Page 1: OCSD Effluent Reuse Study SP-173 Cost Share

OCSD Effluent Reuse Study SP-173 Cost Share

Water Issues Committee

April 8, 2015

1

Page 2: OCSD Effluent Reuse Study SP-173 Cost Share

2

Background

►GWRS currently has 70 mgd treatment capacity

►Initial Expansion under construction will provide additional 30 mgd, for a total of 100 mgd

►Environmental Impact Report evaluated ultimate facility producing up to 130 mgd

Page 3: OCSD Effluent Reuse Study SP-173 Cost Share

Flow Availability Issues for Final Expansion

3

► Availability of sufficient quantities of secondary treated wastewater from OCSD Need approx. 173 mgd of secondary treated wastewater to produce

130 mgd of GWRS purified water This amount is not available from OCSD Plant No. 1 OCSD Plant No.1 cannot produce 173 mgd even if more flow could

be diverted to it Additional flow required must come from OCSD Plant No. 2 and

those flows contain water from SARI Ability to bring flows from Plant No.2 to GWRS don’t currently exist SARI recycling prohibited in current GWRS permit

Page 4: OCSD Effluent Reuse Study SP-173 Cost Share

GWRS Final Expansion to 130 MGD Supplemental Feedwater Alternatives

►If SARI Line cannot be recycled must segregate SARI at OCSD Plant 1 or Plant 2, prevent

comingling with remaining recyclable wastewater

►If SARI Line could be recycled recycle OCSD Plant 2 flows, and/or bring SARI into OCSD Plant 1

4

Page 5: OCSD Effluent Reuse Study SP-173 Cost Share

Feedback from NWRI Independent Advisory Panel for GWRS

► Panel meets annually to review GWRS operations & water quality ► Reviewed information on SARI dischargers & water quality in

August 2014 ► Preliminary Panel feedback

Additional water quality data for overall SARI needed Additional information re: Stringfellow Hazardous Waste Site needed Interested in results from follow-up audit of SAWPA source control Further analysis should be done of segregating SARI flows in OCSD system

5

Page 6: OCSD Effluent Reuse Study SP-173 Cost Share

OCSD SP-173 Effluent Reuse Study

► OCSD Board Five Year Strategic Plan approved in November 2013 includes goal to recycle all Plant No. 2 water

► OCSD staff has prioritized the GWRS Final Expansion to help fulfill their board’s strategic plan

► OCSD Effluent Reuse Study SP-173 developed to help identify how to provide flows necessary for the GWRS Final Expansion

► SP-173 would identify projects and costs to get flows both with and without SARI water to GWRS

6

Page 7: OCSD Effluent Reuse Study SP-173 Cost Share

7

OCSD Effluent Reuse Study SP-173

Page 8: OCSD Effluent Reuse Study SP-173 Cost Share

Scope of Work & Deliverables from OCSD Effluent Reuse Study

► Plant No. 1 and Plant No. 2 Hydraulic Models Final Hydraulic Model Report

► GWRS Final Expansion Implementation Plan and Report Plant No. 2 Secondary Water Quality Report SARI/Sidestream Separate Process Treatment Concept Design Plant No. 2 GWRS Pump Station Concept Design Flow Equalization Concept Design Permit and Environmental Impacts Implementation Plan (Costs and Schedule)

► Collection Diversions Opportunities Report Would increase flows to OCSD for GWRS Potentially segregate municipal domestic sewage away from SARI in Orange County

8

Page 9: OCSD Effluent Reuse Study SP-173 Cost Share

OCSD/OCWD with SARI Location Map

OCSD Plant No. 2

OCWD GWRS Facility

OCSD Plant No. 1

SARI Line

SARI Diversion Line

Page 10: OCSD Effluent Reuse Study SP-173 Cost Share

OCSD Plant No.1 - SARI Segregation Option

A

B

Page 11: OCSD Effluent Reuse Study SP-173 Cost Share

OCSD Plant No.2 - SARI Segregation Option A

Page 12: OCSD Effluent Reuse Study SP-173 Cost Share

OCSD Plant No.2 - SARI Segregation Option B

Page 13: OCSD Effluent Reuse Study SP-173 Cost Share

OCSD Effluent Reuse Study Award and Schedule

► OCSD request for proposals (RFP) issued January 2015 ► Three proposals received: CDM Smith/Brown and Caldwell, RMC/B&V

and MWH/Carollo ► Staff selection was for the CDM Smith/Brown and Caldwell team ► Study to begin in May 2015 and draft report available May 2016 ► OCWD staff will participate in project meetings and review project

deliverables ► OCSD has requested OCWD cost share in study (total negotiated study

cost is $2,008,510)

13

Page 14: OCSD Effluent Reuse Study SP-173 Cost Share

►Agendize for April 15 Board meeting: Set aside $1,004,255 from current operating reserves and authorize payment in the same amount to Orange County Sanitation District (OCSD) for the District’s 50% share of the Agreement to CDM Smith for the OCSD Effluent Reuse Study SP-173.

Recommendation

Page 15: OCSD Effluent Reuse Study SP-173 Cost Share

15

End of Presentation