numi numi review of the infrastructure – w, g & v 20 july 2001 wbs 1.1.7 page 1 1...
TRANSCRIPT
![Page 1: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/1.jpg)
1
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 1
Infrastructure Review - W.B.S. 1.1.7 Water Systems
• Water Systems– Upstream LCW for Extraction and Pre-Target Magnets & P.S.
– Downstream LCW for cooling the MINOS Near Detector Coil, Power supply and Electronics Racks.
– Downstream RAW for cooling the Absorber .
– Decay Pipe Cooling for cooling the decay pipe.
– Horn RAW (RadioActive Water), for cooling the Horns.
– Target RAW for cooling the target, horn protection baffles.
• Vacuum Systems– Extraction and Primary Beam, Hadron Decay Pipe
• Gas Systems– Primary Beam Instrumentation
– Secondary Beam Instrumentation
• WILL HAVE A SEPARATE REVIEW OF THE RAW SYSTEMS ON 8/1/01
![Page 2: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/2.jpg)
2
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 2
Infrastructure Review - W.B.S. 1.1.7 Upstream LCW (MI-62) System
• U.S. LCW System has LCW pumps, Heat Exchanger located in MI-62.
• Heat Exchanger sized for 1200 kW, actual heat load is approximately 750kW. HX is a shell and tube unit and is already in MI-62. Strand needs to be built, stands drawings underway.
• 550 gpm pump, 440 feet TDH, 100 HP. Pump spec’d not purchased. Will include a hot stand-by unit.
• Provides LCW to all magnets in extraction and pre-target areas, Power supplies in MI-62, TSB, Underground Mechanical Space (horn P.S.)
• ~ 4630 gallons of LCW in the piping, more in exp. tank.
• Heat rejected to MI pond G via pumps in PV-9. Existing pumps are not perfectly fit to our application (too much head with two pump operation/too little flow for one pump operation).
![Page 3: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/3.jpg)
3
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 3
Infrastructure Review - W.B.S. 1.1.7 Upstream LCW (MI-62) System
• Status of the Upstream LCW System:– Piping already installed in MI up to the shield wall.– Piping will need to be extended in MI after the shield wall is
removed.– MI-62 piping laid out as far as possible w/o pump and strainer
selections finalized.– Piping Installation in the carrier tunnel, pre-target, shaft,
underground mechanical area, and NuMI Target Service Building (MI-65?) to be in the Outfitting and Service Building Contract
– Instrumentation List Complete• Best scheme to read in to/out of ACNET not yet settled.• Will use one PID loop to control temperature• Will have a few pump interlocks
![Page 4: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/4.jpg)
4
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 4
Infrastructure Review - W.B.S. 1.1.7 Downstream LCW (MINOS) System
• D.S. LCW System has LCW pumps, Heat Exchanger located in the MINOS Near Detector Hall.
• Heat Exchanger sized for 200 kW, actual heat load is approximately 110kW. Will use a welded plate and frame HX.
• 160 gpm pump, 35 feet TDH, 3 HP. Pump not spec not yet written. Will include a hot stand-by unit. Will have a booster pump for the power supply just like the one at NMS currently.
• Provides LCW to the near detector magnet coil, power supply, and 27 water cooled electronics racks.
• ~ 150 gallons of LCW in the piping, more in expansion tank, rack, magnet coil.
• Heat rejected to MINOS chilled water (same water used for de-humidification in the underground spaces).
![Page 5: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/5.jpg)
5
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 5
Infrastructure Review - W.B.S. 1.1.7 Downstream LCW (MINOS) System
• Status of Downstream LCW (MINOS) System:– Piping layout drawings completed.
– Piping to be installed in the Service Building and Outfitting Contract.
– Skid Design not started.
– Instrumentation List Complete• Best scheme to read in to/out of ACNET not yet settled.
• Will use one PID loop to control temperature
• Will have a few pump interlocks
![Page 6: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/6.jpg)
6
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 6
Infrastructure Review - W.B.S. 1.1.7 Absorber Cooling RAW System
• Absorber RAW System has pumps, heat exchanger located in the absorber access tunnel. Intermediate loop has the pumps, heat exchangers and filters located in the MINOS service building.
• Heat Exchangers sized for 200 kW, actual heat load is approximately 130kW. Will use a welded plate and frame HX between RAW and intermediate loop, a S&T between intermediate loop and the pond water.
• Both RAW and Intermediate loop pumps are 60 gpm pumps, 65 feet TDH, 3 HP. Pump not spec not yet written. Will include a hot stand-by unit for both RAW and Intermediate loop pumps.
• Provides cooling to remove the beam energy deposited in the absorber along the vacuum decay pipe.
• ~ 90 gallons of water in the absorber and piping, more in expansion tank, heat exchangers and manifolds.
• Heat rejected to MINOS pond water.• Activation of water not yet quantified.
![Page 7: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/7.jpg)
7
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 7
Infrastructure Review - W.B.S. 1.1.7 Absorber Cooling RAW System
• Status of the Absorber Cooling RAW System:– Piping layout drawings have not been started.
– Piping to be installed in the Service Building and Outfitting Contract.
– Skid Design not started for either the RAW or the Intermediate loop skid.
– Instrumentation List Complete• Best scheme to read in to/out of ACNET not yet settled.
• Will use one PID loop to control temperature for the intermediate loop, no direct temperature control on the RAW loop.
• Will have a few pump interlocks
![Page 8: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/8.jpg)
8
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 8
Infrastructure Review - W.B.S. 1.1.7 Decay Pipe Cooling RAW System
• Decay Pipe RAW System has pumps, heat exchanger located in the absorber access tunnel @ d.s. end and heat exchanger, filter, DI bottle in the underground mechanical support room at u.s. end.
• Heat Exchanger sized for 200 kW, actual heat load is approximately 150kW. Will use a welded plate and frame HX.
• 50 gpm pump, 325 feet TDH, 7.5 HP. Pump not spec not yet written. Will include a hot stand-by unit.
• Provides cooling to remove the beam energy deposited in the shielding along the vacuum decay pipe.
• ~ 1250 gallons of water in the piping, more in expansion tank, heat exchangers.
• Heat rejected to MINOS chilled water (same water used for de-humidification in the underground spaces) at downstream end and to the intermediate loop of CUB water at the upstream end (also used for de-humidification in the underground spaces).
• Activation of water is not severe. Should not have to change this water during the life of the experiment.
![Page 9: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/9.jpg)
9
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 9
Infrastructure Review - W.B.S. 1.1.7 Decay Pipe Cooling RAW System
• Status of the Decay Pipe Cooling System:– Piping layout drawings started in PPD.
• Have begun to change the layout to move the connections between individual tubes and the manifold to an accessible area.
– Piping to be installed in the Service Building and Outfitting Contract.
– Skid Design not started.
– Equipment Purchase Requisitions and specifications not prepared.
– Changing from 1” nominal copper lines to ¾” nominal polyethylene coated copper lines to prevent galvanic corrosion between the copper and the low carbon steel decay pipe.
• The decay pipe is less noble, therefore it would corrode, possibly causing a vacuum leak.
– Instrumentation List Complete• Best scheme to read in to/out of ACNET not yet settled.
• No temperature control
• Will have a few pump interlocks
![Page 10: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/10.jpg)
10
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 10
Infrastructure Review - W.B.S. 1.1.7 Horn 1 Cooling RAW System
• Horn 1 RAW System has pumps, heat exchanger, filter, DI bottle in the underground mechanical support room at u.s. end.
• Heat Exchanger sized for 150 kW, actual heat load is approximately 30kW. Will use a welded plate and frame HX.
• 115 gpm pump, 61 feet TDH, 5 HP. Pump not spec not yet written. Will include a hot stand-by unit.
• Provides cooling to remove the beam energy and I2R deposited in horn 1.
• ~150 gallons of water in the piping, more in expansion tank, heat exchangers.
• Heat rejected to the intermediate loop of CUB water at the upstream end (also used for de-humidification in the underground spaces).
• Activation of water is severe. Will change annually but will also exceed the recommended concentrations.
![Page 11: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/11.jpg)
11
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 11
Infrastructure Review - W.B.S. 1.1.7 Horn 1 Cooling RAW System
• Status of Horn 1 Cooling Raw System:– Piping layout drawings 90% completed.
– Piping to be installed in the Service Building and Outfitting Contract.
– Skid Design has just been started.
– Instrumentation List Complete• Best scheme to read in to/out of ACNET not yet settled.
• No temperature control is used
• Will have a few pump interlocks
![Page 12: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/12.jpg)
12
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 12
Infrastructure Review - W.B.S. 1.1.7 Horn 2 Cooling RAW System
• Horn 2 RAW System has pumps, heat exchanger, filter, DI bottle in the underground mechanical support room at u.s. end.
• Heat Exchanger sized for 50 kW, actual heat load is approximately 10kW. Will use a welded plate and frame HX.
• 115 gpm pump, 61 feet TDH, 5 HP. Pump not spec not yet written. Will include a hot stand-by unit.
• Provides cooling to remove the beam energy and I2R deposited in horn 2.
• ~100 gallons of water in the piping, more in expansion tank, heat exchangers.
• Heat rejected to the intermediate loop of CUB water at the upstream end (also used for de-humidification in the underground spaces).
• Activation of water is severe. Will change annually but will also exceed the recommended concentrations.
![Page 13: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/13.jpg)
13
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 13
Infrastructure Review - W.B.S. 1.1.7 Horn 2 Cooling RAW System
• Status of Horn 2 Cooling RAW System:– Piping layout drawings 90%completed.
– Piping to be installed in the Service Building and Outfitting Contract.
– Skid Design has just been started.
– Instrumentation List Complete• Best scheme to read in to/out of ACNET not yet settled.
• No temperature control is used
• Will have a few pump interlocks
![Page 14: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/14.jpg)
14
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 14
Infrastructure Review - W.B.S. 1.1.7 Target Cooling RAW System
• Target RAW System has pumps, heat exchanger, filter, DI bottle in the underground mechanical support room at u.s. end.
• Heat Exchanger sized for 20 kW, actual heat load is approximately 10kW. Will use a welded plate and frame HX.
• 15 gpm pump, 58 feet TDH, 1 HP. Pump not spec not yet written. Will include a hot stand-by unit.
• Provides cooling to remove the beam energy and I2R deposited in the target and baffle.
• ~50 gallons of water in the piping, more in expansion tank, heat exchangers.
• Heat rejected to the U.S. LCW system.
• Activation of water is unknown as it has not yet been calculated.
![Page 15: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/15.jpg)
15
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 15
Infrastructure Review - W.B.S. 1.1.7 Target Cooling RAW System
• Status of the Target and Baffle RAW System:– Piping layout drawings 90%completed.
– Piping to be installed in the Service Building and Outfitting Contract.
– Skid Design has not started.
– There remains some difference of opinion as to if the beam baffle is, or is not, water cooled. This has a negligible affect on the cost.
– Instrumentation List Complete• Best scheme to read in to/out of ACNET not yet settled.
• No temperature control is used
• Will have a few pump interlocks
![Page 16: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/16.jpg)
16
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 16Vacuum
• Vacuum in the Primary Beam: – Designing for a 1 x 10-6 torr level in the instrumentation region of
the primary beam transport pipe. P&ID prepared.– Generated Instrument Lists for extraction.– Pre-Target Instrument List not completed – Parts for Vacuum Instrumentation being purchased. Custom
building of controller chassis for Ion pumps and instrumentation.
• Decay Pipe Vacuum:– Decay system P&ID prepared. 24 hour pump down calculated
• 48 liters of water is the maximum volume of water in the air in the decay pipe assuming 100% relative humidity at the beginning of the pump down.
– Skid drawings not yet started nor equipment specified.
![Page 17: NUMI NuMI Review of the Infrastructure – W, G & V 20 July 2001 WBS 1.1.7 Page 1 1 Infrastructure Review - W.B.S. 1.1.7 Water Systems Water Systems –Upstream](https://reader036.vdocument.in/reader036/viewer/2022080916/56649e665503460f94b61065/html5/thumbnails/17.jpg)
17
NUMI
NuMI Review of the Infrastructure – W, G & V
20 July 2001WBS 1.1.7
Page 17Gas Systems
• Gas Systems for:
– Loss monitors for primary beam area (Ar-CO2)
– Secondary beam Monitoring (He-2%H2)
• Status:
– Both system designs remain on hold pending instrumentation development.
– Significant chance that the secondary beam monitoring may choose a technology which does not require gas.