nuclear facilities construction project management

154
1 Valeriy Trofimov, Darya Pankova Nuclear facilities construction project management St.Petersburg 2012

Upload: sandy-atomprof

Post on 18-Mar-2016

219 views

Category:

Documents


0 download

DESCRIPTION

Nuclear facilities construction project management

TRANSCRIPT

1

Valeriy Trofimov, Darya Pankova

Nuclear facilities

construction project

management

St.Petersburg

2012

2

JSC Atomenergoprom

Private Educational Institution of Continuing Professional Education

«ATOMPROF»

Valeriy Trofimov, Darya Pankova

Nuclear facilities

construction project

management

St.Petersburg

2012

3

Valeriy Trofimov, Darya Pankova. Nuclear facilities construction project management. –

SPb: Private Educational Institution of Continuing Professional Education «Atomprof», 2012. –

155p.

This workbook is offered as a resource for teaching postgraduate students the

implementation and project management of energy. The purpose is to provide the reader with

theoretical and practical advice on construction of nuclear power facilities using software and

hardware platform based on Oracle Primavera.

The book highlights such issues as Project Management Body of Knowledge (PMBoK)

using and Organizational Project Management Maturity Model (OPMMM) of Project

Management Institute (PMI) overview.

The book is written for postgraduate students, employees and managers, involved into the

launching of project organizational methods. It can be also used by students learning Project

Management and in the teaching of this course.

All rights reserved. No part of this book may be used or reproduced in any manner

whatsoever without written permissions, except in the case of brief quotations.

Recommended for publication by the methodological department of PEI CPE

«Atomprof».

Reviewers:

ISBN

Trofimov V., Pankova D. 2012

4

Introduction ..................................................................................................... 6

Subject matter 1 “Project management methodology” ................................... 7

Introduction ..................................................................................................... 8

Knowledge Structure Project Management ............................................ 8

Introduction to ICB IPMA ...................................................................... 8

Topic 1.1. Project management concept ................................................... 13

1.1.1. Basic notions: “Project” and “Project management” .................. 13

1.1.2. Project environment .................................................................... 17

1.1.3. Project stakeholders .................................................................... 21

1.1.4. PM organizational structures ...................................................... 23

1.1.5. Project structures ......................................................................... 35

1.1.6. Project life time ........................................................................... 41

Topic 1.2. Project management processes ................................................ 45

1.2.1. Project management processes ................................................... 45

1.2.2. Groups of project management processes .................................. 48

1.2.3. Processes in the area of project management knowledge ........... 59

1.2.4. Process interfaces ........................................................................ 69

Topic 1.3. Project risk management processes ......................................... 75

1.3.1. Risk identification ....................................................................... 75

Topic 1.4. Project management information system (PMIS) ................... 86

1.4.1. PMIS configuration ..................................................................... 86

1.4.2. PMIS based on Oracle Primavera software ................................ 96

1.4.3. PMIS organizational support .................................................... 104

Topic 1.5. NPP construction time management ...................................... 107

1.5.1. Managerial structure ................................................................. 107

1.5.2. Development of 1st level schedules .......................................... 112

1.5.3. Development of 2nd level schedules ....................................... 116

1.5.4. Development of 3rd level schedules ........................................ 119

Subject matter 2 Managing Projects in Oracle Primavera P6 Project

Management .......................................................................................................... 128

Introduction ............................................................................................. 128

2.1. Starting up ........................................................................................ 129

2.1.1. Primavera’s Interface ................................................................ 129

..................................................................................................................... 130

2.1.2. Opening a project. ..................................................................... 132

5

2.2. Project settings ................................................................................. 134

2.3. Corporate data structure ................................................................... 135

2.3.1. Code structures .......................................................................... 135

2.3.2. EPS ............................................................................................ 137

2.3.3. OBS ........................................................................................... 137

2.3.4. Roles .......................................................................................... 138

2.3.5. Resources .................................................................................. 139

2.3.6. Calendar .................................................................................... 140

2.4. Project structure ............................................................................... 143

2.4.1. WBS .......................................................................................... 143

2.4.2. Activities ................................................................................... 144

2.4.3. Steps .......................................................................................... 144

2.4.4. Relationships ............................................................................. 145

2.4.5. Assignments .............................................................................. 146

2.5. GROUP, SORT AND FILTERS ....................................................... 147

2.6. REPORTS AND PRINT SETUP ..................................................... 151

2.7. ANALYSYS AND CONTROL ....................................................... 152

2.7.1. What-If ...................................................................................... 153

2.7.2. Fact ............................................................................................ 154

6

Introduction

1st

year learning objective:

Give an idea of project management basics.

Explain to the trainees the main terms, basic notions and information on the

best practices of project management necessary for efficient work whatever

organizational form is used

Subject matter 1 “Project management methodology” is a theoretical course

supplemented with practical classes of the traditional course “Nuclear facilities

construction project management based on Primavera software” during which the

attendees obtain practical skills of project scheduling on the basis of Oracle

Primavera software and get acquainted with the practical implementation of project

management tasks as exemplified by LNPP-2 construction.

Subject matter 2 Managing Projects in Oracle Primavera P6 Project

Management

Tutorial materials are represented with a number of presentations in

Microsoft Power Point 2007, the rubrication and titles of which correspond to the

topics given above.

The programme has been developed by

Prof. Trofimov V., Dr. Eng.

7

Subject matter 1 “Project management methodology”

Subject matter 1 “Project management methodology” is a theoretical

course supplemented with practical classes of the traditional course “Nuclear

facilities construction project management based on Primavera software” during

which the attendees obtain practical skills of project scheduling on the basis of

Oracle Primavera software and get acquainted with the practical implementation of

project management tasks as exemplified by LNPP-2 construction.

Requirements to the trainees: good computer skills, knowledge of MS

Office.

8

Introduction

Knowledge Structure Project Management

Introduction to ICB IPMA

In order to be professional, the discipline «Project Management» shall have

a code of rules and regulations determining the professionals’ work on project

management.

These requirements were determined by way of collecting, processing an

systematizing applied knowledge and experience in the area of the Project

Management.

International rules of project management specialists’ competence (ICB -

International Competence Baseline), developed by the IPMA - International

Project Management Association, contain the requirements on the knowledge,

skills, and personal characteristics of project managers and project team members.

ICB include main terms and notions, sum up advanced experience, skills,

functions, management processes, methods, techniques and tools generally used in

project management as well as special knowledge of innovations and their

implementation in certain project management.

ICB is not a manual or a formula book. ICB opens the way to knowledge,

experience and personal skills in the project management area.

ICB is the basis of all certification programs of national associations and

their certification centers ratified by the International Project Management

Association (IРМА).

Main Areas of the Project Management of ICB IPMA The ICB logo is a sunflower which was used, as a rule, for the unification of

national certification programs.

The sunflower petals show the main areas of project management.

• Core Elements (28)

1. Projects and Project Management

2. Project context

3. Project life cycle

4. Project appraisal

5. Project coal & Strategy

6. Project Success/Failure criteria

7. Standards & Processes

8. System approach & integration

9. Project Start Up

10. Work definition & structuring

11. Scheduling

12. Resources

13. Cost & Finance

14. Performance Measurement

• Additional Elements (14) 29. Information technologies in project

30. Standards and rules

31. Problem solving

32. Negotiations, business meetings

33. Permanent (parent) organization

34. Business processes

35. Human resource management

36. Organizational training

37. Management of change

38 Marketing

39. System management

40. Safety, health, environment

41. Legal aspects

42. Finance and accounting

9

15. Project control

16. Project Close Out/Down

17. Organization

18. Information & Communication

19. Team Work

20. Leadership

21. Conflict Management

22. Personnel development

23. Configuration & Change

Management

24. Contract Administration

25. Risk Management

26. Quality Management

27. Safety, Health & Environment

28. Multi Project Management

Pic.1. 28 Core Elements

10

Certification Validation Management Board Certification Validation Management Board (CVMB) is a commission for the

development and coordination of national association certification programs at the

international level.

Main attention was given to the certification program (ICB) contents, its

organization and certification procedures.

In 1998, IPMA approved a ratification system for a 4-level certification

program (4-L-C - Pure Level Certification), which became world known.

By February 1999, 17 countries signed the agreement with IPMA and 10

countries apply the international certification program.

ICB contains the following sections:

A. Introduction

B. Knowledge and Experience

C. Candidate Personal Attitude

D. Taxonomy

E. Standards and Guidelines, References

F. Literature

National Competence Baseline Each national association develops and adopts its own detail documentation

for the certification program and, first of all, national requirements on competence

(NCB - National Competence Baseline).

This documentation is ratified by IPMA for performing certification.

Thereby, national associations are given certain freedom for taking into

account national cultural features and achievements in the project management

competence area.

On the other hand, the unification performed by IPMA, takes into

consideration the requirements of companies and organizations operating at the

world market.

International Competence Baseline ICB contains 42 elements, determining knowledge and experience in the

project management (28 key + 14 additional elements), as well as +8 aspects

concerning candidate personal attitude and +10 aspects, determining general

opinion of the certified person.

IPMA requires that NCB should contain all the 28 key elements and at least

6 additional elements selected at the national association’s discretion.

Besides, NCB should also contain the sections reflecting the aspects

concerning personal attitudes and determining the general opinion of the candidate.

At the same time, approximately 8 additional elements of knowledge and

skills (about 20% of the 42 elements) may be eliminated or replaced with new

elements taking into consideration national features and achievements in the

project management competence area.

Some specific issues reflected in national association NCB were not included

in the number of elements of project management elements provided in ICB.

11

Such elements are marked with italics in ICB .

These elements might serve as initial points for ICB further development and

widening.

The structure of NCB-SOVNET and ICB 1. Management objects

1. Project ►Projects and Project Management (1)

2. Program ► Management by Project (3)

3. Project Objectives and Strategies ►Project Objectives and Strategies (8)

4. Project Success and Failure Criteria ► Project Success and Failure

Criteria (9)

5. Project Structures ► Project Structures (12)

6. Project Phases and Life Cycle ► Project Phases and Life Cycle (6),

Marketing, Product Management (38)

7. Project Environment ► Project Context (5)

2. Project management subjects and tools 8. Project Stakeholders ► Project Context (5)

9. Permanent or Parents Organization ► Permanent Organization (33)

10. Project Team ► Teamwork (23)

11. Project Manager ► Teamwork (23)

12. Project Organization ► Project Structures (12), Project Organization 22)

13. Leadership ► Leadership (24)

14. Problem Solving ► Problem Solving (31)

15. Negotiations, Meetings) ► Negotiations, Meetings (32)

16. Information Technologies in Project ► Informatics in Project (29)

17. Standards and Regulations ► Standards and Regulations (30)

18. Legal Aspects ► Legal Aspects (41)

3. Project management processes 19. Project Management ► Projects and Project Management (1)

20. Management by Projects ► Management by Projects (3)

21. System Management ► System Management (39)

22. (Project Management Implementation ► Project Management

Implementation (2)

23. Project Start Up ► Project Start Up (10)

24. Project Development ► Project, Development and Appraisal (7)

25. Project Performance ► Project Performance (19)

26. Project Controlling ► Project Controlling (20)

27. Project Close Out ► Project Close Out - (11)

28. Project Scope Management ► Content, Scope (13), Configurations and

Changes (17)

29. Project Time Management ► Time Schedules (14) Resources (15)

30. Project Cost Management ► Project Cost and Finance (16), Finance and

Accounting (42)

12

31. Project Quality Management ► Project Quality- (28) Standards and

Regulations (30)

32. Project Risk Management ► (IS) Project Risks

33. Project Human Resource Management ► Teamwork (23). Personal

development (35). Organizational Learning (36), Conflicts and Crises (26)

34. Project Communications Management ► Communications (25)

Information, Documentation. Reporting (21)

35. Project Contracts Management ► Procurement, Contracts (27)

36. Project Change Management ► Management of Change (37)

Configurations and Changes (17)

37. Project Safety Management ► Safety, Health and Environment (40)

38. Project Conflict Management ► Conflicts and Crises 126)

39. System Approach and Integration in Project Management ► System

Approach and Integration (4)

4. Project management background and tendencies of development 40. Project Management around the World

41. Project Management in Russia

42. Project Management in Transition Economy

43. Project Management in Future

13

Topic 1.1. Project management concept

1.1.1. Basic notions: “Project” and “Project management”

Project Project – a temporary endeavor undertaken to create a unique product or

service.

Project is an undertaking for which human, material and financial resources

are arranged differently every time for performing the project tasks. The time and

costs for the project implementation are strictly limited and the project itself has a

standard life cycle (6).

Project is a complex of interconnected tasks, ensuring the achievement of

preset Project objectives (3) within the framework of established schedule and

allocated budget, as well as meeting other conditions and limitations.

Other Project attributes are novelty, integrity, legal conditions of its

implementation, the necessity to perform works in related areas of activities.

The variety of the projects implemented is very high. They may differ

drastically in terms of application area, configuration of scope (29), scale,

duration, stakeholders, degree of complexity, influence of results, etc.

Basic Notions An activity as the management object is considered to be a project when:

• it objectively has an integrated nature and, the analysis of the internal

structure of a whole set of task (operations, procedures, etc.) is of great

importance for its effective management;

• transitions from one task to another determine the main scope the activity

as a whole;

• achieving the activity’s goals is connected with serial-parallel performance

of all elements of this activity;

• limitations in terms of time, finance, material and labor resources are of

special importance for the work performance process;

• the activity duration and cost is explicitly dependent on the organization of

the whole set of tasks.

Definitions of “Project” 1) Webster’s Dictionary:

“Project (Engl.) – That which is projected or designed; something intended

or devised; a scheme; a design; an intention”.

2) USA, PMI Project Management Body of Knowledge :

“Project – certain undertaking (intention) with initially stated objectives

whose achievement determines the project close-out ".

3) English Association of Project Managers:

“Project is a separate undertaking (intention) with specified goals which

often comprise requirements on time, cost, and quality of the results achieved".

4) Germany, DIN 69901:

“Project is an undertaking (intention) which is, to a high degree,

14

characterized by the uniqueness of conditions in their integrity, for example:

– determining the objective;

– time, finance, HR, and other limitations;

– delimitation from other intentions;

– project-specific organization of its implementation".

General Definition of Project

Project is a temporary, goal-oriented change of a specific system with

established requirements concerning the results, possible frames for means and

resources expenditures, and specific organization.

Project Management

Project Management Body of Knowledge, (PMI) Project Management (PM) is an art of administrating and coordinating

human and material resources during the project life cycle using state-of-the-art

management techniques and practices for achieving the results determined in the

project, in terms of the work scope and content, cost, time, quality, and

stakeholders’ satisfaction.

English Association of Project Managers Project management is a governance challenge of a project completion

timely, within the framework of an established budget, and in compliance with the

technical specifications and requirements

Project Manager is responsible for reaching these results.

Germany - DIN 69901 Project Management is an entity of:

• Governance tasks,

• Organization,

• Technique and

• Project implementation means.

Professor H. Roeshke Project Management - “straight interprofessional corporation of processes:

• planning,

• management and

• decision taking with

• Interprofessional task setting".

Project Management Project Management is the application of skills, methods, means and

technologies during a project implementation, with the aim of achieving or

exceeding the project stakeholders’ expectations.

15

Project Management constitutes planning, organization, monitoring and

controlling all the project aspects as well as the motivation of all of its stakeholders

with the aim of complete achievement of the project goals within the established

period of time and preset parameters.

Project Management may be more broadly defined as a professional,

creative activity oriented for achieving effective results by way of successful

implementation of projects as purposeful changes.

Project Management includes:

– A full set of tasks, organization, management techniques and

governance measures for providing the project implementation.

– Creation of a motivation and encouragement system for all the project

stakeholders for the project goals’ successful achievement within the

specified limitations and requirements.

Project Management Systemic Model The principle system model of the project management consists of three

main interconnected units: Management subjects; Management objects;

Management process.

Pic.2. Project Management Systemic Model

Main Attributes of a Project: 1. attribute of changes, as the main content of a project,

2. attribute of aim, limited in time,

3. attribute of project duration time limitation,

4. attribute of the project budget,

5. attribute of “limiting the required resources",

16

6. attribute of “uniqueness",

7. attribute of “novelty",

8. attribute of “complexity",

9. attribute of “legal and organizational support",

10. attribute of “delimitation”.

1. The attribute of changes characterizes a goal-oriented transfer of a system

from existing condition to a desired one described in the terms of the project goal.

Pic.3. Attribute of changes, as the main content of a project.

2.The attribute of an aim limited in time characterizes the restrictions applied

during the project goal lifetime

3.The attribute of the project time limitation characterizes the restrictions

applied to the period of time necessary for the project implementation

4.Attribute of budget characterizes the fact that the project has a separate

budget

5. The attribute of the required resources limitation characterizes the

presence of a specification and schedule of the resources consumption

6.The attribute of uniqueness characterizes the impossibility to return to the

project start.

7.The attribute of novelty characterizes the presence of novelty (uniqueness)

of the project constituting parts and the presence of novelty (uniqueness) of the

project as a whole

8.The attribute of complexity characterizes the number of the project context

factors and the number of the project stakeholders

9a.The attribute of legal support characterizes the legal regulation of

interests and relations of all the project stakeholders

17

9b.The attribute of organizational support characterizes the project-specific

structure organization

10.The attribute of delimitation characterizes the presence explicitly

defined borders of the project scope and its interfaces with the outer environment

1.1.2. Project environment

Project environment

Pic.4. Project environment interaction

Project environment: external and internal one.

Pic.5. Project environment scheme

Distant project environment Political characteristics and factors:

18

Political stability

Governmental support of the project

Nationalistic demonstrations

Crime level

Balance of trade with member-states

Participation in military alliances.

Economic factors:

National economy structure

Responsibility types and rights of property, incl. for land

Tariffs and taxes

Insurance guarantees

Inflation level and stability of currency

Bank system maturity

Sources of capital investments

Degree of freedom of private business and economic

independence

Market infrastructure maturity

Price level

State of markets: of sales, investments, production means, raw

materials and goods, workforce, etc.

Society – its characteristics and factors:

Conditions and standard of living

Education level

Liberty of movement, “entry-exit”

Labor legislation, ban on strikes

Public health and medicine, rest environment

Public organizations, mass media, TV

Public acceptance of the project

Laws and rights:

Human rights

Right for business activity

Proprietary rights

Laws and regulations on guarantees and privileges

Science and technology:

Fundamental and applied science development level

IT and computerization development level

Industrial and production technology development level

Energetic systems

Transport systems

Communications

Culture:

Literacy level

19

History, cultural traditions, religion

Cultural needs: life support, job, rest, sport, etc.

Level of requirements to labor results and conditions quality

Natural and ecological factors:

Natural and climatic conditions: temperature, precipitation,

humidity, winds, sea level elevation, seismicity, landscape and

topography, etc.

Natural resources

Location and connection with transport networks

Quality standards on: airspace, water sources and top-soil

Sanitary requirements to environment

Law on environmental protection

Characteristics of tendencies and state of ecological systems:

air, water, soil.

Infrastructure characteristics and factors:

Transportation and communication means

Transport of goods

Computer networks and information systems

Power supply

Utilities

Raw materials and services

Sales network

Logistics and procurement

Industrial infrastructure

Support systems, etc.

Near project environment 1. The utility management determines the project goals and main

requirements as well as their adjustment procedure.

2. Financial sphere determines the project budget, its estimate and

sources of financing

3. Sales sphere is determined by customers’ decisions and competitors’

actions

4. Manufacturing sphere demands coordination of the requirements to

the project with the production means market capacities

5. Procurement sphere formulates requirements to the project based on

capabilities to provide with raw and basic materials and equipment at reasonable

prices

6. Infrastructure sphere formulates requirements to publicity, transport,

communications, information support, engineering support

7. Cleaning and utilization sphere formulates requirements to environment

protection and production waste utilization

20

Pic. 6. Utility management overview

Internal environment 1.Managerial style determines psychological climate and atmosphere,

influences creativity and efficiency in the project team.

2.The project specific organization determines relations between the

project main stakeholders, rights, responsibilities and duties allocation and

influences the project implementation success.

3.The project stakeholders realize various interests during project

implementation, formulate their requirements and influence the project in

compliance with their interests, competence and degree of project participation.

4.The project stakeholders’ main interest is connected with obtaining an

income from the project implementation.

5.The project team main interest is connected with obtaining an income of

their activities during the project implementation; the team claim to receive their

part from the reserve fund.

6.Communication methods and means determine completeness, reliability

and efficiency of information exchange between the stakeholders.

7.Project economic conditions determine its main cost characteristics.

8. Project social conditions are characterized by: life conditions; salary

level; public utilities; conditions of work and labor protection; insurance; social

welfare.

21

1.1.3. Project stakeholders

Project stakeholders Project Stakeholders are physical persons and

organizations directly involved in the project or whose interests may be affected

during the project implementation

Pic.7. Types of project stakeholders

1. Initiator – the party that is the author of the project main idea, its

preliminary justification and proposals concerning the project implementation.

Practically, any of would-be stakeholders may act as an initiator but the business

initiative on the project implementation should, ultimately, come from the project

Customer found.

2. Customer – main party interested in the project implementation and

project aim achievement. Would-be owner of the project results. Customer defines

the main requirements to the project, provides for the project financing from its

own or engaged funds, signs contracts with main performers and bears

responsibility for these contracts, manages the interfaces among all the

stakeholders or delegates this function to the main performer, bears responsibility

for the whole project to the law and society, etc.

3. Sponsor – party investing in the project, for example by way of

credits. Sponsors’ aim is to maximize profits for their investments from the project

implementation. If Sponsor and Customer are not one and the same person, then

usually banks, investment funds and other organizations act as sponsors.

4. Project Manager – physical person who is delegated the authorities for

managing all the works under the project: planning, control and coordination of all

the stakeholders’ works. He/she is personally responsible for the project

implementation.

5. Project Team – specific organizational structure, an aggregate of physical

persons and legal entities and their groups united for the purpose of the project

22

implementation. Created for the project implementation period. Project Team main

task - performing all functions of activity coordination and reconciling the

interests of all stakeholders for achieving the project goals.

6. Contractee (General Contractee) – party or project stakeholder who

enters the relations with the Customer and assumes responsibility for performing

works and services under the contract – it may be the whole project or its part.

7. Subcontractee – enters contract relations with Contractee or higher level

Subcontractee. Bears responsibility for performing works and services in

accordance with the contract.

Project Team Typical Organization Chart

Pic.8. Project team typical organization chart

8. Designer – legal entity, performing, under the contract, design and survey

works within the project framework. Enters contract relation with project General

Contractor or directly with Customer.

9. General Contractor – legal entity whose offer was accepted by the

Customer. Responsible for performing works in accordance with a contract. Selects

and signs agreements with subcontractors for performing separate works and

services..

10. Suppliers – subcontractors performing various kinds of supplies on

contractual basis – materials, equipment, transport means, etc.

11. Licensors/Licensing organizations – organizations issuing licenses for

the right of land ownership, bidding, performing specific works and services, etc.

12. Authorities – party, meeting its interests by way of getting taxes from the

project stakeholders, putting and maintaining ecological, social, and other public

and state requirements in connection with the project implementation.

23

13. Land Owner – legal entity or physical person who owns the plot of land

involved in the project.

14. Final Product Manufacturer of the project performs the operation of

created assets and manufactures the final product.

15. Final Product Consumers - legal entities or physical persons who are

buyers and user of the end product, defining the requirements on the product

manufactured and services rendered, forming the demand in them.

16. Public Organizations – layers of population joined by interests.

17. Competitor – party that is always uninterested in the project successful

implementation.

1.1.4. PM organizational structures

General principles of creating PM organizational structures: I. Organizational structure compliance with the system of stakeholders

relations.

II. Organizational structure compliance with the project scope.

III. Organizational structure compliance with the environment requirements.

Organizational structure designing is a complicated, interdisciplinary, poorly

structured and formalized activity.

In this activity, it is possible to highlight several principles the use of which

provides for creating an effective organizational structure of a project.

I. Organizational structure compliance with the system of stakeholders’ relations

1. «Dedicated» organizational structure.

2. «Management by projects».

3. «Overall project management».

4. «Dual» organizational structure.

5. Complex organizational structures:

а) management – customer’s function;

b) management – General Contractor’s function;

c) management – managing company function;

d) management – managing company function, and work performance

is provided by Gen. Contractee (performer).

Pic.9. «Dedicated» organizational structure

24

Pic.10. «Management by projects»

Pic.11. «Overall project management»

Used for internal projects These types of org. structures: «dedicated», «management by projects» and

«overall project management» are used in the following cases:

General contractee of the project is one organization, which takes over the

project management functions and performs the whole scope or main part of

the project executing activities;

Customer, general contractor and investor is one company

These are so-called «internal» projects which are implemented by certain

structural subdivisions of the company for other subdivisions of the same

company.

25

For example, in the project of new product creation:

Customer may be Sales Department,

General contractor — Production and Design Department, and

Investor — Development Dept., or the enterprise as a whole.

Pic.12. «Dual» organizational structure

5. Complex organizational structures: In case when more than two different companies are involved in the project

having different relevant functions in this project, it is possible to implement so-

called «complex» organizational structures of project management having 4

principal variations:

а) project management is implemented by the customer;

b) project management is implemented by general contractor;

c) project management is implemented by a specialized management

company;

d) project management is implemented by a management company,

and work performance is provided by general contractor

Pic.13. а) management – customer’s function

26

Pic.13. b) management – gen. contractor’s function

Pic.13. c) management – management company function

27

Pic.13. d) management – management company’s function, and works are

performed by gen. contractor

Conclusion: The above classification of organizational structure schematics reflects the

effect on the project stakeholders’ interaction system on the project management

structure.

This description highlights «external» connections of the organizational

structure and the project management structure with its stakeholders.

Such description is called «organizational structure schematics» — as

opposed to the organizational structures themselves that are described below from

the point of view of their internal scope.

II. Organizational structure compliance with the project scope Project scope puts requirements on the project optimal organizational

structure from the point of view of the project internal structure, i.e., from the point

of view of division of labor, downloaded in the organizational structure.

Organizational structure classification principles depending on the

project scope 1. vertical (functional-administrative) division of labor (here, not traditional

considering an organization by hierarchical levels is meant, but labor division

depending on participation in various vertical processes of management and

administrative functions) and

2. horizontal (project-target) division of labor (activity structure of an

organization employees depending on their participation in horizontal,

technological processes of work performance is understood)

28

Pic.14. Vertical and horizontal organizational structures

PM organizational structure classification: 1. Functional organizational structures

2. Project -target organizational structures

3. Matrix organizational structures

4. Divisional organizational structures

5. Mixed (hybrid) organizational structures

Pic.15. Functional organizational structures

Project-target structure exists when all the activities of an organization are

focused at executing a specific project, reaching a specific target. Thereby, all other

structural forms are either not presented, or have a support meaning – subdivisions

of headquarters, support subdivisions, committees, etc. Project structures usually

have an explicit border with “parent” organization and interact with it at the

highest level, or function separately from the project stakeholders’ structures.

29

Pic.16. Project-target organizational structures

Though the teams and intermediaries are quite useful and help to settle

drawbacks of functional structures, they are of limited use.

For adequate horizontal integration, vertical functional structure should be

superposed with project-target structure, making, this way, a matrix organizational

structure.

Pic.17. Matrix organizational structures

30

Comparison of project management organizational structures

The following structures may be considered divisional:

structures oriented to client (consumer) type;

Regional organizational structures

Structures oriented to various market sectors.

Pic.18. Divisional organizational structure

5. Mixed organizational structures

31

Pic.19.1. «Partial» matrices

Pic.19.2. Project-functional

Pic.19.3. Project-functional with intermediaries

32

Pic.19.4. Project-functional with teams

III. Organizational structure compliance with the environment requirements

The more flexible and dynamic the outer environment is, the more flexible

and adaptive the project organizational structure must be.

The more stable and predictable the outer environment is, the more

effectively is the use of «rigid», mechanistic, bureaucratic organizations.

Any organizational structure may be implemented in variants having

different possibilities of adaptation. Everything depends on the degree of the staff

activity regulation (quantity and detailing existing rules/procedures of work

performance, business-process description details and organizational behavior) as

well as the degree to which the employees observe this documented order.

This feature may be defined as «structuring level». Various organizational structures in conceptual aspect incline to different

structuring levels, which allows to arrange them in a common «mechanistic —

organistic» continuum.

33

Pic.20. Structuring level: «Mechanistic ↔ Organistic» structure

34

Pic.21. Organizational structure in 2D space «integration direction — structuring

level»

Kinds of project management organizational structures depending on the

project stakeholders’ interrelations, project scope and activity structuring level

Kinds of project management organizational structures depending on the project

stakeholders’ interrelations, project scope and activity structuring level

35

Pic.22. Algorithm of project management organizational structure development

and creation

1.1.5. Project structures

Project Structure – project element composition and their interconnection.

The Project structure is a well-shaped hierarchical project decomposition

into constituent parts, necessary and sufficient for efficient planning and

monitoring of the project progress.

The project structure should comply with the following rules:

1. The complex of elements of each level of the project decomposition

hierarchy should represent the project as a whole. The decomposition

levels differ in the level of detail;

2. Based on the first rule, the total values of the project characteristics

(scope of work, cost, required resources, number of performers, etc.)

at each level of the project structure should coincide;

3. The lower level of the project decomposition should contain such

work elements based on which the values of work characteristics can

be determined that will be necessary and sufficient for the project on-

line control.

Based on the project detailed data, one can obtain aggregated data for any

level of the project structure.

Project structure Structure – is, first of all, links, and then the project

36

composition

The number of project structural model levels is not more than 8

Pic.23. Overall project structure diagram

The lower detalization level in the project hierarchy is called Work

Breakdown Structure (WBS)

Types of project structural models 1. The model meeting the hierarchy conditions, ranking and resources is

called a goal tree

2. The project organization structural chart is called an organization tree

3. Based on the project structural model and the organization tree, a

matrix of responsibility allocation is created

4. Based on the project structural model, the goal tree, the organization

tree and the matrix of responsibility allocation, a project network model is built

37

5. Based on the project structure and project element cost data, a cost

tree is created

6. The project procurement structural diagram is called a project

resource tree

7. The aggregate of negative event probabilities during the project

implementation is described with a risk tree

Pic.24. Types of project structural models

Goal tree. 1.A hierarchical chart meeting the following requirements:

Hierarchical pattern; Ranking; Resources.

38

Pic.25. Goal tree

2. The project organizational chart is called organization tree

Pic.26. Organization tree

3. Based on the project structural model and the organization tree, a matrix of responsibility allocation is built

39

I – autocratic decision; ! – personal liability; D – participation in a collegial

decision w/out power to sign; P – planning; О – organization; C – control; Т –

performing.

Matrix of responsibility allocate

4. Based on the project structural model, the goal tree, the organization tree and the matrix of responsibility allocation, a project network model is built

Pic.27. Project network model

40

5. Based on the project structure and project element cost data, a cost tree is created

Pic.28. Cost tree

6. The project procurement structural diagram is called a project resource tree

Pic.29. Project resource tree

7. The aggregate of negative event probabilities during the project

implementation is described with a risk tree

41

Pic.30. Risk tree

1.1.6. Project life time

Pic.31. Typical example of costs and engaged staff number during the project life

cycle

42

Pic.32. Usual phase sequence in the project life cycle

Pic.33. Relations among project and product life cycles

Pic.34. Interfaces among project stakeholders and the project

43

Pic.35. Complete set of the project development steps makes a whole life cycle

Pic.36. Project Life Cycle Phases

Life cycle

• Life cycle consists of phases.

• Project phases include stages.

• Project stages consist of steps.

• Project steps include activities (works).

• Works consist of processes

• Processes include procedures

• Procedures consist of operations

• Operations include elements

44

Pic.37. Life Cycles of Organization and Project

Life Cycle Phases of IS

The life cycle first stage is called concept.

The life cycle second stage is called development.

The life cycle third phase is called implementation.

The life cycle fourth phase is called closing (dismantling).

PMIS Creation Project at the Development Phase includes the following

stages:

• Feasibility study - FS,

• Terms of reference -TOR,

• Technical design - TT,

• Working design –WD ,

• Implementation – Imp,

• Functioning analysis –FA.

PMIS Terms of Reference Stage includes the following steps:

• Object preliminary survey, diagram of information flows and information

tables.

• Research and development works, scientific report, IS model.

• Outline design, outline design, modeling results, IS parameters and

characteristics.

• Terms of reference processing, ToR issued in accordance with GOST.

45

Topic 1.2. Project management processes

1.2.1. Project management processes

The principle system model of the project management consists of three

main interconnected units: Management subjects; Management objects;

Management process.

Pic.38. Project Management Systemic Model

Project Processes

Projects consist of processes.

Processes are “series of actions giving a result".

Project processes are performed by people and in general are divided into

two main categories:

1. Project management processes - describe, organize and complete the works

under the project. The project management are applicable to most of the

projects, most of the time.

2. Product-oriented processes – specify and create a project product. The

product-oriented processes a typically defined by a project life cycle for the

project and vary by application areas.

The project management processes and the product-oriented processes

overlap and interact through

For example, the scope of the project aim cannot be defined if there is no

basic understanding how to create a product.

46

Pic.39. Deming Cycle “Plan-Do-Check-Act “

Pic.40. Project Management Processes

47

Pic.41. Compliances between Project Management Processes Groups and Deming

Cycle Elements

Pic.42. Project Management Processes

48

Pic.43. Project Borders

1.2.2. Groups of project management processes

Pic.44. Groups of Project Management Processes

Project management Processes

Process groups Project management processes may be arranged in five groups, one or more

processes in each:

1. Initiation process group – project or phase authorization

2. Planning process group – description and specification of aims and selection

of the best ways from alternative directions of actions, for achieving the

goals the project is undertaken for

3. Implementation process group – coordination of human and other resources

for the purposes of the plan implementation

4. Monitoring and control processes - ensuring the aim achieving, with the aid

of monitoring and measuring the project progress on a regular basis for

determining deviations from the plan and taking corrective actions, if

necessary.

49

5. Completion processes group – formal acceptance of the project or a phase

and its proper completion.

Initiation process group

Planning process group

Monitoring and

control processes

Implementation

process group

Completion

processes group

(arrows show

information flows)

Pic.45. Process groups

Processes of Interaction

Within each group of processes, individual processes are interconnected with

by inputs and outputs.

Based on these connections we can describe each process in their own terms:

• Inputs – documents or documented elements which shall be implemented.

• Tools and methods – mechanisms applied to inputs with the purpose of

creating outputs

• Outputs - documents and documented elements which are results of the

processes.

Groups of Project Management Processes Initiation - authorization of the project or its phase as part of project aim

management.

50

Pic.46. Initiation process group

51

Planning process group

Planning is the most important process in the project because the project

implies the implementation of actions which have been performed earlier.

As a result, there is a relatively large number of processes within this group.

Nevertheless, the number of processes does not mean that the project

management is, primarily, planning – the scope of planning shall be commensurate

to the project goals and the developed information comprehensiveness.

Planning is an ongoing effort within the whole life cycle of the project.

52

Pic.47. Planning process group

Main Processes A number of planning processes have clear dependencies which require

performance in a specified order in most projects.

For example, works should be determined prior to scheduling or their cost

estimation.

These main planning processes may be repeated several times at any phase

of a project.

They include:

• Goal planning – development of a written approval of goals as the basis for

further project solutions.

• Goal determining – dividing the main jobs under the project to smaller,

easier controllable components.

• Work determining – identification of specific works to be performed with the

aim of creating various products under the project.

• Work sequence – identification and documentation of interactive

dependencies.

• Work duration assessment – evaluation of the number of work periods

necessary for individual jobs completion.

• Scheduling – analysis of work sequence, work duration, and resource

requirements with the aim of project schedule developing.

• Risk management planning – decision concerning the approaches to be used

for risk management in the project/

• Resource planning – determining the resources (staff, equipment, materials,

etc.) to be used to perform the works under the project.

53

• Cost assessment – development and assessment of the resources required

forthe completion of works under the project.

• Budgeting – allocation of all cost assessment to individual works.

• Project plan development – obtaining the results from other planning

processes, with further placing them into a logically consistent document.

Additional Processes Interrelation among other planning processes are more dependent on the

project nature.

For example, in a number of projects they can be insignificant or non-

recognizable risks up to the completion of planning, and the team realizes that the

cost and schedule goals are exceptionally aggressive and involve significant risks.

In spite of the fact that the additional processes are performed periodically

and on an as-needed basis, they should not be considered optional.

They include:

Quality planning – identification of quality standards corresponding to the

project and how they could be met.

• Organizational planning – identification, documenting, and determining the

roles, responsibilities, and reporting under the project.

• Team selection – selection of human resources required for the work under

the project/

• Communication planning – determining the informational and

communication needs of the project participants: who and to what extent

will need information (and what kind of information), and in what way it

will be received.

• Risk identification – determining risks which normally affect the project, and

documenting characteristics of each risk.

• Risk quality analysis – performing a quality analysis of risks and

determining the rating of their impact to the project goals.

• Risk quantity analysis – measuring a probability and impacts of risks and the

evaluation of their impact to the project goals.

• Risk response planning – developing procedures and methodologies for

increasing the possibilities and reducing dangers for the project goals from

risks.

• Procurement planning – determining of what, how much and when to

deliver.

• Proposal planning – documenting product requirements and identification of

potential sources.

54

Implementation process Group

Pic.48. Implementation process Group

Implementation processes include main and additional processes:

• Project plan implementation – implementation of the project plan by

executing the works included in it.

• Quality guarantee – assessment of the project general efficiency on the

regular basis for ensuring that the project will meet corresponding quality

standards.

• Team development – development of individual and team skills/

competences for the project efficiency enhancement.

• Information distribution – making accessible the information necessary for

the project participants on a regular basis.

• Proposals – receiving corresponding prices, costs, offers or proposals.

• Source selection – selection among potential suppliers.

• Contract administration – managing the interrelations among suppliers.

55

Monitoring and control process group

Pic.49. Monitoring and control process group

Project effectiveness should be controlled and measured on regular basis

with the aim of identification of deviations from the plan.

Deviations may be inside control processes in various areas of knowledge.

When significant differences are found the plan specification can be

performed as a repetition of corresponding processes of the project planning.

For example, an erroneous date of work completion may require

specification of the current plan, overtime works, or a solution on alternatives

between the budget and schedule aims.

Controlling also includes the performance of preventive actions for

preventing possible problems.

Controlling process group includes main and additional processes:

• Control changes of goals – controlling changes in the project goals.

• Schedule control – controlling changes in the project schedule.

56

• Cost control – controlling changes in the project budget.

• Quality control – monitoring specific project results, with the aim of

determining their compliance with quality standards and identification of

ways of eliminating causes of unsatisfactory characteristics.

• Report on efficiency – collection and distribution of on the information on

the performance. It includes the state report, progress determining, and

forecast.

• Risk monitoring and control – following up the identified risks, monitoring

residual risks and identification of new risks, provision of risk plan

execution and evaluation its effectiveness for risk reduction.

Group of completion processes

Pic.50. Group of Completion Processes

Following main processes:

• Contract close-out – close-out and remuneration for the contracts including

the settlement of any open items.

• Administrative close-out – creation, collection, and distribution of

information for formalizing a phase or a project including the project

evaluation and lesson learned for using in future projects or phases

57

Pic.51. Interaction of Process Groups in the Project

58

59

1.2.3. Processes in the area of project management knowledge

Pic.52. Project management overview

60

Pic.53. Project integration management overview

61

Pic.54. Project scope management overview

62

Pic.55. Project time management overview

63

Pic.56. Project cost management overview

64

Pic.57. Project quality management overview

65

Pic.58. Project human resource management overview

66

Pic.59. Project communication management overview

67

Pic.60. Project risk management overview

68

Pic.61. Project procurement management overview

69

1.2.4. Process interfaces

Product-Oriented Processes

Pic.62. Classifier of the Project Final Goals (Products)

Pic.63. Classifier of the Project Final Goals (Products)

Classifier of the Project Life Cycle Phases

Pic.64. Project Implementation Life Cycle

70

Informational Processes

Project management processes acc. to knowledge areas

Pic.65. Knowledge areas

71

Pic.66. Project management areas

Classifier of Project Management Life Cycle

Initiating

processes

Planning

processes

Monitoring and

control processes

Executing

processes

Closing

processes

(arrows show

information flows)

Pic.67. Project management lifecycle

72

Pic.68. The Deming Cycle

Project Management Process Classifier

Pic.69. Project management process classifier

73

Pic.70. Classifier of “Integration Management” Process

Belonging to “Initiation” process group

74

Pic.71. Structure of Information on a Project. Main equipment

Pic.72. The Deming cycle and project life cycle

75

Topic 1.3. Project risk management processes

1.3.1. Risk identification

Project management place in decision making cycle

Pic.73. Project management place in decision making cycle

Decision making is performed:

o In the conditions of certainty

100% certainty of an event occurrence

Exact plans, effective solutions

«certain uncertainty»

o In the risk conditions

the probability of an event occurrence as well as its influence to the

project is known

«certain uncertainty»

o In the conditions of certainty

The probability of an event occurrence is unknown, and

The event itself is not determined

«uncertain uncertainty»

Company risk management is aimed at maximization of condition certainty

at making decisions.

Notions: Risk and Project Management

76

Pic.74. Risk and Project Management

Risk – a value of possible losses/ profits in case of a risk event occurrence

Risk management – aggregate methods, techniques and measures allowing to

predict the risk event occurrences and take measures to their preclusion or

reduction of such event negative consequences

In the design activity interior and exterior environment, there always exist

causes (risk sources) that can lead to an undesirable event occurrence

(occurrence possibility), which can have a negative impact on an activity

results (possible loss size).

Risk management is aimed at the minimization of losses due to an

undesirable event.

The basis for risk management decision making is risk assessment –

characteristics showing how the risk extent is connected with the probability

of the undesirable event occurrence, which causes this loss.

Classification of Causes of Negative Event Occurrence

77

Pic.75. Causes of project risk occurrence

Characteristics of Negative Events

Characteristics of Loss Extent

78

Risk Management Processes in accordance with PMBoK

Pic.76. Risk Management Processes in accordance with PMBoK

1. Selection of an approach, planning and performing project risk

management operation

2. Determining what risks can influence the project, and documenting their

characteristics.

3. Risk arrangement in accordance with their priority for further analysis and

summing up the probability of their occurrence and influence to the project.

4. Qualitative analysis of identified risk potential influence to the project

general goals.

5. Developing possible variants and actions contributing to the enhancement

of favorable possibilities and decreasing dangers for the project aims achievement.

6. Following up the identified risks, monitoring residual risks, identification

of new ones, performing risk response plans and their efficiency assessment

during the whole life cycle.

79

Express-Assessment of Negative Event Occurrence Risk

Risk express-assessment is based on the calculation and assessment of risk

index

Risk index us an indicator of possible loss sizes in the points defined by

"Probability - Loss" Matrix.

R = Pq * Iq where R – risk index (points);

Pq - risk occurrence probability, in accordance with classification (points);

Iq - loss size, in accordance with classification (points).

Risk Index Evaluation

Risk evaluation – decision on the risk influence level and degree, taken on

the basis of risk index analysis.

Risk evaluation technique with the help of risk index R is as follows :

"Probability - Loss" Matrix

Losses

Pro

bab

ilit

y

80

Project Risk Management Techniques

Main methods of:

1. integrated

2. continuous, and

3. extended management

Pic.77. Specific Risks of Project Implementation

81

Schedule Risk Management 1. Works with unknown durations

Event 1. failure to meet the work completion

dates because the performers lack

experience in such work performance.

The main problem in such task planning

is that their duration is not known in

advance as there is no experience in

their performance

Management method 1. It is recommended to change the

project plan in such a way that the

duration prolongation should not tell on

the project completion deadline or

important stages/works completion

deadlines. It would be desirable to

extend the planned duration of these

works to pessimistic values and

calculate the plan taking into account

this duration upgrade. In addition, it is

possible to include additional work for

employees' training to the work

schedule prior to performing works with

unknown duration.

82

2. Works with unknown durations

Event 2 . failure to meet the work completion

dates because the performers lack

experience of performing new/similar

works or because of too optimistic

assessment of the work duration by the

performer.

Similar situation may arise due to

Project Manager fault, assigning

as much time for the work

performance as he thinks fit

(based on the project time

restriction) without asking advice

of a performer.

Management method 2. It is recommended to perform an

analysis of all works from the schedule

that have an unreally short duration. If

works are found in the plan that have

unreasonably short terms, then such

works' duration should be additionally

discussed with would-be performers

Mandatory agreeing the terms

based on the work performance

duration calculation made by the

performer, is recommended

3. Works with unknown durations

Event 3. failure to meet the work completion

dates. Cause – presence in the schedule

of too long works due to their poor

detailing. Without the work detailing, it

is difficult to estimate the labor cost of

such works and possible resource

loading; therefore, the inclusion of works

with long duration to the work schedule

leads to the increase of a possibility of

their completion deadline failure

Management method 3. It is recommended to screen out

works with large duration and detail

them

4. Works with a large amount of resources

Event 4. failure to meet the work completion

dates. Presence of works too

complicated and requiring a lot of

resources in the schedule occurs due to

their poor detailing. Without the work

detailing, it is difficult to estimate the

labor cost of such works and possible

resource loading; therefore, the

inclusion of works requiring a lot of

resources to the work schedule leads to

the increase of a possibility of their

completion deadline failure.

Management method 4. It is recommended to screen out

works with large duration and detail

them

5. Works with a large amount of dependencies

83

Event 5. failure to meet the work completion

dates. The more dependencies a work

has, the higher the risk is that its

performance will be delayed because

one of its predecessor works is not

completed in time. It is especially

dangerous if a job on the critical path

has several predecessors

Management method 5. It is possible to mitigate risks by

increasing scheduled duration of one or

more predecessor works due to their

earlier beginning (if possible).

To decrease the risk by way of planned

duration of task increase if the project

duration restriction allow to do that

6. Works with a external dependencies

Event 6. failure to meet the work completion

dates. Works may depend on events

external to the project, which do not use

project resources and are not subject to

planning.

Management method 6. It is recommended to perform such

work analysis and include in the

"Project Risk Response Plan" measures

to mitigate the impact of such risks to

the project

Control of Resource risks 1. Use of inexperienced employees

Event

1. Involvement of a recently hired

employee (without experience of using

him) increases the risk of failure of

performance time, since it is unknown

whether it can cope with the tasks.

Management method

1. It is necessary to determine works

where inexperience employees are

engaged and describe the risks of their

use. Perform the analysis and mitigate

the risk, e.g., by extending such works

duration

2. Resources with overtime job

2. Failure to meet work completion date

due to employees' fatigue

2. Decrease of overtime work share by

way of working time shift, increase of

work efficiency, informational support

level, and engaging additional resources

3. Employees with unique skills

Event

3. Use of an employee having unique

skills may lead to the project failure in

case the resource becomes unavailable

(illness, firing)

Management method

3. Defining the list of employees with

unique skills, determining a risk level,

and developing measures for its

minimization to be included in "Project

Risk Response Plan"

4. Materials with single suppliers

4. Material supply from the only source 4. Defining a list of unique suppliers,

84

may cause a failure of the project dates

due to supply delays

determining a risk level, and developing

measures for its minimization to be

included in "Project Risk Response

Plan"

Budget Risk Management 1. Increase of some work scope

Event 1. Due to an unfavorable set of

circumstances (implementation of a risk

event) a project work (a number of

works) scope may increase, which will

cause cost growth

Management method 1. Forming a risk fund within the project

budget. Use the Company risk fund

2. Increase of work duration

2. If the work cost is proportional to

their duration, the increase of work

performance will lead to the

proportional increase of the project cost.

2. Forming a risk fund within the project

budget. Use the Company risk fund

Project Risk Monitoring Actions for risk monitoring and control include:

1. Generating and analysis of reports on identified risk management.

2. New risk identification

3. Project stakeholders' regular meetings on risk management.

Aims of the meetings are :

1. "Project Risk Response Plan" execution analysis.

2. Verification of known risk relevance.

3. identification of new project risks.

4. Planning in-depth analysis of certain risks in connection with new

circumstances.

5. Correction of plans for various risks response.

6. Developing variants of new risk responses.

7. Developing and approval preventive actions for avoidance/ minimization of

risks

Results of the project risk monitoring and control measures are as follows:

1. Solutions on corrective actions concerning risks.

2. Solutions/requests on project changes.

3. Solutions on non-scheduled works as measures of risk response.

4. Solutions on reserve use.

5. Addition to the identified risk list.

85

6. Solutions on risk priority changes.

7. Solution on risk new or repeated analysis.

8. Solution on "Project Risk Response Plan" change

9. Supplementation of a risk database

86

Topic 1.4. Project management information system (PMIS)

1.4.1. PMIS configuration

IS Scope One of the main IS properties is the possibility to divide it to subsystems,

which has a number of advantages, from the point of view of its development and

operation, including:

– Simplifying the IS system development and upgrading as a result of

developer groups specialization in subsystems;

– Simplification of produced subsystems introduction and supply in

compliance with the work performance sequence;

– Simplification of IS operation due to specialization of a subject area

workers.

Usually, functional and support systems are highlighted.

Functional subsystems of an IS provide information for certain activities of

an economic system (enterprise) characteristic for this economic system structural

subdivisions and (or) management functions.

The integration of functional subsystems into a united system is reached

through the creation and functioning of support subsystems, such as informational,

program, mathematic, technical, technological, organizational and legal, and HR

subsystems.

IS Functional Subsystems IS functional subsystem is a set of economic tasks with a high degree of

information exchanges (links) among the tasks.

Functional subsystem scopes are to a great extent determined by an

economic system features, its industry classification, form of ownership, size,

enterprise activity nature.

IS functional systems may be built on various principles:

– subject;

– functional;

– problematic;

– mixed (subject-functional)

Solution of Functional Subsystem Tasks

Management

levels

Functional subsystems

Marketing Production Logistics Finance

Strategic New products

and services.

Research and

development

Production

capacities.

Selection of a

technology.

Material

sources.

Commodity

forecast

Financial

sources.

Selection of

tax payment

model.

87

Tactical Sales

quantities

analysis and

planning

Production

programs

analysis and

planning

Purchase

quantities

analysis and

planning

Cash flow

analysis and

planning

Operative Clients’ orders

processing,

invoicing and

billing

Production

orders

processing

Warehouse

operations .

Purchase

orders

Book-

keeping

IS Structure acc. to Functional-Subject Principle

Pic.78. IS Structure acc. to Functional-Subject Principle

88

IS Support Subsystems

Pic.79. IS Support Subsystems

IS Functional Structure

89

IS Informational Support

IS Mathematic Support

90

IS Technical Support

IS Organizational Support Organizational support (OS) is an aggregate of means and methods of

production organization and management in the context of an IS introduction.

Aim of the organizational support is :

• Selection and setting management tasks;

• Analysis of the management system and ways of its upgrading;

• Developing solutions on the IS - personnel interface;

• Management tasks introduction.

The organizational support comprises work performance methodologies,

requirements on documentation processing, job descriptions, etc.

Staffing Support • staffing support is a set of means and methods for personnel organization

and training in the work with IS.

• Aim of the staffing support is the support of the IS operability and the

possibility of its further development.

The staffing support comprises:

• training plan and training session schedule;

• work programs for the disciplines learned;

• methodological support in the form of textbooks, books of tasks, etc.;

• text programs for lecture courses and practical lessons;

• technical aids for training and their operation manuals, etc.

91

IS Linguistic Support

IS Process Support Process support (PS or EDP – Electronic Data Processing) of an IS

corresponds to the IS division to subsystems by process stages of various

information types processing:

– Initial information;

– Organizational and directional documentation;

– Process documentation and drawings ;

– Data bases and knowledge bases;

– Scientific and technical information, GOSTs and technical conditions,

legal documents and files.

EDP of developed IS’s includes subsystems:

1.OLTP (On-Line Transaction Processing);

2.OLAP (On-Line Analytical Processing).

OLAP-technologies provide:

– Data analysis and modeling in on-line mode;

– Work with subject oriented data storages (DS)

– Implementation of free-hand enquiries,

Formation a subject area knowledge system, etc.

IS creation Process Information system creation process is described with the following

hierarchy:

• Life cycle,

• Phases,

92

• Stages ,

• Steps,

• Works,

• Processes,

• Procedures,

• Operations

• Elements.

Company introducing project management methods and means should:

• Rearrange the company organizational structure;

• Develop and approve procedures of business-processes of project

management in the company;

• Develop a set of scientific and technical documents (regulations);

• Carry out training of project managers and work group members.

• Perform the project management in PMIS only

• Introduce an effective control system for project planning and support.

Project management is efficient if:

– Business-process descriptions are relevant;

– Documentation support is relevant;

– Strict control of adherence to standards is performed;

93

– Managerial effect by the control results is effective and inevitable;

– Company staff undergoes regular training and certification;

– Project management is a fundamental principle;

Project Management Office Functions

• Methodological — upgrading PMIS use;

• Analytical — project planning and implementation efficiency

analysis;

• Archive — information storage;

• Infrastructural — PMIS process control;

• Control — project and resource pool monitoring;

• Communicative — information exchange among the stakeholders

PMIS Tasks

• Developing a schedule of project implementation without taking into

account resource limitation;

• Developing a schedule of project implementation taking into account

resource limitation;

• Determining a critical path and time reserves of project operation

performing;

• Determining project demand in financing, materials and equipment;

• Determining the distribution in loading time of renewable resources;

• Analysis of risks and schedule planning taking the risk into account;

• Project performance accounting;

• Analysis of work performance progress deviations from the planned

progress and prediction of the project main parameters.

PMIS Features

• Function distribution by roles;

• Hierarchical structures support;

• Control of resource limitation in multi-project environment;

• Information exchange in real time mode;

• Visualization of information presentation;

• Readiness to integration (1с, AtomSmeta, CAD systems…)

Known Systems

• MS Project Professional (developed by Microsoft)

• Time Line (developed by Time Line Solutions)

• Primavera Project Management (developed by Primavera inc.

representative in Russia – PM SOFT)

• Open Plan - developed by Welcom Software Technology

• Spider Project (developer representative in Russia – “Spider Management

Technologies” company

PMIS provides for:

• Developing basic calendar plan of the project.

94

• Developing alternative calendar plans of the project (”what if”)

• Input of actual information on the project progress

• Control of project planning and executing progress.

• Visual comparing of actual work schedule with the basic plan

• Project plan Corrections.

• Maneuver of resources.

• Possibility of remote access of managing projects to PMIS project base.

• Control of the involved resources loading.

• Keeping an electronic file of the project and forming the project reporting

system.

Pic.80. PMIS Scope and Structure

95

Understanding a project as a structured (informational) object complying

with logical arguments and formal rules, is the basis for project management

professional methods.

96

1.4.2. PMIS based on Oracle Primavera software

Pic.81. Resources and activities intreraction

Structures

Pic.82. Project structures

97

Project documents

Pic.83. Project documents

Project documents (any files and references)

Pic.84. Project documents (any files and references)

98

Structure of projects

Pic.85. Projects structure

Pic.86. Resources structure

99

Pic.87. WBS structure

Activiries of the project

Pic.88. Activities of the project (MS Project)

100

Pic.89. Activities structure

101

Pic.90. Projects, WBS, activities and resources hierarchies

Control by projects

• Unit of control by PMIS means;

• Any design data in specialized reports;

• Any degree of detailing;

• All data in one base => trust to the data;

• "Semaphores" for managers

Notifications on the indicators

102

Variants of project plan execution progress control:

Pic.91. Variants of project plan execution progress control

103

Report forms

Pic.92. Reports

104

Pic.93. Project indicators setup window

1.4.3. PMIS organizational support

Templates of PMIS Managerial Documents Files of templates for PM.

Sets of templates included in compound documents described in PMBOK:

1. Initiation documents,

2. Project documents,

3. Scope basic plan,

4. Project management plan,

5. Basic execution plan,

6. Project schedule,

7. Schedule data ,

8. Human resources management plan,

9. Procurement documents.

PM knowledge areas.

Sets of templates for 9 knowledge areas described in PMBOK:

1. Project integration management,

2. Project scope management,

105

3. Project time management,

4. Project cost management,

5. Project quality management,

6. Project human resources management,

7. Project communication management,

8. Project risk management,

9. Project procurement management.

Project management processes.

Sets of templates for 5 main PM processes:

1. Initiating processes,

2. Planning processes,

3. Executing processes,

4. Monitoring and controlling processes,

5. Closing processes.

Pic.94. PMBoK usage

106

Pic.95. PMIS documentation scope

107

Topic 1.5. NPP construction time management

1.5.1. Managerial structure

The role structure of schedule development organization is meant to

illustrate the main interfaces during the schedule development and updating.

• Below one can find brief descriptions of the role structures of the Customer-

Developer and General Contractor respectively as well as description of

basic business- processes of schedule development and updating conditional

upon their filling with current and reliable data in the shortest time.

• The Customer-Developer/ General Contractor interaction procedure during

Level 3 schedule development and correction is considered; a list of

documents to be developed or corrected by the Customer-Developer or

General Contractor as appropriate in order to provide for the efficient

application of Level 3 schedule as an NPP construction project management

tool.

Customer-Developer’ role structure

Customer-Developer’s main internal role groups • Customer-Developer’s management (NPP construction project general

management on the part of the Customer-Developer),

• Customer-Developer’s PMO (Support of NPP construction project schedule

development methodology based on Primavera, control of schedule

development and updating by General Contractors, supply of report forms

on up-to-date schedules to the NPP construction project manager, delivery of

108

schedule reports to other Customer-Developer’s services),

• NPP construction project manager on the part of Customer-Developer (NPP

construction project day-to-day management on the part of the Customer-

Developer, organization of interaction with other Customer-Developer’s

services).

Role of an NPP construction project manager on the part of Customer-Developer

An NPP construction project manager on behalf of the Customer-Developer

has the following responsibilities in the process of an NPP construction project

schedules:

1. NPP construction project schedules development control.

2. NPP construction project schedules coordination with the General

Contractor and the Customer-Developer’s management.

3. Making decisions on NPP construction project schedules amendment.

4. Approval of a Report on risks and problems to be laid before the

management which should be documented.

5. Arrangement of an informational exchange with the Customer-Developer’s

services.

6. Control of information publication and dissemination based on NPP

construction project schedules.

Role of the Customer-Developer project management office manager An NPP construction project office manager on behalf of the Customer-

Developer has the following responsibilities in the process of an NPP construction

project schedules development and updating:

1. NPP construction project schedules development coordination.

2. Management of support and development of the uniform NPP construction

project schedule development methodology based on Primavera.

3. Check of the schedules received from the General Contractor for compliance

with the requirements of the uniform NPP construction schedule

development methodology based on Primavera.

4. Regular analysis of an NPP construction project current state on the basis of

the up-to-date schedules.

5. Preparation of decisions on NPP construction project schedules amendment.

6. Coordination of reports preparation on the basis of NPP construction project

schedules in compliance with the standard accepted by the General

Contractor and also with the Government Contract requirements.

7. Supporting the NPP construction project schedules handover from the

General Contractor to the Customer-Developer in line with the procedure

approved by both parties.

109

Role of a Customer-Developer Methodologist The Methodologist of the Customer-Developer has the following

responsibilities in the NPP construction project schedules development and

updating :

1. Support and development of the uniform NPP construction project

schedule development methodology based on Primavera.

2. Quality control of the schedule development by both the Customer-

Developer and General Contractor specialists.

Role of the Customer-Developer’s Planner The Customer-Contractor Planner has the following responsibilities in the

NPP construction project schedules development and updating :

1. Interaction with the Customer-Contractor methodologist in the area of the

NPP construction project schedules development.

2. Making amendments in the schedules based on the current information.

3. Preparation of reports on the basis of NPP construction project schedules in

compliance with the NPP construction project schedule development

methodology based on Primavera and also with the requirements of the

Customer-Contractor management and the NPP construction project

manager from the Customer-Contractor.

General Contractor’s role structure

General Contractor’s main internal role groups • The General Contractor management (Overall NPP construction project

110

management by the General Contractor),

• The General Contractor project management office (PMO) (Support of the

NPP construction project schedule development methodology– supplements

to the Governmental Contract, schedule development and updating

organization, interaction with the Customer-Developer services in charge of

the NPP construction project schedules on the part of the Customer-

Developer),

• Engineering&Design (EAD) unit (Implementation of design and engineering

work),

• Material and Technical Resource delivery unit (Implementation of material

resources procurement),

• Construction&installation unit (Implementation of construction and

installation operations - CIO),

• Commissioning unit (Implementation of commissioning work),

• Control unit (Regular delivery of current data on the works in progress).

Explanatory notes to the diagram • In each role group, the roles of the schedule development and updating

process participants are emphasized.

• Temporary work groups (teams) routinely organized for the development of

the schedule various parts for various periods of Level 3 schedule life cycle,

are highlighted in color.

• The development team consists of a PMO representative (methodologist in a

work stream) and representative(s) of a functional unit responsible for the

work stream.

• The functional unit representative provides the initial data and enters them

into CNP, and the methodologist of a work stream coordinates this work,

recommends using the most suitable for the current situation methods and

means and also controls the work implementation in compliance with the

existing standards.

Role of an NPP construction project manager on behalf of the General Contractor

An NPP construction project manager on behalf of the General Contractor

has the following responsibilities in the process of an NPP construction project

schedules development:

1. NPP construction project schedules development control.

2. NPP construction project schedules coordination with the General

Contractor Management.

3. NPP construction project schedules coordination with the Customer-

Developer on demand or by the General Contractor Management

order.

4. Making amendments in the schedules based on the current

111

information.

5. Bringing up at the General Contractor and Customer-Developer

management level of problems and risks associated with the NPP construction

project schedules implementation, if such cannot be eliminated by the General

Contractor himself. The report on risks and problems to be laid before the

management should be documented.

6. Control of information publication and dissemination based on NPP

construction project schedules.

Role of the General Contractor project management office manager An NPP construction project office manager on behalf of the General

Contractor has the following responsibilities in the process of an NPP construction

project schedules development and updating:

1. NPP construction project schedules development coordination.

2. Management of support and development of the project management

standard accepted by the General Contractor .

3. NPP construction project schedules coordination with the NPP construction

project manager from the General Contractor.

4. Coordination of a regular analysis of an NPP construction project current

state on the basis of the up-to-date schedules.

5. Preparation of decisions on NPP construction project schedules amendment.

6. Coordination of reports preparation on the basis of NPP construction project

schedules in compliance with the standard accepted by the General

Contractor and also with the Governmental Contract requirements.

7. Supporting the NPP construction project schedules handover from the

General Contractor to the Customer-Developer in line with the procedure

approved by both parties.

Role of a Methodologist of a work stream The Methodologist of a work stream has the following responsibilities in the

NPP construction project schedules development and updating :

1. Interaction with the specialists of the functional units in the area of the NPP

construction project schedules development for his work stream.

2. Development of methods and means mostly appropriate for the work with a

schedule for his work stream, and training of the functional unit specialists

in their application.

3. Quality control of the schedule development by the functional unit

specialists.

4. Regular analysis of an NPP construction project current state on the basis of

the up-to-date schedules for his work streams.

5. Work cost expertise in case of the working documentation unavailability.

112

Role of a General Contractor Planner The General Contractor Planner has the following responsibilities in the NPP

construction project schedules development and updating :

1. Interaction with methodologists of work streams in the area of the NPP

construction project schedules development in terms of mutual agreement of

a work stream schedules.

2. Making amendments in the schedules based on the current information.

3. Compilation of reports on the basis of NPP construction project schedules in

compliance with the standard accepted by the General Contractor and also

with the Government Contract requirements.

Role of a Specialist of a work stream The Specialist of a work stream has the following responsibilities in the NPP

construction project schedules development and updating :

1. Interaction with a methodologist of a work stream in the area of the NPP

construction project schedules development for his work stream.

2. Filling of the NPP construction project schedules with data relevant for his

work stream.

Role of a Work Supervisor The Work supervisor has the following responsibilities in the NPP

construction project schedules development and updating:

1. Regular delivery of reports on Level 3 schedule work completion in the

format accepted by the General Contractor.

1.5.2. Development of 1st level schedules

Schedule levels

113

Pic.96. Schedule levels

Level 1 schedule

1.Purpose

• Provide State Customer and Customer-Developer with actual and

trustworthy summary information on the NPP unit construction project

current status for making decisions concerning required time for reaching

key milestones of the project

• Provide visual presentation of the NPP unit construction project at the

meetings of State Customer and Customer-Developer

• Provide the Federal Target Program (FTP) actual condition

2. Scope

• WBS in accordance with the overall summary estimate (OSE) structure and

operational control (OC) objects.

• Works, describing global kinds of work for each OC object construction

from the point of view of each global work commencement and completion

and cost in basic and current process

• Milestones of the NPP unit construction project described in State Contract

used to control the project current status to control the State Contract

conditions observing by the Parties

3. Basic work definition

Work is an aggregate of interconnected actions belonging to one global

work for OC object construction:

114

• characterized by the cost in basic and current prices,

• the cost of which can be unambiguously attributed to one cost item -

construction and installation operations (CIO), Equipments, or Other.

4.Users

Management and members of headquarters and meetings at the State

Customer and Customer-Developer level

5. What can be controlled

• Planned and actual terms of achieving all milestones in the NPP unit

construction;

• Planned and actual terms of beginning and completion, sequence of

performing global works for each OP object construction;

• Planned and actual cost of global works for each OP object construction in

basic and current prices.

6.Planning period

• Level 1 schedule is developed once for the whole NPP unit construction

period

• Permitted tolerance of determining the dates for separate operations

commencement and completion is 6 calendar weeks

7.Actualization period

• Monthly after the Level 3 schedule actualization

In case the Level 3 schedule is unavailable or incomplete the Level 1

schedule may actualized based on the 2nd

level schedule or based on expert

judgment.

8. Life cycle

• The first version of the Level 1 schedule is developed by General Contractor

on the basis of rules and standards and expert judgments and submitted to

State Customer and Customer-Developer within the scope of Technical

Design.

• The second version of the Level 1 schedule is developed by General

Contractor on the basis of the Level 3 schedule after State Contract

conclusion whereupon it is submitted to Customer-Developer.

• The Level 1 schedule is actualized by Customer-Developer based on the

Level 3 schedule information.

9. Introduction of changes

• Changes to the Level 1 schedule are introduced on the basis of decisions

made by headquarters and meetings of the State Customer and Customer-

Developer level

• Changes to the Level 1 schedules are introduced by the Customer-Developer

employees on the basis of the Level 3 schedule data.

115

116

Pic.97. Level 1 schedule

1.5.3. Development of 2nd level schedules

Level 2 schedule

1. Purpose

• Ensure timely planning and executing subject tasks within the framework of

NPP unit construction project in case of the Level 3 schedule unavailability.

2. Scope

• WBS in accordance with the requirements of each part of the OC object

construction sub-project and for each kind of activities.

• Works, describing:

– contractor organizations’ on-site activities in terms of commencement

and completion terms, cost in basic and current prices, contractor

organizations’ profile, physical amounts in accordance with individual

requirements to each operation and each activity,

– list of WD sets and terms of its issuance and approval to provide for

CIO executing,

117

– scope and terms of commissioning documentation (CMD) issuance to

provide for operations for the power unit commissioning,

– terms of MTS delivery to ensure the CIO executing. Special attention

to be given to prolonged manufacturing cycle (PMC) and top-priority

deliveries

• NPP unit construction milestones

Dependencies among operations.

3. Basic CIO definition

CIO in part of main buildings and structures is an aggregate of interrelated

operations for the construction and/or finishing of building structures:

– performed continuously throughout the period limited by

commencement and completion dates,

– belonging to one type of work,

– aimed at achieving a result measured by one physical amount

corresponding to the work type,

– characterized by one profile of a contractor company,

– performed by one contractor company with a corresponding profile,

– performed in accordance with the requirement of one set of drawings,

– cost of which is calculated based on one local cost estimate,

– cost of which may be unambiguously attributed to the CIO cost item.

CIO in terms of auxiliary buildings and structures replicates the 1st level

schedule works.

4. Users

• Administration and subdivisions of General Contractor,

• Direction on Development of Rosenergoatom Concern,

• Rosenergoatom concern subdivisions on construction site,

• Members of headquarters and meetings at the level of State Customer and

Customer-Developer, contractors and suppliers’ administration included

5. What can be controlled

• Planned and actual terms of NPP unit construction project milestone

achievements

• Planned and actual terms of commencement and completion, sequence of

operations in terms of Engineering&Design (EAD), CIO, MTR

procurement (in particular, PMC), Commissioning

• Planned and actual physical amounts in accordance with the list

• Planned and actual cost in basic and current prices

6. Planning period

• Level 2 schedule is developed sequentially along with new information

appearing and/or issuing subject tasks.

• During the first version development , Level 2 schedule in developed in the

scope sufficient for detailed planning of first priority operations and

118

preliminary planning of further operations.

• In the case when necessary initial data are not sufficient during the Level 2

schedule development, the Level 2 schedule may be issued with an

incomplete data set. In this case, General Contractor must provide

Customer-Developer with an official justification of the impossibility to

introduce certain kind of data to the Level 2 schedule, at the current moment

and/or to a preset date, and define the conditions under which this kind of

data can be introduced to the Level 2 schedule later.

7. Actualization period

• Weekly, on the basis of General Contractor on-site supervisor’ s data

• Monthly, based on completed work protocols generated by General

Contractor and approved by Customer-Developer.

8. Life cycle

• Level 2 schedule is developed by General Contractor based on expert

judgment or design and estimate documentation (DED) and specified

throughout its issuing. Each version of the Level 2 schedule is passed over to

the Customer-Developer.

• The Level 2 schedule is actualized by General Contractor employees.

• The actualized Level 2 schedule is passed over to the Customer-Developer

monthly.

• In case of the Level 3 schedule availability, the Level 2 schedule is not

used.

9. Introduction of changes

• Changes to the Level 2 schedule in terms of scope and operation

technological sequence are introduced on the basis of decisions made by

headquarters and meetings of the General Contractor level

• Changes to the Level 2 schedule are introduced by General Contractor

employees on the basis of DED and/or contractor organizations’ data and/or

General Contractor administration decisions

• Changes to the Level 2 schedule must lead to the Level 1 schedule changes

only in accordance with a procedure agreed by State Contract parties. If the

Level 2 schedule changes lead to the Level 1 schedule changes they must be

approved by Customer-Developer

119

Legend

• Colors show temporary working groups (teams) formed on a routine basis

for developing various parts of the schedule in different periods of the Level

3 schedule life cycle.

• A developing team consists of PMO representative ( methodologist for a

certain direction) and a functional unit representative(s) responsible for the

direction.

• The functional unit representative provides initial data and inputs them to

calendar network plan (CNP), and the methodologist for a direction

coordinates this work, recommends the use of the techniques and means

most adequate for the current situation, and controls the work performance

against valid standards.

1.5.4. Development of 3rd level schedules

Level 3 schedule

1. Purpose

• Ensure monthly-weekly planning and controlling of works performed by

companies participating in the project of NPP unit construction

• Provide coordination of activities of the companies participating in the

project of NPP unit construction

• Provide the process of subject planning and reporting with regular and

trustworthy data

120

2. Scope

• WBS in accordance with the requirements of each part of the operational

control (OC) object construction sub-project and for each kind of activities.

• Works, describing :

– contractor organizations’ on-site activities in terms of commencement

and completion terms, cost in basic and current prices, labor efforts,

contractor organizations’ profile, physical amounts in accordance

with individual requirements to each operation and each activity,

– list of WD sets and terms of their issuance and approval to provide

for CIO executing,

– scope and terms of commissioning documentation (CMD) issuance to

provide for operations for the power unit commissioning,

– MTR delivery terms in order to provide CIO execution.

• Milestones of NPP unit construction

• Dependencies among operations.

3. Basic CIO definition

Work is an aggregate of interconnected actions for constructing and/or

finishing building structures:

– performed continuously throughout the period limited by

commencement and completion dates,

– belonging to one type of work,

– aimed at achieving a result measured by one physical amount

corresponding to the work type,

– characterized by one profile of a contractor company,

– performed by one contractor company with a corresponding profile,

– performed in accordance with the requirement of one set of drawings,

– cost of which is calculated based on one local cost estimate,

– cost of which may be unambiguously attributed to the CIO cost item.

4. Users

• Administration and subdivisions of General Contractor,

• Rosenergoatom Concern, Direction on Development,

• Rosenergoatom concern subdivisions on construction site,

• Members of headquarters and meetings at the level of General Contractor,

contractors and suppliers’ administration included

5. What can be controlled

• Planned and actual terms of achieving milestones of the NPP unit

construction project

• Planned and actual terms of beginning and completion, sequence of work

executing in part of Engineering &Design (EAD), construction and

Installation operations (CIO), material and technical resource procurement

(MTR delivery), commissioning works.

121

• Planned and actual labor required for the work execution including those

with the separation to contract companies’ profiles and Contractors

• Planned and actual physical amounts in accordance with the list

• Planned and actual cost of works in basic and current prices

• Actual availability of working forces on site in the previous periods, with

the breakdown for profiles and contractors

6. Planning period

• Level 1 schedule is developed once for the whole NPP unit construction

period and revised sequentially along with DED development.

• When the Level 3 schedule first version is developed, it has a scope

sufficient for detailed planning of the first priority works and preliminary

planning of further works.

• In the case when necessary initial data are not sufficient during the Level 3

schedule development, the Level 3 schedule may be issued with an

incomplete data set. В In this case, General Contractor must provide

Customer-Developer with an official justification of the impossibility to

introduce certain kind of data to the Level 3 schedule, at the current moment

and/or to a preset date, and define the conditions under which this kind of

data can be introduced to the Level 3 schedule later.

7. Actualization period

• Weekly, on the basis of General Contractor on-site supervisor’ s data

• Monthly, based on completed work protocols generated by General

Contractor and approved by Customer-Developer

8. Life cycle

• Level 3 schedule is developed by General Contractor based on design and

estimate documentation (DED) and specified throughout its issuing. Each

version of the Level 3 schedule is passed over to the Customer-Developer

• The Level 3 schedule is actualized by General Contractor employees.

• The actualized Level 3 schedule is passed over to the Customer-Developer

monthly.

9. Introduction of changes

• Changes to the Level 3 schedule in terms of scope and operation

technological sequence are introduced on the basis of decisions made by

headquarters and meetings of the General Contractor level

• Changes to the Level 2 schedule are introduced by General Contractor

employees on the basis of DED and/or contractor organizations’ data and/or

General Contractor administration decisions

• Changes to the Level 3 schedule must lead to the Level 1 schedule changes

only in accordance with a procedure agreed by State Contract parties. If the

Level 3 schedule changes lead to the Level 1 schedule changes they must be

approved by Customer-Developer

122

Legend

• Colors show temporary working groups (teams) formed on a routine basis

for developing various parts of the schedule in different periods of the Level

3 schedule life cycle.

• A developing team consists of PMO representative ( methodologist for a

certain direction) and a functional unit representative(s) responsible for the

direction.

• The functional unit representative provides initial data and inputs them to

calendar network plan (CNP), and the methodologist for a direction

coordinates this work, recommends the use of the techniques and means

most adequate for the current situation, and controls the work performance

against valid standards.

123

124

125

Pic.98. Level 3 schedule

126

Pic.99. Level 3 actualization

Pic.100. General Contractor and Customer-developer interaction process during

change development for level 3 schedule of NPP construction project

127

List of Documentation Necessary for Level 3 Schedule

Customer-Developer’s 1.Regulation on controlling Level 3 schedule changes (as an appendix to the

State Contract)

2.Regulation on Customer-Developer’s PMO

3.Job description for Project Manager on Customer- Developer’s part

4.Job description for PMO Head of Customer-Developer

5.Job description for Methodologist of Customer-Developer

6.Job description for Planner of Customer-Developer

7.Role instructions for Primavera P6 Software use

Gen.Contractor’s

1.Regulation on Gen. Contractor’s PMO

2.Job description for Project Manager on Gen. Contractor’s part

3.Job description for PMO Head of Gen. Contractor

4.Job description for Methodologist of Gen. Contractor

5.Job description for Planner of Gen. Contractor

6.Job description for Superintendent of Gen. Contractor

7.Job description for Functional Unit Specialist

8.Role instructions for Primavera P6 Software use

128

Subject matter 2 Managing Projects in Oracle Primavera P6 Project Management

Introduction

Primavera was developed by Primavera Inc and two years ago was merged by

Oracle. in October 2008 Oracle acquired Primavera Systems. Primavera includes

several modules: Contract Management, Risk Analysis, Project Management

module, etc.

PM module has competitors. The most popular are Microsoft Office Project +

Project Server and Spider. But it’s a leading provider of Project Portfolio

Management (PPM) solutions for project-intensive industries.

For large projects such as constructing ones Primavera suits best as more

powerful, flexible and stable.

Primavera P6 Professional Project Management, the recognized standard for

high-performance project management software, is designed to handle large-scale,

highly sophisticated and multifaceted projects. It can be used to organize projects

up to 100,000 activities, and it provides unlimited resources and an unlimited

number of target plans. Massive data requires sophisticated, yet highly flexible

organization tools to provide you a multitude of ways to organize, filter and sort

activities, projects, and resources.

BENEFITS

Balance resource capacity

Plan, schedule, and control complex projects

Allocate best resources and track progress

Monitor and visualize project performance versus. plan

Conduct what-if analysis and analyze alternative project plans

This guide will learn you how to set up the main project options, how to

create a new project and to manage it.

129

2.1. Starting up

Pic.101. Primavera Project Management icon on the desktop.

To start working with Primavera software you should double click its icon on

your desktop (pic.101) or select it from Start → All Programs → Primavera →

Project Management.

Pic.102. Logging into Primavera Project Management

In both cases Primavera will ask you to put in your user name and the password. In

this guidance we are using the profile with the login “admin” and an empty

password (pic. 102)

At this point you should not change the database name in the window above.

2.1.1. Primavera’s Interface

130

After Primavera starts, you will see the next window:

Pic.103. Primavera Home page.

On the standard layout Primavera has the next toolbars:

1) Title bar (dark blue bar at the top of Primavera window) shows all the open

projects comma separated.

2) Menu bar (File, Edit, e.t.c.)

3) Directory. It includes two types of directories: global (four directories) and

project (next 8 directories). Project directories are available only when a project is

opened, otherwise they are in gray as shown on a picture above.

4) Command bar

5) Navigate bar to navigate throw the views.

6) Status bar shows current status of a project and a base.

Primavera saves all changes in the project base automatically. That's why there is

no such command as File → Save As... And you should not worry that your last

changes can be lost in case of PC power switching off. Also it means that it is

necessary to export your project base to roll it back for one of the previous states.

131

If you'd like to change this layout you should go into Display → Toolbars (pic.

104) and unselect the necessary one.

Pic.104. Setting up Primavera layout.

Name bar shows names of all open projects. Pay attention on this bar while editing

a project: you may change not that project that you want. To be sure go into File →

Close All (Ctrl + W) to close all opened projects and then open a necessary one.

All the current views of the Primavera interface could be saved. You can change

the layout for your future purpose as a maquette and then use it when it is

necessary. Maquettes save the layouts and usually are named as their intended

uses are: “Resources inputting”, for example.

To obtain a layout press on Layot → Open (pic. 105). After that you will see a new

window (pic. 106). If you’d like to change a current layout, press Yes, but it is

strongly advised not to damage existing layouts and press No. A list of all available

layouts will be shown (pic. 107). There you can select a necessary layout by

clicking on its name and press Open. Notice how the view of your Primavera

desktop will be changed.

132

Pic.105. Open Layout menu

Pic.106. Open Layout question

Pic.107. Open Layout window

2.1.2. Opening a project.

There are several ways to open a project.

a. 1. Select the project (marked as a gray folder) in Enterprise Project Structure

(marked with a pyramid icon): left click on it, it highlights with dark blue.

2. Right click on it

3. In the context menu select the first item: Open Project (Ctrl + O). (pic. 108)

133

Pic.108. Open project item

b. 1. Select the project (marked as a gray folder) in Enterprise Project Structure

(marked with a pyramid icon): left click on it, it highlights with dark blue.

2. File → Open (Ctrl + O) (pic. 109).

Pic.109. Open project menu

This way has more options that the previous one: pic 110. First of all you should

select a project to open. Also here you can select an success mode: Exclusive,

Shared or Read Only.

If the project is opened by someone else, you can look throw its users by clicking

Users button at the right top part of this window.

134

Pic.110. Open Project window

2.2. Project settings

Most of Primavera settings are duplicated: you can use them from the Menu or in

the Bottom Layout. Usually the layout includes a lot of tabs. By changing

parameters on the different tabs you can set up all the necessary project settings.

Pic.111. Project bottom layout

135

2.3. Corporate data structure

Pic.112. Projects resources reports and tracking – global directories

2.3.1. Code structures

Primavera allows to group and classify projects, activities and resources by

special criteria. There is an opportunity to create required codes for creating

reports, summation, filtering, grouping, selecting and sorting support.

Codes are useful when similar projects are situated on different levels of

enterprise project structure.

Project codes Project codes are general for all enterprise projects. They can be grouped

hierarchically. To evoke the project codes window go into Enterprise Project

Codes… (pic. 113).

136

Pic.113. Project codes

Activity codes These codes can be accessed by Enterprise Activity Codes… They are of

two types:

1) General – available for all projects in the base;

2) Project – available only in current project.

The type of displayed codes can be selected in the top options bar of the

window (pic.114).

Pic.114. Activity codes

Resource codes These codes can be accessed by Enterprise Resource Codes… They are

global, can be hierarchically structured.

137

Pic.115. Resource codes

2.3.2. EPS

A project must be created in an EPS, not at the root of a base.

EPS – Enterprise Project Structure - is a way to group all projects into

portfolios for easy and transparent managing them. Also calculate all the

summaries in projects into EPS.

The EPS in Primavera contains details of the projects that are in the

database and the ownership of those projects. When a project is created, it is

assigned to an EPS node. You must select an EPS node to open the Export section

on the Export tab. You cannot export data if you do not select an EPS node.

2.3.3. OBS

Organization Breakdown Structure - is a hierarchical managing project

structure which shows relations between project participants.

To enter or edit OBS go into Enterprise menu OBS (pic. 116).

Pic.116. OBS

138

The new window will be opened (pic. 117). There you will see OBS tree and

a layout.

Pic.117. OBS settings

If the form is not displayed press Display OBS Details. On the form there

are 3 tabs: General, Users, Responsibility.

To search an item in this tree you can use:

a) View Search (or Ctrl + F);

b) Display Expand All (or “+” icon in the tree);

c) Display Collapse All (or “-” icon in the tree).

Also you can display the OBS in a diagram view. To do that press Display

Diagram.

To increase/decrease the scale of the diagram:

1) press the Alt button on your keyboard (the cursor will turn into a magnifying

glass) and

2) while the left key of your mouse is pressed,

3) scroll the mouse down /up the diagram area.

2.3.4. Roles

Before creating a resources structure, a roles structure should be developed.

Roles are resources’ knowledge and skills, which can be used to simplify

resources assignment. The roles structure can be hierarchical.

In Primavera there is an opportunity to assign several roles to one resource.

And vice versa, one role could be assigned to several resources. The picture 118

illustrates it.

Resources Roles

Employee1 Role1

Employee2 Role2

Employee3 Role3

Employee4 Role4

Role5

Pic.118. Resources and roles relations.

139

The role structure in Primavera is available in Enterprise menu Roles

(pic. 119). There you can edit an existing structure or create new items. To display

the form at the bottom of the window press Display Roles Details (it should be

checked).

Pic.119. Roles structure

2.3.5. Resources

The resources list can be evoked by clicking on the Resources button in the Global

Divisions or into Enterprise Resources (pic. 120).

Pic.120. Opening resources

140

Pic.121. Resources structure

To view all the resource’s parameters you can use a form below: each tab shows

different parameters. Also the list can be displayed in a diagram view by clicking

Display Chart View (pic. 122)

. Pic.122. Chart view of project resources.

2.3.6. Calendar

Primavera uses several common calendar templates: 24*7 and 8*5 hours a week

calendars. You are able to create your own calendar, extending standard ones.

To create a new one go into Enterprise → Calendars… . A new window will open

up (pic.123). There you can select a template calendar's type and a name for a new

calendar.

141

Pic.123. Calendar selecting window

Primavera works with calendars of three types: global, resource and project ones.

Global calendars are available for all projects in the base. When you change one

of global calendars, all its child resource or project calendars are changed to.

A resource can use global or resource calendar. A project can use global or project

calendar. For new project or resource calendar global or existing resource

calendars can be used.

Pic.124.Creating a new project calendar.

1. To create a project calendar you should select a Project option at the top of the

window.

2. Press the Add button (at the right side of the window with a blank sheet icon)

(pic.125)

Pic.125. Add button

3. Then select a template (Standard 5 days a week, for example) and click on a

button with a green cross - “Select” button.

4. Type in the calendar's name.

142

5. Click on the Modify button, a new window “Project calendar” will show up

(pic.126).

6. Make changes.

7. Press OK.

Pic.126. Modifying a new calendar

To navigate throw Years you should click on the button with a month and a year.

143

2.4. Project structure

The whole structure of a project should be the next:

Activity

Steps

2.4.1. WBS

Work Breakdown Structure – is a way to group activities. Each WBS level

can include other WBS or activities. WBS can be created on the EPS level or on a

project level (only after creating).

Project manager must create WBS of a project, assign OBS units on WBS

levels, assign documents, define activities, which are included into WBS.

1. Open a project.

2. Project WBS or WBS in the left panel.

3. At the right panel select the first item Add.

4. Fill in ‘WBS Code’ and ‘WBS Name’ fields

5. ‘Project ID’ and ‘Project State’ will be filled in automatically.

6. In the Bottom Layout you can change all the appropriate

settings.

7. To change WBS hierarchy you can move items using 4 arrows

at the right panel:

Pic.127. Hierarchy changing arrows

144

2.4.2. Activities

Activities – are the lowest level of project WBS. They show all information

about project. Activities are described by:

1. Activity ID

2. Description

3. Duration

4. Calendar

5. Type

6. Codes

7. WBS

8. Relationships: Predecessors and Successors

9. Resources

10. Expenses

11. Summary

12. Feedback

13. Notebook

14. Steps

15. Documents.

Pic.128. Activity type

In Primavera activities can be one of 2 types: task dependent or resource

dependent. Also they can be divided into 3 groups: start/finish milestone, level

of effort or a simple activity.

2.4.3. Steps

An activity can be decompose to a smaller part – steps. They are characterize

by its weight: if your activity consists of 2 steps: Step1 with weight 1 and Step2

with weight 3 it means that your activity is divided into two parts: 25% and 75%.

If Step1 is completed, 25% of the activity is done.

To work with steps on the General tab of a Bottom Layout select %Complete

Type Physical.

To create a new activity with steps:

1) Open the project

2) Project Activities

3) Select Add in the right menu

145

4) In the wizard window type in Activity ID and Activity Name

5) Press finish

6) In the Bottom Layout go on Steps tab

7) Press Add button at the bottom

8) Type in Step Name, Step Weight

9) Check Completed flag if the step is completed.

2.4.4. Relationships

Primavera can automatically calculate a schedule and a duration of a project.

To do that you must not feel in Start Date and Finish Date fields. Instead you must

select Predecessors or Successors for each of activity (it can be done in the Activity

Table, in the Bottom Layout or in the Gantt Chart). If an activity does not have a

logical predecessors or successors, it must have relations with start or finish

milestone of a project.

To assign relations do the next steps:

1) Open a project

2) Project Activities

3) On the Bottom Layout select one of the tabs: Predecessors,

Successors or Relationships (shows both of them)

4) At the bottom select Assign button

5) Select predecessors or successors from a list

6) Press the button with a green plus icon – Assign – in the new

window

7) The new window can be closed.

Pic.129. Assignment

1

146

2.4.5. Assignments

When activities are created the next step is Assignments.

In Primavera there is a way to assign documents, resources and expenses. To

assign each of them you should do the next steps:

1) On the Bottom Layout select one of the tabs: Documents,

Resources or Expenses

2) Press Assign button on the bottom

3) A new window will be opened

4) Select appropriate item

5) Press a button with green plus Assign

6) Documents, Resources or expenses will be assigned to the

activity.

7) Clicking Delete will delete assignment but not documents,

resources or expenses themselves.

Pic.130. How to assign

To create documents, resources or expenses click the appropriate item

in the left menu of directories. There you can press Add button at the right

panel, type in Name and other information. Also in the Bottom Layout you

can select an activity, to which you want to assign documents, resources or

expenses. Clicking Delete will delete documents, resources and expenses

and all their assignments.

147

2.5. GROUP, SORT AND FILTERS

Primavera has a powerful module, which allows you to change your layout.

To use it click on Layout button:

It can be totally used in Activities directory. You will see a drop-down menu

with the next items:

Pic.131. Filters, Group &Sort

Group menu provides options to set up display options of table of activities:

Pic.132. Group and Sort

148

By clicking on the first cell of Group By table you can select a column name

to group activities from a long list:

Pic.133. Grouping fields

Also font, color and group level can be selected. To apply your settings click

on OK button in the top right corner of the window.

To use Sort tool click on Sort button in the right panel of the window. In this

case you will see another window:

Pic.134. Sort

It has a table with two columns: Field Name and Sort Order. In the first cell

you can select a field name to sort a table of activities and in the second: ascending

or descending, hierarchical for some fields. By clicking Add button a complex sort

can be created:

149

Pic.135. Sorting fields

The next way to sort the table of activities is to click on a column name:

Pic.136. Sorting in the activities table

An arrow up/down shows that the table is sorted by the field

ascending/descending. Clicking on Layout Filters shows the next window:

Pic.137. Filters

150

On this window different kind of filters can be selected. Simple filter consists

of one condition and complex – of two or more.

Pic.138. Complex filter

151

2.6. REPORTS AND PRINT SETUP

There are a lot of predefined global report templates in Primavera base.

Pic.139. Reports

To create a report select one of this template and press Run Report button in

the top right corner. After that you are able to change report settings:

A report can be printed or saved as *.pdf, *.html or *.txt file. To set up the

report layout go into Print setup in the left op corner of the window.

152

2.7. ANALYSYS AND CONTROL

Now when the project structure is

created, when activities are entered and

have predecessors and successors, when

resources, document are assigned, it’s time

to schedule the project. Go into Tools

Schedule or press F9 button on the

keyboard or select Schedule item in the

tools panel (it has the same icon: a clock

with a folder).

You will be provided with schedule

options:

Pic.140. Scheduling options

Press Schedule button to make all activities scheduled. After this you can

analyze using of resources and expenses and base plan.

The blue line on the picture shows the date on which the timetable was

scheduled.

Base plan is shown with yellow under strike of activities bars.

To manage resource usage you can select Resource Usage Spreadsheet or Resource

Usage Profile:

Pic.141. Resource Usage icons

153

The layout will be divided into 5 parts:

Pic.142. Resource Usage Profile

By selecting activities in the 1st part and resources in the 3

rd, you can view

resources activities.

2.7.1. What-If

If you are going to create several versions of you project, not to sum each of

them in the portfolio, you should create a project with what-if status. To do that go

into Projects General tab Status:

Pic.143. Project status settings

Make sure that the project icon is changed:

Pic.144. What-if project icon

154

2.7.2. Fact

For entering actual status of any activity go into Activities table of

activities create a new column Activity Status (or Activity % Complete).

Pic.145. Activity status

There you can select activity actual status through the project managing

process.