staffon the • proper maintenance ofthe detention basins.

• Maintain records ofmaintenance activities .

Department.

For newly installed detention basins on private properties, the Town requires that the homeowners maintain the BMP. If lthe homeowners do not properly maintain the BMP, the Town requires that the homeowners pay he Town to oerform the work.

6a. Additions

No additions to report at this time.

16

Page 17: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

7. BMPs for Meeting Total Maximum Daily Load (TMDL) Waste Load Allocations (WLA)

Not Applicable to the Town of Stoneham

BMP ID#

BMP Description Responsible Dept./Person Name

Measurable Goal(s) Progress on Goal(s) -Permit Year 8 (Reliance on non-municipal partners indicated, if any)

Planned Activities

Revised

Revised

Revised

Revised

Revised

7a. Additions

7b. WLA Assessment

17

Page 18: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

Part IV. Summary of Information Collected and Analyzed

As part of the Town ofStoneham's Clean Water Act Administrative Order from EPA, wet- and dry-weather sampling was conducted at various outfalls and manholes throughout the collection system in 2016. These sampling results are included in this annual stormwater report on the next page.

18

Page 19: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

Appendix A Sampling Results - 2016

Table A-1

Structure ID Date Weather Type Location Flow Sampled Surfactants Ammonia Total E.Coli Chlorine

NO SAMPLES

Part V. Program Outputs & Accomplishments (OPTIONAL)

19

Page 20: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

Programmatic (Pfire erre dU")mts Response

Stormwater management position created/staffed (yin) N Annual program budget/expenditures** ($) 0 Total program expenditures since beginning ofoermit coverage ($) 0 Funding mechanism(s) (General Fund, Enterorise, Utility, etc) NIA

Education, Involvement, and Training

Estimated number ofproperty owners reached bv education ororrrarn(s) (#or%) 100% Stormwater management committee established (yin) yStream teams established or supported (# or yin) N Shoreline clean-up participation or quantity ofshoreline miles cleaned** (yin or mi.) NIA Shoreline cleaned since beginning ofpermit coverage (mi.) NIA Household Hazardous Waste Collection Days

• days sponsored ** (#) 2

• community participation** (#or%) • material collected * * (tons or gal)

School curricula implemented (yin) N

20

Page 21: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

Legal/Regulatory

Regulatory Mechanism Status (indicate with "X")

In Place Prior to Phase II

Reviewing Existing

A h .. ut ontles Dafted r

Draft m

R .ev1ew Adopted

• Illicit Discharge Detection & Elimination

• Erosion & Sediment Control

• Post-Development Stormwater Management

Accompanying Regulation Status (indicate with "X")

• Illicit Discharge Detection & Elimination

• Erosion & Sediment Control

• Post-Development Stormwater Management

Mapping and Illicit Discharges (Preferred Units) Response

Outfall maooing complete (%) Estimated or actual number of outfalls (#) System-Wide mapping complete ( complete storm sewer infrastructure) (%) Mapping method( s)

• Paper/Mylar (%) • CADD (%) • GIS (%)

Outfalls inspected/screened ** (#or%) Outfalls inspected/screened (Since beginning of permit coverage) Illicit discharges identified * *

(# or %) (#)

Illicit discharges identified (Since beginning ofpermit coverage) Illicit connections removed **

(#) (# );and (est. !!Pd)

Illicit connections removed (Since beginning of permit coverage) (#); and (est. gpd)

% ofpopulation on sewer (%) 98.47%

21

Page 22: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

I% of population on septic systems I (%) 1 1.s3%

Construction re erre dU.)R(Pf; mts esponse

Number ofconstruction starts (>1-acre) * * (#) 2 Estimated percentage of construction starts adequately reirulated for erosion and sediment control * * (%) 100% Site inspections completed * * (#or%) 100% Tickets/Stop work orders issued * * (#or%) 0 Fines collected ** (#and $) 0 Complaints/concerns received from public * * (#) 0

Post-Development Stormwater Management

Estimated percentage of development/redevelopment projects adequately regulated for post- (%) 100% construction stormwater control Site inspections (for proper BMP installation & operation) completed ** BMP maintenance required through covenants, escrow, deed restrictions, etc. Low-impact development (LID) practices permitted and encouraged

(#or%) (y/n) (y/n)

0 y N

Operations and Maintenance

Average frequency ofcatch basin cleaning (non-commercial/non-arterial streets)** (times/yr) 1/yr Average frequency of catch basin cleaning (commercial/arterial or other critical streets)** (times/yr) 1/yr Qty of structures cleaned * * (#) 2030 Qty. ofstorm drain cleaned * * (%, LF or 0

mi.) Qty. of screenings/debris removed from storm sewer infrastructure** (lbs. or 400 tons

tons) Disposal or use of screenings (landfill, POTW, compost, beneficial use, etc.) ** (location) Landfill

22

Page 23: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

Basin Cleaning Costs

Annual budget/expenditure (labor & equipment)** • ($) $24,000

Hourly or per basin contract rate * * • ($/hr or$ $1 l .35lper per basin) Basin

Disposal cost** • ($) $8,000 Cleaning Equipment

Clam shell truck(s) owned/leased • (#) 0

Vacuum truck(s) owned/leased • (#) 0

Vacuum trucks specified in contracts • (yin) N

• % Structures cleaned with clam shells * * (%) 100%

• % Structures cleaned with vactor * * (%) 0

Preferred Units) Response Average frequency of street sweeping (non-commercial/non-arterial streets) * * (times/yr) 1/yr Average frequency of street sweeping ( commercial/arterial or other critical streets) * * (times/yr) llyr Qty. ofsand/debris collected by sweeping** (lbs. or 1,000 Tons

tons) Disposal of sweepings (landfill, POTW, compost, beneficial use, etc.) ** (location) Landfill Annual Sweeping Costs

Annual budget/expenditure (labor & equipment)** • Hourly or lane mile contract rate * * •

($) ($/hr. or

$40,000 NIA

In mi.) Disposal cost** • ($) $20,000

Sweeping Equipment

Rotary brush street sweepers owned/leased • (#) I Vacuum street sweepers owned/leased • (#) 0

Vacuum street sweepers specified in contracts • (yin) NIA % Roads swept w ith rotary brush sweepers**• % Roads swept with vacuum sweepers ** •

%

%

100%

0%

IReduction (since beginning of permit coverage) in application on public land of:

23

Page 24: NPDES PII Small MS4 General Permit Annual Report...The Town has a SeeClickFix ; General Permits for : button on its homepage for ; MS4 stormwater : reporting problems. discharges in

("NIA" = never used; "100%" = elimination) • Fertilizers (lbs. or%) None • Herbicides (lbs. or%) None • Pesticides (lbs. or%) None

Integrated Pest Management (1PM) Practices Implemented (yin)

IPreferred Units) Response Average Ratio of Anti-/De-Icing products used * * ¾NaCl

¾CaCh (also identify chemicals and ratios used in specific areas, e.g., water supply protection areas) ¾MgCh

¾CMA ¾Kac ¾KCl ¾Sand

Pre-wetting techniques utilized * * (y/n or%) Manual control spreaders used * * (yin or%) Zero-velocity spreaders used** (yin or%) Estimated net reduction or increase in typical year salt/chemical application rate (±lbs/In mi.

or%) Estimated net reduction or increase in typical year sand application rate ** (±lbs/In mi.

or ¾) % of salt/chemical pile(s) covered in storage shed(s) (%) 100 Storage shed(s) in design or under construction (yin or #) 1 100% of salt/chemical pile(s) covered in storage shed(s) by May 2008 (y/n) y

Water Supply Protection

Storm water outfalls to public water supplies eliminated or relocated # or y/n Installed or planned treatment BMPs for public drinking water supplies and their protection areas # or y/n Treatment units induce infiltration within 500-feet of a wellhead protection area # or y/n

24