NPDgamma Liquid Hydrogen Target Safety Review

Project and Safety

At LANL

November 29-30, 2005

Page 2: NPDgamma Liquid Hydrogen Target Safety Review Project and Safety At LANL November 29-30, 2005

NPDgamma Experiment:

Precision measurement of parity-violating directional gamma-ray asymmetry A in polarized cold neutron capture on proton.The goal is to measure Awith the accuracy of 10-8. The measurement will unambiguously determine the weak NN coupling constant.

Page 3: NPDgamma Liquid Hydrogen Target Safety Review Project and Safety At LANL November 29-30, 2005

NPDGamma Experiment Setup in FP12 at ER2

FP12 Cave

Page 4: NPDgamma Liquid Hydrogen Target Safety Review Project and Safety At LANL November 29-30, 2005

The NPD Collaboration

Page 5: NPDgamma Liquid Hydrogen Target Safety Review Project and Safety At LANL November 29-30, 2005

About NPDgamma Project

• Scientific proposal was written in 1997 • Management Plan “The n+pD+ Project Management Plan for Experiment and Beam Line Construction” was signed in 2001. • Sponsors: DoE Nuclear Physics, NSF, NSERC, LANL, collaborating institutes• Capital cost of the project is roughly $2.5mil + $2.5 mil• Beamline construction project completed 02/04• Experiment construction project has:

11 work packages responsibilities by collaborators and LANLcompleted except of the LH2 target work packageproject completion forecast 6/03

Page 6: NPDgamma Liquid Hydrogen Target Safety Review Project and Safety At LANL November 29-30, 2005

Status and plans

• Status– Beamline completed in 2004– Experiment completed in 2004 except of the LH2 target

• Our goal is to – have the LH2 target ready for beam and for

production at the end of March 2006 when beam is assumed to be again available at the Lujan Center after the facility maintenance break.

– For this we need to complete• Testing in shed• Install the target on FP12• Test the target again on FP12• And pass the reviews

rn + p → d +γ

Page 7: NPDgamma Liquid Hydrogen Target Safety Review Project and Safety At LANL November 29-30, 2005

• Scientific proposal was written in 1997• Pendlebury Committee’s physics review in 1997• Spinka I Committee’ technical review in 1998• In 1999 the 1st Target Review “Preliminary

Conceptual Design Review of the NPDGamma Experiment Hydrogen Target”

• Spinka II Committee’s technical review in 2000• In 2001 the 2nd Target Review “10% design

review” set “ a baseline” for further design. • Spinka III technical review in November 2002• DOE technical progress review on October 2004• In 2004 the vent line review

• In 2005 the 3rd Target Review

• Preliminary plan for the DOE closeout review of the construction project agreed to be on August 2006.

Project’s review history and futureProject’s review history and future

Page 8: NPDgamma Liquid Hydrogen Target Safety Review Project and Safety At LANL November 29-30, 2005

DOEDOEJohn McClellandLANL NPPJohn McClellandLANL NPPPhysics andLANSCE Council

Susan SeestromPhysics DivisionSusan SeestromPhysics DivisionPaul LisowskiLANSCE Division(Facility Owner)Paul LisowskiLANSCE Division(Facility Owner)Mary HockadayP-23 Group LeaderMary HockadayP-23 Group LeaderJ. David BowmanSpokespersonJ. David BowmanSpokespersonManagement Team:•Bowman / LANL•Penttila / LANL•Wilburn / LANLSeppo PenttilaProject ManagerSeppo PenttilaProject ManagerJeff SchinkelProject SafetyProject Construction(See Fig. 3.2)

Executive Committee:•Bowman / LANL•Penttila / LANL•Coulter / Michigan•Leuschner / UNH•Page / Manitoba•Snow / Indiana

DOEDOEJohn McClellandLANL NPPJohn McClellandLANL NPPPhysics andLANSCE Council

Susan SeestromPhysics DivisionSusan SeestromPhysics DivisionPaul LisowskiLANSCE Division(Facility Owner)Paul LisowskiLANSCE Division(Facility Owner)Mary HockadayP-23 Group LeaderMary HockadayP-23 Group LeaderJ. David BowmanSpokespersonJ. David BowmanSpokespersonManagement Team:•Bowman / LANL•Penttila / LANL•Wilburn / LANLSeppo PenttilaProject ManagerSeppo PenttilaProject ManagerJeff SchinkelProject SafetyProject Construction(See Fig. 3.2)

Executive Committee:•Bowman / LANL•Penttila / LANL•Coulter / Michigan•Leuschner / UNH•Page / Manitoba•Snow / IndianaExecutive Committee:•Bowman / LANL•Penttila / LANL•Coulter / Michigan•Leuschner / UNH•Page / Manitoba•Snow / Indiana

Organizational Chart for the NPDGamma Project in Nuclear Physics ProgramOrganizational Chart for the NPDGamma Project in Nuclear Physics Program

Bill Louis

Jack Shlachter

Doug Fulton

TBA

Hersman/UNHGentile/NIST

Page 9: NPDgamma Liquid Hydrogen Target Safety Review Project and Safety At LANL November 29-30, 2005

Safety Hierarchy in the LH2 Target Project

• DOE is involved through the Facility Authorization Basis. – We need to perform USI(=Unreviewed Safety Issue) against the

ISAD(=InterimSafety Assessment Document) in addition to the USQs (=unresolved/unreviewed safety questions) that have already been done.

• At Lab the highest level signature is coming from LANSCE Division leader; Paul Lisowski. He signs the Authorization Basis, and he is the RDL=responsible Division Leader who signs IWD=Integrated Work Document.

• Next level of signature is coming from RGL=responsible Group Leader D. Fulton, P-23) who signs IWD to authorize the work and personnel.

• Readiness Review by facility - signed by Alan Hurd, Director of Lujan Center.

Page 10: NPDgamma Liquid Hydrogen Target Safety Review Project and Safety At LANL November 29-30, 2005

IWD

• IDW JHA ID 3501 “Testing of the NPDGamma Liquid Hydrogen Target” – Tasks and steps– Hazard analysis– Controls and requirements– Responsibilities - RDL, RGL, Preparer, SMEs, workers– Target personnel - training, authorization process

• Target IWD refers to– Lab documents– Engineering Document– Target Operating Procedures

• IWD can also give steps for safe performance of a task. If we identify an important task with a higher safety risk we can have a separate IWD for that task.

Page 11: NPDgamma Liquid Hydrogen Target Safety Review Project and Safety At LANL November 29-30, 2005

Value of this review

• Independent review of the target by experts– Improves overall target safety

• Will create the final design baseline for the target. After this review

• drawings• engineering document

will be under the change control

• The review result will effect on – authorization in different management levels

Page 12: NPDgamma Liquid Hydrogen Target Safety Review Project and Safety At LANL November 29-30, 2005

Flow chart for the shed and ER2 LH2 target effort

Flow chart for the shed and ER2 LH2 target effort Start July '04

Develop reqm'ts

for Shed relief line

(Penttila)

Shed Relief Line

review by Internal

Committee

(10% design)

Build Shed relief

Convene H

Committee ASAP

(internal/external)

Finish Shed setup

Readiness Review

(Shed operations)

by Lujan EAM

Operate in Shed

Review of FP12

relief line and GHS

vent 10% design by

Internal Committee

Build & Install

Design review of

system at 10-20%

point by H

Committee

Finish ER2 setup

Readiness Review

(ER2 operations)

by Lujan EAM

Experiment runs

with LH target

2

2

2

J. Knudson, chairP. Kelley

D. HillJ. LatailleP. LewisB. Etuk,

….

Page 13: NPDgamma Liquid Hydrogen Target Safety Review Project and Safety At LANL November 29-30, 2005

Hydrogen Target in Shed

30 cm

30 c

m

The goal is to review safety of: • as built the LH2 Target cryostat and relief system. They will be almost same for the shed and ER2 operation.• as built the gas handling system in shed• a plan for the gas handling system for ER2• plans for controls and operations

Page 14: NPDgamma Liquid Hydrogen Target Safety Review Project and Safety At LANL November 29-30, 2005

LH2 Target Vessel and Isolation Vacuum