nuclear energy development in lithuania - international …€¦ · · 2016-03-04establishing a...
TRANSCRIPT
Gediminas Karalius Electricity Sector Division
10 February 2016
MINISTRY OF ENERGY OF THE
REPUBLIC OF LITHUANIA
IAEA Technical Meeting TM-52851 Establishing a Strategic Partnership and Contract Model for Expansion/Introduction of NPP
Hosted by Ministry of Economics of Poland and PGE Warsaw, Poland, 10-12 February 2016
Nuclear Energy Development in Lithuania
1. Existing and planned nuclear installations
2. Legal and Institutional System in Lithuania
3. Legal Reform. Improvements of Regulatory
Framework
4. Legal Reform. Improvements of Investment
Framework
5. Activities in HR development
2
Contents
Nuclear facilities at Ignalina NPP site (existing, planned, or under construction)
New Visaginas NPP
Maišiagala radioactive waste storage
4
Existing and planned nuclear installations Existing Ignalina NPP (under decommissioning):
2 RBMK-1500 units (2x1500MW) 1983-2004 and 1987-2009
Spent nuclear fuel storage facility Liquid radioactive waste management facilities Cementation and interim storage of solidified (cemented) waste Maišiagalal radioactive waste storage facility Under construction or planned New spent nuclear fuel storage facility New solid radioactive waste treatment and storage facilities Storage facility and a repository for very low activity waste Repository for low and intermediate activity radioactive waste Visaginas New Nuclear Power Plant
Largest and most advanced RBMK design (also with later safety upgrading)
Intended to serve NW region of Soviet Union
Supplied 70-88% of LT national demand
Closed at around mid-life (as a condition for LT accession to EU)
Construction Operation Decommissioning 1974-1987 1983-2009 2010-2038
Plant type
Number of units
Power per unit
Staff
Unit 1 Unit 2
First operation Dec 1983 Aug 1987
Final Closure Dec 2004 Dec 2009
Power generation 137 TWh 170 TWh
Op
era
tio
nB
asic
s
RBMK-1500
2 (of 4 planned)
1500 MW
5600 during operation
5
Ignalina NPP
6
Rationale of Visaginas NPP Project
Energy security
Diversification of region’s energy mix and market
competitivenes
“Green Agenda” and region’s environmental goals
Visaginas NPP project development overview
Main pre-development works completed
Hitachi selected as the Strategic Investor with
ABWR 1350 MW reactor (2011);
Favorable opinion by the European Commission
received (2012);
Legal environment for project development
adjusted
Advisory non-binding referendum held (2012)
Sites approved by VATESI (2014)
Post-referendum activities:
Eonomic competitiveness of the
project improved
Principal national agreement to
develop Visaginas NPP project by
main Parliamentary parties is reached
Discussions with the Regional
Partners and Strategic Investor
continued
National energy startegy review in
progress
New Visaginas NPP Visaginas new nuclear power plant is a strategically
important Project for the Baltic region
Operation Pre-construction Preparation
2007-2015 ~ 3 yers 60 years ~ 5 years
Decomm
Project company
Construction
LT Contractor
(Hitachi-GE) Operation and maintenance contractor
10 years
Preparatory activities
Technical preparatory activities including EIAR
Organization for direct negotiations and selection of
strategic investor
Regulations and licensing, appropriate legal and
investment environments
Project notification to EC
Site evaluation
Special planning procedures for main haul road completed
Pre-construction period
! Establishment of the Project company: Shareholders,
Concession, EPC agreements
• Detailed plant design activities
• Preparatory activities for equipment ordering necessary for
reactor construction
• PSAR preparation and coordination;
• License for construction and operation
Construction period
• Main haul road construction and finishing the route
construction
• NPP Construction activities
• Systems’ testing, adjustments, testing, FSAR preparation
and adjustment
NPP operation
• New nuclear power plant operation
• Plant improvements
Decommissioning
• Decommissioning activities
• Utilization of the decommissioning fund
Current
Visaginas NPP project timeline
7
Main legal acts for nuclear
In accordance with fundamentals and requirements set forth in the international
Conventions, EU directives as well as in IAEA Safety Standards, national legal
infrastructure was established and is further enhanced
International conventions: Nuclear Safety Convention (ratified in 1995) and Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management (ratified in 2003)
EU legislation: Directive on Nuclear Safety; Directive on Safe management of Spent Fuel and Radioactive Waste; Directive on Basic Safety Standards
Laws, Governmental decisions: Nuclear energy law; Nuclear safety law; Radioactive waste management law; Radiation Protection law; Law on [new] Nuclear Power Plant; Regulations for Licensing of Nuclear Power Related Activities, other
VATESI requirements and rules (more then 50 valid documents)
Standards: ASME, KTA, etc.
License holder’s technical normative documentation
9
10
Parliament of the Republic of Lithuania
Government of the Republic of Lithuania
Ministry of Environment
Fire and Rescue Department
State
Security
Department
Radiation Protection
Centre
State Border
Guard Service
Ministry of Energy
President of the Republic of
Lithuania
State Territorial Planning and Construction
Inspection
Environment Protection
Agency
Ministry of Finance
Ignalina NPP
Shareholder
“Lietuvos energija”, UAB
UAB “VAE SPB”
Shareholder
Ministry of Social Security and
Labor
Ministry of Interior
Ministry of Health
Ministry of National Defense
Labor Inspection
Vilnius University
Kaunas University of Technology
Vilnius Gediminas Technical University
Lithuanian Energy Institute
Centre for Physical Sciences and Technology
State Nuclear Power Safety Inspectorate
(VATESI)
UTILITY
INVOLVED MINISTRY
INVOLVED REGULATORY INSTITUTION
INVOLVED
INSTITUTION
MAIN R&D INSTITUTIONS
Legend
Visaginas
Municipality
INTERESTED
MUNICIPALIY
Shareholder
Institutional Framework for Nuclear Energy
11
Nuclear regulatory body (VATESI)
State Nuclear Power Safety Inspectorate (VATESI) – from 1991 Mandate of VATESI (the main issues): State regulation and supervision of nuclear safety,
radiation safety, physical protection and safeguards in Nuclear Facilities
State control of safeguards implementation State regulation and supervision of physical protection
nuclear material Performs international cooperation in all of the
competence areas Regulatory duties of VATESI: Preparation of regulations Review and assessment of information relevant to
safety Issuance of licenses and permits, approval of documents
Inspection of facilities and consultation Enforcement Oversight of non-proliferation
State Nuclear Power Safety Inspectorate (VATESI)
was established in 1991 and since then together
with the whole nuclear power infrastructure of
Lithuania has succesfully passed a long way of
development and gaining experience
Structure of VATESI
Main aims of such reforms were to: Adjust regulation and nuclear safety provisions in line with latest International and EU
requirements and best practices Adjust the existing legal and regulatory regime to the actual needs of the new Visaginas
NPP project and Ignalina NPP decommissioning Establish effective and transparent licensing process Make authorisation, regulation and supervision more flexible, efficient, transparent and
streamlined Enhance the independence of the regulator Specify and clearify the functions of responsible institutions in order to avoid duplication
of functions Set up more effective decision making principles
Result: Set of 12 Laws approved by the Parliament in June 2011 and followd by ammendments and introduction of up tio70 lower level legal acts
Improvements in Legal and Regulatory regime
With regard to the development of new Visaginas NPP project and preparation for its
construction legal and regulatory reform, in line with the International and EU requirements,
was performed through years 209-2011
13
14
Legal framework improvements
Law on Nuclear Energy (ammended): establishes the basis for a stronger and independent nuclear regulatory authority
Law on Nuclear Safety (New ): strengthened regulatory system of nuclear safety more detailed and clear rules of the state regulation and supervision of nuclear safety in nuclear installations explicitly defined system of licensing and forms of authorization, enforcement measures, etc
Law on Radiation Protection (ammended) clear separation of functions of the Radiation Protection Centre and the State Nuclear Power Safety Inspectorate in the field of radiation protection
Law on Radioactive waste management (ammended) change of institutions competences and responsibilities in state regulation of radioactive waste management
Law on Nuclear Energy
Law on
Radiation
Protection
Law on
Radioactive
Waste
Management
Law on Nuclear
Safety
(newly
introduced)
International
conventions
IAEA requirements
Set of Regulatory Requirements
General
requirements
Detailed
requirements
EU legal acts
15
Independence of Nuclear regulatory body (VATESI)
Appropriate Position of VATESI in State’s Governmental Framework VATESI reports to President and Government (Law on Nuclear
Energy, Article 21) Head of VATESI appointed by President in accordance with offer
of Prime Minister
Promotion and regulatory functions separated (Law on Nuclear Energy) Promotion functions – Ministry of Energy Nuclear safety regulation functions – VATESI
Regulatory decisions are based on established nuclear safety requirements or other good practice (IAEA, WENRA etc.) Technically competent staff
Regulatory framework improvements
Nuclear Facilities
State Nuclear Power Safety Inspectorate
(VATESI)
(Nuclear and Radiation Safety)
Radiation Protection Centre (RSC)
(Radiation Safety)
Non-Nuclear Facilities
Redistribution of functions between the regulatory authorities
Regulatory framework improvements (cont.)
Environmental Protection Agency
Environment radiological monitoring functions remain
16
Authorisation process for construction and operation
Commissioning
Operation license. USAR
OPERATION LICENSE
Permit for the first launch of the
reactor. USAR
Construction
Permit for commercial operation.
Final SAR
CONSTRUCTION LICENSE
Approval of Commissioning
Program
COMBINED (CONSTRUCTION AND OPERATION) LICENSE
Permit for the first transportation of the NF into the
site. USAR
Permits to resume
operation after shut
down
Operation
Combined license.
PSAR
Construction license. PSAR
Operation
Regulatory framework improvements (cont.) Tw
o o
pti
on
s
Commissioning Construction
17
18
Licensing Roadmap for new NPP
Government Government Decision on
initiation of construction
PSAR VATESI (taking into account
conclusions of Geological
Survey, Fire Rescue
Department, Ministry of Health,
Hydrometeorological Service
and Civil Aviation
administration)
Preparation of
Design and PSAR
Parliament Law on NPP
June 2007
Nuclear Facility Technical Specification VATESI
Preparation of special conditions for design by authorities to
applicant; agreement by applicant of design with them in
accordance with Construction Law
VATESI
Site evaluation
October 2014
Construction and
Operation
LICENCE
EIA
April 2009
Ministry of the Environment (MoE), VATESI, the local authorities,
authorities responsible for healthcare, fire prevention, protection of cultural
values, economic development, development of agriculture
VATESI, if Permit for Construction by State Territorial Planning and Construction
Inspectorate under MoE is issued and valid
Construction
Regulatory oversight by VATESI and State Territorial Planning and
Construction Inspectorate under MoE – in terms of structures (buildings);
Supervision by VATESI – in terms of systems and components and other important
to safety issues
Commercial Operation Periodical
Safety Review
FSAR VATESI
PERMIT for Commercial Operation VATESI
VATESI
Commissioning
Positive conclusion of the IAEA mission on performed
procedures and results received in 2010
Consists of number of permitting stages. Permits issued by
VATESI. Includes preparation of USAR
COMPLETED
Law on Change of Law on Nuclear Power Plant
Law on Granting the Concession and Assuming the
Essential Property Obligations of The Republic of Lithuania
in the Visaginas Nuclear Power Plant Project
Law on Change of Law on Enterprises and Facilities of
Strategic Importance to National Security and other
Enterprises of Importance to Ensuring National Security
Law on Ammendment of Law on Joint Stock Companies
Law on Ammendment of Law on Elecrtric Energy
Law on Change and Ammendment of Law on Energy
Law on Ammendment of Law on Concessions
Law on Ammendment of Law on Income Tax
Law on Ammendment of Law on Construction
Law on Ammendment and Law on Legal Status of
Foreigners
Law on Ammendment of Law on Land
Law on Ammendment of Law on Expropriation of Land for
Implementation of Projects of Critical Importance to the State
20
Set of legal acts approved in 2012
21 June 2012 Lithuanian
Parliament approved the
dedicated package of laws
necessary for further
Visaginas NPP project
development, inter alia
setting legal conditions for
Project Company
organization (PCO)
establishment and signing
of Concession agreement
21
Main legal acts for Visaginas NPP project environment
Law on the Nuclear Power Plant
The purpose of this Law - to create favourable legal, financial and organisational conditions that would help to implement the new nuclear power plant project Project Company Organisation described – establishement, role and
responisbilities
Legal status and requirements of Strategic Investor, National investor and
Strategic Partners described
Business Relations Model (MANKALA) and Taxation of the Project
Implementing Company
Concession model established
Requirements on project financing sources provided
Other: provision of land plots as the contribution in kind clarified; special
conditions for work and stay permits for non EU citizens; exemptions with
regard to qualification confirmation and certification of companies etc.
English translation of the law can be found following this link: http://www3.lrs.lt/pls/inter3/dokpaieska.showdoc_l?p_id=437747
22
Main legal acts for Visaginas NPP project environment
Law on Granting the Concession and Assuming the Essential Property Obligations of The Republic of Lithuania in the Visaginas Nuclear Power Plant Project
The purpose of the law: Approval of granting of the concession to the PCO in Visaginas NPP
project Approval of “Hitachi“ as the strategic investor, as well as the
development of the project based on Hitachi-GE ABWR technology Assumption of the essential property obligations of the Republic of
Lithuania stipulated in the draft concession agreement Approval of draft Concession Agreement (CA)
English translation of the law can be found following this link: http://www3.lrs.lt/pls/inter3/dokpaieska.showdoc_l?p_id=436569
23
Lithuania’s support and obligations to facilitate Visaginas
NPP project development
Essential State obligations stipulated in the CA
Lithuania’s obligations to facilitate project development
Design of the main access road of the Visaginas NPP project prepared Ensure transfer of the site and the related intellectual property to the
PCO
Foreign investments protection Buying-out of PCO shares (put option) in case of CA termination for the
events attributed to Lithuania’s liability Compensation to the entities indicated in the CA for the losses arising
from breach of the confidentiality undertaking by the Republic of Lithuania and violations of concession granting procedures and (or) guaranties
Draft Concession Agreement can be found following this link: http://www3.lrs.lt/pls/inter3/dokpaieska.dok_priedas?p_id=56758
25
National Plan for Preparation of Specialists in Nuclear Energy
The National Plan for preparation of highly qualified nuclear energy specialists has been adopted in May 2011 by the joint order of the Minister of Energy and the Minister of Science and Education.
The Plan foresees tasks and measures needed to educate the students later able to work in nuclear industry and related institutions
Organization of studies in nuclear
energy
Assurance of quality of study
programmes
Establishment of encouragement and
motivation system for students
Maintenance of material base of
educational and scientific institutions
Tasks and Measures
26
National HR Developments to Support Nuclear Capabilities
Estimation of HR needs for Visaginas NPP:
30 nuclear energy specialists during pre-project phase 100 nuclear professionals for nuclear power plant design and construction period about 300 nuclear professionals for NPP operation period around 60 professionals for state, higher education and research institutions
National Plan for Preparation of High Qualification Specialists in Nuclear Energy
Energy Physics Nuclear Engineering
Programme of HR Development
Nuclear Management and Engineering courses
Available sourcess
Ignalina NPP
Re-qualification and re-training
Thank You for the attention
Gediminas Karalius Adviser on nuclear energy development /Visaginas NPP project
Electricity Sector Division e-mail: [email protected]